GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 4046
TO BE ANSWERED ON 12.08.2026
STATUS OF ROBS AND RUBS IN KERALA
4046. SHRI KODIKUNNIL SURESH:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of Railway Over Bridges (ROBs) and Railway Under Bridges
(RUBs) sanctioned, approved and under construction in Kerala,
indicating the estimated cost, cost- sharing pattern and implementing
agency, district-wise;
(b) the details of funds allocated, released and utilised for each ROB and
RUB project during the last five years and the current year, year-wise;
(c) the present status of each project, indicating works completed, works
under execution, projects yet to commence and projects delayed along
with the reasons therefor;
(d) whether any new ROBs and RUBs have been sanctioned/approved for
Kerala during the last three years and if so, the details thereof, district
and year-wise; and
(e) the steps taken/being taken by the Government to expedite the
completion of pending ROB and RUB projects in the said State along
with the revised timeline fixed for completion of each project?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Sanctioning of works of Road over Bridge (ROB)/Road under
Bridge (RUB) in lieu of Level crossings (LCs) is a continuous and dynamic
process of Indian Railway. Such works are prioritised and taken up on the
basis of their impact on safety in train operations, mobility of trains &
impact for road users and feasibility etc.
§ Page 1 of 7No. of ROBs/ RUBs constructed on Indian Railways during the period
2004-14 vis a vis 2014-26 (Upto May’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-26 (Upto May’26) 14,451 Nos. (131 Nos. in the State of Kerala)
As on 01.06.2026, 4,993 Nos. ROB/ RUB works are sanctioned at a cost
of approx. ₹ 1,17,492 Cr on Indian Railways including 145 Nos. ROB/ RUB at
a cost of approx. ₹ 4,786 Cr in the state of Kerala which are at various
stages of planning and execution. Out of these works, 104 works are
sanctioned on cost sharing basis and 41 Nos. works are on 100% Railways
cost.
52 Nos. ROBs/RUBs are delayed on account of the State Govt. The
details are as under:
# Reason ROBs/RUBs (in
No.)
1. Delay in Land Acquisition by State Govt. 34
2. Finalization of Alignment by State Govt. 13
3. Agency yet to be fixed 5
Completion & commissioning of ROB/RUB works depends on various
factors like cooperation of State Governments in giving consent for
closure of LC, fixing of approach alignment, approval of General
Arrangement Drawing (GAD), land acquisition, removal of encroachment,
shifting of infringing utilities, statutory clearances from various authorities,
law and order situation in the area of project / work sites, duration of
Page 2 of 7working season in a year for the particular project / area due to climatic
conditions etc. All these factors affect the completion time of the projects /
works.
Railways have taken following measures to expedite the progress of
ROB/RUB works:
i. Joint survey with concerned State Govt./Road Owning Authority is
done before finalizing the General Arrangement Drawing (GAD) to
ensure smooth execution.
ii. Periodic meetings of Railway & State Government officials are done
to resolve various issues related to ROB/RUB works.
iii. Standardization of superstructure and substructure drawings for
various combinations of span, skewness and width of road on the
Railway portion has been done to avoid delays during the design
approval. This has been issued in the form of a compendium, which
can be directly adopted for Road Over Bridge across Railway lines for
expeditious planning.
Railway Budget:-
Budget allocation in the recent years has increased significantly.
Budget allocation for infrastructure projects and safety works, falling
fully/partly in the State of Keralam is as under:-
Period Outlay
2009-14 ₹ 372 crore/year
2026-27 ₹3,795 crore (more than 10 times)
Page 3 of 7Projects Sanctioned:-
As on 01.04.2026, 09 projects (03 new line and 06 doubling) of 302 km
length, costing ₹11,650 crore falling fully/partly in Keralam are sanctioned.
The summary is as under:-
Category No. of Total Length Total Expenditure
projects Length Commissioned upto March, 2026
(in Km) upto March, 2026 (₹ in Cr.)
(in Km)
New line 03 148 0 317
Doubling 06 154 40 3,550
/multitracking
Total 09 302 40 3,867
Recently Completed Projects:-
Details of some of the recently completed projects falling fully/partly in
the State of Keralam are as under:
# Project Cost
(₹ in
Crores)
1 Dindigul - Palghat & Pollachi - Coimbatore gauge 1,360
conversion (217 km)
2 Quilon- Tiruchendur gauge conversion (357 km) 1,122
3 Mulanturutti-Kuruppantara doubling (24 km) 303
4 Chenganur-Chingavanam doubling (27 km) 436
5 Ambalapuzha-Haripad doubling (18 km) 346
6 Kurruppanthara-Chingavanam doubling (27 km) 749
Page 4 of 7Ongoing Projects:-
Some of the projects falling fully/partly in the State of Keralam which
have been taken up are as under:
S.No. Project Cost
(₹ in
Crores)
1 Angamali-Sabarimala new line (111 km) 3,801
2 Ernakulam-Kumbalam doubling (8 km) 808
3 Kumbalam - Thuravur doubling (16 km) 1,172
4 Trivandrum- Kanyakumari doubling (87 km) 4,494
5 Alappuzha-Ambalapuzha doubling (13 km) 324
6 Turavur - Mararikulam doubling (21 km) 451
7 Mararikulam-Alappuzha doubling (11 km) 221
Execution of important infrastructure projects falling fully/partly in the
State of Keralam are held up due to delay in land acquisition. Status of land
acquisition in the State of Keralam is as under:
Total Land required for Projects in Keralam 618 ha
Land Acquired 78 ha (13%)
Balance Land to be acquired 540 ha (87%)
Railway had deposited ₹1,976 crore for land acquisition to Government
of Keralam. Support of the Government of Keralam is needed to expedite
the land acquisition. For instance, details of some major projects which are
delayed due to land acquisition are as under:
Page 5 of 7SN Name of the project Total Land Balance
land acquired Land to
required (in Ha) be
(in Ha) acquired
(in Ha)
1. Angamali - Sabarimala new line (111 304 25 279
km)
2. Ernakulam – Kumbalam Patch 4 3 1
doubling (8 km)
3. Kumbalam–Turavur Patch doubling(16 10 9 1
km)
4. Shoranur-Vallathol doubling (10 Km) 5 0 5
Government of India is geared up to execute projects, however success
depends upon the support of Government of Keralam.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Page 6 of 7Completion of Railway project/s depends on various factors which
include the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****
Page 7 of 7