See Full Document Text
Official Journal EN
of the European Union L series
2024/1274 3.5.2024
COMMISSION DECISION (EU) 2024/1274
of 29 April 2024
granting the Hellenic Republic a derogation from certain provisions of Regulation (EU) 2019/943 of
the European Parliament and of the Council and of Directive (EU) 2019/944 of the European
Parliament and of the Council, as regards the island of Crete
(notified under document C(2024) 2890)
(Only the Greek text is authentic)
(Text with EEA relevance)
THE EUROPEAN COMMISSION,
Having regard to the Treaty on the Functioning of the European Union,
Having regard to Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June 2019on the internal
market for electricity(1), and in particular Article 64 thereof,
Having regard to Directive (EU) 2019/944 of the European Parliament and of the Council of 5 June 2019on common rules
for the internal market for electricity and amending Directive 2012/27/EU(2), and in particular Article 66 thereof,
Whereas:
1. PROCEDURE
(1) On 21 February 2022, the Commission adopted Decision (EU) 2022/258(3)granting to Greece a derogation from
the following provisions of Regulation (EU) 2019/943 and Directive (EU) 2019/944, as regards the island of Crete:
(a) Article 6 of Regulation (EU) 2019/943, which sets out the rules applicable to electricity balancing markets;
(b) Article 7(1) of Regulation (EU) 2019/943, which refers to the organisation of the management of the
integrated day-ahead and intraday markets by transmission system operators (‘TSOs’) and nominated
electricity market operator (‘NEMOs’), in accordance with Commission Regulation (EU) 2015/1222(4);
(c) Article 8(1) and (4) of Regulation (EU) 2019/943, which, respectively, impose on NEMOs the obligation to
allow market participants to trade energy as close to real time as possible and at least up to the intraday
cross-zonal gate closure time and set out the imbalance settlement period to 15 minutes in all scheduling
areas;
(d) Article 9 of Regulation (EU) 2019/943, which refers to forward electricity markets;
(e) Article 10 of Regulation (EU) 2019/943, which refers to technical bidding limits applicable to wholesale
energy prices;
(f) Article 11 of Regulation (EU) 2019/943, which refers to the determination of the value of lost load, that is to
say, an estimation of the maximum electricity price that customers are willing to pay to avoid an outage;
(g) Article 40(4) to (7) of Directive (EU) 2019/944, which set out certain responsibilities of TSOs including the
procurement of non-frequency ancillary services.
(1) OJ L 158, 14.6.2019, p. 54, ELI: http://data.europa.eu/eli/reg/2019/943/oj.
(2) OJ L 158, 14.6.2019, p. 125, ELI: http://data.europa.eu/eli/dir/2019/944/oj.
(3) Commission Decision (EU) 2022/258 of 21 February 2022 granting the Hellenic Republic a derogation from certain provisions of
Regulation (EU) 2019/943 of the European Parliament and of the Council and Directive (EU) 2019/944 of the European Parliament
and of the Council as regards Crete (OJ L 42, 23.2.2022, p. 92, ELI: http://data.europa.eu/eli/dec/2022/258/oj).
(4) Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a guideline on capacity allocation and congestion management
(OJ L 197, 25.7.2015, p. 24, ELI: http://data.europa.eu/eli/reg/2015/1222/oj).
ELI: http://data.europa.eu/eli/dec/2024/1274/oj 1/8EN
OJ L, 3.5.2024
(2) The derogation granted in Decision (EU) 2022/258 applied until 31 December 2023 or until the island of Crete
would be fully interconnected with mainland Greece, whichever came first.
(3) On 18 December 2023, Greece submitted to the Commission a new request for derogation (the ‘Application’) from
the provisions referred to in recital 1 as regards the island of Crete. In the new request, Greece explained that, due to
unforeseeable delays in the relevant construction and licencing processes, the full interconnection of the island of
Crete could not take place by the end of December 2023 and requested a new derogation from those provisions
until 31 December 2025or the completion of the full interconnection of the island of Crete with mainland Greece,
whichever would come first.
(4) On 28 February 2024, the Commission published the Application on its website and invited Member States and
stakeholders to provide comments by 27 March 2024. Only one party submitted comments, which related to the
installation of additional conventional generation capacity in Crete as well as the remuneration of such capacity.
