## Policy Analysis Report: Land Acquisition for Wadsa Gadchiroli New BG Rail Line Project
**1. Executive Summary:**
This report analyzes a government notification regarding the acquisition of land for the Wadsa Gadchiroli New BG Rail line project (49.50 KM) in the Gadchiroli District of Maharashtra, based on a provided notification. The notification, essentially an amendment related to land acquisition, declares that the specified land will be acquired for the project's execution, maintenance, management, and operation. Key findings are that objections were received, heard, and addressed according to the Railways Act, and that the Central Government now declares the specified land to be acquired and vested absolutely in the Central Government, free from all encumbrances, after the notification's publication.
**2. Introduction:**
The purpose of this report is to provide an informative analysis of a government policy notification concerning land acquisition for the Wadsa Gadchiroli New BG Rail line project. This analysis is based solely on the provided policy text.
**3. Policy Overview:**
This notification amends a previous notification (S.O. 3162E, dated 05th July, 2022) regarding the intention to acquire land for the Wadsa Gadchiroli New BG Rail line project.
* **Core Objective:** The primary objective, as inferred from the text, is to facilitate the execution, maintenance, management, and operation of the Wadsa Gadchiroli New BG Rail line project by acquiring the necessary land.
**4. Background and Rationale:**
The notification details the progression of the land acquisition process, starting with the declaration of intent to acquire land and subsequent publication in local newspapers. The fact that the notification mentions "objections were received; Competent Authority has heard the objections and orders have been passed" suggests that there were challenges or disputes regarding the land acquisition, requiring a formal process of hearing and resolution. This notification effectively confirms the completion of that process and the progression to the next stage: the actual acquisition.
**5. Key Provisions / Changes:**
This notification serves as the final declaration of land acquisition. The key changes/provisions are:
* **Confirmation of Acquisition:** The Central Government declares that the land specified in the schedule annexed to the notification *shall* be acquired for the Wadsa Gadchiroli New BG Rail line project.
* **Land Vesting:** Upon publication of the notification in the Official Gazette, the land specified in the schedule will vest absolutely in the Central Government, free from all encumbrances. This signifies the transfer of ownership to the government and the removal of any existing claims or liabilities on the land.
**6. Target Audience and Stakeholders:**
Based on the provided text, the direct target audience and stakeholders include:
* **Landholders:** Those individuals and entities whose land is listed in the schedule and is being acquired. The notification lists names and addresses of landowners affected.
* **Local Residents of Gadchiroli District:** As the land acquisition impacts land use in the area, this notification is of interest to the community.
* **The Ministry of Railways:** The project's success relies on the successful acquisition and vesting of the land, as the rail line construction requires the land to be owned by the government.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency:** The Ministry of Railways, specifically the South East Central Railway, is the responsible agency. The "Competent Authority" is also mentioned as being involved in hearing objections and submitting a report.
* **Timelines/Procedures:** The notification triggers a process upon publication. After its publication, the land vests in the Central Government.
* The land acquisition is managed according to the Railways Act, 1989, with specific sections (20A, 20D, and 20E) being referenced in the document.
**8. Expected Outcomes / Impact of Changes:**
The intended outcome of this notification is to clear the way for the Wadsa Gadchiroli New BG Rail line project to proceed without further delays related to land acquisition. The land will be legally transferred to the Central Government, ensuring its availability for the project's construction and operation. The landholders will be affected.
**9. Conclusion:**
This policy analysis report has examined a government notification concerning land acquisition for the Wadsa Gadchiroli New BG Rail line project. The notification signifies the culmination of the land acquisition process, with the land now vesting absolutely in the Central Government. This is a crucial step for the successful implementation of the railway project.
Key Entities Referenced
Railways Act, 1989: A law under which the land acquisition is being carried out.
Ministry of Railways: The government ministry responsible for the railway project.
South East Central Railway: The specific railway zone involved in the land acquisition.
Wadsa Gadchiroli New BG Rail line 49.50 KM Project: The special railway project for which land is being acquired.
Gadchiroli District: The district in Maharashtra where the project is located.
Maharashtra: The state in which Gadchiroli District is located.
