This document is the Record of Discussion for the 132nd meeting of the PPPAC held on August 8th, 2025, concerning two road proposals from the Ministry of Road, Transport & Highways (MoRTH) to be developed under the PPP model. One project was recommended with stipulations, while the other, concerning the construction of a highway in Karnataka, was deferred pending further information from MoRTH. The document contains a list of attendees.
**Key Points / Main Content**
* **Project 1: 4-laning of NH-167 in Telangana**
* Project Details:
* 4-laning of NH-167 from Gudebellur to Mahabubnagar (Hyderabad-Panaji section)
* Length: 80.01 km
* Hybrid Annuity Mode (HAM)
* Implementing Agency: National Highways Authority of India (NHAI)
* Estimated Total Capital Cost: Rs. 2574.34 crore.
* The PPPAC unanimously recommended the proposal, subject to the following:
* MoRTH to submit a revised BOT analysis, and the mode and capital cost of the project will be recommended in the next PPPAC meeting.
* MoRTH to formulate a standardized guideline/SOP to determine appropriate parameters for developing an access-controlled corridor.
* For future projects, MoRTH must submit the assumptions used to estimate PIB cost and current proposed cost, along with justifications for variation, with the PPPAC proposal.
* The cost of debt is to be considered as per prevailing lending rates for future projects
* For all future projects, the project shall be justified not only on traffic volumes measured in PCUs, but also in terms of the Level of Service (LoS) requirements.
* Revalidation of Recommendation:
* Revalidation by PPPAC is not required for the following:
* Changes in date/time for time-bound actions
* Non-substantial change in risk-allocation
* Changes/modifications to make the project successful
* MoRTH/NHAI may decide if the changes fall within the threshold criteria as stated above.
* **Project 2: Access Controlled Highway in Karnataka**
* Construction of Access Controlled Highway of 4-Lane with Paved Shoulders from Ranganathpura to Keresooragondanahalli in Hassan Hiriyur section (EC-20) in Karnataka on HAM under NH (O).
* The project was deferred until MoRTH provides responses to the PPPAC's observations (documented in Annexure-II).
**Impact Analysis**
* **MoRTH (Ministry of Road Transport & Highways)**
* **Impact:** Needs to address queries and observations raised by PPPAC, including justifications for cost escalations, reassessment of viability, and providing standardized guidelines. Responsible for BOT reassessment.
* **Action Required:** Provide revised BOT analysis for the Telangana project. Submit responses to the observations regarding the Karnataka project (Annexure-II). Develop a SOP. Submit project cost with justifications for future projects.
* **NHAI (National Highways Authority of India)**
* **Impact:** Responsible for implementing the approved project and providing necessary documentation.
* **Action Required:** Implement approved project.
* **Department of Economic Affairs**
* **Impact:** Forwarding the Record of Discussion of the PPPAC for the consideration of the road proposals.
* **Action Required:** For information and necessary action.
* **Secretary, Department of Expenditure**
* **Impact:** Responsible for expenditure.
* **Action Required:** For information and necessary action.
* **CEO, NITI Aayog**
* **Impact:** Responsible for analysis.
* **Action Required:** For information and necessary action.
* **Secretary, Department of Legal Affairs**
* **Impact:** Responsible for legal affairs.
* **Action Required:** For information and necessary action.
Key Entities Referenced
Public Private Partnership Appraisal Committee (PPPAC) : Committee responsible for appraising PPP projects; the Record of Discussion documents the committee's 132nd meeting.
Ministry of Road Transport and Highways (MoRTH) : The ministry that proposed the road projects considered in the meeting.
NH-167 : National Highway 167, the subject of the first road project proposal discussed.
National Highways Authority of India (NHAI) : The implementing agency for the road projects discussed.
Hybrid Annuity Mode (HAM) : The model under which the road projects are proposed to be executed.
See Full Document Text
F.No.2/11/2025-PIU
Government of India
Ministry of
Finance
Department of
Economic Affairs
Infrastructure Finance
Secretariat
ISD Division
(PIU)
KKKKK
4' Floor, STC Building,
Janpath, New
Delhi-01
Dated: 3"
September, 2025
Record of Discussion
Subject: Record of Discussion of the 132" meeting of the PPPAC for considering two
road proposals of the Ministry of Road, Transport & Highways (MoRTH) on PPP mode.
Sir/Madam,
The undersigned is directed to forward the Record of Discussion of the 132TM meeting of
the PPPAC held on 08" August 2025 under the chairmanship of Secretary (EA) for information
and necessary action.
yy
This issues with the approval of the Competent Authority.
