Date: 2019-04-10Category: Not ApplicableState: Union GovernmentCountry: Europe
Commission Implementing Decision (EU) 2019/570 of 8 April 2019 laying down rules for the implementation of Decision No 1313/2013/EU of the European Parliament and of the Council as regards rescEU capacities and amending Commission Implementing Decision 2014/762/EU (notified under document C(2019) 2644) (Text with EEA relevance.)
Issued by European Commission
· Directorate-General for European Civil Protection and Humanitarian Aid Operations (ECHO)
Executive Summary:
This Commission Implementing Decision (EU) 2019/570 lays down rules for implementing Decision No 1313/2013/EU regarding rescEU capacities, focusing on aerial forest firefighting. It defines the initial composition of rescEU, its quality requirements, and the financing of capacities during the transitional period. It also amends Implementing Decision 2014/762/EU by deleting Chapter 7. The decision was adopted on April 8, 2019, and is addressed to the Member States.
Key Points / Main Content:
* **Subject Matter:**
* Establishes rules for implementing Decision No 1313/2013/EU concerning:
* The initial composition of rescEU and its quality requirements.
* Financing of capacities during the transitional period per Article 35 of Decision No 1313/2013/EU.
* **Initial Composition of rescEU:**
* rescEU shall consist of aerial forest firefighting capacities, including:
* Airplanes.
* Helicopters.
* Quality requirements for these capacities are detailed in the Annex.
* **Financial Arrangements:**
* The Commission will define criteria in the annual work program for awarding direct grants to cover costs necessary to ensure rapid access to capacities corresponding to those in Article 2, as per Article 35 of Decision No 1313/2013/EU.
* Covered costs include:
* Standby costs (including maintenance).
* Staff costs.
* Training costs (including crew and technical staff).
* Warehousing costs.
* Insurance costs.
* Other costs to ensure effective availability.
* **Amendment to Implementing Decision 2014/762/EU:**
* Chapter 7 of Implementing Decision 2014/762/EU is deleted.
* **Annex: Quality Requirements for rescEU Capacities:**
* **Aerial Forest Firefighting Capacities using Airplanes:**
* *Tasks:* Contribute to extinguishing large forest fires.
* *Capacities:* Minimum 2 airplanes (3,000 litres each) or 1 airplane (8,000 litres). Continuous operation ability.
* *Main Components:* Airplane, minimum two crews, technical staff, field maintenance kit, communication equipment.
* *Self-sufficiency:* Equipment storage, maintenance, and communication equipment.
* *Deployment:* Availability for departure within 3 hours for rapid intervention, deployable within 24 hours in a 2,000 km range.
* **Aerial Forest Firefighting Capacities using Helicopters:**
* *Tasks:* Contribute to extinguishing large forest fires.
* *Capacities:* 1 helicopter (minimum 3,000 litres). Continuous operation ability. Up to 3 helicopters (total 3,000 litres minimum) when justified by regional vulnerability assessment.
* *Main Components:* Helicopter, minimum two crews, technical staff, water bucket/releasing kit, maintenance/spare parts set, rescue hoists, communication equipment.
* *Self-sufficiency:* Equipment storage, maintenance, and communication equipment.
* *Deployment:* Availability for departure within 3 hours for rapid intervention, deployable within 24 hours in a 2,000 km range.
Impact Analysis:
* **Member States:**
* *Impact:* This decision affects Member States by defining the requirements for their contribution to rescEU aerial firefighting capabilities and outlining the financial support available during the transitional period.
* *Action Required:* Member States need to review and align their aerial forest firefighting capacities with the quality requirements specified in the Annex, and prepare to apply for direct grants based on the criteria defined in the Commission's annual work program. They must also note the amendment to Implementing Decision 2014/762/EU.
Key Entities Referenced
European Union: A political and economic union of member states located primarily in Europe.
European Parliament: One of the legislative branches of the European Union.
Council of the European Union: A legislative body of the European Union, composed of government ministers from each member state.
European Commission: An executive branch of the European Union responsible for proposing legislation, implementing decisions, upholding the EU treaties and managing the day-to-day business of the EU.
rescEU: A system established within the Union Civil Protection Mechanism to provide assistance in overwhelming situations where existing national capacities and those committed by Member States are insufficient.
