See Full Document Text
फा. सं. ऐरा/20010/एमवाईटीपी/जीआईएएल/सीपी-III/2022-27
F. No. AERA/20010/MYTP/GIAL/CP-III/2022-27
परामर्श पत्र संख् या 01/2024-25
Consultation Paper No. 01/2024-25
भारतीय ववमानपत् तन आवथशक वववनयामक प्राविकरण
Airports Economic Regulatory Authority of India
लोकवप्रय गोपीनाथ बारदोलाई अंतरराष्ट्रीय हवाईअड्डा (एलजीबीआईए) के वलए तृतीय वनयंत्रण
अववि (01.04.2022–31.03.2027) के वलए वैमावनक टैररफ वनिाशररत करने के मामले में
IN THE MATTER OF
DETERMINATION OF AERONAUTICAL TARIFF FOR
LOKPRIYA GOPINATH BORDOLOI INTERNATIONAL AIRPORT, GUWAHATI
(LGBIA)
FOR THE THIRD CONTROL PERIOD
(01.04.2022 - 31.03.2027)
जारी करने की तारीख : 06 जून, 2024
Date of Issue: 06 June, 2024
उड़ान भवन/ Udaan Bhawan, तृतीय तल/ 3rd Floor
डी ब्लॉक/ D Block, ऱाजीव ग़ाांधी भवन/ Rajiv Gandhi Bhawan
सफदरजांग एयरपोर्ट/ Safdarjung Airport
नई ददल् ली/New Delhi – 110003
पऱामर्ट पत्र सांख् य़ा 01/2024-25/Consultation Paper No 01/2024-25 पृष् ठ 254 क़ा 1/ Page 1 of 254STAKEHOLDERS’ COMMENTS
STAKEHOLDERS’ COMMENTS
Lokpriya Gopinath Bordoloi International Airport (LGBIA) is a Major Airport as per the definition outlined
in Section 2 (i) of the AERA Act 2008 read with AERA (Amendment) Acts of 2019 and 2021, based on
annual passenger throughput volume. It had passenger throughput of about 5.45 MPPA in the FY 2019-20
(being the pre-pandemic year). The Airport witnessed a steady recovery in the passenger traffic from FY
2021-22, in the aftermath of COVID-19 pandemic and has handled 5.05 million passengers in FY’231
LGBIA was operated by Airports Authority of India (AAI), which had entered into a Concession Agreement
with the current Airport Operator (Guwahati International Airport Limited) on January 19, 2021, for the
Operation, Management and Development of LGBIA for a period of 50 years from the Commercial
Operation Date (COD). The COD was achieved on October 8, 2021. The period from FY’17 to FY’21
was Second Control Period, the period starting from 1st April’2021 to October 7, 2021 has been
considered as pre-COD period and the period from COD till March 31, 2022, has been considered as
post-COD period. In this tariff determination exercise, as two airport operators are involved i.e., Airports
Authority of India (Second Control Period and pre-COD) and Guwahati International Airport Limited (post-
COD and third control period). For the sake of clarity in this Consultation Paper, the Authority has used AAI
for Airports Authority of India for prior to COD and GIAL for Guwahati International Airport Limited after
the COD including third control period.
GIAL, on 15th April 2022 sought clarification from the Authority related to control period for LGBIA. The
Authority vide its Public Notice No. 05/2022-23 dated 20th June 2022 decided the following:
“To shift the Control Period for Guwahati Airport from 01.04.2021-31.03.2026 to 01.04.2022-
31.03.2027. The periodicity of the Control Period will be five years only.
To consider the true up for 01.04.2021 to 31.03.2022 at the time of determination of tariff for the Third
Control Period as per AERA policy.”
As per the provisions of the Concession Agreement, AAI and the GIAL have submitted their Multi Year
Tariff Proposal (MYTP) as follows:
True up submission of AAI for the Second Control Period and for the period from April 01, 2021
up to COD
True up submission of GIAL for the post-COD period from the COD up to March 31, 2022
MYTP for the Third Control Period from April 1, 2022 to March 31, 2027 submitted by GIAL.
For this Consultation Paper, the Authority has considered the audited figures submitted by AAI for LGBIA
for the Second Control Period and for the period from April 01, 2021 up to COD (FY 2016-17 to COD) and
the audited financials submitted by GIAL from COD till March 31, 2022 and from April 1, 2022 till March
31,2023.
The Authority has released this Consultation Paper putting forward its proposals in the background of
involvement of two airport operators in the tariff determination process.
The Authority shall consider written evidence-based feedback, comments, and suggestions from all the
stakeholders on the proposals made in the Consultation Paper and pass suitable Order determining the tariff
for aeronautical services taking on board the feedback from the stakeholders, on merit. The Authority would
like to emphasize that the timelines for consultation process are sacrosanct and hereby requests the
stakeholders to provide their comments/ inputs within the timelines specified in this Consultation Paper,
beyond which the same will not be considered by the Authority.
1 AAI.aero https://www.aai.aero/sites/default/files/traffic-news/rev_Mar2k23Annex3.pdf
Consultation Paper No. 01/2024-25 Page 2 of 254STAKEHOLDERS’ COMMENTS
As per the provisions of Section 13(2) of the AERA Act 2008, the tariff so determined under the Tariff Order
can be reviewed and revised.
Thus, in accordance with the provisions of Section 13(4) of the AERA Act, the written comments on
Consultation Paper No. 01/2024-25 dated 06th June 2024, are invited from the stakeholders, preferably in
electronic form, at the following address:
Director (P&S, Tariff)
Udaan Bhawan, 3rd Floor
D Block, Rajiv Gandhi Bhawan
Safdarjung Airport
New Delhi – 110003
Email: director-ps@aera.gov.in, rajan.gupta1@aera.gov.in, inderpal.s@aera.gov.in copy to
secretary@aera.gov.in
Stakeholders’ Consultation Meeting 21st June 2024
Last Date for submission of comments 06th July 2024
Last Date for submission of counter comments 16th July 2024
Comments and Counter Comments will be posted on AERA’s website: www.aera.gov.in.
For any clarification/ information, Director (P&S, Tariff) may be contacted at Telephone
Number: Tel: 011-24695048.
Consultation Paper No. 01/2024-25 Page 3 of 254TABLE OF CONTENTS
TABLE OF CONTENTS
1 INTRODUCTION ............................................................ 17
1.1 Background .................................................................................................................................... 17
1.2 Profile of LGBIA ........................................................................................................................... 17
1.3 Development of LGBIA through PPP mode ................................................................................. 18
1.4 Cargo Facility ................................................................................................................................ 18
1.5 Ground handling operations .......................................................................................................... 19
1.6 Fuel Facility Operations ................................................................................................................ 19
2 TARIFF DETERMINATION OF LGBIA ............................................................ 20
2.1 Introduction ................................................................................................................................... 20
2.2 Authority’s orders applied in tariff proposals in this Consultation Paper ..................................... 21
2.3 Background to tariff determination process of LGBIA ................................................................. 21
2.4 Multi Year Tariff Proposal submission ......................................................................................... 22
2.5 Construct of this Consultation Paper ............................................................................................. 25
2.6 Studies commissioned by the Authority ........................................................................................ 26
3 FRAMEWORK FOR TARIFF DETERMINATION OF LGBIA FOR THE THIRD
CONTROL PERIOD ............................................................ 28
3.1 Methodology .................................................................................................................................. 28
3.2 Revenues from Air Navigation Services (ANS) ........................................................................... 28
4 TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD AND PRE-COD
PERIOD ............................................................ 30
4.1 Background .................................................................................................................................... 30
4.2 AAI’s submission regarding True up for SCP and period from 1st Apr’21 to 7th Oct’21 ............. 30
4.3 Authority’s examination of True up submitted by AAI for Second Control Period and pre-COD
period ............................................................................................................................................. 31
4.4 True up of Traffic .......................................................................................................................... 34
4.5 True up of Capital Expenditure (CAPEX) .................................................................................... 36
4.6 True up of Depreciation ................................................................................................................. 49
4.7 True up of RAB ............................................................................................................................. 50
4.8 True up of Fair Rate of Return ...................................................................................................... 52
4.9 True up of Aeronautical Operation and Maintenance (O&M) expenses ...................................... 53
4.10 True up of Non-aeronautical revenue ............................................................................................ 60
4.11 True up of Aeronautical Revenue .................................................................................................. 61
4.12 True up of Taxation ....................................................................................................................... 63
4.13 True up of Aggregate Revenue Requirement (ARR) for Second Control Period and the Pre-COD
Consultation Paper No. 01/2024-25 Page 4 of 254TABLE OF CONTENTS
period ............................................................................................................................................. 65
4.14 Adjusted Deemed Initial RAB ....................................................................................................... 66
4.15 Authority’s proposals regarding true up for SCP and pre-COD period (FY17 up to COD) ......... 68
5 TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022 ... 69
5.1 Background .................................................................................................................................... 69
5.2 GIAL’s submission regarding True up for the period from COD till March 31, 2022 ................. 69
5.3 Authority’s examination of the true up submitted by GIAL for the period from COD till March 31,
2022 ............................................................................................................................................... 70
5.4 True up of Capital Expenditure (CAPEX) .................................................................................... 70
5.5 True up of Depreciation ................................................................................................................. 72
5.6 True up of FRoR ............................................................................................................................ 73
5.7 True up of Aeronautical O&M expenses ...................................................................................... 74
5.8 True up of Non-aeronautical revenue (NAR) ................................................................................ 79
5.9 True up of Aeronautical Revenue .................................................................................................. 79
5.10 True up of Taxation ....................................................................................................................... 80
5.11 True up of Aggregate Revenue Requirement (ARR) for period from COD till March 31, 2022 . 81
5.12 Authority’s proposal regarding True up for the period from COD till March 31, 2022 ............... 81
6 TRAFFIC PROJECTIONS FOR THE THIRD CONTROL PERIOD ..................... 83
6.1 GIAL’s submission regarding Traffic projections for the Third Control Period .......................... 83
6.2 Authority’s examination regarding Traffic projections for the Third Control Period .................. 84
6.3 Authority’s Proposal regarding Traffic for the Third Control Period ........................................... 90
7 CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY
ASSET BASE (RAB) FOR THE THIRD CONTROL PERIOD ................................ 91
7.1 Background .................................................................................................................................... 91
7.2 GIAL’s submission regarding Capital Expenditure proposed for the Third Control Period ........ 93
7.3 Authority’s examination regarding Capex, Depreciation and RAB for the Third Control Period 93
7.4 Capital addition for the Third Control Period ............................................................................. 154
7.5 Depreciation for the Third Control Period .................................................................................. 157
7.6 Regulatory Asset Base (RAB) for the Third Control Period........................................................ 161
7.7 Authority’s proposal regarding CAPEX, Depreciation and RAB for the Third Control Period. 162
8 FAIR RATE OF RETURN (FROR) FOR THE THIRD CONTROL PERIOD .... 164
8.1 GIAL’s submission regarding FRoR for the Third Control Period ............................................. 164
8.2 Authority’s Examination regarding FRoR for the Third Control Period .................................... 165
8.3 Authority’s proposals regarding FRoR for the Third Control Period ......................................... 168
Consultation Paper No. 01/2024-25 Page 5 of 254TABLE OF CONTENTS
9 INFLATION FOR THE THIRD CONTROL PERIOD ........................................... 169
9.1 GIAL’s submission regarding Inflation for the Third Control Period ........................................ 169
9.2 Authority’s examination regarding Inflation for the Third Control Period ................................. 169
9.3 Authority’s proposal relating to inflation for the Third Control Period ...................................... 169
10 OPERATION AND MAINTENANCE (O&M) EXPENSES FOR THE THIRD
CONTROL PERIOD .......................................................... 170
10.1 GIAL’s submission regarding Operation and Maintenance (O&M) Expenses for the Third Control
Period ........................................................................................................................................... 170
10.2 Authority’s examination regarding Operation and Maintenance (O&M) Expenses for the Third
Control Period .............................................................................................................................. 173
10.3 Authority’s proposal regarding Aeronautical O&M expenses for Third Control Period ............ 203
11 NON-AERONAUTICAL REVENUE FOR THE THIRD CONTROL PERIOD .. 204
11.1 GIAL’s submission of Non-aeronautical revenue for the Third Control Period ......................... 204
11.2 Authority’s examination regarding Non-aeronautical revenue for the Third Control Period ..... 205
11.3 Authority’s proposal relating to Non-aeronautical revenue for the Third Control Period .......... 210
12 TAXATION FOR THE THIRD CONTROL PERIOD ............................................. 211
12.1 GIAL’s submission regarding Taxation for the Third Control Period ........................................ 211
12.2 Authority’s examination regarding Taxation for the Third Control Period .................................. 211
12.3 Authority’s proposal regarding Taxation for the Third Control Period ...................................... 212
13 QUALITY OF SERVICE FOR THE THIRD CONTROL PERIOD ...................... 213
13.1 GIAL’s submission relating to Quality of Service ...................................................................... 213
13.2 Authority’s examination regarding Quality of Service for the Third Control Period ................. 213
13.3 Authority’s proposal relating to Quality of Service for the Third Control Period ...................... 214
14 AGGREGATE REVENUE REQUIREMENT (ARR) FOR THE THIRD CONTROL
PERIOD .......................................................... 215
14.1 GIAL’s submission regarding ARR for the Third Control Period .............................................. 215
14.2 Authority’s examination of Aggregate Revenue Requirement (ARR) for the Third Control Period
..................................................................................................................................................... 215
14.3 Authority’s proposal regarding Aggregate Revenue Requirement (ARR) for the Third Control
Period ........................................................................................................................................... 217
15 SUMMARY OF THE AUTHORITY’S PROPOSALS PUT FORTH FOR
STAKEHOLDER CONSULTATION .......................................................... 219
Chapter 4: True up of AAI for the Second Control period from FY 2017 till COD ............................... 219
Chapter 5: True up of GIAL for the period from COD till March 31, 2022 ........................................... 219
Chapter 6: Traffic Projections for the Third Control Period .................................................................... 219
Consultation Paper No. 01/2024-25 Page 6 of 254TABLE OF CONTENTS
Chapter 7: Capital Expenditure (Capex), Depreciation and RAB for the Third Control Period ............. 219
Chapter 8: Fair Rate of Return (FRoR) for the Third Control Period ..................................................... 220
Chapter 9: Inflation for the Third Control Period .................................................................................... 220
Chapter 10: Operation and Maintenance Expenses for the Third Control Period ................................... 220
Chapter 11: Non-aeronautical revenue for the Third Control Period ...................................................... 220
Chapter 12: Taxation for the Third Control Period.................................................................................. 221
Chapter 13: Quality of Service for the Third Control Period .................................................................. 221
Chapter 14: Aggregate Revenue Requirement (ARR) for the Third Control Period .............................. 221
16 STAKEHOLDERS’ CONSULTATION TIMELINE................................................ 222
17 ANNEXURES .......................................................... 223
17.1 Annexure 1 – Summary of study on allocation of assets between Aeronautical and Non-
aeronautical assets ........................................................................................................................ 223
17.2 Annexure 2 - Summary of study on efficient Operation and Maintenance expenses ................. 233
17.3 Annexure 3 – Clauses of the Concession Agreement entered between AAI and GIAL ............. 239
18 APPENDICES .......................................................... 254
Consultation Paper No. 01/2024-25 Page 7 of 254LIST OF TABLES
LIST OF TABLES
Table 1: Shareholding pattern of GIAL .............................................................................................................. 17
Table 2: Technical and Terminal Building details of LGBIA as submitted by GIAL ....................................... 18
Table 3: Chronology of AERA orders with regard to extension of tariff at LGBIA .......................................... 22
Table 4: Sequence of events regarding true up submissions by AAI ................................................................. 23
Table 5: Sequence of events regarding true up and MYTP submissions by GIAL ............................................ 23
Table 6: Services provided to GIAL by related parties ...................................................................................... 25
Table 7: Submission of True up by AAI for the SCP and Pre-COD period ....................................................... 31
Table 8: AAI’s submission for True up of traffic for the Second Control Period for LGBIA ........................... 34
Table 9: Passenger traffic and ATM approved by the Authority for the Second Control Period ....................... 35
Table 10: RAB for Second Control Period and pre COD period as per AAI’s Submission .............................. 36
Table 11: Allocation of assets as per AAI’s submission .................................................................................... 36
Table 12: Allocation ratios as per AAI’s submission ......................................................................................... 37
Table 13: RAB as approved by Authority in the Tariff Order for Second Control Period (Table 33 of the
Order) ................................................................................................................................................................. 38
Table 14: Allocation Ratios proposed by the Authority ..................................................................................... 39
Table 15: Opening RAB approved by the Authority in the Second Control Period Tariff Order ...................... 40
Table 16: Capital additions submitted by AAI for the SCP and Pre-COD Period for LGBIA .......................... 40
Table 17: Reconciliation of Additions considered in the Second Control Period Order and Actuals incurred by
AAI ..................................................................................................................................................................... 41
Table 18: Reconciliation of Additions allowed in Second Control Period Order and Actuals incurred by AAI
............................................................................................................................................................................ 42
Table 19: Impact due to reclassification of AAI assets proposed by the Authority ........................................... 44
Table 20: Reclassification of assets capitalized in the Second Control Period and Pre-COD Period proposed by
the Authority ....................................................................................................................................................... 45
Table 21: Gross Block proposed by the Authority for Second Control Period and Pre COD period ................ 47
Table 22: Impact on depreciation due to reclassification of AAI assets for the SCP and pre-COD period ....... 49
Table 23: Depreciation considered by the Authority for True up of the SCP and Pre-COD Period .................. 49
Table 24: Adjusted RAB submitted by AAI and proposed by the Authority post re-classification for SCP and
pre-COD period .................................................................................................................................................. 50
Table 25: Assets transferred by AAI to GIAL as per JARS as on COD ........................................................... 51
Table 26: Determination of Deemed Initial RAB by the Authority ................................................................... 52
Table 27: Pro-rated FRoR for FY’22 considered by the Authority for true up of pre-COD period ................... 53
Table 28: O&M expenses submitted by AAI for True up of the SCP and Pre-COD Period .............................. 53
Table 29: Aeronautical O&M expenses approved by the Authority for Second Control Period ....................... 53
Table 30: CHQ/ RHQ expenses proposed by the Authority as part of True up of O&M expenses for the
Second Control Period and pre-COD period ...................................................................................................... 58
Table 31: Impact of proposed reallocation of AAI’s Aeronautical O&M expenses as per the independent study
conducted by the Authority ................................................................................................................................ 59
Table 32: Aeronautical O&M expenses considered by the Authority for True up of the Second Control Period
and Pre-COD period ........................................................................................................................................... 59
Table 33: Non-aeronautical revenue submitted by AAI for SCP and up to Pre-COD period ............................ 60
Table 34: Comparison of Actual NAR with Projections submitted by AAI for the Second Control Period and
Pre-COD period .................................................................................................................................................. 60
Table 35: “Space rentals collected from Airlines” as submitted by AAI ........................................................... 61
Table 36: Total Non-Aeronautical revenue as per Authority for the Second Control Period and Pre-COD
period .................................................................................................................................................................. 61
Table 37: Aeronautical revenue as per AAI for the Second Control Period and Pre-COD period .................... 61
Table 38: Comparison of Actual Aeronautical revenue and Projections submitted by AAI for the Second
Control Period and Pre-COD Period .................................................................................................................. 62
Table 39: Total Aeronautical revenue as per Authority for the Second Control Period and Pre-COD period ... 63
Table 40: Taxation submitted by AAI for the Second Control Period and Pre-COD period ............................. 63
Table 41: Taxation proposed by the Authority for the Second Control Period and Pre-COD period ................ 64
Consultation Paper No. 01/2024-25 Page 8 of 254LIST OF TABLES
Table 42: ARR proposed by the Authority for Second Control Period and Pre-COD Period............................ 65
Table 43: Determination of Adjusted Deemed Initial RAB as on COD by the Authority ................................. 66
Table 44: Determination of Adjusted Deemed Initial RAB as on Specified and Future Payment Dates ........... 67
Table 45: True Up submitted by GIAL from COD till March 31, 2022 ............................................................ 69
