Date: 2019-09-27Category: Not ApplicableState: Union GovernmentCountry: Europe
Resolution (EU, Euratom) 2019/1549 of the European Parliament of 26 March 2019 with observations forming an integral part of the decision on discharge in respect of the implementation of the budget for the European Joint Undertaking for ITER and the Development of Fusion Energy for the financial year 2017
Executive Summary:
The European Parliament resolution addresses the discharge of the European Joint Undertaking for ITER and the Development of Fusion Energy's budget implementation for the 2017 financial year. It acknowledges the fairness and legality of the Joint Undertaking's accounts but expresses concerns regarding project delays, cost increases, and shortcomings in budget planning, recruitment, and internal controls. The resolution calls for action to address these issues and improve the management of the ITER project.
Key Points / Main Content:
General Observations:
* The Joint Undertaking was established in March 2007 to contribute to the ITER project, implement the broader approach agreement with Japan, and prepare for a demonstration fusion reactor.
* The Court of Auditors found the Joint Undertaking's 2017 annual accounts to be fairly presented and legal and regular in all material respects.
* The budget cap of EUR 6,600,000,000 until 2020 must be maintained.
* The ITER project faces an estimated 15-year delay compared to the original baseline, with the first strategic milestone (First Plasma) targeted for December 2025 and completion by December 2035.
* An additional EUR 5,400,000,000 in funding (2008 values) may be required after 2020, representing an 82% increase over the approved budget.
* The cost of the operational phase after 2035 has not yet been estimated, and the Joint Undertaking is requested to do so.
* The Commission suggests allowing for a contingency of up to 24 months in terms of schedule and 10-20% in terms of budget.
Budget and Financial Management:
* The final 2017 budget included EUR 588,916,058 in commitment appropriations and EUR 864,914,263 in payment appropriations, with utilization rates of 99.9% and 96.3%, respectively.
* The Joint Undertaking required an additional EUR 832,600,000 in payment appropriations for 2017 due to shortcomings in budget planning.
* A lack of payment appropriations of approximately EUR 150,000,000 was estimated for the 2018 budget.
Performance:
* The Joint Undertaking uses technical and non-technical objectives and key performance indicators to measure its performance.
* Seven of the nine planned ITER Council milestones were delivered in 2017.
Prevention and Management of Conflicts of Interest and Transparency:
* The Joint Undertaking continued implementing the public procurement part of the antifraud strategy and adopted a checklist based on procurement fraud risk indicators.
Personal Selection and Recruitment:
* Significant shortcomings were found in the recruitment of key management staff.
Internal Control:
* The Joint Undertaking has not consistently followed up on the declarations of interests from senior management.
* The General Court of the Court of Justice of the European Union annulled two 2015 employment decisions due to irregularities in the recruitment process.
* Significant shortcomings in internal communication strategies led to a failure to disclose a provision for decommissioning costs in previous years' accounts.
Operational Procurement and Grants:
* 83 operational procurement procedures were launched, and 69 operational procurement contracts were signed in 2017.
Impact Analysis:
European Joint Undertaking for ITER and the Development of Fusion Energy:
*Impact:* Must address concerns raised about project delays, cost increases, budget planning, recruitment practices, internal controls, and communication strategies.
*Action Required:* Develop and implement an action plan to mitigate risks, improve management and control, and address shortcomings in recruitment and internal communication. Estimate the cost of the operational phase after 2035. Report improvements in recruitment and declaration of interest follow-up to the discharge authority.
ITER Project Parties:
*Impact:* Face potential risks of further cost increases and delays.
*Action Required:* Collaborate with the Joint Undertaking to identify and analyze potential risks and implement an action plan.
European Commission:
*Impact:* Responsible for overseeing the Joint Undertaking's budget and ensuring adherence to the EUR 6,600,000,000 budget cap.
*Action Required:* Monitor the Joint Undertaking's progress in addressing concerns raised in the resolution and ensure appropriate measures are taken to manage costs and risks.
Council of the European Union:
*Impact:* Sets the budget for the Joint Undertaking and approves key project milestones.
*Action Required:* Consider future Multiannual Financial Framework commitments to address the additional funding required for the ITER project.
European Parliament (Discharge Authority):
*Impact:* Responsible for granting discharge in respect of the implementation of the budget.
*Action Required:* Monitor the Joint Undertaking's progress in addressing the concerns raised and take appropriate action if necessary.
Key Entities Referenced
European Joint Undertaking for ITER and the Development of Fusion Energy: A Joint Undertaking established in March 2007, responsible for the Union's contribution to the ITER project.
ITER: The International Thermonuclear Experimental Reactor, an international fusion energy project.
Euratom: European Atomic Energy Community, a member of the Joint Undertaking represented by the Commission.
