UN Regulation No 168 – Uniform provisions concerning the approval of light duty passenger and commercial
vehicles with regards to real driving emissions (RDE) [2024/211]
Date of entry into force: 26 March 2024
This document is meant purely as documentation tool. The authentic and legally binding text is: ECE/TRANS/WP.29/2023/77.
CONTENTS
Regulation
1. Scope and application
2. Abbreviations
3. Definitions
4. Application for Approval
5. Approval
6. General requirements
7. Performance requirements for instrumentation
8. Test conditions
9. Test procedure
10. Test data analysis
11. Modifications and extensions to Type Approval
12. Conformity of Production
13. Penalties for non-conformity of production
14. Production definitively discontinued
15. Transitional provisions
16. Names and addresses of the Technical Services responsible for conducting approval tests and of Type Approval
Authorities
Annexes
1 Engine and vehicle characteristics and information concerning the conduct of tests
2 Communication
3 Arrangement of the approval mark
4 Test procedure for vehicle emissions testing with a portable emissions measurement system (PEMS)
5 Specifications and calibration of PEMS components and signals
6 Validation of PEMS and non-traceable exhaust mass flow rate
7 Determination of instantaneous emissions
8 Assessment of overall trip validity using the moving averaging window method
9 Assessment of excess or absence of trip dynamics
10 Procedure to determine the cumulative positive elevation gain of a PEMS trip
11 Calculation of the final RDE emissions results
12 Manufacturer's RDE certificate of compliance
ELI: http://data.europa.eu/eli/reg/2024/211/oj 1/98EN
OJ L, 12.1.2024
1. Scope and application
This Regulation aims at providing a worldwide harmonized method to determine the levels of Real Driving
Emissions (RDE) of gaseous compounds and particles from light-duty vehicles.
This Regulation applies to the type approval of vehicles of categories M with a reference mass not exceeding
1
2 610 kg and vehicles of categories M and N with a reference mass not exceeding 2 610 kg and a technical
2 1
permissible maximum laden mass not exceeding 3 500kg with regard to their Real Driving Emissions.
At the manufacturer's request, type approval granted under this Regulation may be extended from vehicles
mentioned above to vehicles of categories M with a reference mass not exceeding 2 840 kg and vehicles of
1
categories M and N with a reference mass not exceeding 2 840kg and a technical permissible maximum laden
2 1
mass not exceeding 3 500kg and which meet the conditions laid down in this Regulation.
Pure Electric Vehicles and Fuel Cell Vehicles are out of the scope of this Regulation.
2. Abbreviations
Abbreviations refer generically to both the singular and the plural forms of abbreviated terms.
CLD — ChemiLuminescence Detector
CVS — Constant Volume Sampler
DCT — Dual Clutch Transmission
ECU — Engine Control Unit
EFM — Exhaust mass Flow Meter
FID — Flame Ionisation Detector
FS — full scale
GNSS — Global Navigation Satellite System
HCLD — Heated ChemiLuminescence Detector
HEV — Hybrid Electric Vehicle
ICE — Internal Combustion Engine
LPG — Liquid Petroleum Gas
NDIR — Non-Dispersive InfraRed analyser
NDUV — Non-Dispersive UltraViolet analyser
NG — Natural Gas
NMC — Non-Methane Cutter
NMC-FID — Non-Methane Cutter in combination with a Flame-Ionisation
Detector
NMHC — Non-Methane HydroCarbons
NOVC-HEV — Not off-vehicle charging hybrid electric vehicle
OBD — On-Board Diagnostics
OVC-HEV — Off-vehicle charging hybrid electric vehicle
PEMS — Portable Emissions Measurement System
RPA — Relative Positive Acceleration
SEE — Standard Error of Estimate
THC — Total HydroCarbons
2/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
VIN — Vehicle Identification Number
WLTC — Worldwide harmonized Light vehicles Test Cycle
WLTP — Worldwide harmonized Light vehicles Test Procedure
WWH-OBD — WorldWide Harmonized On-Board Diagnostics
3. Definitions
For the purposes of this regulation, the following definitions shall apply:
3.1. "Vehicle type with regard to Real Driving Emissions" means a group of vehicles which do not differ with respect to the
criteria constituting a "PEMS test family" as defined in paragraph 6.3.1.
3.2. Test equipment
3.2.1. "Accuracy" means the difference between a measured value and a reference value, traceable to a national or
international standard and describes the correctness of a result, as depicted in Figure 1.
3.2.2. "Adapter" means in the context of this regulation mechanical parts that allow the connection of the vehicle to a
commonly used or standardised measurement device connector.
3.2.3. "Analyser" means any measurement device that is not part of the vehicle but installed to determine the
concentration or the amount of gaseous or particle pollutants.
3.2.4. "Calibration" means the process of setting a measurement system's response so that its output agrees with a range
of reference signals.
3.2.5. "Calibration gas" means a gas mixture used to calibrate gas analysers.
3.2.6. "Delay time" means the difference in time between the change of the component to be measured at the reference
point and a system response of 10 per cent of the final reading (t ) with the sampling probe being defined as the
10
reference point, as depicted in Figure 2.
3.2.7. "Full scale" means the full range of an analyser, flow-measuring instrument or sensor as specified by the equipment
manufacturer or the highest range used for the specific test.
3.2.8. "Hydrocarbon response factor" of a particular hydrocarbon species means the ratio between the reading of a FID and
the concentration of the hydrocarbon species under consideration in the reference gas cylinder, expressed as
ppmC1.
3.2.9. "Major maintenance" means the adjustment, repair or replacement of a component or module that could affect the
accuracy of a measurement.
3.2.10. "Noise" means two times the root mean square of ten standard deviations, each calculated from the zero responses
measured at a constant frequency which is a multiple of 1,0 Hz during a period of 30 seconds.
3.2.11. "Non-methane hydrocarbons" (NMHC) means the Total Hydrocarbons (THC) minus the methane (CH ) contribution.
4
3.2.12. "Precision" means the degree to which repeated measurements under unchanged conditions show the same results
(Figure 1).
ELI: http://data.europa.eu/eli/reg/2024/211/oj 3/98EN
OJ L, 12.1.2024
3.2.13. "Reading" means the numerical value displayed by an analyser, flow-measuring instrument, sensor or any other
measurement devise applied in the context of vehicle emission measurements.
3.2.14. "Reference value" means a value traceable to a national or international standard, as depicted in Figure 1.
3.2.15. "Response time" (t ) means the difference in time between the change of the component to be measured at the
90
reference point and a system response of 90 per cent of the final reading (t ) with the sampling probe being
90
defined as the reference point, whereby the change of the measured component is at least 60 per cent full scale
(FS) and takes place in less than 0,1 second. The system response time consists of the delay time to the system
and of the rise time of the system, as depicted in Figure 2.
3.2.16. "Rise time" means the difference in time between the 10 per cent and 90 per cent response of the final reading (t
10
to t ), as depicted in Figure 2.
90
3.2.17. “Sensor” means any measurement device that is not part of the vehicle itself but installed to determine parameters
other than the concentration of gaseous and particle pollutants and the exhaust mass flow.
3.2.18. “Set point” means the target value a control system aims to reach.
3.2.19. “Span” means to adjust an instrument so that it gives a proper response to a calibration standard that represents
between 75 per cent and 100 per cent of the maximum value in the instrument range or expected range of use.
3.2.20. “Span response” means the mean response to a span signal over a time interval of at least 30 seconds.
3.2.21. “Span response drift” means the difference between the mean response to a span signal and the actual span signal
that is measured over a defined time period after an analyser, flow-measuring instrument or sensor has been
accurately spanned.
3.2.22. “Total hydrocarbons” (THC) means the sum of all volatile compounds measurable by a flame ionization detector
(FID).
3.2.23. “Traceable” means the ability to relate a measurement or reading through an unbroken chain of comparisons to a
national or international standard.
3.2.24. “Transformation time” means the time difference between a change of concentration or flow (t ) at the reference
0
point and a system response of 50 per cent of the final reading (t ), as depicted in Figure 2.
50
3.2.25. "Type of analyser", also referred to as "analyser type" means a group of analysers produced by the same
manufacturer that apply an identical principle to determine the concentration of one specific gaseous component
or the number of particles.
3.2.26. "Type of exhaust mass flow meter" means a group of exhaust mass flow meters produced by the same manufacturer
that share a similar tube inner diameter and function on an identical principle to determine the mass flow rate of
the exhaust gas.
3.2.27. "Verification" means the process of evaluating whether the measured or calculated output of an analyser, flow-
measuring instrument, sensor or signal or method agrees with a reference signal or value within one or more
predetermined thresholds for acceptance.
3.2.28. "Zero" means the calibration of an analyser, flow-measuring instrument or sensor so that it gives an accurate
response to a zero signal.
4/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
3.2.29. "Zero gas" means a gas containing no analyte, which is used to set a zero response on an analyser.
3.2.30. "Zero response" means the mean response to a zero signal over a time interval of at least 30 seconds.
3.2.31. "Zero response drift" means the difference between the mean response to a zero signal and the actual zero signal that
is measured over a defined time period after an analyser, flow-measuring instrument or sensor has been accurately
zero calibrated.
Figure 1
Definition of accuracy, precision and reference value
Figure 2
Definition of delay, rise, transformation and response times
ELI: http://data.europa.eu/eli/reg/2024/211/oj 5/98EN
OJ L, 12.1.2024
3.3. Vehicle characteristics and driver
3.3.1. "Actual mass of the vehicle" means the mass in running order plus the mass of the fitted optional equipment to an
individual vehicle.
3.3.2. "Auxiliary devices" means energy consuming, converting, storing or supplying non-peripheral devices or systems
which are installed in the vehicle for purposes other than the propulsion of the vehicle and are therefore not
considered to be part of the powertrain.
3.3.3. "Mass in running order" means the mass of the vehicle, with its fuel tank(s) filled to at least 90 per cent of its or
their capacity/capacities, including the mass of the driver, fuel and liquids, fitted with the standard equipment in
accordance with the manufacturer's specifications and, when they are fitted, the mass of the bodywork, the cabin,
the coupling and the spare wheel(s) as well as the tools.
3.3.4. "Maximum Permissible Test mass of the vehicle" means the sum of:
(a) The actual mass of the vehicle; and
(b) 90 per cent of the difference between the technically permissible maximum laden mass and the actual mass of
the vehicle (Figure 3).
3.3.5. "Odometer" means an instrument indicating to the driver the total distance driven by the vehicle since its
production.
3.3.6. "Optional equipment" means all the features not included in the standard equipment which are fitted to a vehicle
under the responsibility of the manufacturer, and that can be ordered by the customer.
3.3.7. "Power-to-test-mass-ratio" corresponds to the ratio of the rated engine power of the internal combustion engine
over the test mass of the tested vehicle as defined in paragraph 8.3.1.
3.3.8. “Power-to-mass-ratio” is the ratio of rated power to the mass in running order.
3.3.9. "Rated engine power (P )" means maximum net power of the engine or motor in kW as per the requirements of
rated
UN Regulation No. 85.
3.3.10. "Technically permissible maximum laden mass" means the maximum mass allocated to a vehicle on the basis of its
construction features and its design performances.
3.3.11. "Vehicle OBD information" means information relating to an on-board diagnostic system for any electronic system
on the vehicle.
6/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
Figure 3
Mass definitions
(a) means the mass of the vehicle, with its fuel tank(s) filled to at least 90 per cent of its or their capacity/capacities,
including the mass of the driver, fuel and liquids, fitted with the standard equipment in accordance with the
manufacturer’s specifications and, when they are fitted, the mass of the bodywork, the cabin, the coupling
and the spare wheel(s) as well as the tools.
(b) means all the features not included in the standard equipment which are fitted to a vehicle under the
responsibility of the manufacturer, and that can be ordered by the customer.
3.4. Types of vehicles
3.4.1. "Flex fuel vehicle" means a vehicle with one fuel storage system that can run on different mixtures of two or more
fuels.
3.4.2. "Mono-fuel vehicle" means a vehicle that is designed to run primarily on one type of fuel.
3.4.3. "Not off-vehicle charging hybrid electric vehicle" (NOVC-HEV) means a hybrid electric vehicle that cannot be charged
from an external source.
3.4.4. "Off-vehicle charging hybrid electric vehicle" (OVC-HEV) means a hybrid electric vehicle that can be charged from an
external source.
3.5. Calculations
3.5.1. "Coefficient of determination" (r2) means:
r2 ¼1 –
∑n
i¼1ðyi – a0 –
ða1×xiÞÞ2
∑n
i¼1ðyi –
yÞ2
ELI: http://data.europa.eu/eli/reg/2024/211/oj 7/98EN
OJ L, 12.1.2024
where:
a is the axis intercept of the linear regression line
0
a is the slope of the linear regression line
1
x is the measured reference value
i
y is the measured value of the parameter to be verified
i
y is the mean value of the parameter to be verified
n is the number of values
3.5.2. "Cross-correlation coefficient" (r) means:
r¼qffiffiffiffiffiffiffiffi∑ ffiffiffin iffi¼ffi ffi– ffi1 ffi1 ffiffiðffiffixffiiffi ffi–ffiffi qxÞ×ffiðffiyffiffiiffi ffi–ffi ffiffiyffiffiÞffiffiffiffiffiffiffiffiffiffiffiffiffiffi
∑n
i¼
–
1
1
ðxi –
xÞ2
×
∑n
i¼
–
1
1
ðyi –
yÞ2
where:
x is the measured reference value
i
y is the measured value of the parameter to be verified
i
x is the mean reference value
y is the mean value of the parameter to be verified
n is the number of values
3.5.3. "Root mean square" (x ) means the square root of the arithmetic mean of the squares of values and defined as:
rms
qffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
x ¼ 1∑n x2
rms n i¼1 i
where:
x is the measured or calculated value
i
n is the number of values
3.5.4. "Slope" of a linear regression (a ) means:
1
a ¼
∑n
i¼1ðxi – xÞ×ðyi – yÞ
1 ∑n i¼1ðxi – xÞ2
where:
x is the actual value of the reference parameter
i
y is the actual value of the parameter to be verified
i
x is the mean value of the reference parameter
y is the mean value of the parameter to be verified
n is the number of values
3.5.5. "Standard error of estimate" (SEE) means:
rffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
SEE¼
∑n
i¼1ðyi –
ýÞ2
n – 2
8/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
where:
ý is the estimated value of the parameter to be verified
y is the actual value of the parameter to be verified
i
n is the number of values
3.6. General
3.6.1. "Cold start period" means the period from the test start as defined in paragraph 3.8.5. until the point when the
vehicle has run for 5 minutes. If the coolant temperature is determined, the cold start period ends once the
coolant is at least 70 °C for the first time but no later than 5 minutes after test start. In the case that measuring
the coolant temperature is not feasible, on request of the manufacturer and with approval of the approval
authority, instead of using the coolant temperature, the engine oil temperature may be used.
3.6.2. "Criteria emissions" means those emission compounds for which limits are set in regional legislation.
3.6.3. "Deactivated internal combustion engine" means an internal combustion engine for which one of the following
criteria apply:
(a) The recorded engine speed is < 50 rpm;
(b) Or when the engine speed is not recorded, the exhaust mass flow rate is measured at < 3 kg/h.
3.6.4. "Engine capacity" means either of the following:
(a) For reciprocating piston engines, the nominal engine swept volume;
(b) For rotary piston (Wankel) engines, double the nominal engine swept volume.
3.6.5. "Engine control unit" means the electronic unit that controls various actuators to ensure the optimal performance of
the engine.
3.6.6. "Exhaust emissions" means the emission of gaseous, solid and liquid compounds from the tailpipe.
3.6.7. "Extended factor" means a factor which accounts for the effect of extended ambient temperature or altitude
conditions upon criteria emissions.
3.7. Particles
The term "particle" is conventionally used for the matter being characterised (measured) in the airborne phase
(suspended matter), and the term "particulate" for the deposited matter.
3.7.1. "Particle number emissions" (PN) means the total number of solid particles emitted from the vehicle exhaust
quantified according to the dilution, sampling and measurement methods as specified in this regulation.
3.8. Procedure
3.8.1. "Cold start PEMS trip" means a trip with conditioning of the vehicle prior to the test as described in paragraph
8.3.2.
3.8.2. "Hot start PEMS trip" means a trip without conditioning of the vehicle prior to the test as described in paragraph
8.3.2, but with a warm engine with coolant temperature above 70 °C. In the case that measuring the coolant
temperature is not feasible, on request of the manufacturer and with approval of the approval authority, instead
of using the coolant temperature, the engine oil temperature may be used.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 9/98EN
OJ L, 12.1.2024
3.8.3. "Periodically regenerating system" means an exhaust emissions control device (e.g. catalytic converter, particulate
trap) that requires a periodical regeneration.
3.8.4. "Reagent" means any product other than fuel that is stored on-board the vehicle and is provided to the exhaust
after-treatment system upon request of the emission control system.
3.8.5. "Test start" means (Figure 4) whichever occurs first from:
(a) The first activation of the internal combustion engine;
(b) The first movement of the vehicle with speed greater than 1 km/h for OVC-HEVs and NOVC-HEVS.
Figure 4
Test start definition
3.8.6. "Test end" means (Figure 5) that the vehicle has completed the trip and whichever occurs last from:
(a) The final deactivation of the internal combustion engine;
(b) The vehicle stops and the speed is lower than or equal to 1 km/h for OVC-HEVs and NOVC-HEVS finishing the
test with deactivated internal combustion engine.
10/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
Figure 5
Test end definition
3.8.7. "Validation of PEMS" means the process of evaluating on a chassis dynamometer the correct installation and
functionality within the given accuracy limits of a Portable Emissions Measurement System and exhaust mass
flow rate measurements as obtained from one or multiple non-traceable exhaust mass flow meters or as
calculated from sensors or ECU signals.
4. Application for approval
4.1. The application for approval of a vehicle type with regard to the requirements of this Regulation shall be
submitted by the vehicle manufacturer or by their authorized representative, who is any natural or legal person
who is duly appointed by the manufacturer to represent him before the approval authority and to act on his
behalf in matters covered by this Regulation.
4.1.1. The application referred to in paragraph 4.1. shall be drawn up in accordance with the model of the information
document set out in Annex 1 to this Regulation.
4.2. An appropriate number of vehicles representative of the vehicle type to be approved shall be submitted to the
Technical Service responsible for the approval tests.
4.3. Changes to the make of a system, component or separate technical unit that occur after a type approval shall not
automatically invalidate a type approval, unless its original characteristics or technical parameters are changed in
such a way that the functionality of the engine or pollution control system is adversely affected.
4.4. The manufacturer shall confirm compliance with this Regulation by completing the RDE compliance certificate
set out in Annex 12.
5. Approval
5.1. If the vehicle type submitted for approval meets all the relevant requirements of paragraphs 6., 7., 8., 9., 10.
and 11. of this Regulation, approval of that vehicle type shall be granted.
5.2. An approval number shall be assigned to each type approved.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 11/98EN
OJ L, 12.1.2024
5.2.1. The type approval number shall consist of four sections. Each section shall be separated by the '*' character.
Section 1: The capital letter 'E' followed by the distinguishing number of the Contracting Party which has
granted the type approval.
Section 2: The number [of this UN Regulation,] followed by the letter 'R', successively followed by:
(a) Two digits (with leading zeros as applicable) indicating the series of amendments
incorporating the technical provisions of the UN Regulation applied to the approval (00 for
the UN Regulation in its original form);
(b) A slash (/) and two digits (with leading zeros as applicable) indicating the number of
supplements to the series of amendments applied to the approval (00 for the series of
amendments in its original form);
Section 3: A four-digit sequential number (with leading zeros as applicable). The sequence shall start from
0001.
Section 4: A two-digit sequential number (with leading zeros if applicable) to denote the extension. The
sequence shall start from 00.
All digits shall be Arabic digits.
5.2.2. Example of an Approval Number to this Regulation:
E11*168R01/00/02*0123*01
The first extension of the Approval numbered 0123, issued by the United Kingdom to Series of Amendments 01
which is a Level 2 Approval.
5.2.3. The same Contracting Party shall not assign the same number to another vehicle type.
5.3. Notice of approval or of extension or refusal of approval of a vehicle type pursuant to this Regulation shall be
communicated to the Contracting Parties to the 1958 Agreement which apply this Regulation by means of a
form conforming to the model in Annex 1 to this Regulation.
5.3.1. In the event of amendment to the present text, for example, if new limit values are prescribed, the Contracting
Parties to the 1958 Agreement shall be informed which vehicle types already approved comply with the new
provisions.
5.4. There shall be affixed, conspicuously and in a readily accessible place specified on the approval form, to every
vehicle conforming to a vehicle type approved under this Regulation, an international approval mark consisting
of:
5.4.1. A circle surrounding the letter "E" followed by the distinguishing number of the country that has granted
approval(1).
5.4.2. The number of this Regulation, followed by the letter "R", a dash and the approval number to the right of the circle
described in paragraph 5.4.1.
5.5. If the vehicle conforms to a vehicle type approved, under one or more other Regulations annexed to the 1958
Agreement, in the country which has granted approval under this Regulation, the symbol prescribed in
paragraph 5.4.1. need not be repeated; in such a case, the Regulation, approval numbers and the additional
symbols of all the Regulations under which approval has been granted in the country which has granted approval
under this Regulation shall be placed in vertical columns to the right of the symbol prescribed in paragraph 5.4.1.
(1) The distinguishing numbers of the Contracting Parties to the 1958 Agreement are reproduced in Annex 3 to the Consolidated
Resolution on the Construction of Vehicles (R.E.3), document ECE/TRANS/WP.29/78/Rev.6 – Annex 3, https://unece.org/transport/
standards/transport/vehicle-regulations-wp29/resolutions.
12/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
5.6. The approval mark shall be clearly legible and be indelible.
5.7. The approval mark shall be placed close to or on the vehicle data plate.
5.7.1. Annex 3 to this Regulation gives examples of arrangements of the approval mark.
6. General requirements
6.1. Compliance requirements
For vehicle types approved according to this Regulation, the final emissions at any possible RDE test performed in
accordance with the requirements of this Regulation, shall be calculated for evaluation with a 3-phase and
a 4-phase WLTC.
Requirements for evaluation with 4 Phase WLTC Requirements for evaluation with 3 Phase WLTC
The final emissions for the 4-phase analysis shall not be For vehicles with a diesel engine the final emissions for
higher than any of the limits for the relevant criteria the 3-phase analysis shall not be higher than the NO
X
emissions (i.e. NO and PN) found in Table 1A of limits found in Table 1B of paragraph 6.3.10. of the 03
X
paragraph 6.3.10. of the 03 series of Amendments to series of Amendments to UN Regulation No. 154 on
UN Regulation No. 154 on WLTP. WLTP.
The requirements of emission limits shall be fulfilled for the urban operation and the complete PEMS trip.
The RDE tests required by this Regulation provide a presumption of conformity. The presumed conformity may be
reassessed by additional RDE tests.
The manufacturer shall ensure that all vehicles within the PEMS test family are compliant with UN Regulation No.
154 on WLTP, including conformity of production requirements.
The RDE performance shall be demonstrated by performing the necessary tests in the PEMS test family on the road
operated over their normal driving patterns, conditions and payloads. The necessary tests shall be representative
for vehicles operated on their real driving routes, with their normal load.
6.2. Facilitation of PEMS testing
A Contracting Party shall ensure that vehicles can be tested with PEMS on public roads in accordance with the
procedures under their own national law, while respecting local road traffic legislation and safety requirements.
Manufacturers shall ensure that vehicles can be tested with PEMS. This shall include:
(a) Constructing the exhaust pipes in order to facilitate sampling of the exhaust, or making available suitable
adapters for exhaust pipes for testing by the authorities;
(b) For Contracting Parties applying Regulation 83, 08 Series, in case the exhaust pipe construction does not
facilitate sampling of the exhaust, the manufacturer shall also make available to independent parties, adapters
for purchase or rent via their spare parts or service tools network (e.g. RMI portal), through authorised dealers
or via a contact point on the referred publicly accessible website;
(c) Providing guidance available online, without the need of registration or login, on how to attach a PEMS system
to vehicles approved under this Regulation;
(d) Granting access to ECU signals relevant to this Regulation, as mentioned in Table A4/1 of Annex 4; and
(e) Making the necessary administrative arrangements.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 13/98EN
OJ L, 12.1.2024
6.3. Selection of vehicles for PEMS testing
PEMS tests shall not be required for each ‘vehicle type with regard to emissions’ as defined in UN Regulation No. 154
on WLTP, hereinafter ‘vehicle emission type’. Several vehicle emission types may be put together by the vehicle
manufacturer to form a "PEMS test family" in accordance with the requirements of paragraph 6.3.1., which shall
be validated in accordance with the requirements of paragraph 6.4.
Symbols, parameters and units
N — Number of vehicle emission types
NT — Minimum number of vehicle emission types
PMR — highest power-to-mass-ratio of all vehicles in the PEMS test family
H
PMR — lowest power-to-mass-ratio of all vehicles in the PEMS test family
L
V_eng_max — maximum engine volume of all vehicles within the PEMS test family
6.3.1. PEMS test family building
A PEMS test family shall comprise finished vehicles of a manufacturer with similar emission characteristics.
Vehicle emission types may be included in a PEMS test family only as long as the vehicles within a PEMS test
family are identical with respect to the characteristics in all the administrative and technical criteria listed below.
6.3.1.1. Administrative criteria
(a) The approval authority issuing the emission type approval in accordance with this Regulation ("authority")
(b) The manufacturer having received the emission type approval in accordance with this Regulation
("manufacturer").
6.3.1.2. Technical criteria
(a) Propulsion type (e.g. ICE, NOVC-HEV, OVC-HEV)
(b) Type(s) of fuel(s) (e.g. petrol, diesel, LPG, NG, …). Bi- or flex-fuelled vehicles may be grouped with other
vehicles, with which they have one of the fuels in common.
(c) Combustion process (e.g. two stroke, four stroke)
(d) Number of cylinders
(e) Configuration of the cylinder block (e.g. in-line, V, radial, horizontally opposed, …)
(f) Engine volume
The vehicle manufacturer shall specify a value V_eng_max (= maximum engine volume of all vehicles within
the PEMS test family). The engine volumes of vehicles in the PEMS test family shall not deviate more than –
22 per cent from V_eng_max if V_eng_max ≥ 1 500ccm and – 32 per cent from V_eng_max if V_eng_max <
1 500ccm.
