Date: 2025-06-20Category: Public Private Partnership in IndiaState: Union GovernmentCountry: India
Construction of 4 laning of Sahebganj Areraj Bettiah of NH-139W with Spur connectivity to Maker of (96.726 km) in the State of Bihar on HAM Mode comprising of (i) Package1: - Sahebganj to Areraj (38.362 km) and (ii) Package 2: - Areraj to Bettiah (40.580 km) and (iii) Construction of Spur Connectivity from NH-139w to NH722 (From Darihara to Maker (17.784 km)) in the state of Bihar.
**Executive Summary**
This document is the Record of Discussion of the 129th meeting of the Public Private Partnership Appraisal Committee (PPPAC) held on June 20, 2025, concerning the proposal for the construction of a four-lane highway in Bihar. The project involves the construction of 96.726 km of highway on Hybrid Annuity Mode. The PPPAC has recommended the proposal subject to certain recommendations, for consideration of the competent authority for giving administrative approval.
**Key Points / Main Content**
* **Project Overview:**
* Construction of 4-laning of Sahebganj Areraj Bettiah of NH-139W with Spur connectivity to Maker of (96.726 km) in Bihar on HAM Mode.
* Comprises three packages: Sahebganj to Areraj (38.362 km), Areraj to Bettiah (40.580 km), and Spur Connectivity from NH-139W to NH-722 (17.784 km).
* **Project Details:**
* PPP Model: Hybrid Annuity Mode (HAM).
* Sponsoring Authority: Ministry of Road Transport and Highways (MoRTH).
* Implementing Agency: National Highways Authority of India (NHAI).
* Lane configuration: 4-lanes.
* Concession Period: 17 years (including 2 years of construction).
* Estimated Total Capital Cost: ₹4531.81 crore.
* **Land Acquisition Status:**
* Varies across packages, with 3G acquisition yet to be initiated for the Spur connectivity.
* Balance 3A expected to be completed by December 2024.
* **Financial Viability:**
* PIRR: 13.04% (Sahebganj-Areraj), 12.23% (Areraj-Bettiah), 12.25% (Spur Connectivity).
* EIRR: 15.00% for all packages.
* Project will be implemented as per the Model Concession Agreement dated 09.12.2016.
* **Recommendations (PPPAC):**
* MoRTH should seek guidance from Cabinet Secretariat and develop a clear Standard Operating Procedure (SOP) for approving new NHs.
* Give priority to upgrading existing SHs/NHs over creating parallel greenfield corridors.
* MoRTH should ensure connectivity to habitations and economic nodes in future projects.
* Combine Package-I and Package-II for economies of scale.
* Do not develop Spur connectivity because it lacks economic and project optimization logic.
* Call for financial bids only after obtaining environmental clearance.
**Impact Analysis**
**Ministry of Road Transport and Highways (MoRTH)**
* **Impact**: Subject to specific recommendations, MoRTH is responsible for the successful implementation of the highway project to enhance connectivity in Bihar.
* **Action Required**:
* Seek guidance from Cabinet Secretariat and develop a SOP for approving new NHs.
* Re-evaluate the Spur connectivity and combine Package-I and Package-II.
**National Highways Authority of India (NHAI)**
* **Impact**: NHAI is the implementing agency and is responsible for executing the project according to the guidelines and recommendations provided.
* **Action Required**: Ensure project execution adheres to the PPPAC recommendations, including obtaining environmental clearances before financial bids and addressing land acquisition challenges.
**Department of Economic Affairs, Ministry of Finance**
* **Impact:** The Department has overseen the appraisal of the project.
* **Action Required:** Not stated in the document, but they are responsible for forwarding the document for information and action.
**Contractors/Concessionaires**
* **Impact**: They will be responsible for the construction and maintenance of the highway under the HAM model, facing risks related to project costs, construction timelines, and land acquisition delays.
* **Action Required**: The concessionaire will be responsible for utility shifting.
They must ensure that they have an environmental clearance for the project before the call for financial bids.
Key Entities Referenced
PPPAC: Public Private Partnership Appraisal Committee; responsible for considering and recommending the project proposal.