More specifically, the party raised concerns that the applicable remuneration scheme may not be compatible with
the EU rules applicable to capacity mechanisms. For the avoidance of doubt, Greece has not requested a derogation
from the EU rules applicable to capacity mechanisms, which means that those rules continue to apply to any
remuneration schemes for generation capacity in Crete. Hence, the comments received are outside the scope of the
present decision. In addition, the present decision is without prejudice to EU State aid law.
2. THE ISLAND OF CRETE
The electricity system and electricity market in the island of Crete
(5) The island of Crete is located in the Mediterranean Sea, south of the continental mainland of Greece. Until 3 July
2021, it had an autonomous power system, unconnected to the continental electricity system of Greece.
(6) As explained in recitals (6) to (9) of Decision (EU) 2022/258, Greece treated the full interconnection of the island of
Crete with the mainland Greece as a priority project which was scheduled to be completed by the end of 2023and to
materialise in two phases:
(a) phase I of the interconnection project, which relates to the interconnection of Crete with the Peloponnese
peninsula (the ‘Phase I interconnection’) was completed on 1 November 2021;
(b) phase II of the interconnection project refers to the interconnection of the central part of Crete (Heraklion
Prefecture) to mainland Greece (Attica region) (the ‘Phase II interconnection’). Upon completion of the Phase
II interconnection, the island of Crete is expected to be fully interconnected to the continental electricity
transmission system and the electricity demand on the island is to be fully covered.
(7) Prior to the completion of the Phase I interconnection, the electricity market in Crete was such that producers and
suppliers did not submit any bids in the Greek market and the generation units were dispatched according to their
minimum variable costs. The wholesale clearing price for electricity in Crete was calculated on a monthly basis,
based on the variable and total costs of the conventional power units, all of which belonged to the incumbent
company Public Power Cooperation S.A. (‘PPC S.A.’). PPC S.A. was the only conventional power generator on the
island. In addition, there were several electricity producers from renewable energy sources (‘RES’) with a fixed tariff
pursuant to a power purchase agreement or a fixed tariff depending on the date of the start of operation of each
unit. The application of this model ceased once Phase I was completed (1 November 2021).
2/8 ELI: http://data.europa.eu/eli/dec/2024/1274/ojEN
OJ L, 3.5.2024
(8) For the transitional period between the completion of Phase I and the completion of Phase II, (the ‘transitional
period’) a hybrid market model applies to the electricity market in Crete (the ‘hybrid model’). Details of the
operation of the hybrid model were set out in recitals 15 to 19 of Decision (EU) 2022/258.
(9) In sum, according to the hybrid model, the Greek electricity power exchange HEnEX submits orders for the entire
load and thermal generation in Crete to both the day-ahead and intraday markets. Those submissions are made on
behalf of all load representatives and thermal generators in Crete. All RES contracts have been transferred to the
Operator of Renewable Energy Sources & Guarantees of Origin (‘DAPEEP’) by way of Ministerial decision and all
relevant metering data for both existing and new RES in Crete are provided to DAPEEP by the Distribution System
Operator (‘HEDNO S.A.’). Simultaneously, DAPEEP submits orders for all RES generation in Crete. Based on those
orders, the total electricity demand, as forecasted by the Greek Transmission System Operator (‘IPTO S.A.’), is
allocated to load representatives in accordance with their supply percentage ratio calculated ex ante on a monthly
basis by HEDNO S.A.. Upon completion of that process, the complete load and generation profile of Crete are
virtually introduced into the day-ahead and intraday markets of the Greek mainland interconnected system.
(10) According to the Application, the operation of the Phase I interconnection follows the economic signals of the price
formation in the mainland interconnected system vis-à-vis the electricity market in Crete. Given that the costs for
thermal electricity generation in Crete are high, the Phase I interconnection mostly imports electricity to Crete.
However, this is not always the case. During periods of low load and high generation of electricity from RES in
Crete, the flow on the cables of the Phase I interconnection reverses and electricity flows from Crete to the
mainland. Greece explained that when that happens, any such electricity has been generated from RES, because all
thermal generation is considered to serve the local load in Crete.