Table 46: Additional items included in RAB by GIAL from COD till March 31, 2022 .................................... 70
Table 47: Impact of Reclassification of Asset Additions by GIAL from COD till March 31, 2022 .................. 72
Table 48: Impact on Depreciation post reclassification and revised useful life by the Authority ...................... 72
Table 49: Depreciation impact due to Reclassification of Asset Additions (Post-COD Period)........................ 72
Table 50: Average RAB considered by the Authority from COD till March 31, 2022 ...................................... 73
Table 51: FRoR proposed by the Authority from COD to March 31, 2022 ....................................................... 74
Table 52: O&M expenses submitted by GIAL for the period from COD till March 31, 2022 .......................... 74
Table 53: Bank & Finance Charges considered by the Authority for Post COD Period .................................... 74
Table 54: Pre-COD expenses proposed by the Authority for the Third Control Period..................................... 76
Table 55: Impact of proposed reallocation of GIAL’s Aeronautical O&M expenses ........................................ 78
Table 56: Reallocated Aeronautical O&M expenses of GIAL from COD to March 31, 2022 .......................... 78
Table 57: NAR submitted by GIAL for True up from COD till March 31, 2022 .............................................. 79
Table 58: NAR proposed by the Authority for True up from COD till March 31, 2022 ................................... 79
Table 59: Aeronautical Revenue submitted by GIAL for True up from COD till March 31, 2022 ................... 80
Table 60: Aeronautical Revenue proposed by the Authority for True up from COD till March 31, 2022 ........ 80
Table 61: Taxation proposed by the Authority for true up (COD till 31st March 2022) ................................... 80
Table 62: ARR and Shortfall proposed by the Authority (COD till March 31, 2022) ....................................... 81
Table 63: Historical passenger, ATM and Cargo traffic at LGBIA ................................................................... 83
Table 64: Traffic and growth (%) Y-o-Y proposed by GIAL ........................................................................... 83
Table 65: Cargo volumes to be handled by GIAL out of the total cargo traffic during the Third Control Period
............................................................................................................................................................................ 84
Table 66: Traffic growth rates (Y-o-Y) submitted by GIAL, after adjustment of exempt traffic ..................... 84
Table 67: Exempt traffic considered by the Authority for the Third Control Period ......................................... 85
Table 68: CAGR for passenger traffic, ATM, and Cargo .................................................................................. 86
Table 69: Comparison of Passenger, ATM and Cargo traffic at LGBIA of FY2019-20 vs FY 2022-23 .......... 87
Table 70: Forecasted and Actual Passenger, ATM, Cargo traffic submitted by GIAL for FY’24 ..................... 87
Table 71: Traffic proposed to be considered by the Authority for the Third Control Period ............................. 88
Table 72: Asset-wise Aero Capitalisation submitted by GIAL for the Third Control Period ............................ 93
Table 73: Project wise Capital Expenditure submitted by GIAL for the Third Control Period ......................... 94
Table 74: Details of Total CAPEX as submitted by GIAL ................................................................................ 98
Table 75: Inflation Adjusted normative rates computed for the Terminal Building by the Authority ............. 101
Table 76: Inflation adjusted Normative rates computed for runway/taxiway/apron by the Authority ............. 101
Table 77: Details of Change in area proposed by GIAL over previous design ................................................ 105
Table 78: Cost comparison of NITB sanctioned originally, awarded and project by GIAL ............................ 106
Table 79 : Details of cost of Terminal Building proposed by the Authority. ................................................... 108
Table 80: Details of cost for kerbside development ......................................................................................... 109
Table 81: Details of normative cost for Runway/Taxiway/Apron works ......................................................... 111
Table 82: Details of the cost submitted by GIAL and proposed by the Authority towards Apron works ....... 112
Table 83: Authority’s examination of Airside Storm Water Drainage cost ..................................................... 113
Table 84: Authority’s examination of Part Parallel Taxiway and Link Taxiway cost ..................................... 114
Table 85: Authority’s examination of cost pertaining to land development works: ........................................ 115
Table 86: Authority’s examination of widening of Runway Basis Strip .......................................................... 118
Table 87: Authority’s examination of Extension of Runway cost.................................................................... 119
Table 88: Normative cost for Apron (FY’25) .................................................................................................. 120
Table 89: Authority’s examination of Cost towards new isolation bay ........................................................... 121
Table 90: Authority’s examination of cost towards Rapid Exit Taxiway project ............................................ 121
Table 91: Details of other minor works proposed by GIAL and the Authority ................................................ 123
Table 92: Air Cargo demand projections, capacity of LGBIA ......................................................................... 126
Table 93: Cost proposed by GIAL towards ICC Facility ................................................................................. 127
Table 94: Details of Fuel farm capex submitted by GIAL ............................................................................... 127
Consultation Paper No. 01/2024-25 Page 9 of 254LIST OF TABLES
Table 95: Cost proposed toward Vehicles by the Authority for the Third Control Period ............................... 129
Table 96: Details of Plant and Machinery submitted by GIAL and proposed by the Authority ...................... 131
Table 97: Cost of administrative building as per GIAL and proposed by the Authority.................................. 133
Table 98: Details of Integrated building submitted by GIAL and proposed by the Authority ......................... 133
Table 99: Capex proposed toward Other Buildings by the Authority for Third Control Period ...................... 134
Table 100: Capex proposed toward IT equipment by the Authority for Third Control Period ........................ 135
Table 101: Details of miscellaneous security equipment ................................................................................. 137
Table 102: Details of sustaining capex for FY'23 ............................................................................................ 138
Table 103: Capital Expenditure proposed by the Authority for the Third Control Period ............................... 138
Table 104: Asset head wise analysis and observation regarding soft cost ....................................................... 148
Table 105: FA and IDC submitted by GIAL .................................................................................................... 149
Table 106: Asset category wise details of Interest During Construction as per the Authority ......................... 150
Table 107: IDC proposed by the Authority for the Third Control Period ........................................................ 151
Table 108: Summary of the CAPEX proposed by the Authority for Third Control Period ............................. 151
Table 109: Asset wise allocation for asset addition proposed in third control period ...................................... 154
Table 110: Capitalization schedule proposed by the Authority for the Third Control Period .......................... 154
Table 111: Year wise details for Aeronautical capex proposed by the Authority for the Third Control Period
.......................................................................................................................................................................... 154
Table 112: Depreciation rates determined by GIAL for the Third Control Period .......................................... 157
Table 113: Depreciation submitted by GIAL for the Third Control Period ..................................................... 158
Table 114: Useful Life proposed by the Authority for all the assets in the Third Control Period ................... 160
Table 115: Aeronautical depreciation proposed by the Authority for the Third Control Period ...................... 160
Table 116: Depreciation claimed by GIAL and proposed by the Authority for the Third Control Period....... 161
Table 117: RAB proposed by GIAL for LGBIA for the Third Control Period ................................................ 161
Table 118: RAB proposed by the Authority for LGBIA for the Third Control Period .................................... 162
Table 119: Cost of equity computation as per GIAL’s submission .................................................................. 164
Table 120: Breakdown of all-in External Commercial Borrowing cost of Adani Airport Holdings Limited .. 164
Table 121: FRoR computation submitted by GIAL ......................................................................................... 165
Table 122: Computation of Cost of equity as per IIM Bangalore independent study reports .......................... 165
Table 123: Fair Rate of Return proposed by the Authority for the Third Control Period ................................ 167
Table 124: WPI inflation rate submitted by GIAL ........................................................................................... 169
Table 125: WPI inflation rates as per RBI’s annual forecast ........................................................................... 169
Table 126: Inflation rates proposed by the Authority for Third Control Period ............................................... 169
Table 127: Details of increase in the Terminal Building area projected by GIAL ........................................... 170
Table 128: O&M expenses (category wise) claimed by GIAL for the Third Control Period .......................... 170
Table 129: Segregation of O&M expenses and basis of allocation as per GIAL’s submission ....................... 171
Table 130: Total Aeronautical Operation and Maintenance expenses submitted by GIAL ............................. 171
Table 131: Growth rates for Aeronautical O&M expenses submitted by GIAL for the Third Control Period 172
Table 132: One-time Escalation rates for Aeronautical O&M expenses submitted by GIAL for the Third
Control Period .................................................................................................................................................. 173
Table 133: Allocation of O&M expenses submitted by GIAL and proposed by the Authority for the Third
Control Period .................................................................................................................................................. 177
Table 134: One-time escalation claimed by GIAL and Increase % Proposed by the Authority ...................... 177
Table 135: Department-wise Select employees of AAI deputed to LGBIA as submitted by GIAL ................ 178
Table 136: Manpower cost of AAI employees claimed by GIAL and proposed by the Authority .................. 179
Table 137: Dept. wise Head Count of Employees as per GIAL’s submission for the Third Control Period ... 181
Table 138: Headcount of Aeronautical employees of LGBIA for the Period from FY’17 to FY’20 ............... 184
Table 139: Estimated Passenger and ATM traffic of LGBIA .......................................................................... 184
Table 140: Employee Head Count of GIAL and revised EHCR proposed by the Authority for the Third
Control Period .................................................................................................................................................. 185
Table 141: Manpower cost of Aero employees proposed by the Authority for the Third Control Period ...... 186
Table 142: Utility expenses claimed by GIAL and proposed by the Authority for the Third Control Period . 188
Table 143: IT expense of GIAL as proposed by the Authority for the Third Control Period .......................... 188
Table 144: Rates and Taxes of GIAL as proposed by the Authority for the Third Control Period .................. 189
Consultation Paper No. 01/2024-25 Page 10 of 254LIST OF TABLES
Table 145: Security expense of GIAL as proposed by the Authority for the Third Control Period ................. 190
Table 146: Actual Corporate Cost incurred with allocation basis submitted by GIAL for FY’23 ................... 191
Table 147: Corporate Cost Allocation expenses claimed by GIAL and Proposed by the Authority ......... 192
Table 148: Admin expenses claimed by GIAL and proposed by the Authority for the Third Control
Period ............................................................................................................................................................... 193
Table 149: Insurance expenses claimed by GIAL and proposed by the Authority for the Third Control
Period ............................................................................................................................................................... 194
Table 150: R&M on Opening Net block of Assets claimed by GIAL and Proposed by the Authority for the
Third Control Period ......................................................................................................................................... 194
Table 151: Other Opex claimed by GIAL and proposed by the Authority for the Third Control Period 195
Table 152: Fuel O&M expenses claimed by GIAL for each FY for the Third Control Period................. 197
Table 153: Fuel Opex claimed by GIAL and allowed by the Authority for the Third Control Period ............ 198
Table 154: Cargo O&M expenses claimed by GIAL and proposed by the Authority for the Third Control
Period ................................................................................................................................................................ 199
Table 155: Working Capital Interest, Annual Fees for PBG and Finance Charges claimed by GIAL and
proposed by the Authority for the Third Control Period .................................................................................. 200
Table 156: Total Aeronautical O&M expenses proposed by the Authority for the Third Control Period ....... 201
Table 157: Growth rates in Aeronautical O&M expenses proposed by the Authority for the Third Control
Period ................................................................................................................................................................ 202
Table 158: Non-aeronautical revenue submitted by GIAL for the Third Control Period ................................ 205
Table 159: Year wise NAR earned by AAI and projected by GIAL ................................................................ 207
Table 160: Adjustment to Revenue from Non-Aeronautical Services considered by the Authority for FY 2022-
23 ...................................................................................................................................................................... 209
Table 161:Total Non-aeronautical revenues proposed by the Authority for Third Control Period .................. 210
Table 162: Taxation submitted by GIAL for the Third Control Period............................................................ 211
Table 163: Taxation proposed by the Authority for the Third Control Period ................................................. 212
Table 164: ASQ rating for LGBIA ................................................................................................................... 213
Table 165: ARR submitted by GIAL for the Third Control Period ................................................................. 215
Table 166: ARR proposed by the Authority for the Third Control Period ....................................................... 217
Table 167: The ratio of Aeronautical to Non-aeronautical considered by the Study for the period from FY’17
to FY’22 ........................................................................................................................................................... 224
Table 168: Impact due to reclassification of AAI assets as per Study ............................................................. 226
Table 169: Impact on depreciation due to reclassification of AAI assets ........................................................ 226
Table 170: Adjusted RAB derived by the Authority post reclassification ...................................................... 227
Table 171: Impact of Reclassification of Asset Additions by GIAL from COD till March 31, 2022 .............. 229
Table 172: Useful Life proposed by GIAL and the Authority ........................................................................ 229
Table 173: Impact on Depreciation due to Reclassification of Asset Additions by GIAL and Revised Useful
Life as per the Authority from COD till March 31, 2022 ................................................................................. 230
Table 174: Total Impact on Depreciation due to Reclassification of Asset Additions from COD till March 31,
2022 .................................................................................................................................................................. 230
Table 175: Average RAB considered by the Authority from COD till March 31, 2022 .................................. 230
Table 176: Revised Gross block of Assets up to COD as per the Study report ................................................ 231
Table 177: Revised Gross block of Assets as on March 31, 2022 as per the Study ......................................... 231
Table 178: Aeronautical O&M expenses of LGBIA for the Second Control Period - Approved vs. Actuals . 233
Table 179: Segregation ratio for O&M expenses as per AAI’s submission .................................................... 235
Table 180: Revised segregation ratio for O&M expenses as per the study ...................................................... 235
Table 181: O&M expenses submitted by AAI and as per Study for the SCP and pre-COD Period ............... 236
Table 182: Impact of proposed reallocation of GIAL’s Aeronautical O&M expenses .................................... 236
Table 183: Year-wise summary of reclassification and other adjustments to Aero O&M expenses ............... 237
Consultation Paper No. 01/2024-25 Page 11 of 254GLOSSARY
List of Figures
Figure 1: Ownership Structure ........................................................................................................................... 17
Figure 2: Proposed layout for Arrival Floor ..................................................................................................... 103
Figure 3: Proposed layout for Mezannine Floor ............................................................................................... 104
Figure 4: Proposed layout for Departure Floor................................................................................................. 104
Figure 5: Proposed layout for Departure Mezzanine Floor .............................................................................. 105
Figure 6: Proposed layout for Apron 2 at LGBIA ............................................................................................ 111
Figure 7: Existing drainage system at LGBIA ................................................................................................. 113
Figure 8: Low lying area at LGBIA ................................................................................................................. 115
Figure 9: Proposed aircraft movement at part parallel taxiway ........................................................................ 119
Figure 10: Proposed Hydrant System at LGBIA .............................................................................................. 128
Figure 11: Year wise NAR earned by AAI and projected by GIAL ................................................................ 207
Figure 12: Year-wise NAR per passenger earned by AAI and projected by GIAL ......................................... 208
Consultation Paper No. 01/2024-25 Page 12 of 254GLOSSARY
GLOSSARY
Abbreviation Full Form
A&G Administrative & General
AAHL Adani Airport Holdings Limited
AAI Airports Authority of India
AAICLAS AAI Cargo Logistics and Allied Services
ACI Airports Council International
ADP Automatic Data Processing
AERA / The Authority Airports Economic Regulatory Authority of India
AERA Act Airports Economic Regulatory Authority of India Act, 2008
AEL Adani Enterprises Limited
AFS Air Freight Station
AIC Aeronautical Information Circulars
ANS Air Navigation Services
AO Airport Operator
AOCC Airport Operations Control Centre
ARFF Aircraft Rescue and Fire Fighting
ARR Aggregate Revenue Requirement
ASQ Airport Service Quality
Asset Allocation Study Study on allocation of assets between Aeronautical and Non-aeronautical assets for
Report Lokpriya Gopinath Bordoloi International Airport, Guwahati
ATC Air Traffic Control
ATF Aviation Turbine Fuel
ATM Aircraft Traffic Movement
AUCC Airport Users Consultative Committee
BCAS Bureau of Civil Aviation Security
BDDS Bomb Detection and Disposal Squad
BHS Baggage Handling System
BIAL Bangalore International Airport Limited
BOQ Bill of Quantities
BPCL Bharat Petroleum Corporation Limited
Cr. crores
CA Concession Agreement
CAG Comptroller and Auditor General of India
CAGR Compounded Annual Growth Rate
CAO Chief Airport Officer
CAPEX Capital Expenditure
CAR Civil Aviation Regulations
CBR California Bearing Ratio
CFT Crash Fire Tender
Consultation Paper No. 01/2024-25 Page 13 of 254GLOSSARY
Abbreviation Full Form
CGF Cargo Facility, Ground Handling and Supply of Fuel to Aircraft
CHQ Corporate Headquarters
CIAL Cochin International Airport Limited
CISF Central Industrial Security Force
CNS Communication, Navigation and Surveillance
COD Commercial Operation Date
CP Consultation Paper
CPWD Central Public Works Department
CSR Corporate Social Responsibility
CUSS Common User Self Service
CUTE Common User Terminal Equipment
CWIP Capital Works in Progress
DG Sets Diesel Generator Sets
DGCA Directorate General of Civil Aviation
DIAL Delhi International Airport Limited
DSR Delhi Schedule of Rates
DVOR Doppler Very High Frequency Omni Range
EHCR Employee Head Count Ratio
e-PoS Electronic Point of Sale
ESS Environmental Support Services
ETD Explosive Trace Detectors
FA Financing Allowance
FAR Fixed Asset Register
FCP First Control Period
FICCI Federation of Indian Chambers of Commerce and Industry
FIDS Flight Information Display System
FOD Foreign Object Debris
FRoR Fair Rate of Return
FTC Fuel Throughput Charge
FRoR
FY Financial Year
GA General Aviation
GBR Gross Block Ratio
GDP Gross Domestic Product
GHA Ground Handling Agent
GHIAL GMR Hyderabad International Airport Limited
GoI Government of India
GSE Ground Support Equipment
GST Goods and Services Tax
GIAL Guwahati International Airport Limited
Consultation Paper No. 01/2024-25 Page 14 of 254GLOSSARY
Abbreviation Full Form
HIAL Hyderabad International Airport Limited
HPCL Hindustan Petroleum Corporation Limited
HR Human Resources
HVAC Heat Ventilation and Air Conditioning
IAF Indian Air Force
IATA International Air Transport Association
ICAO International Civil Aviation Organization
ICD Inland Container Depot
ICT Integrated Cargo Terminal
IDC Interest During Construction
ILHBS Inline Hold Baggage Screening
ILS Instrument Landing System
IMG Inter-Ministerial Group
IOCL Indian Oil Corporation Limited
IT Information Technology
JARS Joint Asset Reconciliation Statement
KL Kilo Litres
KLD Kilo Litres per day
LED Light Emitting Diode
LGBIA Lokpriya Gopinath Bordoloi International Airport
LOA Letter of Award
MESS Mechanized Environmental Support Services
MoCA Ministry of Civil Aviation
MoU Memorandum of Understanding
MPPA Million Passengers per Annum
MYTP Multi-Year Tariff Proposal
MIAL Mumbai International Airport Limited
MT Metric Tonne
NAR Non-aeronautical revenue
NITB New Integrated Terminal Building
O&M Operation and Maintenance
O&M study report Study on Efficient Operations & Maintenance expenses for Lokpriya Gopinath
NAR Bordoloi International Airport, Guwahati
OMCs Oil Marketing Companies
OPEX Operating Expenditure
ORAT Operational Readiness and Airport Transfer
OWS Oil Water Separator
PAX Passenger
PBB Passenger Boarding Bridge
Consultation Paper No. 01/2024-25 Page 15 of 254GLOSSARY
Abbreviation Full Form
PBG Performance Bank Guarantee
PBT Profit Before Tax
PCN Pavement Classification Number
PHP Peak Hour Passenger
PIDS Perimeter Intrusion Detection System
PMC Project Management Consultancy
PPP Public Private Partnership
PSF Passenger Service Fee
PTB Passenger Terminal Building
PV Present Value
PQCSND Quality and Service Delivery
QTR Quarters Ratio
R&M Repair and Maintenance
RAB Regulatory Asset Base
RBI Reserve Bank of India
RCS Regional Connectivity Scheme
RESA Runway End Safety Area
RFP Request for Proposal
RHQ Regional Headquarters
RIL Reliance Industries Limited
Sq.m. Square Metre
SCP Second Control Period
SITC Supply, Installation, Testing & Commissioning
SPV Special Purpose Vehicle
STP Sewage Treatment Plant
TB Terminal Building
TB Ratio Terminal Building Ratio
TCP Third Control Period
UDF User Development Fees
VDGS Visual Docking Guidance System
WDV Written Down Value
WIP Work In Progress
WPI Wholesale Price Index
XBIS X-ray Baggage Inspection System
YPP Yield per Passenger
Y-o-Y Year on Year
YTD Year to Date
Consultation Paper No. 01/2024-25 Page 16 of 254INTRODUCTION
1 INTRODUCTION
1.1 Background
1.1.1 Lokpriya Gopinath Bordoloi International Airport (LGBIA) (IATA: GAU, ICAO: VEGT), situated
about 20 km west of Guwahati City, is an International Airport serving the economic capital of Assam.