Ministry of Road Transport and Highways (MoRTH): The Sponsoring Authority for the project, responsible for highways.
National Highways Authority of India (NHAI): The Implementing Agency for the project.
Bihar: The state where the highway project is located.
Construction of 4 laning of Sahebganj Areraj Bettiah of NH-139W with Spur connectivity to Maker: The road construction project under consideration.
Subject: Record of Discussion of the 129th meeting of the PPPAC for considering the
“Construction of 4 laning of Sahebganj Areraj Bettiah of NH-139W with Spur
connectivity to Maker of (96.726 km) in the State of Bihar on HAM Mode
comprising of (i) Package1: - Sahebganj to Areraj (38.362 km), (ii) Package
2: - Areraj to Bettiah (40.580 km) & (iii) Construction of Spur Connectivity
from NH-139w to NH-722 (From Darihara to Maker 17.784 km) in the state of
Bihar”.
1. The 129th meeting of the PPPAC was held on 20th June 2025 at 12:30 hours to consider
the above proposals of MoRTH.
2. List of attendees is placed at Annexure-I.
3. With the permission of Finance Secretary cum Secretary (EA), Joint Secretary (ISD)
welcomed all the attendees to the meeting. NHAI made a detailed presentation on the
proposed road project.
4. The details of the project are given in the table below:
Table: Details of the project
Construction of 4-laning of Sahebganj-Areraj-Bettiah of NH-139W with Spur
connectivity to Maker of 96.726 km in the State of Bihar on HAM Mode
comprising of
(i) Package I: Sahebganj to Areraj (38.362 km)
Project Description
(ii) Package II: Areraj to Bettiah (40.580 km)
(iii) Spur connectivity: Construction of Spur Connectivity from NH-
139W to NH-722 (from Darihara to Maker 17.784 km)
PPP Model Hybrid Annuity Mode
Sponsoring Ministry of Road Transport and Highways, Government of India
Authority
Implementing National Highways Authority of India (NHAI)
Agency
State: Bihar
Location District: Purbi, Champaran
Town: Muzaffarpur, Paschim Champaran
Flexible
Type of Pavement
4-lanes
Lane configuration
S.N. Description Spur
Sahebganj Areraj Areraj Bettiah
Connectivity
Details of 1 Length (km) 38.362 km 40.580 km 17.784 km
Structures 2 Type of Flexible Pavement Flexible Flexible
Pavement (4L +PS) Pavement Pavement
(4L +PS) (4L +PS)
Page 2 of 123 Major Bridges Nil Bridge across Bridge across
(Nos.) Tirhut Canal: 01 Canal: 01 Nos
Nos Span-2x40
(250 m.;5 X50)
At Ch.29+998
4 Minor Bridges 05 Nos. 06 nos --
over river/
channels
5 Minor Bridges 07 nos. 04 Nos 04 Nos
over canals
6 Flyovers/ 02 Nos. 03 Nos. 03 Nos
grade
separator
(nos.)
7 Cloverleaf/
1 no. 1 no. 01 Nos
Trumpet
8 ROB Nil Nil 01 Nos (On
proposed railway
line)
9 VUP (Nos.) 3 Nos. 3 Nos. 2 Nos
LVUP (Nos.) 5 Nos. 5 Nos. 16 Nos
SVUP (Nos.) 4 Nos. 30 Nos. Nil
11 Box Culverts 85 Nos. 124 Nos. 31 Nos
(Nos.)
