**Executive Summary**
This document is the Record of Discussion from the 139th meeting of the PPPAC, held on February 6th, 2026, to consider four road project proposals from the Ministry of Road, Transport & Highways (MoRTH). The meeting unanimously recommended the "Kanpur-Kabrai" project, subject to specific recommendations for Administrative Approval.
**Key Points / Main Content**
* **PPPAC Meeting Details:**
* The 139th meeting of the PPPAC was held on February 6th, 2026.
* The meeting considered four road project proposals from MoRTH.
* The record of discussion is being forwarded for information and necessary action.
* **Considered Road Project Proposals:**
* **Kanpur-Kabrai:** Development of a 4/6 lane access-controlled greenfield highway and overlay/strengthening works on an existing section, to be executed on a DBFOT pattern at BOT (Toll) Mode under NH(O).
* **Anisabad-Deedargunj:** Construction of a Six Lane Elevated Road along with a Six Lane At-Grade Road with Service Road, to be implemented on Hybrid Annuity Mode.
* **Patna to Purnea:** Construction of a 4-Lane Greenfield Expressway on Hybrid Annuity Mode (HAM) under NH(O).
* **Varanasi-Ranchi-Kolkata Highway:** Construction of a 6-lane Greenfield section on Hybrid Annuity Mode.
* **Project Status & Next Steps:**
* The Anisabad-Deedargunj, Patna to Purnea, and Varanasi-Ranchi-Kolkata Highway projects are currently undergoing cost revision and will be presented again in the next PPPAC meeting.
* The Kanpur-Kabrai project is recommended for implementation on BOT (Toll) under the NH(O) scheme.
* **Kanpur-Kabrai Project Specifics:**
* **Project Description:** Section-1: Development of a 4/6 lane access-controlled greenfield highway from Kanpur Ring road to Kabrai. Section-2: Overlay/Strengthening and improvement works on the existing Kanpur-Kabrai section.
* **Model:** DBFOT pattern at BOT (Toll) Mode.
* **Concession Period:** 20 years, including a 30-month construction period.
* **Total Capital Cost:** Rs. 7164.22 crore.
* **Estimated Project Cost (excluding GST):** Rs. 4694.48 crore.
* **Financial Viability:** Project IRR 12.95%, Equity IRR 14%.
* **Key Objective:** To enable de-congestion in Kanpur, Ghatampur, Hamirpur & Kabrai and improve connectivity and freight movement.
* **Recommendations for Kanpur-Kabrai Project:**
* Boundary wall component to be replaced with Toe wall and tree plantation.
* Grant requirement capped at a maximum of 40% of concession period.
* MoRTH to fund the grant requirement under NH(O) scheme.
* Land acquisition and necessary clearances to be obtained in a time-bound manner before the bid due date.
* **Post-Recommendation Changes:**
* Revalidation of PPPAC recommendations is not required for changes in date/time periods, non-substantial changes in risk allocation, or other modifications aiming for project success, subject to appraisal at the Secretary (RTH)/BoD of NHAI level.
**Impact Analysis**
**Ministry of Road, Transport & Highways (MoRTH)**
* **Impact:** MoRTH has presented four road project proposals for consideration and has been tasked with implementing the recommended Kanpur-Kabrai project.
* **Action Required:** To proceed with the administrative approval for the Kanpur-Kabrai project based on the PPPAC's recommendations, ensuring land acquisition and necessary clearances are obtained promptly. MoRTH/NHAI will also decide on the appraisal level for post-recommendation changes.
**Department of Expenditure (DoE)**
* **Impact:** The Department of Expenditure, represented by AS, DoE, raised observations regarding land acquisition, site clearance costs, and salvage value for the Kanpur-Kabrai project.
* **Action Required:** To consider the observations raised by AS, DoE regarding efficient cost management for the Kanpur-Kabrai project.
**NITI Aayog**
* **Impact:** PD, NITI Aayog, raised observations concerning tolling rates, the necessity of boundary walls, and the specification of wayside amenities for the Kanpur-Kabrai project.
* **Action Required:** To consider the observations raised by PD, NITI Aayog, regarding operational and contractual aspects of the Kanpur-Kabrai project, particularly regarding tolling, infrastructure, and wayside amenities.