It is the gateway airport to the state of Assam and the wider North-East Region of India.
1.1.2 LGBIA has a single runway measuring 3103 meters. It is designated to handle aircraft up to Category
4D but can accommodate aircraft up to Category 4E with prior intimation under load penalty. The
airport is connected by direct flights to Bhutan and South-East Asia, apart from multiple daily flights
to all major cities in India.
1.1.3 LGBIA is currently operated and managed by Guwahati International Airport Limited (GIAL) (Airport
Operator), a Special Purpose Vehicle (SPV), promoted and incorporated by Adani Enterprises Limited
(AEL). AEL has incorporated a 100% subsidiary named Adani Airport Holdings Limited (AAHL). As
on date, AEL holds 100% shareholders equity in GIAL, directly or indirectly through AAHL. The
current shareholding pattern of GIAL is shown in the table below:
Table 1: Shareholding pattern of GIAL
S.no. Name of Shareholder % Shareholding
1 Adani Enterprises Limited (AEL) 51%
2 Adani Airport Holdings Limited (AAHL) 49%
TOTAL 100%
Figure 1: Ownership Structure
1.2 Profile of LGBIA
1.2.1 Lokpriya Gopinath Bordoloi International Airport, Guwahati (LGBIA) is a major airport as per the
definition of Major Airport under section 2(i) of the Airports Economic Regulatory Authority of India
Act, 2008 read with AERA Amendment Act, 2019 and AERA Amendment Act, 2021.
1.2.2 Technical and Terminal Building details of LGBIA submitted by GIAL are provided in the table
below:
Consultation Paper No. 01/2024-25 Page 17 of 254INTRODUCTION
Table 2: Technical and Terminal Building details of LGBIA as submitted by GIAL
Particulars Details
Total airport area 826.243 acres
Carved Out approx. 28.4 Acres
Demised approx. 797.843 Acres
Total covered area of Terminal Building Terminal I - 20,300 Sq.m.
(TB)
Designated Capacity Existing 2 MPPA
Main Runway orientation and length Runway 02/20, dimension 3103m x 45m
Apron Apron 1: 09 Code C Stands
Apron 2: 11 Code C Stands
1.2.3 LGBIA handled 5.05 MPPA in FY 2022-232 and 5.96 MPPA in FY2023-243. As per the passenger
mix, the domestic passengers handled during FY 2022-23 were 5.04 MPPA (99.8% of total passenger
traffic) and international passengers handled during FY 2022-23 were 0.01 MPPA (0.2% of total
passenger traffic).
1.3 Development of LGBIA through PPP mode
1.3.1 LGBIA was operated by the Airports Authority of India (AAI) which had entered into a Concession
Agreement with Guwahati International Airport Limited (Airport Operator) on January 19, 2021,
for the Operation, Management and Development of LGBIA for a period of 50 years from the
Commercial Operation Date (COD). The COD was achieved on October 8, 2021, in accordance
with the terms and conditions mentioned in the Concession Agreement. In consideration for the
grant of such concession, the Airport Operator shall pay the AAI a monthly concession fee during
the concession period, namely, specified amount of ‘Per Passenger’ fee for both domestic and
international passengers (refer to Para 17.3.2 of Annexure 3 in Chapter 17 for the relevant clause
of the Concession Agreement).
1.3.2 However, as per the relevant provisions of the Concession Agreement and MoU dated August 25,
2021, only the AAI and other designated GoI agencies, shall be authorized to undertake the
‘reserved services’ at the airport, namely, CNS/ATM services, Security services, Meteorological
services, Mandatory health services, Customs control, Immigration services, Quarantine services
and any other services as may be notified by GoI (refer to Para 17.3.2 of Annexure 3 of Chapter
17 for the relevant clause of the Concession Agreement).
1.4 Cargo Facility
1.4.1 Currently, the domestic and international air cargo is handled by AAI Cargo Logistics and Allied
Services (AAICLAS) through a carved-out facility as per the Concession Agreement, hence, same is
retained by AAI.
1.4.2 In accordance with the terms of the Concession Agreement GIAL is required to upgrade, develop,
operate and maintain the Cargo Facilities in accordance with the provisions of the Concession
Agreement (refer to Para 17.3.5 of Annexure 3 of Chapter 17).
1.4.3 GIAL has commenced domestic cargo operations from an interim facility having annual handling
capacity of 2,750 MT. Pursuant to the terms of the Concession Agreement and in order to cater to the
2 As per aai.aero https://www.aai.aero/sites/default/files/traffic-news/rev_Mar2k23Annex3.pdf
3 As per aai.aero https://www.aai.aero/sites/default/files/traffic-news/Mar2k24Annex3.pdf
Consultation Paper No. 01/2024-25 Page 18 of 254INTRODUCTION
growing cargo demand at the LGBIA, GIAL has planned to develop a new Integrated Cargo Terminal
(ICT) with a handling capacity of 43,260 MT p.a., by refurbishing/retrofitting the existing passenger
Terminal I post the commissioning of the NITB. The ICT is proposed to be made operational in FY25-
26.
1.4.4 The Authority vide interim Tariff Order No. 41/2023-24 dated March 15, 2024 extended the prevailing
tariffs for Guwahati International Airport Limited and AAICLAS till September 30, 2024.
1.5 Ground handling operations
1.5.1 The Clause 19.2 of the Concession Agreement mentions GIAL’s obligations towards provision of
infrastructure required for ground handling services at the LGBIA and the extract of the relevant Clause
has been provided in Para 17.3.6 of Annexure 3 of Chapter 17.
1.5.2 Further, subject to the provisions of the Concession Agreement GIAL has the right to grant License to
any entity for providing Ground Handling Services at LGBIA on such terms and conditions as
mentioned in the License Agreement between GIAL and the potential service providers.
1.5.3 Pursuant to above terms of the Concession Agreement GIAL has engaged two ground handling
agencies for providing ground handling services at the Airport. (1) Indo Thai Airport Management
Services Private Limited, (2) AI Airport Services Limited (AIASL).
The revenue share/royalty from both the agencies has been set at 45% on gross revenue from ground
handling services. Revenue shall mean and include all revenue, consideration, benefit and amount
earned and/or accrued at the Airport, whether invoiced or not.
1.5.4 The Authority vide Tariff Order No. 22/2023-24 dated November 14, 2023 determined the tariffs for
Indo Thai Airport Management Services Private Limited till March 31, 2027.
1.5.5 The Authority vide interim Tariff Order No. 41/2023-24 dated March 15, 2024 extended the prevailing
tariffs for AI Airport Services Limited (AIASL) till September 30, 2024.
1.6 Fuel Facility Operations
1.6.1 The Clause 19.3. of the Concession Agreement mentions the GIAL’s obligations towards providing
aircraft fueling services, which has been provided in Para 17.3.7 of Annexure 3 of Chapter 17.
1.6.2 At present, the fuel facilities are being managed by the Oil Marketing Companies (OMCs) such as,
IOCL, RIL, BPCL and HPCL. These OMCs have their own respective fuel tanks and refueling facilities
with capacities 800KL, 140KL, 800KL and 200KL respectively. OMCs manage the operations on their
own, and currently operating expenditure and other charges are embedded in Aviation Turbine Fuel
(ATF) fuel price. Therefore, as on date there is no concept of open access facility at the Airport.
1.6.3 GIAL has proposed to initially purchase the existing assets of IOCL and RIL having fuel storage
capacity of 940 KL, and subsequently convert it into Open Access facility by building a new facility
of approx. 4,000 KL with hydrant system.
Consultation Paper No. 01/2024-25 Page 19 of 254TARIFF DETERMINATION OF LGBIA GUWAHATI
2 TARIFF DETERMINATION OF LGBIA
2.1 Introduction
2.1.1 AERA was established by the Government of India vide notification No. GSR 317(E) dated May 12,
2009. The functions of AERA, in respect of Major Airports, are specified in section 13(1) of The
Airports Economic Regulatory Authority of India Act, 2008 (‘AERA Act’ or ‘the Act’) read with
AERA (Amendment) Act 2019 and 2021, which are as below:
a) To determine the tariff for Aeronautical services taking into consideration –
i. the capital expenditure incurred and timely investment in the improvement of airport facilities.
ii. the service provided, its quality and other relevant factors.
iii. the cost for improving efficiency.
iv. economic and viable operation of Major Airports.
v. revenue received from services other than the Aeronautical services.
vi. the concession offered by the Central Government in any agreement or memorandum of
understanding or otherwise; and
vii. any other factor which may be relevant for the purpose of the Act.
b) To determine the amount of the development fees in respect of Major Airports.
c) To determine the amount of the passengers’ service fee levied under Rule 88 of the Aircraft Rules,
1937 made under the Aircraft Act, 1934.
d) To monitor the set performance standards relating to quality, continuity and reliability of service as
may be specified by the Central Government or any authority authorized by it in this behalf.
e) To call for any such information as may be necessary to determine the tariff for Aeronautical
services; and
f) To perform such other functions relating to tariff, as may be entrusted to it by the Central Government
or as may be necessary to carry out the provisions of the Act, 2008.
2.1.2 As per the AERA Act, 2008, the following are the Aeronautical services for which tariff is determined
by the Authority:
i. Aeronautical services provided by the Airport Operators.
ii. Cargo Facility, Ground Handling and Fuel Supply Services; and
iii. Air Navigation Services.
2.1.3 AAI shall be handling the Air Navigation Systems (ANS) at LGBIA. Tariff for ANS is presently
regulated by the Ministry of Civil Aviation. All the assets, expenses and revenues pertaining to ANS
are considered separately by the Ministry while determining tariff for ANS services. Further, the tariff
for ANS services is determined at the Central level by the Ministry of Civil Aviation to ensure
uniformity across the Airports in the Country. Hence, AERA determines tariff for Aeronautical services
of the Airport Operator, by excluding the assets, expenses, and revenues from ANS.
Consultation Paper No. 01/2024-25 Page 20 of 254TARIFF DETERMINATION OF LGBIA GUWAHATI
2.2 Authority’s orders applied in tariff proposals in this Consultation Paper
2.2.1 Detailed Guidelines laying down information requirements, periodicity and procedure for Tariff
determination have been issued by the Authority. The details of Orders and Guidelines issued in this
regard are as under:
i. Order No. 13 dated 12.01.2011 (Regulatory philosophy and approach in Economic Regulation of
Airport Operators) and Direction No. 5 dated 28.02.2011 (Terms and conditions for determination
of tariff for Airport Operators); and
ii. Order No. 05 dated 02.08.2010 ((Regulatory philosophy and approach in Economic Regulation of
the services provided for Cargo facility, Ground Handling and Supply of Fuel to aircrafts); Order
No. 12 dated 10.01.2011 and Direction No. 4 dated 10.01.2011 (Terms and conditions for
determination of tariff for services provided for Cargo facility, Ground Handling and Supply of Fuel
to aircrafts).
iii. Order No. 07/2016-17 dated 13.06.2016 (Normative Approach to Building Blocks in Economic
Regulation of Major Airports).
iv. Order No. 14/2016-17 dated 12.01.2017 (Aligning certain aspects of AERA’s regulatory approach
with the provisions of the National Civil Aviation Policy – 2016).
v. Order No. 20/2016-17 dated 31.03.2017 (Allowing concession to RCS flights under Regional
Connectivity Scheme (RCS)).
vi. Order No. 35/2017-18 dated 12.01.2018 and Amendment No. 01 to Order No. 35/2017-18 dated
09.04.2018 (In the matter of determination of useful life of Airport assets).
vii. Order No. 42/2018-19 dated 05.03.2019 (Determination of FRoR to be provided on the cost of Land
incurred by various Airport Operators in India).
2.3 Background to tariff determination process of LGBIA
2.3.1 LGBIA is a Major Airport as per the definition of Major Airport under section 2(i) of the Airports
Economic Regulatory Authority of India Act, 2008 read with AERA Amendment Act, 2019 and AERA
Amendment Act, 2021.
2.3.2 With respect to the First Control Period of LGBIA commencing from FY 2011-12 to FY 2015-16, the
Authority had determined the Aeronautical tariff vide its Order No. 34/2013-14, dated November 18,
2013.
2.3.3 With respect to the Second Control Period of LGBIA commencing from FY 2016-17 to FY 2020-21,
the Authority had determined the Aeronautical tariff vide its Order No. 38/2017-18, dated February 16,
2018. Also, the Authority had issued Order No. 20/ 2020-21 dated July 1, 2020, with respect to
provision of compensation in lieu of discontinuation of Fuel throughput charges at LGBIA.
2.3.4 AAI and Guwahati International Airport Limited (GIAL) entered into a Concession agreement on
January 19, 2021 for exclusive right of Operation, Management and Development of LGBIA, for a
period of 50 (fifty) years from the Commercial Operations Date (COD). GIAL achieved Commercial
Operations Date (COD) on October 8, 2021.