12 Length of Service Road - Service Road - Slip Road 5.950
Service 6.286 km (including 6.20 km Km (including
Roads/Slip both hand side) (including both both hand sides)
Roads (in Slip Road 10.162 hand side) Slip
Km) km (including both Road -3.80 km
hand side) (including both
hand side) &
Connecting link
road 2.278 km
(including both
hand side)
13 Total
construction 24 months 24 months 18 Months
period
Concession Period 17 years (Including 2 years Construction Period)
S. Description of Work Sahebganj Areraj Spur
Estimated Capital No Areraj Bettiah Connectivity
Cost with Break-up (Rs. in crore) (Rs. in crore) (Rs. in crore)
under major heads 1 Civil Construction Cost 888.43 998.66 370.10
of expenditure (including Utility
Shifting, Labor cess &
Page 3 of 12Seigniorage Charges
excluding GST)
2 Estimated Project Cost 934.73 1050.13 489.94
without GST
3 Estimated land and 350 471.33 113.4
other preconstruction
cost
4 Estimated Total Capital 1765.11 2057.20 709.50
Cost (including GST)
5 Total Combined Capital
4531.81
Cost
6 Estimated Bid Project 1169.54 1321.69 501.68
Cost
S r. Sahebganj to Spur
Description Areraj to Bettiah
No Areraj Connectivity
1 Total additional 210.00 Ha. out 194.0211 Ha. out of Additional
Land Required of which 1.95 which 21.5302 Ha. is Land of
(Ha) Ha. is govt. govt. land 86.561 Ha to
land be acquired.
2 3A Status 199.42 Ha has East Champaran Under
been published District: - Out of 77.7262 progress
on 10.02.2021 HA complete 76.9623 HA
& 20.10.2022. have been approved
published vide 4036(A)
Balance 3A is dated 19.09.2024
expected to be West Champaran
completed by District – Out of 116.295
December ’24. HA complete 100.658 HA
Land Acquisition
have been published on
Status
29.10.2024
3 3D Status 199.42 Ha has 3D of 76.77 Ha East Yet to start
been published Champaran published on
on 09.02.2022 27.02.2025, 3D of west
& 26.07.2023. Champaran completed,
likely to be submitted
after concurrence of
PPPAC
4 3G Status 3(G) of 158.34 Yet to initiated. Yet to start
Ha. land
amounting to
Rs. 222.28 Cr.
has been
approved.
Page 4 of 12Balance under
process.
Particulars Spur
Sahebganj-Areraj Areraj – Bettiah
Connectivity
status status
Financial Viability Status
PIRR 13.04 % 12.23 % 12.25%
EIRR 15.00% 15.00% 15.00%
Concession The project is proposed to be implemented as per Model Concession
Agreement Agreement dated 09.12.2016 uploaded on MoRTH website.
Bidding parameter Lowest Bid Project Cost.
Bidding process Single Stage Two-part system of bidding
5. The primary purpose of the proposed partially-access controlled four-lane greenfield
project corridor is to improve travel efficiency between Patna and Bettiah and enhance
connectivity in North Bihar. The proposed corridor shall also improve connectivity across
Hajipur, Saran, Vaishali, Siwan, Gopalganj, East and west Champaran including Nepal
border districts. The projected traffic on the proposed corridor is about 16,000 PCU/day
in 2025 and is expected to cross 50,000 PCU/day by 2047. Additionally, the upgradation
of the existing 2-lane SH-54 and SH-74 to a 4-lane/access-controlled facility were not
found feasible as it passes through dense habitations. Accordingly, the instant proposal
is to develop 4-lane partially access-controlled, greenfield corridor from Sahebganj to
Areraj (Package-1), Areraj to Battiah (Package-2) and Spur connectivity from Maker to
Darihara (connecting NH-722 and NH-139W).
6. The proposed greenfield alignment including the Spur is of 96.726 km length, supporting
average vehicular speeds of 80 km/h with design speed of 100 km/h. This will reduce
the overall travel time to approximately 2 hours, cutting journey time by over 50%
compared to existing alternatives, while offering safer, faster, and uninterrupted
connectivity for both passenger and freight vehicles.
7. The project will be executed under the HAM model with a Total Capital Cost of
Rs.4531.81 crore. The project is included under the NH(O) for the FY 2025-26. The
financial assessment indicates the project IRR is higher than 12% and the equity IRR is
15%.
8. After the detailed presentation, the Chair asked the PPPAC members for their
observations. DoLA supported the proposal and stated that no further comments to offer.
9. Director, DoE raised the following observations:
Page 5 of 12a) Despite relatively low projected traffic (4,884 PCUs for the year 2025), the Spur is
proposed as a 4-lane corridor. It is suggested that MoRTH may consider developing
2-lane Spur with provision for 4-lane ROW to accommodate future expansion.
b) MoRTH may develop a productivity test, similar to the one used by the Ministry of
Railways to assess project outcomes against initial objectives.
