**Executive Summary**
The Union Cabinet, chaired by the Prime Minister, has approved the extension of the existing North-South corridor from GIFT City to Shahpur for the Gujarat Metro Rail Corporation Limited (GMRC). The 3.33 km extension will include three elevated stations and is scheduled for completion in approximately four years. The project's estimated cost is Rs.1,067.35 crore.
**Key Points / Main Content**
* **Project Overview:**
* Approval for the extension of the North-South corridor from GIFT City to Shahpur.
* The extension will be 3.33 kilometers long with three elevated stations.
* Estimated project cost: Rs.1,067.35 crore.
* Expected completion time: approximately four years.
* **Benefits:**
* Expected ridership of approximately 23,702 passengers in 2029 and approximately 58,059 passengers in 2041.
* Improved connectivity between Ahmedabad and GIFT region.
* Benefits to major multinational companies, educational institutions, and commercial centers along the route.
* Enhanced travel convenience for daily commuters traveling between Ahmedabad & GIFT region for business, employment, and education.
* Improved network integration.
* **Job Creation:**
* Approximately 1,000 construction jobs will be generated.
* Approximately 250 post-construction jobs will be available for operations and maintenance.
* Other activities will generate indirect employment.
* **Implementation:**
* The project will be implemented by Gujarat Metro Rail Corporation Limited (GMRC).
* GMRC is a 50:50 joint venture between the Government of India and the Government of Gujarat.
* **Background:**
* Gujarat Metro's 68.28-km Ahmedabad Metro Phase-I & Phase-II with total 53 stations have been successfully made operational since Sep-2022 (Phase-I) and January-2026 (Phase-II).
* The daily ridership on this line is approximately 1,60,000.
**Impact Analysis**
**Stakeholder: Daily Commuters between Ahmedabad and GIFT Region**
* **Impact:** Enhanced travel convenience for business, employment, and education purposes, improved network integration, and increased passenger convenience.
* **Action Required:** None explicitly stated.
**Stakeholder: Multinational Companies, Educational Institutions, and Commercial Centers along the Route**
* **Impact:** Direct benefit from improved connectivity and accessibility.
* **Action Required:** None explicitly stated.
**Stakeholder: Job Seekers**
* **Impact:** Availability of approximately 1,000 construction jobs and 250 post-construction operations and maintenance jobs.
* **Action Required:** Apply for available positions.
Key Entities Referenced
Gujarat Metro Rail Corporation Limited (GMRC): The implementing agency of the metro rail project.
Union Cabinet: The approving authority for the metro rail extension project.
GIFT City: Starting point of the metro extension corridor.
Shahpur: Ending point of the metro extension corridor.
Ahmedabad Metro Phase-I & Phase-II: Existing metro lines being extended.
Ministry of Housing & Urban Affairs
Cabinet approves extension of existing North-
South corridor from GIFT City to Shahpur of
Gujarat Metro Rail Corporation Limited (GMRC)
Posted On: 24 FEB 2026 3:56PM by PIB Delhi
The Union Cabinet chaired by the Prime Minister, Shri Narendra Modi, today approved the extension,
from GIFT City to Shahpur, will be 3.33 kilometers long and include three elevated stations. The project is
scheduled to be completed in approximately four years.
The estimated cost of the project is Rs.1,067.35 crore. This extended corridor is expected to benefit
approximately 23,702 passengers in 2029 and approximately 58,059 passengers in 2041.
This corridor will strengthen connectivity between Ahmedabad & GIFT region. Major multinational
companies, educational institutions, and commercial centers located along the proposed route will directly
benefit.
Additionally, this extension will be beneficial to the daily commuters travelling between Ahmedabad &
GIFT region for catering the travel need related to Business, Employment and Education, thereby
significantly enhancing network integration and passenger convenience.
The project is expected to generate approximately 1,000 jobs in construction. Approximately 250 people
will be employed in the post-construction phase for operations and maintenance. This project will generate
a significant number of direct employment opportunities, equivalent to the number mentioned above.
Additionally, other activities will generate indirect employment for even more people.
The project will be implemented by Gujarat Metro Rail Corporation Limited (GMRC), a 50:50 joint
venture between the Government of India and the Government of Gujarat.
Background:
Currently, the Gujarat Metro's 68.28-km Ahmedabad Metro Phase-I {APMC to Motera Stadium (North-
South Corridor) & Thaltej Gam to Vastral Gam (East-West Corridor)} & Phase-II (Motera Stadium to
Mahatma Mandir & GNLU to GIFT City), with total 53 stations have been successfully made operational
since Sep-2022 (Phase-I) and January-2026 (Phase-II). The daily ridership on this line is approximately
1,60,000.
****