Mahasagar Gadchiroli Edition: A local newspaper in Gadchiroli.
Dhawanilahri Gadchiroli Edition: A local newspaper in Gadchiroli.
Adpalli: Village in Gadchiroli District, Maharashtra
Gogaon: Village in Gadchiroli District, Maharashtra
Mahadwadi: Village in Gadchiroli District, Maharashtra
shakhara: Village in Gadchiroli District, Maharashtra
Mohjharee: Village in Gadchiroli District, Maharashtra
Lanjheda: Village in Gadchiroli District, Maharashtra
H. P. Tripathi: Chief Admn. Officer Con.
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
सी.जी.-सी.जी.-अ.-29112022-240629
xxxGIDHxxx
CG-CG-E-29112022-240629
xxxGIDExxx
असाधारण
EXTRAORDINARY
भाग II—खण् ड 3—उप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 5278] नई ददल्ली, सोमर्ार, नर्म्ि र 28, 2022/अग्रहायण 7, 1944
No. 5278] NEW DELHI, MONDAY, NOVEMBER 28, 2022/AGRAHAYANA 7, 1944
रेल मत्रं ालय
(दजिण पूर् वमध्य रेलर्)े
अजधसचू ना
जिलासपुर, 25 नर्म् िर, 2022
का.आ. 5508(अ).—dsUnhz; ljdkj u s jys vf/kfu;e] 1989 ¼1989 dk 24½ ¼ftlds पश्चात vf/kfu;e dgk x;k gS½ dh /kkjk
20d dh mi/kkjk ¼1½ ds v/khu tkjh] Hkkjr ds jkti=] vlk/kkj.k] Hkkx II [k.M 3] mi[k.M ¼ii½] rkjh[k 05 tqykbZ 2022 es a izdkf”kr]
Hkkjr ljdkj ds jys ea=ky; ¼nf{k.k iwo Z e/; jys os½ dh vf/klpw uk l[a ;k dk vk- 3162 ¼v½ 11 tqykbZ 2022 }kjk mDr vf/klwpuk ls
mikc) vulq pw h es a fofufnZ’V dks egk + + jkT; ds xMfpjksyh ftys es a fo'ks"k jsy ifj;kstuk] vFkkZr oMlk xMfpjksyh
राष्ट
czkWM xts ifj;kstuk ¼49-5 fd-eh-½]ds fu’iknu] vuqj{ku] izca/k vkSj izpkyu ds iz;kstu ds fy, vftZr djus ds viu s vk'k; dh /kks"k.kk
dh Fkh]
vkSj mDr vf/klwpuk dk lkj] mDr vf/kfu;e dh /kkjk 20d dh mi/kkjk ¼4½ ds v/khu nfSud LFkkuh; lekpkj i=ksa] vFkkZr
egklkxj ¼ xMfpjksyh lLa dj.k½ rkjh[k 04 vxLr 2022 ,oa /ofuygjh ¼xMfpjksyh lLa dj.k½ rkjh[k 04 vxLr 2022 dks izdkf'kr
fd;k x;k FkkA
vkSj l{ke izkf/kdkjh dks vk{ksi izkIr gq, Fks( l{ke vf/kdkjh }kjk mu vk{ksiks a dh luq okbZ dh x;h ,ao mDr vf/kfu;e dh /kkjk
20?k ds vuqlj.k es a vkn's k ikfjr dj fn;s x, gaS(
vkSj l{ke izkf/kdkjh u s mDr vf/kfu;e dh /kkjk 20M + dh mi/kkjk ¼1½ ds vuqlj.k es a viuh fjiksVZ lkSai nh gSA
vr% vc] dsUnhz; ljdkj] l{ke izkf/kdkjh ls fjiksVZ izkIr gksus ij vkSj mDr vf/kfu;e dh /kkjk 20M + dh mi/kkjk ¼1½ }kjk
iznRr “kfDr;ksa dk iz;ksx djrs gq,] ;g ?kks’k.kk djrh gS fd mikc) vulq pw h Hkwfe fofufnZ’V Hkwfe iqoksDZ r iz;kstu ds fy, vftZr dh
tk,xhA
7877 GI/2022 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
vr% ;g fd dsUnhz; ljdkj mDr vf/kfu;e dh /kkjk 20M+ dh mi/kkjk ¼2½ ds vulq j.k es a ;g ?kks"k.kk djrh gS fd bl
vf/klwpuk es a jkti= es a izdkf'kr gksus ij bll s mikc) vulq pw h esa fofufnZ’V Hkwfe lHkh foYyaxeksa ls eqDr gksdj dsUnhz; ljdkj es a