**Department of Legal Affairs (DoLA)**
* **Impact:** DoLA supported the Kanpur-Kabrai proposal and stated no further comments.
* **Action Required:** No specific action is required as DoLA has indicated their support.
**National Highways Authority of India (NHAI)**
* **Impact:** NHAI made a detailed presentation on the four road project proposals and will be involved in the implementation of the Kanpur-Kabrai project.
* **Action Required:** To proceed with the project as per the recommendations and policies, including the development of wayside amenities as per NHAI policy. NHAI will also appraise changes falling within threshold criteria.
**Competent Authority**
* **Impact:** The Competent Authority needs to grant Administrative Approval for the Kanpur-Kabrai project.
* **Action Required:** To consider the PPPAC's recommendations and provide Administrative Approval for the "Development of 4/6 Lane of access-controlled Kanpur - Kabrai greenfield highway..." project.
Key Entities Referenced
PPPAC: Public-Private Partnership Appraisal Committee, responsible for considering and recommending infrastructure project proposals.
Ministry of Road, Transport & Highways (MoRTH): The government ministry responsible for the development and administration of roads, national highways, transport, and roadways in India.
Kanpur - Kabrai greenfield highway project: A specific road development project involving a new greenfield highway and upgrading an existing section.
DBFOT pattern at BOT (Toll) Mode under NH(O): A project delivery and financing model (Design, Build, Finance, Operate, Transfer) for toll-based projects under the National Highways (Original) scheme.
National Highways Authority of India (NHAI): The agency responsible for the development, maintenance, and management of national highways in India.
F. No. 2/24/2025 - PIU
Government of India
Ministry of Finance
Department of Economic Affairs
Infrastructure Finance Secretariat
ISD Division
(PIU)
4th Floor, STCs Building,
Janpath New Delhi
Dated: 3rd March 2026
Record of Discussion
Subject: Record of Discussion of the 139lh meeting of the PPPAC for considering
four road project proposals of Ministry of Road, Transport & Highways (MoRTH)
on PPP mode.
Reterence: 139th meeting of the PPPAC held on 0h February 2026.
Sir/Madam,
The undersigned is directed to forward the Record of Discussion of the 133
meeting of the PPPAC held on 06 " February 2026 under the chairmanship of Secretary
(EA) for information and necessary action.
2. This issues with the approval of the Competent Authority.
(Arya Balan Kumari)
Joint Director (PIU)
011-2370 1219
To,
1. Secretary, Department of Expenditure, New Delhi-01
2. CEO, NITI Aayog, Yojana Bhawan, New Delhi-01
3. Secretary, Ministry of Road, Transport & Highways, Transport Bhawan, New
Delhi.
4. Secretary, Department of Legal Affairs, Shastri Bhawan, New Delhi.
Copy to:
1. Sr. PPSt o Secrelary (EA)
2. PPS to JS (|FS)
3. PPS to Advisory (Energy)Subject: Record of Discussion of the 139th meeting of the PPPAC for considering the
following four road proposals:
i. Kanpur – Kabrai proposal:- Section-1: Development of 4/6 Lane of access-controlled
Kanpur - Kabrai greenfield highway, starting from design km 0+000 (Kanpur Ring road)
to design km 117+700 (near village Kabrai in district Mahoba) in the State of Uttar
Pradesh and, Section-2: Overlay/Strengthening, other road safety and improvement
works on existing Kanpur - Kabrai section from km 7+430 to km 130+100 (Design
chainage 0+000 to 123+860) of NH-34 (old NH-86) in the State of Uttar Pradesh on
DBFOT pattern at BOT (Toll) Mode under NH(O).
ii. Anisabad-Deedargunj proposal:- Construction of Six Lane Elevated Road Along with
Six Lane At-Grade Road with Service Road in Anisabad-Deedargunj Section Of NH-
22(Old NH-30) & NH-31(Old NH-30) Starting Near Saristabad (Existing Chainage
Km.181+300, Junction Of NH-30(Old) & NH-83(Old)) and Terminating after Deedargunj
Junction (Existing Chainage Km.195+420 of NH30(Old)) in the State of Bihar on Hybrid
Annuity Mode
iii. Patna to Purnea proposal: - Construction of 4-Lane Greenfield Expressway from
Patna to Purnea (NE-9) (Design Ch. Km. 0.000 to Km. 244.960, Total Design Length –
244.960 Km.) in the state of Bihar on Hybrid Annuity Mode (HAM) under NH(O)
iv. Section of Varanasi-Ranchi-Kolkata Highway: - Construction of 6-lane Greenfield
Varanasi-Ranchi-Kolkata Highway from Konki Village to Lerua village from Km 0+000
to Km 41+955 under NH (O) in the State of Bihar on Hybrid Annuity Mode.