2.
(Arya Balan Kumari)
Joint Director (PIU)
011-2370 1219
To,
Secretary, Department of Expenditure, North block, New Delhi-01
1:
CEO, NITI Aayog, Yojana Bhawan, New Delhi-01
2.
Secretary, Ministry of Road, Transport & Highways, Transport Bhawan, New
3.
Delhi.
Secretary, Department of Legal Affairs, Shastri Bhawan, New Delhi.
4.
Copy to:
Sr. PPS to Secretary (EA)
1.
PSO to JS (ISD)
2.
Page 1 of 11Subject: Record of Discussion of the 132TM meeting of the PPPAC for considering the
following proposals: -
(i) 4 laning of NH-167 from Gudebellur to
Mahabubnagar of Hyderabad-
Panaji section under NH(O) on HAM in the State of Telangana;
(ii)
Construction of Access Controlled Highway of 4-Lane with Paved
Shoulders from
Ranganathpura (Hassan) to
Keresooragondanahalli in
Hassan Hiriyur section (EC-20) in Karnataka on HAM under NH (O).
1. The 132" meeting of the PPPAC was held on 08" August 2025 at 12:15 hours to
consider the above proposals of MoRTH.
2. List of attendees is placed at Annexure-l.
3. With the permission of Secretary (EA), Joint Secretary (ISD) welcomed all the attendees
to the meeting. NHAI made a detailed presentation on the proposed road projects.
(i) 4 laning of NH-167 from Gudebellur to
Mahabubnagar of
Hyderabad-Panaji
section under NH(O) on HAM in the state of Telangana
4. The details of the project are given in the table below:
Table-1: Details of the project
4 laning of NH-167 from Gudebellur at Design Km.182+930 to
prsiect Deccription
Mahabubnagar at Design Km 262+940 of
Hyderabad-Panaji
foe P section (length 80.01km) under NH(O) on HAM in the state off
Telangana
PPP Model
Hybrid Annuity Mode
Sponsoring
Ministry of Road Transport and Highways, Government of India
Authority
implementing
National Highways Authority of India (NHAI)
Agency
State: Telangana
ocati
ocean
District: Narayanpet & Mahabubnagar
Type of Pavement | Flexible
Lane
configuration | 4-lane
S. |Description
Details a
N
:
80.01 km
T| Length
Details of
Structures
2 Major Bridges _ e 05 Nos.
3 | Minor Bridges
36 Nos.
189 Nos.
4 | Culverts5 | Interchange Nil
6 | Viaduct 01 Nos. |
7 | Vehicular Overpass (VOP) _Nil
8 | Proposed RoW 60m
9 | VUP | 11 Nos.
10) LVUP 22 Nos
11| Animal Underpass (AUP) Nil
12) Truck lay bays 03 Nos.
13] ROB/RUB 01 No. /01 No. |
14} Toll Plaza 02 Nos.
15] Minor Junctions 14 Nos.
16] Service Road / Slip Road 15.34km/55.12km |
17) Bus-bays/ Shelters Nil / 54 Nos.
18) Rest Area with Wayside 01 (Area= 3.5 ha)
Amenities
19} Design Traffic (MSA) 70
20] Bypass / Realignments 04 Nos for 21.27 km /
07 Nos. for 15.53 km
Concession Period 17 years (including 2 years for construction)
=
Sr. Details
Details (Rs. in
No
Crore)
1 Civil Construction Cost |
Estimated Capital
Cost with Break-up
under major heads
of expenditure
1708.90
including utility (without
GST)
2 IC and Pre-operative {17.09
Expenses (1% Civil
Construction Cost)
3 Financing Charges
6.28
4 | Interest During Construction [58.74
(IDC)
5 | Estimated Project Cost excl. |1791.01
GST
6 | Total Land Acquisition Cost 446.58
7 Environmental Management | 9.68
Plan (EMP) Cost
8 Contingencies
@1% of Civil 16.62
Cost
9 | Supervision charges @2.5% | | 2.85
____| on the Utility Cost
iE
a
10 | Total Pre-Construction Cost 475.73
(7+8+9+10)
Page 3 of 11
POR Te11 GST 18% on (2) 307.60
12 Estimated Project Costincl. [2098.61
GST
13 Bid Project Cost on Bid Due = [2089.87
Date
14 | Price Escalation during 152
Construction Period
15 | O&M Cost for 15 years 217
16 Total Capital Cost 2574.34
17 Civil Construction Cost per 21.36
Km
18 | Total Capital cost per km 32.18
Sr Description Details
No
| 1 Total Land 465.74 Ha.
