## Report on Land Acquisition Policy for Eastern Dedicated Freight Corridor Project in Uttar Pradesh
**1. Executive Summary:**
This report analyzes a government notification regarding land acquisition for the Eastern Dedicated Freight Corridor (EDFC) project in the Muzaffarnagar district of Uttar Pradesh. The notification declares the government's intention to acquire land for the project's execution, maintenance, management, and operation. It also outlines the process for affected individuals to raise objections to the acquisition. The key finding is that the policy establishes a defined legal process for acquiring land for a specific railway project, including avenues for grievance redressal.
**2. Introduction:**
This report aims to provide an overview of a government notification pertaining to land acquisition for the Eastern Dedicated Freight Corridor project in the Muzaffarnagar district of Uttar Pradesh, based solely on the provided policy text. The analysis focuses on the objectives, provisions, affected parties, and inferred implementation aspects of this notification.
**3. Policy Overview:**
This is a notification regarding a *new* land acquisition for a specific project.
* **Core Objective(s):** The primary objective, as stated in the text, is to acquire land in the Muzaffarnagar district of Uttar Pradesh for the execution, maintenance, management, and operation of the Eastern Dedicated Freight Corridor (EDFC) project. The policy aims to facilitate the development of this special railway project.
**4. Background and Rationale:**
As a new policy notification, the text suggests that the government requires land to proceed with the Eastern Dedicated Freight Corridor project. The policy likely addresses the need for land acquisition to build and maintain the railway infrastructure. The rationale is to enable the construction and operation of this special railway project for a stated public purpose.
**5. Key Provisions / Changes:**
Since this is a notification for a new land acquisition, the key provisions are:
* **Declaration of Intent:** The Central Government declares its intention to acquire land in the Muzaffarnagar district for the EDFC project.
* **Objection Mechanism:** Individuals with an interest in the land are granted the right to raise objections to the acquisition within 30 days of the notification's publication in the Official Gazette.
* **Competent Authority:** The Additional District Magistrate (Finance and Revenue), Muzaffarnagar, Uttar Pradesh, is designated as the Competent Authority to receive and adjudicate objections.
* **Objection Procedure:** Objections must be submitted in writing, outlining the grounds for the objection. The Competent Authority is required to provide the objector with an opportunity to be heard, either in person or through a legal representative.
* **Order Finality:** Any order issued by the Competent Authority regarding the objections is final.
* **Land Details Availability:** Land plans and other details are available for inspection at the office of the Competent Authority.
* **Brief Land Description:** The provided table includes a brief description of the land to be acquired, including District, Tehsil, Village, Plot Number and area in Hectares.
**6. Target Audience and Stakeholders:**
The primary target audience and stakeholders are:
* Individuals who own land or have an interest in land located in the Muzaffarnagar district of Uttar Pradesh that falls within the area designated for the EDFC project.
* The Competent Authority (Additional District Magistrate, Finance and Revenue, Muzaffarnagar, Uttar Pradesh).
* The Ministry of Railways/Railway Board.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency/Bodies:** The Ministry of Railways (Railway Board) is responsible for initiating the land acquisition. The Additional District Magistrate (Finance and Revenue), Muzaffarnagar, Uttar Pradesh, is responsible for handling objections and making decisions regarding the acquisition.
* **Timelines:** Interested parties have 30 days from the date of publication of the notification in the Official Gazette to raise objections. No other specific timelines are provided in the text.
* **Procedure:** The process involves the government declaring its intention to acquire land, followed by a period for affected individuals to raise objections. The Competent Authority then hears these objections and makes a final decision.
**8. Expected Outcomes / Impact of Changes:**
The intended outcome is the acquisition of land necessary for the construction and operation of the Eastern Dedicated Freight Corridor project. The policy aims to balance the need for infrastructure development with the rights of landowners through the establishment of an objection mechanism and due process. The project is expected to enhance freight transportation efficiency.
**9. Conclusion:**
The government notification outlines the procedure for acquiring land for the Eastern Dedicated Freight Corridor project in the Muzaffarnagar district of Uttar Pradesh. It establishes a framework for land acquisition, including provisions for public consultation and grievance redressal. This policy is significant for facilitating the development of critical railway infrastructure.
Key Entities Referenced
Mayapuri, New Delhi: Location of the Government of India Press.
Railways Act, 1989: An act of the Indian Parliament pertaining to railways. Referenced as the 'said Act' in the document.
Section 20A: Section of the Railways Act, 1989 that grants powers related to land acquisition for railway projects.
Uttar Pradesh: A state in India where land acquisition is taking place for the railway project.
Muzaffarnagar: A district in Uttar Pradesh where land is being acquired for the railway project.
Eastern Dedicated Freight Corridor: A Special Railway Project for which land is being acquired.
Section 20D: Section of the Railways Act, 1989 outlines the process for raising objections to land acquisition.
Additional District Magistrate Finance and Revenue, Muzaffarnagar, Uttar Pradesh: The Competent Authority designated to hear objections related to the land acquisition.
Khatauli: Tehsil in Muzaffarnagar district of Uttar Pradesh where land is being acquired.
Tabita: Village in Khatauli tehsil, Muzaffarnagar district of Uttar Pradesh where land is being acquired.
Railway board: An organization associated with the MINISTRY OF RAILWAYS.
A.K. SINHA: Executive Director LA and SD.
