**Executive Summary**
The 103rd meeting of the Network Planning Group (NPG) was convened on November 28, 2025, to evaluate three rail infrastructure projects proposed by the Ministry of Railways (MoR) for alignment with the PM GatiShakti National Master Plan. These projects aim to enhance multimodal connectivity, improve logistics efficiency, and provide socio-economic benefits. One project includes a completion date of July 2030.
**Key Points / Main Content**
* **Overall Focus**
* Evaluation of three railway infrastructure projects for integration with the PM GatiShakti National Master Plan.
* Emphasis on multimodal connectivity, logistics efficiency, and socio-economic impact.
* **Project 1: Barbenda - Damrughutu - Bokaro 3rd & 4th Line (West Bengal & Jharkhand)**
* Construction of a third and fourth railway line spanning 51.761 km.
* Enhancement of the Barbenda–Damrughutu-Bokaro Steel City corridor to meet rising traffic demands.
* Involves constructing bridges, RUBs, and upgrading station yards.
* Aims to improve freight mobility, reduce congestion, and support industrial growth.
* **Project 2: Jamalpur Munger Sabdalpur Double Line (Bihar)**
* Construction of a double line with a bridge over the Ganga River and a bypass alignment covering 15 km.
* Anticipated completion by July 2030.
* Aims to enhance connectivity for industrial hubs, boost economic development, and generate employment.
* **Project 3: Santragachi - Panskura - Kharagpur 4th Line (West Bengal)**
* Construction of a fourth railway line spanning 110.919 km, with a total track length of 133.781 km.
* Upgrade 30 station yards and build bridges, including major and minor constructions.
* Aims to ease congestion, enhance operational capacity, and improve rail transport efficiency.
**Impact Analysis**
**Ministry of Railways (MoR)**
* **Impact:** Responsible for proposing, constructing, and managing the infrastructure projects.
* **Action Required:** Execute the projects in alignment with the PM GatiShakti principles, adhering to timelines and specifications.
**Industries in Project Regions (Bokaro Steel Plant, Tata Steel Limited, Dalmia Cement, Hindustan Petroleum Corporation, ITC Ltd., etc.)**
* **Impact:** Will benefit from improved freight mobility, reduced transportation costs, and enhanced connectivity.
* **Action Required:** Monitor project progress and coordinate with MoR to optimize logistics and supply chain operations.
**Local Communities in West Bengal, Jharkhand, and Bihar**
* **Impact:** Potential for increased economic opportunities, employment, and socio-economic development.
* **Action Required:** Support the project by facilitating land acquisition and cooperating with construction activities.
**Freight and Passenger Transportation**
* **Impact:** Improved efficiency, reduced congestion, and enhanced reliability of rail transport.
* **Action Required:** Adapt to the new infrastructure by optimizing schedules and operations to maximize benefits.
Key Entities Referenced
PM GatiShakti National Master Plan (PMGS NMP): A national plan focused on enhancing multimodal connectivity and logistics efficiency in India.
Network Planning Group (NPG): A group convened to evaluate infrastructure projects in alignment with the PM GatiShakti initiative.
Ministry of Railways (MoR): The primary ministry proposing and developing the railway projects discussed.
West Bengal: The state where railway projects (Barbenda-Damrughutu and Santragachi-Panskura-Kharagpur) are to be constructed.
Bihar: The state where the Jamalpur-Munger-Sabdalpur railway project is to be constructed.
Ministry of Commerce & Industry
103rd Meeting of Network Planning Group under
PM GatiShakti evaluates key Infrastructure
projects
NPG evaluates 03 projects from Ministry of Railways (MoR)
प्रव तथ: 28 NOV 2025 7:35PM by PIB Delhi
The 103rd meeting of the Network Planning Group (NPG), convened today to evaluate infrastructure
projects. The meeting focused on enhancing multimodal connectivity and logistics efficiency in alignment
with the PM GatiShakti National Master Plan (PMGS NMP).