(g) Method of engine fuelling (e.g. indirect or direct or combined injection)
(h) Type of cooling system (e.g. air, water, oil)
(i) Method of aspiration such as naturally aspirated, pressure charged, type of pressure charger (e.g. externally
driven, single or multiple turbo, variable geometries …)
(j) Types and sequence of exhaust after-treatment components (e.g. three-way catalyst, oxidation catalyst, lean
NO trap, SCR, lean NO catalyst, particulate trap)
X X
(k) Exhaust gas recirculation (with or without, internal/external, cooled/non-cooled, low/high pressure)
14/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
6.3.2. Alternative PEMS test family definition
As an alternative to the provisions of paragraph 6.3.1. the vehicle manufacturer may define a PEMS test family
that is identical to a single vehicle emission type or a single WLTP IP-family. In this case, only one vehicle has to
be tested from the family in either a hot or a cold test, at the choice of the authority and there is no need to
validate the PEMS test family as in paragraph 6.4.
6.4. Validation of a PEMS test family
6.4.1. General requirements for validating a PEMS test family
6.4.1.1. The vehicle manufacturer shall present a representative vehicle of the PEMS test family to the authority. The
vehicle shall be subject to a PEMS test carried out by a Technical Service to demonstrate compliance of the
representative vehicle with the requirements of this Regulation.
6.4.1.2. The authority shall select additional vehicles according to the requirements of paragraph 6.4.3. for PEMS testing
carried out by a Technical Service to demonstrate compliance of the selected vehicles with the requirements of
this Regulation. The technical criteria for selection of an additional vehicle according to paragraph 6.4.2. shall be
recorded with the test results.
6.4.1.3. With agreement of the authority, a PEMS test can also be driven by a different operator witnessed by a Technical
Service, provided that at least the tests of the vehicles required by paragraphs 6.4.2.2. and 6.4.2.6. and in total at
least 50 per cent of the PEMS tests required by paragraph 6.4.3.7. for validating the PEMS test family are driven
by a Technical Service. In such case the Technical Service remains responsible for the proper execution of all
PEMS tests pursuant to the requirements of this Regulation.
6.4.1.4. A PEMS test results of a specific vehicle may be used for validating different PEMS test families under the following
conditions:
(a) The vehicles included in all PEMS test families to be validated are approved by a single authority according to
this Regulation and this authority agrees to the use of the specific vehicle's PEMS test results for validating
different PEMS test families;
(b) Each PEMS test family to be validated includes a vehicle emission type, which comprises the specific vehicle.
6.4.2. For each validation, the applicable responsibilities are considered to be borne by the manufacturer of the vehicles
in the respective family, regardless of whether this manufacturer was involved in the PEMS test of the specific
vehicle emission type.
6.4.3. Selection of vehicles for PEMS testing when validating a PEMS test family
When selecting vehicles from a PEMS test family, it shall be ensured that the following technical characteristics
relevant for criteria emissions are covered by a PEMS test. A particular vehicle selected for testing can be
representative for different technical characteristics. For the validation of a PEMS test family vehicles shall be
selected for PEMS testing as follows:
6.4.3.1. For each combination of fuels (e.g. petrol-LPG, petrol-NG, petrol only), on which some vehicles of the PEMS test
family can operate, at least one vehicle that can operate on such combination of fuels shall be selected for PEMS
testing.
6.4.3.2. The manufacturer shall specify a value PMR (= highest power-to- mass-ratio of all vehicles in the PEMS test
H
family) and a value PMR (= lowest power-to-mass-ratio of all vehicles in the PEMS test family). At least one
L
vehicle configuration representative for the specified PMR and one vehicle configuration representative for the
H
specified PMR of a PEMS test family shall be selected for testing. The power-to-mass ratio of a vehicle shall not
L
deviate by more than 5 per cent from the specified value for PMR , or PMR for the vehicle to be considered as
H L
representative for this value.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 15/98EN
OJ L, 12.1.2024
6.4.3.3. At least one vehicle for each transmission type (e.g., manual, automatic, DCT) installed in vehicles of the PEMS test
family shall be selected for testing.
6.4.3.4. At least one vehicle per each configuration of driven axles shall be selected for testing if such vehicles are part of
the PEMS test family.
6.4.3.5. For each engine volume associated with a vehicle in the PEMS test family at least one representative vehicle shall be
tested.
6.4.3.6. At least one vehicle in the PEMS test family shall be tested in hot start testing.
6.4.3.7. Notwithstanding the provisions in paragraphs 6.4.3.1. to 6.4.3.6., at least the following number of vehicle
emission types of a given PEMS test family shall be selected for testing:
Minimum number of vehicle emission
Number of vehicle emission types in a Minimum number of vehicle emission
types selected for PEMS cold start
PEMS test family (N) types selected for PEMS hot start testing
testing (NT)
1 1 1(2)
From 2 to 4 2 1
from 5 to 7 3 1
from 8 to 10 4 1
from 11 to 49 NT = 3 + 0,1 × N(1) 2
more than 49 NT = 0,15 × N(1) 3
(1) NT shall be rounded to the next higher integer number
(2) When there is only one vehicle emission type in a PEMS test family, the type approval authority shall decide whether the
vehicle shall be tested in hot or cold start.
6.5. Reporting for type approval
6.5.1. The vehicle manufacturer shall provide a full description of the PEMS test family, which shall include the technical
criteria described in paragraph 6.3.1.2. and submit it to the authority.
6.5.2. The manufacturer attributes a unique identification number of the format PF-CP-nnnnnnnnn…-WMI to the PEMS
test family and communicates it to the authority:
where:
PF denotes that this is a PEMS test Family
CP is the Contracting Party issuing the type approval according to this Regulation(2)
nnnnnnnnn… is a string with a maximum of twenty five characters, restricted to using the
characters 0-9, A-Z and the underscore character '_'.
WMI (world manufacturer is a code that identifies the manufacturer in a unique manner defined in
identifier) ISO 3780:2009.
(2) The distinguishing numbers of the Contracting Parties to the 1958 Agreement are reproduced in Annex 3 to the Consolidated
Resolution on the Construction of Vehicles (R.E.3), document ECE/TRANS/WP.29/78/Rev.6 – Annex 3, https://unece.org/transport/
standards/transport/vehicle-regulations-wp29/resolutions.
16/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
It is the responsibility of the owner of the WMI to ensure that the combination of the string nnnnnnnnn… and the
WMI is unique to the family and that the string nnnnnnnnn… is unique within that WMI to the approval tests
performed to obtain the approval.
6.5.3. The granting approval authority and the vehicle manufacturer shall maintain a list of vehicle emission types being
part of a given PEMS test family on the basis of emission type approval numbers.
6.5.4. The granting approval authority and the vehicle manufacturer shall maintain a list of vehicle emission types
selected for PEMS testing in order to validate a PEMS test family in accordance with paragraph 6.4., which also
provides the necessary information on how the selection criteria of paragraph 6.4.3 are covered. This list shall
also indicate whether the provisions of paragraph 6.4.1.3. were applied for a particular PEMS test.
6.6. Rounding requirements:
Rounding of data in the data exchange file, as defined in paragraph 10. of Annex 7, is not permitted. In the pre-
processing file, the data may be rounded to the same order of magnitude of the accuracy of the measurement of a
respective parameter.
The intermediate and final emission test results, as calculated in Annex 11, shall be rounded in one step to the
number of places to the right of the decimal point indicated by the applicable emission standard plus one
additional significant figure. Preceding steps in the calculations shall not be rounded.
7. Performance requirements for instrumentation
The instrumentation used for RDE tests shall comply with the requirements as defined in Annex 5. If requested by
the authorities, the tester shall provide proof that the instrumentation used complies with the requirements in
Annex 5.
8. Test conditions
Only an RDE test fulfilling the requirements of this Section shall be accepted as valid. Tests performed outside the
test conditions specified in this Section shall be considered as invalid, unless specified otherwise.
8.1. Ambient conditions
The test shall be conducted under the ambient conditions laid down in this section. The ambient conditions
become ‘extended’ when at least one of the temperature or altitude conditions is extended. The factor for
extended conditions as defined in paragraph 10.5. shall only be applied once even if both conditions are extended
in the same time period. Notwithstanding the opening paragraph of this section, if a part of the test or the entire
test is performed outside of extended conditions, the test shall be invalid only when final emissions as calculated
in Annex 11, are greater than the applicable emission limits. The conditions are as follows:
Moderate altitude conditions Altitude lower or equal to 700 meters above sea level.
Extended altitude conditions Altitude higher than 700 meters above sea level and lower or equal to
1 300meters above sea level.
Moderate temperature conditions Greater than or equal to 273,15 K (0 °C) and lower than or equal to
308,15 K (35 °C).
Extended temperature conditions Greater than or equal to 266,15 K (– 7 °C) and lower than 273,15 K (0 °C) or
greater than 308,15 K (35 °C) and lower than or equal to 311,15 K (38 °C).
ELI: http://data.europa.eu/eli/reg/2024/211/oj 17/98EN
OJ L, 12.1.2024
8.2. Dynamic conditions of trip
The dynamic conditions encompass the effect of road grade, head wind and driving dynamics (accelerations,
decelerations) and auxiliary systems upon energy consumption and emissions of the test vehicle. The validity of
the trip for the dynamic conditions shall be checked after the test is completed, using the recorded data. This
verification shall be conducted in 2 steps:
— STEP i: The excess or insufficiency of driving dynamics during the trip shall be checked using the methods
described in Annex 9.
— STEP ii: If the trip is valid following the verifications in accordance with STEP i, the methods for verifying the
validity of the trip as laid down in Annexes 8 and 10 shall be applied.
8.3. Vehicle condition and operation
8.3.1. Vehicle condition
The vehicle, including the emission related components, shall be in good mechanical condition and shall have
been run in and driven at least 3 000 km before the test. The mileage and the age of the vehicle used for RDE
testing shall be recorded.
All vehicles, and in particular OVC-HEVs vehicles may be tested in any selectable mode, including battery charge
mode. On the basis of technical evidence provided by the manufacturer and with the agreement of the
responsible authority, the dedicated driver-selectable modes for very special limited purposes shall not be
considered (e.g. maintenance mode, race driving, crawler mode). All remaining modes used for forward and for
rearwards driving where road and traffic conditions demand this may be considered and the criteria emissions
limits shall be fulfilled in all these modes.
Modifications that affect the vehicle aerodynamics are not permitted, with the exception of the PEMS installation.
The tyre types and pressure shall be according to the vehicle's manufacturer recommendations. The tyre pressure
shall be checked prior to the pre-conditioning and adjusted to the recommended values if needed. Driving the
vehicle with snow chains is not permitted.
Vehicles should not be tested with an empty starter battery. In case the vehicle has problems starting, the battery
shall be replaced following the recommendations of the vehicle's manufacturer.
The vehicle's test mass comprises of the driver, a witness of the test (if applicable), the test equipment, including
the mounting and the power supply devices and any artificial payload. It shall be between the actual mass of the
vehicle and the maximum permissible test mass of the vehicle at the beginning of the test and shall not increase
during the test.
The test vehicles shall not be driven with the intention to generate a passed or failed test due to extreme driving
that do not represent normal conditions of use. If necessary, verification of normal driving may be based on
expert judgement made by or on behalf of the granting type approval authority through cross-correlation on
several signals, which may include exhaust flow rate, exhaust temperature, CO , O etc. in combination with
2 2
vehicle speed, acceleration and GNSS data and potentially further vehicle data parameters like engine speed, gear,
accelerator pedal position etc.
8.3.2. Vehicle conditioning for cold start PEMS trip
Before RDE testing, the vehicle shall be preconditioned in the following way:
The vehicle shall be driven, preferably on the same route as the planned RDE testing, or for at least 10 min per
type of operation (e.g. urban, rural, motorway) or 30 minutes with a minimum average speed of 30 km/h. The
validation test in the laboratory, as in paragraph 8.4., also counts as preconditioning. The vehicle shall
subsequently be parked with doors and bonnet closed and kept in engine-off status within moderate or extended
altitude and temperatures, in accordance with paragraph 8.1., for between 6 and 72 hours. Exposure to extreme
atmospheric conditions (such as heavy snowfall, storm, hail) and excessive amounts of dust or smoke should be
avoided.
18/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
Before the test start, the vehicle and equipment shall be checked for damages and the presence of warning signals
that may suggest malfunctioning. In the case of a malfunction the source of the malfunctioning shall be identified
and corrected or the vehicle shall be rejected.
8.3.3. Auxiliary devices
The air conditioning system or other auxiliary devices shall be operated in a way which corresponds to their
typically intended use during real driving on the road. Any use shall be documented. The vehicle windows shall
be closed when the air conditioning or heating are used.
8.3.4. Vehicles equipped with periodically regenerating systems
8.3.4.1. All results shall be corrected with the K factors or with the K offsets developed by the procedures in Appendix 1
i i
to Annex B6 of UN Regulation No. 154 on WLTP for type-approval of a vehicle type with a periodically
regenerating system. The K factor or the K offset shall be applied to the final results after evaluation in
i i
accordance with Annex 11.
8.3.4.2. If the final emissions as calculated in Annex 11 are above the applicable emission limits, then the occurrence of
regeneration shall be verified. The verification of a regeneration may be based on expert judgement through
cross-correlation of several of the following signals, which may include exhaust temperature, PN, CO O
2, 2
measurements in combination with vehicle speed and acceleration. If the vehicle has a regeneration recognition
feature, it shall be used to determine the occurrence of regeneration. The manufacturer may advise how to
recognise whether regeneration has taken place in case such a signal is not available.
8.3.4.3. If regeneration occurred during the test, the final emission result without the application of either the K -factor or
i
the K offset shall be checked against applicable emission limits. If the final emissions are above the emission
i
limits, then the test shall be invalid and repeated once. The completion of the regeneration and stabilisation,
through approximately 1 hour of driving, shall be done prior to the start of the second test. The second test is
considered valid even if regeneration occurs during it.
Even if the final emission results fall below the applicable emission limits, the occurrence of regeneration may be
verified as in paragraph 8.3.4.2. If the presence of regeneration can be proved and with the agreement of the
Type Approval Authority, the final results shall be calculated without the application of either the K factor or the
i
Ki offset.
8.4. PEMS operational requirements
The trip shall be selected in such a way that the testing is uninterrupted and the data continuously recorded to
reach the minimum test duration defined in paragraph 9.3.3.
Electrical power shall be supplied to the PEMS by an external power supply unit and not from a source that draws
its energy either directly or indirectly from the engine of the test vehicle.
The installation of the PEMS equipment shall be done in a way to minimise the influence on the vehicle’s
emissions or performance or both to the greatest extent possible. Care should be exercised to minimise the mass
of the installed equipment and potential aerodynamic modifications of the test vehicle.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 19/98EN
OJ L, 12.1.2024
During type approval, a validation test in the laboratory shall be performed before running an RDE test according
to Annex 6. For OVC-HEV the applicable WLTP test shall be conducted in Charge Sustaining vehicle operation.
8.5. Lubricating oil, fuel and reagent
For the test performed during type approval, the fuel used for RDE testing shall be either the reference fuel defined
in Annex B3 of UN Regulation No. 154 on WLTP or within the specifications issued by the manufacturer for
vehicle operation by the customer. The reagent (where applicable) and lubricant used shall be within the
specifications recommended or issued by the manufacturer.
9. Test procedure
9.1. Types of speed bins
Urban speed bin (for both 3-phase and 4-phase analysis) is characterised by vehicle speeds lower than or equal to
60 km/h.
Rural speed bin (for 4-phase analysis) is characterised by vehicle speeds higher than 60 km/h and lower than or
equal to 90 km/h. For those vehicles that are equipped with a device permanently limiting vehicle speed to
90 km/h, rural speed bin is characterised by vehicle speed higher than 60 km/h and lower than or equal to
80 km/h.
Motorway speed bin (for 4-phase analysis) is characterised by speeds above 90 km/h.
For those vehicles that are equipped with a device permanently limiting vehicle speed to 100 km/h, the motorway
speed bin is characterised by a speed higher than 90 km/h.
For those vehicles that are equipped with a device permanently limiting vehicle speed to 90 km/h, the motorway
speed bin is characterised by a speed higher than 80 km/h.
Expressway speed bin (for 3-phase analysis) is characterised by speeds above 60 km/h and up to 100 km/h.
A complete trip for 4-phase analysis consists of urban, rural and motorway bins whereby a complete trip for
3-phase analysis consists of urban and expressway bins.
9.1.1. Other requirements
The average speed (including stops) of the urban speed bin shall be between 15 and 40 km/h.
The speed range of the motorway driving shall properly cover a range between 90 and at least 110 km/h. The
vehicle’s speed shall be above 100 km/h for at least 5 minutes.
For M category vehicles that are equipped with a device permanently limiting vehicle speed to 100 km/h, the
2
speed range of the motorway speed bin shall properly cover a range between 90 and 100 km/h. The vehicle’s
speed shall be above 90 km/h for at least 5 minutes.
For those vehicles that are equipped with a device limiting vehicle speed to 90 km/h, the speed range of the
motorway speed bin shall properly cover a range between 80 and 90 km/h. The vehicle’s speed shall be above
80 km/h for at least 5 minutes.
In the case that the local speed limits for the specific vehicle being tested prevent compliance with the
requirements of this paragraph, the requirements of the following paragraph shall apply:
The speed range of the motorway driving shall properly cover a range between X – 10 and X km/h. The vehicle’s
speed shall be above X - 10 km/h for at least 5 minutes. Where X = the local speed limit for the tested vehicle.
9.2. Required distance shares of trip speed bins
The following is the distribution of the speed bins in an RDE trip that are required for respecting the needs of
evaluation for both the 4-phase WLTC and 3-phase WLTC:
20/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
Requirements for evaluation with 4-Phase WLTC Requirements for evaluation with 3-Phase WLTC
The trip shall consist of approximately 34 per cent The trip shall consist of approximately 55 per cent urban
urban, 33 per cent rural and 33 per cent motorway and 45 per cent expressway speed bins. ‘Approximately’
speed bins. ‘Approximately’ shall mean the interval of shall mean the interval of ±10 per cent points around the
±10 per cent points around the stated percentages. stated percentages. The urban speed bin however can be
The urban speed bin shall however never be less lower than 45 per cent but never be less than 40 per cent
than 29 per cent of the total trip distance. of the total trip distance.
The shares of urban, rural and motorway speed bins shall be expressed as a percentage of the total trip distance for
analysis with 4-Phase WLTC.
The shares of urban and expressway speed bins shall be expressed as a percentage of the trip distance with speed
not exceeding 100km/h for analysis with 3-Phase WLTC.
The minimum distance of each, urban, rural and motorway or expressway speed bins shall be 16 km.
9.3. RDE test to be performed
The RDE performance shall be demonstrated by testing vehicles on the road, operated over their normal driving
patterns, conditions and payloads. RDE tests shall be conducted on paved roads (e.g. off-road operation is not
permitted). Either a single RDE trip or two dedicated RDE trips shall be driven in order to prove compliance with
the emission requirements against both 3-Phase WLTC and 4-Phase WLTC.
9.3.1. The design of the trip shall be such as to comprise driving that would in principle cover all of the required shares
of speed bins in paragraph 9.2 and comply with all other requirements described in paragraphs 9.1.1. and 9.3,
paragraphs 4.5.1. and 4.5.2. of Annex 8 and paragraph 4. of Annex 9.
9.3.2. The planned RDE trip shall always start with urban operation followed by rural, then motorway or expressway
operation, in accordance with the required shares for speed bins in paragraph 9.2. The urban, rural
and motorway/expressway operation shall be run consecutively, but may also include a trip which starts and ends
at the same point. Rural operation may be interrupted by short periods of urban speed bin when driving through
urban areas. Motorway/expressway operation may be interrupted by short periods of urban or rural speed bins,
e.g., when passing toll stations or sections of road work.
9.3.3. The vehicle speed shall normally not exceed 145 km/h. This maximum speed may be exceeded by a tolerance of
15 km/h for not more than 3 per cent of the time duration of the motorway operation. Local speed limits remain
in force during a PEMS test, notwithstanding other legal consequences. Violations of local speed limits per se do
not invalidate the results of a PEMS test.
Stop periods, defined by vehicle speed of less than 1 km/h, shall account for 6-30 per cent of the time duration of
urban operation. Urban operation may contain several stop periods of 10 s or longer. If stop periods in urban
driving part are over 30 per cent or there are individual stop periods exceeding 300 consecutive seconds, the test
shall be invalid only if the emission limits are not met.
The trip duration shall be between 90 and 120 minutes.
The start and the end points of a trip shall not differ in their elevation above sea level by more than 100 m. In
addition, the proportional cumulative positive altitude gain over the entire trip and over the urban operation
shall be less than 1 200m/100 km and be determined in accordance with Annex 10.
9.3.4. The average speed (including stops) during cold start period shall be between 15 and 40 km/h. The maximum
speed during the cold start period shall not exceed 60 km/h.
At the test start, the vehicle shall move within 15 seconds. The vehicle stop periods during the entire cold start
period, as defined in paragraph 3.6.1., shall be kept to the minimum possible and it shall not exceed 90 s in total.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 21/98EN
OJ L, 12.1.2024
9.4. Other trip requirements
If the engine stalls during the test, it may be restarted, but the sampling and data recording shall not be
interrupted. If the engine stops during the test, the sampling and data recording shall not be interrupted.
In general the exhaust mass flow shall be determined by measurement equipment functioning independently from
the vehicle. With agreement of the approval authority, vehicle ECU data may be used in this respect during type
approval.
If the approval authority is not satisfied with the data quality check and validation results of a PEMS test conducted
in accordance with Annex 4, the approval authority may consider the test to be invalid. In such case, the test data
and the reasons for invalidating the test shall be recorded by the approval authority.
The manufacturer shall demonstrate to the approval authority that the chosen vehicle, driving patterns, conditions
and payloads are representative of the PEMS test family. The ambient conditions and payload requirements, as
specified in paragraph 8.1. and paragraph 8.3.1. respectively, shall be used ex-ante to determine whether the
conditions are acceptable for RDE testing.
The approval authority shall propose a test trip in urban, rural and motorway/expressway operation meeting the
requirements of paragraph 9.2. If applicable, for the purpose of trip design, the urban, rural and motorway/ex
pressway parts shall be selected based on a topographic map.
If for a vehicle the collection of ECU data influences the vehicle's emissions or performance, the entire PEMS test
family to which the vehicle belongs shall be considered as non-compliant.
For RDE tests performed during type approval, the type approval authority may verify if the test setup and the
equipment used fulfil the requirements of Annexes 4 and 5 through a direct inspection or an analysis of the
supporting evidence (e.g. photographs, records).
9.5. Compliance of software tools
Any software tool used to verify the trip validity and calculate emissions compliance with the provisions laid
down in paragraphs 8 and 9 and Annexes 8, 9 10 and 11 shall be validated by an entity defined by the
Contracting Party. Where such software tool is incorporated in the PEMS instrument, proof of the validation shall
be provided along with the instrument.
10. Test data analysis
10.1. Emissions and trip evaluation
The test shall be conducted in accordance with Annex 4.
10.2. The trip validity shall be assessed in a three-step procedure as follows:
STEP A: The trip complies with the general requirements, boundary conditions, trip and operational requirements,
and the specifications for lubricating oil, fuel and reagents set out in paragraphs 8 and 9 and Annex 10.
STEP B: The trip complies with the requirements set out in Annex 9.
STEP C: The trip complies with the requirements set out in Annex 8.
The steps of the procedure are detailed in Figure 6.
If at least one of the requirements is not fulfilled, the trip shall be declared invalid.
22/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojELI:
http://data.europa.eu/eli/reg/2024/211/oj
23/98
Figure 6
Assessment of trip validity – schematic
(i.e. not all details are included in the steps included in the figure, see the relevant annexes for such details)
OJ
L,
12.1.2024
ENEN
OJ L, 12.1.2024
10.3. In order to preserve data integrity, it shall not be permitted to combine data of different RDE trips in a single data
set or to modify or remove data from an RDE trip, except for cases mentioned explicitly in this Regulation.
10.4. Emission results shall be calculated using the methods laid down in Annex 7 and Annex 11. The emissions
calculations shall be made between test start and test end.
10.5. The extended factor for this Regulation is set at 1.6. If during a particular time interval the ambient conditions are
extended, in accordance with paragraph 8.1., then the criteria emissions calculated according to Annex 11, during
that particular time interval, shall be divided by the extended factor. This provision does not apply to carbon
dioxide emissions.
10.6. Gaseous pollutant and particle number emissions during the cold start period, as defined in paragraph 3.6.1., shall
be included in the normal evaluation in accordance with Annexes 7, 8 and 11.
If the vehicle was conditioned for the last three hours prior to the test at an average temperature that falls within
the extended range in accordance with paragraph 8.1., then the provisions of paragraph 10.5. apply to the data
collected during the cold start period, even if the test ambient conditions are not within the extended temperature
range.
10.7. Where applicable, separate data-sets shall be created for 3-phase and 4-phase evaluation. The data collected during
the entire trip shall be the basis of the 4-phase RDE emission results, while the data with the exclusion of any data
point with speed above 100 km/h shall be the basis of the 3-phase RDE trip validity and emission results
calculations according to paragraphs 8 and 9 and Annexes 8, 9 and 11. For data analysis continuity Annex 10
will begin with the entire data set for both analyses.
10.7.1. In the case that a single RDE trip is not capable of complying with all validity requirements described in
paragraphs 9.1.1., 9.2. and 9.3., paragraphs 4.5.1. and 4.5.2. of Annex 8 and paragraph 4. of Annex 9
simultaneously, then a second RDE trip shall be done. The second trip shall be designed to meet either the
3-phase or 4-phase WLTC trip requirements not yet satisfied, as well as all other relevant trip validity
requirements, but it is not necessary to satisfy again the 4-phase or 3-phase WLTC trip requirements previously
met by the first trip.
10.7.2. In case the emission calculated for the 3-phase RDE trip exceed the emission limits for the total trip due to the
exclusion of all data points with speed above 100 km/h even though the trip is compliant, then a second trip
with the speed limited to less than or equal to 100 km/h shall be made and evaluated for compliance with the
3-phase requirements.