1. The 139th meeting of the PPPAC was held on 06th February 2026 at 11:15 hours to
consider the above-mentioned four road proposals of MoRTH.
2. List of attendees is placed at Annexure-I.
3. With the permission of Secretary (EA), Adviser (Energy) welcomed all the attendees to
the meeting. NHAI made a detailed presentation on all the four PPPAC road project
proposals.
4. The projects at serial no. ii, iii and iv are currently under cost revision as per
MoRTH guideline on HAM dated 06.11.2025 and shall be presented again to the
PPPAC for the approval in the next PPPAC meeting.
I. Development of 4/6 Lane of access-controlled Kanpur - Kabrai greenfield highway and
Overlay/Strengthening, other road safety and improvement works on existing Kanpur -
Kabrai section on DBFOT pattern at BOT (Toll) Mode under NH(O).
1. The details of the project are given in the table below:
Table 1: Details of the project
Section-1: Development of 4/6 Lane of access-controlled Kanpur - Kabrai
Project greenfield highway, starting from design km 0+000 (Kanpur Ring road) to
Description design km 117+700 (near village Kabrai in district Mahoba) in the State of
Uttar Pradesh and,Section-2: Overlay/Strengthening, other road safety and improvement
works on existing Kanpur - Kabrai section from km 7+430 to km 130+100
(Design chainage 0+000 to 123+860) of NH-34 (old NH-86) in the State
of Uttar Pradesh on DBFOT pattern at BOT (Toll) Mode under NH(O).
PPP Model DBFOT pattern at BOT (Toll) Mode
Sponsoring Ministry of Road Transport and Highways, Government of India
Authority
Implementing National Highways Authority of India (NHAI)
Agency
State: Uttar Pradesh
Location
District: Kanpur, Hamirpur & Mahoba
Type of Pavement Flexible Pavement except toll plaza
Lane 4/6 lane with PS
configuration
S. Total Amount
Description
No (Rs. in Crore)
1 Length (Km) 117.700 km
4-lane with Paved Shoulder
2 Carriageway (2x7.0m) + (2x3.5m) + (2x0.5m
edge strip)
3 Design Speed 100 Kmph
Major Bridge / Major bridge cum 09/07 (Irrigation canal – 5, Nalla +
4
Underpasses (Nos) road – 2)
Minor Bridge / Minor bridge cum 29/46 (Irrigation canal – 24, Nalla
5
Underpasses (Nos) + road – 22)
Details of Box Culverts – 308 (MCW-255,
Structures 6 Culverts (Nos) Interchange-46), Pipe Culverts -
07
7 Flyover (Nos) 05
8 Elevated Viaduct (Nos) 07
9 ROB (Nos) 01
VUP/LVUP/SVUP/Cross Road Box
10 09/19/29/43
Structures
Length of Service Road/Slip Road
11 12.002 Km
(Km) (Each Side)
Interchange Locations (for
12 08 locations
Entry/Exit) (Nos)
Concession 20 years (including 30 months construction period)
Period
Estimated Capital
Sr. Total
Cost with Break- Particulars
No. Amount
up under majorheads of (Rs. in
expenditure Crore)
Total Civil Construction Cost including Utility Shifting
i 4082.32
Cost for (FY 2025-26)
Escalation up to Appointed Date @ 4% for 6 months
ii 80.85
from 01.04.2026
Total Civil Construction Cost including Utility Shifting
1 4163.17
Cost up to Appointed Date
2 Escalation during Construction @ 4% 244.24
3 IC & pre-operative expenses @1% of (C) 41.63
4 Financing charges 0.75% of debt 16.63
5 Interest during Construction (IDC) @ 10.17% p.a. 213.40
6 O&M during Construction on existing highway 15.41
Estimated Project Cost (without GST)
7 4694.48
(1+2+3+4+5+6)
8 Estimated Project Cost per km 39.88
9 GST@18% on Civil Construction Cost (Sr no. 1, 2&6) 796.11
10 GST@18% on Sr. No. 3&4 10.49
11 Total Project Cost (with GST) (7+9+10) 5501.06
12 Pre-Construction Cost
(i) Land Acquisition Cost 1643.14
(ii) Environmental Cost 20.00
(iii) Total Cost of Pre-Construction Activities 1663.14
13 Total Capital Cost [11+12 (iii)] 7164.22
S.
