GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3920
TO BE ANSWERED ON 12.08.2026
DELAY IN REDEVELOPMENT OF UDAIPUR RAILWAY STATION
†3920. SHRI RAJKUMAR ROAT:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the stipulated deadline for the Udaipur Railway Station
redevelopment project (costing 354 crore) has expired, if so, the
duration for which the deadline has been extended;
(b) the details of the rule/provision under which the extension was granted
along with the current progress of the project and the revised
completion date of said project;
(c) whether several major works proposed in the project including parking,
16 escalators and more than a dozen lifts still remain incomplete and
passengers are facing severe inconvenience during summer and the
rainy season due to lack of adequate passenger shades on platform
numbers of 1 to 5, if so, the details thereof and the steps taken/being
taken by the Government in this regard;
(d) the details of the action taken so far against the concerned contractor
for the delay in the said project; and
(e) whether the Government proposes to conduct an independent technical
examination/investigation regarding the quality of construction works
and if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Ministry of Railways has identified Udaipur City Stations for
redevelopment under Amrit Bharat Station Scheme. The status of this
station is given below:
Udaipur City Station: The redevelopment of Udaipur City station has been
sanctioned at a cost of Rs. 354 Crores. The master plan of Udaipur City
station redevelopment envisages following works:
§ Page 1 of 6 Provision of main entry station building (West side)
Provision of second entry station building (East side)
72 m wide air concourse
Provision of platform shelter and improvement of platform surface
Provision of lifts and escalators
Improvement of circulating area and parking
Skywalk for connecting foot over bridge to second entry station
building
At Udaipur City station, the passenger amenities like platform shelters,
high level platforms, urinals, lavatories, waiting hall, drinking water
facilities, foot over bridge are available.
The structural work of main station building and second entry station
building has been completed. The works of finishes of main entry station
building & second entry station buildings, platform shelter, air concourse,
lifts and escalator have been taken up. The agency is regularly being
instructed to expedite the work.
Amrit Bharat Station Scheme envisages development of stations on a
continuous basis with a long-term approach. It involves preparation of
master plans and their implementation in phases to improve the stations of
Indian Railways. The master planning, keeping in view the necessity of
each station, includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/subway to commensurate with
passenger traffic
Provision of lifts/escalators/ramps
Page 2 of 6 Improvement of platform surface/ provision of platform shelter
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking development
Amenities for Divyangjans
Better passenger information systems
Provision of air concourse, executive lounges, Multimodal integration,
landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions,
provision of ballastless tracks etc. as per necessity, phasing and feasibility
and creation of city centre at the station in the long term.
So far, 1340 stations have been identified for development under Amrit
Bharat Station Scheme, out of which 85 stations including Udaipur City
station are located in Rajasthan. The names of stations identified for
development under Amrit Bharat Station Scheme in Rajasthan are as
following:
State No. of Names of Stations
Stations
Rajasthan 85 Abu Road, Ajmer, Alwar, Anupgarh, Asalpur Jobner,
Balotra, Bandikui, Baran, Barmer, Bayana, Beawar,
Bharatpur, Bhawani Mandi, Bhilwara, Bijainagar,
Bikaner, Bundi, Chanderiya, Chhabra Gugor,
Chittorgarh Jn., Churu, Dakaniya Talav, Dausa,
Deeg, Degana, Deshnoke, Dholpur, Didwana,
Dungarpur, Falna, Fatehnagar, Fatehpur
Shekhawati, Gandhinagar Jaipur, Gangapur City,
Gogameri, Gotan, Govind Garh, Hanumangarh,
Hindaun City, Jaipur Jn, Jaisalmer, Jalor, Jawai
Page 3 of 6Bandh, Jhalawar City, Jhunjhunu, Jodhpur,
Kapasan, Khairthal, Kherli, Kota Jn, Lalgarh Jn,
Mandal Garh, Mandawar Mahwa Road, Marwar
Bhinmal, Marwar Jn, Mavli Jn, Merta Road Jn,
Nagaur, Naraina, Nim ka Thana, Nokha, Pali