2.3.5 GIAL has been provided an exclusive right to demand, collect and appropriate fees from COD onwards
at the rates determined by AERA. As an interim measure, GIAL applied to AERA vide letter with
reference no. AGIAL/CO/AERA-IT/2021/1 dated 27th August, 2021 to allow the existing tariff rates
at LGBIA from COD till March 31, 2022. Accordingly, AERA from time to time issued multiple orders
Consultation Paper No. 01/2024-25 Page 21 of 254TARIFF DETERMINATION OF LGBIA GUWAHATI
extending the existing tariff rates:
Table 3: Chronology of AERA orders with regard to extension of tariff at LGBIA
GIAL application letter and AERA Order and Date Rates Extended up to
Date
AGIAL/CO/AERA-IT/2021/1 22/2021-22 dated 6th October 2021 31st March 2022
dated 27th August, 2021
GIAL/CO/AERA-IT/2022/1 42/2021-22 dated 14th March 2022 30th September 2022
dated 23rd February 2022
GIAL/CO/AERA-IT/2022/3 22/2022-23 dated 20th September 2022 31st March 2023
dated 1st September 2022
GIAL/CO/AERA-IT/2023/1 41/2022-23 dated 22nd March 2023 30th September 2023
dated 2nd March 2023
GIAL/CO/AERA-IT/2023/4 19/2023-24 dated 20th September 2023 31st March 2024
dated 5th September 2023
GIAL/CO/AERA-IT/2024/1 40/2023-24 dated 15th March 2024 30th September 2024 or till
dated 28th February 2024 determination of regular
tariffs for the Control
Period, whichever is
earlier.
Control Period
2.3.6 It is to be noted that as per Order no. 38/2017-18 the second control period starts from 1st April 2016
and ends on 31st March 2021. AERA considering the transition phase had vide public notice no.
05/2022-23 dated 20th June 2022, decided to shift the third control period of LGBIA from 1st April
2021 – 31st March 2026 to 1st April 2022 – 31st March 2027.
2.4 Multi Year Tariff Proposal submission
2.4.1 As per the Concession Agreement between AAI and GIAL (clause 28.11.3), the Estimated Deemed
Initial RAB as on March 31, 2018, was ₹ 69 crores. Further, it is stated in the Concession Agreement
that the amount which was due and payable by the Concessionaire to AAI, is subject to reconciliation,
true up and final determination by AERA. The extract of the relevant clauses 28.11.3, 28.11.4 and
28.11.5 from the Concession Agreement have been provided in Para 17.3.8 of Annexure 3 under
Chapter 17.
2.4.2 In compliance with the above terms of the Concession Agreement, AAI and GIAL have submitted
MYTP to the Authority for the following period:
• Submission made by AAI for true up of the period from FY 2016-17 up to COD.
• Submission made by GIAL for true up of the period from COD up to March 31, 2022
• Submission made by GIAL for MYTP for the Third Control Period.
Tariff determination for Pre- COD and Post-COD period
i. Pre-COD period
2.4.3 AAI had submitted initial true up for the Pre-COD period from FY 2016-17 up to COD vide letter dated
July 6, 2023. The document is available on the AERA’s website. The Authority based on its preliminary
scrutiny of the true up figures submitted by AAI, observed various discrepancies and upon enquiry,
AAI provided information from time to time till April 2024. To ensure clarity and understanding, a
chronological timeline was established to represent the sequence of events leading up to the issue of
Consultation Paper No. 01/2024-25 Page 22 of 254TARIFF DETERMINATION OF LGBIA GUWAHATI
Consultation Paper. The timeline captures key milestones such as the submission of the proposal, the
preliminary scrutiny, the identification of discrepancies, the commencement of the inquiry, and the
subsequent provision of information by AAI which has been presented in the table below:
Table 4: Sequence of events regarding true up submissions by AAI
S. No. Event Date
1 Submission of original true up proposal of AAI July 6, 2023
Review of true-up submission and documentation provided by
2 July 2023 to September 2023
AAI
3 Additional information on CAPEX and OPEX October 2023
4 Additional information on O&M expenses December 2023
5 Additional information on Capital Expenditure December 2023
6 Additional information on Fixed Asset Register January 2024
7 Additional information on Fixed Asset Register February 2024
8 Additional information on left out assets February 2024
9 Clarification on R&M expenses April 2024
10 Additional information on Capital Expenditure April 2024
11 Additional clarification on space rentals from airlines April 2024
ii. Post COD period
2.4.4 The tariff determination for the post-COD period has been considered for GIAL under the following
categories:
• True up of the period from COD till March 31, 2022
• Tariff determination for the Third Control Period i.e. from April 1, 2022 to March 31, 2027.
2.4.5 GIAL submitted its MYTP for true up of Post COD period and determination of aeronautical tariff for
Third Control Period on July 28, 2023. The document is available on the AERA's website.
Table 5: Sequence of events regarding true up and MYTP submissions by GIAL
S. No. Events Date
1 Submission of MYTP by GIAL July 28 2023
2 Review of true-up submission and documentation provided by GIAL August – October
2023
3 Additional information on CAPEX and OPEX October 2023
4 Additional information on NITB December 2023
5 Additional information on Fixed Asset Register January 2024
6 Additional information on JARS March 2024
7 Clarification on Cargo and Fuel O&M expenses April 2024
8 Additional information on traffic April 2024
9 Additional information on NAR April 2024
10 Additional information on Utility expenses April 2024
11 Additional information on CAPEX, CWIP April 2024
2.4.6 As the LGBIA was taken over and operated by GIAL from the COD i.e. October 8, 2021, the
Authority has considered to true up the necessary building blocks of GIAL for the six month period
commencing from October 8, 2021 up to March 31, 2022.
2.4.7 The Authority has appointed an Independent Consultant, M/s Deloitte Touche Tohmatsu India LLP to
assess the MYTP submitted by GIAL for the Third Control period. Accordingly, M/s Deloitte Touche
Tohmatsu India LLP has assisted the Authority in examining true up submission of AAI and GIAL for
the pre and post COD period respectively, the MYTP of GIAL, including verifying the data from
various supporting documents such as audited financials, Fixed Asset Register (FAR) submitted by
Consultation Paper No. 01/2024-25 Page 23 of 254TARIFF DETERMINATION OF LGBIA GUWAHATI
GIAL, examining the building blocks in tariff determination, and ensuring that the treatment given to it
is consistent with the Authority’s methodology and approach.
2.4.8 The Authority vide its letter dated July 7, 2023 requested the Airport Operator to undertake a proper
due diligence in respect of CAPEX plan and other regulatory building blocks in the MYTP to be
submitted in the respect of LGBIA. Further, the Authority has, in this Consultation Paper, assessed the
Capital Expenditure based on site visit, available capacities, future traffic estimates, normative and the
need to ensure modular development of infrastructure at the Airport, with a view to ensure
determination of optimal Aeronautical charges to be levied on the airport users.
2.4.9 In carrying out the analysis of MYTP submitted by GIAL, the Authority, through it’s independent
consultant, has carried out review of all details, break up of cost items etc. provided by GIAL together
with considering the financials of FY 2022-23 and status of projects as of march 2024. Wherever details
have not been provided/ not completely provided, the Authority has carried out appropriate
rationalisation of such costs. The Authority also has, in its analysis, indicated certain activities where
the costs are proposed to be considered on incurrence basis. These have been elaborated in the relevant
paragraphs.
2.4.10 The Authority relies on the information available in the audited financial statements and Fixed Asset
Register (FAR) for its analysis. The Authority expects that the Airport Operator would ensure accuracy
of the information captured in its Books of Accounts and FAR and that there are no duplication of
expenses. It is the sole responsibility of the Airport Operator to maintain proper Books of Accounts and
FAR diligently and present accurate information in its submission.
2.4.11 The Authority notes that clause 5.7.1 of Direction 5/ 2010-11 pertaining to Terms and Conditions for
determination of Tariff for Airport Operators Guidelines, 2011 states that “ For any service provided
by the Airport Operator for (i) ground handling services relating to aircraft, passengers and cargo at
an airport; (ii) the cargo facility at an airport and (iii) supplying fuel to the aircraft at an airport, the
Authority shall follow the regulatory approach and process for tariff determination as mentioned in the
Direction No. 4/ 2010-11 on Terms and Conditions for determination of Tariff for services provided for
Cargo facility, Ground Handling and Supply of Fuel to the Aircraft Guidelines, 2011”.
Further, clause 1.2 of the Direction No.4/ 2010-11 states that “these Guidelines shall apply to Service
Provider(s) for (i) the Cargo facility at a Major Airport, (ii) ground handling relating to aircraft,
passengers and cargo at a major airport and for (iii) supplying fuel to the aircraft at a major airport:
Provided that Airport Operator providing the Regulated Service(s) as defined herein shall be excluded
from the application of these Guidelines.
Taking cognizance of the above provisions laid out under Direction 5/ 2010-11 and Direction 4/ 2010-
11 and the fact that the Airport Operator is providing the services on cargo facility and fuel supply to
the aircraft, the Authority has examined the Assets, Expenses and Revenues pertaining to Cargo and
Fuel farm of GIAL separately under the relevant chapters in this Consultation Paper, for the purpose of
determining Aggregate Revenue Requirement of GIAL.
Related Party Transactions
The Authority, through its Independent Consultant, got details regarding the tendering procedures
implemented by GIAL and has examined the associated contract agreements concerning operating
expenses and revenues entered into with related parties.
The Authority, on a sample review of contracts, notes that GIAL has involved certain Related Parties
as detailed hereunder:
Consultation Paper No. 01/2024-25 Page 24 of 254TARIFF DETERMINATION OF LGBIA GUWAHATI
Table 6: Services provided to GIAL by related parties
S. Description of
Nature of Services Name of Related Party
No. Relationship
Master Service Agreement to
1 Adani Airport Holdings Company holding 49%
operate and manage Non-
Limited shareholding in GIAL
Aeronautical Facilities
2 Adani Airport Holdings Company holding 49%
Corporate Support Service
Limited shareholding in GIAL
3
Corporate Support Service Adani Enterprises Limited Holding Company
4 Adani Airport Holdings Company holding 49%
Borrowing
Limited shareholding in GIAL
The Authority also notes the following from the Concession Agreement signed between GIAL and AAI:
“5.6.1 The Concessionaire agrees and undertakes that it shall procure contracts, goods and services for
the operations, management and development of the airport in a fair, transparent and efficient manner
and without any undue favour or discrimination in this behalf. In pursuance hereof, it shall, within six
(6) months from the COD, frame policy specifying the principles and procedures that it shall follow in
awarding for supply of goods and services, and shall place the policy on its website for the information
of general public and all interested parties, The policy shall:
(a) include the principles and procedures followed for sub-leasing, sub-licensing or grant or allocation
of any space, building, rights or privileges to private entities in the Airport
(b) be approved by the Board of Directors of the Concessionaire
5.6.2 For procurement of goods, works, services, sub-lease(s), sub-license(s) or any other rights or
previleges where the consideration (including deposits in any form or respect thereof) exceeds Rs.
25,00,00,000/- (Rupees Twenty Five Crore) in any accounting year (collectively, the contracts) the
Concessionaire shall invite offers through open competitive bidding by means of e-tendering and shall
select the awardees in accordance with the policy specified under clause 5.6.1
5.6.3 The Parties agree that the Concessionaire should pre-quality and short-list the applicants in a fair
and transparent manner for ensuring that only experienced and qualified applicants are finally selected
on arm’s length basis in a manner that is commercially prudent and protects interest of users.”
5.6.4 The Concessionaire hereby agrees not to have any subsidiary or joint venture or any other similar
form of arrangement with any other party.
AERA expects that GIAL and the AAI, (Concession granting Authority) will ensure that the contracts
with Related Parties are at arm’s length and that the Related Party has relevant experience of providing
similar service to ensure protection of interest of all stakeholders, as per the terms of the Concession
Agreement detailed above, which may be followed in letter and spirit.
2.5 Construct of this Consultation Paper
This Consultation paper has been developed in the order of the events as explained above. Chapter-
wise details have been summarized as follows:
i. The background of the Authority’s tariff determination process is explained in this Chapter and in
Chapter 3, the framework for determination of tariff is discussed.
Consultation Paper No. 01/2024-25 Page 25 of 254TARIFF DETERMINATION OF LGBIA GUWAHATI
ii. Chapter 4 lists out the submissions of AAI for true up of the Pre- COD period which is from FY
2016-17 to October 7, 2021. This is followed by the Authority’s examination and proposals on the
specific issues regarding the true up for the Period FY 2016-17 till COD. This chapter also
discusses the assessment and the outcome of the studies commissioned by the Authority regarding
asset allocation ratios between aeronautical and non-aeronautical assets and efficient cost
segregation between aeronautical and non-aeronautical operating expenses. The summary of these
reports is given under Annexures to this Consultation Paper and the reports have been appended
separately to the Consultation Paper.
iii. Chapter 5 lists out submission of GIAL for true up of the period from October 8, 2021 (COD) up
to March 31, 2022. This is followed by the Authority’s examination and proposals on the specific
issues regarding the true up for the said post-COD period. This chapter also discusses the
assessment and the outcome of the studies conducted by the Authority regarding asset allocation
ratios between aeronautical and non-aeronautical assets and efficient cost segregation between
aeronautical and non-aeronautical operating expenses. The summary of these reports is given
under Annexures to this Consultation Paper and the reports have been appended separately to the
Consultation Paper.
iv. Chapter 6 presents the submissions of GIAL regarding Traffic Projections and the Authority’s
proposals on the same.
v. Chapter 7 includes the submissions of GIAL regarding Capital Expenditure (CAPEX),
Depreciation and RAB for the Third Control Period along with the Authority’s detailed
examination, adjustments, rationalisation and proposals on the Aeronautical capital expenditure,
depreciation, and RAB for the Third Control Period.
vi. Chapter 8-13 includes the submissions of GIAL regarding various building blocks pertaining to
the Third Control Period including Fair Rate of Return, Inflation, Operating Expenses, Non-
aeronautical Revenue, Taxation and Quality of Service along with Authority's examination and
proposals on each matter.
vii. Chapter 14 presents the Aggregate Revenue Requirement as determined by the Authority based
on the proposals for the Third Control Period.
viii. Chapter 15 summarizes the Authority’s proposals put forward for consultation.
ix. In Chapter 16 the Authority invites views of all the stakeholders regarding proposals put forward
for tariff determination for the Third Control Period in the Consultation Paper.
x. Chapter 17 contains Annexures:
• Annexure 1 – Summary of study on allocation of assets between Aeronautical and Non-
aeronautical assets
• Annexure 2 – Summary of study on efficient Operation and Maintenance expenses
• Annexure 3 – Clauses of the Concession Agreement entered between AAI and GIAL
xi. Chapter 18 contains the list of Appendices.
2.6 Studies commissioned by the Authority
2.6.1 The Authority commissioned the following studies through its Independent Consultant for the purpose
of tariff determination and the resultant recommendations have been used in this Consultation paper:
a) Study on allocation of Assets between Aeronautical and Non-Aeronautical Assets: The Study
Consultation Paper No. 01/2024-25 Page 26 of 254TARIFF DETERMINATION OF LGBIA GUWAHATI
has carried out a detailed analysis of the Regulatory Asset Base (RAB) of both AAI and GIAL.
The study has developed a rationale for classification of assets into Aeronautical, Non-
aeronautical, Air Navigation Services (ANS) and Common. It then apportioned the Common
assets based on appropriate ratios. Further, the Study has also examined the assets transferred
from AAI to GIAL (as on COD) and determined the Deemed Initial RAB as on COD.
b) Study on efficient Operation and Maintenance Expenses: The Study examined the historical
trends in the O&M expenses of LGBIA and assessed how the Airport has been performing in
comparison to the select peers in the industry. The Study verified the classification of the various
expenses between Aeronautical, Non-aeronautical, ANS and Common and made revisions
wherever necessary. The Common expenses were further apportioned based on appropriate ratios.
Further, the Study ascertained the expenses that were unreasonably high and rationalized them
based on suitable benchmarks.
2.6.2 The recommendations of these studies have been used in this Consultation Paper. The summary of the
Study on Allocation of Assets is given in Annexure 1 of this Consultation Paper and the study is attached
as Appendix 1 of this Consultation Paper. The summary of the Study on Efficient Operation and
Maintenance Expenses is given in Annexure 2 of this Consultation Paper and the study is attached as
Appendix 2 of this Consultation Paper.
Consultation Paper No. 01/2024-25 Page 27 of 254FRAMEWORK FOR TARIFF DETERMINATION FOR THE THIRD CONTROL PERIOD FOR LGBIA
3 FRAMEWORK FOR TARIFF DETERMINATION OF LGBIA FOR THE THIRD CONTROL
PERIOD
3.1 Methodology
3.1.1 The Methodology adopted by the Authority to determine Aggregate Revenue Requirement (ARR) is
based on AERA Act, 2008 read with AERA (Amendment) Act, 2019 and AERA Amendment Act,
2021, the AERA (Terms and Conditions for determination of Tariff for Airport Operators) Guidelines,
2011 and further Guidelines issued by AERA from time to time.
3.1.2 As per the guidelines, the Authority has adopted the Hybrid-Till mechanism for tariff determination for
the Third Control Period wherein, 30% of the Non-aeronautical revenues is to be used for cross-
subsidizing the Aeronautical charges. The Authority has considered the same methodology in the
analysis of true up submission for Second Control Period, pre-COD and post-COD Period.
3.1.3 The ARR under hybrid till for the Control Period (ARR) shall be expressed as under:
ARR = (FRoR x RAB) + D + O + T - s x NAR
t t t t t t
Where,
t is the tariff year in the control period, ranging from 1 to 5
ARR is the Aggregate Revenue Requirement for tariff year ‘t’
t
FRoR is the Fair Rate of Return for the Control Period
RAB is the Aeronautical Regulatory Asset Base for tariff year ‘t’
t
D is the Depreciation corresponding to the Regulatory Asset Base for tariff year ‘t’
t
O is the Aeronautical Operation and Maintenance expenditure for the tariff year ‘t’
t
T is the Aeronautical taxation expense for the tariff year ‘t’
t
s is the cross-subsidy factor for revenue from services other than Aeronautical services. Under the
Hybrid Till methodology followed by the Authority, s = 30%.