Description Kanpur- Kabrai (Greenfield)
No.
Total Land to be
1 821.7976 Ha
Required (Ha.)
Diversion of Forest
2 12.401 Ha. (Protected Forest)
Land (Ha.)
Sr. Area
Gazetted Date
No. (Ha.)
Land Acquisition
Notified vide SO No 3428 dt
and other 1 316.530
25/07/2025
clearance 3 3A Status
Notified vide SO No 2916 dt
2 266.85
01/07/2025
Notified vide SO
3 252.542
No2938 dt 01/07/2025
4 3D Status Draft 3D is ready
S. Target
Activity Status
No. CompletionTOR for EIA/ EMP study has been
Environmental approved from the MoEF&CC, and 15th March,
1
Clearances Environmental clearance is in 2026
progress.
The Forest land diversion proposal
has been uploaded on Parivesh 15th March,
2 Forest Proposal
Portal and Stage-I Forest clearance 2026
is in progress.
• Estimates obtained.
• Details of Existing Utility
February 28,
3 Shifting of utilities specified in Schedule A and
2026
its shifting is under the
scope of Concessionaire
• Proposal uploaded on
Railroad Crossing GAD
GAD Approval of
Approval System.
ROB from the February 28,
4 • Joint site inspection has
Ministry of 2026
been completed.
Railways
• GAD submitted to railways
for approval.
Approval under progress February 28,
5 IWAI Clearance
2026
NOC for Namami Approval under progress February 28,
6
Gange program 2026
7 Wildlife clearance Not Applicable NA
PIRR 12.95%
Financial Viability EIRR 14%
Concession The project is proposed to be implemented as per Model Concession
Agreement Agreement uploaded on MoRTH web site.
Bidding
Lowest Grant or highest premium
parameter
Bidding process Single Stage two-part system of bidding
2. The primary purpose of the proposed project is to enable de-congestion in Kanpur,
Ghatampur, Hamirpur & Kabrai. The proposed project section is part of the Bhopal–Kanpur
Economic Corridor and the region around Kabrai has significant aggregate mining activity
(serving both Kanpur on one side and Bhopal on the other) which make it necessary to upgrade
the existing 2-lane road to a 4-lane access-controlled with 6-lane structures along a stretch of
117.7 kilometres. The projected traffic on the proposed greenfield corridor is about 18,069
PCUs in 2028 and is expected to cross 24,997 PCUs by 2035 and 41,240 PCUs by 2050.3. The instant proposal is divided into two sections: Section-1 includes development of a
4-lane access-controlled greenfield corridor with 6-lane structures from Kanpur to Kabrai and
Section-2 includes operation and maintenance of the existing alignment with two toll plaza
(i.e. Aliyapur & Khanna) from Kanpur to Kabrai. The existing road is at present a 2-lane+PS
which was under BOT mode and concession got over on 20.01.2025 and is taken over by
NHAI. The existing road shall also be handed over to the concessionaire for operation and
maintenance which will act as a sweetener to carry out the project on BOT (Toll) mode.
4. The proposed connectivity will reduce the travel time between Kanpur and Kabrai from
existing 3.5 hrs to 1.5 hrs (58% reduction in travel time). The proposed alignment, designed
for a speed range of 80–100 km/h compared to the existing 2-lane road’s average speed of
30-50km/h. The proposed highway will also enhance the freight movement and will ensure,
smooth and safe traffic flow and will result in substantial gain in terms of reduced Vehicle
Operating Cost (VOC) and reduced delays.
5. The project will be executed under the BOT (Toll) model with a Total Capital Cost of Rs.
7164.22 crore and an Estimated project cost (EPC) of Rs. 4694.48 crore. The project is
included under the NH(O) scheme. The financial assessment indicates the project IRR as
12.95% and the equity IRR as 14%.