(11) Greece submitted that the hybrid model entered into force by way of the following national measures: Articles 105,
107 and 108 of Greek Law 4821/2021 and the national regulatory authority’s (RAE) Decisions No 755/2021
and 807/2021.
(12) Greece further submitted that, for the transitional period, the hybrid model has proven to be the most suitable,
efficient and effective market system for Crete compared to the two alternatives that were considered, namely the
integration of Crete in the Greek electricity market through a single or two bidding zones respectively. In support of
that statement, Greece submitted information demonstrating that the hybrid model has resulted in significant cost
savings, the avoidance of excessive redispatching costs, lower costs of supplied electricity and the efficient use of
less polluting technologies.
(13) In relation to the retail market, Greece submitted that it is open to all suppliers, with approximately fifteen currently
active in the island of Crete. Given the fact that the generation costs in the island of Crete are higher than the costs of
the Greek interconnected electricity system, Greece opted for the application by the suppliers of a single tariff for
each category of customers throughout its entire territory. That decision was driven by reasons of social cohesion.
3. THE REQUESTED DEROGATION
(14) The request for derogation submitted for the island of Crete is based on its qualification as a small connected system
within the meaning of Article 64(1), point (a), of Regulation (EU) 2019/943. This qualification was confirmed in
recitals 36 to 40 of Decision (EU) 2022/258.
3.1. Derogation pursuant to Article 64 of the Regulation (EU) 2019/943
(15) Greece requested a new derogation for the island of Crete from Article 6, Article 7(1), Article 8(1) and (4) and
Articles 9, 10 and 11 of Regulation (EU) 2019/943.
ELI: http://data.europa.eu/eli/dec/2024/1274/oj 3/8EN
OJ L, 3.5.2024
3.2. Derogation pursuant to Article 66 of Directive (EU) 2019/944
(16) Greece requested a new derogation for the island of Crete from Article 40(4) to (7) of Directive (EU) 2019/944.
3.3. Duration of the requested derogation
(17) Greece requested that the derogation be of equal duration as that of the transitional period, namely until the end of
2025, by which time Crete will be fully interconnected to mainland Greece. Greece clarified that while certain
network upgrades on the island of Crete will be gradually taking place until the end of 2028, they will not
jeopardise the completion and operation of the Phase II interconnection.
(18) In the Application, Greece submitted that, while full interconnection had been scheduled to be completed by the end
of 2023, corresponding to the duration of the derogation granted in Decision (EU) 2022/258, the completion of the
project has been delayed. According to the updated timeline submitted by Greece, full interconnection is due to be
completed by the end of 2025. Greece explained that the project is experiencing substantial delays due to events
which could not have been foreseen prior to the commencement of the construction works.
(19) More specifically, Greece submitted that the COVID-19 pandemic brought about considerable delays in the
procurement of certain construction materials and services. In addition, the discovery of significant antiquities
during the excavation works caused further delays, because the competent archaeological authorities had to be
involved in the permitting processes, which were already ongoing. Greece also mentioned that the finding of karstic
cavities in the underground area of the construction field meant that works had to be suspended until those cavities
were assessed and dealt with sufficiently. Finally, the floods that took place in September 2023 caused further delays
to the project as they affected the production process of the steel structure supplier of the converter station in Crete.
4. ASSESSMENT
4.1. Small connected systems whose operation poses substantial problems
(20) In accordance with Article 64 of Regulation (EU) 2019/943, a derogation from the relevant provisions of Articles 6,
Article 7(1), Article 8(1) and (4), and Articles 9, 10 and 11 of that Regulation may be granted in two cases:
(a) for small isolated systems and small connected systems, if the Member State(s) can demonstrate that there are
substantial problems for the operation of those systems, whereas in such a case, the derogation is to be
subject to conditions that aim to increase competition and integration with the internal market for electricity;
(b) for outermost regions with the meaning of Article 349 of the Treaty, if they cannot be interconnected with
the Union’s energy market for evident physical reasons.
(21) In accordance with Article 66(1), first subparagraph, of Directive (EU) 2019/944, a derogation from the relevant
provisions of Articles 7 and 8 and of Chapters IV, V and VI of that Directive may be granted for small isolated
systems and small connected systems, if the Member State(s) can demonstrate that there are substantial problems
for the operation of those systems.