NAR is the Non-aeronautical revenue in tariff year ‘t’.
t
3.1.4 Based on ARR, Yield per passenger (Y) is calculated as per the formula given below:
∑5 𝑃𝑉(𝐴𝑅𝑅 )
𝑡=1 𝑡
𝑌𝑖𝑒𝑙𝑑 𝑝𝑒𝑟 𝑝𝑎𝑠𝑠𝑒𝑛𝑔𝑒𝑟(𝑌) =
∑5 𝑉𝐸
𝑡=1 𝑡
Where, PV (ARR) is the Present Value of ARR for all the tariff years. All cash flows are assumed
t
to occur at the end of the year. The Authority has considered discounting cash flows, one year from
the start of the Control Period.
VE is the passenger traffic in year ‘t’.
t
3.1.5 All the figures presented in this Consultation Paper have been rounded off up to two decimals.
3.1.6 As per the provisions of Section 13(2) of the AERA Act 2008, the tariff so determined under the Tariff
Order can be reviewed and revised.
3.2 Revenues from Air Navigation Services (ANS)
3.2.1 GIAL shall be performing Aeronautical services like landing, parking, ground handling, cargo and fuel
supply to aircraft services at LGBIA and has submitted revenue projections for the Third Control Period
Consultation Paper No. 01/2024-25 Page 28 of 254FRAMEWORK FOR TARIFF DETERMINATION FOR THE THIRD CONTROL PERIOD FOR LGBIA
in its MYTP. However, AAI shall be handling the Air Navigation Systems (ANS) at LGBIA and hence
the MYTP submitted by GIAL does not consider revenues, expenditure, and assets on account of ANS.
3.2.2 Tariff for ANS is presently regulated by the Ministry of Civil Aviation. All the assets, expenses and
revenues pertaining to ANS are considered separately by the Ministry while determining tariff for ANS
services. Further, the tariff for ANS services is determined at the Central level by the Ministry of Civil
Aviation to ensure uniformity across the Airports in the Country. Hence, AERA determines tariff for
Aeronautical services of the Airport Operator, by excluding the assets, expenses and revenues from
ANS.
Consultation Paper No. 01/2024-25 Page 29 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
4 TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD AND PRE-COD PERIOD
4.1 Background
4.1.1 AAI had entered into a Concession Agreement dated January 19, 2021, with Guwahati International
Airport Limited (the ‘Concessionaire’) for the operations, management, and development of LGBIA
for a period of 50 years from the COD, i.e., October 8, 2021.
4.1.2 As per the Concession Agreement between AAI and GIAL (clause 28.11.3), the amount which was due
and payable by the Concessionaire to AAI, is subject to reconciliation, true up and final determination
by AERA.
4.1.3 Pursuant to the above Concession Agreement, AAI has submitted True up workings for the period April
1, 2016 up to October 7, 2021
4.1.4 The true up workings submitted by AAI covers the following building blocks:
i. Traffic
ii. Capital Expenditure
iii. Aeronautical Depreciation
iv. Regulatory Asset Base
v. Fair Rate of Return
vi. Aeronautical Operation and Maintenance Expenses
vii. Non-aeronautical Revenue
viii. Aeronautical Taxes
ix. Aggregate Revenue Requirement
4.1.5 The Authority has analyzed the AAI’s true up submission in detail. The analysis by the Authority, has
been organized as follows:
i. Recorded AAI’s submissions for true up under different Regulatory building blocks.
ii. Recapped the decisions taken by the Authority in the Tariff Order for the Second Control Period
(Order No. 38/ 2017-18 dated February 16, 2018)
iii. Provided Authority’s examination through its Independent Consultant on each regulatory
building block and put forth its proposals.
iv. Authority also examined Pre COD period (1st April’2021 to 7th Oct’2021) and considered
amount against each regulatory building block in true up exercise.
4.1.6 The Authority has considered the following documents for determining true up for the Second Control
Period and Pre-COD Period:
i. Tariff Order for LGBIA (Order No. 38/ 2017-18) dated February 16, 2018.
ii. Trial balance figures of AAI for the Second Control Period and Pre-COD Period.
iii. AERA Guidelines and Orders.
iv. Authority’s decisions on the Regulatory Building Blocks as per previously issued Tariff Orders
of other airports.
4.2 AAI’s submission regarding True up for SCP and period from 1st Apr’21 to 7th Oct’21
4.2.1 As mentioned in Para No. 2.4.3 of this Consultation Paper, AAI has submitted its True Up submission
dated 6th July 2023. The details of the same have been provided below:
Consultation Paper No. 01/2024-25 Page 30 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Table 7: Submission of True up by AAI for the SCP and Pre-COD period
(₹ crores)
Total FY’22 Total
FY
Particulars FY’ 17 FY’18 FY’19 FY’20 till up to till
’21
FY’21 COD COD
Opening RAB 84.00 78.85 80.44 154.28 172.29 163.26
Closing RAB 78.85 80.44 154.28 172.29 163.26 166.21
Average RAB 81.43 79.65 117.36 163.29 167.78 609.49 164.74 774.22
Fair Rate of Return 14% 14% 14% 14% 14% 14%
(FRoR)
Return on Average RAB 11.40 11.15 16.43 22.86 23.49 85.32 12.01 97.33
Depreciation 7.00 7.17 9.93 13.32 13.84 51.27 7.31 58.58
Operating Expenditure 43.50 80.96 94.70 113.17 93.98 426.31 73.89 500.19
Opening RAB - Financing - 0.002 0.02 1.11 2.10 2.75
Allowance
Additions - Financing 0.002 0.02 1.10 1.06 0.75 2.94 0.10 3.04
Allowance
Depreciation - Financing 0.00 0.001 0.01 0.07 0.10 0.19 0.07 0.26
Allowance
Closing RAB - Financing 0.002 0.02 1.11 2.10 2.75 2.78
Allowance
Average RAB - Financing 0.001 0.01 0.56 1.60 2.42 4.61 2.76 7.37
Allowance
Return on Average RAB - 0.0001 0.002 0.08 0.22 0.34 0.65 0.20 0.85
Financing Allowance
Interest on Working - - - - - - 0.51 0.51
Capital
Corporate Tax 15.66 10.16 17.99 6.44 - 50.24 - 50.24
Corporate Tax on shortfall 26.95 26.95
(under recovery) to be
collected from
Concessionaire
Shortfall in 1st Control 107.70 - - - - 107.70 - 107.70
Period as on 01.04.2016
Less: Deductions for Non- 8.23 4.69 9.70 15.09 7.26 44.97 3.09 48.06
aeronautical Revenues
Total Gross ARR 177.02 104.76 129.43 140.99 124.50 676.71 117.83 794.54
Revenue earned from 97.05 118.91 158.14 156.04 73.65 603.79 41.73 645.52
Aeronautical Services
(Excess) / Shortfall 79.97 (14.15) (28.70) (15.05) 50.85 72.92 76.11 149.02
PV Factor 1.81 1.59 1.39 1.22 1.07 1.00
PV of (Excess) / Shortfall 144.60 (22.44) (39.94) (18.36) 54.44 118.29 76.11 194.40
on COD*
*COD 8th October 2021
4.3 Authority’s examination of True up submitted by AAI for Second Control Period and pre-COD
period
The Authority has taken cognizance of the decisions taken at the time of determination of tariff for
the Second Control Period and has then proceeded to examine the same as part of the tariff
determination for the current Control Period.
The decisions taken at the time of determination of tariff for Aeronautical services for the Second
Control Period vide Order No. 38/2017-18 dated February 16, 2018, have been reproduced below:
Consultation Paper No. 01/2024-25 Page 31 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
• Decision No.1 – True Up for the 1st Control Period
1.a. The Authority decides to true-up the 1st Control Period on the basis of Single Till
1.b. The Authority decides to adopt CHQ/ RHQ overheads apportionment on revenue basis.
1.c. The Authority decides to consider the revenues from Cargo facility, Ground Handling
services and Supply of fuel to aircraft including land lease rentals as aeronautical revenue.
1.d. The Authority decides the following depreciation rates.
i. For asset types not defined under Companies Act (runway, taxiway and aprons): 3.33%
based on useful life of 30 years from FY 2011-12 onwards.
ii. For asset types defined under Companies Act: rates prevalent under the Companies Act
1956 till FY 2013-14 and as per the Companies Act 2013 from FY 2014-15 onwards as
the effective date of implementation of the Companies Act 2013 is 01.04.2014. The
depreciation rates as submitted by AAI and as considered by the Authority are given in
Table 30.
1.e. The Authority decides to consider short fall of ₹ 107.7 crores in the 1st control period to be
added to ARR for the 2nd Control Period.
• Decision No. 2 – Traffic Forecast
2.a. The Authority decides to consider the ATM and passenger traffic as per Table 20.
2.b. The Authority decides to true up the traffic volume (ATM and passengers) based on actual
traffic in 2nd Control period while determining tariffs for the 3rd control period.
• Decision No. 3 – Allocation of assets between Aeronautical and Non-Aeronautical
services
3.a. The Authority decides to allocate assets as on 1st April 2016 between aeronautical and non-
aeronautical assets as detailed in Table 24.
• Decision No. 4 – Opening Regulatory Asset Base for the 2nd control period
4.a. The Authority decides to consider the opening regulatory base for the 2nd control period under
Hybrid Till as ₹ 65.5 crores.
• Decision No. 5 – Capital Expenditure
5.a. The Authority decides to consider allowable project cost of ₹ 261.9 crores and accordingly
reckon the amount of ₹ 261.9 crores as additions to total assets during the 2nd control period.
5.b. The Authority directs AAI to undertake user stakeholder consultation process for major
capital expenditure items as per the Guidelines.
5.c. The Authority decides to true up the Opening RAB of the next control period depending on
the capital expenditure incurred and date of capitalization of underlying assets in a given
year.
• Decision No. 6 – Treatment of Depreciation
6.a. The Authority decides to adopt depreciation rates as per Table 30 and depreciation for the
2nd control period as per Table 31.
Consultation Paper No. 01/2024-25 Page 32 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
6.b. The Authority decides to consider the deprecation rates as per the order No. 35/2017 18 dated
12.01.2018 issued by the Authority, at the time of determination of tariff for the 3rd control
period. It shall make necessary adjustments in RAB accordingly.
• Decision No. 7 – RAB for 2nd control period
7.a. The Authority decides to consider RAB for 2nd control period as given in Table 33.
7.b. The Authority decides to true up the RAB of 2nd control period based on actual asset addition
and consider the depreciation rates as per the order no. 35/2017-18 dated 12.01.2018 issued
by the Authority, at the time of determination of tariff for the 3rd control period.
Decision No. 8 – FRoR
8.a. The Authority decides to consider the FRoR at 14% for LGBIA for the 1st and 2nd control
period.
8.b. The Authority decides to undertake a study to determine FRoR for major AAI airports given
the low debt structure of AAI as a whole.
• Decision No. 9 – Non-Aeronautical Revenues
9.a. The Authority decides to consider the revenues accruing to AAI on account of the
aeronautical services of Cargo facility, Ground Handling Services and Supply of fuel to
aircraft (FTC) including land lease rentals and building rent from these activities as
aeronautical revenue.
9.b. The Authority decides to consider the Non-Aeronautical revenue as per Table 37.
9.c. The Authority decides that Non-Aeronautical revenues will be trued up if it is higher than the
projected revenues. In case there is a shortfall, true up would be undertaken only if the
Authority is satisfied that there are reasonably sufficient grounds for not realizing the
projected revenues.
• Decision No. 10 – Operation and Maintenance Expenditure
10.a. The Authority decides to consider the operational and maintenance expenditure as given in
Table 44 above, for the purpose of determination of aeronautical tariffs for the 2nd control
period.
10.b. The Authority expects AAI to reduce O&M expenditure over a period of time.
10.c. The Authority decides to true up the O&M expenditure for 2016-17 to 2020-21 of the 2nd
control period based on the actuals at the time of determination of tariffs for the 3rd control
period.
10.d. The Authority decides the following factors for corrections while determining tariffs for the
next control period:
(i) Mandated cost incurred due to directions issued by regulatory agencies like DGCA;
(ii) Cost of actual operating expenses including electricity;
(iii) All statutory levies in the nature of fees, levies, taxes, and other such charges by Central
or State Government or local bodies, local taxes, levies directly imposed on and paid
by AAI on final product/service provided by AAI will be reviewed by the Authority for
the purpose of corrections. Any additional expenditure by way of interest payments,
penalties, fines, and such penal levies associated with such statutory levies which AAI
has to pay, for either any delay or non-compliance, the same may not be trued up.
Consultation Paper No. 01/2024-25 Page 33 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
• Decision No. 11 – Taxation
11.a. The Authority decides the corporate tax for aeronautical activities as per Table 45 for the 2nd
control period.
11.b. The Authority decides to true up the difference between the actual/ apportioned corporate tax
paid and that estimated by the Authority for the 2nd control period during determination of
tariffs for the 3rd control period.
• Decision No. 12 – Tariff rate card
12.a. The Authority decides to accept Annual Tariff Proposal as given in Table 49 (and Annexure)
for the 2nd control period as the present value of proposed revenues (yield) by AAI is lower
than the present value of ARR (yield) as per Authority. The Authority decides to accept the
increase in tariffs for subsequent years of the second control period as below:
i. Yearly increase of 4% per annum every subsequent year (FY 2018-19 onwards) in UDF
per departing passenger
ii. Yearly increase of 4% every subsequent year (FY 2018-19 onwards) on landing
charges
iii. Yearly increase of 5% per annum every subsequent year (FY 2018-19 onwards) in fuel
throughput charges
12.b. The Authority decides to continue with waiver of landing charges for (a) aircraft with a
maximum certified capacity of less than 80 seats, being operated by domestic scheduled
operators (b) Helicopters of all types as approved by Govt. of India vide order no.
G.17018/7/2001- AAI dated 9th Feb 2004 in order to encourage and promote intra-regional
connectivity at LGBIA.
12.c. The Authority decides to provide waiver of landing and other charges in line with the Order
No. 20/2016-17 dated 31.03.2017 of the Authority.
12.d. The Authority decides to merge UDF and PSF (facilitation) charges and only UDF charges
to be applicable on each domestic and international embarking passenger w.e.f. 01.03.2018.
12.e. The Authority decides to consider shortfall/ excess in revenues for the 2nd control period
based on proposed tariffs by AAI while determining aeronautical tariffs for the 3rd control
period.
4.4 True up of Traffic
4.4.1 The actual passenger and ATM traffic of LGBIA for the Second Control Period submitted by AAI is as
follows:
Table 8: AAI’s submission for True up of traffic for the Second Control Period for LGBIA
(in Nos.)
Total
Domestic International Domestic International Total
Financial Year Passenger
Passengers Passengers ATM ATM ATM
traffic
FY’17 3,759,494 30,162 3,789,656 37,383 490 37,873
FY’18 4,636,604 31,449 4,668,053 40,668 504 41,172
FY’19 5,714,561 31,067 5,745,628 49,845 643 50,488
FY’20 5,422,289 35,160 5,457,449 44,539 1,000 45,539
FY’21 2,188,767 368 2,189,135 23,422 20 23,442
Consultation Paper No. 01/2024-25 Page 34 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Total
Domestic International Domestic International Total
Financial Year Passenger
Passengers Passengers ATM ATM ATM
traffic
Total 21,721,715 128,206 21,849,921 195,857 2,657 198,514
FY’22 (till COD) 1,163,923 16 1,163,939 14,388 5 14,393
Total (till COD) 22,885,638 128,222 23,013,860 210,245 2,662 212,907
4.4.2 The Authority verified the actual Passenger traffic and ATM (as per Table 8) for the Second Control
Period based on the details available on AAI’s website and noted no variances.
4.4.3 The Authority examined the actual passenger traffic and ATM of LGBIA with the traffic projections
approved by the Authority in the Tariff Order No. 38/2017-18 dated 16 February 2018, for the Second
Control Period, which is as follows:
Table 9: Passenger traffic and ATM approved by the Authority for the Second Control Period
(in Nos.)
Total
Domestic International Domestic International
Financial Year Passenger Total ATM
Passengers Passengers ATM ATM
traffic
FY’17 3,759,494 30,162 3,789,656 37,383 490 37,873
FY’18 4,622,417 30,775 4,653,192 41,688 502 42,190
FY’19 5,084,659 33,852 5,118,511 44,641 548 45,189
FY’20 5,593,125 37,237 5,630,362 47,803 597 48,400
FY’21 6,152,437 40,961 6,193,398 51,189 651 51,840
Total 25,212,132 172,987 25,385,119 222,704 2,788 225,492
4.4.4 The Authority notes from the above table that the actual Passenger and ATM traffic for the first three
tariff years of the Second Control Period (as per Table 8) is same or near to what was approved by the
Authority in the Tariff Order for the Second Control Period.
4.4.5 The Authority notes that there has been a decrease in the Passenger and ATM traffic particularly in the
FY 2019-20 (pre-COVID year), due to the closure of operations by Jet Airways with no replacement
for those vacant slots and the impact of COVID pandemic in the last quarter of the FY 2019-20.
4.4.6 The actual traffic for the 5th tariff year viz., FY 2020-21 is significantly lower than the projections in
Tariff order for the Second Control Period, due to the adverse impact of the ongoing COVID-19
pandemic.
4.4.7 Based on the above facts, the Authority proposes to consider the actual passenger and ATM traffic as
submitted by AAI (Table 8) for true up of the Second Control Period (up to COD), in line with its
decision no. 2.b. of the Tariff Order No. 38/ 2017-18 dated February 16, 2018, which states “The
Authority decides to true up the traffic volume (ATM and passengers) based on actual traffic in 2nd
Control period while determining tariffs for the 3rd control period.”