6. After the detailed presentation, the Chair asked the PPPAC members for their
observations. DoLA supported the proposal and stated that no further comments to offer.
7. PD, NITI Aayog raised the following observations:
a. Will the tolling rates for the existing 2-lane and the proposed 4-lane highway be same
or different? In case of different toll charges, there would be an incentive for the traffic
to use the 2-lane. How will be the over-crowding of 2-lane highway be managed? Also,
what if the concessionaire neglects the 2-lane road as toll collection charges are less
and focus only on the 4-lane road?
b. What is the need for providing a boundary wall of length 204 km in the proposed
project?
c. There are two wayside amenities planned in Section-1 of the proposed project. The
minimum facilities including O&M requirement, KPIs etc. required for wayside
amenities need to be clearly specified in DCA and investment towards these facilities
need to be duly recognized under the Concession Agreement.
8. AS, DoE raised the following observations:
a. As per the PPPAC Memorandum, 821.79 ha of land is to be acquired for the project.
The contract should be awarded after completing land acquisition to avoid cost and
time overruns. Also, the DPR shows a cost of Rs. 19.04 crore for site clearance and
dismantling. The realizable/salvage value of dismantled materials should be deducted
from the estimated project cost to reduce the overall project cost.
9. The Chair made the following observations:a. The project includes two parallel sections, one greenfield and one brownfield which are
connecting the same start and end points. What is the rationale for creating two
simultaneous corridors to the same destination?
b. The proposed project is viable under the BOT (Toll) mode. Whether this viability is
primarily due to the provision of sweeteners in the financing structure?
c. The project involves a very high number of structures, including 9 major bridges, 7
major bridge-cum-underpasses, 29 minor bridges, 47 minor bridge-cum-underpasses,
5 flyovers, 7 elevated viaducts, and 308 box culverts. MoRTH may confirm if it is
essential to provide these number of structures?
d. As per the financial analysis, the project requires a VGF of 42.43% for a 20-year
concession period. With the proposed optimization such as replacing boundary walls
with toe walls the project should be viable with an upper VGF cap of 40%.
10. MoRTH submitted the following to the queries raised by the PPPAC Members: -
a. The toll charges for the 2-lane and 4-lane highway would be different. The existing road
traffic has already crossed its capacity and is presently operating at LOS-D/E resulting
in congestion. The travel time using the proposed road will be reduced to 1.5 hours
from present 3.5 hours. Therefore, the end-to-end traffic will consider the savings in
time the proposed 4-lane is going to offer and hence prefer the greenfield
alignment. Additionally, if the concessionaire does not maintain 2-lane road, the
suspension clause from the DCA will get triggered.
b. As the proposed corridor is access-controlled, boundary walls were proposed.
However, the same shall be removed and replaced by Toe walls with tree plantation.
c. The scope of Concessionaire for Wayside amenities would involve only construction of
boundary wall with provision of entry and exit ramps. The same has been specified in
Schedule-C of DCA. Further development of way side amenities will be done in
separate Contract as per NHAI policy by Competent Authority (NHLML).
d. The project shall be bided out only after completing of 90% of the land acquisition. An
amount of Rs.19.04 crore, which is part of civil cost, has been considered towards site
clearance (Clearing and Grubbing) only. As the subject project is a greenfield
alignment, there are no existing bridge/ underpass structures requiring dismantling;
therefore, no realizable or salvage value of dismantled materials has been considered.
e. The existing alignment has an available ROW of about 30 m, whereas the proposed
access-controlled highway requires a ROW of about 60 m, necessitating acquisition of
an additional 30 m. Land costs along the existing alignment are high, and upgrading
the existing 2-lane highway to 4-lane highway with 6-lane structure would require
demolition of more than 800 building structures. Although the option of using the
existing alignment with bypasses was examined during the alignment study, the
alignment passes through densely populated areas, leading to large-scale demolition
and substantially high Capital cost due to higher land acquisition and R&R costs.