10.8. Data Reporting: All data of a single RDE test shall be recorded according to the data reporting files found in the
same weblink as this Regulation(3).
A test report shall be prepared by the Technical Service in accordance with the Data Reporting File and shall be
made available to the Contracting Party.
11. Modifications and extensions to type approval
11.1. Every modification of a vehicle emission type shall be notified to the Type Approval Authority that approved the
vehicle type. The Type Approval Authority may then either:
11.1.1. Consider that the modifications made are contained within the families covered by the approval or are unlikely to
have an appreciable adverse effect on the values of any of the criteria emissions and that, in this case, the original
approval will be valid for the modified vehicle type; or
11.1.2. Require a further test report from the Technical Service responsible for conducting the tests.
(3) [link to be inserted after the final notification]
24/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
11.2. Confirmation or refusal of approval, specifying the alterations, shall be communicated by the procedure specified
in paragraph 5.3. to the Contracting Parties to the Agreement which apply this Regulation.
11.3. The Type Approval Authority issuing the extension of approval shall assign a series number to the extension and
inform thereof the other Contracting Parties to the 1958 Agreement applying this Regulation by means of a
communication form conforming to the model in Annex 2 to this Regulation.
11.4. Extension of a PEMS test family
An existing PEMS test family may be extended by adding new vehicle emission types to it. The extended PEMS test
family and its validation must also fulfil the requirements of paragraphs 6.3. and 6.4. This may require the PEMS
testing of additional vehicles to validate the extended PEMS test family according to paragraph 6.4.
12. Conformity of production
12.1. The conformity of production requirements relating to light duty vehicle emissions are already covered by the
rules specified in paragraph 8 of UN Regulation No. 154 on WLTP and therefore compliance with the conformity
of production requirements of UN Regulation No. 154 can be considered as sufficient to cover the conformity of
production requirements for vehicles type approved under this Regulation.
12.2. In addition to the provisions in paragraph 12.1. the manufacturer shall ensure that all vehicles within the PEMS
test family are compliant with the Type 1 conformity of production requirements of UN Regulation No. 154 on
WLTP.
13. Penalties for non-conformity of production
13.1. The approval granted in respect of a vehicle type pursuant to this Regulation, may be withdrawn if the
requirements of this Regulation are not complied with.
13.2. If a Contracting Party to the 1958 Agreement which applies this Regulation withdraws an approval it has
previously granted, it shall forthwith so notify the other Contracting Parties applying this Regulation, by means
of a communication form conforming to the model in Annex 2 to this Regulation.
14. Production definitively discontinued
14.1. If the holder of the approval completely ceases to manufacture a type of vehicle approved in accordance with this
Regulation, they shall so inform the Type Approval Authority which granted the approval. Upon receiving the
relevant communication, that authority shall inform thereof the other Contracting Parties to the 1958
Agreement applying this Regulation by means of copies of the communication form conforming to the model in
Annex 2 to this Regulation.
15. Transitional provisions
15.1. As from the official date of entry into force of the 00 series of amendments to this Regulation, and by way of
derogation to the obligations of Contracting Parties, the Contracting Parties applying this Regulation and also
applying the 08 or a later series of amendments to UN Regulation No. 83 may refuse to accept type approvals
granted on the basis of this Regulation which are not accompanied by an approval to the 08 or a later series of
amendments to UN Regulation No. 83.
16. Names and addresses of the Technical Services responsible for conducting approval tests and of Type Approval
Authorities
ELI: http://data.europa.eu/eli/reg/2024/211/oj 25/98EN
OJ L, 12.1.2024
16.1. The Contracting Parties to the 1958 Agreement which apply this Regulation shall communicate to the United
Nations Secretariat the names and addresses of the Technical Services responsible for conducting approval tests
and of the Type Approval Authorities which grant approval and to which forms certifying approval or extension
or refusal or withdrawal of approval, issued in other countries, are to be sent.
26/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
ANNEX 1
Engine and vehicle characteristics and information concerning the conduct of tests
The authority and the vehicle manufacturer shall maintain a list of vehicle emission types as defined in UN Regulation No.
154 on WLTP being part of a given PEMS test family on the basis of emission type approval numbers or equivalent
information. For each emission type all corresponding combinations of vehicle type approval numbers or equivalent
information, types, variants and versions shall be provided as well.
The authority and the vehicle manufacturer shall maintain a list of vehicle emission types selected for PEMS testing in order
validate a PEMS test family in accordance with paragraph 6.4., of this Regulation which shall provide the necessary
information on how the selection criteria of paragraph 6.4.3. of this Regulation are covered. This list shall also indicate
whether the provisions of paragraph 6.4.1.3. of this Regulation were applied for a particular PEMS test.
The following information, when applicable, shall be supplied in triplicate and include a list of contents.
If there are drawings, they shall be to an appropriate scale and show sufficient detail; they shall be presented in A4 format or
folded to that format. Photographs, if any, shall show sufficient detail.
If the systems, components or separate technical units have electronic controls, information concerning their performance
shall be supplied.
Part 1 In the case that all vehicles included in the approval to this Regulation are also approved to UN Regulation No.
154 :
Approval number(s) to UN Regulation No. 154 : …..
0 GENERAL
0.1. Make (trade name of manufacturer): …
0.2. Type: …
0.2.1. Commercial name(s) (if available): …
0.2.2.1. Allowed Parameter Values for multistage type approval (if applicable) to use the base vehicle emission
values (insert range if applicable):
Final Vehicle mass in running order (in kg):
Frontal area for final vehicle (in cm2):
Rolling resistance (kg/t):
Cross-sectional area of air entrance of the front grille (in cm2):
0.2.3. Family identifiers:
0.2.3.1. Interpolation family(s): …
0.2.3.3. PEMS family identifier:
2. MASSES AND DIMENSIONS (f) (g) (7)
(in kg and mm) (Refer to drawing where applicable)
2.6. Mass in running order (h)
(a) maximum and minimum for each variant: …
3. PROPULSION ENERGY CONVERTER (k)
3.1. Manufacturer of the propulsion energy converter(s): …
3.1.1. Manufacturer's code (as marked on the propulsion energy converter or other means of identification):
…
3.2. Internal combustion engine
ELI: http://data.europa.eu/eli/reg/2024/211/oj 27/98EN
OJ L, 12.1.2024
3.2.1.1. Working principle: positive ignition/compression ignition/dual fuel (1)
Cycle: four stroke/two stroke/rotary (1)
3.2.1.2. Number and arrangement of cylinders: …
3.2.1.3. Engine capacity (m): … cm3
3.2.2. Fuel
3.2.2.1. Diesel/Petrol/LPG/NG or Biomethane/Ethanol (E 85)/Biodiesel/Hydrogen (1),
3.2.2.4. Vehicle fuel type: Mono fuel, Bi fuel, Flex fuel (1)
3.2.4. Fuel feed
3.2.4.1. By carburettor(s): yes/no (1)
3.2.4.2. By fuel injection (compression ignition or dual fuel only): yes/no (1)
3.2.4.2.1. System description (common rail/unit injectors/distribution pump etc.): …
3.2.4.2.2. Working principle: direct injection/pre-chamber/swirl chamber (1)
3.2.4.3. By fuel injection (positive ignition only): yes/no (1)
3.2.4.3.1. Working principle: intake manifold (single-/multi-point/direct injection (1) /other (specify): …
3.2.7. Cooling system: liquid/air (1)
3.2.8.1. Pressure charger: yes/no (1)
3.2.8.1.2. Type(s): …
3.2.9. Exhaust system
3.2.9.2. Description and/or drawing of the exhaust system: …
3.2.12. Measures taken against air pollution
3.2.12.1. Device for recycling crankcase gases (description and drawings): …
3.2.12.2. Pollution control devices (if not covered by another heading)
3.2.12.2.1. Catalytic converter
3.2.12.2.1.1. Number of catalytic converters and elements (provide the information below for each separate unit): …
3.2.12.2.1.2. Dimensions, shape and volume of the catalytic converter(s): …
3.2.12.2.1.3. Type of catalytic action: …
3.2.12.2.1.9. Location of the catalytic converter(s) (place and reference distance in the exhaust line): …
3.2.12.2.4. Exhaust gas recirculation (EGR): yes/no (1)
3.2.12.2.4.1. Characteristics (make, type, flow, high pressure/low pressure/combined pressure, etc.): …
3.2.12.2.4.2. Water-cooled system (to be specified for each EGR system e.g. low pressure/high pressure/combined
pressure: yes/no (1)
3.2.12.2.6. Particulate trap (PT): yes/no (1)
3.2.12.2.11. Catalytic converter systems using consumable reagents (provide the information below for each
separate unit) yes/no (1)
3.4. Combinations of propulsion energy converters
3.4.1. Hybrid electric vehicle: yes/no (1)
3.4.2. Category of hybrid electric vehicle: off-vehicle charging/not off-vehicle charging: (1)
28/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
Part 2 In the case that any vehicles included in the approval to this Regulation are not approved according to UN
Regulation No.154:
0 GENERAL
0.1. Make (trade name of manufacturer): …
0.2. Type: …
0.2.1. Commercial name(s) (if available): …
0.2.2.1. Allowed Parameter Values for multistage type approval (if applicable) to use the base vehicle
emission values (insert range if applicable):
Final Vehicle mass in running order (in kg):
Frontal area for final vehicle (in cm2):
Rolling resistance (kg/t):
Cross-sectional area of air entrance of the front grille (in cm2):
0.2.3. Family identifiers:
0.2.3.1. Interpolation family: …
0.2.3.3. PEMS family identifier:
0.2.3.6. Periodic regeneration family(s): …
0.2.3.10. ER family(s): …
0.2.3.11. Gas Fuelled Vehicle family(s): …
0.2.3.12. other family(s): …
0.4. Category of vehicle (c): …
0.8. Name(s) and address(es) of assembly plant(s): …
0.9. Name and address of the manufacturer's representative (if any): …
1. GENERAL CONSTRUCTION CHARACTERISTICS
1.1. Photographs and/or drawings of a representative vehicle/component/separate technical unit (1):
1.3.3. Powered axles (number, position, interconnection): …
2. MASSES AND DIMENSIONS (f) (g) (7)
(in kg and mm) (Refer to drawing where applicable)
2.6. Mass in running order (h)
(a) maximum and minimum for each variant: …
2.6.3. Rotational mass: 3 % of the sum of mass in running order and 25 kg or value, per axle (kg): …
2.8. Technically permissible maximum laden mass stated by the manufacturer (i) (3): …
3. PROPULSION ENERGY CONVERTER (k)
3.1. Manufacturer of the propulsion energy converter(s): …
3.1.1. Manufacturer's code (as marked on the propulsion energy converter or other means of
identification): …
3.2. Internal combustion engine
3.2.1.1. Working principle: positive ignition/compression ignition/dual fuel (1)
Cycle: four stroke/two stroke/rotary (1)
3.2.1.2. Number and arrangement of cylinders: …
ELI: http://data.europa.eu/eli/reg/2024/211/oj 29/98EN
OJ L, 12.1.2024
3.2.1.2.1. Bore (1): … mm
3.2.1.2.2. Stroke (1): … mm
3.2.1.2.3. Firing order: …
3.2.1.3. Engine capacity (m): … cm3
3.2.1.4. Volumetric compression ratio (2): …
3.2.1.5. Drawings of combustion chamber, piston crown and, in the case of positive ignition engines,
piston rings: …
3.2.1.6. Normal engine idling speed (2): … min–1
3.2.1.6.1. High engine idling speed (2): … min–1
3.2.1.8. Rated engine power (n): … kW at … min–1 (manufacturer's declared value)
3.2.1.9. Maximum permitted engine speed as prescribed by the manufacturer: … min–1
3.2.1.10. Maximum net torque (n): … Nm at … min–1 (manufacturer's declared value)
3.2.2. Fuel
3.2.2.1. Diesel/Petrol/LPG/NG or Biomethane/Ethanol (E 85)/Biodiesel/Hydrogen (1),
3.2.2.1.1. RON, unleaded: …
3.2.2.4. Vehicle fuel type: Mono fuel, Bi fuel, Flex fuel (1)
3.2.2.5. Maximum amount of biofuel acceptable in fuel (manufacturer's declared value): … % by volume
3.2.4. Fuel feed
3.2.4.1. By carburettor(s): yes/no (1)
3.2.4.2. By fuel injection (compression ignition or dual fuel only): yes/no (1)
3.2.4.2.1. System description (common rail/unit injectors/distribution pump etc.): …
3.2.4.2.2. Working principle: direct injection/pre-chamber/swirl chamber (1)
3.2.4.2.3. Injection/Delivery pump
3.2.4.2.3.1. Make(s): …
3.2.4.2.3.2. Type(s): …
3.2.4.2.3.3. Maximum fuel delivery (1) (2): … mm3 /stroke or cycle at an engine speed of: … min–1 or,
alternatively, a characteristic diagram: … (When boost control is supplied, state the characteristic
fuel delivery and boost pressure versus engine speed)
3.2.4.2.4. Engine speed limitation control
3.2.4.2.4.2.1. Speed at which cut-off starts under load: … min–1
3.2.4.2.4.2.2. Maximum no-load speed: … min–1
3.2.4.2.6. Injector(s)
3.2.4.2.6.1. Make(s): …
3.2.4.2.6.2. Type(s): …
3.2.4.2.8. Auxiliary starting aid
3.2.4.2.8.1. Make(s): …
3.2.4.2.8.2. Type(s): …
30/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
3.2.4.2.8.3. System description: …
3.2.4.2.9. Electronic controlled injection: yes/no (1)
3.2.4.2.9.1. Make(s): …
3.2.4.2.9.2. Type(s):
3.2.4.2.9.3 Description of the system: …
3.2.4.2.9.3.1. Make and type of the control unit (ECU): …
3.2.4.2.9.3.1.1. Software version of the ECU: …
3.2.4.2.9.3.2. Make and type of the fuel regulator: …
3.2.4.2.9.3.3. Make and type of the air-flow sensor: …
3.2.4.2.9.3.4. Make and type of fuel distributor: …
3.2.4.2.9.3.5. Make and type of the throttle housing: …
3.2.4.2.9.3.6. Make and type or working principle of water temperature sensor: …
3.2.4.2.9.3.7. Make and type or working principle of air temperature sensor: …
3.2.4.2.9.3.8. Make and type or working principle of air pressure sensor: …
3.2.4.3. By fuel injection (positive ignition only): yes/no (1)
3.2.4.3.1. Working principle: intake manifold (single-/multi-point/direct injection (1) /other (specify): …
3.2.4.3.2. Make(s): …
3.2.4.3.3. Type(s): …
3.2.4.3.4. System description (In the case of systems other than continuous injection give equivalent details):
…
3.2.4.3.4.1. Make and type of the control unit (ECU): …
3.2.4.3.4.1.1. Software version of the ECU: …
3.2.4.3.4.3. Make and type or working principle of air-flow sensor: …
3.2.4.3.4.8. Make and type of throttle housing: …
3.2.4.3.4.9. Make and type or working principle of water temperature sensor: …
3.2.4.3.4.10. Make and type or working principle of air temperature sensor: …
3.2.4.3.4.11. Make and type or working principle of air pressure sensor: …
3.2.4.3.5. Injectors
3.2.4.3.5.1. Make: …
3.2.4.3.5.2. Type: …
3.2.4.3.7. Cold start system
3.2.4.3.7.1. Operating principle(s): …
3.2.4.3.7.2. Operating limits/settings (1) (2): …
3.2.4.4. Feed pump
3.2.4.4.1. Pressure (2): … kPa or characteristic diagram (2): …
3.2.4.4.2. Make(s): …
3.2.4.4.3. Type(s): …
3.2.5. Electrical system
ELI: http://data.europa.eu/eli/reg/2024/211/oj 31/98EN
OJ L, 12.1.2024
3.2.5.1. Rated voltage: … V, positive/negative ground (1)
3.2.5.2. Generator
3.2.5.2.1. Type: …
3.2.5.2.2. Nominal output: … VA
3.2.6. Ignition system (spark ignition engines only)
3.2.6.1. Make(s): …
3.2.6.2. Type(s): …
3.2.6.3. Working principle: …
3.2.6.6. Spark plugs
3.2.6.6.1. Make: …
3.2.6.6.2. Type: …
3.2.6.6.3. Gap setting: … mm
3.2.6.7. Ignition coil(s)
3.2.6.7.1. Make: …
3.2.6.7.2. Type: …
3.2.7. Cooling system: liquid/air (1)
3.2.7.1. Nominal setting of the engine temperature control mechanism: …
3.2.7.2. Liquid
3.2.7.2.1. Nature of liquid: …
3.2.7.2.2. Circulating pump(s): yes/no (1)
3.2.7.2.3. Characteristics: … or
3.2.7.2.3.1. Make(s): …
3.2.7.2.3.2. Type(s): …
3.2.7.2.4. Drive ratio(s): …
3.2.7.2.5. Description of the fan and its drive mechanism: …
3.2.7.3. Air
3.2.7.3.1. Fan: yes/no (1)
3.2.7.3.2. Characteristics: … or
3.2.7.3.2.1. Make(s): …
3.2.7.3.2.2. Type(s): …
3.2.7.3.3. Drive ratio(s): …
3.2.8. Intake system
3.2.8.1. Pressure charger: yes/no (1)
3.2.8.1.1. Make(s): …
3.2.8.1.2. Type(s): …
3.2.8.1.3. Description of the system (e.g. maximum charge pressure: … kPa; wastegate if applicable): …
3.2.8.2. Intercooler: yes/no (1)
32/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
3.2.8.2.1. Type: air-air/air-water (1)
3.2.8.3. Intake depression at rated engine speed and at 100 % load (compression ignition engines only)
3.2.8.4. Description and drawings of inlet pipes and their accessories (plenum chamber, heating device,
additional air intakes, etc.): …
3.2.8.4.1. Intake manifold description (include drawings and/or photos): …
3.2.8.4.2. Air filter, drawings: … or
3.2.8.4.2.1. Make(s): …
3.2.8.4.2.2. Type(s): …
3.2.8.4.3. Intake silencer, drawings: … or
3.2.8.4.3.1. Make(s): …
3.2.8.4.3.2. Type(s): …
3.2.9. Exhaust system
3.2.9.1. Description and/or drawing of the exhaust manifold: …
3.2.9.2. Description and/or drawing of the exhaust system: …
3.2.9.3. Maximum allowable exhaust back pressure at rated engine speed and at 100 % load (compression
ignition engines only): … kPa
3.2.10. Minimum cross-sectional areas of inlet and outlet ports: …
3.2.11. Valve timing or equivalent data
3.2.11.1. Maximum lift of valves, angles of opening and closing, or timing details of alternative distribution
systems, in relation to dead centres. For variable timing system, minimum and maximum timing:
…
3.2.11.2. Reference and/or setting ranges (1): …
3.2.12. Measures taken against air pollution
3.2.12.1. Device for recycling crankcase gases (description and drawings): …
3.2.12.2. Pollution control devices (if not covered by another heading)
3.2.12.2.1. Catalytic converter
3.2.12.2.1.1. Number of catalytic converters and elements (provide the information below for each separate
unit): …
3.2.12.2.1.2. Dimensions, shape and volume of the catalytic converter(s): …
3.2.12.2.1.3. Type of catalytic action: …
3.2.12.2.1.4. Total charge of precious metals: …
3.2.12.2.1.5. Relative concentration: …
3.2.12.2.1.6. Substrate (structure and material): …
3.2.12.2.1.7. Cell density: …
3.2.12.2.1.8. Type of casing for the catalytic converter(s): …
3.2.12.2.1.9. Location of the catalytic converter(s) (place and reference distance in the exhaust line): …
3.2.12.2.1.11. Normal operating temperature range: … °C
3.2.12.2.1.12. Make of catalytic converter: …
3.2.12.2.1.13. Identifying part number: …
ELI: http://data.europa.eu/eli/reg/2024/211/oj 33/98EN
OJ L, 12.1.2024
3.2.12.2.2. Sensors
3.2.12.2.2.1. Oxygen and/or lambda sensor(s): yes/no (1)
3.2.12.2.2.1.1. Make: …
3.2.12.2.2.1.2. Location: …
3.2.12.2.2.1.3. Control range: …
3.2.12.2.2.1.4. Type or working principle: …
3.2.12.2.2.1.5. Identifying part number: …
3.2.12.2.2.2. NO sensor: yes/no (1)
X
3.2.12.2.2.2.1. Make: …
3.2.12.2.2.2.2. Type: …
3.2.12.2.2.2.3. Location
3.2.12.2.2.3. Particulate sensor: yes/no (1)
3.2.12.2.2.3.1. Make: …
3.2.12.2.2.3.2. Type: …
3.2.12.2.2.3.3. Location: …
3.2.12.2.3. Air injection: yes/no (1)
3.2.12.2.3.1. Type (pulse air, air pump, etc.): …
3.2.12.2.4. Exhaust gas recirculation (EGR): yes/no (1)
3.2.12.2.4.1. Characteristics (make, type, flow, high pressure/low pressure/combined pressure, etc.): …
3.2.12.2.4.2. Water-cooled system (to be specified for each EGR system e.g. low pressure/high
pressure/combined pressure: yes/no (1)
3.2.12.2.6. Particulate trap (PT): yes/no (1)
3.2.12.2.6.1. Dimensions, shape and capacity of the particulate trap: …
3.2.12.2.6.2. Design of the particulate trap: …
3.2.12.2.6.3. Location (reference distance in the exhaust line): …
3.2.12.2.6.4. Make of particulate trap: …
3.2.12.2.6.5. Identifying part number: …
3.2.12.2.10. Periodically regenerating system: (provide the information below for each separate unit)
3.2.12.2.10.1. Method or system of regeneration, description and/or drawing: …
3.2.12.2.10.2. The number of Type 1 operating cycles, or equivalent engine test bench cycles, between two cycles
where regenerative phases occur under the conditions equivalent to Type 1 test (Distance ‘D’): …
3.2.12.2.10.2.1. Applicable Type 1 cycle: …
3.2.12.2.10.2.2. The number of complete applicable test cycles required for regeneration (distance ‘d’)
3.2.12.2.10.3. Description of method employed to determine the number of cycles between two cycles where
regenerative phases occur: …
3.2.12.2.10.4. Parameters to determine the level of loading required before regeneration occurs (i.e. temperature,
pressure etc.): …
34/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
3.2.12.2.10.5. Description of method used to load system: …
3.2.12.2.11. Catalytic converter systems using consumable reagents (provide the information below for each
separate unit) yes/no (1)
3.2.12.2.11.1. Type and concentration of reagent needed: …
3.2.12.2.11.2. Normal operational temperature range of reagent: …
3.2.12.2.11.3. International standard: …
3.2.12.2.11.4. Frequency of reagent refill: continuous/maintenance (where appropriate):
3.2.12.2.11.5. Reagent indicator: (description and location)
3.2.12.2.11.6. Reagent tank
3.2.12.2.11.6.1. Capacity: …
3.2.12.2.11.6.2. Heating system: yes/no
3.2.12.2.11.6.2.1. Description or drawing
3.2.12.2.11.7. Reagent control unit: yes/no (1)
3.2.12.2.11.7.1. Make: …
3.2.12.2.11.7.2. Type: …
3.2.12.2.11.8. Reagent injector (make type and location): …
3.2.12.2.11.9. Reagent quality sensor (make, type and location): …
3.2.12.2.12. Water injection: yes/no (1)
3.2.14. Details of any devices designed to influence fuel economy (if not covered by other items):.…
3.2.15. LPG fuelling system: yes/no (1)
3.2.15.1. Approval number (approval number of UN Regulation No. 67): …
3.2.15.2. Electronic engine management control unit for LPG fuelling
3.2.15.2.1. Make(s): …
3.2.15.2.2. Type(s): …
3.2.15.2.3. Emission-related adjustment possibilities: …
3.2.15.3. Further documentation
3.2.15.3.1. Description of the safeguarding of the catalyst at switch-over from petrol to LPG or back: …
3.2.15.3.2. System lay-out (electrical connections, vacuum connections compensation hoses, etc.): …
3.2.15.3.3. Drawing of the symbol: …
3.2.16. NG fuelling system: yes/no (1)
3.2.16.1. Approval number (approval number of UN Regulation No. 110):
3.2.16.2. Electronic engine management control unit for NG fuelling
3.2.16.2.1. Make(s): …
3.2.16.2.2. Type(s): …
3.2.16.2.3. Emission-related adjustment possibilities: …
3.2.16.3. Further documentation
3.2.16.3.1. Description of the safeguarding of the catalyst at switch-over from petrol to NG or back: …
ELI: http://data.europa.eu/eli/reg/2024/211/oj 35/98EN
OJ L, 12.1.2024
3.2.16.3.2. System lay-out (electrical connections, vacuum connections compensation hoses, etc.): …
3.2.16.3.3. Drawing of the symbol: …
3.4. Combinations of propulsion energy converters
3.4.1. Hybrid electric vehicle: yes/no (1)
3.4.2. Category of hybrid electric vehicle: off-vehicle charging/not off-vehicle charging: (1)
3.4.3. Operating mode switch: with/without (1)
3.4.3.1. Selectable modes
3.4.3.1.1. Pure electric: yes/no (1)
3.4.3.1.2. Pure fuel consuming: yes/no (1)
3.4.3.1.3. Hybrid modes: yes/no (1)
(if yes, short description): …
3.4.4. Description of the energy storage device: (REESS, capacitor, flywheel/generator)
3.4.4.1. Make(s): …
3.4.4.2. Type(s): …
3.4.4.3. Identification number: …
3.4.4.4. Kind of electrochemical couple: …
3.4.4.5. Energy: … (for REESS: voltage and capacity Ah in 2 h, for capacitor: J, …)
3.4.4.6. Charger: on board/external/without (1)
3.4.5. Electric machine (describe each type of electric machine separately)
3.4.5.1. Make: …
3.4.5.2. Type: …
3.4.5.3. Primary use: traction motor/generator (1)
3.4.5.3.1. When used as traction motor: single-/multimotors (number) (1): …
3.4.5.4. Maximum power: … kW
3.4.5.5. Working principle
3.4.5.5.5.1 Direct current/alternating current/number of phases: …
3.4.5.5.2. Separate excitation/series/compound (1)
3.4.5.5.3. Synchronous/asynchronous (1)
3.4.6. Control unit
3.4.6.1. Make(s): …
3.4.6.2. Type(s): …
3.4.6.3. Identification number: …
3.4.7. Power controller
3.4.7.1. Make: …
3.4.7.2. Type: …
3.4.7.3. Identification number: …
36/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
3.6.5. Lubricant temperature
Minimum: … K — maximum: … K
3.8. Lubrication system
3.8.1. Description of the system
3.8.1.1. Position of lubricant reservoir: …
3.8.1.2. Feed system (by pump/injection into intake/mixing with fuel, etc.) (1)
3.8.2. Lubricating pump
3.8.2.1. Make(s): …
3.8.2.2. Type(s): …
3.8.3. Mixture with fuel
3.8.3.1. Percentage: …
3.8.4. Oil cooler: yes/no (1)
3.8.4.1. Drawing(s): … or
3.8.4.1.1. Make(s): …
3.8.4.1.2. Type(s): …
3.8.5. Lubricant specification: …W…
4. TRANSMISSION (p)
4.4. Clutch(es)
4.4.1. Type: …
4.4.2. Maximum torque conversion: …
4.5. Gearbox
4.5.1. Type (manual/automatic/CVT (continuously variable transmission)) (1)
4.5.1.4. Torque rating: …
4.5.1.5. Number of clutches: …
4.6. Gear ratios
Gear Internal gearbox Final drive ratio(s) Total gear ratios
ratios (ratios of engine (ratio of gearbox
to gearbox output output shaft to driven
shaft revolutions) wheel revolutions)
Maximum for CVT
1
2
3
…
Minimum for CVT
4.7. Maximum vehicle design speed (in km/h) (q): …
4.12. Gearbox lubricant: …W…
ELI: http://data.europa.eu/eli/reg/2024/211/oj 37/98EN
OJ L, 12.1.2024
6. SUSPENSION
6.6. Tyres and wheels
6.6.1. Tyre/wheel combination(s)
6.6.1.1. Axles
6.6.1.1.1. Axle 1: …
6.6.1.1.1.1. Tyre size designation
6.6.1.1.2. Axle 2: …
6.6.1.1.2.1. Tyre size designation
etc.