Required (Ha)
2 Existing ROW (Ha) 149.306 Ha
3 Private Land 316.434 Ha.
Required (Ha)
316.434 Ha (100%) by
Land Acquisition 4 3(A) Status
notification dt.10.02.2021,
Status
23.02.2021, 14.02.2022 &
03.03.2022
5 3(D) Status 316.434 Ha (100%)
6 3(G) Status 316.434 Ha (100%)
7 3(H) Status Likely by Sep 2025
8 Balance 3(A) Nil
9 Balance 3(D) Nil
10 Balance 3(G) Nil
Particulars Details
Financial Viability PIRR 11.16%
EIRR 15%
SLRS
The project is proposed to be implemented as per Model
Concession Agreement uploaded on MoRTH web site in
Concession
November 2020 with subsequent amendments issued
Agreement
thereafter
Bids will be evaluated on the basis of the lowest Bid Project
Bidding parameter
Cost.
Single Stage two-part system of bidding
Bidding process
Page 4 of 11
REA ee tan a a2. The Gudebellur to Mahabubnagar section is a part of Hyderabad - Panaji Economic
Corridor-10 which starts from the end of major bridge over river Krishna in Gudebellur
village in Narayanpet district and ends at Mahabubnagar district. The primary purpose
of the proposed 4-lane project corridor is to provide connectivity to Raichur city in
Karnataka and Jadcherla on Hyderabad — Bengalore NH 44. This corridor also serves
as a major connectivity to the State capital from Narayanpet & Mahabubnagar districts.
Additionally, the proposed corridor traverses through major towns such as Makthal,
Magnoor, Marikal and Devarkadra.
3. This connectivity will decrease the distance by 1.19 km (from 81.2 km to 80.01 km) only,
it will yield significant benefit in terms of reduction in travel time by 1 hour 30 minutes. It
will also facilitate speedy and hassle-free passenger and freight transport in this region.
The projected traffic volume in the year 2024 was 17,991 PCUs which is expected to be
24,214 PCUs in the year 2030. The existing 2-lane road with paved shoulders will not
be able to cater to the projected traffic in the coming years.
4. The total length of the project is 80.01 km. Out of which 43.2 km is greenfield and 36.81
km is brownfield. The project will be executed on Hybrid Annuity Mode (HAM) model
with a Total Capital Cost of Rs. 2574.34 crore under the NH(O). The financial
assessment indicates the project IRR is 11.16% and the equity IRR is 15%. |
5. After the detailed presentation, the Chair asked the PPPAC members for their
observations. DoLA supported the proposal and stated that no further comments to offer.
6. Director, DoE raised the following observations:
a) The contingency charge of 10% has been included in land acquisition cost.
Normally, contingencies are accounted in the civil construction cost and not on land
acquisition cost. The same may be revised.
b) The base year taken for traffic projections is 2017. To ensure accuracy and
relevance in traffic forecasting, it is suggested that the traffic survey data used for
projections should not be older than 1 to 1.5 years when submitted to the PPPAC.
7. PD, NITI Aayog made the following observations:
a) While assessing the viability of the project under HAM and BOT, the Estimated
Project Cost (EPC) considered under the HAM model is Rs. 1,800 crore whereas |
the same in BOT is Rs. 2,800 crore, indicating a significant cost difference. It is :
suggested that the cost difference for BoT mode should be reasonable and
reassessed,
8. JS(ISD) raised the following observations:
Page 5 of 11
nemaa) The project cost submitted to PPPAC has increased substantially (48% increase in
civil construction cost) as compared to the PIB cost. What is the rationale behind
this significant cost escalation?
b) The cost of debt considered in the project proposal is on the higher side and it needs
to be revised as per the existing cost of debt for construction period and post CoD
period.
|
|
c) Has the project been proposed as an access-controlled corridor? It may be noted
that in the previous PPPAC meetings, MoRTH was requested to formulate a
standardized guideline/SOP to determine appropriate parameters under which a
corridor should be developed as an access-controlled corridor.
d) The per km cost of the project is Rs. 23 crore, whereas the per km cost of the nearby
stretch is approx. Rs. 18 crore only. Why is the per km. cost of the proposed stretch
is higher?
e) The current traffic level in the proposed corridor is 17,991 PCUs only. MoRTH may
clarify whether the traffic is sufficient to trigger for four-lane upgradation?
f) How is the significant travel time savings of 1 hour 30 minutes justified with only a
minimal reduction (1.19 km) in distance?
g) The proposed project is partially greenfield and partially brownfield. Why is the
project not envisaged as a complete brownfield project?
h) The proposed project starts at the end of bridge across river Krishna. What is the
status of the bridge, is it under construction or is it in the planned stage?
i) Are service roads to be constructed as part of the project and who will borne its
cost?
j) MoRTH may do a BoT reassessment, based on revised cost assessment, debt rate
revision, traffic impact of Surat-Chennai corridor, etc.