Union Civil Protection Mechanism: A framework for cooperation between the European Union and Member States to improve the Union's response to natural and man-made disasters.
Christos Stylianides: A Member of the European Commission.
Brussels: The location where the decision was made.
10.4.2019 EN Official Journal of the European Union L 99/41
COMMISSION IMPLEMENTING DECISION (EU) 2019/570
of 8 April 2019
laying down rules for the implementation of Decision No 1313/2013/EU of the European
Parliament and of the Council as regards rescEU capacities and amending Commission
Implementing Decision 2014/762/EU
(notified under document C(2019) 2644)
(Text with EEA relevance)
THE EUROPEAN COMMISSION,
Having regard to the Treaty on the Functioning of the European Union,
Having regard to Decision No 1313/2013/EU of the European Parliament and of the Council of 17 December 2013 on
a Union Civil Protection Mechanism (1), and in particular Article 32(1)(g) thereof,
Whereas:
(1) The Union Civil Protection Mechanism (‘the Union Mechanism’) set out in Decision No 1313/2013/EU
strengthens cooperation between the Union and the Member States and facilitates coordination in the field of
civil protection in order to improve the Union's response to natural and man-made disasters.
(2) Decision No 1313/2013/EU defines the legal framework of rescEU. RescEU aims to provide assistance in
overwhelming situations where overall existing capacities at national level and those committed by Member
States to the European Civil Protection Pool are not able to ensure an effective response.
(3) In recent years there has been a sharp increase in the number of extreme forest fires in Europe with serious
economic, environmental and social consequences. In particular, the 2017 and 2018 forest fire seasons
demonstrated the need to be prepared when disasters severely and simultaneously affect several Member States.
(4) The changing nature of the forest fire risk has resulted in proven response capacity gaps at Union level. These
gaps were particularly evident during the 2017 forest firefighting season when capacities made available via the
Union Mechanism were insufficient to respond to the needs of countries requesting assistance.
(5) The initial composition of rescEU should therefore be defined with the utmost urgency in accordance with
Article 12(2) of Decision No 1313/2013/EU and should in the first implementing decision include aerial forest
firefighting capacities to respond to wild fires. Due to the necessary flexibility during the transitional period
pursuant to Article 35 of Decision No 1313/2013/EU, the number of rescEU capacities should be indicatively set
out in subsequent implementing decisions.
(6) In accordance with Article 12(4) of Decision No 1313/2013/EU, quality requirements for aerial forest firefighting
capacities under rescEU should be laid down after consultation with Member States and should be based on
established international standards, where such standards already exist. Given the lack of established international
standards for aerial forest firefighting capacities, the quality requirements for aerial forest firefighting capacities
should be based on the existing general requirements for modules under the European Civil Protection Pool and
best practices within the Union Mechanism. Those quality requirements should be laid down in an Annex to this
Decision.
(7) For reasons of budgetary discipline, it is necessary to lay down in this Decision the costs associated with the
Union financial support under rescEU during the transitional period.
(8) In the interest of sound financial management, direct grants for rescEU capacities during the transitional period
should be awarded on the basis of an annual work programme.
(1) OJ L 347, 20.12.2013, p. 924.L 99/42 EN Official Journal of the European Union 10.4.2019
(9) With the entry into force on 21 March 2019 of Decision (EU) 2019/420 of the European Parliament and of the
Council (2), the rules on addressing temporary shortcomings in extraordinary disasters laid out in Commission
Implementing Decision 2014/762/EU (3) have become obsolete. For reasons of consistency, Chapter 7 of
Implementing Decision 2014/762/EU should be deleted.
(10) The measures provided for in this Decision are in accordance with the opinion of the committee referred to in
Article 33(1) of Decision No 1313/2013/EU,
HAS ADOPTED THIS DECISION:
Article 1
Subject matter
This Decision lays down rules for the implementation of Decision No 1313/2013/EU as regards:
(a) the initial composition of rescEU in terms of capacities and its quality requirements;
(b) the financing of capacities during the transitional period referred to in Article 35 of Decision No 1313/2013/EU.
Article 2
The initial composition of rescEU
1. rescEU shall consist of aerial forest firefighting capacities.
2. The aerial forest firefighting capacities referred to in paragraph 1 shall include:
(a) aerial forest firefighting capacities using airplanes;
(b) aerial forest firefighting capacities using helicopters.