10. PD, NITI Aayog raised the following observations:
a) The traffic survey is 06 years old, as it was conducted in 2019. Whether there is any
change in the current pattern of traffic which may impact the design criteria?
b) Considering the low tollable-traffic (for instance, the tollable traffic of Areraj-Bettiah
is only 3000 vehicles) what is the justification for a greenfield 4-lane highway?
Whether the traffic loads been considered while designing the project?
c) The projected traffic level for the Spur connectivity in 2027 is 5,324 PCU only and
does not meet the criteria for construction of for 4-lane greenfield highway. MoRTH
may consider going for 2-lane in Spur connectivity.
d) The list of utilities to be shifted by the concessionaire needs to be properly identified
and listed out in the Schedule of the DCA.
11. JS(ISD) highlighted the following observations:
a) The project is designed as a partially access-controlled corridor. What is the
rationale behind going for partially access-controlled design?
b) The instant project is proposed to undertake in three packages including the Spur
connectivity. It is suggested to undertake the project in one package.
c) The cost of debt considered is 11.10% which is on a high side which may be revised
as per current market trend.
12. The Chair made the following observations:
a) Whether any Origin-Destination (OD) survey been conducted to assess existing
traffic patterns and justify the projected demand of Spur connectivity?
b) SH-54 and SH-74 are running parallel to the proposed project within a distance of
~20 kms. What is the rationale behind developing a greenfield highway running
close parallel to already existing State Highways?
Page 6 of 12c) Who is the competent authority to approve a new NH?
d) The Spur from Darihara to Maker is proposed to connect NH-139W to NH-722, but
these NHs are already connected at Manikpur, which is in close proximity to the
proposed Spur. The projected traffic in 2027 is ~5000 PCU only. Moreover, the spur
does not link to the main Sahebganj–Areraj-Bettiah section. In such a scenario,
what is the justification of the proposed Spur connectivity as a part of Sahebganj-
Areraj-Bettiah corridor?
e) The purpose of the NH shall be to connect large habitations and economic/industrial
nodes, whereas, in the instant proposal, road alignment runs parallel to a river and
does not appear to connect any significant habitation clusters. What is the rationale
for such alignment?
f) What is the anticipated timeline for obtaining environmental clearance from
MoEF&CC?
g) What is the tolling mechanism for the entire project?
13. MoRTH submitted the following to the queries raised by the PPPAC Members: -
a) The Spur would provide connectivity to NH-139W and NH-722 both having 4-lane
configuration. Therefore, it is proposed to keep the Spur connectivity as 4-lane and the
same was approved by the Alignment approval committee on 15.01.2025.
b) MoRTH has issued a circular on ‘Mechanism for monitoring outcome parameters of all
capacity-augmentation projects, including under Bharatmala Pariyojana-I’ on 5th June,
2025 wherein outcome parameters of the projects will be assessed against its initial
parameters.
c) The base traffic survey was conducted in 2019 and adjusted using econometric growth
models and vehicle registration trends till 2025. The current trend in vehicles have been
captured from vehicle registration data. The methodology is consistent with accepted
practices for long-term traffic forecasting. Hence, the 2019 data continue to provide a
reliable basis for corridor design and capacity planning.
d) As per the Indo-HCM 2017, the threshold capacity of a 2-lane road with paved shoulders
under mixed traffic is approximately 15,000 PCU/day. The projected AADT (Average
Annual Daily Traffic) for 2025 in the NH-139W corridor is 15,983–16,180 PCU/day,
indicating operation at or above LOS-E (Level of Service), which denotes high
congestion and sub-optimal travel conditions. This justifies the need for 4-laning for
smooth level of service. Further, the traffic survey used for forecasting follows the
Page 7 of 12standard DPR methodology wherein traffic counts are taken for a base year and
forecasted using established growth rates derived from regional development trends,
past registration data, and economic indicators. The traffic load has been considered
while designing the project.
e) Considering a comparative small length spur of about 18 km proposed to connect
between to NHs ( NH-139W with 4-lane configuration and NH-722 having more than
15,000 PCU and proposed for upgradation in coming years) , it is proposed to keep this
spur connectivity as 4-lane.
f) The utilities which need to be shifted is under scope of the concessionaire and shall be
made a part of final concession agreement.
g) The project is proposed to be access-controlled highway based on balance, cost-
effective approach. A Partially Access-Controlled Highway is a roadway where access
is regulated through designated entry and exit points but does not follow full
expressway-level restrictions. In the context of the proposed NH-139W corridor, access
is provided only through planned slip roads and service lanes connecting to the main
carriageway.