vkR;afrd :i ls fufgr gks tk,xhA
विशेष
Lkaijnuk
7@12
dz- ftys dk rglhy xkao dk HkksxoVnkj [kkyhy
[kkrns kj dk uke vkSj irk losZ dza- vkjkth gs-
la- uke dk uke uke ox Z {ks= g-s
vkj
vkj
1 xMfpjksyh xMfpjksyh vMiYyh l[kqckbZ ;kno pkS/kjh o vU; 7 106 0-12 1 0-01
1 xMfpjksyh xMfpjksyh Xkksxko ;”onkckbZ Jko.k dkacys o vU; 9 168 0-54 1 0-15
1 foBksck odV q MksbZtM 57 0-40 1 0-11
2 y{ke.k FkksVw Hkks;kj vU; 28 55 2-38 2 0-37
3
xMfpjksyh xMfpjksyh egknokMh
Lkat; nos jko cko.ks o vU; 28 118 4-26 1 0-010
d`’.kkuna rqdkjke HkjMdj o vU;
4 19@1 1-25 1 0-01
20
1 Hkkmjko tSjke xk;dokM o vU; 6 180 0-77 1 0-16
2 fejk l[kkjke yksgkV o vU; 42 199 1-20 1 0-24
xMfpjksyh xMfpjksyh Lkk[kjk
3 izHkkckbZ ukenos xsMke o vU; 20 241 0-30 1 0-10
4 fnudj eq[k: uSrke o vU; 20 242 0-18 1 0-01
1 fouksn ek/ko oMiYyhokj o vU; 0-40
40@1 1 0-001
eaxs”k Qfdjkth HkjMdj 1-24
2 xMfpjksyh xMfpjksyh eksg>jh
l[q knos [kq”kky Hkks;j o vU; 1 40@2 0-82 1
3 fxjh/kj gjck tqeukds o vU; 12 38 1-28 1 0-06
mekth nos kth rkokM s 638@2@v
1 1
xMfpjksyh xMfpjksyh xMfpjksyh 0-91 0-02
fnuegaen xyq keglq us dMhoky o
638@2@ि
vU; 1
1 :’kh cqpk “ksMa s o vU; 12 310 0-56 1 0-04
2 ryq ”khjke Jko.k “ksMa s o vU; 6 309 0-44 1 0-001
3 vryq d`’.kjko cksjdj 302@2 0-62 1 0-10
4
HkkLdj ckykth dkacys o vU; 17 285 2-60 1 0-50
5
xMfpjksyh xMfpjksyh yk>sMa k vryq d`’.kjko cksjdj 287 0-64 1 0-20
6
dkrhZd lqdnos dksdksMs o vU; 10 366 1-20 1 0-78
7 Ik=kckbZ tkxksth /kqoZ s o vU; 8 203 2-27 1 0-43
8 fnyhi iqMa fyd xsMke o vU; 8 38@1 0-28 2 0-11
9 oanuk v”kskd xsMke 38@2 0-27 1 0-12[भाग II—खण् ड3(ii)] भारत का रािपत्र : असाधारण 3
10
fnokdj nsojko gksyh o vU; 11 35@3 0-18 1 0-18
11 fot; iq:’kksRre dksriYyhokj o vU; 2 34 1-12 1 0-05
12 fyyk/kj dk”khukFk dksdksMs o vU; 4 33 0-55 1 0-05
13 vful fijeksgEen duksts o vU; 5 30 0-51 1 0-06
14 foykl “kadjjko cYyeokj o vU; 5 29 0-58 1 0-02
15 foykl “kadjjko cYyeokj o vU; 5 28 0-55 1 0-009
16 Eaknk jkts”k Mksaxj s 27@2 0-30 1 0-30
17 “kadjjko eYyukth tDdqyokj vU; 3 27@4 0-0650 1 0-0650
18 vCnqy c”khj vCnqy d¸;qe “ks[k 27@5 0-0093 1 0-0093
19 Ekukst izsepan cgsrh 27@5@1 0-0470 1 0-0470
20 Ukkenos “kkyhdjke cudj 0-0186 1 0-0186
27@6
v”kksd lksekth jktxMdj 0-0186 1 0-0186
21 iq’ik lHqkk’k dkoys o vU; 1 27@6@1@v 0-0380 1 0-0380
xMfpjksyh xMfpjksyh yk>sMa k
22 Izkdk”k iaMhrjko dkoys 26@1 0-3650 1 0-3300
23 vjfoan eqjyh/kj fVxa lq ys o vU; 3 14@32 2-02 2 0-30
24 vkseizdk”k vkMdqth ckacksys o vU; 10 14@33 2-02 2 0-18
25 dfork xksfoa ank uSrke o vU; 17 22@1 0-4968 2 0-003
[फा. सं. lh-,-vks-@lh-@ch-,l-ih-@oMlk&xMfpjksyh@xMfpjksyh ftyk@ xMfpjksyh@20b]
एच. पी. जत्रपाठी, मुख् य प्रिासजनक अजधकारी (जनमावण)