European Parliament: The parliamentary body of the European Union, responsible for decisions on discharge in respect of budget implementation.
Court of Auditors: The European Court of Auditors, responsible for auditing the Joint Undertaking's annual accounts.
ITER Council: The governing body of the ITER Organisation, responsible for approving project baselines and schedules.
Japan: A country that has a broader approach agreement with Euratom in the field of controlled nuclear fusion.
Brexit: The withdrawal of the United Kingdom from the European Union, the impact of which needs further analysis by the Joint Undertaking.
L 249/344 EN Official Journal of the European Union 27.9.2019
RESOLUTION (EU, Euratom) 2019/1549 OF THE EUROPEAN PARLIAMENT
of 26 March 2019
with observations forming an integral part of the decision on discharge in respect of the
implementation of the budget for the European Joint Undertaking for ITER and the Development
of Fusion Energy for the financial year 2017
THE EUROPEAN PARLIAMENT,
— having regard to its decision on discharge in respect of the implementation of the budget of the European Joint
Undertaking for ITER and the Development of Fusion Energy for the financial year 2017,
— having regard to Rule 94 of and Annex IV to its Rules of Procedure,
— having regard to the report of the Committee on Budgetary Control (A8-0126/2019),
A. whereas the European Joint Undertaking for ITER and the Development of Fusion Energy (the ‘Joint Undertaking’)
was established in March 2007 for a period of 35 years by Council Decision 2007/198/Euratom (1);
B. whereas the members of the Joint Undertaking are Euratom, represented by the Commission, the member states of
Euratom, and third countries which have concluded a cooperation agreement with Euratom in the field of
controlled nuclear fusion;
C. whereas the objectives of the Joint Undertaking are to provide the Union's contribution to the ITER international
fusion energy project, to implement the broader approach agreement between Euratom and Japan, and to prepare
for the construction of a demonstration fusion reactor;
D. whereas the Joint Undertaking started to work autonomously in March 2008;
General
1. Notes that the report of the Court of Auditors (the ‘Court’) on the Joint Undertaking's annual accounts for the
financial year 2017 (the ‘Court's report’) finds the annual accounts to be presented fairly, in all material respects, its
financial position as at 31 December 2017 and the results of its operations, its cash flows and the changes in its
net assets for the year then ended, to be in compliance with its financial regulation and the accounting rules
adopted by the Commission's accounting officer;
2. Acknowledges that the transactions underlying the annual accounts of the Joint Undertaking for the financial year
2017 are, in all material respects, legal and regular;
3. Highlights the fact that the Joint Undertaking is responsible for the management of the Union's contribution to the
ITER project and that the budget cap of EUR 6 600 000 000 until 2020 must be maintained; notes that that figure
does not include the EUR 663 000 000 proposed by the Commission in 2010 to cover potential contingencies;
4. Notes that in November 2016, the Council of ITER Organisation (the ‘ITER Council’) approved a new ITER project
baseline for the scope, schedule and the costs of the project; notes, moreover, that the overall project schedule for
operations ‘First Plasma’ and ‘Deuterium-Tritium’ was approved; notes the fact that following the approval of the
new ITER project baseline, the Joint Undertaking set the new timetable and recalculated the related cost at
completion of the Joint Undertaking's contribution to the project construction phase;
5. Expresses ongoing concern that the estimated completion date for the whole construction phase is currently
planned with a delay of about 15 years compared to the original baseline; acknowledges the fact that the ITER
Project reported completing 50 percent of the ‘total construction work scope through First Plasma’ at the end of
2017; notes that the new schedule endorsed by the ITER Council set out a four-stage approach, making December
2025 the deadline for achieving the first strategic milestone of the project construction phase (‘First Plasma’) and
December 2035 the estimated completion date for the whole construction phase; acknowledges the fact that the
aim of the new staged approach is to better align the project implementation with the priorities and constraints of
all members of the ITER Organisation;
(1) Council Decision No 2007/198/Euratom of 27 March 2007 establishing a Joint Undertaking for ITER and the Development of Fusion
Energy and conferring advantages upon it (OJ L 90, 30.3.2007, p. 58).27.9.2019 EN Official Journal of the European Union L 249/345
6. Notes that the Court's report found that the results, which were presented to the Joint Undertaking's Governing
Board in December 2016, indicated an expected additional funding requirement of EUR 5 400 000 000 (in 2008
values) to that already committed for the construction phase after 2020, which represents an increase of 82 % in
relation to the approved EUR 6 600 000 000 (in 2008 values) budget; reiterates the fact that the amount of
EUR 6 600 000 000 adopted by the Council in 2010 serves as a ceiling for the Joint Undertaking's spending up to
2020; recognises that the additional funding required to complete the ITER project must involve future Multiannual
Financial Framework commitments;