Consultation Paper No. 01/2024-25 Page 35 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
4.5 True up of Capital Expenditure (CAPEX)
AAI’s submission for true up of RAB for the Second Control Period and Pre-COD Period:
4.5.1 AAI has submitted the details of RAB during the Second Control Period and Pre-COD period as follows:
Table 10: RAB for Second Control Period and pre COD period as per AAI’s Submission
(₹ crores)
FY’22
Particulars FY’17 FY’18 FY’19 FY’20 FY’21 till Total
COD
Opening RAB (A) 84.00* 78.85 80.44 154.28 172.29 163.26
Additions to RAB during the year (B) 9.77# 8.84 83.77 31.33 4.82 10.26 148.79
Deletions from RAB during the year (C) 7.92 0.08 8.00
Depreciation for the year (D) 7.00 7.17 9.93 13.32 13.84 7.31 58.57
Closing RAB for the year (E=A+B-C-D) 78.85 80.44 154.28 172.29 163.27 166.21
* includes left out assets worth ₹ 16.59 crores and cost apportionment worth 1.90 crores in First Control Period
# excludes left out asset and cost apportionment as the same has been included in Opening RAB
4.5.2 AAI has classified the above capital additions into Aeronautical, Non-aeronautical, Common and ANS
as shown below:
Table 11: Allocation of assets as per AAI’s submission
Asset
Asset Category Asset Sub-Category / Description
Classification
Boundary Boundary in CPWD Quarters Aeronautical
Operational boundary walls Aeronautical
Building Expansion and modification of existing Term. Bldg. Aeronautical
(Misc. works)
Construction of E&M Workshop Aeronautical
Tensile Fabric Canopy for Terminal building Aeronautical
Civil and Electrical works for Air link corridors Aeronautical
Construction of Dog kennel and associated works at CISF Aeronautical
complex
Construction of Fire pit and approach road Aeronautical
Supply and installation of public toilet Aeronautical
Frangible security w/towers Aeronautical
Portable shelters Aeronautical
SITC of Smoke Cabin indoor type Aeronautical
Construction of Child Care room and facelift works Aeronautical
Construction of LLZ/ILS Hut ANS
Surface Movement Radar Tower and ASMGCS room ANS
Furniture & Fixtures 3-seater Airport Terminal chairs Aeronautical
Furniture & Fixtures at administrative offices Aeronautical
Iron beds Aeronautical
Ladies Frisking booth Aeronautical
Standing Platform Aeronautical
Immigration Counters Aeronautical
Rifle racks Aeronautical
Furniture and Fixtures for ANS use ANS
Office appliances IT assets and other office equipment at the airport, BCAS Aeronautical
and CISF offices
IT assets and other office equipment at ANS offices ANS
Consultation Paper No. 01/2024-25 Page 36 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Asset
Asset Category Asset Sub-Category / Description
Classification
Plant & Equipment FIDS, CUTE, CUSS Aeronautical
CCTV and Access Control System Aeronautical
Perimeter Lighting System Aeronautical
Escalators and Elevators Aeronautical
Passenger boarding bridges and AVDGS Aeronautical
Rubber Removal Machine Aeronautical
Bomb Suits Aeronautical
Hand-Held Metal Detectors and DFMDs Aeronautical
Explosive vapour Detector Aeronautical
Passenger Baggage Trolleys Aeronautical
Signages Aeronautical
Equipment at CISF Barracks Aeronautical
X-ray Baggage Inspection System Aeronautical
SITC of video conferencing system Aeronautical
Mini Remote Operating Vehicle Aeronautical
SITC for E-Gates for Immigration Aeronautical
Human Life Detector Aeronautical
SITC of SCCTV system Aeronautical
SITC of drinking water fountains Aeronautical
Public Address Sound Management System Aeronautical
Aadhar based Biometric Machines Aeronautical
SITC of Biometric Access Control System Aeronautical
Firefighting and protection equipment Aeronautical
Air Conditioning at terminal building Aeronautical
SITC of sub-station equipment and associated work Common
SITC of ground mounted solar plant Common
Equipment related to ANS/CNS facilities ANS
Runways, Taxiways Strengthening of Existing Runway 02/20 Aeronautical
and Apron Construction and strengthening of internal and access Aeronautical
roads
Car park in front of Cargo and RHQ building Non-Aero
Vehicles Fire trucks, ambulances, tractors, SUVs, and other Aeronautical
vehicles for airside operations
Vehicles for ANS operations ANS
Computer Software Software for airport operations Aeronautical
Software licences Common
4.5.3 Further, AAI has submitted the following ratios:
Table 12: Allocation ratios as per AAI’s submission
Particulars FY 2016- FY 2017- FY 2018-19 FY 2019-20 FY 2020-21 FY 2021-22
17 18 till COD
Employee Ratio 98.65:1.35 98.08:1.92 98.84:1.16 98.10:1.90 98.03:1.97 98.60:1.40
(Aeronautical : Non-
aeronautical)
Terminal Building ratio 89.67:10.33 90.50:9.50 90.60:9.40 92.32:7.68 92.81:7.19 92.58:7.42
(Aeronautical : Non-
aeronautical)
Consultation Paper No. 01/2024-25 Page 37 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Particulars FY 2016- FY 2017- FY 2018-19 FY 2019-20 FY 2020-21 FY 2021-22
17 18 till COD
Electricity ratio 84.79: 84.76: 84.74: 84.77: 84.75: 84.52:
(Aeronautical : ANS : 15.00: 15.05: 15.08: 15.08: 15.05: 15.19:
Non-aeronautical) 0.21 0.19 0.18 0.16 0.20 0.29
Staff Quarters ratio 49.11:50.89 52.94:46.08 60.83:38.33 65.81:33.33 64.85:35.42 59.21:40.79
(Aeronautical : ANS)
Vehicle Ratio 74.07: 75.86: 77.14: 82.61: 83.33: 80.00:
(Aeronautical : ANS : 18.52: 17.24: 17.14: 13.04: 12.50: 15.00:
Non-aeronautical) 7.41 6.90 5.71 4.35 4.17 5.00
Recap of decision taken by the Authority for RAB at the time of tariff determination for the Second
Control Period
4.5.4 The Authority vide its decision no. 4, 5 and 7 of Order no. 38/2017-2018 dated February 16, 2018
decided the following with respect to Opening Aeronautical RAB, Additions and RAB for Second
Control Period:
• Decision no. 4.a. The Authority decides to consider the opening regulatory base for the 2nd control
period under Hybrid Till as ₹ 65.5 crores.
• Decision no. 5.a. The Authority decides to consider allowable project cost of ₹ 261.9 crores and
accordingly reckon the amount of ₹ 261.9 crores as additions to total assets during the 2nd control
period.
• Decision no. 5.b. The Authority directs AAI to undertake user stakeholder consultation process for
major capital expenditure items as per the Guidelines.
• Decision no. 5.c. The Authority decides to true up the Opening RAB of the next control period
depending on the capital expenditure incurred and date of capitalization of underlying assets in a
given year.
• Decision no. 7.a. The Authority decides to consider RAB for 2nd control period as given in Table 33.
• Decision no. 7.b. The Authority decides to true up the RAB of 2nd control period based on actual
asset addition and consider the depreciation rates as per the order no. 35/2017-18 dated 12.01.2018
issued by the Authority, at the time of determination of tariff for the 3rd control period.
Table 13: RAB as approved by Authority in the Tariff Order for Second Control Period (Table
33 of the Order)
(₹ crores)
Particulars FY 17 FY 18 FY 19 FY 20 FY 21 Total
Opening RAB (A) 65.50 66.30 71.20 102.00 269.70
Addition (B) 6.90 11.20 37.80 178.00 28.00 261.90
Sales/Disposals/Transfers (C) - - - - - -
Depreciation (D) 6.10 6.30 7.00 10.30 13.30 43.00
Closing RAB (E = A + B – C – D) 66.30 71.20 102.00 269.70 284.40
Average RAB [(A + E) ÷ 2] 65.90 68.80 86.60 185.90 277.10
Authority’s examination regarding CAPEX, Depreciation and RAB as part of tariff determination
for the Second Control Period and Pre-COD Period:
4.5.5 The Authority had undertaken the “Study on Allocation of Assets between Aeronautical and Non-
Aeronautical Assets” to carry out a detailed analysis of the Regulatory Assets, apportion the common
assets based on appropriate ratios, and examine the assets transferred from AAI to GIAL.
Consultation Paper No. 01/2024-25 Page 38 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
4.5.6 Allocation Ratios
a. Terminal Building ratio: It was observed that as per AAI’s True up submission for the period up to
October 8, 2021, LGBIA had an average terminal building ratio of 91.41:8.59 based on actual
utilization. The Authority in its order 38/2017-18 for SCP of LGBIA, had decided to adopt 89.02% as
aeronautical area based on terminal area ratio calculations submitted by AAI for FY 2015-16.
This is also consistent with the IMG norms, which has recommended the Non-Aeronautical area within
the terminal building for airports having passenger traffic less than 10 MPPA to be in the range of 8%
to 12% of the total terminal area and for airports having passenger traffic greater than 10 MPPA to be
up to 20%.
The Authority had commissioned an independent study on the Allocation of Assets (summary of the
study is given in Annexure 1 and the study is attached as Appendix 1 of this Consultation Paper). Based
the outcome of the study, the Authority proposes to consider the Terminal Building ratio of 89.02:10.98
(Aeronautical: Non-Aeronautical) as was approved by the Authority in the Tariff Order for the Second
Control Period. The same has been explained in para 4.3.1 of the Asset Allocation study report.
b. Staff Quarters ratio: The Authoirty proposes to consider staff quarters ratio as submitted by AAI.
c. Employee Headcount ratio: The Authority proposes to consider the five-year average Employee
Head Count Ratio of AAI, i.e. 90.45:9.55 (Aeronautical: Non-aeronautical) for the purpose of
allocation of assets during the period from FY 2016-17 up to COD, as the Authority considers the
same to be a reasonable basis for allocation of assets. The same has been explained in para 4.4.3 of
the O&M Study report and the same is presented in the table below:
Table 14: Allocation Ratios proposed by the Authority
FY22 till Average
Particulars FY 17 FY 18 FY 19 FY 20 FY 21
COD Ratio
Employee Ratio 90.35:9. 89.53:10.4 91.56: 90.59: 90.59: 90.10: 9.90 90.45:9.
(Aero : Non-Aero) 65 7 8.44 9.41 9.41 55
Terminal Building
Ratio 89.02% : 10.98%
(Aero : Non-Aero)
Staff Quarters 49.11: 52.94: 60.83: 65.81: 64.58: 59.21:
Ratio 50.89: 46.08: 38.33: 33.33: 35.42: 40.79:
(Aeronautical :
0 0.98 0.83 0.85 0 0
ANS: Non
Aeronautical)
4.5.7 The Authority notes the following while comparing the RAB as submitted by AAI for true up (Table
10) and that approved in Second Control Period tariff order (Table 13):
• There is a difference between Opening RAB as on 1st April 2016 as submitted by AAI and that
approved by AERA in the Second Control Period Order. This variation has been discussed in para
4.5.9.
• The capital expenditure incurred by AAI vis a vis approved by the Authority for the Second
Control Period is lower by ₹ 123.37 crores. Additionally, AAI has incurred ₹ 10.26 crores
during FY’22 till COD i.e. 8th October, 2021. The same has been discussed in para 4.5.14.
4.5.8 The Authority notes that at the time of determination of tariff for the Second Control Period, in the
Tariff Order, the Opening RAB for FY 2016-17 was determined to be ₹ 65.50 crores (Decision No. 4a,
Tariff Order No. 38/2017-18 dated February 16, 2018). The details are as follows:
Consultation Paper No. 01/2024-25 Page 39 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Table 15: Opening RAB approved by the Authority in the Second Control Period Tariff Order
(₹ crores)
Particulars Ref. Amount
Original Cost of Aeronautical Assets excluding CNS/ATM related A 162.0
assets as on 01.04.2011
Aeronautical asset addition during the First Control Period B 21.5
Cost of Aeronautical Assets as on 31.03.2016 C = A + B 183.5
Accumulated Depreciation as on 31.03.2016 D 117.9
Closing RAB as on 31.03.2016 E = C – D 65.5
Opening RAB as on 01.04.2016 F = E 65.5
4.5.9 For true-up, AAI has considered an amount of ₹ 84.00 crores for Opening RAB for FY 2016-17 which
is at variance from what was approved by the Authority in the Tariff Order for LGBIA for the Second
Control Period. The opening RAB submitted by AAI as part of the true up proposal submission is ₹
84.00 crores which includes left out assets of ₹ 16.59 crores at the time of finalization of Tariff for the
Second Control Period and hence, these assets have been added to the True up of Second Control Period.
Further, AAI has added an amount of ₹ 1.90 crores shown as ‘Cost Apportionment’ or Improvement
cost to the Opening RAB of Second Control Period.
4.5.10 Based on the information/details provided by AAI and the comparison of the left-out assets and Cost
Apportionment (the list of left out assets and improvements are detailed in Annexure II of Asset
Allocation Study Report) with the fixed asset register, it is noted that these assets exclusively belong to
LGBIA. Hence, the Authority proposes to include these assets as part of the Opening RAB for FY 2016-
17 of the Second Control Period.
4.5.11 The Authority, based on the above facts, proposes to consider the opening RAB for true-up of the
Second Control Period as submitted by AAI i.e., ₹ 84.00 crores (₹ 65.5 crores + ₹ 16.59 crores + ₹ 1.90
crores).
Capital additions submitted by AAI for Second Control Period and Pre-COD Period
4.5.12 The Authority notes variance between the approved CAPEX in the Tariff Order for the Second Control
Period and the actual capitalization of aeronautical assets. The Tariff Order for the Second Control
period had projected a capitalization of aeronautical assets amounting to ₹ 261.9 crores for SCP, but as
per AAI's submission, ₹ 148.78 crores of aeronautical assets have been capitalized (56.8% of approved
CAPEX) (refer Table 18) until the COD (Commercial Operation Date).
4.5.13 The Authority reviewed the actual capital additions to RAB during the Second Control Period, which
is explained as follows:
Table 16: Capital additions submitted by AAI for the SCP and Pre-COD Period for LGBIA
(₹ crores)
FY’17 FY’18 FY’19 FY’20 FY’21 Total FY’22 Total
S.
Particulars till till till
No
FY’21 COD COD
1 Runway 0.00 1.08 49.71 1.78 0.38 52.94 0.00 52.94
3 Roads Bridges &Culverts 0.61 0.00 0.00 0.00 0.00 0.61 0.00 0.61
4 Terminal Building 0.00 2.76 11.96 5.14 0.00 19.86 1.82 21.68
5 Temp. Building 0.00 0.09 0.05 0.18 0.18 0.50 0.00 0.50
6 Residential Building 0.00 0.00 0.30 0.00 0.00 0.30 1.10 1.40
7 Operational B/Wall 0.00 0.00 7.07 0.00 0.15 7.22 6.05 13.26
8 Residential Security Fencing 0.00 0.00 0.00 0.00 0.22 0.22 0.00 0.22
Consultation Paper No. 01/2024-25 Page 40 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
FY’17 FY’18 FY’19 FY’20 FY’21 Total FY’22 Total
S.
Particulars till till till
No
FY’21 COD COD
9 Computer & Peripherals 0.04 0.03 0.17 0.09 0.40 0.73 0.00 0.73
10 Software 0.02 0.01 0.00 0.00 0.00 0.03 0.00 0.03
11 Plant & Machinery 7.29 2.68 9.50 8.23 2.68 30.38 1.23 31.61
12 Tools & Equipment 1.73 1.20 4.23 6.01 0.60 13.77 0.06 13.83
13 Furniture-Office 0.01 0.62 0.47 1.41 0.08 2.58 0.00 2.58
14 Vehicles 0.05 0.38 0.22 0.73 0.00 1.38 0.00 1.38
15 Office Eqpt 0.01 0.00 0.10 0.10 0.13 0.33 0.00 0.33
16 X-Ray 0.00 0.00 0.00 2.38 0.00 2.38 0.00 2.38
17 CFT/Fire Fighting 0.00 0.00 0.00 5.29 0.00 5.29 0.00 5.29
Equipments
Total 9.77 8.84 83.77 31.33 4.82 138.53 10.26 148.78
4.5.14 The Authority compared the total capital additions provided by AAI with the capital additions approved
in the Second Control Period order as detailed below:
Table 17: Reconciliation of Additions considered in the Second Control Period Order and Actuals
incurred by AAI
(₹ crores)
Total FY22
Particulars FY’17 FY’18 FY’19 FY’20 FY’21 up to till Total
FY21 COD*
Amount approved as per 6.90 11.20 37.80 178.00 28.00 261.90 - 261.90
Tariff Order (A)
Actual additions to RAB 9.77 8.84 83.77 31.33 4.82 138.53 10.26 148.79
(B)
Difference (B-A) 2.87 (2.36) 45.97 (146.67) (23.18) (123.37) 10.26 -
* up to October 8, 2021
4.5.15 The Authority has analyzed the reasons for such differences which are detailed below as mentioned in
Table 18:
• Out of the total CAPEX of ₹ 261.90 crores approved in SCP, ₹ 177.56 crores CAPEX was
deferred due to the anticipated concessioning out of LGBIA to GIAL.
• The cost of assets commissioned by AAI as compared to the approved amount in SCP order
resulted in a cost overrun of ₹ 10.29 crores due to actual tendered costs being marginally higher
than the estimates.
• AAI capitalized assets worth ₹ 54.16 crores, which were not approved in the SCP Order. These
assets were commissioned mainly for enhancing passenger facilitation (such as installation of
air conditioners, passenger chairs etc.), improving security (procurement of bomb suit, X ray
machines, dog squad vehicles, mobile command post, SCCTV systems etc.), and maintaining
the overall operational efficiency of the airport like provision of additional PBB, provision of
CUTE, CUSS and scanner, procurement of rubber removal vehicles, various electrical works,
PA System etc.