6.6.2. Upper and lower limits of rolling radii
6.6.2.1. Axle 1: …
6.6.2.2. Axle 2: …
6.6.3. Tyre pressure(s) as recommended by the vehicle manufacturer: … kPa
9. BODYWORK
9.1. Type of bodywork (c): …
12. MISCELLANEOUS
12.10. Devices or systems with driver selectable modes which influence CO emissions, electric energy
2
consumption and/or criteria emissions and do not have a predominant mode: yes/no (1)
12.10.1. Charge sustaining test (if applicable) (state for each device or system)
12.10.1.0. Predominant mode under CS condition: yes/no (1)
12.10.1.0.1. Predominant mode under CS condition: … (if applicable)
12.10.1.1. Best case mode: … (if applicable)
12.10.1.2. Worst case mode: … (if applicable)
12.10.1.3. Mode which enables the vehicle to follow the reference test cycle: … (in case no predominant
mode under CS condition and only one mode is able to follow the reference test cycle)
12.10.2. Charge depleting test (if applicable) (state for each device or system)
12.10.2.0. Predominant mode under CD condition: yes/no (1)
12.10.2.0.1. Predominant mode under CD condition: … (if applicable)
12.10.2.1. Most energy consuming mode: … (if applicable)
12.10.2.2. Mode which enables the vehicle to follow the reference test cycle: … (in case no predominant
mode under CD condition and only one mode is able to follow the reference test cycle)
12.10.3. Type 1 test (if applicable) (state for each device or system)
12.10.3.1. Best case mode: …
12.10.3.2. Worst case mode: …
38/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
Explanatory notes:
(1) Delete where not applicable (there are cases where nothing needs to be deleted when more than one entry is applicable).
(2) Specify the tolerance.
(3) Please fill in here the upper and lower values for each variant.
(7) Optional equipment that affects the dimensions of the vehicle shall be specified.
(c) As defined in the Consolidated Resolution on the Construction of Vehicles (R.E.3.), document ECE/TRANS/WP.29/78/Rev.6, para. 2. -
www.unece.org/trans/main/wp29/wp29wgs/wp29gen/wp29resolutions.html.
(f) Where there is one version with a normal cab and another with a sleeper cab, both sets of masses and dimensions are to be stated.
(g) Standard ISO 612: 1978 — Road vehicles — Dimensions of motor vehicles and towed vehicles — terms and definitions.
(h) The mass of the driver is assessed at 75 kg.
The liquid containing systems (except those for used water that must remain empty) are filled to 100 % of the capacity specified by the
manufacturer.
(i) For trailers or semi-trailers, and for vehicles coupled with a trailer or a semi-trailer, which exert a significant vertical load on the
coupling device or the fifth wheel, this load, divided by standard acceleration of gravity, is included in the maximum technically
permissible mass.
(k) In the case of a vehicle that can run either on petrol, diesel, etc., or also in combination with another fuel, items shall be repeated.
In the case of non-conventional engines and systems, particulars equivalent to those referred to here shall be supplied by the
manufacturer.
(m) This value shall be calculated (π = 3,1416) and rounded off to the nearest cm3.
(n) Determined in accordance with the requirements of UN Regulation No. 85.
(p) The specified particulars are to be given for any proposed variants.
(q) With respect to trailers, maximum speed permitted by the manufacturer.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 39/98EN
OJ L, 12.1.2024
ANNEX 2
Communication
(Maximum format: A4 (210 × 297 mm)
issued by: (Name of administration)
.........................................
.........................................
.........................................
()
Concerning:(2) Approval granted
Approval extended
Approval refused
Approval withdrawn
Production definitively discontinued
of a vehicle type with regard to the emission of gaseous pollutants by the engine pursuant to UN Regulation No. 168
Approval No. .................................................................................................................
Reason for extension: .........................................................................................................
SECTION I
0.1. Make (trade name of manufacturer): ...................................................................................
0.2. Type: ...................................................................................................................
0.2.1. Commercial name(s) (if available): .....................................................................................
0.3. Means of identification of type if marked on the vehicle(3)
0.3.1. Location of that marking: .............................................................................................
0.4. Category of vehicle:(4).................................................................................................
0.5. Name and address of manufacturer: ...................................................................................
0.8. Name(s) and address(es) of assembly plant(s): .........................................................................
0.9. If applicable, name and address of manufacturer's representative: .....................................................
1.0. Remarks: ..............................................................................................................
SECTION II
1. Additional information (where applicable):
(1) Distinguishing number of the country which has granted/extended/refused/withdrawn approval (see approval provisions in the
Regulation).
(2) Strike out what does not apply.
(3) If the means of identification of type contains characters not relevant to describe the vehicle, component or separate technical unit
types covered by this information document, such characters shall be represented in the documentation by the symbol '?' (e.g. ABC??
123??).
(4) As defined in the Consolidated Resolution on the Construction of Vehicles (R.E.3.), document ECE/TRANS/WP.29/78/Rev.6, para. 2. -
www.unece.org/trans/main/wp29/wp29wgs/wp29gen/wp29resolutions.html.
40/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
2. Technical Service responsible for carrying out the tests: ...............................................................
3. Dates of RDE test report: ..............................................................................................
4. Number of RDE test reports: ..........................................................................................
5. Remarks (if any):
6. Place: ..................................................................................................................
7. Date: ...................................................................................................................
8. Signature: ......................................................................
Attachments: 1. Information package.
2. Test reports (as prescribed in paragraph 10.8. of this Regulation)
ELI: http://data.europa.eu/eli/reg/2024/211/oj 41/98EN
OJ L, 12.1.2024
ANNEX 3
Arrangement of the approval mark
In the approval mark issued and affixed to a vehicle in conformity with paragraph 5. of this Regulation, the type approval
number shall be accompanied by an alphanumeric character reflecting the level that the approval is limited to.
This annex outlines the appearance of this mark and gives an example how it shall be composed.
The following schematic graphic presents the general lay-out, proportions and contents of the marking. The meaning of
numbers and alphabetical character are identified, and sources to determine the corresponding alternatives for each
approval case are also referred.
()
a = 8 mm (minimum)
The following graphic is a practical example of how the marking should be composed.
(1) Number of country according to footnote in paragraph 5.4.1. of this Regulation.
42/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
ANNEX 4
Test procedure for vehicle emissions testing with a portable emissions measurement system (PEMS)
1. Introduction
This annex describes the test procedure to determine exhaust emissions from light passenger and commercial
vehicles using a Portable Emissions Measurement System.
2. Symbols, Parameters and Units
p — evacuated pressure [kPa]
e
q — volume flow rate of the system [l/min]
vs
ppmC — parts per million carbon equivalent
1
V — system volume [l]
s
3. General requirements
3.1. PEMS
The test shall be carried out with a PEMS, composed of components specified in paragraphs 3.1.1. to 3.1.5. If
applicable, a connection with the vehicle ECU may be established to determine relevant engine and vehicle
parameters as specified in paragraph 3.2.
3.1.1. Analysers to determine the concentration of pollutants in the exhaust gas.
3.1.2. One or multiple instruments or sensors to measure or determine the exhaust mass flow.
3.1.3. A GNSS receiver to determine the position, altitude and speed of the vehicle.
3.1.4. If applicable, sensors and other appliances being not part of the vehicle, e.g. to measure ambient temperature,
relative humidity and air pressure.
3.1.5. An energy source independent of the vehicle to power the PEMS.
3.2. Test parameters
Test parameters, as specified in Table A4/1, shall be measured at a constant frequency of 1,0 Hz or higher and
recorded and reported in accordance with the requirements of paragraph 10. of Annex 7 at a sampling frequency
of 1,0 Hz. If ECU parameters are obtained, these may be obtained at a substantially higher frequency but the
recording rate shall be 1,0 Hz. The PEMS analysers, flow-measuring instruments and sensors shall comply with the
requirements laid down in Annexes 5 and 6.
Table A4/1
Test parameters
Parameter Recommended unit Source(1)
THC concentration(2)(3)(if ppm C Analyser
1
applicable)
CH concentration(1)(2)(3)(if ppm C Analyser
4 1
applicable)
NMHC concentration (1)(2)(3)(if ppm C Analyser(4)
1
applicable)
CO concentration(1)(2)(3) ppm Analyser
CO concentration(2) ppm Analyser
2
ELI: http://data.europa.eu/eli/reg/2024/211/oj 43/98EN
OJ L, 12.1.2024
NO concentration(2)(3) ppm Analyser(5)
X
PN concentration(3) #/m3 Analyser
Exhaust mass flow rate kg/s EFM, any methods described in
paragraph 7. of Annex 5.
Ambient humidity % Sensor
Ambient temperature K Sensor
Ambient pressure kPa Sensor
Vehicle speed km/h Sensor, GNSS, or ECU(6)
Vehicle latitude Degree GNSS
Vehicle longitude Degree GNSS
Vehicle altitude(7)(8) m GNSS or Sensor
Exhaust gas temperature(7) K Sensor
Engine coolant temperature(7) K Sensor or ECU
Engine speed(7) RPM Sensor or ECU
Engine torque(7) Nm Sensor or ECU
Torque at driven axle(7)(if Nm Rim torque meter
applicable)
Pedal position(7) % Sensor or ECU
Engine fuel flow(1)(9)(if g/s Sensor or ECU
applicable)
Engine intake air flow(9)(if g/s Sensor or ECU
applicable)
Fault status(7) — ECU
Intake air flow temperature K Sensor or ECU
Regeneration status(7)(if — ECU
applicable)
Engine oil temperature(7) K Sensor or ECU
Actual gear(7) # ECU
Desired gear (e.g. gear shift # ECU
indicator)(7)
Other vehicle data(7) unspecified ECU
(1) Multiple parameter sources may be used.
(2) To be measured on a wet basis or to be corrected as described in paragraph 5.1. of Annex 7.
(3) Parameter only mandatory if measurement required for compliance with the limits.
(4) May be calculated from THC and CH concentrations according to paragraph 6.2. to Annex 7.
4
(5) May be calculated from measured NO and NO concentrations.
2
(6) Method to be chosen according to paragraph 4.7. of this annex.
(7) To be determined only if necessary to verify the vehicle status and operating conditions.
(8) The preferable source is the ambient pressure sensor.
(9) To be determined only if indirect methods are used to calculate exhaust mass flow rate as described in paragraphs 7.2. and 7.4.
of Annex 7.
44/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
3.4. Installation of PEMS
3.4.1. General:
The installation of the PEMS shall follow the instructions of the PEMS manufacturer and the local health and safety
regulations. When the PEMS is installed inside the vehicle, the vehicle should be equipped with gas monitors or
warning systems for hazardous gases (e.g. CO). The PEMS should be installed as to minimise electromagnetic
interferences during the test as well as exposure to shocks, vibration, dust and variability in temperature. The
installation and operation of the PEMS shall be such that it avoids leakage and minimise heat loss. The installation
and operation of PEMS shall not change the nature of the exhaust gas nor unduly increase the length of the tailpipe.
To avoid the generation of particles, connectors shall be thermally stable at the exhaust gas temperatures expected
during the test. It is recommended to avoid the use elastomer connectors to connect the vehicle exhaust outlet and
the connecting tube. Elastomer connectors, if used, shall have no contact with the exhaust gas to avoid artefacts. If
the test performed with the use of elastomer connectors fails, the test shall be repeated without the use of elastomer
connectors.
3.4.2. Permissible backpressure
The installation and operation of the PEMS sampling probes shall not unduly increase the pressure at the exhaust
outlet in a way that may influence the representativeness of the measurements. It is thus recommended that only
one sampling probe is installed in the same plane. If technically feasible, any extension to facilitate the sampling or
connection with the exhaust mass flow meter shall have an equivalent, or larger, cross sectional area than the
exhaust pipe.
3.4.3. Exhaust mass flow meter
Whenever used, the exhaust mass flow meter shall be attached to the vehicle’s tailpipe(s) in accordance with the
recommendations of the EFM manufacturer. The measurement range of the EFM shall match the range of the
exhaust mass flow rate expected during the test. It is recommended to select the EFM so that the maximum
expected flow rate during the test reaches at least 75 per cent of the EFM full range but does not exceed the EFM
full range. The installation of the EFM and any exhaust pipe adaptors or junctions shall not adversely affect the
operation of the engine or exhaust after-treatment system. A minimum of four pipe diameters or 150 mm of
straight tubing, whichever is larger, shall be placed at either side of the flow-sensing element. When testing a multi-
cylinder engine with a branched exhaust manifold, it is recommended to position the exhaust mass flow meter
downstream of where the manifolds combine and to increase the cross section of the piping such as to have an
equivalent, or larger, cross sectional area from which to sample. If this is not feasible, exhaust flow measurements
with several exhaust mass flow meters may be used. The wide variety of exhaust pipe configurations, dimensions
and exhaust mass flow rates may require compromises, guided by good engineering judgement, when selecting and
installing the EFM(s). It is permissible to install an EFM with a diameter smaller than that of the exhaust outlet or the
total cross-sectional area of multiple outlets, providing it improves measurement accuracy and does not adversely
affect the operation or the exhaust after-treatment as specified in paragraph 3.4.2. It is recommended to document
the EFM set-up using photographs.
3.4.4. Global Navigation Satellite System (GNSS)
The GNSS antenna shall be mounted as near as possible to the highest location on the vehicle, so as to ensure good
reception of the satellite signal. The mounted GNSS antenna shall interfere as little as possible with the vehicle
operation.
3.4.5. Connection with the Engine Control Unit (ECU)
If desired, relevant vehicle and engine parameters listed in Table A4/1 can be recorded by using a data logger
connected with the ECU or the vehicle network through national or international standards, such as ISO 15031-5
or SAE J1979, OBD-II, EOBD or WWH-OBD. If applicable, manufacturers shall disclose labels to allow the
identification of required parameters.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 45/98EN
OJ L, 12.1.2024
3.4.6. Sensors and auxiliary devices
Vehicle speed sensors, temperature sensors, coolant thermocouples or any other measurement device not part of the
vehicle shall be installed to measure the parameter under consideration in a representative, reliable and accurate
manner without unduly interfering with the vehicle operation and the functioning of other analysers, flow-
measuring instruments, sensors and signals. Sensors and auxiliary equipment shall be powered independently of
the vehicle. It is permitted to power any safety-related illumination of fixtures and installations of PEMS
components outside of the vehicle’s cabin by the vehicle’s battery.
3.5. Emissions sampling
Emissions sampling shall be representative and conducted at locations of well-mixed exhaust, where the influence of
ambient air downstream of the sampling point is minimal. If applicable, emissions shall be sampled downstream of
the exhaust mass flow meter, respecting a distance of at least 150 mm to the flow sensing element. The sampling
probes shall be fitted at least 200 mm or three times the inner diameter of the exhaust pipe, whichever is larger,
upstream of the point at which the exhaust gas exits the PEMS sampling installation into the environment.
If the PEMS feeds part of the sample back to the exhaust flow, this shall occur downstream of the sampling probe in
a manner that does not affect the nature of the exhaust gas at the sampling point(s). If the length of the sampling line
is changed, the system transport times shall be verified and, if necessary, corrected. If the vehicle is equipped with
more than one tailpipe then all functioning tailpipes shall be connected before sampling and measuring exhaust
flow.
If the engine is equipped with an exhaust after-treatment system, the exhaust sample shall be taken downstream of
the exhaust after-treatment system. When testing a vehicle with a branched exhaust manifold, the inlet of the
sampling probe shall be located sufficiently far downstream so as to ensure that the sample is representative of the
average exhaust emissions of all cylinders. In multi-cylinder engines, having distinct groups of manifolds, such as in
a ‘V’ engine configuration, the sampling probe shall be positioned downstream of where the manifolds combine. If
this is technically not feasible, multi-point sampling at locations of well-mixed exhaust may be used. In this case,
the number and location of sampling probes shall match as far as possible those of the exhaust mass flow meters.
In case of unequal exhaust flows, proportional sampling or sampling with multiple analysers shall be considered.
If particles are measured, they shall be sampled from the centre of the exhaust stream. If several probes are used for
emissions sampling, the particle sampling probe should be placed upstream of the other sampling probes. The
particle sampling probe should not interfere with the sampling of gaseous pollutants. The type and specifications
of the probe and its mounting shall be documented in detail (e.g. L type or 45° cut, internal diameter, with or
without hat, etc).
If hydrocarbons are measured, the sampling line shall be heated to 463 ± 10 K (190 ± 10 °C). For the measurement
of other gaseous components, with or without cooler, the sampling line shall be kept at a minimum of 333 K (60 °C)
to avoid condensation and to ensure appropriate penetration efficiencies of the various gases. For low pressure
sampling systems, the temperature can be lowered correspondingly to the pressure decrease provided that the
sampling system ensures a penetration efficiency of 95 per cent for all regulated gaseous pollutants. If particles are
sampled and not diluted at the tailpipe, the sampling line from the raw exhaust sample point to the point of
dilution or particle detector shall be heated to a minimum of 373 K (100 °C). The residence time of the sample in
the particle sampling line shall be less than 3 s until reaching first dilution or the particle detector.
All parts of the sampling system from the tailpipe up to the particle detector, which are in contact with raw or
diluted exhaust gas, shall be designed to minimize deposition of particles. All parts shall be made from antistatic
material to prevent electrostatic effects.
46/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
4. Pre-test procedures
4.1. PEMS leak check
After the installation of the PEMS is completed, a leak check shall be performed at least once for each PEMS-vehicle
installation as prescribed by the PEMS manufacturer or as follows. The probe shall be disconnected from the exhaust
system and the end plugged. The analyser pump shall be switched on. After an initial stabilization period, all flow
meters shall read approximately zero in the absence of a leak. If this is not the case the sampling lines shall be
checked and the fault shall be corrected.
The leakage rate on the vacuum side shall not exceed 0,5 per cent of the in-use flow rate for the portion of the
system being checked. The analyser flows and bypass flows may be used to estimate the in-use flow rate.
Alternatively, the system may be evacuated to a pressure of at least 20 kPa vacuum (80 kPa absolute). After an initial
stabilization period the pressure increase Δp (kPa/min) in the system shall not exceed:
Δp¼ pe× q ×0;005
Vs vs
where:
p is the evacuated pressure [Pa],
e
V is the system volume [l],
s
q is the volume flow rate of the system [l/min].
vs
Alternatively, a concentration step change at the beginning of the sampling line shall be introduced by switching
from zero to span gas while maintaining the same pressure conditions as under normal system operation. If for a
correctly calibrated analyser after an adequate period of time the reading is ≤ 99 per cent compared to the
introduced concentration, the leakage problem shall be corrected.
4.2. Starting and stabilizing the PEMS
The PEMS shall be switched on, warmed up and stabilized in accordance with the specifications of the PEMS
manufacturer until key functional parameters (e.g., pressures, temperatures and flows) have reached their operating
set points before test start. To ensure correct functioning, the PEMS may be kept switched on or can be warmed up
and stabilized during vehicle conditioning. The system shall be free of errors and critical warnings.
4.3. Preparing the sampling system
The sampling system, consisting of the sampling probe and sampling lines shall be prepared for testing by following
the instruction of the PEMS manufacturer. It shall be ensured that the sampling system is clean and free of moisture
condensation.
4.4. Preparing the Exhaust mass Flow Meter (EFM)
If used for measuring the exhaust mass flow, the EFM shall be purged and prepared for operation in accordance with
the specifications of the EFM manufacturer. This procedure shall, if applicable, remove condensation and deposits
from the lines and the associated measurement ports.
4.5. Checking and calibrating the analysers for measuring gaseous emissions
Zero and span calibration adjustments of the analysers shall be performed using calibration gases that meet the
requirements of paragraph 5. of Annex 5. The calibration gases shall be chosen to match the range of pollutant
concentrations expected during the RDE test. To minimise analyser drift, it is recommended to conduct the zero
and span calibration of analysers at an ambient temperature that resembles, as closely as possible, the temperature
experienced by the test equipment during the trip.
4.6. Checking the analyser for measuring particle emissions
The zero level of the analyser shall be recorded by sampling HEPA filtered ambient air at an appropriate sampling
point, ideally at the inlet of the sampling line. The signal shall be recorded at a constant frequency which is a
multiple of 1,0 Hz averaged over a period of 2 minutes. The final concentration shall be within the manufacturer’s
specifications, but shall not exceed 5 000particles per cubic-centimetre.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 47/98EN
OJ L, 12.1.2024
4.7. Determining vehicle speed
Vehicle speed shall be determined by at least one of the following methods:
(a) A sensor (e.g., optical or micro-wave sensor); if vehicle speed is determined by a sensor, the speed measurements
shall comply with the requirements of paragraph 8. of Annex 5, or alternatively, the total trip distance
determined by the sensor shall be compared with a reference distance obtained from a digital road network or
topographic map. The total trip distance determined by the sensor shall deviate by no more than 4 per cent
from the reference distance.
(b) The ECU; if vehicle speed is determined by the ECU, the total trip distance shall be validated according to
paragraph 3. of Annex 6 and the ECU speed signal adjusted, if necessary, to fulfil the requirements of
paragraph 3. of Annex 6. Alternatively, the total trip distance as determined by the ECU can be compared with
a reference distance obtained from a digital road network or topographic map. The total trip distance
determined by the ECU shall deviate by no more than 4 per cent from the reference distance.
(c) A GNSS; if vehicle speed is determined by a GNSS, the total trip distance shall be checked against the
measurements of another method according to paragraph 6.5. of Annex 4.
4.8. Check of PEMS set up
The correctness of connections with all sensors and, if applicable, the ECU shall be verified. If engine parameters are
retrieved, it shall be ensured that the ECU reports values correctly (e.g., zero engine speed [rpm] while the
combustion engine is in key-on-engine-off status). The PEMS shall function free of errors and critical warnings.
5. Emissions test
5.1. Test start
Sampling, measurement and recording of parameters shall begin prior to the test start (as defined in paragraph
3.8.5. of this Regulation). Before the test start it shall be confirmed that all necessary parameters are recorded by
the data logger.
To facilitate time alignment, it is recommended to record the parameters that are subject to time alignment either by
a single data recording device or with a synchronised time stamp.
5.2. Test
Sampling, measurement and recording of parameters shall continue throughout the on-road test of the vehicle. The
engine may be stopped and started, but emissions sampling and parameter recording shall continue. Repeated
stalling of the engine (i.e. unintentional stopping of the engine) should be avoided during an RDE trip. Any
warning signals, suggesting malfunctioning of the PEMS, shall be documented and verified. If any error signal(s)
appear during the test, the test shall be invalid. Parameter recording shall reach a data completeness of higher than
99 per cent. Measurement and data recording may be interrupted for less than 1 per cent of the total trip duration
but for no more than a consecutive period of 30 s solely in the case of unintended signal loss or for the purpose of
PEMS system maintenance. Interruptions may be recorded directly by the PEMS but it is not permissible to introduce
interruptions in the recorded parameter via the pre-processing, exchange or post-processing of data. If conducted,
auto zeroing shall be performed against a traceable zero standard similar to the one used to zero the analyser. It is
strongly recommended to initiate PEMS system maintenance during periods of zero vehicle speed.
5.3. Test end
Excessive idling of the engine after the completion of the trip shall be avoided. The data recording shall continue
after the test end (as defined in paragraph 3.8.6. of this Regulation) and until the response time of the sampling
systems has elapsed. For vehicles with a signal detecting regeneration, the OBD-check shall be performed and
documented directly after data recording and before any further driven distance is driven.
48/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
6. Post-test procedure
6.1. Checking the analysers for measuring gaseous emissions
The zero and span of the analysers of gaseous components shall be checked by using calibration gases identical to
the ones applied under paragraph 4.5. to evaluate the analyser's zero and response drift compared to the pre-test
calibration. It is permissible to zero the analyser prior to verifying the span drift, if the zero drift was determined to
be within the permissible range. The post-test drift check shall be completed as soon as possible after the test and
before the PEMS, or individual analysers or sensors, are turned off or have switched into a non-operating mode.
The difference between the pre-test and post-test results shall comply with the requirements specified in Table A4/2.