An access-controlled road is envisaged to improve travel efficiency between Patna and
Bettiah. Upon completion, it will offer a direct 163 km access-controlled corridor,
supporting average vehicular speeds of 80 km/h with design speed of 100 km/h. This
will reduce the overall travel time to approximately 2 hrs, cutting journey time by over
50% compared to existing alternatives, while offering safer, faster, and uninterrupted
connectivity for both passenger and freight vehicles.
h) The packaging of complete NH-139W corridor was planned as per differential land
acquisition readiness and administrative manageability. At present, approximately 80%
of land acquisition under Section 3G for the Sahebganj–Areraj package has been
completed, with disbursement underway. Land acquisition for the Areraj–Bettiah
package is still at the Section 3D stage. Land acquisition for the Spur package (3A) has
yet to commence. Combining these packages at this stage would likely to delay
construction timelines and significantly increase the total capital cost of the project.
i) The cost of debt shall be revised as per the prevalent market rate.
j) The Origin-Destination (OD) survey was conducted as part of the comprehensive traffic
study for the main corridor from Bakarpur to Dhumariya Ghat, carried out in Oct-Nov
2024. The proposed Maker Spur, constitutes the initial segment of this broader corridor.
Hence, the OD data relevant to the spur was adequately covered under the main survey
scope.
Page 8 of 12k) The existing route of Sahegbganj to Bettiah i.e., Via SH-74 & SH-54, which broadly runs
parallel to the proposed alignment, is a 2-lane intermediate standard road with poor
geometrics, non-uniform carriageway widths, and high levels of road side local
movement. It mainly caters to short-distance, intra-district rural and agricultural traffic,
and is unable to provide uninterrupted flow for inter-regional connectivity or heavy freight
movement. SH-74, SH-54 operates with limited capacity and poor Level of Service
(LOS), often falling under very LOS E during peak hours due to mixed traffic and
absence of shoulders or bypasses. Moreover, SH-74, SH-54 passes through multiple
built-up sections and market areas, leading to safety risks, travel time delays, and high
vehicle operating costs. Its widening to 4-lane standards was evaluated but found
infeasible due to higher cost and extensive resettlement issues and corridor
obstructions.
l) MoRTH is the Competent Authority for notifying a highway as National Highway.
m) The spur connectivity aims to connect NH-139W to NH-722 (From Darihara to Maker).
It will also improve connectivity in the northern parts of Bihar with capital city, ultimately
enhancing the efficiency of long-route traffic and freight movement from the
southwestern to the northeastern sector of the states. As there is no existing road along
the proposed project, the Spur connectivity would ensure last mile connectivity to the
surrounding settlements. Though Spur connectivity is not connected to Package-I and
Package-II of the proposal, it would connect to the habitations of west Ghandak river.
n) The project provides connectivity to scattered habitation areas throughout the project
alignment.
o) The environmental clearance from MoEF&CC shall be obtained within 3 months. The
public hearing is going on at present.
p) The corridor is currently proposed under open tolling with 03 toll plaza in entire corridor.
Although the corridor is initially proposed for open tolling due to staged implementation,
it will be considered for closed tolling via gantry-based or other barrierless methods once
completed.