Consultation Paper No. 01/2024-25 Page 41 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Table 18: Reconciliation of Additions allowed in Second Control Period Order and Actuals incurred
by AAI
Particulars Reference Amount
Additions as per SCP Tariff Order A 261.90
Capital Expenditure proposed in SCP but later deferred due to consideration for B 177.56
handing over of LGBI Airport, Guwahati under PPP
Variance in cost between additions approved and incurred due to cost overun C 10.29
Capital additions capitalized in the SCP but not approved in SCP Tariff Order D 54.16
Total additions proposed by AAI in its True-up of SCP E=A-B+C+D 148.79
4.5.16 Based on the above analysis, the Authority proposes to allow the actual capital expenditure submitted
by AAI till COD as per Table 18.
Reclassification and Reallocation of assets submitted by AAI for the Second Control Period and
Pre-COD Period
4.5.17 The Authority has commissioned an independent study through the Consultant appointed by AERA on
allocation of assets between Aeronautical and Non-aeronautical services for LGBIA for the Second
Control Period and FY 2021-22 (Pre and Post COD of AAI and GIAL respectively) (summary of the
study is given in Annexure 1 and the Study is attached as Appendix 1) and used the recommendation of
the study, while truing up the RAB till COD for AAI.
4.5.18 The Authority notes that the Independent Study has provided a broad framework for allocation of
various classes of airport assets into Aeronautical, Non-aeronautical and Common. The process
followed by the Study is as follows:
• The assets responsible for/ used exclusively for the provision of aeronautical (as defined in section 2
(a) of the AERA Act, 2008) services have been classified as ‘Aeronautical’ for the purposes of Study.
Additionally, the decisions of AERA on allocation of certain assets in the previous control periods
and in the case of other airports have also been taken into consideration for this exercise.
• Assets which are solely used for the provision of services other than aeronautical services are
classified as ‘Non-Aeronautical’.
• If any asset is not exclusively used for the provision of either Aeronautical service or Non-
Aeronautical service, it has been classified as ‘Common’.
• Apart from being an airport operator, AAI is also responsible for the provision of Air Navigation
Services (ANS) over the Indian airspace. Therefore, certain ANS assets also form part of the books
of AAI. However, since this service is managed separately by AAI and the tariff for the same are
presently regulated by Ministry of Civil Aviation (MoCA), the assets related to the same are not
considered under the RAB of AAI. Therefore, such assets have been excluded from the Aeronautical
Gross Block of AAI.
• However, certain ANS related assets were also transferred to GIAL as on COD. As per the terms of
the Concession Agreement, AAI would continue to provide ANS services at LGBIA. As mentioned
in Schedule Q of Clause 20.2.1 of the Concession Agreement, GIAL is required to make available
all necessary civil infrastructure and necessary support to AAI for providing ANS services.
Therefore, the ANS related assets, when transferred to the books of the GIAL, would be considered
as aeronautical in nature considering that GIAL is not providing or charging for ANS services at
LGBIA whereas it is required to provide the supporting infrastructure.
• Aeronautical assets (e.g. aerobridges, runway, apron etc.) are directly added to RAB and assets
identified to be Non-Aeronautical (e.g. commercial complex) are excluded from it. The assets that
have been classified as Common assets need to be further bifurcated into aeronautical and non-
Consultation Paper No. 01/2024-25 Page 42 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
aeronautical based on a suitable ratio. This ratio has been determined based on the underlying
proportion of their expected utilization for Aeronautical and Non-aeronautical services and activities
at the Airport.
• Assets have been analysed on a case-to-case basis and in case of any misclassification identified in
allocation, appropriate reclassification has been made for such assets.
4.5.19 Reclassification of assets transferred by AAI to GIAL
The Authority has conducted an independent study on allocation of assets for the period FY 2016-17
till COD and used the outcome of the study to true up the RAB as on COD for AAI.
The Authority has considered the opening RAB submitted by AAI, Capital additions and corresponding
depreciation based on the results of the Asset Allocation Study report (refer Annexure 1 for the
Summary of the report and Appendix 1 for the detailed report on Study on allocation of assets between
Aeronautical and Non-aeronautical assets for Guwahti International Airport.)
The asset allocation study report reviewed the various asset categories and developed a basis for
segregation of various assets into Aeronautical, Non-aeronautical and Common. Based on the same, the
Authority has reclassified some portion of assets submitted by AAI for true up of the Pre-COD Period.
(i) Terminal building:
Details of Asset: Expansion and Modification of Existing Terminal Building
Allocation proposed by AAI: Aeronautical
Observation: The assets pertaining to development of terminal building have been considered as
Aeronautical assets by AAI. However, as these assets are within / pertaining to the terminal
building, wherein both Aeronautical and Non-aeronautical activities are carried out, the same is
reclassified as Common asset and segregated in the Terminal Building ratio (89.02:10.98).
Allocation proposed by the Authority: Common
Impact: Reclassifying these assets from Aeronautical to Common reduces the Capital Additions to
the extent of ₹ 0.91 crores.
(ii) Plant & Machinery:
Details of Asset: VRV System, Solar plant, AC plant, Water Softening plant,
Allocation proposed by AAI: Aeronautical
Observation: The assets pertain to various machinery at several locations in the airport terminal
have been classified as Aeronautical assets by AAI. As these assets are used for servicing both
Aeronautical and Non-aeronautical activities within the terminal building, these are reclassified as
Common assets and have been reallocated in the ratio of the Terminal Building (89.02:10.98).
Allocation proposed by the Authority: Common
Impact: Reclassifying these assets reduces the Capital Additions to the extent of ₹ 0.57
crores.
(iii) Furniture & Fixtures:
Details of Asset: Furniture and Fixtures at Administrative offices
Allocation proposed by AAI: Aeronautical
Observation: The furniture at the administrative offices in the terminal building have been
Consultation Paper No. 01/2024-25 Page 43 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
classified as Aeronautical assets by AAI. As these assets are used by staff who perform both
Aeronautical and Non-aeronautical activities, these assets are reclassified as Common assets and
have been reallocated using the Employee ratio.
Allocation proposed by the Authority: Common
Impact: Reclassifying these assets reduces the Capital Additions to the extent of ₹ 0.09
crores.
(iv) Tools and Equipment:
Details of Asset: Sub-station equipment, DG set, Split AC, Lights, Fan, Baggage disinfectant
system, Radio communication equipment, Breath analyzer.
Allocation proposed by AAI: Aeronautical
Observation: The assets pertaining to the various equipment at several locations in the airport have
been classified as Aeronautical assets by AAI. As these assets are used for servicing both
Aeronautical and Non-aeronautical activities within the terminal building, these are reclassified as
Common assets and have been reallocated in the ratio of the Terminal Building (89.02:10.98).
Radio communication equipment and Breath analyzer equipment at ATC Building have been
classified as Aeronautical asset by AAI. However, since these assets are for ANS staff use, they
have been reclassified as ANS assets.
Allocation proposed by the Authority: Common / ANS
Impact: Reclassifying these assets reduces the Capital Additions to the extent of ₹ 0.10 crores.
(v) Office Appliances:
Details of Asset: Computer, Printer, Scanner, DVD, Fox screen, DSLR Camera, Xerox machine,
Handheld Multimeter
Allocation proposed by AAI: Aeronautical
Observation: Computers, Laptop, Printers, and DVD used in the terminal building have been
classified as Aeronautical asset by AAI. As these assets are used by staff who perform both
Aeronautical and Non-aeronautical activities, these assets are reclassified as Common assets and
have been reallocated using the Employee ratio.
Computers, Scanner, Fox screen, Xerox machine, DSLR Camera, DVD, and Handheld multimeter
at the ATC tower and CNS section have been classified as Aeronautical assets by AAI. As these
assets are for CNS use, the assets have been reclassified as ANS assets.
Allocation proposed by the Authority: Common, ANS
Impact: Reclassifying these assets reduces the Capital Additions to the extent of ₹ 0.05 crores.
The following table presents the impact of adjustments in Asset Addition/WIP Capitalization values due to
reclassification of assets of AAI for the period April 1, 2016 to COD.
Table 19: Impact due to reclassification of AAI assets proposed by the Authority
(₹ crores)
Additions - WIP FY22 till Total
FY17 FY18 FY19 FY20 FY21
Capitalization COD
Terminal - - (0.91) - - - (0.91)
Building
Consultation Paper No. 01/2024-25 Page 44 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Additions - WIP FY22 till Total
FY17 FY18 FY19 FY20 FY21
Capitalization COD
Computers (0.01) - - (0.03) - - (0.04)
Machinery (0.03) (0.03) (0.05) (0.03) (0.43) - (0.57)
Tools & - - (0.06) - (0.03) - (0.10)
Equipment
Furniture-Office - (0.08) (0.01) - - - (0.09)
Office - - - - (0.01) - (0.01)
Equipment
Total Impact on (0.04) (0.11) (1.03) (0.07) (0.47) - (1.71)
Additions
Table 20: Reclassification of assets capitalized in the Second Control Period and Pre-COD Period
proposed by the Authority
(₹)
Asset No. Asset Description Classification Revised Aero Impact on Aero
as per Study Value Value
50011157 Modification & Expansion of Existing TB (Alluminium & Common TB 73,461,474.11 (9,060,963.67)
misc work)
150010556 L/OP HP-440(i5/4GB/500GB/14 INCH/DVD RW/WIN8.1) ANS - (55,125.00)
150010562 DESKTOP COMPUTER HP406G1 Common ER 36,776.78 (3,927.22)
(i3/4GB/500GB/18.5TFT/DVD
150010563 DESKTOP COMPUTER HP406G1 Common ER 36,776.78 (3,927.22)
(i3/4GB/500GB/18.5TFT/DVD
150012891 Printer Epson LX-310 dotmatrix impact printer 04 n Common ER 22,012.19 (2,574.57)
150014097 Proc of IT Item. Multifunctional Machines 17 nos. Common ER 178,283.57 (16,438.46)
150014098 Note Book Computer Laptop 2 nos. Common ER 85,296.36 (7,864.66)
150015980 All in One PC-VERITON Z4660G 01 no. Common ER 36,807.12 (3,822.88)
150015981 All in One PC-VERITON Z4660G 01 no. Common ER 36,807.12 (3,822.88)
150015982 All in One PC-VERITON Z4660G 01 no. Common ER 36,807.12 (3,822.88)
150015983 All in One PC-VERITON Z4660G 01 no. Common ER 36,807.12 (3,822.88)
150015984 All in One PC-VERITON Z4660G 01 no. ANS - (40,630.00)
150015985 All in One PC-VERITON Z4660G 01 no. ANS - (40,630.00)
150015986 All in One PC-VERITON Z4660G 01 no. ANS - (40,630.00)
150015987 All in One PC-VERITON Z4660G 01 no. ANS - (39,858.54)
150015988 All in One PC-VERITON Z4660G 01 no. ANS - (39,858.54)
150015989 All in One PC-VERITON Z4660G 01 no. Common ER 36,807.12 (3,051.42)
150015990 All in One PC-VERITON Z4660G 01 no. Common ER 36,807.12 (3,051.42)
150016019 HP ScanJet Pro 3000 s3 Sheet-feed Scanner 01 No. ANS - (20,701.03)
150016022 HP ScanJet Pro 3000 s3 Sheet-feed Scanner 01 No. ANS - (21,101.70)
150016023 HP ScanJet Pro 3000 s3 Sheet-feed Scanner 01 No. ANS - (21,101.70)
150016033 HP ScanJet Pro 3000 s3 Sheet-feed Scanner 01 No. ANS - (20,701.03)
90033679 SITC of 250 KW Ground mounted solar plant Common TB 13,149,700.69 (95,346.33)
90033597 REPLACEMENT OF 8X10TR A/C PLANT AT SHA AT Common TB 4,168,889.98 (30,227.94)
LGBI AIR
90040146 PROVISION OF VRV/VRF AC SYSTEM FOR Common TB 18,088,242.89 (131,154.89)
PROPOSED EXTENS
90035062 SITC of LED Luminaries & allied works at TB Common TB 3,148,913.36 (22,832.26)
90034972 PROVISION OF WATER SOFTENING PLANT FOR Common TB 528,778.80 (3,834.09)
3X225TR AC
Consultation Paper No. 01/2024-25 Page 45 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Asset No. Asset Description Classification Revised Aero Impact on Aero
as per Study Value Value
90034870 PROVISION OF COMPOUND LIGHTING FOR 250 KWP Common TB 846,188.03 (6,135.57)
SOLAR
90036286 Provision of Air Conditioners and Water Coolers at Common ER 1,098,449.87 (104,881.40)
90037005 Terminal Expansion Internal Electrification Interi Common TB 893,235.58 (14,849.45)
90040027 SITC OF 8.5TR AIR COOLED DUCTABLE SPLIT UNIT. Common TB 973,170.71 (120,033.86)
90036984 SITC OF SPLIT AC UNIT AT FIRST FLOOR AT TB Common TB 1,118,484.73 (18,594.07)
90038012 Provision of HVLS fan, 03 nos Common TB 2,323,664.06 (38,629.38)
90039608 SITC of sub station Eqpt and associated work. Common TB 13,748,741.50 (244,103.64)
90040833 IMPROVEMENT OF EXISTING CENTRAL AC Common TB 4,153,074.10 (73,736.24)
SYSTEM AT LGBI
90039841 Provision of 750KVA DG Set and LT Panel at LGBI Ai Common TB 8,040,374.14 (142,753.76)
90040774 SUPPLY LAYING STANDBY 33KV HT CABLE AT Common TB 2,113,981.91 (37,532.94)
GUWAHTI AIR
90042644 Wall mounted split AC 1.5TR 5 star 25 nos. Common TB 855,614.42 (31,748.46)
90042645 Wall mounted split AC 2.00TR Inverter ty 2 nos. Common TB 78,157.09 (2,900.10)
90042646 Floor mounted 3.00 ty Interter Type 1 nos. Common TB 62,352.47 (2,313.65)
90042649 Replacement of Old AC, Ater Cooler (Installation) Common TB 397,496.98 (14,749.54)
90045216 R/o existng panels, cables & AHU of central AC sys Common TB 2,607,730.52 (96,762.54)
90043436 PROV OF 25 KVA TROLLEY MOUNTED DG SET AT Common TB 363,246.87 (13,478.65)
LGBI AIRP
90045724 S/o 15 nos wall mounted split AC 1.5 TR 3star Common TB 738,540.19 (91,093.81)
90045725 S/o 02 nos wall mounted split AC 3TR 5star Common TB 150,586.23 (18,573.77)
90045272 SITC 08 nos 1.5 Tr (4500 K Cal/hr) s/type AC 5star Common TB 313,350.40 (38,649.60)
90047968 Capacity 2 x 20000 BTU/hr A/Cool Refr. 02 units Cargo - (1,330,628.00)
90048239 Capacity 2 x 10000 BTU/hr A/Cool Refr. 01 unit Cargo - (650,372.00)
90047039 Standalone Type UV Based Baggage Disinfectant Sys. Common TB 617,798.80 (26,311.92)
90049569 RADIO COMMUNICATION TEST SET - 1173.2000K18- ANS - (2,290,188.92)
102497
90039840 SITC OF WALK IN COLD ROOM BEHIND OLD RED ANS - (627,119.00)
BLDG.
90045208 BREATH ALCOHOL ANALIZER 01 NO ANS - (48,000.00)
90047150 Touch Screen Kiosk & Network items for FB/LB Proj. Common TB 379,336.34 (16,155.85)
90047538 10 PAIR PIJF CABLE - FIBRE CABLE FOR ANS - (288,374.65)
NETWORKING
90049831 PROCUREMENT OF SCANNER CANON DR- F120 3 Common ER 55,030.95 (5,719.05)
NOS
110012784 Chair PCH 7001D Common ER 15,060.74 (1,608.26)
110012785 Chair PCH 7001D Common ER 15,060.74 (1,608.26)
110012781 TableT104 Common ER 21,107.98 (2,254.02)
110012782 TableT104 Common ER 21,107.98 (2,254.02)
110012783 TableT104 Common ER 21,107.98 (2,254.02)
110014798 Storewell minor plain 3 nos Common ER 34,531.19 (4,038.81)
110014799 Executive Table 2 nos Common ER 32,258.06 (3,772.94)
110014800 High Back Chair PCH-7001D 2 NOS Common ER 23,009.75 (2,691.25)
110014801 SOFA SET PARTO SOFA 1 SET Common ER 39,463.32 (4,615.68)
110014802 STEEL ALMIRAH STOREWEL PLAIN 2 NOS Common ER 25,376.89 (2,968.11)
110014792 PROC. OF EGRESS TABLE & OTHER ACESSORIES Common ER 1,614,021.00 (188,778.00)
110014813 Workstation for ASMGCS ANS - (176,573.40)
110014772 Supply of Furniture Sofa 6nos, Centre Table 3 nos Common ER 358,114.46 (41,885.54)
Consultation Paper No. 01/2024-25 Page 46 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Asset No. Asset Description Classification Revised Aero Impact on Aero
as per Study Value Value
110014640 SUPPLY OF 3 SEATER CHAIRS 124 NOS Common ER 3,214,763.07 (376,002.89)
110015460 PLU 4D PRE GREY METAL 5 NOS Common TB 45,608.51 (809.76)
110015505 Executive Table 1 nos. Common ER 31,028.09 (2,860.91)
110015506 Ex Chair 6 nos. Common ER 76,910.54 (7,091.46)
110015507 Visitor Chair 12 Nos. Common ER 84,294.69 (7,772.31)
110015508 Computer Table. Common ER 48,740.89 (4,494.11)
110015509 Ex Table T-3 nos. Common ER 41,462.03 (3,822.97)
110015511 ALMIRAH BIG STOREWEL PLAIN. 4 NOS Common ER 59,375.36 (5,474.64)
110015512 STEEL RACK 6 PANEL 9 NOS. Common ER 83,624.49 (7,710.51)
110015513 4DR FILLING CABINET. Common ER 57,066.26 (5,261.74)
110015514 EXECUTIVE TABLE T-8. Common ER 26,259.75 (2,421.25)
110015515 PERSONEL LOCKER 4DR 5 NOS. Common ER 50,219.56 (4,630.44)
110015516 ALMIRAH SMALL 1 NOS. Common ER 12,199.19 (1,124.81)
110015517 NON-EX CHAIR 3 NOS. Common ER 32,411.53 (2,988.47)
110015518 COMPUTER CHAIR 3 NOS. Common ER 11,632.76 (1,072.59)
110015519 SOFA PARTO SOFA. 2 NOS Common ER 85,237.74 (7,859.26)
110016936 COMPANION C 11 COMPUTER TABLE. 1 NO Common ER 7,139.52 (741.53)
110016937 REGENCY HIGH BACK 700 1 D 2 NOS. Common ER 25,027.68 (2,599.44)
110016938 PARTO 2 SEATER SOFA 2 NOS. Common ER 40,067.33 (4,161.49)
110016939 GODREJ MINOR PLAIN ALMIRAH 1 NOS. Common ER 11,277.81 (1,171.34)
110016940 PARTO 1 SEATER 4 NOS. Common ER 24,563.96 (2,551.28)
110016941 GODREJ STOREWEL PLAIN 11 NOS. Common ER 159,735.71 (16,590.55)
110016942 GODREJ T-8 TABLE 9 NOS. Common ER 76,280.67 (7,922.70)
110016943 GODREJ 4 DRAWER VERTIFAL FILING CABINET. 1 Common ER 14,640.43 (1,520.59)
NOS.