(22) Both under Regulation (EU) 2019/943 and Directive (EU) 2019/944, in the case of small connected systems,
Member States need to demonstrate that there are substantial problems for the operation of such systems.
Moreover, the derogation should be limited in time and subject to conditions aiming to increase competition and
integration with the internal electricity market.
Small connected system
(23) The qualification of the island of Crete as a small connected system was assessed in recitals 36 to 40 of Decision
(EU) 2022/258. As that assessment is still valid, the island of Crete qualifies as a small connected system for the
purposes of Article 64 of Regulation (EU) 2019/943 and Article 66 of Directive (EU) 2019/944.
4/8 ELI: http://data.europa.eu/eli/dec/2024/1274/ojEN
OJ L, 3.5.2024
Substantial problems for the operation of the system
(24) The term ‘substantial problems’ referred to in Article 64(1), point (a), of Regulation (EU) 2019/943 has been defined
neither by the legislator nor by the Commission in its decision-making practice. The open formulation allows the
Commission to take into account all potential problems related to the particular situation of small systems,
provided they are substantial and not only marginal. Such problems can vary significantly depending on the
geographical particularities, production and consumption of the system in question, but also on the basis of
technical developments, such as electricity storage and small generation. Furthermore, those substantial problems
need to be in relation to the operation of the small isolated systems and small connected systems.
(25) In the Application, Greece explained the problems it would encounter in operating the electricity system in Crete,
were it to apply Regulation (EU) 2019/943 and Directive (EU) 2019/944 in their entirety during the transitional
period. The full application of those legal acts would require the integration of Crete in the Greek electricity
markets, through a single (‘one-bidding zone scenario’) or two bidding zones (‘two-bidding zones scenario’). The
related challenges as submitted in the Application referred to the same substantial problems that had been assessed
by the Commission in Decision (EU) 2022/258.
(26) In sum, Greece highlighted problems for the operation of the electricity market in Crete, were Regulation
(EU) 2019/943 and Directive (EU) 2019/944 to apply in their entirety.
(27) On the one hand, the integration of Crete’s market participants into the Greek electricity market in the one-bidding
zone scenario would cause high redispatching costs, which would have to ultimately be paid by the electricity
consumers. In any event, metering infrastructure inadequacies would not allow the full participation of Crete
market participants in the day-ahead, intraday and balancing electricity markets of Greece. In particular, the
necessary metering systems are not in place and will not be before the first quarter of 2024.
(28) On the other hand, the creation of a separate bidding zone would not only necessitate additional infrastructure
investments, which in any event would not be completed during the period of the requested derogation, but it
would also appear to be unsuitable for reasons of overall market efficiency, stability and robustness of the bidding
zone. Moreover, it would not be a proportionate solution either, considering the limited duration of the derogation.
(29) In the Application, Greece also provided certain updates to the information submitted prior to the adoption of
Decision (EU) 2022/258. Among other things, it estimated that in the hypothetical one-bidding zone and two
bidding zones scenarios, the total cost of electricity would, respectively, be approximately EUR 190 million and
EUR 217 million higher compared to the actual cost in the context of the hybrid model for the period.
(30) It is therefore necessary to refer to the respective assessment in recitals 41 to 48 of Decision (EU) 2022/258 and to
conclude that Greece has demonstrated that there are substantial problems for the operation of the electricity
system in Crete as a small connected system, until the island is fully interconnected to the continental grid, that is to
say, until Phase II of the interconnection project is completed.
(31) The temporary hybrid model currently applicable in Crete aims to address those problems and, for the reasons set
out in recital 29, yields significant benefits compared to the full integration of the Crete’s system into the Greek
electricity market during the transitional period.
4.2. Scope of the requested derogation
4.2.1. Article 6, Article 7(1), Article 8(1) and (4), Articles 9, 10 and 11 of Regulation (EU) 2019/943
ELI: http://data.europa.eu/eli/dec/2024/1274/oj 5/8EN
OJ L, 3.5.2024
4.2.1.1. The Application
(32) With regard to Article 6 of Regulation (EU) 2019/943, Greece submitted that the hybrid model currently applicable
in the island of Crete does not include a balancing market. Hence a derogation from that Article would be necessary
for the hybrid model to continue to apply until the island of Crete is fully interconnected.