9. The Chair made the following observations:
|
a) As per the proposal, the distance between the toll plazas is 65.45 km. Is it the
standard distance followed between two toll plazas in NHAI projects?
j
10.MoRTH submitted the following to the queries raised by the PPPAC Members: -
'
Page 6 of 11a) The contingency charges imposed on land acquisition cost shall be removed.
b) For the instant proposal, the traffic survey was originally conducted in 2017 and
subsequently revalidated in 2024. For future projects, if the traffic survey data is
more than one year old at the time of project submission to the PPPAC, a
revalidation
exercise shall be undertaken.
The cost of Rs.2800 crore is the Total Project Cost (TPC) including the cost of land
acquisition in BOT Analysis. However, the financial assessment for BOT has been
done on EPC cost of Rs.2535 crore and not on TPC.
At the time of PIB approval, the projects were reviewed and sanctioned at the
programme level, which included approximately 700 individual projects with
indicative cost estimates. The DPRs for these projects had not been finalized at that
stage. The instant proposal under PPPAC is being undertaken at the individual
project level, based on finalized DPRs, resulting in a more accurate but at a higher
cost.
Slo
The cost of debt shall be optimized using a formula-based approach or a reliable
published benchmark. Accordingly, the project financials shall be reassessed and
submitted.
The corridor at present is not access-controlled.
Since the project connects to the
Surat—Chennai corridor, it can be developed as an access-controlled
corridor to
enhance connectivity to Hyderabad with an additional cost of Rs. 150 crore. F urther,
a standardized guideline/SOP for undertaking access-controlled
corridor is under
preparation.
9) Out of 80.01km project length, the structure length including the approaches is
around 32.264 km. Further, the slip/service road length in the current project are of
higher length compared to the nearby projects. Additionally, the nearby project SOR
is based on year 2021-22 while the proposed project estimate is prepared on the
basis of SOR 2024-25. The SOR 2024-25 rates are almost 15% higher than the
SOR 2021-22 rates. All these factors contributed to high per km cost in the instant
proposal.
h) The current traffic level on the proposed corridor is 17,991 PCUs which surpasses
the triggering point of 13500 PCUs as per Level of Service ‘C’ indicating the need
for upgradation to 4-lane corridor.
Page 7 of 11
Yaa es ©
TE rer aesi) The
significant travel time saving of 1 hour and 30
minutes, despite a minimal
reduction in
distance, is
because of the
enhanced road
geometry,
reduced
congestion,
increased
average speed and better spacing
between
vehicles.
j) The
greenfield
sections have been
proposed
specifically to
bypass
densely
populated or
congested
stretches, thereby
improving overall corridor
performance,
safety, and level of service. If
brownfield
development is done in such
stretches, it
will entail higher cost than the
greenfield
development.
k) The bridge across river
Krishna is under
construction and is
expected to be
completed by 2026.
1) Since the
proposed service road is not an urban bypass, the cost for the slip roads
shall be borne by MoRTH only.
m) As per Fee Rule 2008, the standard distance between two toll plazas should be 60
km. If the distance is less than 60 km then
relaxation has to be provided by the
Ministry. In the instant proposal, there are two toll plazas in the
proposed corridor
which is at a distance of 65.45km. However, the distance of the proposed toll plazas
with preceding and
succeeding toll plazas are less than 50 km for which relaxation
for which relaxation has already been granted by the Ministry.
Recommendations
141.After detailed
deliberations, the PPPAC
unanimously
recommended the proposal for “4
laning of NH-167 from Gudebellur at Design
Km.182+930 to
Mahabubnagar at Design
Km 262+940 of
Hyderabad-Panaji section (length 80.01km) in the State of Telangana”
subject to following
recommendations, for
consideration of the competent authority for
OS
giving
administrative approval.
a) The mode and accordingly appraised capital cost of the project shall be
recommended in the next PPPAC meeting subject to the submission of the revised
BoT analysis by MoRTH.
b) It is recommended that MoRTH may formulate a standardized guideline/SOP to
determine appropriate parameters under which a corridor should be developed as
an
access-controlled corridor.