MINISTRY OF RAILWAYS
(SOUTH EAST CENTRAL RAILWAY)
NOTIFICATION
Bilaspur, the 25th November, 2022
Notice under Section 20E of the Railway Act, 1989
S.O. 5508(E).—Whereas, by the notification of the Government of India in the Ministry of Railways
(South East Central Railway), number S.O. 3162(E), dated the 05th July, 2022 published in the Gazette of India,
Extraordinary, Part-ii, section 3, Sub-section (ii), dated the 11th July, 2022 and issued under sub-section (I) of
section 20A of the Railways Act, 1989 (24 of 1989)(here in after referred as the said Act), the Central
Government declared its intention to acquire the land in the schedule annexed to the said notification for the
purpose of execution, maintenance, management and operation of the Special Railway Project namely “Wadsa –
Gadchiroli New BG Rail line (49.50 KM) Project” in Gadchiroli District in the State of Maharashtra
And whereas, the substance of the said notification has been published in the daily local newspapers,
namely, Mahasagar (Gadchiroli Edition) of dated 04th August, 2022 & Dhawanilahri (Gadchiroli Edition) of dated 04th
August, 2022 under sub-section (4) of section 20A of the said Act;
And whereas, objections were received; Competent Authority has heard the objections and orders have
been passed in terms of section 20 D of the said act;
And whereas,in pursuance of sub-section (1) of section 20E of the said Act, the Competent Authority
has submitted its report to the Central Government.
Now therefore, upon receipt of the report of the Competent Authority and in exercise of the powers conferred
by sub- section (1) of section 20E of the said Act, the Central Government hereby declares that the land specified in
the Schedule annexed hereto shall be acquired for the aforesaid purpose.
And further, in the pursuance of sub-section (2) of section 20E of the said Act, the Central Govt. hereby
declares that on publication of the notification in the Official Gazette, the land specified in the Schedule annexed hereto
shall vest absolutely in the Central Government free from all encumbrances.4 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
SCHEDULE
Brief description of the land to be acquired, with or without structures for the Special Railway Project “Wadsa –
gadchiroli New BG Rail line (49.50 KM) Project” in Gadchiroli District in the State of Maharashtra
District - Gadchiroli State – Maharashtra
Wadsa - Gadchiroli new Broad Gauge line
Total
Survey Category Acquisi-
Sl. Name of Name of Name of Name of Land holder & area as
Numbe of Land tion Area
No. District Taluka Village Address per 7/12
r holding in (Ha.)