Table A4/2
Permissible analyser drift over a PEMS test
Pollutant Absolute Zero response drift Absolute Span response drift(1)
CO ≤ 2 000ppm per test ≤ 2 % of reading or ≤ 2 000ppm per test, whichever is larger
2
CO ≤ 75 ppm per test ≤ 2 % of reading or ≤ 75 ppm per test, whichever is larger
NO ≤ 3 ppm per test ≤ 2 % of reading or ≤ 3 ppm per test, whichever is larger
X
CH ≤ 10 ppm C per test ≤ 2 % of reading or ≤ 10 ppm C per test, whichever is larger
4 1 1
THC ≤ 10 ppm C per test ≤ 2 % of reading or ≤ 10 ppm C per test, whichever is larger
1 1
(1) If the zero drift is within the permissible range, it is permissible to zero the analyser prior to verifying the span drift.
If the difference between the pre-test and post-test results for the zero and span drift is higher than permitted, all test
results shall be invalid and the test repeated.
6.2. Checking the analyser for measuring particle emissions
The zero level of the analyser shall be recorded in accordance with paragraph 4.6.
6.3. Checking the on-road emission measurements
The span gas concentration that was used for the calibration of the analysers in accordance with paragraph 4.5. at
the test start shall cover at least 90 per cent of the concentration values obtained from 99 per cent of the
measurements of the valid parts of the emissions test. It is permissible that 1 per cent of the total number of
measurements used for evaluation exceeds the concentration of the span gas used by up to a factor of two. If these
requirements are not met, the test shall be invalid.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 49/98EN
OJ L, 12.1.2024
6.4. Consistency check of vehicle altitude
In case altitude has only been measured with a GNSS, the GNSS altitude data shall be checked for consistency and, if
necessary, corrected. The consistency of data shall be checked by comparing the latitude, longitude and altitude data
obtained from the GNSS with the altitude indicated by a digital terrain model or a topographic map of suitable scale.
Measurements that deviate by more than 40 m from the altitude depicted in the topographic map shall be manually
corrected. The original and uncorrected data shall be retained and any corrected data shall be marked.
The instantaneous altitude data shall be checked for completeness. Data gaps shall be completed by data
interpolation. The correctness of interpolated data shall be verified by a topographic map. It is recommended to
correct interpolated data if the following condition applies:
jh ðtÞ – h ðtÞj>;40 m
GNSS map
The altitude correction shall be applied so that:
jhðtÞ – h ðtÞj<;40 m
map
where:
h(t) — vehicle altitude after the screening and principle check of data quality at data point t [m above
sea level]
h (t) — vehicle altitude measured with GNSS at data point t [m above sea level]
GNSS
h (t) — vehicle altitude based on topographic map at data point t [m above sea level]
map
6.5. Consistency check of GNSS vehicle speed
The vehicle speed as determined by the GNSS shall be checked for consistency by calculating and comparing the
total trip distance with reference measurements obtained from either a sensor, the validated ECU or, alternatively,
from a digital road network or topographic map. It is mandatory to correct GNSS data for obvious errors, e.g., by
applying a dead reckoning sensor, prior to the consistency check. The original and uncorrected data shall be
retained and any corrected data shall be marked. The corrected data shall not exceed an uninterrupted time period
of 120 s or a total of 300 s. The total trip distance as calculated from the corrected GNSS data shall deviate by no
more than 4 per cent from the reference. If the GNSS data do not meet these requirements and no other reliable
speed source is available, the test shall be invalid.
6.6. Consistency check of the ambient temperature
The ambient temperature data shall be checked for consistency and inconsistent values corrected by substituting
outliers with the average of the neighbouring values. The original and uncorrected data shall be retained and any
corrected data shall be marked.
50/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
ANNEX 5
Specifications and calibration of PEMS components and signals
1. Introduction
This annex sets out the specifications and calibration of PEMS components and signals.
2. Symbols, Parameters and Units
A — undiluted CO concentration [%]
2
a — y-axis intercept of the linear regression line
0
a — slope of the linear regression line
1
B — diluted CO concentration [%]
2
C — diluted NO concentration [ppm]
c — analyser response in the oxygen interference test
C Measured diluted NO concentration through bubbler
b
c — full scale HC concentration in step (b) [ppmC ]
FS,b 1
c — full scale HC concentration in step (d) [ppmC ]
FS,d 1
c — HC concentration with CH or C H flowing through the NMC [ppmC ]
HC(w/NMC) 4 2 6 1
c — HC concentration with CH or C H bypassing the NMC [ppmC ]
HC(w/o NMC) 4 2 6 1
c — measured HC concentration in step (b) [ppmC ]
m,b 1
c — measured HC concentration in step (d) [ppmC ]
m,d 1
c — reference HC concentration in step (b) [ppmC ]
ref,b 1
c — reference HC concentration in step (d) [ppmC ]
ref,d 1
D — undiluted NO concentration [ppm]
D — expected diluted NO concentration [ppm]
e
E — absolute operating pressure [kPa]
E — per cent CO quench
CO2 2
E(d ) — PEMS-PN analyser efficiency
p
E — ethane efficiency
E
E — per cent water quench
H2O
E — methane efficiency
M
E — oxygen interference
O2
F — water temperature [K]
G — saturation vapour pressure [kPa]
H — water vapour concentration [%]
H — maximum water vapour concentration [%]
m
NO — moisture-corrected mean concentration of the stabilized NO recordings
X,dry X
NO — mean concentration of the stabilized NO recordings
X,m X
NO — reference mean concentration of the stabilized NO recordings
X,ref X
r2 — coefficient of determination
ELI: http://data.europa.eu/eli/reg/2024/211/oj 51/98EN
OJ L, 12.1.2024
t — time point of gas flow switching [s]
0
t — time point of 10 % response of the final reading
10
t — time point of 50 % response of the final reading
50
t — time point of 90 % response of the final reading
90
Tbd — to be determined
X — independent variable or reference value
x — minimum value
min
Y — dependent variable or measured value
3. Linearity verification
3.1. General
The accuracy and linearity of analysers, flow-measuring instruments, sensors and signals shall be traceable to
international or national standards. Any sensors or signals that are not directly traceable (e.g., simplified flow-
measuring instruments) shall be calibrated alternatively against chassis dynamometer laboratory equipment that
has been calibrated against international or national standards.
3.2. Linearity requirements
All analysers, flow-measuring instruments, sensors and signals shall comply with the linearity requirements given in
Table A5/1. If air flow, fuel flow, the air-to-fuel ratio or the exhaust mass flow rate is obtained from the ECU, the
calculated exhaust mass flow rate shall meet the linearity requirements specified in Table A5/1.
Table A5/1
Linearity requirements of measurement parameters and systems
Measurement Slope Standard error of the Coefficient of
jx ×ða – 1Þþaj
parameter/instrument min 1 0 a estimate SEE determination r2
1
Fuel flow rate(1) ≤ 1 % x 0,98– 1,02 ≤ 2% of x ≥ 0,990
max max
Air flow rate(2) ≤ 1 % x 0,98– 1,02 ≤ 2% of x ≥ 0,990
max max
Exhaust mass flow rate ≤ 2 % x 0,97– 1,03 ≤ 3% of x ≥ 0,990
max max
Gas analysers ≤ 0.5 % max 0,99– 1,01 ≤ 1% of x ≥ 0,998
max
Torque(3) ≤ 1 % x 0,98– 1,02 ≤ 2% of x ≥ 0,990
max max
PN analysers(4) ≤ 5 % x 0,85– 1,15 (5) ≤ 10% of x ≥ 0,950
max max
(1) Optional to determine exhaust mass flow.
(2) Optional to determine exhaust mass flow.
(3) Optional parameter.
(4) The linearity check shall be verified with soot-like particles, as these are defined in paragraph 6.2. of this annex.
(5) To be updated based on error propagation and traceability charts.
3.3. Frequency of linearity verification
The linearity requirements pursuant to paragraph 3.2. shall be verified:
(a) For each gas analyser at least every 12 months or whenever a system repair or component change or
modification is made that could influence the calibration;
52/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
(b) For other relevant instruments, such as PN analysers, exhaust mass flow meters and traceably calibrated sensors,
whenever damage is observed, as required by internal audit procedures or by the instrument manufacturer but
no longer than one year before the actual test.
The linearity requirements pursuant to paragraph 3.2. for sensors or ECU signals that are not directly traceable shall
be performed using a measurement device with a traceable calibration on the chassis dynamometer, once for each
PEMS-vehicle setup.
3.4. Procedure of linearity verification
3.4.1. General requirements
The relevant analysers, instruments and sensors shall be brought to their normal operating condition according to
the recommendations of their manufacturer. The analysers, instruments and sensors shall be operated at their
specified temperatures, pressures and flows.
3.4.2. General procedure
The linearity shall be verified for each normal operating range by executing the following steps:
(a) The analyser, flow-measuring instrument or sensor shall be set to zero by introducing a zero signal. For gas
analysers, purified synthetic air or nitrogen shall be introduced to the analyser port via a gas path that is as
direct and short as possible.
(b) The analyser, flow-measuring instrument or sensor shall be spanned by introducing a span signal. For gas
analysers, an appropriate span gas shall be introduced to the analyser port via a gas path that is as direct and
short as possible.
(c) The zero procedure of (a) shall be repeated.
(d) The linearity shall be verified by introducing at least 10, approximately equally spaced and valid, reference
values (including zero). The reference values with respect to the concentration of components, the exhaust
mass flow rate or any other relevant parameter shall be chosen to match the range of values expected during
the emissions test. For measurements of exhaust mass flow, reference points below 5 per cent of the maximum
calibration value can be excluded from the linearity verification.
(e) For gas analysers, known gas concentrations in accordance with paragraph 5. shall be introduced to the analyser
port. Sufficient time for signal stabilisation shall be given. For particle number analysers, the particle number
concentrations shall be at least two times the limit of detection (defined in paragraph 6.2.).
(f) The values under evaluation and, if needed, the reference values shall be recorded at a constant frequency which
is a multiple of 1,0 Hz over a period of 30 seconds (60 s for particle number analysers).
(g) The arithmetic mean values over the 30 seconds (or 60 s) period shall be used to calculate the least squares
linear regression parameters, with the best-fit equation having the form:
y¼axþa
1 0
where:
y is the actual value of the measurement system
a is the slope of the regression line
1
x is the reference value
a is the y intercept of the regression line
0
The standard error of estimate (SEE) of y on x and the coefficient of determination (r2) shall be calculated for each
measurement parameter and system.
(h) The linear regression parameters shall meet the requirements specified in Table A5/1.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 53/98EN
OJ L, 12.1.2024
3.4.3. Requirements for linearity verification on a chassis dynamometer
Non-traceable flow-measuring instruments, sensors or ECU signals, that cannot directly be calibrated according to
traceable standards, shall be calibrated on a chassis dynamometer. The procedure shall follow, as far as applicable,
the requirements of UN Regulation No. 154 on WLTP. If necessary, the instrument or sensor to be calibrated shall
be installed on the test vehicle and operated according to the requirements of Annex 4. The calibration procedure
shall follow whenever possible the requirements of paragraph 3.4.2. At least 10 appropriate reference values shall
be selected as to ensure that at least 90 per cent of the maximum value expected to occur during the RDE test is
covered.
If a non-traceable flow-measuring instrument, sensor or ECU signal for determining exhaust flow is to be calibrated,
a reference exhaust mass flow meter with traceable calibration or the CVS shall be attached to the vehicle’s tailpipe.
It shall be ensured that the vehicle exhaust is accurately measured by the exhaust mass flow meter according to
paragraph 3.4.3. of Annex 4. The vehicle shall be operated by applying constant throttle at a constant gear
selection and chassis dynamometer load.
4. Analysers for measuring gaseous components
4.1. Permissible types of analysers
4.1.1. Standard analysers
The gaseous components shall be measured with analysers specified in paragraph 4.1.4., Annex B5 to UN
Regulation No. 154 on WLTP. If an NDUV analyser measures both NO and NO , a NO /NO converter is not
2 2
required.
4.1.2. Alternative analysers
Any analyser not meeting the design specifications of paragraph 4.1.1. is permissible provided that it fulfils the
requirements of paragraph 4.2. The manufacturer shall ensure that the alternative analyser achieves an equivalent
or higher measurement performance compared to a standard analyser over the range of pollutant concentrations
and co-existing gases that can be expected from vehicles operated with permissible fuels under moderate and
extended conditions of valid RDE testing as specified in paragraphs 5., 6. and 7. of this annex. Upon request, the
manufacturer of the analyser shall submit in writing supplemental information, demonstrating that the
measurement performance of the alternative analyser is consistently and reliably in line with the measurement
performance of standard analysers. Supplemental information shall contain:
(a) A description of the theoretical basis and the technical components of the alternative analyser;
(b) A demonstration of equivalency with the respective standard analyser specified in paragraph 4.1.1. over the
expected range of pollutant concentrations and ambient conditions of the type-approval test defined in UN
Regulation No. 154 on WLTP as well as a validation test as described in paragraph 3. of Annex 6 for a vehicle
equipped with a spark-ignition and compression-ignition engine; the manufacturer of the analyser shall
demonstrate the significance of equivalency within the permissible tolerances given in paragraph 3.3. of Annex
6.
(c) A demonstration of equivalency with the respective standard analyser specified in paragraph 4.1.1. with respect
to the influence of atmospheric pressure on the measurement performance of the analyser; the demonstration
test shall determine the response to span gas having a concentration within the analyser range to check the
influence of atmospheric pressure under moderate and extended altitude conditions defined in paragraph 8.1.
Such a test can be performed in an altitude environmental test chamber.
(d) A demonstration of equivalency with the respective standard analyser specified in paragraph 4.1.1. over at least
three on-road tests that fulfil the requirements of this Annex.
(e) A demonstration that the influence of vibrations, accelerations and ambient temperature on the analyser
reading does not exceed the noise requirements for analysers set out in paragraph 4.2.4.
54/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
Approval authorities may request additional information to substantiate equivalency or refuse approval if
measurements demonstrate that an alternative analyser is not equivalent to a standard analyser.
4.2. Analyser specifications
4.2.1. General
In addition to the linearity requirements defined for each analyser in paragraph 3., the compliance of analyser types
with the specifications laid down in paragraphs 4.2.2. to 4.2.8. shall be demonstrated by the analyser manufacturer.
Analysers shall have a measuring range and response time appropriate to measure with adequate accuracy the
concentrations of the exhaust gas components at the applicable emissions standard under transient and steady state
conditions. The sensitivity of the analysers to shocks, vibration, aging, variability in temperature and air pressure as
well as electromagnetic interferences and other impacts related to vehicle and analyser operation shall be limited as
far as possible.
4.2.2. Accuracy
The accuracy, defined as the deviation of the analyser reading from the reference value, shall not exceed 2 per cent of
reading or 0.3 per cent of full scale, whichever is larger.
4.2.3. Precision
The precision, defined as 2.5 times the standard deviation of 10 repetitive responses to a given calibration or span
gas, shall be no greater than 1 per cent of the full scale concentration for a measurement range equal or above 155
ppm (or ppmC ) and 2 per cent of the full scale concentration for a measurement range of below 155 ppm (or
1
ppmC ).
1
4.2.4. Noise
The noise shall not exceed 2 per cent of full scale. Each of the 10 measurement periods shall be interspersed with an
interval of 30 seconds in which the analyser is exposed to an appropriate span gas. Before each sampling period and
before each span period, sufficient time shall be given to purge the analyser and the sampling lines.
4.2.5. Zero response drift
The drift of the zero response, defined as the mean response to a zero gas during a time interval of at least 30
seconds, shall comply with the specifications given in Table A5/2.
4.2.6. Span response drift
The drift of the span response, defined as the mean response to a span gas during a time interval of at least 30
seconds, shall comply with the specifications given in Table A5/2.
Table A5/2
Permissible zero and span response drift of analysers for measuring gaseous components under laboratory
conditions
Pollutant Absolute Zero response drift Absolute Span response drift
CO ≤ 1 000ppm over 4 h ≤ 2 % of reading or ≤ 1 000ppm over 4 h,
2
whichever is larger
CO ≤ 50 ppm over 4 h ≤ 2 % of reading or ≤ 50 ppm over 4 h,
whichever is larger
PN 5 000particles per cubic centimetre over 4 h According to manufacturer specifications
NO ≤ 3 ppm over 4 h ≤ 2 % of reading or ≤ 3 ppm over 4 h, whichever
X
is larger
ELI: http://data.europa.eu/eli/reg/2024/211/oj 55/98EN
OJ L, 12.1.2024
CH ≤ 10 ppm C ≤ 2 % of reading or ≤ 10 ppm C over 4 h,
4 1 1
whichever is larger
THC ≤ 10 ppm C ≤ 2 % of reading or ≤ 10 ppm C over 4 h,
1 1
whichever is larger
4.2.7. Rise time
The rise time, defined as the time between the 10 per cent and 90 per cent response of the final reading (t to t ;
10 90
see paragraph 4.4.), shall not exceed 3 seconds.
4.2.8. Gas drying
Exhaust gases may be measured wet or dry. A gas-drying device, if used, shall have a minimal effect on the
composition of the measured gases. Chemical dryers are not permitted.
4.3. Additional requirements
4.3.1. General
The provisions in paragraphs 4.3.2. to 4.3.5. define additional performance requirements for specific analyser types
and apply only to cases in which the analyser under consideration is used for RDE emission measurements.
4.3.2. Efficiency test for NOX converters
If a NO converter is applied, for example to convert NO into NO for analysis with a chemiluminescence analyser,
X 2
its efficiency shall be tested by following the requirements in paragraph 5.5. of Annex B5 to UN Regulation No. 154
on WLTP. The efficiency of the NO converter shall be verified no longer than one month before the emissions test.
X
4.3.3. Adjustment of the Flame Ionisation Detector (FID)
(a) Optimization of the detector response
If hydrocarbons are measured, the FID shall be adjusted as specified by the instrument manufacturer by
following paragraph 5.4.1. of Annex B5 to UN Regulation No. 154 on WLTP. A propane-in-air or propane-in-
nitrogen span gas shall be used to optimize the response in the most common operating range.
(b) Hydrocarbon response factors
If hydrocarbons are measured, the hydrocarbon response factor of the FID shall be verified by following the
provisions of paragraph 5.4.3. of Annex B5 to UN Regulation No. 154 on WLTP, using propane-in-air or
propane-in-nitrogen as span gases and purified synthetic air or nitrogen as zero gases, respectively.
(c) Oxygen interference check
The oxygen interference check shall be performed when introducing a FID into service and after major
maintenance intervals. A measuring range shall be chosen in which the oxygen interference check gases fall in
the upper 50 per cent. The test shall be conducted with the oven temperature set as required. The specifications
of the oxygen interference check gases are described in paragraph 5.3.
The following procedure applies:
(i) The analyser shall be set at zero;
(ii) The analyser shall be spanned with a 0 per cent oxygen blend for positive ignition engines and a 21 per
cent oxygen blend for compression ignition engines;
(iii) The zero response shall be rechecked. If it has changed by more than 0.5 per cent of full scale, steps (i) and
(ii) shall be repeated;
(iv) The 5 per cent and 10 per cent oxygen interference check gases shall be introduced;
(v) The zero response shall be rechecked. If it has changed by more than ±1 per cent of full scale, the test shall
be repeated;
56/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
(vi) The oxygen interference E [%] shall be calculated for each oxygen interference check gas in step (iv) as
O2
follows:
E
¼ðcref;d – cÞ
×100
O2 cref;d
where the analyser response is:
c¼ðcref;d×cFS;bÞ ×cm;d
cm;b cFS;d
where:
c is the reference HC concentration in step (ii) [ppmC ]
ref, 1
b
c is the reference HC concentration in step (iv) [ppmC ]
ref, 1
d
c is the full scale HC concentration in step (ii) [ppmC ]
FS,b 1
c is the full scale HC concentration in step (iv) [ppmC ]
FS,d 1
c is the measured HC concentration in step (ii) [ppmC ]
m,b 1
c is the measured HC concentration in step (iv) [ppmC ]
m,d 1
(vii) The oxygen interference E shall be less than ±1,5 per cent for all required oxygen interference check
O2
gases.
(viii) If the oxygen interference E is higher than ±1,5 per cent, corrective action may be taken by
O2
incrementally adjusting the air flow (above and below the manufacturer's specifications), the fuel flow
and the sample flow.
(ix) The oxygen interference check shall be repeated for each new setting.
4.3.4. Conversion efficiency of the non-methane cutter (NMC)
If hydrocarbons are analysed, a NMC can be used to remove non-methane hydrocarbons from the gas sample by
oxidizing all hydrocarbons except methane. Ideally, the conversion for methane is 0 per cent and for the other
hydrocarbons, represented by ethane, is 100 per cent. For the accurate measurement of NMHC, the two efficiencies
shall be determined and used for the calculation of the NMHC emissions (see paragraph 6.2. of Annex 7). It is not
necessary to determine the methane conversion efficiency in the case where the NMC-FID is calibrated according to
method (b) in paragraph 6.2. of Annex 7 by passing the methane/air calibration gas through the NMC.
(a) Methane conversion efficiency
Methane calibration gas shall be flowed through the FID with and without bypassing the NMC; the two
concentrations shall be recorded. The methane efficiency shall be determined as:
E ¼1 –
cHCðw=NMCÞ
M cHCðw=oNMCÞ
where:
c is the HC concentration with CH flowing through the NMC [ppmC ]
HC(w/NMC) 4 1
c is the HC concentration with CH bypassing the NMC [ppmC ]
HC(w/o NMC) 4 1
(b) Ethane conversion efficiency
Ethane calibration gas shall be flowed through the FID with and without bypassing the NMC; the two
concentrations shall be recorded. The ethane efficiency shall be determined as:
E ¼1 –
cHCðw=NMCÞ
E cHCðw=oNMCÞ
ELI: http://data.europa.eu/eli/reg/2024/211/oj 57/98EN
OJ L, 12.1.2024
where:
c is the HC concentration with C H flowing through the NMC [ppmC ]
HC(w/NMC) 2 6 1
c is the HC concentration with C H bypassing the NMC [ppmC ]
HC(w/o NMC) 2 6 1
4.3.5. Interference effects
(a) General
Other gases than the ones being analysed can affect the analyser reading. A check for interference effects and the
correct functionality of analysers shall be performed by the analyser manufacturer prior to market introduction
at least once for each type of analyser or device addressed in paragraphs 4.3.5. (b) to (f).
(b) CO analyser interference check
Water and CO can interfere with the measurements of the CO analyser. Therefore, a CO span gas, having a
2 2
concentration of 80 to 100 per cent of the full scale of the maximum operating range of the CO analyser used
2
during the test, shall be bubbled through water at room temperature and the analyser response recorded. The
analyser response shall not be more than 2 per cent of the mean CO concentration expected during normal
on-road testing or ± 50 ppm, whichever is larger. The interference check for H O and CO may be run as
2 2
separate procedures. If the H O and CO levels used for the interference check are higher than the maximum
2 2
levels expected during the test, each observed interference value shall be scaled down by multiplying the
observed interference with the ratio of the maximum expected concentration value during the test and the
actual concentration value used during this check. Separate interference checks with concentrations of H O
2
that are lower than the maximum concentration expected during the test may be run and the observed H O
2
interference shall be scaled up by multiplying the observed interference with the ratio of the maximum H O
2
concentration value expected during the test and the actual concentration value used during this check. The
sum of the two scaled interference values shall meet the tolerance specified in this point.
(c) NO analyser quench check
X
The two gases of concern for CLD and HCLD analysers are CO and water vapour. The quench response to these
2
gases is proportional to the gas concentrations. A test shall determine the quench at the highest concentrations
expected during the test. If the CLD and HCLD analysers use quench compensation algorithms that utilize H O
2
or CO measurement analysers or both, quench shall be evaluated with these analysers active and with the
2
compensation algorithms applied.
(i) CO quench check
2
A CO span gas having a concentration of 80 to 100 per cent of the maximum operating range shall be
2
passed through the NDIR analyser; the CO value shall be recorded as A. The CO span gas shall then be
2 2
diluted by approximately 50 per cent with NO span gas and passed through the NDIR and CLD or HCLD;
the CO and NO values shall be recorded as B and C, respectively. The CO gas flow shall then be shut off
2 2
and only the NO span gas shall be passed through the CLD or HCLD; the NO value shall be recorded as D.
The per cent quench shall be calculated as:
h i
E ¼ 1 – ð C×A Þ ×100
CO2 ðD×AÞ – ðD×BÞ
where:
A is the undiluted CO concentration measured with the NDIR [%]
2
B is the diluted CO concentration measured with the NDIR [%]
2
C is the diluted NO concentration measured with the CLD or HCLD [ppm]
D is the undiluted NO concentration measured with the CLD or HCLD [ppm]
58/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
Alternative methods of diluting and quantifying of CO and NO span gas values such as
2
dynamic mixing/blending are permitted upon approval of the approval authority.
(ii) Water quench check
This check applies to measurements of wet gas concentrations only. The calculation of water quench shall
consider dilution of the NO span gas with water vapour and the scaling of the water vapour concentration
in the gas mixture to concentration levels that are expected to occur during an emissions test. A NO span
gas having a concentration of 80 per cent to 100 per cent of full scale of the normal operating range shall
be passed through the CLD or HCLD; the NO value shall be recorded as D. The NO span gas shall then be
bubbled through water at room temperature and passed through the CLD or HCLD; the NO value shall be
recorded as C. The analyser's absolute operating pressure and the water temperature shall be determined
b
and recorded as E and F, respectively. The mixture's saturation vapour pressure that corresponds to the
water temperature of the bubbler F shall be determined and recorded as G. The water vapour
concentration H [%] of the gas mixture shall be calculated as:
H ¼G × 100
E
The expected concentration of the diluted NO-water vapour span gas shall be recorded as D after being
e
calculated as:
D ¼D × ð1 – HÞ
e 100
For diesel exhaust, the maximum concentration of water vapour in the exhaust gas (in per cent) expected
during the test shall be recorded as H after being estimated, under the assumption of a fuel H/C ratio of
m
1.8/1, from the maximum CO concentration in the exhaust gas A as follows:
2
H ¼0;9 × A
m
The per cent water quench shall be calculated as:
E ¼ðDe – CbÞ × ðHmÞ × 100
H2O De H
where:
D is the expected diluted NO concentration [ppm]
e
C is the measured diluted NO concentration [ppm]
b
H is the maximum water vapour concentration [%]
m
H is the actual water vapour concentration [%]
(iii) Maximum allowable quench
The combined CO and water quench shall not exceed 2 per cent of full scale.