7. Highlights the fact that in addition to the construction phase, the Joint Undertaking will have to contribute to the
ITER operational phase and to the subsequent ITER deactivation and decommissioning phases; takes note that the
contribution to the deactivation and the decommissioning phases were estimated at EUR 95 540 000 (in 2001
values) and EUR 180 200 000 (in 2001 values); is concerned that the contribution for the operational phase after
2035 has not yet been estimated in financial terms; calls on the Joint Undertaking to estimate the cost of the
operational phase after 2035 as soon as possible;
8. Stresses that on 14 June 2017, the Commission issued a communication entitled ‘EU contribution to a reformed
ITER project’, in which it suggested that a contingency of up to 24 months in terms of schedule and 10 to 20 % in
terms of budget would be appropriate; notes in addition that the measures taken to respect the
EUR 6 600 000 000 capped budget included postponing the procurement and installation of all components not
essential to First Plasma; is very concerned that while positive steps have been taken to improve the management
and control of the ITER project construction phase, there remains an ongoing risk of further cost increases and
delays in project implementation compared to the new proposed baseline; calls on the Joint Undertaking and
indeed all parties of the project to take appropriate action to identify and analyse all potential risks and set up an
Action Plan that will also include a further analysis on the impact of Brexit;
Budget and financial management
9. Notes that the final 2017 budget available for implementation included commitment appropriations of
EUR 588 916 058 and payment appropriations of EUR 864 914 263; notes that the utilisation rates for
commitment and payment appropriations were 99,9 % and 96,3 % respectively (99,8 % and 98,1 % in 2016);
10. Regrets that, due to serious shortcomings in the budget planning process coupled with the acceleration of some
contracts, the Joint Undertaking finally needed EUR 832 600 000 in payment appropriations for 2017, while the
initial amount approved in February 2017 amounted to EUR 548 600 000; notes with regret that the Joint
Undertaking has estimated a lack of payment appropriations of about EUR 150 000 000 for the 2018 budget;
notes from the Joint Undertaking's reply that the Euratom provided additional payment appropriations and that the
payment forecasting system has been totally redesigned and integrated;
11. Notes that out of EUR 588 916 058 available for commitment appropriations, 96,5 % was implemented through
direct individual commitments (99,7 % in 2016);
12. Acknowledges almost full implementation of the 2017 budget and the automatic carry-overs;
13. Notes that, in 2017, the balance of the budget outturn amounted to EUR 17 236 192 (EUR 5 880 000 in 2016);
Performance
14. Observes that the Joint Undertaking uses sets of technical and non-technical objectives and key performance
indicators to measure its performance; welcomes that the Joint Undertaking delivered seven of the nine planned
ITER Council milestones in 2017; notes with appreciation that at the overall ITER Project level, 30 out of 32 ITER
Council milestones were achieved;
15. Notes that the content, structure and therefore the reliability and effectiveness of the schedules has been improved
during the last years;L 249/346 EN Official Journal of the European Union 27.9.2019
Prevention and management of conflicts of interest and transparency
16. Notes that in 2017, the Joint Undertaking's governing board continued implementing the public procurement part
of the anti-fraud strategy; notes that the Joint Undertaking adopted a checklist based in its own set of procurement
fraud risk indicators, i.e., red flags, considered a prerequisite to the development of the Anti-fraud IT tool, having
developed them internally; acknowledges that the use of the checklist is now being introduced in the internal
processes of the Joint Undertaking together with other procurement changes; notes that the Ethics and Integrity
sessions were given to newcomers;
Personal selection and recruitment
17. Notes with regret that significant shortcomings were found by the Court in relation to the recruitment of key
management staff; calls on the Joint Undertaking to report to the discharge authority in any improvement made in
that regard;
Internal control
18. Notes that the Joint Undertaking has not consistently followed on the declarations of interests from senior
management; calls on the Joint Undertaking to report to the discharge authority any improvement made in this
regard;
19. Observes that in 2018 the General Court of the Court of Justice of the European Union annulled two 2015
employment decisions due to irregularities in the recruitment process; notes from the Joint Undertaking's reply that
it appealed against those annulments and that the European Ombudsman had ruled in favour of the Joint
Undertaking in those cases;
20. Notes with regret that significant shortcomings in the internal communication strategies did not ensure the dissemi
nation of appropriate information on the estimated costs of the decommissioning phase within the organisation
and, therefore, the Joint Undertaking disclosed no provision for such liability in the accounts of the previous years;
notes that the amount of the accounting provision up to 31 December 2017 has been estimated at
EUR 85 200 000;
Operational procurement and grants
21. Notes that during 2017, 83 operational procurement procedures were launched, and 69 operational procurement
contracts were signed.