(Ha)
1 2 3 4 5 6 7 8 9
Sakhubai Yadav Chaudhari
1 Gadchiroli Gadchiroli Adpalli 106 0.12 1 0.01
and Other 7
Yashvadabai Shravan Kamble
1 Gadchiroli Gadchiroli Gogaon 168 0.54 1 0.15
and Other 9
1 Vithoba Vaktu Doeejad 57 0.40 1 0.11
Lakhsman Thotu Bhoyar and
2 55 2.38 2 0.37
Other 28
Gadchiroli Gadchiroli Mahadwadi Sanjay Deorao Bawne and
3 118 4.26 1 0.010
Other 28
Krishnanand Tukaram
4 19/1 1.25 1 0.01
Bhardkar and Other 20
Bhaurao Jairam Gayakvad and
1 180 0.77 1 0.16
Other 6
Mira Sakharam Lohat and
2 199 1.20 1 0.24
Other 42
Gadchiroli Gadchiroli shakhara
Prabhabai Namdev Gedam and
3 241 0.30 1 0.10
Other 20
Dinkar Mukharu Naitam and
4 242 0.18 1 0.01
Other 20
Vinod Madhav Wadpalliwar
1 0.40
and Other 40/1
Mangesh Fakiraji Bhardkar 1.24 1 0.001
2 Gadchiroli Gadchiroli Mohjharee Sukhdev Khushal Bhoyar and
40/2 0.82
others 1
Gireedhar Harba Jumnake and
3 38 1.28 1 0.06
Other 12
Umajee Devajee Tavade 638/2/अ
1
1 Gadchiroli Gadchiroli Gadchiroli 0.91 0.02
Dinmahnmad Gulamhusen
Kadeeval and Other 1
638/2/ब
Rushee Bucha Shende and
1 310 0.56 1 0.04
Other 12
Tulsheeram Shravan Shende
2 309 0.44 1 0.001
and Other 6
Gadchiroli Gadchiroli Lanjheda
3 Atul Krushnarao Borkar 302/2 0.62 1 0.10
Bhaskar Balajee Kamble and
4 285 2.60 1 0.50
Other 17
5 Atul Krushnarao Borkar 287 0.64 1 0.20[भाग II—खण् ड3(ii)] भारत का रािपत्र : असाधारण 5
Karteek Sukdev Kokode and
6 366 1.20 1 0.78
Other 10
Patrabai Jagojee Dhurve and
7 203 2.27 1 0.43
Other 8
Dileep Pundlik Gedam and
8 38/1 0.28 2 0.11
Other 8
9 Vandana Ashok Gedam 38/2 0.27 1 0.12
Divakar Devrao Holee and
10 35/3 0.18 1 0.18
Other 11
Vijay Purushottam Kotpallivar
11 34 1.12 1 0.05
and Other 2
Liladhar Kasheenath Kokode
12 33 0.55 1 0.05
and Other 4
Anis Pirmahmad Kanoje and
13 30 0.51 1 0.06
others 5
Vilas Shankarrao Ballamvar
14 29 0.58 1 0.02
and Other 5
Vilas Shankarrao Ballamvar
15 28 0.55 1 0.009
and Other 5
16 Manda Rajesh Dongre 27/2 0.30 1 0.30
Shankararao Mallnajee
17 27/4 0.0650 1 0.0650
Jakkulvar & Other 3
Abdul Basheer Abdul Kayyum
18 27/5 0.0093 1 0.0093
Shekh
19 Manoj Premchand Baheti 27/5/1 0.0470 1 0.0470
Namdeo Shaleekram Bankar 0.0186 1 0.0186
20 27/6
Ashok Somajee Rajgadkar 0.0186 1 0.0186
Pushpa Subhash Kavle and
21
Other 1
27/6/1/अ 0.0380 1 0.0380
22 Prakash Pandeetrao Kavle 26/1 0.3650 1 0.3300
Arvind Murleedhar Tingusle
23 14/32 2.02 2 0.30
and Other 3
Omprakash Aadkujee Bambole
24 14/33 2.02 2 0.18
and Other 10
Kavita Govinda Naitam and
25 22/1 0.4968 2 0.003
others 17
[F. No. CAO/C/BSP/Wadsa – Gadchiroli/Gadchiroli Dist/ Gadchiroli /20E]
H. P. TRIPATHI, Chief Admn. Officer (Con.)