For all future projects, MoRTH may ensure that the assumptions used to estimate
the PIB cost/ and the currently proposed cost along with justifications for variation
are submitted with the PPPAC proposal.
Eg ea eaed) The cost of debt to be considered as per the prevailing lending rates and not at the
higher side for future projects. In addition, rather than applying a uniform rate for
the entire concession period, appropriate rate shall be used for the pre-CoD and
post CoD phases.
e) For all future proposals, the project shall be justified not only on traffic volumes
measured in PCUs, but also in terms of the Level of Service (LoS) requirements.
12.Revalidation of its recommendation by the PPPAC is not required for following post
recommendation changes in the project costs/bid documents: -
a) Any change in the date/time period for any time-bound actions like appointed date,
financial close, construction period etc.
b) Non-substantial change in risk-allocation.
c) Any other changes/modification in the project proposal with the overall objective of
making project successful.
d) Further, MoRTH/NHAI may decide whether the changes proposed post
recommendations of the project proposal by the PPPAC fall within the threshold
criteria as stated above. All such changes falling within the threshold criteria shall
be appraised at the level of Secretary (RTH)/BoD of NHAI as the case may be,
without any further need of revalidation by the PPPAC and shall proceed with the
approval process accordingly
(ii) Construction of Access Controlled Highway of 4-Lane with Paved Shoulders
from Ranganathpura (Hassan) to Keresooragondanahalli in Hassan Hiriyur
section (EC-20) in Karnataka on HAM under NH (0).
1. The project was deferred. It will be considered after receiving response of the
MoRTH on the observations of the PPPAC placed at Annexure-ll.
Page 9 of 11Annexure-l ,
List of the participants of the 132"¢ meeting of the PPPAC :
a) Department of Economic Affairs, Ministry of Finance
ee
1. Ms. Anuradha Thakur, Secretary (EA)
Shri Baldeo Purushartha, JS (ISD)
Ms. Arya Balan Kumari, Joint Director
Shri Rajender Singh, SO (PIU)
Ms. Anuradha Talwar, SO (PIU)
Shri Manjeet Yadav, ASO
ee
oO Ok
ee
b) Department of Expenditure
1. Shri L. K. Trivedi, Director
AR Oe, Seen eae eee a ae ee
Seas
c) NITI Aayog
1. Shri. Partha Reddy, Programme Director
RRS Se eee te eee
d) Department of Legal Affairs
1. Shri Hemant Kumar, Deputy Legal Adviser, DoLA
e) Ministry of Road Transport and Highways i
1. Shri V Umashankar, Secretary (RTH) i
2. Shri Puneet Agarwal AS&FA
3. Shri Vinay Kumar, AS(H) .
4. Shri Manoj Kumar, CE %
5. Shri V K Joshi, SE (BPSP and HA) fe
f) National Highway Authority of India (NHAI) e
1. Shri Anil Chaudhary, Member |
2. Shri Anil Chaudhary, Member (P) ‘
3. Shri D.K. Chaturvedi, GM (Technical) i
4. Shri Saket Mishra, Manager (Technical) i
é
Page 10 of 11 :
@Annexure-ll
Comments on MoRTH Proposal
(ii) Construction of Access Controlled Highway of 4 Lane with Paved Shoulders from
Ranganathpura (Hassan) to Keresooragondanahalli in Hassan Hiriyur section EC-
20 in Karnataka on HAM under NH (0)
a) The projected traffic on the proposed corridor does not justify the need of the project.
The only justification of the project is that the land has already been acquired.
b) When was the land acquisition completed and what is the interest obligation of
MoRTH on the land acquired? MoRTH may explore the implication of returning the
land to the owners in case the project is not taken ahead?
There is a substantial increase in the project cost submitted in the PPPAC as
compared to the PIB appraisal. The justification for the increased cost may be
provided along with underlying assumptions considered.
qd) It is noted that the per km cost arrived for the proposed project is Rs. 25.45 crore,
whereas the per km cost for the greenfield highways is typically Rs. 22 crore per
km. The justification for the higher per km cost to be provided.
The need for access-controlled corridor is also not justified. MoRTH may reassess
the same.
The proposed project from Hassan to Huliyar, covering a length of 76 km, is
proposed as a 4-lane access-controlled corridor. However, the adjacent section
from Huliyar to Hiriyur, spanning 38 km, is currently under implementation as a 2-
lane with paved shoulder (2L+PS) configuration. Given the continuity of the corridor,
what is the rationale for not upgrading the Huliyar—-Hiriyur section to a 4-lane
configuration in-line with the adjoining stretches?