Date: 2021-03-16Category: Not ApplicableState: Uttar PradeshCountry: India
वित्तीय वर्ष 2020-21 के आय-व्ययक में बुन्देलखण्ड एक्सप्रेस-वे परियोजना के साथ डिफेन्स कॉरिडोर परियोजना के जनपद अलीगढ में तहसील खैर के ग्राम अण्डला में 33/11 केवीए ििवद्युत उपकेन्द्र, 33 केवीए लाइन, 33 केबी बे व 11 केवी लाइन के ििनर्माणहेतु धनराशि रु0 769.76 लाख की स्वीकृति के सम्बन्ध में।
On March 16, 2021, Anand Kumar Singh, Deputy Secretary of the Government of Uttar Pradesh, issued an order (number 16/2021/579/77-3-2021-147(M)/2020) to the Chief Executive Officer of UPIDA (Uttar Pradesh Expressways Industrial Development Authority) in Lucknow regarding financial approval for the construction of a 33/11 kV power substation (2x5 MVA), 33 kV line, 33 kV bay, and 11 kV line in Andla village, Tehsil Khair, Aligarh district, as part of the Bundelkhand Expressway project and Defence Corridor.
The Government of Uttar Pradesh has approved ₹769.76 lakh (Rupees Seven Crore Sixty-Nine Lakh Seventy-Six Thousand Only) from the budget head "5054- Capital Outlay on Roads and Bridges 03-State Highways 337-Road Construction Work 08-Bundelkhand Expressway Project along with Defence Corridor Project 24-Major Construction Work" for the current fiscal year 2020-21.
Key conditions and restrictions for the release of funds:
* UPIDA will withdraw the funds and make them available to the Executive Engineer, Electricity Distribution Division-I, Aligarh, based on their demand.
* Withdrawals should only be made based on immediate requirements.
* UPIDA will obtain utilization certificates from the Executive Engineer, Electricity Distribution Division-I, Aligarh, and provide them to the government on time.
* Project implementation should adhere to relevant financial rules and regulations.
* Disbursement of funds is subject to proper approval and compliance with relevant office orders, including office memorandum number 1/2020/B-1-149/Ten-2020-231/2020, dated 24/03/2020, Government Order number 4/2020/B-1-192/Ten-2020-231/2020 dated 07/04/2020, Government Order number 5/2020/B-1-196/Ten-2020-231/2020 dated 11.04.2020, 18.05.2020 and 29.09.2020 and all directions issued through other related government orders.
* The approved funds should be used solely for the specified purpose.
* The administrative department must ensure the accuracy of data related to the funds.
This order is being issued with the concurrence of the Finance (Expenditure Control) Section-6.
Copies of the order were sent to various officials, including the Accountant General, Additional Chief Secretary (Energy Department), Chief/Senior Treasury Officer, Managing Director of U.P. Power Corporation Ltd., Director of Financial Statistics Directorate, Private Secretary to Additional Chief Secretary (Industrial Development Department), Finance (E) Section-6, Finance (Income-Expenditure) Section-1, and the Guard File.
The authenticity of the order can be verified on the website http://shasanadesh.up.gov.in.
Key Entities Referenced
Bundelkhand Expressway: Expressway project in Uttar Pradesh, linked to a defence corridor project.
UPIDA (Uttar Pradesh Expressways Industrial Development Authority): Agency responsible for the construction of expressways and industrial development in Uttar Pradesh. Receives the order.
Defence Industrial Corridor: Project linked to Bundelkhand Expressway. Project for which the expenditure is being made.
Aligarh: District in Uttar Pradesh where the substation is being constructed in the village of Andla.
Finance Department: Department that needs to provide approvals for funds to be released.