3. The quality requirements for the capacities referred to in paragraph 2 are set out in the Annex.
Article 3
Financial arrangements for the rescEU capacities referred to in Article 35 of Decision
No 1313/2013/EU
1. The Commission shall define in the annual work programme the criteria for awarding direct grants to cover the
costs referred to in Article 35 of Decision No 1313/2013/EU which are necessary to ensure rapid access to capacities
corresponding to those referred to in Article 2.
2. The costs referred to in Article 35 of Decision No 1313/2013/EU shall include stand-by costs, including if
applicable, costs related to maintenance, costs related to staff, costs related to training, including the training of crew
and technical staff, costs related to warehousing, costs related to insurance, as well as other costs necessary to ensure the
effective availability of such capacities.
Article 4
Amendment to Implementing Decision 2014/762/EU
Chapter 7 of Implementing Decision 2014/762/EU is deleted.
(2) Decision (EU) 2019/420 of the European Parliament and of the Council of 13 March 2019 amending Decision No 1313/2013/EU on
a Union Civil Protection Mechanism (OJ L 77 I, 20.3.2019, p. 1).
(3) Commission Implementing Decision 2014/762/EU of 16 October 2014 laying down rules for the implementation of Decision
No 1313/2013/EU of the European Parliament and of the Council on a Union Civil Protection Mechanism and repealing Commission
Decisions 2004/277/EC, Euratom and 2007/606/EC, Euratom (OJ L 320, 6.11.2014, p. 1).10.4.2019 EN Official Journal of the European Union L 99/43
Article 5
Addressees
This Decision is addressed to the Member States.
Done at Brussels, 8 April 2019.
For the Commission
Christos STYLIANIDES
Member of the CommissionL 99/44 EN Official Journal of the European Union 10.4.2019
ANNEX
QUALITY REQUIREMENTS FOR RESCEU CAPACITIES
1. Aerial forest firefighting capacities using airplanes
Tasks — Contribute to the extinction of large forest and vegetal fires by performing aerial fire
fighting.
Capacities — 2 airplanes with a minimum capacity of 3 000 litres each or 1 airplane with a minimum
capacity of 8 000 litres(1).
— Ability to perform continuous operations.
Main components — Airplane.
— Minimum of two crews.
— Technical staff.
— Field maintenance kit.
— Communication equipment allowing air-to-air and air-to-ground communication.
Self-sufficiency — Equipment storage and maintenance of the equipment of the module;
— Equipment for the communication with the relevant partners, notably those in charge of
the coordination on site.
Deployment — Availability for departure maximum 3 hours after the acceptance of the offer in the case
of a rapid intervention response(2).
— Ability to be deployed in a range of 2 000 km within maximum 24 hours.
(1) Such requirements may be subject to review based on possible developments on the market of aerial forest firefighting capacities,
including in relation to the availability of spare parts.
(2) Rapid intervention response is a response operation lasting maximum one day including the flight to and from the site where the
rescEU capacity is positioned.
2. Aerial forest firefighting capacities using helicopters
Tasks — Contribute to the extinction of large forest and vegetal by performing aerial firefighting.
Capacities — 1 helicopter with a minimum capacity of 3 000 litres(1)
— Ability to perform continuous operations.
Main components — Helicopter with minimum two crews.
— Technical staff.
— Water bucket or releasing kit.
— 1 maintenance set.
— 1 spare parts set.
— Rescue hoists.
— Communication equipment allowing air-to-air and air-to-ground communication.
Self-sufficiency — Equipment storage and maintenance of the equipment of the module;
— Equipment for the communication with the relevant partners, notably those in charge of
the coordination on site.10.4.2019 EN Official Journal of the European Union L 99/45
Deployment — Availability for departure maximum 3 hours after the acceptance of the offer in the case
of a rapid intervention response(2).
— Ability to be deployed in a range of 2 000 km within maximum 24 hours.
(1) For the purposes of implementing Article 35 of Decision No 1313/2013/EU and when justified based on assessment of regional
vulnerability, aerial forest firefighting capacities using helicopters may be composed of maximum 3 helicopters with a total mini
mum capacity of 3 000 litres.
(2) Rapid intervention response is a response operation lasting maximum one day including the flight to and from the site where the
rescEU capacity is positioned.