Recommendations:
14. After detailed deliberations, the PPPAC unanimously recommended the proposal for
“Construction of 4 laning of Sahebganj Areraj Bettiah of NH-139W in the State of Bihar on
HAM Mode”, subject to following recommendations, for consideration of the competent
authority for giving administrative approval.
a) The decision of approving new NHs is not only about enhancing connectivity, it is also
about incurring huge public expenditure for developing such highways. It has been
Page 9 of 12observed that NHs are approved and the land acquisition starts before approval of such
expenditure by the Competent Authority. Therefore, MoRTH should seek guidance from
Cabinet Secretariat and develop a clear SOP for approving new NHs.
b) The practice of developing competing facilities at close proximity to existing NH/SH may
impact the toll potential of the existing roads. In addition, it is non-optimal use of
resources. Upgrading existing SHs/NHs should get priority over creating parallel
greenfield corridors. MoRTH should consider this factor for future Highway projects.
c) The fundamental objective of developing NHs is to establish connectivity between large
habitations and facilitate socio-economic integration. For future projects, MoRTH should
ensure that the NH alignment is designed to provides connectivity to the habitations and
economic nodes.
d) There should be an objective decision framework for deciding greenfield, brownfield,
bypass, access-controlled corridor, RoW, cost sharing by state governments for the
land, norms to regulate ribbon development, etc, considering competing demands on
the budget government resources. MoRTH should formulate such a framework,
undertake inter-ministerial consultation, and obtain approval of the competent authority
for the framework.
e) The appraised Total Capital Cost of Sahebganj-Areraj-Bettiah corridor is Rs. 3822.31
crore.
f) The Package-I (Sahebganj to Areraj) and Package-II (Areraj to Bettiah) should be
combined into a single package to leverage economies of scale and foster greater
synergy to the projects.
g) The Package-III, i.e., Spur connectivity from Darihara to Maker, is not an integral part of
proposed Sahebganj-Areraj-Bettiah corridor. It is neither connecting large habitational
areas nor economic nodes. NH-139W is already connected to NH-722 at Manikpur
which is in proximity to the proposed Spur at Maker. The projected traffic along the spur
is also not justifying the need of this spur. This spur connectivity lacks economic and
project optimization logic. Hence, the development of Spur connectivity is not
recommended.
h) The project may be taken up on HAM mode with 15-year concession period (including
the construction period) under the NH(O) scheme.
i) Financial bids for the project should be called only after obtaining the environmental
clearance.
Page 10 of 1215. Revalidation of its recommendation by the PPPAC is not required for the following post
recommendation changes in the project costs/bid documents: -
a) Any change in the date/time period for any time-bound actions like appointed date,
financial close, construction period etc.
b) Non-substantial change in risk-allocation.
c) Any other changes/modification in the project proposal with the overall objective of
making project successful.
d) Further, MoRTH/ NHAI may decide whether the changes proposed post
recommendations of the project proposal by the PPPAC fall within the threshold criteria
as stated above. All such changes falling within the threshold criteria shall be appraised
at the level of Secretary (RTH)/ BoD of NHAI as the case may be, without any further
need of revalidation by the PPPAC and shall proceed with the approval process
accordingly.
Page 11 of 12Annexure-I
List of the participants of the 129th meeting of the PPPAC
a) Department of Economic Affairs, Ministry of Finance
1. Shri Ajay Seth, Secretary, EA- In Chair
2. Ms. Anuradha Thakur, OSD(EA)
3. Shri Baldeo Purushartha, JS (ISD)
4. Ms. Arya Balan Kumari, Joint Director
5. Shri Rajender Singh, SO (PIU)
6. Shri Manjeet Yadav, ASO(PIU)
7. Shri Deepak Meena, ASO(PIU)
b) Department of Expenditure
1. Shri L. K. Trivedi, Director
c) NITI Aayog
1. Shri. Partha Reddy, Programme Director
d) Department of Legal Affairs
1. Dr. R.J.R. Kasibhatla, Joint Secretary & Legal Adviser
e) Ministry of Road Transport and Highways
1. Shri V Umashankar, Secretary (RTH)
2. Shri Puneet Agarwal AS&FA
3. Shri Vinay Kumar, AS(H)
4. Shri Manoj Kumar, CE
5. Shri Nazim Khan, AEE
f) National Highway Authority of India (NHAI)
1. Shri Santosh Kumar Yadav, Chairman
2. Shri Anil Chaudhary, Member
3. Shri L P Padhy, CGM
4. Shri Bhaskar Mishra, GM
5. Shri Abhishek Lodhwal, Manager
***