Marwar, Phalodi Jn, Phulera Jn, Pindwara, Rai
singh nagar, Rajgarh, Ramdevra, Ramganj Mandi
Jn, Ranapratapnagar, Rani, Ratangarh Jn, Ren,
Ringas, Sadulpur, Sanganer, Sawai Madhopur, Shri
Mahaveerji, Sikar, Sojat Road, Somesar, Sri
ganganagar, Sujangarh, Suratgarh, Udaipur City
Completed Stations:
Development works at railway stations under Amrit Bharat Station Scheme
in Rajasthan have been taken up at a good pace. Details of stations
completed in Rajasthan are as under:
State No. of Name of stations
stations
Barmer, Bundi, Dausa, Deeg, Deshnoke,
Fatehnagar, Fatehpur Shekhawati, Gangapur
Rajasthan 18 City, Gogameri, Gotan, Govind Garh, Jaisalmer,
Khairthal, Mandal Garh, Mandawar Mahwa Road,
Rajgarh, Sojat Road, Somesar
The activities for redevelopment at other stations in Rajasthan have also
been taken up at good pace and progress of some of the stations is as
given below:
New Kota: The structural work of front &rear station building, parcel
building, new panel room, RPF building, improvement of rear & front side
Page 4 of 6circulating area, platform shelter at platform no. 1 and air concourse have
been completed. The work of lifts, escalators, through roof, finishing of
front & rear side station building, improvement of platform shelters at
platform no 2&3, overhead tank and underground tank etc. have also been
taken up.
Gandhi Nagar Jaipur Station: The works of main entry station building,
second entry station building, two level basement, air concourse, through
roof launching, provision of platform shelters, platform resurfacing and
improvement of circulating area and utilities have been completed. The
work of finishes has been taken up.
Jaipur Station: The works of 6 m wide foot over bridge at dausa end,
second entry side basement, approach road, structural work of main entry
side basement, structural work of air concourse and 8m wide central foot
over bridge connecting concourse have been completed. The work of 6m
wide foot over bridge at Sikar end, structural work of main entry station
building, foot over bridge along the track and roofing & flooring work of
central foot over bridge have been taken up.
Churu station: The works of new station building, improvement of platform
shelter at platform no. 1 & 2, booking office, waiting room, retiring room,
toilet, installation of coach indication board and signages have been
completed. The work of lifts and 12 m wide foot over bridge has been taken
up.
Dungarpur Station: The works for improvement of station building, porch,
circulating area, parking, platform shelters, platform surfacing, toilet block,
installation of coach indication board and signages have been completed.
The work of foot over bridge and amenities for Divyangjan has been taken
up.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
Page 5 of 6in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on category
of station/condition/traffic handled etc.
Development / Upgradation of stations is complex in nature involving safety
of passengers & trains and requires various statutory clearances such as
fire clearance, heritage, tree cutting, airport clearance etc. The progress
also gets affected due to brownfield related challenges such as shifting of
utilities (involving water/sewage lines, optical fibre cables, gas pipelines,
power/signal cables, etc.), infringements, operation of trains without
hindering passenger movement, speed restrictions due to works carried out
in close proximity of tracks and high voltage power lines, etc. and these
factors affect the completion time. Accordingly, any extension to the
contract is dealt as per the extent norms and contractual provisions.
Indian Railways has a well established mechanism to monitor
implementation of projects including their reviews, inspection, check for
time and cost overruns, quality of works and audits. Monitoring of projects
is done at various levels including through dedicated portal of Indian
Railways named Indian Railway Project Sanction and Management (IRPSM).
Works are carried out adhering to the standards and specifications laid
down in various codes and manuals. Inspections/audits/checks are carried
out from time to time by various agencies/officials/multi-disciplinary teams
as per laid down instructions and actions for correction are taken
immediately. The issues faced by the executing units are accordingly
addressed. This is a continuous and ongoing process.
*****
Page 6 of 6