(33) With regard to Article 7(1) and Article 8(1) and (4) of Regulation (EU) 2019/943, Greece notes that the hybrid
model as currently applicable in the island of Crete does not provide for day-ahead and intraday markets, or trades
on either of these markets. Hence, according to Greece, a derogation from those Articles would be necessary for the
hybrid model to continue to apply until the island of Crete is fully interconnected.
(34) Likewise, following on from what is set out in recital 33, Greece considers that the integration of forward markets,
technical bidding limits and the value of lost load referred to in Articles 9, 10 and 11 of Regulation (EU) 2019/943
do not apply to the hybrid model in the island of Crete. Hence, according to Greece, a derogation from those
Articles would be necessary for the hybrid model to continue to apply until the island of Crete is fully
interconnected.
4.2.1.2. Assessment
(35) With respect to the requested derogation from Article 6, Article 7(1), Article 8(1) and (4) and Articles 9, 10 and 11
of Regulation (EU) 2019/943, those provisions refer to requirements regarding the forward, day-ahead, intraday and
balancing markets. Based on the information submitted by Greece, it appears that those markets cannot be
implemented effectively in the island of Crete considering the particularities of the electricity system currently
applicable in that territory. Hence, a derogation from those provisions is justified.
4.2.2. Article 40(4) to (7) of Directive (EU) 2019/944
4.2.2.1. The Application
(36) Greece submitted that the hybrid model does not provide for a balancing market or market-based procurement of
ancillary services. In order for the hybrid model to continue operating in the transitional period, a derogation from
that Article would be necessary.
4.2.2.2. Assessment
(37) Given the absence of a balancing market and of a market-based procurement of non-frequency ancillary services in
the island of Crete, a derogation from the obligations in Article 40(4) to (7) of Directive (EU) 2019/944 is justified.
4.3. No obstruction to the transition towards renewable energy, increased flexibility, energy storage, electro-
mobility and demand response
(38) Pursuant to Article 64(1), fifth subparagraph, of Regulation (EU) 2019/943 and Article 66(2) of Directive
(EU) 2019/944, a derogation decision is to ensure that it does not obstruct the transition towards renewable energy,
increased flexibility, energy storage, electro-mobility and demand response.
(39) As regards the transition towards renewable energy and increased flexibility, including demand response, and energy
storage, it should be noted that well-functioning forward, day-ahead, intraday and balancing markets, in accordance
with the requirements set in Regulation (EU) 2019/943 and Directive (EU) 2019/944 should provide the necessary
dispatch and investment signals to maximise the potential development of those technologies. This is expected to be
the case once the island of Crete is fully interconnected with mainland Greece.
6/8 ELI: http://data.europa.eu/eli/dec/2024/1274/ojEN
OJ L, 3.5.2024
(40) As indicated in recital 56 of Decision (EU) 2022/258, prior to the completion of the Phase I interconnection,
technical limitations were applied to Crete, imposing a maximum penetration of renewables to 25 % of the load,
due to operational security constraints. The completion of Phase I relieved, to a certain extent, that limitation
imposed on renewables. The hybrid model allows Crete to export its electricity in case of low load and high
renewables generation, in order to avoid curtailment of renewables. Greece submitted figures in support of that
statement, demonstrating that during 2021 and especially 2022, which marked the first full year of the operation of
the Phase I interconnection, there was an increase in RES production compared to previous years.
(41) Greece notes that the requested derogation will not slow down the already ongoing development and preparation for
the installation of new RES capacities on the island of Crete. Greece also submitted that upon completion of the full
interconnection, Crete will accommodate at least 2 150MW of RES, which, considering the installation of storage
units, may increase to 2 500MW.
