**1. Executive Summary:**
This report analyzes a notification, S.O. 2763(E), issued by the Ministry of Railways, South Eastern Railway Construction Organization, designating a railway project in Jharkhand as a "Special Railway Project." The core purpose, inferred from the text, is to expedite the "3rd line 4th line work between Sini and Kandra" to enhance railway infrastructure in the region. The key finding is that the notification invokes powers under the Railways Act of 1989 to grant special status to this specific project.
**2. Introduction:**
This report provides an overview and analysis of Notification S.O. 2763(E), pertaining to a Special Railway Project, based solely on the information contained within the provided document. The report aims to inform stakeholders about the policy's provisions, implications, and potential impact.
**3. Policy Overview:**
* This appears to be a *new policy* notification rather than an amendment.
* **Core Objective(s):** Based on the provided text, the primary objective is to officially designate the "3rd line 4th line work between Sini and Kandra" project in Jharkhand as a "Special Railway Project." This designation likely aims to facilitate faster project implementation, potentially through streamlined processes or prioritization of resources.
**4. Background and Rationale:**
* **New Policy Rationale:** The notification designates a specific railway construction project as "Special." The likely rationale is to address existing rail infrastructure limitations. The addition of 3rd and 4th lines suggests a need to increase capacity and reduce congestion on the Sini-Kandra route. Declaring it a "Special Railway Project" implies the government views this upgrade as strategically important for regional development or transportation efficiency.
**5. Key Provisions / Changes:**
* **New Policy Provisions:** This notification officially designates the "3rd line 4th line work between Sini and Kandra 12.53 Km." project in Jharkhand as a "Special Railway Project" under clause 37A of section 2 of the Railways Act, 1989. The effective date is the date of publication in the Official Gazette (June 20, 2025). The document cites the specific file number for this project: F. No. SERCONOrgn.HQLandDCECTATASINIKANDRA 3rd 4th lineSRP1. This designation grants the project certain special considerations and powers under the Railways Act.
**6. Target Audience and Stakeholders:**
Based on the text, the direct stakeholders include:
* **South Eastern Railway Construction Organization:** The agency responsible for the project's execution.
* **Ministry of Railways:** The governing body initiating and overseeing the project.
* **Residents and Businesses along the Sini-Kandra Route (Jharkhand):** Potentially affected by land acquisition, construction, and eventual operation of the new railway lines.
* **Rail users in the region:** Who will benefit from the increased capacity and efficiency of the upgraded railway line.
* **Contractors and Suppliers:** Involved in the construction and material provision for the project.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency/Bodies:** South Eastern Railway Construction Organization (SERCON).
* **Timelines/Procedures:** The notification takes effect immediately upon publication (June 20, 2025). Specific procedures for land acquisition, construction, and project management are likely governed by the Railways Act, 1989 and related guidelines, but are not detailed in this text. The file number provided could be useful for further inquiries.
**8. Expected Outcomes / Impact of Changes:**
* **Likely Intended Outcomes:** The designation of the Sini-Kandra railway work as a "Special Railway Project" is expected to:
* Accelerate project completion.
* Improve railway capacity and efficiency on the Sini-Kandra route.
* Contribute to regional economic development by facilitating smoother transportation of goods and passengers.
* Potentially streamline land acquisition and regulatory approvals.
**9. Conclusion:**
Notification S.O. 2763(E) marks a significant step in upgrading railway infrastructure in Jharkhand by designating the Sini-Kandra 3rd and 4th line project as a "Special Railway Project." This designation, under the Railways Act of 1989, is intended to expedite the project and improve railway connectivity in the region. Stakeholders should be aware of the implications of this designation and monitor the project's progress. This analysis is based solely on the provided text, and further information may be required for a more comprehensive understanding.
Key Entities Referenced
Railways Act, 1989: An act of parliament cited as the source of power for the notification.
Central Government: The governing authority issuing the notification.
Special Railway Project: A designated category for the project being notified.
South Eastern Railway Construction Organization: The railway organization that is the subject of the notification.
Kolkata: City where the notification was issued.
Sini: Starting point of railway line work, located in Jharkhand.
Kandra: End point of railway line work, located in Jharkhand.
Jharkhand: The State where the railway project is located.
3rd line 4th line work between Sini and Kandra: Description of the railway project.
RAJEEV SHRIVASTAVA: Chief Admin.OfficerConSER
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
सी.जी.-डब्लू.बी.-अ.-20062025-264013
CG-WxBx-xEG-I2D0H0x6x2x0 25-264013
xxxGIDExxx
असाधारण
EXTRAORDINARY
भाग II—खण्ड 3—उप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 2697] िई कदलली, िुक्रर्ार, ििू 20, 2025/ज्य ष्े ठ 30, 1947
No. 2697] NEW DELHI, FRIDAY, JUNE 20, 2025/JYAISTHA 30, 1947
रेल मत्रं ालय
[दजिण पर्ू व रेलर् े (जिमाणव सगं ठि)]
अजधसचू िा
कोलकाता, 20 िूि, 2025
का.आ. 2763(अ).—केंद्रीय सरकार, रेल अजधजियम, 1989 की धारा 2 के खडं (37क) द्वारा प्रदत्त िजियों का
प्रयोग करते हुए, रािपत्र म ें इस अजधसूचिा के प्रकािि की तारीख स,े सारणी के स्ट्तम्भ (3) म ें उजललजखत राज्य के िीच े
सारणी के स्ट्त म्भ (2) म ें यथा-उजललजखत जर्िेष रेल पररयोििा के रूप म ें जिम्िजलजखत पररयोििा को अजधसूजचत करती
ह ै।
सारणी
क्रम स.ं पररयोििा का िाम राज्य / केंद्र िाजसत प्रदेि
(1) ( 2) ( 3)
1 जसिी और कांड्रा के बीच तीसरी और चौथी लाइि का काय व (12.53 ककमी.)। झारखंड
[फा. सं. दपरू े/जिमाणव -संगठि/मख्ु यालय/डीसीई/सी/टाटा/जसिी-कांड्रा तीसरी और चौथी लाइि /एसआरपी/1]
रािीर् श्रीर्ास्ट्तर्, मुख्य प्रिासजिक अजधकारी (जिमावण)/द.पू.रेलर् े
4040 GI/2025 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
MINISTRY OF RAILWAYS
[South Eastern Railway (Construction Organization)]
NOTIFICATION
Kolkata, the 20th June, 2025
S.O. 2763(E).—In exercise of the powers conferred by clause (37A) of section 2 of the Railways Act,1989,
the Central Government hereby notifies the following project as Special Railway Project, as mentioned in column (2)
of the Table below in the State mentioned in column (3) of the Table, with effect from the date of publication of this
notification in the Official Gazette.
TABLE
Sl. Name of Projects State/Union Territory
No.
(1) (2) (3)
1 3rd line & 4th line work between Sini and Kandra (12.53 Km.) Jharkhand
[F. No. SER/CON-Orgn./HQ/Land/DCE/C/TATA/SINI-KANDRA 3rd & 4th line/SRP/1]
RAJEEV SHRIVASTAVA, Chief Admin.Officer(Con)/SER