Bulk Drug Park Scheme in Himachal Pradesh - 31st July 2026 - Ministry of Chemicals and Fertilizers : Department of Pharmaceuticals - Gazette Notification PDF
Issued by Ministry of Chemicals and Fertilizers : Department of Pharmaceuticals
Read or download the official PDF of this gazette notification issued by the Ministry of Chemicals and Fertilizers : Department of Pharmaceuticals on 31st July 2026. Classified under Press Release.
Executive Summary & Key Takeaways
Executive Summary This report provides a progress update on the development of the Bulk Drug Park in Haroli, Himachal Pradesh, under the "Promotion of Bulk Drug Parks" scheme. It details the financial sanctions of ₹1000 crore from the Central Government and ₹118.46 crore from the State, alongside current infrastructure completion statuses. Due to initial delays in statutory clearances, the scheme's tenure has been extended to FY 2026-27 to ensure project completion and operationalization.
Key Points / Main Content
Financial Allocations and Utilization
- Central Funding: The Department of Pharmaceuticals sanctioned ₹1000 crore on 11.10.2022, with an initial release of ₹225 crore on 20.02.2023.
- State Funding: The State Government sanctioned ₹118.46 crore and released ₹35.53 crore as its share for FY 22-23 toward Common Infrastructure Facilities (CIF).
- Utilization Progress: Between FY 2023-24 and FY 2026-27, total fund utilization reached ₹116 crore for the Central share and ₹0.24 crore for the State share.
Project Infrastructure Status
- Site Development: Approximately 20% of Phase-I site development work is finished.
- Water Supply: Works for 15 MLD capacity water supply and groundwater recharge are 98% complete.
- Power Infrastructure: HPSEBL has completed the 20 MVA power infrastructure required for the construction phase.
- Major Tenders: Tenders have been released for the Common Effluent Treatment Plant with Zero Liquid Discharge (₹273 crore) and the Steam Generation System (₹300 crore).
- Utilities: The procurement process for other critical utilities is currently underway.
Timeline and Regulatory Factors
- Scheme Extension: The tenure of the scheme has been extended to FY 2026-27 based on project status and anticipated completion dates.
- Regulatory Hurdles: Primary delays were caused by the pending Environmental Clearance (granted 25.09.2025) and procedural requirements for tree felling.
- Oversight: Progress is regularly reviewed by the Scheme Steering Committee and a High-Powered Committee headed by the Himachal Pradesh Minister of Industries.
Impact Analysis
Department of Pharmaceuticals (DoP) / Central Government Impact The department is the primary funding body and provides national-level oversight for the scheme's execution. Action Required Continue regular progress reviews through the Scheme Steering Committee and monitor the phased utilization of the remaining sanctioned funds.
Himachal Pradesh State Government & Implementing Agencies Impact They are responsible for on-ground execution, state-level funding, and obtaining necessary statutory clearances. Action Required Expedite remaining statutory clearances, manage the awarding of infrastructure contracts, and ensure project activities maintain momentum following the receipt of Environmental Clearance.
Himachal Pradesh State Electricity Board Ltd (HPSEBL) Impact As a designated agency, they have successfully delivered the 20 MVA power infrastructure for the construction phase. Action Required Coordinate with project developers to ensure power systems are scaled or maintained as the park moves toward operationalization.