(42) As regards increased flexibility, energy storage and demand response, the possibility of offering flexibility services,
including storage, to support the electric system depends on the quality of the price signals and their ability to
provide efficient investment and dispatch incentives to the providers of those services. As a rule, structural
congestion within a bidding zone, which will be the case during the transitional period from Phase I to Phase II, can
result in distorted investment signals for location-specific flexibility services. However, in a two-bidding zones
approach for Crete and mainland Greece, the investment signals would be highly unstable, given the timeframe for
the completion of Phase II and the full interconnection of Crete to mainland Greece, which will relieve structural
congestion. Therefore, since the connection to the mainland will enable market-based provision of flexibility
services, a short-term derogation which enables rapid integration of Crete into the mainland system is beneficial to
the integration of demand response, energy storage and other flexibility sources.
(43) Article 64 of Regulation (EU) 2019/943 does not require that derogation decisions maximise the potential for
flexibility or energy storage. A derogation under that Article only aims to ensure that it does not obstruct such
transition. In other words, the derogation should not prevent developments which, without the derogation, would
occur naturally. It is unlikely that, absent the derogation, well-functioning forward, day-ahead, intraday and
balancing markets would develop in each of the electricity systems in the island of Crete. This is due to the
challenges linked to the operation of the small connected electricity systems, the very low levels of competition in
the generation segment, and the lack of connection to the mainland market. In that respect, the limited duration of
the derogation, and the readiness for a full market operation as soon as Phase II is completed, is of utmost
importance.
(44) Given its short-term nature, the hybrid model does not appear to have a noticeable impact on the further
development of renewable energy, flexibility, energy storage, electromobility and demand response.
(45) Finally, Article 64(1) of Regulation (EU) 2019/943 requires the Commission to set out to what extent the derogation
is to take into account the application of the network codes and guidelines. In this case, except for the provisions
affected by the scope of the derogation detailed in recitals 32 to 37, the network codes and guidelines are, and are to
remain, applicable to the island of Crete.
4.4. Limitation of the derogation in time and conditions aiming to increase competition and integration with
the internal market for electricity
(46) Article 64 of Regulation (EU) 2019/943 and Article 66 of Directive (EU) 2019/944 expressly set out that the
derogation is to be limited in time and is to be subject to conditions aiming to increase competition and integration
with the internal market for electricity.
(47) In light of the reasons put forward by Greece in recital 19, the new derogation request is limited to the transitional
period ending on 31 December 2025at the latest.
ELI: http://data.europa.eu/eli/dec/2024/1274/oj 7/8EN
OJ L, 3.5.2024
(48) It is understood that by 31 December 2025the interconnector between Crete and the Greek continental system is
expected to be operational, together with the appropriate metering infrastructure enabling Crete to become part of
the Greek wholesale electricity markets. Greece confirmed that there will not be any further delay to the completion
of the interconnection project.
4.5. Time of effect
(49) While the Application was received on 18 December 2023, it was not possible to adopt this decision before
31 December 2023, at which point the derogation granted in Decision (EU) 2022/258 expired. In order to avoid
rapid and unpredictable changes of the regulatory framework for the period between 1 January 2024and the date
of adoption of this Decision, which could seriously harm market functioning on the island of Crete and possibly in
mainland Greece, this Decision should apply from the date following the end date of the derogation granted in
Decision (EU) 2022/258, namely from 1 January 2024.
HAS ADOPTED THIS DECISION:
Article 1
A derogation is granted to the Hellenic Republic from the provisions of Article 6, Article 7(1), Article 8(1) and (4) and
Articles 9, 10 and 11 of Regulation (EU) 2019/943 and from the provisions of Article 40(4) to (7) of Directive
(EU) 2019/944, as regards the island of Crete.
Article 2
The derogation granted under Article 1 shall apply from 1 January 2024until 31 December 2025or until the completion
of Phase II of the interconnection between Crete and mainland Greece, whichever comes first.
Article 3
The Hellenic Republic shall inform the Commission in two instances, first by 31 December 2024and second by 30 June
2025, of the progress and remaining planning towards the completion and commercial operation of Phase II of the
interconnection between Crete and mainland Greece, including regarding the deployment and operation of the adequate
metering infrastructure allowing the participation of Crete in the Greek wholesale and balancing market.
Article 4
This Decision is addressed to the Hellenic Republic.
Done at Brussels, 29 April 2024.
For the Commission
Kadri SIMSON
Member of the Commission
8/8 ELI: http://data.europa.eu/eli/dec/2024/1274/oj