2
(d) Quench check for NDUV analysers
Hydrocarbons and water can positively interfere with NDUV analysers by causing a response similar to that of
NO . The manufacturer of the NDUV analyser shall use the following procedure to verify that quench effects
X
are limited:
(i) The analyser and chiller shall be set up by following the operating instructions of the manufacturer;
adjustments should be made as to optimise the analyser and chiller performance.
(ii) A zero calibration and span calibration at concentration values expected during emissions testing shall be
performed for the analyser.
(iii) A NO calibration gas shall be selected that matches as far as possible the maximum NO concentration
2 2
expected during emissions testing.
(iv) The NO calibration gas shall overflow at the gas sampling system's probe until the NO response of the
2 X
analyser has stabilised.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 59/98EN
OJ L, 12.1.2024
(v) The mean concentration of the stabilized NO recordings over a period of 30 s shall be calculated and
X
recorded as NO .
X,ref
(vi) The flow of the NO calibration gas shall be stopped and the sampling system saturated by overflowing
2
with a dew point generator's output, set at a dew point of 50 °C. The dew point generator's output shall
be sampled through the sampling system and chiller for at least 10 minutes until the chiller is expected to
be removing a constant rate of water.
(vii) Upon completion of (vi), the sampling system shall again be overflown by the NO calibration gas used to
2
establish NO until the total NO response has stabilized.
X,ref X
(viii) The mean concentration of the stabilized NO recordings over a period of 30 s shall be calculated and
X
recorded as NO .
X,m
(ix) NO shall be corrected to NO based upon the residual water vapour that passed through the chiller
X,m X,dry
at the chiller's outlet temperature and pressure.
The calculated NO shall at least amount to 95 per cent of NO .
X,dry X,ref
(e) Sample dryer
A sample dryer removes water, which can otherwise interfere with the NO measurement. For dry CLD
X
analysers, it shall be demonstrated that at the highest expected water vapour concentration H the sample
m
dryer maintains the CLD humidity at ≤ 5 g water/kg dry air (or about 0,8 per cent H O), which is 100 per cent
2
relative humidity at 3,9 °C and 101,3 kPa or about 25 per cent relative humidity at 25 °C and 101,3 kPa.
Compliance may be demonstrated by measuring the temperature at the outlet of a thermal sample dryer or by
measuring the humidity at a point just upstream of the CLD. The humidity of the CLD exhaust might also be
measured as long as the only flow into the CLD is the flow from the sample dryer.
(f) Sample dryer NO penetration
2
Liquid water remaining in an improperly designed sample dryer can remove NO from the sample. If a sample
2
dryer is used in combination with a NDUV analyser without an NO /NO converter upstream, water could
2
therefore remove NO from the sample prior to the NO measurement. The sample dryer shall allow for
2 X
measuring at least 95 per cent of the NO contained in a gas that is saturated with water vapour and consists of
2
the maximum NO concentration expected to occur during emission testing.
2
4.4. Response time check of the analytical system
For the response time check, the settings of the analytical system shall be exactly the same as during the emissions
test (i.e. pressure, flow rates, filter settings in the analysers and all other parameters influencing the response time).
The response time shall be determined with gas switching directly at the inlet of the sample probe. The gas
switching shall be done in less than 0,1 second. The gases used for the test shall cause a concentration change of at
least 60 per cent full scale of the analyser.
The concentration trace of each single gas component shall be recorded.
For time alignment of the analyser and exhaust flow signals, the transformation time is defined as the time from the
change (t ) until the response is 50 per cent of the final reading (t ).
0 50
The system response time shall be ≤ 12 s with a rise time of ≤ 3 seconds for all components and all ranges used.
When using a NMC for the measurement of NMHC, the system response time may exceed 12 seconds.
5. Gases
5.1. Calibration and span gases for RDE tests
5.1.1. General
The shelf life of calibration and span gases shall be respected. Pure as well as mixed calibration and span gases shall
fulfil the specifications of Annex B5 of UN Regulation No. 154 on WLTP.
60/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
5.1.2. NO calibration gas
2
In addition, NO calibration gas is permissible. The concentration of the NO calibration gas shall be within two per
2 2
cent of the declared concentration value. The amount of NO contained in the NO calibration gas shall not exceed 5
2
per cent of the NO content.
2
5.1.3. Multicomponent mixtures
Only multicomponent mixtures which fulfil the requirements of paragraph 5.1.1. shall be used. These mixtures may
contain two or more of the components. Multicomponent mixtures containing both NO and NO are exempted of
2
the NO impurity requirement set out in paragraphs 5.1.1. and 5.1.2.
2
5.2. Gas dividers
Gas dividers (i.e., precision blending devices that dilute with purified N or synthetic air) can be used to obtain
2
calibration and span gases. The accuracy of the gas divider shall be such that the concentration of the blended
calibration gases is accurate to within ± 2 per cent. The verification shall be performed at between 15 and 50 per
cent of full scale for each calibration incorporating a gas divider. An additional verification may be performed using
another calibration gas, if the first verification has failed.
Optionally, the gas divider may be checked with an instrument which by nature is linear, e.g. using NO gas in
combination with a CLD. The span value of the instrument shall be adjusted with the span gas directly connected to
the instrument. The gas divider shall be checked at the settings typically used and the nominal value shall be
compared with the concentration measured by the instrument. The difference shall in each point be within ±1 per
cent of the nominal concentration value.
5.3. Oxygen interference check gases
Oxygen interference check gases consist of a blend of propane, oxygen and nitrogen and shall contain propane at a
concentration of 350 ± 75 ppmC . The concentration shall be determined by gravimetric methods, dynamic
1
blending or the chromatographic analysis of total hydrocarbons plus impurities. The oxygen concentrations of the
oxygen interference check gases shall meet the requirements listed in Table A5/3; the remainder of the oxygen
interference check gas shall consist of purified nitrogen.
Table A5/3
Oxygen interference check gases
Engine type
Compression ignition Positive ignition
O concentration 21± 1% 10± 1%
2
10± 1% 5± 1%
5± 1% 0,5± 0,5%
6. Analysers for measuring (solid) particle emissions
This section will define future requirement for analysers for measuring particle number emissions, once their
measurement becomes mandatory.
6.1. General
The PN analyser shall consist of a pre-conditioning unit and a particle detector that counts with 50 per cent
efficiency from approximately 23 nm. It is permissible that the particle detector also pre-conditions the aerosol.
The sensitivity of the analysers to shocks, vibration, aging, variability in temperature and air pressure as well as
electromagnetic interferences and other impacts related to vehicle and analyser operation shall be limited as far as
possible and shall be clearly stated by the equipment manufacturer in its support material. The PN analyser shall
only be used within its manufacturer’s declared parameters of operation. An example of a PN analyser setup is
provided in Figure A5/1.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 61/98EN
OJ L, 12.1.2024
Figure A5/1
Example of a PN analyser setup
(Dotted lines depict optional parts. EFM = Exhaust mass Flow Meter, d = inner diameter, PND = Particle Number Diluter)
The PN analyser shall be connected to the sampling point via a sampling probe which extracts a sample from the
centreline of the tailpipe tube. As specified in paragraph 3.5. of Annex 4, if particles are not diluted at the tailpipe,
the sampling line shall be heated to a minimum temperature of 373 K (100 °C) until the point of first dilution of
the PN analyser or the particle detector of the analyser. The residence time in the sampling line shall be less than 3 s.
All parts in contact with the sampled exhaust gas shall be always kept at a temperature that avoids condensation of
any compound in the device. This can be achieved for example by heating at a higher temperature and diluting the
sample or oxidizing the (semi)volatile species.
The PN analyser shall include a heated section at wall temperature ≥ 573 K. The unit shall control the heated stages
to constant nominal operating temperatures, within a tolerance of ± 10 K, and provide an indication of whether or
not heated stages are at their correct operating temperatures. Lower temperatures are acceptable as long as the
volatile particle removal efficiency fulfils the specifications of paragraph 6.4.
Pressure, temperature and other sensors shall monitor the proper operation of the instrument during operation and
trigger a warning or message in case of malfunction.
The delay time of the PN analyser shall be ≤ 5 s.
The PN analyser (and/or particle detector) shall have a rise time of ≤ 3,5 s.
Particle concentration measurements shall be reported normalised to 273 K and 101,3 kPa. If necessary, the
pressure and/or temperature at the inlet of the detector shall be measured and reported for the purposes of
normalizing the particle concentration.
PN systems that comply with the calibration requirements of UN Regulation Nos 83 or 49 or UN Regulation No.
154 on WLTP automatically comply with the calibration requirements of this annex.
6.2. Efficiency requirements
The complete PN analyser system including the sampling line shall fulfil the efficiency requirements of Table A5/3a.
62/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
Table A5/3a
PN analyser (including the sampling line) system efficiency requirements
d [nm] Sub-23 23 30 50 70 100 200
p
E(d ) PN analyser To be determined 0,2– 0,6 0,3– 1,2 0,6– 1,3 0,7– 1,3 0,7– 1,3 0,5– 2,0
p
Efficiency E(d ) is defined as the ratio in the readings of the PN analyser system to a reference Condensation Particle
p
Counter (CPC)’s (d = 10 nm or lower, checked for linearity and calibrated with an electrometer) or an
50 %
Electrometer’s number concentration measuring in parallel monodisperse aerosol of mobility diameter d and
p
normalized at the same temperature and pressure conditions.
The material should be thermally stable soot-like (e.g. spark discharged graphite or diffusion flame soot with
thermal pre-treatment). If the efficiency curve is measured with a different aerosol (e.g. NaCl), the correlation to the
soot-like curve must be provided as a chart which compares the efficiencies obtained using both test aerosols. The
differences in the counting efficiencies shall be taken into account by adjusting the measured efficiencies based on
the provided chart to give soot-like aerosol efficiencies. The correction for multiply charged particles shall be
applied and documented but shall not exceed 10 per cent. These efficiencies refer to the PN analysers with the
sampling line. The PN analyser can also be calibrated in parts (i.e. the pre-conditioning unit separately from the
particle detector) as long as it is proven that the PN analyser and the sampling line together fulfil the requirements
of Table A5/3a. The measured signal from the detector shall be > 2 times the limit of detection (here defined as the
zero level plus 3 standard deviations).
6.3. Linearity requirements
The PN analyser including the sampling line shall fulfil the linearity requirements of paragraph 3.2. of Annex 5
using monodisperse or polydisperse soot-like particles. The particle size (mobility diameter or count median
diameter) shall be larger than 45 nm. The reference instrument shall be an Electrometer or a Condensation Particle
Counter (CPC) with d = 10 nm or lower, verified for linearity. Alternatively, a particle number system compliant
50
with UN Regulation No. 154 on WLTP.
In addition, the differences of the PN analyser from the reference instrument at all points checked (except the zero
point) shall be within 15 per cent of their mean value. At least 5 points equally distributed (plus the zero) shall be
checked. The maximum checked concentration shall be > 90 per cent of the PN analyser nominal measurement
range.
If the PN analyser is calibrated in parts, then the linearity can be checked only for the PN detector, but the efficiencies
of the rest parts and the sampling line shall be considered in the slope calculation.
6.4. Volatile removal efficiency
The system shall achieve > 99 per cent removal of ≥ 30 nm tetracontane (CH (CH ) CH ) particles with an inlet
3 238 3
concentration of ≥ 10 000particles per cubic-centimetre at the minimum dilution.
The system shall also achieve a > 99 per cent removal efficiency of tetracontane with count median diameter > 50
nm and mass > 1 mg/m3.
The volatile removal efficiency with tetracontane shall be proven only once for the instrument family. The
instrument manufacturer though shall provide the maintenance or replacement interval that ensures that the
removal efficiency does not drop below the technical requirements. If such information is not provided, the volatile
removal efficiency shall be checked yearly for each instrument.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 63/98EN
OJ L, 12.1.2024
7. Instruments for measuring exhaust mass flow
7.1. General
Instruments or signals for measuring the exhaust mass flow rate shall have a measuring range and response time
appropriate for the accuracy required to measure the exhaust mass flow rate under transient and steady state
conditions. The sensitivity of instruments and signals to shocks, vibration, aging, variability in temperature,
ambient air pressure, electromagnetic interferences and other impacts related to vehicle and instrument operation
shall be on a level as to eliminate additional errors.
7.2. Instrument specifications
The exhaust mass flow rate shall be determined by a direct measurement method applied in either of the following
instruments:
(a) Pitot-based flow devices;
(b) Pressure differential devices like flow nozzle (details see ISO 5167);
(c) Ultrasonic flow meter;
(d) Vortex flow meter.
Each individual exhaust mass flow meter shall fulfil the linearity requirements set out in paragraph 3. Furthermore,
the instrument manufacturer shall demonstrate the compliance of each type of exhaust mass flow meter with the
specifications in paragraphs 7.2.3. to 7.2.9.
It is permissible to calculate the exhaust mass flow rate based on air flow and fuel flow measurements obtained
from sensors with traceable calibration if these fulfil the linearity requirements of paragraph 3., the accuracy
requirements of paragraph 8. and if the resulting exhaust mass flow rate is validated according to paragraph 4. of
Annex 6.
In addition, other methods that determine the exhaust mass flow rate based on non-traceable instruments and
signals, such as simplified exhaust mass flow meters or ECU signals, are permissible if the resulting exhaust mass
flow rate fulfils the linearity requirements of paragraph 3. and is validated according to paragraph 4. of Annex 6.
7.2.1. Calibration and verification standards
The measurement performance of exhaust mass flow meters shall be verified with air or exhaust gas against a
traceable standard such as a calibrated exhaust mass flow meter or a full flow dilution tunnel.
7.2.2. Frequency of verification
The compliance of exhaust mass flow meters with paragraphs 7.2.3. to 7.2.9. shall be verified no longer than one
year before the actual test.
7.2.3. Accuracy
The accuracy of the EFM, defined as the deviation of the EFM reading from the reference flow value, shall not exceed
± 3 per cent of the reading, or 0.3 per cent of full scale, whichever is larger.
7.2.4. Precision
The precision, defined as 2.5 times the standard deviation of 10 repetitive responses to a given nominal flow,
approximately in the middle of the calibration range, shall not exceed 1 per cent of the maximum flow at which
the EFM has been calibrated.
7.2.5. Noise
The noise shall not exceed 2 per cent of the maximum calibrated flow value. Each of the 10 measurement periods
shall be interspersed with an interval of 30 seconds in which the EFM is exposed to the maximum calibrated flow.
64/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
7.2.6. Zero response drift
The zero response drift is defined as the mean response to zero flow during a time interval of at least 30 seconds.
The zero response drift can be verified based on the reported primary signals, e.g., pressure. The drift of the
primary signals over a period of 4 hours shall be less than ±2 per cent of the maximum value of the primary signal
recorded at the flow at which the EFM was calibrated.
7.2.7. Span response drift
The span response drift is defined as the mean response to a span flow during a time interval of at least 30 seconds.
The span response drift can be verified based on the reported primary signals, e.g., pressure. The drift of the primary
signals over a period of 4 hours shall be less than ± 2 per cent of the maximum value of the primary signal recorded
at the flow at which the EFM was calibrated.
7.2.8. Rise time
The rise time of the exhaust flow instruments and methods should match as far as possible the rise time of the gas
analysers as specified in paragraph 4.2.7. but shall not exceed 1 second.
7.2.9. Response time check
The response time of exhaust mass flow meters shall be determined by applying similar parameters as those applied
for the emissions test (i.e., pressure, flow rates, filter settings and all other response time influences). The response
time determination shall be done with gas switching directly at the inlet of the exhaust mass flow meter. The gas
flow switching shall be done as fast as possible, but in less than 0,1 second is highly recommended. The gas flow
rate used for the test shall cause a flow rate change of at least 60 per cent full scale of the exhaust mass flow meter.
The gas flow shall be recorded. The delay time is defined as the time from the gas flow switching (t ) until the
0
response is 10 per cent (t ) of the final reading. The rise time is defined as the time between 10 per cent and 90
10
per cent response (t to t ) of the final reading. The response time (t ) is defined as the sum of the delay time and
10 90 90
the rise time. The exhaust mass flow meter response time (t ) shall be ≤ 3 seconds with a rise time (t to t ) of ≤ 1
90 10 90
second in accordance with paragraph 7.2.8.
8. Sensors and auxiliary equipment
Any sensor or auxiliary equipment used to determine temperature, atmospheric pressure, ambient humidity, vehicle
speed, fuel flow or intake air flow, for example, shall not alter or unduly affect the performance of the vehicle’s
engine and exhaust after-treatment system. The accuracy of sensors and auxiliary equipment shall fulfil the
requirements of Table A5/4. Compliance with the requirements of Table A5/4 shall be demonstrated at intervals
specified by the instrument manufacturer, as required by internal audit procedures or in accordance with ISO 9000.
Table A5/4
Accuracy requirements for measurement parameters
Measurement parameter Accuracy
Fuel flow(1) ± 1 % of reading(2)
Air flow(3) ± 2 % of reading
Vehicle speed(4) ± 1,0 km/h absolute
Temperatures ≤ 600 K ± 2 K absolute
Temperatures > 600 K ± 0,4 % of reading in Kelvin
Ambient pressure ± 0,2 kPa absolute
Relative humidity ± 5 % absolute
Absolute humidity ± 10 % of reading or, 1 gH O/kg dry air, whichever is larger
2
ELI: http://data.europa.eu/eli/reg/2024/211/oj 65/98EN
OJ L, 12.1.2024
(1) Optional to determine exhaust mass flow.
(2) The accuracy shall be 0,02 per cent of reading if used to calculate the air and exhaust mass flow rate from the fuel flow
according to paragraph 7 of Annex 7.
(3) Optional to determine exhaust mass flow.
(4) This requirement applies to the speed sensor only; if vehicle speed is used to determine parameters like acceleration, the
product of speed and positive acceleration, or RPA, the speed signal shall have an accuracy of 0,1 % above 3 km/h and a
sampling frequency of 1 Hz. This accuracy requirement can be met by using a wheel rotational speed signal.
66/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
ANNEX 6
Validation of PEMS and non-traceable exhaust mass flow rate
1. Introduction
This annex describes the requirements to validate under transient conditions the functionality of the installed PEMS
as well as the correctness of the exhaust mass flow rate obtained from non-traceable exhaust mass flow meters or
calculated from ECU signals.
2. Symbols, Parameters and Units
a — y intercept of the regression line
0
a — slope of the regression line
1
r2 — coefficient of determination
x — actual value of the reference signal
y — actual value of the signal under validation
3. Validation procedure for PEMS
3.1. Frequency of PEMS validation
It is recommended to validate the correct installation of a PEMS on a vehicle via comparison with laboratory
installed equipment on a test performed on a chassis dynamometer either before the RDE test or, alternatively, after
the completion of the test. For tests performed during type approval, the validation test is required.
3.2. PEMS validation procedure
3.2.1. PEMS installation
The PEMS shall be installed and prepared according to the requirements of Annex 4. The PEMS installation shall be
kept unchanged in the time period between the validation and the RDE test.
3.2.2. Test conditions
The validation test shall be conducted on a chassis dynamometer, as far as possible, under type approval conditions
by following the requirements of UN Regulation No. 154 on WLTP for a 4-phase cycle. It is recommended to feed
the exhaust flow extracted by the PEMS during the validation test back to the CVS. If this is not feasible, the CVS
results shall be corrected for the extracted exhaust mass. If the exhaust mass flow rate is validated with an exhaust
mass flow meter, it is recommended to cross-check the mass flow rate measurements with data obtained from a
sensor or the ECU.
3.2.3. Data analysis
The total distance-specific emissions [g/km] measured with laboratory equipment shall be calculated in accordance
with UN Regulation No. 154 on WLTP. The emissions as measured with the PEMS shall be calculated according to
Annex 7, summed to give the total mass of pollutants [g] and then divided by the test distance [km] as obtained
from the chassis dynamometer. The total distance-specific mass of pollutants [g/km], as determined by the PEMS
and the reference laboratory system, shall be evaluated against the requirements specified in paragraph 3.3. For the
validation of NO emission measurements, humidity correction shall be applied in accordance with UN Regulation
X
No. 154 on WLTP.
3.3. Permissible tolerances for PEMS validation
The PEMS validation results shall fulfil the requirements given in Table A6/1. If any permissible tolerance is not met,
corrective action shall be taken and the PEMS validation shall be repeated.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 67/98EN
OJ L, 12.1.2024
Table A6/1
Permissible tolerances
Parameter [Unit] Permissible absolute tolerance
Distance [km](1) 250 m of the laboratory reference
THC(2)[mg/km] 15 mg/km or 15 % of the laboratory reference, whichever is larger
CH42 [mg/km] 15 mg/km or 15 % of the laboratory reference, whichever is larger
NMHC2 [mg/km] 20 mg/km or 20 % of the laboratory reference, whichever is larger
PN2 [#/km] 8 × 1010 p/km or 42 % of the laboratory reference(3)whichever is larger
CO2 [mg/km] 100 mg/km or 15 % of the laboratory reference, whichever is larger
CO [g/km] 10 g/km or 7,5 % of the laboratory reference, whichever is larger
2
NO 2 [mg/km] 10 mg/km or 12,5 % of the laboratory reference, whichever is larger
X
(1) Only applicable if vehicle speed is determined by the ECU; to meet the permissible tolerance it is permitted to adjust the ECU
vehicle speed measurements based on the outcome of the validation test.
(2) Parameter only mandatory if measurement required for compliance with the limits.
(3) PN measurement equipment in accordance with Annex B5 of UN Regulation No 154.
4. Validation procedure for the exhaust mass flow rate determined by non-traceable instruments and sensors
4.1. Frequency of validation
In addition to fulfilling the linearity requirements of paragraph 3. of Annex 5 under steady-state conditions, the
linearity of non-traceable exhaust mass flow meters or the exhaust mass flow rate calculated from non-traceable
sensors or ECU signals shall be validated under transient conditions for each test vehicle against a calibrated
exhaust mass flow meter or the CVS.
4.2. Validation procedure
The validation shall be conducted on a chassis dynamometer under type approval conditions, as far as applicable on
the same vehicle used for the RDE test. As reference, a flow meter with traceable calibration shall be used. The
ambient temperature can be any within the range specified in paragraph 8.1. of this Regulation. The installation of
the exhaust mass flow meter and the execution of the test shall fulfil the requirement of paragraph 3.4.3. of
Annex 4.
The following calculation steps shall be taken to validate the linearity:
(a) The signal under validation and the reference signal shall be time corrected by following, as far as applicable, the
requirements of paragraph 3. of Annex 7.
(b) Points below 10 per cent of the maximum flow value shall be excluded from the further analysis.
(c) At a constant frequency of at least 1,0 Hz, the signal under validation and the reference signal shall be correlated
using the best-fit equation having the form:
y¼axþa
1 0
68/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
where:
y is the actual value of the signal under validation
a is the slope of the regression line
1
x is the actual value of the reference signal
a is the y intercept of the regression line
0
The standard error of estimate (SEE) of y on x and the coefficient of determination (r2) shall be calculated for each
measurement parameter and system.
(d) The linear regression parameters shall meet the requirements specified in Table A6/2.
4.3. Requirements
The linearity requirements given in Table A6/2 shall be fulfilled. If any permissible tolerance is not met, corrective
action shall be taken and the validation shall be repeated.
Table A6/2
Linearity requirements of calculated and measured exhaust mass flow
Coefficient of
Measurement Standard error of the
a Slope a determination
parameter/system 0 1 estimate SEE
r2
Exhaust mass flow 0,0± 3,0kg/h 1,00± 0,075 ≤ 10% max ≥ 0,90
ELI: http://data.europa.eu/eli/reg/2024/211/oj 69/98EN
OJ L, 12.1.2024
ANNEX 7
Determination of instantaneous emissions
1. Introduction
This annex describes the procedure to determine the instantaneous mass and particle number emissions [g/s; #/s],
following application of the data consistency rules of Annex 4. The instantaneous mass and particle number
emissions shall then be used for the subsequent evaluation of a RDE trip and the calculation of the intermediate
and final emission result as described in Annex 11.
2. Symbols, Parameters and Units
α — molar hydrogen ratio (H/C)
β — molar carbon ratio (C/C)
γ — molar sulphur ratio (S/C)
δ — molar nitrogen ratio (N/C)
Δt — transformation time t of the analyser [s]
t,i
Δt — transformation time t of the exhaust mass flow meter [s]
t,m
ε — molar oxygen ratio (O/C)
ρ — density of the exhaust
e
ρ — density of the exhaust component ‘gas’
gas
λ — excess air ratio
λ — instantaneous excess air ratio
i
A/F — stoichiometric air-to-fuel ratio [kg/kg]
st
c — concentration of methane
CH4
c — dry CO concentration [%]
CO
c — dry CO concentration [%]
CO2 2
c — dry concentration of a pollutant in ppm or per cent volume
dry
c — instantaneous concentration of the exhaust component ‘gas’ [ppm]
gas,i
c — wet HC concentration [ppm]
HCw
c — HC concentration with CH or C H flowing through the NMC [ppmC ]
HC(w/NMC) 4 2 6 1
c — HC concentration with CH or C H bypassing the NMC [ppmC ]
HC(w/oNMC) 4 2 6 1
c — time-corrected concentration of component i [ppm]
i,c
c — concentration of component i [ppm] in the exhaust
i,r
c — concentration of non-methane hydrocarbons
NMHC
c — wet concentration of a pollutant in ppm or per cent volume
wet
E — ethane efficiency
E
E — methane efficiency
M
H — intake air humidity [g water per kg dry air]
a
i — number of the measurement
m — mass of the exhaust component ‘gas’ [g/s]
gas,i
q — instantaneous intake air mass flow rate [kg/s]
maw,i
70/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
q — time-corrected exhaust mass flow rate [kg/s]
m,c
q — instantaneous exhaust mass flow rate [kg/s]
mew,i
q — instantaneous fuel mass flow rate [kg/s]
mf,i
q — raw exhaust mass flow rate [kg/s]
m,r
r — cross-correlation coefficient
r2 — coefficient of determination
r — hydrocarbon response factor
h
u — u value of the exhaust component ‘gas’
gas
3. Time correction of parameters
For the correct calculation of distance-specific emissions, the recorded traces of component concentrations, exhaust
mass flow rate, vehicle speed, and other vehicle data shall be time corrected. To facilitate the time correction, data
which are subject to time alignment shall be recorded either in a single data recording device or with a
synchronised timestamp following paragraph 5.1. of Annex 4. The time correction and alignment of parameters
shall be carried out by following the sequence described in paragraphs 3.1. to 3.3.