Additionally, the development of the proposed 4-lane greenfield corridor would result
in a combined 6-lane facility at an estimated cost of Rs. 6,601.98 crore, whereas
upgrading the existing 2-lane brownfield corridor delivers only a 4-lane capacity at a
higher cost of Rs. 7,137 crore. This clearly indicates that the greenfield option providesgreater capacity at a significantly lower investment, making it a more efficient and
cost-effective solution.
f. The project’s viability under the BOT (Toll) framework is partly supported by the
proposed sweetener. In addition, the corridor benefits from factors such as minimal
traffic leakages and the absence of competing routes, which further enhance tolling
potential and overall project viability.
g. The high number of structures is necessitated by the large number of waterbody
intersections, as the natural drainage channels in the project area predominantly flow
from north to south, requiring appropriate cross-drainage works. Additionally, as per
standard engineering practice, culverts are provided at intervals of approximately 200–
300 meters.
h. With the optimization of boundary wall provisions, the project viability can be improved,
and an upper VGF cap of 40% is achievable. Further, during the bidding process, it is
typically observed that bidders offer a discount of 20% to 30%. Therefore, setting the
upper VGF ceiling at 40% is appropriate.
Recommendations
11. After detailed deliberations, the PPPAC unanimously recommended the proposal for
“Development of 4/6 Lane of access-controlled Kanpur - Kabrai greenfield highway, starting
from design km 0+000 (Kanpur Ring road) to design km 117+700 (near village Kabrai in district
Mahoba) in the State of Uttar Pradesh and, Overlay/Strengthening, other road safety and
improvement works on existing Kanpur - Kabrai section from km 7+430 to km 130+100 (Design
chainage 0+000 to 123+860) of NH-34 (old NH-86) in the State of Uttar Pradesh on DBFOT
pattern at BOT (Toll) Mode under NH(O)” subject to following recommendations, for
consideration of the Competent Authority for giving Administrative Approval.
a. The appraised Total Capital Cost of the proposed Kanpur – Kabrai proposal is Rs.
7164.22 crore with a total estimated project cost (excluding GST) of Rs. 4694.48 crore.
b. The project should be taken up on BOT (Toll) under the NH(O) scheme.
c. The boundary wall component to be removed and replace with Toe wall with tree
plantation along the proposed project. Cost of the project as mentioned at 11 (a) above
to be adjusted accordingly.
d. PPPAC assess that the project would be viable with a VGF support of 40%. Hence, the
grant requirement is capped at a maximum of 40% for a concession period of 20 years,
including a construction period of 3 years.
e. The MoRTH shall fund the grant requirement under NH(O) scheme.
f. Land acquisition and necessary clearances to be obtained in a time bound manner
before the bid due date so as to avoid any delay in the project.
12. Revalidation of its recommendation by the PPPAC is not required for following post
recommendation changes in the project costs/bid documents: -
a. Any change in the date/time period for any time-bound actions like appointed date,
financial close, construction period etc.
b. Non-substantial change in risk-allocation.c. Any other changes/modification in the project proposal with the overall objective of
making project successful.
d. Further, MoRTH/NHAI may decide whether the changes proposed post
recommendations of the project proposal by the PPPAC fall within the threshold criteria
as stated above. All such changes falling within the threshold criteria shall be appraised
at the level of Secretary (RTH)/BoD of NHAI as the case may be, without any further
need of revalidation by the PPPAC and shall proceed with the approval process
accordingly.
***Annexure-I
List of the participants of the 139th meeting of the PPPAC
a. Department of Economic Affairs, Ministry of Finance
1. Ms. Anuradha Thakur, Secretary (EA)
2. Shri Chuni Lal Ghosh, Adviser (Energy)
3. Ms. Arya Balan Kumari, Joint Director (PIU)
4. Shri Rajender Singh, SO (PIU)
5. Shri Manjeet Yadav, ASO (PIU)
b. Department of Expenditure
1. Shri D. Anandan, Additional Secretary, Public Finance Central- I
c. NITI Aayog
1. Shri. Partha Reddy, Programme Director
d. Department of Legal Affairs
1. Shri Jagat Prakash, Assistant Legal Adviser
e. Ministry of Road Transport and Highways
1. Shri V Umashankar, Secretary (RTH)
2. Shri Puneet Agarwal- AS&FA
3. Shri Manoj Kumar, CE
f. National Highway Authority of India (NHAI)
1. Vishal Chauhan, Member (Admin)
2. Naveen Kumar, CGM(T) NHAI HQ
3. Sunil Kumar, GM(T)
4. Prashant Mahajan, DGM(T)