The NPG evaluated 03 projects in which 03 Rail projects for their conformity to the PM GatiShakti
principles of integrated multimodal infrastructure, last-mile connectivity to economic and social nodes and
‘Whole of Government’ approach. These initiatives are expected to boost logistics efficiency, reduce travel
times, and deliver significant socio-economic benefits to the catchment areas of the project. The
evaluation and anticipated impacts of these projects are detailed below:
Ministry of Railways(MoR)
1. Barbenda -Damrughutu doubling and Damrughutu - Bokaro 3rd and 4th line (West Bengal &
Jharkhand) : The Ministry of Railways has proposed the construction of a third and fourth railway line
between Barbenda and Damrughutu, spanning 51.761 km across the State of West Bengal and Jharkhand.
The project involves augmenting the existing Barbenda–Damrughutu–Bokaro Steel City corridor under
the South Eastern Railway to meet rising traffic demands and enhance operational efficiency.
The scope of work includes the construction of one major bridge, eighteen minor bridges, one Road Under
Bridge (RUB), and the extension of an existing level crossing. As part of the third-line development,
upgrades will be undertaken across five station yards, including block cabins, along with the construction
of five major bridges, fifty-two minor bridges, five RUBs, and the extension of five additional level
crossings.
This corridor is a vital freight route serving major industrial establishments such as Bokaro Steel Plant
(BSL), Tata Steel Limited, Dalmia Cement, and Hindustan Petroleum Corporation. The proposed
enhancement will significantly improve freight mobility, reduce congestion and delays, support industrial
growth in the region, and strengthen the overall reliability of the BBDA–DRGU–BKSC railway corridor.
2. Jamalpur Munger Sabdalpur Double line including bridge over Ganga including Jamalpur avoiding
line (Bihar): The Ministry of Railways has proposed the construction of the Jamalpur–Munger Double
Line along with a new bridge over the River Ganga and the Jamalpur avoiding line under the Eastern and
East Central Railway in Bihar. The 15 km project, which includes the double line, Ganga bridge, and
bypass alignment, is planned for completion by July 2030.The corridor passes through the densely populated Gangetic plains of Munger and Begusarai and holds
strategic importance as a key link between North Bihar and the southeastern regions of Bihar and
Jharkhand. The alignment will enhance connectivity for major industrial hubs including ITC Ltd. (India
Tobacco Division, Dairy Plant, and Packaging & Printing Unit), Sitakund Industrial Area, the Ordnance
Gun Factory, Jamalpur Railway Workshop, Bhagalpur Mega Handloom Cluster, Kahalgaon and Barauni
Thermal Power Stations, Barauni Refinery, Hindustan Urvarak & Rasayan Ltd., and the Kanti Thermal
Power Plant.
The project is expected to significantly boost economic and social development by providing faster, safer,
and seamless rail connectivity. It will also serve as a vital link between industrial and mining zones,
lowering transportation costs and improving the global competitiveness of Indian industries. Additionally,
the project will generate substantial direct and indirect employment opportunities during both construction
and operation, particularly in loading and unloading facilities, industrial areas, and railway yards.
3. 4th Line between Santragachi -Panskura-Kharagpur (West Bengal): The Ministry of Railways has
proposed the construction of a fourth railway line between Santragachi and Kharagpur in the State of West
Bengal, aimed at strengthening one of the region’s most vital and heavily utilized corridors. The route
currently handles substantial freight and passenger traffic, facilitating the movement of essential
commodities such as food grains, coal, cement, clinker, and steel, while also accommodating
approximately 115 coaching trains each day.
The proposed fourth line will extend across 110.919 km, with a total track length of 133.781 km. It
traverses 50.319 km in Howrah district, 26.70 km in East Medinipur, and 33.9 km in West Medinipur. The
project scope covers upgrades across 30 station yards and the construction of one important bridge, 15
major bridges, 100 minor bridges, and 12 Road Under Bridges (RUBs). With freight volumes projected to
rise from 20.37 MTPA in Year 1 to 28.12 MTPA by Year 11, the expansion is essential to easing
congestion, enhancing operational capacity, and ensuring more reliable movement of goods and
passengers. The project is expected to significantly improve the efficiency and resilience of rail transport
across this critical corridor.
The meeting was chaired by Joint Secretary, Logistics, Department for Promotion of Industry, and Internal
Trade (DPIIT)
*****
Abhishek Dayal/Shabbir Azad/Anushka Pandey