3.1. Time correction of component concentrations
The recorded traces of all component concentrations shall be time corrected by reverse shifting according to the
transformation times of the respective analysers. The transformation time of analysers shall be determined
according to paragraph 4.4. of Annex 5:
c ðt – Δt Þ¼c ðtÞ
i;c t;i i;r
where:
c is the time-corrected concentration of component i as function of time t
i,c
c is the raw concentration of component i as function of time t
i,r
Δt is the transformation time t of the analyser measuring component i
t,i
3.2. Time correction of exhaust mass flow rate
The exhaust mass flow rate measured with an exhaust flow meter shall be time corrected by reverse shifting
according to the transformation time of the exhaust mass flow meter. The transformation time of the mass flow
meter shall be determined according to paragraph 4.4. of Annex 5:
q ðt – Δt Þ¼q ðtÞ
m;c t;m m;r
where:
q is the time-corrected exhaust mass flow rate as function of time t
m,c
q is the raw exhaust mass flow rate as function of time t
m,r
Δt is the transformation time t of the exhaust mass flow meter
t,m
In case the exhaust mass flow rate is determined by ECU data or a sensor, an additional transformation time shall be
considered and obtained by cross-correlation between the calculated exhaust mass flow rate and the exhaust mass
flow rate measured following paragraph 4. of Annex 6.
3.3. Time alignment of vehicle data
Other data obtained from a sensor or the ECU shall be time-aligned by cross-correlation with suitable emission data
(e.g., component concentrations).
ELI: http://data.europa.eu/eli/reg/2024/211/oj 71/98EN
OJ L, 12.1.2024
3.3.1. Vehicle speed from different sources
To time align vehicle speed with the exhaust mass flow rate, it is first necessary to establish one valid speed trace. In
case vehicle speed is obtained from multiple sources (e.g., the GNSS, a sensor or the ECU), the speed values shall be
time aligned by cross-correlation.
3.3.2. Vehicle speed with exhaust mass flow rate
Vehicle speed shall be time aligned with the exhaust mass flow rate by cross-correlation between the exhaust mass
flow rate and the product of vehicle speed and positive acceleration.
3.3.3. Further signals
The time alignment of signals whose values change slowly and within a small value range, e.g. ambient temperature,
can be omitted.
4. Emission measurements during stop of the combustion engine
Any instantaneous emissions or exhaust flow measurements obtained while the combustion engine is deactivated
shall be recorded in the data exchange file.
5. Correction of measured values
5.0. Drift correction
c ¼c þðc – c Þð
2cgas – ðcpre;zþcpost;zÞ
Þ
cor ref;z ref;s ref;z
ðcpre;sþcpost;sÞ – ðcpre;zþcpost;zÞ
c is the reference concentration of the zero gas (usually zero) [ppm]
ref,z
c is the reference concentration of the span gas [ppm]
ref,s
c is the pre-test analyser concentration of the zero gas [ppm]
pre,z
c is the pre-test analyser concentration of the span gas [ppm]
pre,s
c is the post-test analyser concentration of the zero gas [ppm]
post,z
c is the post-test analyser concentration of the span gas [ppm]
post,s
c is the sample gas concentration [ppm]
gas
5.1. Dry-wet correction
If the emissions are measured on a dry basis, the measured concentrations shall be converted to a wet basis as:
where:
c ¼k ×c
wet w dry
c is the wet concentration of a pollutant in ppm or per cent volume
wet
c is the dry concentration of a pollutant in ppm or per cent volume
dry
k is the dry-wet correction factor
w
The following equation shall be used to calculate k :
w
k ¼ð 1 – k Þ×1;008
w 1þα×0;005×ðcCO2þcCOÞ w1
where:
k ¼ 1;608×Ha
w1 1000þð1;608×HaÞ
72/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
where:
H is the intake air humidity [g water per kg dry air]
a
c is the dry CO concentration [%]
CO2 2
c is the dry CO concentration [%]
CO
α is the molar hydrogen ratio of the fuel (H/C)
5.2. Correction of NO for ambient humidity and temperature
X
NO emissions shall not be corrected for ambient temperature and humidity.
X
5.3. Correction of negative emission results
Negative instantaneous results shall not be corrected.
6. Determination of the instantaneous gaseous exhaust components
6.1. Introduction
The components in the raw exhaust shall be measured with the measurement and sampling analysers described in
Annex 5. The raw concentrations of relevant components shall be measured in accordance with Annex 4. The data
shall be time corrected and aligned in accordance with paragraph 3 of this annex.
6.2. Calculating NMHC and CH concentrations
4
For methane measurement using a NMC-FID, the calculation of NMHC depends on the calibration gas/method used
for the zero/span calibration adjustment. When a FID is used for THC measurement without a NMC, it shall be
calibrated with propane/air or propane/N in the normal manner. For the calibration of the FID in series with a
2
NMC, the following methods are permitted:
(a) the calibration gas consisting of propane/air bypasses the NMC;
(b) the calibration gas consisting of methane/air passes through the NMC.
It is strongly recommended to calibrate the methane FID with methane/air through the NMC.
In method (a), the concentrations of CH and NMHC shall be calculated as follows:
4
c ¼
cHCðw=oNMCÞ×ð1 – EMÞ – cHCðw=NMCÞ
CH4 EE – EM
c ¼
cHCðw=NMCÞ – cHCðw=oNMCÞ×ð1 – EEÞ
NMHC rh×ðEE – EMÞ
In method (b), the concentration of CH and NMHC shall be calculated as follows:
4
c ¼
cHCðw=NMCÞ×rh×ð1 – EMÞ – cHCðw=oNMCÞ×ð1 – EEÞ
CH4 rh×ðEE – EMÞ
c ¼
cHCðw=oNMCÞ×ð1 – EMÞ – cHCðw=NMCÞ×rh×ð1 – EMÞ
NMHC ðEE – EMÞ
where:
c is the HC concentration with CH or C H bypassing the NMC [ppmC ]
HC(w/oNMC) 4 2 6 1
c is the HC concentration with CH or C H flowing through the NMC [ppmC ]
HC(w/NMC) 4 2 6 1
r is the hydrocarbon response factor as determined in paragraph 4.3.3.(b) of Annex 5
h
E is the methane efficiency as determined in paragraph 4.3.4.(a) of Annex 5
M
E is the ethane efficiency as determined in paragraph 4.3.4.(b) of Annex 5
E
If the methane FID is calibrated through the cutter (method b), then the methane conversion efficiency as
determined in paragraph 4.3.4.(a) of Annex 5 is zero. The density used for calculating the NMHC mass shall be
equal to that of total hydrocarbons at 273,15 K and 101,325 kPa and is fuel-dependent.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 73/98EN
OJ L, 12.1.2024
7. Determination of exhaust mass flow rate
7.1. Introduction
The calculation of instantaneous mass emissions according to paragraphs 8. and 9. requires determining the exhaust
mass flow rate. The exhaust mass flow rate shall be determined by one of the direct measurement methods specified
in paragraph 7.2. of Annex 5. Alternatively, it is permissible to calculate the exhaust mass flow rate as described in
paragraphs 7.2. to 7.4. of this annex.
7.2. Calculation method using air mass flow rate and fuel mass flow rate
The instantaneous exhaust mass flow rate can be calculated from the air mass flow rate and the fuel mass flow rate
as follows:
q ¼q þq
mew;i maw;i mf;i
where:
q is the instantaneous exhaust mass flow rate [kg/s]
mew,i
q is the instantaneous intake air mass flow rate [kg/s]
maw,i
q is the instantaneous fuel mass flow rate [kg/s]
mf,i
If the air mass flow rate and the fuel mass flow rate or the exhaust mass flow rate are determined from ECU
recording, the calculated instantaneous exhaust mass flow rate shall meet the linearity requirements specified for
the exhaust mass flow rate in paragraph 3. of Annex 5 and the validation requirements specified in paragraph 4.3.
of Annex 6.
7.3. Calculation method using air mass flow and air-to-fuel ratio
The instantaneous exhaust mass flow rate can be calculated from the air mass flow rate and the air-to-fuel ratio as
follows:
q ¼q ×ð1þ 1 Þ
mew;i maw;i A=Fst×λi
where:
α ε
138;0×ð1þ 4 – 2þγÞ
A=F ¼
st 12;011þ1;008×αþ15;9994×εþ14;0067×δþ32;0675×γ
ð100 – c CO× 210 – 4 – cHCw×10 – 4Þþðα 4×1
1
–
þ
2 c× C3c O;C 5O × ×c 1× C 01 O –0 2 4– 4 – 2ε – 2δ Þ×ðcCO2þcCO×10 – 4Þ
λ i ¼ 4;764×ð1þα 4 – 2ε þγÞ×ðcCO2þcCO3 ×;5 1×c 0C O –2 4þcHCw×10 – 4Þ
where:
q is the instantaneous intake air mass flow rate [kg/s]
maw,i
A/F is the stoichiometric air-to-fuel ratio [kg/kg]
st
λ is the instantaneous excess air ratio
i
c is the dry CO concentration [%]
CO2 2
c is the dry CO concentration [ppm]
CO
c is the wet HC concentration [ppm]
HCw
α is the molar hydrogen ratio (H/C)
β is the molar carbon ratio (C/C)
γ is the molar sulphur ratio (S/C)
δ is the molar nitrogen ratio (N/C)
ε is the molar oxygen ratio (O/C)
74/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
Coefficients refer to a fuel C H O N S with β = 1 for carbon based fuels. The concentration of HC emissions is
β α ε δ γ
typically low and may be omitted when calculating λ.
i
If the air mass flow rate and air-to-fuel ratio are determined from ECU recording, the calculated instantaneous
exhaust mass flow rate shall meet the linearity requirements specified for the exhaust mass flow rate in
paragraph 3. of Annex 5 and the validation requirements specified in paragraph 4.3. of Annex 6.
7.4. Calculation method using fuel mass flow and air-to-fuel ratio
The instantaneous exhaust mass flow rate can be calculated from the fuel flow and the air-to-fuel ratio (calculated
with A/F and λ according to paragraph 7.3.) as follows:
st i
q ¼q ×ð1þ 1 Þ
mew;i maw;i A=Fst×λi
q ¼q ×ð1þ A=F ×λÞ
mew;i mf;i st i
The calculated instantaneous exhaust mass flow rate shall meet the linearity requirements specified for the exhaust
gas mass flow rate in paragraph 3. of Annex 5 and the validation requirements specified in paragraph 4.3. of
Annex 6.
8. Calculating the instantaneous mass emissions of gaseous components
The instantaneous mass emissions [g/s] shall be determined by multiplying the instantaneous concentration of the
pollutant under consideration [ppm] with the instantaneous exhaust mass flow rate [kg/s], both corrected and
aligned for the transformation time, and the respective u value in Table A7/1. If measured on a dry basis, the dry-
wet correction according to paragraph 5.1. shall be applied to the instantaneous component concentrations before
executing any further calculations. If occurring, negative instantaneous emission values shall enter all subsequent
data evaluations. Parameter values shall enter the calculation of instantaneous emissions [g/s] as reported by the
analyser, flow-measuring instrument, sensor or the ECU. The following equation shall be applied:
m ¼u •c •q
gas;i gas gas;i mew;i
where:
m is the mass of the exhaust component ‘gas’ [g/s]
gas,i
u is the ratio of the density of the exhaust component ‘gas’ and the overall density of the exhaust as listed in
gas
Table A7/1
c is the measured concentration of the exhaust component ‘gas’ in the exhaust [ppm]
gas,i
q is the measured exhaust mass flow rate [kg/s]
mew,i
gas is the respective component
i number of the measurement
Table A7/1
Raw exhaust gas u values depicting the ratio between the densities of exhaust component or pollutant i [kg/m3]
and the density of the exhaust gas [kg/m3]
Component or pollutant i
NO CO HC CO O CH
X 2 2 4
Fuel ρ [kg/m3] ρ [kg/m3]
e gas
2,052 1,249 (a) 1,9630 1,4276 0,715
u (b)(f)
gas
Diesel (B0) 1,2893 0,001593 0,000969 0,000480 0,001523 0,001108 0,000555
Diesel (B5) 1,2893 0,001593 0,000969 0,000480 0,001523 0,001108 0,000555
ELI: http://data.europa.eu/eli/reg/2024/211/oj 75/98EN
OJ L, 12.1.2024
Diesel (B7) 1,2894 0,001593 0,000969 0,000480 0,001523 0,001108 0,000555
Ethanol 1,2768 0,001609 0,000980 0,000780 0,001539 0,001119 0,000561
(ED95)
CNG(c) 1,2661 0,001621 0,000987 0,000528(d) 0,001551 0,001128 0,000565
Propane 1,2805 0,001603 0,000976 0,000512 0,001533 0,001115 0,000559
Butane 1,2832 0,001600 0,000974 0,000505 0,001530 0,001113 0,000558
LPG(e) 1,2811 0,001602 0,000976 0,000510 0,001533 0,001115 0,000559
Petrol (E0) 1,2910 0,001591 0,000968 0,000480 0,001521 0,001106 0,000554
Petrol (E5) 1,2897 0,001592 0,000969 0,000480 0,001523 0,001108 0,000555
Petrol (E10) 1,2883 0,001594 0,000970 0,000481 0,001524 0,001109 0,000555
Ethanol (E85) 1,2797 0,001604 0,000977 0,000730 0,001534 0,001116 0,000559
(a) depending on fuel
(b) at λ = 2, dry air, 273 K, 101,3 kPa
(c) u values accurate within 0,2 % for mass composition of: C=66-76%; H=22-25%; N=0-12%
(d) NMHC on the basis of CH (for THC the u coefficient of CH shall be used)
2.93 gas 4
(e) u accurate within 0,2 % for mass composition of: C =70-90%; C=10-30%
3 4
(f) u is a unitless parameter; the u values include unit conversions to ensure that the instantaneous emissions are obtained in the
gas gas
specified physical unit, i.e., g/s
As an alternative to the above method, emission rates might also be calculated with the method described in Annex
A.7 of GTR 11.
9. Calculating the instantaneous particle number emissions
The instantaneous particle number emissions [particles/s] shall be determined by multiplying the instantaneous
concentration of the pollutant under consideration [particles/cm3] with the instantaneous exhaust mass flow
rate [kg/s], both corrected and aligned for the transformation time and by dividing with the density [kg/m3]
according to Table A7/1. If applicable, negative instantaneous emission values shall enter all subsequent data
evaluations. All significant digits of preceding results shall enter the calculation of the instantaneous emissions. The
following equation shall apply:
PN ¼c q =<1
i PN;i mew;i e
where:
PNi is the particle number flux [particles/s]
c is the measured particle number concentration [#/m3] normalized at 0 °C
PN,
i
q is the measured exhaust mass flow rate [kg/s]
m
ew,i
ρ is the density of the exhaust gas [kg/m3] at 0 °C (Table A7/1)
e
10. Data exchange
Data Exchange: The data shall be exchanged between the measurement systems and the data evaluation software by
a standardised data exchange file found at the same weblink(1)as the UN Regulation.
(1) [link to be inserted after the final notification]
76/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
Any pre-processing of data (e.g. time correction according to paragraph 3 of this annex, vehicle speed correction
according to paragraph 4.7. of Annex 4 or the correction of the GNSS vehicle speed signal according to
paragraph 6.5. of Annex 4) shall be done with the control software of the measurement systems and shall be
completed before the data exchange file is generated.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 77/98EN
OJ L, 12.1.2024
ANNEX 8
Assessment of overall trip validity using the moving averaging window method
1. Introduction
The Moving Averaging Window method shall be used to assess the overall trip dynamics. The test is divided in
sub-sections (windows) and the subsequent analysis aims at determining whether the trip is valid for RDE
purposes. The ‘normality’ of the windows shall be assessed by comparing their CO distance-specific emissions
2
with a reference curve obtained from the vehicle CO emissions measured in accordance with the WLTP test.
2
For compliance with this Regulation, the method shall be applied using the 4-phase and the 3-phase WLTC
requirements.
2. Symbols, Parameters and Units
Index (i) refers to the time step
Index (j) refers to the window
Index (k) refers to the category (t=total, ls=low speed, ms=medium speed, hs=high speed) or to the CO
2
characteristic curve (cc)
a ,b - coefficients of the CO characteristic curve
1 1 2
a ,b - coefficients of the CO characteristic curve
2 2 2
M - CO mass, [g]
CO2 2
M - CO mass in window j, [g]
CO2;j 2
t - total time in step i, [s]
i
t - duration of a test, [s]
t
v - actual vehicle speed in time step i, [km/h]
i
v - average vehicle speed in window j, [km/h]
j
tol - upper tolerance for the vehicle CO characteristic curve, [%]
1H 2
tol - lower tolerance for the vehicle CO characteristic curve, [%]
1L 2
3. Moving averaging windows
3.1. Definition of averaging windows
The instantaneous CO emissions calculated according to Annex 7 shall be integrated using a moving averaging
2
window method, based on a reference CO mass.
2
The usage of the reference CO mass is illustrated in Figure A8/2. The principle of the calculation is as follows: The
2
RDE distance-specific CO mass emissions are not calculated for the complete data set, but for sub-sets of the
2
complete data set, the length of these sub-sets being determined so as to always match the same fraction of the
CO mass emitted by the vehicle over the applicable WLTP test (after all appropriate corrections e.g. ATCT are
2
applied, where relevant). The moving window calculations are conducted with a time increment Δt corresponding
to the data sampling frequency. These sub-sets used to calculate the vehicle on-road CO emissions and its average
2
speed are referred to as ‘averaging windows’ in the following sections. The calculation described in this point shall
be run from the first data point (forward), as shown in Figure A8/1.
The following data shall not be considered for the calculation of the CO mass, the distance and the vehicle
2
average speed in each averaging window:
The periodic verification of the instruments and/or after the zero drift verifications;
Vehicle ground speed < 1 km/h;
The calculation shall start from when vehicle ground speed is higher than or equal to 1 km/h and include driving
events during which no CO is emitted and where the vehicle ground speed is higher than or equal to 1 km/h.
2
78/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
The mass emissions M shall be determined by integrating the instantaneous emissions in g/s as specified in Annex 7.
CO2;j
Figure A8/1
Vehicle speed versus time - Vehicle averaged emissions versus time, starting from the first averaging window
Figure A8/2
Definition of CO mass based on averaging windows
2
The duration ðt – t Þof the jth averaging window is determined by:
2;j 1;j
M ðt Þ – M ðt Þ≥M
CO2 2;j CO2 1;j CO2;ref
Where:
M ðt Þ is the CO mass measured between the test start and time t , [g];
CO2 i;j 2 i,j
M is the reference CO mass (half of the CO mass emitted by the vehicle over the applicable WLTP test).
CO2;ref 2 2
During type approval, the CO mass reference value shall be taken from the WLTP test of the individual vehicle,
2
obtained in accordance with UN Regulation No. 154, including all appropriate corrections.
t shall be selected such as:
2,j
M ðt – ΔtÞ – M ðt Þ<M ≤M ðt Þ – M ðt Þ
CO2 2;j CO2 1;j CO2;ref CO2 2;j CO2 1;j
Where Δtis the data sampling period.
The CO masses M in the windows are calculated by integrating the instantaneous emissions calculated as specified in
2 CO2;j
Annex 7.
ELI: http://data.europa.eu/eli/reg/2024/211/oj 79/98EN
OJ L, 12.1.2024
3.2. Calculation of window parameters
The following shall be calculated for each window determined in accordance with paragraph 3.1.
(a) The distance-specific CO emissions M ;
2 CO2,d,j
(b) The average vehicle speed v
j
4. Evaluation of windows
4.1. Introduction
The reference dynamic conditions of the test vehicle are defined from the vehicle CO emissions versus average
2
speed measured at type approval on the WLTP test and referred to as ‘vehicle CO characteristic curve’.
2
4.2. CO characteristic curve reference points
2
The distance specific CO emissions of the tested vehicle shall be taken from the applicable phases of the
2
validation WLTP 4-phase test run in accordance with UN Regulation No. 154 on WLTP on that particular vehicle.
The value for OVC-HEV vehicles is to be that obtained from the applicable WLTP test conducted using Charge
Sustaining vehicle operation.
During type approval, the CO reference values shall be taken from the WLTP test of the individual vehicle,
2
obtained in accordance with UN Regulation No 154, including all appropriate corrections.
The reference points P P and P required to define the vehicle CO characteristic curve shall be established as
1, 2 3 2
follows:
4.2.1. Point P
1
v ¼18;882 km=h (Average Speed of the Low Speed phase of the WLTP cycle)
P1
M = Vehicle CO emissions over the Low Speed phase of the WLTP test [g/km]
CO2;d;P1 2
4.2.2. Point P
2
v ¼56;664 km=h (Average Speed of the High Speed phase of the WLTP cycle)
P2
M = Vehicle CO emissions over the High Speed phase of the WLTP test [g/km]
CO2;d;P2 2
4.2.3. Point P
3
v ¼91;997 km=h (Average Speed of the Extra High Speed phase of the WLTP cycle)
P3
M = Vehicle CO emissions over the Extra High Speed phase of the WLTP test [g/km] (for analysis with
CO2;d;P3 2
4-phase WLTP)
and
M = M (for analysis with 3-phase WLTP)
CO2;d;P3 CO2;d;P2
4.3. CO characteristic curve definition
2
Using the reference points defined in paragraph 4.2., the characteristic curve CO emissions are calculated as a
2
function of the average speed using two linear sections (P , P ) and (P , P ). The section (P , P ) is limited to
1 2 2 3 2 3
145 km/h on the vehicle speed axis. The characteristic curve is defined by equations as follows:
For the section (P;PÞ:
1 2
M ðvÞ¼avþb
CO2;d;CC 1 1
.
with: a 1 ¼ðM CO 2;d;P 2 – M CO 2;d;P 1Þ ðv P2 – v P1Þ
and: b ¼M – av
1 CO2;d;P1 1 P1
For the section (P;PÞ:
2 3
M ðvÞ¼avþb
CO2;d;CC 2 2
80/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
.
with: a 2 ¼ðM CO 2;d;P 3 – M CO 2;d;P 2Þ ðv P3 – v P2Þ
and: b ¼M – av
2 CO2;d;P2 2 P2
Figure A8/3
Vehicle CO characteristic curve and tolerances for ICE and NOVC-HEV vehicles
2
Figure A8/4
Vehicle CO characteristic curve and tolerances for OVC-HEV vehicles
2
ELI: http://data.europa.eu/eli/reg/2024/211/oj 81/98EN
OJ L, 12.1.2024
Figure A8/3-2
Vehicle CO characteristic curve and tolerances for ICE and NOVC-HEV vehicles for 3-phase WLTP
2
Figure A8/4-2
Vehicle CO characteristic curve and tolerances for OVC-HEV vehicles for 3-phase WLTP
2
4.4.1. Low, medium and high speed windows (for analysis with 4-phase WLTP)
The windows shall be categorised into low, medium and high speed bins according to their average speed.
4.4.1.1. Low speed windows
Low speed windows are characterized by average vehicle ground speeds v lower than 45 km/h.
j
4.4.1.2. Medium speed windows
Medium speed windows are characterized by average vehicle ground speeds v greater than or equal to 45 km/h
j
and lower than 80 km/h.
4.4.1.3. High speed windows
High speed windows are characterized by average vehicle ground speeds v greater than or equal to 80 km/h and
j
lower than 145 km/h
82/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
Figure A8/5
Vehicle CO characteristic curve: low, medium and high speed definitions
2
(Illustrated for ICE and NOVC-HEV vehicles)
Figure A8/6
Vehicle CO characteristic curve: low, medium and high speed definitions
2
(Illustrated for OVC-HEV vehicles)
4.4.2. Low/and high speed windows (for analysis with 3-phase WLTP)
The windows shall be categorised into low and high speed bins according to their average speed.
4.4.2.1. Low speed windows
Low speed windows are characterized by average vehicle ground speeds v lower than 50 km/h.
j
4.4.2.2. High speed windows
High speed windows are characterized by average vehicle ground speeds v greater than or equal to 50 km/h.
j
ELI: http://data.europa.eu/eli/reg/2024/211/oj 83/98EN
OJ L, 12.1.2024
Figure A8/5-2
Vehicle CO characteristic curve: low and high speed definitions
2
(Illustrated for ICE and NOVC-HEV vehicles)
Figure A8/6-2
Vehicle CO characteristic curve: low and high speed definitions
2
(Illustrated for OVC-HEV vehicles)
4.5.1. Assessment of trip validity (for analysis with 4-phase WLTP)
4.5.1.1. Tolerances around the vehicle CO characteristic curve
2
The upper tolerance of the vehicle CO characteristic curve is tol ¼45 % for low speed driving and
2 1H
tol ¼40 %for medium and high speed driving.
1H
The lower tolerance of the vehicle CO characteristic curve is tol ¼25 %for ICE and NOVC-HEV vehicles and
2 1L
tol ¼100 %for OVC-HEV vehicles.
1L
4.5.1.2. Assessment of test validity
The test is valid when it comprises at least 50 per cent of the low, medium and high speed windows that are within
the tolerances defined for the CO characteristic curve.
2
For NOVC-HEVs and OVC-HEVs, if the minimum requirement of 50 per cent between tol and tol is not met,
1H 1L
the upper positive tolerance tol may be increased until the value of tol reaches 50 per cent.
1H 1H
For OVC-HEVs when no MAWs are calculated as result of the ICE not turning on, the test is still valid.
4.5.2. Assessment of trip validity (for analysis with 3-phase WLTP)
4.5.2.1. Tolerances around the vehicle CO characteristic curve
2
The upper tolerance of the vehicle CO characteristic curve is tol ¼45 % for low speed driving and
2 1H
tol ¼40 %for high speed driving.
1H
84/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
The lower tolerance of the vehicle CO characteristic curve is tol ¼25 %for ICE and NOVC-HEV vehicles and
2 1L
tol ¼100 %for OVC-HEV vehicles.