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
xxxGIDHxxx
सी.जी.-डी.एxलx.x-GअID.-E0xx8x0 72021-228173
CG-DL-E-08072021-228173
असाधारण
EXTRAORDINARY
भाग II—खण् ड 3—उप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 2529] नई दिल्ली, बुधवार, िुलाई 7, 2021/ आषाढ़ 16, 1943
No. 2529] NEW DELHI, WEDNESDAY, JULY 7, 2021/ASHADHA 16, 1943
रेल मत्रं ालय
( )
अजधसचू ना
, 6 िुलाई, 2021
का.आ. 2733(अ).—dsUnzh; ljdkj] jys vf/kfu;e] 1989 ¼1989 dk 24½ ¼ftls blesa blds Ik'pkr~ mDr
vf/kfu;e dgk x;k gS½ dh /kkjk 20d dh mi&/kkjk ¼1½ }kjk iznÙk 'kfDr;ks a dk iz;ksx djr s gq,] ;g lek/kku gks tkus ds
i'pkr ~ fd yksd iz;kstu ds fy,] ,slh Hkwfe dk] ftldk laf{kIr fooj.k blls mikc) vuqlwph eas fn;k x;k gS] mÙkj izns'k
jkT; ds eqt¶Qjuxj ftys eas fo'ks’k jsy ifj;kstuk vFkkZr~] bZLVuZ MsMhdsVsM ÝsV dkWfjMksj ds fu"iknu] vuqj{k.k] izca/k
vkSj izpkyu ds iz;kstu ds fy, visf{kr gS] ,slh Hkwfe dk vtZu dju s ds vius vk'k; dh ?kks"k.kk djrh gS(
mDr Hkwfe eas fgrc) dkbs Z O;fDr bl vf/klwpuk ds jkti= eas izdk'ku dh rkjh[k ls rhl fnu dh vof/k ds
Hkhrj] mDr vf/kfu;e dh /kkjk 20?k dh mi&/kkjk ¼1½ ds v/khu iwoksZDr iz;kstu ds fy, ,slh Hkwfe ds vtZu vkSj mi;ksx ds
laca/k eas vk{ksi dj ldsxk(
,slk izR;sd vk{ksi l{ke izkf/kdkjh vFkkZr~] vij ftykf/kdkjh ¼foRr vkSj jktLo½] eqt¶Qjuxj] mRrj izns'k dks
fyf[kr es a fd;k tk,xk vkSj mlesa mlds vk/kkj miof.kZr fd, tk,axs rFkk l{ke izkf/kdkjh] vk{ksidrkZ dks oS;fDrd :i ls
;k fof/k O;olk;h ds ek/;e ls lquokbZ dk volj iznku djsxk vkSj ,sl s lHkh vk{ksika s dh lquokbZ djus rFkk ,slh vkSj
tkpa ] ;fn dkbs Z gks] rks bl s dju s ds i'pkr~] tks l{ke izkf/kdkjh vko';d le>s vkns'k }kjk vk{ksiks a dks ;k rks vuKq kr ;k
vuuqKkr dj ldsxk(
mDr vf/kfu;e dh /kkjk 20?k dh mi&/kkjk ¼2½ ds v/khu l{ke izkf/kdkjh }kjk fd;k x;k dkbs Z vkns'k vafre
gksxk(
bl vf/klwpuk ds v/khu vkus okyh Hkwfe dk js[kkadu vkSj vU; C;kSj s miyC/k gS vkSj fgrc) O;fDr }kjk
l{ke izkf/kdkjh ds mijksDr dk;kZy; es a mudk fujh{k.k fd;k tk ldrk gSA
3760GI/2021 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
mRrj izns'k jkT; ds eqt¶Qjuxj ftys es a fo'ks"k jys ifj;kstuk vFkkZr bZLVuZ MsMhdsVMs ÝsV dksjhMksj ds fy, lajpuk lfgr
;k mlds fcuk vftZr dh tku s okyh Hkwfe dk laf{kIr fooj.kA
(1) (3) (4) (5) (6)
1 [krkSyh VfcVk 86 0.0270
[फा. सं. II )]
,
MINISTRY OF RAILWAYS
(Railway board)
NOTIFICATION
New Delhi, 6th July, 2021
S.O. 2733(E).— In exercise of the powers conferred by sub-section (1) of Section 20A of the Railways Act,
1989 (24 of 1989) (hereinafter referred to as the said Act), the Central Government after being satisfied that for the
public purpose the land the brief description of which is given in the schedule annexed hereto is required for the
purpose of execution, maintenance, management and operation of the Special Railway Project namely, Eastern
Dedicated Freight Corridor in the district of Muzaffarnagar in the State of Uttar Pradesh hereby declares its intention
to acquire such land;
Any person interested in the said land may within a period of thirty days from the date of publication of this
notification in the Official Gazette, raise objection to the acquisition of such land for the aforesaid purpose under sub-
section (1) of Section 20D of the said Act;
Every such objection shall be made to the Competent Authority namely, Additional District Magistrate
(Finance and Revenue), Muzaffarnagar, Uttar Pradesh in writing and shall set out the grounds thereof and the
Competent Authority shall give the objector an opportunity of being heard either in person or by legal practitioner and
may after hearing all such objections and after making such further enquiry if any as the Competent Authority thinks
necessary by order either allow or disallow the objections;
Any order made by the Competent Authority under sub-section (2) of Section 20D of the said Act shall be
final;
The land plans and other details of the land covered under this notification are available and can be inspected
by the interested person at the aforesaid office of the Competent Authority.
SCHEDULE
Brief description of the land to be acquired with or without structure for the Special Railway Project namely,
Eastern Dedicated Freight Corridor in the district of Muzaffarnagar in the State of Uttar Pradesh.
District- Muzaffarnagar
Area
Sr. No. Tehsil Village Plot No.
(in hect.)
(1) (3) (4) (5) (6)
1 Khatauli Tabita 86 0.0270
[F. No. 2021/LML-II/12/2/EC/2165]
A.K. SINHA, Executive Director (L&A and SD)
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.