1L
4.5.2.2. Assessment of test validity
The test is valid when it comprises at least 50 per cent of the low, and high speed windows that are within the
tolerances defined for the CO characteristic curve.
2
For NOVC-HEVs and OVC-HEVs, if the minimum requirement of 50 per cent between tol and tol is not met,
1H 1L
the upper positive tolerance tol may be increased by steps of 1 per cent until the 50 % target is reached. When
1H
using this mechanism, the value of tol shall never exceed 50 per cent.
1H
ELI: http://data.europa.eu/eli/reg/2024/211/oj 85/98EN
OJ L, 12.1.2024
ANNEX 9
Assessment of excess or absence of trip dynamics
1. Introduction
This annex describes the calculation procedures to verify the trip dynamics by determining the excess or absence
of dynamics during an RDE trip.
2. Symbols, Parameters and Units
a — acceleration [m/s2]
a — acceleration in time step i [m/s2]
i
a — positive acceleration greater than 0,1 m/s2 [m/s2]
pos
a — positive acceleration greater than 0,1 m/s2 in time step i considering the urban, rural and
pos,i,k
motorway/expressway shares [m/s2]
a — acceleration resolution [m/s2]
res
d — distance covered in time step i [m]
i
d — distance covered in time step i considering the urban, rural and motorway/expressway
i,k
shares [m]
Index (i) — discrete time step
Index (j) — discrete time step of positive acceleration datasets
Index (k) — refers to the respective category (t=total, u=urban, r=rural, m=motorway, e=expressway)
M — number of samples for urban, rural and motorway/expressway shares with positive
k
acceleration greater than 0.1 m/s2
N — total number of samples for the urban, rural and motorway/expressway shares and the
k
complete trip
RPA — relative positive acceleration for urban, rural and motorway/expressway shares [m/s2 or
k
kWs/(kg*km)]
t — duration of the urban, rural and motorway/expressway shares and the complete trip [s]
k
v — vehicle speed [km/h]
v — actual vehicle speed in time step i [km/h]
i
v — actual vehicle speed in time step i considering the urban, rural and motorway/expressway
i,k
shares [km/h]
ðv×aÞ — actual vehicle speed per acceleration in time step i [m2/s3 or W/kg]
i
ðv×aÞ — actual vehicle speed per positive acceleration greater than 0,1 m/s2 in time step j
j;k
considering the urban, rural and motorway/expressway shares [m2/s3 or W/kg].
ðv×a Þ ½95� — 95th percentile of the product of vehicle speed per positive acceleration greater than 0,1
pos k –
m/s2 for urban, rural and motorway/expressway shares [m2/s3 or W/kg]
v — average vehicle speed for urban, rural and motorway/expressway shares [km/h]
k
3. Trip indicators
3.1. Calculations
86/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
3.1.1. Data pre-processing
Dynamic parameters, such as acceleration, ðv×a Þor RPA, shall be determined with a speed signal of an accuracy
pos
of 0,1 per cent for all speed values above 3 km/h and a sampling frequency of 1 Hz. Otherwise, acceleration shall
be determined with an accuracy of 0,01 m/s2 and a sampling frequency of 1 Hz. In this case, a separate speed
signal is required for ðv×a Þand shall have an accuracy of at least 0,1 km/h. The speed trace shall form the basis
pos
for further calculations and binning as described in paragraphs 3.1.2. and 3.1.3.
3.1.2. Calculation of distance, acceleration and (v×a)
The following calculations shall be performed over the whole time based speed trace from the beginning to the
end of the test data.
The distance increment per data sample shall be calculated as follows:
d ¼ vi i¼1 to N
i 3;6 t
where:
d is the distance covered in time step i [m]
i
ν is the actual vehicle speed in time step i [km/h]
i
N is the total number of samples
t
The acceleration shall be calculated as follows:
a ¼viþ1 – vi – 1 i¼1 to N
i 2×3;6 t
where:
a is the acceleration in time step i [m/s2].
i
For i = 1: v–1= 0,
i
for i = N: v =0.
t i+ 1
The product of vehicle speed per acceleration shall be calculated as follows:
ðv×aÞ ¼v×a=3;6
i i i
where:
ðv×aÞ is the product of the actual vehicle speed per acceleration in time step i [m2/s3 or W/kg].
i
3.1.3. Binning of the results
3.1.3.1. Binning of the results (for analysis with 4-phase WLTP)
After the calculation of a and ðv×aÞ, the values v, d, a and ðv×aÞ shall be ranked in ascending order of the
i i i i i i
vehicle speed.
All datasets with (v≤ 60 km/h) belong to the ‘urban’ speed bin, all datasets with (60 km/h < v ≤ 90 km/h) belong
i i
to the ‘rural’ speed bin and all datasets with (v > 90 km/h) belong to the ‘motorway’ speed bin.
i
The number of datasets with acceleration values a >0,1 m/s2 shall be greater than or equal to 100 in each speed
i
bin.
For each speed bin the average vehicle speed (v) shall be calculated as follows:
k
v ¼ 1 ∑ v i¼1 to N ; k¼u;r;m
k Nk i i;k k
where:
N is the total number of samples of the urban, rural, and motorway shares.
k
3.1.3.2. Binning of the results (for the analysis with 3-phase WLTP)
ELI: http://data.europa.eu/eli/reg/2024/211/oj 87/98EN
OJ L, 12.1.2024
After the calculation of a, v, d, the values v, d, a and ðv×aÞ shall be ranked in ascending order of the vehicle
i i i i i i i
speed.
All datasets with (v ≤ 60 km/h) belong to the ‘urban’ speed bin and all datasets with (v > 60 km/h) belong to the
i i
‘expressway’ speed bin.
The number of datasets with acceleration values a > 0,1 m/s2 shall be greater than or equal to 100 in each speed
i
bin.
For each speed bin the average vehicle speed (v) shall be calculated as follows:
k
v ¼ 1 ∑ v i¼1 to N ; k¼u; e
k Nk i i;k k
where:
N is the total number of samples of the urban and expressway shares.
k
3.1.4. Calculation of ðv×a Þ ½95�per speed bin
pos k –
3.1.4.1. Calculation of ðv×a Þ ½95�per speed bin (for analysis with 4-phase WLTP)
pos k –
The 95th percentile of the ðv×a Þvalues shall be calculated as follows:
pos
The ðv×a Þ values in each speed bin shall be ranked in ascending order for all datasets with a > 0,1m/s2 and the
pos i;k i,k
total number of these samples M shall be determined.
k
Percentile values are then assigned to theðv×a Þ values with a > 0,1 m/s2 as follows:
pos i;k i,k
The lowest ðv×a Þ value gets the percentile 1/M, the second lowest 2/M, the third lowest 3/M and the highest
pos k k k
value (M /M = 100 %.)
k k
ðv×a Þ ½95� is the ðv×a Þ value, with j/M = 95 %. If j/M = 95 % cannot be met, ðv×a Þ ½95�shall be
pos k – pos j;k k k pos k –
calculated by linear interpolation between consecutive samples j and j+1 with j/M < 95 % and (j+1)/M > 95%.
k k
The relative positive acceleration per speed bin shall be calculated as follows:
RPA
¼∑ jðΔt×ðv×aposÞj;kÞ
; j¼1 to M ; i¼1 to N ; k¼u;r;m
k ∑ idi;k k k
where:
RP is the relative positive acceleration for urban, rural and motorway shares in [m/s2 or kWs/(kg*km)]
A
k
M is the sample number for urban, rural and motorway shares with positive acceleration
k
N is the total sample number for urban, rural and motorway shares
k
Δt is a time difference equal to 1 second
3.1.4.2. Calculation of ðv×a Þ ½95�per speed bin (for analysis with 3-phase WLTP)
pos k –
The 95th percentile of the ðv×a Þvalues shall be calculated as follows:
pos
The ðv×a Þ values in each speed bin shall be ranked in ascending order for all datasets with a > 0,1 m/s2 and the
pos i;k i,k
total number of these samples M shall be determined.
k
Percentile values are then assigned to ðv×a Þ values with a > 0,1 m/s2 as follows:
pos i;k i,k
The lowest ðv×a Þvalue gets the percentile 1/M, the second lowest 2/M, the third lowest 3/M and the highest
pos k k k
value (M /M = 100 %.)
k k
ðv×a Þ ½95� is theðv×a Þ value, with j/M = 95%. If j/M = 95% cannot be met, ðv×a Þ ½95� shall be
pos k – pos j;k k k pos k –
calculated by linear interpolation between consecutive samples j and j+1 with j/M < 95% and (j+1)/M > 95%.
k k
88/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
The relative positive acceleration per speed bin shall be calculated as follows:
RPA
¼∑ jðΔt×ðv×aposÞj;kÞ
; j¼1 to M ; i¼1 to N ; k¼u;e
k ∑ idi;k k k
where:
RPA is the relative positive acceleration for urban and expressway shares in [m/s2 or kWs/(kg*km)]
k
M is the sample number for urban and expressway shares with positive acceleration
k
N is the total sample number for urban and expressway shares
k
Δt is a time difference equal to 1 second
4. Assessment of trip validity
4.1.1. Assessment of ðv×a Þ ½95�per speed bin (with v in [km/h])
pos k –
If v ≤74;6 km=hand
k
ðv×a Þ ½95�>ð0;136× vþ14;44Þ
pos k – k
is fulfilled, the trip is invalid.
If v >74;6 km=hand
k
ðv×a Þ ½95�>ð0;0742× vþ18;966Þ
pos k – k
is fulfilled, the trip is invalid.
Upon the request of the manufacturer, and only for those N1 vehicles where the vehicle power-to-test-mass-ratio
is less than or equal to 44 W/kg then:
If v≤74;6km=hand
k
ðv×a Þ ½95�>ð0;136×vþ14;44Þ
pos k – k
is fulfilled, the trip is invalid.
If v >74;6 km=hand
k
ðv×a Þ ½95�>ð – 0;097×v þ 31;635Þ
pos k – k
is fulfilled, the trip is invalid.
4.1.2. Assessment of RPA per speed bin
If v≤94;05 km=hand
k
RPA <ð – 0;0016•v þ 0;1755Þ
k k
is fulfilled, the trip is invalid.
If v >94;05km=hand RPA <0;025is fulfilled, the trip is invalid.
k k
ELI: http://data.europa.eu/eli/reg/2024/211/oj 89/98EN
OJ L, 12.1.2024
ANNEX 10
Procedure to determine the cumulative positive elevation gain of a PEMS trip
1. Introduction
This annex describes the procedure to determine the cumulative elevation gain of a PEMS trip.
2. Symbols, Parameters and Units
d(0) — distance at the start of a trip [m]
d — cumulative distance travelled at the discrete way point under consideration [m]
d — cumulative distance travelled until the measurement directly before the respective way
0
point d [m]
d — cumulative distance travelled until the measurement directly after the respective way
1
point d [m]
d — reference way point at d(0) [m]
a
d — cumulative distance travelled until the last discrete way point [m]
e
d — instantaneous distance [m]
i
d — total test distance [m]
tot
h(0) — vehicle altitude after the screening and principle verification of data quality at the start of
a trip [m above sea level]
h(t) — vehicle altitude after the screening and principle verification of data quality at point t [m
above sea level]
h(d) — vehicle altitude at the way point d [m above sea level]
h(t-1) — vehicle altitude after the screening and principle verification of data quality at point t-1
[m above sea level]
h (0) — corrected altitude directly before the respective way point d [m above sea level]
corr
h (1) — corrected altitude directly after the respective way point d [m above sea level]
corr
h (t) — corrected instantaneous vehicle altitude at data point t [m above sea level]
corr
h (t-1) — corrected instantaneous vehicle altitude at data point t-1 [m above sea level]
corr
h — instantaneous vehicle altitude measured with GNSS [m above sea level]
GNSS,i
h (t) — vehicle altitude measured with GNSS at data point t [m above sea level]
GNSS
h (d) — interpolated altitude at the discrete way point under consideration d [m above sea level]
int
h (d) — smoothed and interpolated altitude, after the first smoothing run at the discrete way
int,sm,1
point under consideration d [m above sea level]
h (t) — vehicle altitude based on topographic map at data point t [m above sea level]
map
road (d) — smoothed road grade at the discrete way point under consideration d after the first
grade,1
smoothing run [m/m]
90/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
road (d) — smoothed road grade at the discrete way point under consideration d after the second
grade,2
smoothing run [m/m]
sin — trigonometric sine function
t — time passed since test start [s]
t — time passed at the measurement directly located before the respective way point d [s]
0
v — instantaneous vehicle speed [km/h]
i
v(t) — vehicle speed at a data point t [km/h]
3. General requirements
The cumulative positive elevation gain of a RDE trip shall be determined based on three parameters: the
instantaneous vehicle altitude h [m above sea level] as measured with the GNSS, the instantaneous vehicle
GNSS,i
speed v [km/h] recorded at a frequency of 1 Hz and the corresponding time t [s] that has passed since test start.
i
4. Calculation of cumulative positive elevation gain
4.1. General
The cumulative positive elevation gain of a RDE trip shall be calculated as a two-step procedure, consisting of (i) the
correction of instantaneous vehicle altitude data, and (ii) the calculation of the cumulative positive elevation gain.
4.2. Correction of instantaneous vehicle altitude data
The altitude h(0) at the start of a trip at d(0) shall be obtained by GNSS and verified for correctness with information
from a topographic map. The deviation shall not be larger than 40 m. Any instantaneous altitude data h(t) shall be
corrected if the following condition applies:
jhðtÞ – hðt – 1Þj>vðtÞ=3;6 ×sin45°
The altitude correction shall be applied so that:
h ðtÞ¼h ðt – 1Þ
corr corr
where:
h(t) — vehicle altitude after the screening and principle check of data quality at data point t [m
above sea level]
h(t-1) — vehicle altitude after the screening and principle check of data quality at data point t-1 [m
above sea level]
v(t) — vehicle speed of data point t [km/h]
h (t) — corrected instantaneous vehicle altitude at data point t [m above sea level]
corr
h (t-1) — corrected instantaneous vehicle altitude at data point t-1 [m above sea level]
corr
Upon the completion of the correction procedure, a valid set of altitude data is established. This data set shall be
used for the calculation of the cumulative positive elevation gain as described in the following.
4.3. Final calculation of the cumulative positive elevation gain
4.3.1. Establishment of a uniform spatial resolution
The cumulative elevation gain shall be calculated from data of a constant spatial resolution of 1 m starting with the
first measurement at the start of a trip d(0). The discrete data points at a resolution of 1 m are referred to as way
points, characterized by a specific distance value d (e.g., 0, 1, 2, 3 m…) and their corresponding altitude h(d) [m
above sea level].
ELI: http://data.europa.eu/eli/reg/2024/211/oj 91/98EN
OJ L, 12.1.2024
The altitude of each discrete way point d shall be calculated through interpolation of the instantaneous altitude
h (t) as:
corr
h ðdÞ¼h ð0Þþhcorrð1Þ – hcorrð0Þ×ðd – d Þ
int corr d1 – d0 0
where:
h (d) — interpolated altitude at the discrete way point under consideration d [m above sea level]
int
h (0) — corrected altitude directly before the respective way point d [m above sea level]
corr
h (1) — corrected altitude directly after the respective way point d [m above sea level]
corr
d — cumulative distance travelled at the discrete way point under consideration d [m]
d — cumulative distance travelled until the measurement located directly before the respective
0
way point d [m]
d — cumulative distance travelled until the measurement located directly after the respective
1
way point d [m]
4.3.2. Additional data smoothing
The altitude data obtained for each discrete way point shall be smoothed by applying a two-step procedure; d and d
a e
denote the first and last data point respectively (see Figure A10/1). The first smoothing run shall be applied as
follows:
road ðdÞ¼hintðdþ200mÞ – hintðdaÞ for d≤200 m
grade;1 ðdþ200mÞ
road ðdÞ¼hintðdþ200mÞ – hintðd – 200mÞ for 200 m<d<ðd – 200 mÞ
grade;1 e
ðdþ200mÞ – ðd – 200mÞ
road ðdÞ¼hintðdeÞ – hintðd – 200mÞ for d≥ðd – 200 mÞ
grade;1 de – ðd – 200mÞ e
h ðdÞ¼h ðd – 1 mÞþroad ðdÞ for d¼ðd þ1Þ to d
int;sm;1 int;sm;1 grade;1 a e
h ðd Þ¼h ðd Þþroad ðd Þ
int;sm;1 a int a grade;1 a
where:
road (d) — smoothed road grade at the discrete way point under consideration after the first
grade,1
smoothing run [m/m]
h (d) — interpolated altitude at the discrete way point under consideration d [m above sea level]
int
h (d) — smoothed interpolated altitude, after the first smoothing run at the discrete way point
int,sm,1
under consideration d [m above sea level]
d — cumulative distance travelled at the discrete way point under consideration [m]
d — reference way point at d(0) [m]
a
d — cumulative distance travelled until the last discrete way point [m]
e
92/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
The second smoothing run shall be applied as follows:
road
ðdÞ¼hint;sm;1ðdþ200mÞ – hint;sm;1ðdaÞ
for d≤200 m
grade;2 ðdþ200mÞ
road
ðdÞ¼hint;sm;1ðdþ200mÞ – hint;sm;1ðd – 200mÞ
for 200 m<d<ðd – 200 mÞ
grade;2 ðdþ200mÞ – ðd – 200mÞ e
road
ðdÞ¼hint;sm;1ðdeÞ – hint;sm;1ðd – 200mÞ
for d≥ðd – 200 mÞ
grade;2 de – ðd – 200mÞ e
where:
road (d) — smoothed road grade at the discrete way point under consideration after the second
grade,2
smoothing run [m/m]
h (d) — smoothed interpolated altitude, after the first smoothing run at the discrete way point
int,sm,1
under consideration d [m above sea level]
d — cumulative distance travelled at the discrete way point under consideration [m]
d — reference way point at d(0) [m]
a
d — cumulative distance travelled until the last discrete way point [m]
e
Figure A10/1
Illustration of the procedure to smooth the interpolated altitude signals
4.3.3. Calculation of the final result
The positive cumulative elevation gain of a total trip shall be calculated by integrating all positive interpolated and
smoothed road grades, i.e., road (d). The result should be normalized by the total test distance d and expressed
grade,2 tot
in meters of cumulative elevation gain per one hundred kilometres of distance.
The waypoint vehicle speed v shall then be calculated over each discrete way point of 1m:
w
v ¼ 1
w ðtw;i – tw;i – 1Þ
For 3-phase WLTP evaluation all datasets with v ≤ 100 km/h are used for the calculation of the cumulative positive
w
altitude gain of the complete trip.
All of the positive interpolated and smoothed road gradients that correspond to ≤ 100 km/h datasets shall be
integrated.
The number of 1m waypoints which correspond to ≤ 100 km/h datasets shall be integrated and converted to km to
define the ≤ 100 km/h test distance d100 [km].
ELI: http://data.europa.eu/eli/reg/2024/211/oj 93/98EN
OJ L, 12.1.2024
The positive cumulative elevation gain of the urban part of the trip shall then be calculated based on the vehicle
speed over each discrete way point. All datasets with v ≤ 60 km/h belong to the urban part of the trip. All of the
w
positive interpolated and smoothed road grades that correspond to urban datasets shall be integrated.
The number of 1m waypoints which correspond to urban datasets shall be integrated and converted to km to define
the urban test distance d [km].
urban
The positive cumulative elevation gain of the urban part of a trip shall then be calculated by dividing the urban
elevation gain by the urban test distance, and expressed in metres of cumulative elevation gain per one hundred
kilometres of distance.
94/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
ANNEX 11
Calculation of the final RDE emissions results
1. Introduction
This annex describes the procedure to calculate the final criteria emissions for the complete and urban part of an RDE
trip for the 3-phase and 4-phase WLTP.
2. Symbols, Parameters and Units
Index (k) refers to the category (t=total, u=urban, 1-2=first two phases of the WLTP test)
IC is the distance share of usage of the internal combustion engine for an OVC-HEV over the RDE
k
trip
d is the distance driven [km], with the internal combustion engine on for an OVC-HEV over the
ICE,k
RDE trip
d is the distance driven [km], with the internal combustion engine off for an OVC-HEV over the
EV,k
RDE trip
M is the final RDE distance-specific mass of gaseous pollutants [mg/km] or particle
RDE,k
number [#/km]
m is the distance-specific mass of gaseous pollutant [mg/km] or particle number [#/km]
RDE,k
emissions, emitted over the complete RDE trip and prior to any correction in accordance with
this annex
M is the distance-specific mass of CO [g/km], emitted over the RDE trip
CO2;RDE;k 2
M is the distance-specific mass of CO [g/km], emitted over the WLTC cycle
CO2;WLTC;k 2
M is the distance-specific mass of CO [g/km], emitted over the WLTC cycle for an OVC-HEV
CO2;WLTCCS;k 2
vehicle tested in charge sustaining vehicle operation
r is the ratio between the CO emissions measured during the RDE test and the WLTP test
k 2
RF is the result evaluation factor calculated for the RDE trip
k
RF is the first parameter of the function used to calculate the result evaluation factor
L1
RF is the second parameter of the function used to calculate the result evaluation factor
L2
3. Calculation of the Intermediate RDE emissions results
For the valid trips, the intermediate RDE results are calculated as follows for vehicles with ICE, NOVC-HEV and OVC-
HEV.
Any instantaneous emissions or exhaust flow measurements obtained while the combustion engine is deactivated, as
defined in paragraph 3.6.3. of this Regulation, shall be set to zero.
Any correction of the instantaneous criteria emissions for Extended conditions according to paragraphs 8.1., 10.5.
and 10.6. of this Regulation shall be applied.
For the complete RDE trip and for the urban part of the RDE trip (k=t=total, k=u=urban):
M ¼m ×RF
RDE;k RDE;k k
The values of the parameter RF and RF of the function used to calculate the result evaluation factor are as follows:
L1 L2
RF ¼1;30and RF ¼1;50;
L1 L2
The RDE result evaluation factors RF (k=t=total, k=u=urban) shall be obtained using the functions laid down in
k
paragraph 2.2. for vehicles with ICE and NOVC-HEV, and in paragraph 2.3. for OVC-HEV. A graphical illustration of
the method is provided in Figure A11/1 below, while the mathematical formulas are found in Table A11/1:
ELI: http://data.europa.eu/eli/reg/2024/211/oj 95/98EN
OJ L, 12.1.2024
Figure A11/1
Function to calculate the result evaluation factor
Table A11/1
Result evaluation factors calculation
When: Then the Result evaluation factor RF is: Where:
k
r≤RF RF ¼1
k L1 k
RF L1 <r k≤RF L2 RF k ¼a 1r kþb 1 a 1 ¼ ½RFL2×R ðRF FL L2 1 – –1 RFL2Þ�
b ¼1 – aRF
1 1 L1
r >RF RF ¼ 1
k L2 k rk
3.1. RDE result evaluation factor for vehicles with ICE and NOVC-HEV
The value of the RDE result evaluation factor depends on the ratio r between the distance specific CO emissions
k 2
measured during the RDE test and the distance-specific CO emitted by the vehicle over the validation WLTP test
2
conducted on this vehicle including all appropriate corrections.
For the urban emissions, the relevant phases of the WLTP test shall be:
(a) For ICE vehicles, the first two WLTC phases, i.e. the Low and the Medium speed phases,
r ¼
MCO2;RDE;k
k MCO2;WLTP;k
(b) For NOVC-HEVs, all the phases of the WLTC driving cycle.
r ¼
MCO2;RDE;k
k MCO2;WLTP;t
3.2. RDE result evaluation factor for OVC-HEV
The value of the RDE result evaluation factor depends on the ratio r between the distance-specific CO emissions
k 2
measured during the RDE test and the distance-specific CO2 emitted by the vehicle over the applicable WLTP test
conducted in Charge Sustaining vehicle operation including all appropriate corrections. The ratio r is corrected by a
k
ratio reflecting the respective usage of the internal combustion engine during the RDE trip and on the WLTP test, to
be conducted in charge sustaining vehicle operation.
96/98 ELI: http://data.europa.eu/eli/reg/2024/211/ojEN
OJ L, 12.1.2024
For either the urban or the total driving:
r ¼ MCO2;RDE;k ×0;85
k MCO2;WLTP CS;t ICk
where IC is the ratio of the distance driven either in urban or total trip with the combustion engine activated, divided
k
by the total urban or total trip distance:
IC ¼
dICE;k
k dICE;kþdEV;k
With determination of combustion engine operation in accordance with paragraph 3.6.3. of this Regulation.
4. Final RDE emission results taking into account the PEMS margin
In order to take into account the uncertainty of the PEMS measurements compared to the ones performed in the
laboratory with the applicable WLTP test, the intermediate calculated emission values M shall be divided by 1
RDE, k
+margin , where margin defined in the Table A11/2.
pollutant. pollutant
The PEMS margin for each pollutant is specified as follows:
Table A11/2
Combined mass of
Mass of total total hydrocarbons
Mass of oxides of Number of Mass of carbon
Pollutant hydrocarbons and oxides of
nitrogen (NO ) particles (PN) monoxide (CO)
X (THC) nitrogen (THC +
NO )
X
Margin 0,10 0,34 Not yet specified Not yet specified Not yet specified
pollutant
Any negative final results shall be set to zero.
Any Ki factors which are applicable, according to paragraph 8.3.4. of this Regulation, shall be applied.
These values shall be considered the Final RDE emission results for NO and PN.
X
ELI: http://data.europa.eu/eli/reg/2024/211/oj 97/98EN
OJ L, 12.1.2024
ANNEX 12
Manufacturer's RDE certificate of compliance
Manufacturer's certificate of compliance with the Real Driving Emissions requirements in UN Regulation No. 168
(Manufacturer): ................................................................................................................
(Address of the Manufacturer): ................................................................................................
Certifies that:
The vehicle types listed in the annex to this Certificate comply with the requirements laid down in paragraph 6.1. of UN
Regulation No. 168 for all valid RDE tests which are performed in accordance with the requirements of that Regulation.
Done at ...................... (Place)
On ........................... (Date)
................................................................................................................................
(Stamp and signature of the manufacturer's representative)
Annex:
— List of vehicle types to which this certificate applies
98/98 ELI: http://data.europa.eu/eli/reg/2024/211/oj