150013808 Fox screen 8 feet*6 feet. 2 nos ANS - (14,152.54)
150016046 DSLR Camera Model-D-3500-18-55PVR ANS - (30,504.00)
150016148 SUPPLY OF KYOCERA MFPS Xerox Machine at Ghy ANS - (42,500.00)
150016879 FLUKE HAND HELD DIGITAL MULTIMETER ANS - (9,048.27)
Total (17,145,377.25)
4.5.20 Based on the revision of asset allocation methodology adopted for assets of LGBIA as discussed above,
a revision in the Aeronautical Gross block has been proposed. The year-wise revised value of assets
from FY 2016-17 to FY 2020-21 has been summarized in the tables below:
Table 21: Gross Block proposed by the Authority for Second Control Period and Pre COD period
(₹ crores)
Particulars FY 17 FY 18 FY 19 FY 20 FY 21 FY22 till
COD
As per AAI Submission
Aeronautical Gross Block (A) 273.23 281.99 365.76 397.09 401.91 412.17
Non-Aeronautical Gross Block (B) 25.35 23.97 24.51 25.08 25.08 25.47
Total Gross Block (C = A + B) 298.58 305.96 390.27 422.17 426.99 437.64
Percentage Aeronautical (D = A ÷ C) 91.51% 92.17% 93.72% 94.06% 94.13% 94.18%
Proposed by the Authority as per the Independent Study
Aeronautical Gross Block (E) 273.19 281.84 364.58 395.84 400.19 410.44
Non-Aeronautical Gross Block (F) 25.39 25.53 27.04 27.64 27.65 28.04
Consultation Paper No. 01/2024-25 Page 47 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Particulars FY 17 FY 18 FY 19 FY 20 FY 21 FY22 till
COD
Total Gross Block (G = E + F) 298.58 307.37 391.61 423.48 427.84 438.48
Percentage Aeronautical (H = 91.50% 91.70% 93.10% 93.47% 93.54% 93.61%
(E/G)*100)
4.5.21 Financing Allowance
The Authority notes that AAI has claimed financing allowance amounting to ₹ 84.66 lakhs, as part of
RAB. The Authority has the following views on the aspect of Financing Allowance:
a. Providing return on capital expenditure from the very beginning of construction will significantly
lower the risks for an airport operator and may require revisiting the return on equity allowed to
airport operators as the investment in the asset class will then be equated to risk free rate of return.
b. Further, provision of Financing Allowance will disincentivize the Airport Operators from ensuring
timely completion of projects and delivery of services to the users. Therefore, a return should be
provided only when the assets are made available to the airport users except in the case of certain
costs like IDC that will have to be incurred if debt is used for funding projects.
c. Furthermore, the future returns from the project should generate adequate returns to cover the cost
of equity during the construction stage. The airport operator is adequately compensated for the risks
associated with the equity investments in a construction project once the project is capitalized by
means of a reasonable cost of equity.
d. Developments at greenfield airports inherently take longer durations to commission and
operationalize. Thus, airport operators would have to wait for a considerable duration before getting
returns on large capital projects. Keeping this in view, financing allowance was provisioned in the
initial stages to such airports. It may be further noted that financing allowance was never provided
in the case of brownfield airports like MIAL, DIAL and other AAI airports. Further, financing
allowance for greenfield airports of BIAL, HIAL, CIAL etc. was allowed only for the initial stages
of their development, after which IDC was permitted on the debt portion of the proposed capital
expenditure.
e. It is pertinent to note that in case of a greenfield airport, investment in regulatory blocks by the
Airport Operator would not make the airport facilities available to the passengers. Brownfield and
Greenfield airports can’t be equated on this issue. In greenfield airports, the tariff is not applicable,
and no revenue is available to the Airport Operator till the aeronautical services have been created
and put to use. However, in the case of brownfield airports, where Airport Operator brings in
additional investments, the airport facilities are mobilized and enabled to other functional parts of
the airport, which remains functional, and Airport Operator keeps on enjoying the charges from the
users. In the case of LGBIA, the Airport is a brownfield airport, which would not be eligible for an
allowance on the equity portion of newly funded capital projects.
f. Financing Allowance is a notional allowance and different from interest during construction.
Therefore, the provision of Financing Allowance on the entire capital work in progress would lead
to a difference between the projected capitalization and actual cost incurred, especially when the
Airport Operator funds the projects through a mix of equity and debt.
g. AERA Guidelines, 2011 does not specifically state that Financing Allowance is to be provided on
equity portion of the capital expenditure. The proviso to Section 13 (1) (a) of the AERA Act states
that “different tariff structures may be determined for different airports having regard to all or any
of the above considerations specified at sub-clauses (i) to (vii) of Section 13 (1) (a)”.
Consultation Paper No. 01/2024-25 Page 48 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
In view of above, the Authority proposes not to consider any expense related to financing allowance as
a part of ARR.
4.6 True up of Depreciation
4.6.1 The Authority notes that while submitting the True up for the Pre-COD period for LGBIA, AAI has
taken cognizance of the rates of depreciation approved by the Authority in its order (Order No. 35/2017-
18 dated January 12, 2018 and Amendment No. 01 to Order No. 35 on ‘Determination of Useful Life
on Airport Assets’). Accordingly, the depreciation order has been applied by AAI for LGBIA from FY
2018-19 onwards. For the FY 2016-17 and FY 2017-18, AAI has computed depreciation as per its
Accounting Policy.
4.6.2 For the additions to RAB, AAI has calculated the depreciation during year of capitalization based on
number of days, the asset was put to use. The Authority proposes to consider the same.
4.6.3 Accordingly, the year-wise impact on depreciation on asset additions as determined by the independent
study conducted by the Authority (due to reclassification and other adjustments) is summarized in the
table below:
Table 22: Impact on depreciation due to reclassification of AAI assets for the SCP and pre-COD period
(₹ crores)
Depreciation on FY 17 FY 18 FY 19 FY 20 FY 21 FY22 till Total
Additions during COD
the Year
Terminal Building - - - (0.03) (0.03) (0.02) (0.08)
Computers (0.001) (0.001) (0.002) (0.004) (0.011) (0.006) (0.03)
Machinery (0.001) (0.003) (0.006) (0.008) (0.022) (0.020) (0.06)
Tools & Equipment - - (0.004) (0.004) (0.005) (0.003) (0.02)
Furniture-Office - (0.001) (0.012) (0.013) (0.013) (0.007) (0.05)
Office Equipment - - - - (0.002) (0.001) (0.003)
Total Impact of (0.002) (0.005) (0.025) (0.060) (0.083) (0.052) (0.23)
Adjustments on
Depreciation on
Additions
4.6.4 The Authority has computed depreciation for the Second Control Period and Pre-COD period, after
making necessary adjustments to the assets excluded from RAB and the same is presented as below:
Table 23: Depreciation considered by the Authority for True up of the SCP and Pre-COD Period
(₹ crores)
FY’17 FY’18 FY’19 FY’20 FY’21 Total FY’22 Total
Particulars till till till
FY’21 COD COD
Depreciation as per AAI (A) 7.00 7.17 9.93 13.32 13.84 51.27 7.31 58.57
Depreciation impact on (0.002) (0.005) (0.025) (0.060) (0.083) (0.175) (0.052) (0.23)
reclassification (B)
Depreciation as per the independent 7.00 7.17 9.90 13.26 13.76 51.09 7.26 58.34
study conducted by the Authority
(C=A-B)
Reference: Table 11 of the Study on Allocation of assets between Aeronautical and Non-aeronautical assets for LGBIA
The Authority, based on this examination and recommendation of the independent study on asset allocation
proposes to consider depreciation as per Table 23 for true up of the pre-COD period.
Consultation Paper No. 01/2024-25 Page 49 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
4.7 True up of RAB
4.7.1 The Authority compared the year-wise additions to RAB submitted by AAI to the Aeronautical capital
expenditure approved by it in the Tariff Order for the Second Control period and the same is summarized
in Table 17.
4.7.2 Subsequent to the reclassifications and revisions in asset allocation ratios, the adjusted RAB has been
derived by the Authority as under:
Table 24: Adjusted RAB submitted by AAI and proposed by the Authority post re-classification for SCP
and pre-COD period
(₹ crores)
FY’22
Particulars FY’17 FY’18 FY’19 FY’20 FY’21 till Total
COD
As per AAI
Opening RAB (A) 84.00* 78.85 80.44 154.28 172.29 163.26
Additions to RAB during the year (B) 9.77# 8.84 83.77 31.33 4.82 10.26 148.79
Deletions from RAB during the year (C) 7.92 0.08 8.00
Depreciation for the year (D) 7.00 7.17 9.93 13.32 13.84 7.31 58.57
Closing RAB for the year (E=A+B-C- 78.85 80.44 154.28 172.29 163.27 166.21
D)
As per Authority
Opening RAB (F) 84.00* 78.81 80.30 153.13 171.13 161.73
Reclassification adjustments
- Reclassification impact (0.04) (0.11) (1.03) (0.07) (0.47) (1.71)
(other than depreciation) (G)
- Depreciation impact on reclassification (0.00) (0.01) (0.03) (0.06) (0.08) (0.05) (0.23)
(H)
Total reclassification impact (I=G+H) (0.04) (0.12) (1.06) (0.13) (0.55) (0.05) (1.95)
Additions as per Study^ (J=B+G) 9.73 8.73 82.74 31.26 4.35 10.26 147.07
Deletions as per Study (K=C) 7.92 0.08 0.00 0.00 0.00 0.00 8.00
Depreciation as per Study^ (L=D+H) 7.00 7.17 9.91 13.26 13.76 7.26 58.34
Closing RAB (M=F+J-K-L) 78.81 80.30 153.13 171.13 161.73 164.73
Average RAB (N=(F+M)/2 81.41 79.55 116.71 162.13 166.43 163.23
* includes left out assets worth ₹ 16.59 crores and cost apportionment worth 1.90 crores in First Control Period
# excludes left out asset and cost apportionment as the same has been included in Opening RAB
^As per the independent asset allocation study conducted by the Authority
4.7.3 Deemed Initial RAB
a. The extract of the Concession Agreement with respect to determination of “Deemed Initial RAB”
has been provided hereunder:
Clause 28.11.3 states that:
i. “It is agreed by the Parties that the Concessionaire shall be liable to pay to the Authority an
amount equivalent to the investments made by the Authority in the Aeronautical assets as of
the COD and considered by the Regulator as part of the Regulatory Asset Base, subject to
requisite reconciliation, true-up and final determination by the Regulator of the quantum of
such investment (“Deemed Initial RAB”).
ii. The estimated depreciated value of investments made by the Authority in the Aeronautical
assets at the Airport as on March 31, 2018, is ₹ 69,00,00,000 (Rupees Sixty Nine crores)
(“Estimated Deemed Initial RAB”). It is agreed by the Parties that the Estimated Deemed
Consultation Paper No. 01/2024-25 Page 50 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Initial RAB shall be due and payable by the Concessionaire to the Authority within 90 (ninety)
days of COD.”
Clause 28.11.4 states that:
“Pursuant to the payment of the Estimated Deemed Initial RAB, and upon the reconciliation, true-
up and final determination by the Regulator of the quantum of the investment under 28.11.3(a). any
surplus or deficit in the Estimated Deemed Initial RAB with respect to the Deemed Initial RAB shall
be adjusted as part of the Balancing Payment that becomes due and payable as per Clause 31.4
after the expiry of 15 (fifteen) days from such final determination by the Regulator, with due
adjustment for the following ("Adjusted Deemed Initial RAB'"):
(a) reduced to the extent of over-recoveries, if any, of Aeronautical Revenues by the Authority
until the COD, that the Regulator would provide for as a downward adjustment while
determining Aeronautical Charges for the next Control Period; or
(b) increased to the extent of under-recoveries, if any, of Aeronautical Revenues by the Authority
until the COD, that the Regulator would provide for as an upward adjustment while
determining Aeronautical Charges for the next Control Period.
The amount(s) to be paid by the Authority or Concessionaire shall be the present value of Adjusted
Deemed Initial RAB calculated using the fair rate of return as determined by the Regulator for the
time period from the COD to the date of actual payment of the Adjusted Deemed Initial RAB.”
Clause 28.11.5 states that:
“Upon reimbursement of such amount by the Concessionaire to the Authority, the Deemed Initial
RAB will, in addition to the investments made by the Concessionaire, be considered for the purpose
of determination of Aeronautical Charges by the Regulator.
(a) The Authority undertakes to make any required supporting submissions to the Regulator
towards such consideration and determination by the Regulator.
(b) The Parties shall submit to and request the Regulator to separately identify the Deemed Initial
RAB in future determinations of Aeronautical Charges with regard to consideration of
depreciation, required returns, etc.”
Joint Asset Reconciliation Statement (JARS)
b. The Authority notes that in June 2023, both the AAI and GIAL had collaborated to conduct a
physical verification of the assets. Following this verification, they jointly signed the joint asset
reconciliation statement (JARS) to confirm the assets transferred as on COD. GIAL has accepted
that the value of aeronautical assets transferred by AAI as on COD was ₹ 156.60 crores and that the
value of ANS related assets transferred was ₹ 3.16 crores as detailed in Joint Asset Reconciliation
Statement.
Table 25: Assets transferred by AAI to GIAL as per JARS as on COD
(₹ crores)
S. No. Particulars No. of Assets Net Asset Value as on
COD*
A1 Aeronautical assets handed over to GIAL 957 156.60
A2 Non-Aeronautical assets handed over to GIAL 132 6.74
A3 ANS assets handed over to GIAL 52 3.16
Total (A1 + A2 + A3) 1141 166.50
Consultation Paper No. 01/2024-25 Page 51 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
*8th October 2021
c. Taking cognizance of the above clauses in the Concession Agreement and adjustments &
reclassification proposed by the Authority based on the outcome of the independent study conducted
by the Independent Consultant appointed by AERA on allocation of assets for LGBIA, including
disallowance of Financing Allowance, inclusion of IDC and the left out assets, reclassification of
assets and the resulting change in depreciation, the Authority has determined the Deemed Initial
RAB as on COD, as follows:
Table 26: Determination of Deemed Initial RAB by the Authority
(₹ crores)
Non-
Aeronautical ANS assets Total
Particulars aeronautical
assets (A) (C) D = (A + B + C)
assets (B)
Net block value of assets handed over 156.60 6.74 3.16 166.50
by AAI on COD as per JARS
Impact due to reclassification of RAB (0.96) 0.96 -
on transferred assets*
Net assets transferred by AAI to GIAL 155.64 7.70 3.16 166.50
as on COD*
Deemed Initial RAB as on COD for 158.80
GIAL (Aero + ANS)
* Refer Annexure III of Study on Allocation of assets between Aeronautical and Non-aeronautical for LGBIA
d. The Authority examined that GIAL in their submission has considered all assets including non-
aeronautical, as part of Deemed Initial RAB. However, as per the allocation methodology adopted
as part of the independent study commissioned by the Authority, the Deemed Initial RAB considers
only Aeronautical and ANS assets.
e. The deemed initial RAB as on COD is thus subsequently determined by including only Net
Aeronautical (₹ 155.64 Cr.) and ANS assets (₹ 3.16 Cr.) transferred by AAI to GIAL as on COD;
and derived to be ₹ 158.80 crores.
4.8 True up of Fair Rate of Return
4.8.1 AAI had considered the FRoR at 14% in line with the decision taken by the Authority for Chennai,
Kolkata, Guwahati and Lucknow airports for the First Control Period.
4.8.2 The Authority notes that AAI had not availed any debt during second control period till COD.
4.8.3 At the time of determination of tariff for the Second Control Period, the Authority had decided to
consider FRoR for LGBIA as 14%. In line with its decision of second control period order no. 10/2017-
18, the Authority proposes to consider the FRoR at 14% for true up of second control period till COD.
4.8.4 However, it is to be noted that AAI has operated the Airport in FY 2021-22 only till October 7, 2021.
Therefore, AAI is eligible to claim return on RAB only till COD. Hence, for FY 2021-22, the Authority
proposes to pro-rate the FRoR for 190 days during which AAI operated the Airport. The pro-rated FRoR
for FY 2021-22 (till COD-190 days) has been computed as follows:
FRoR = FRoR* n/ 365
COD
Where, FRoR is the fair rate of return for entire FY 2021-22, FRoR is the pro-rated FRoR for the
COD
period till COD and n is the number of days in operation in FY 2021-22.
Based on the above approach the pro-rated FRoR for FY 2021-22 has been computed as follows:
Consultation Paper No. 01/2024-25 Page 52 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Table 27: Pro-rated FRoR for FY’22 considered by the Authority for true up of pre-COD
period
Particulars Value (%)
FRoR for FY’22 (A) 14%
Number of days of operations in FY’22 (B) 190
Pro-rated FRoR for FY’22 (till COD) (A*B/365) 7.29%
4.8.5 Based on the above analysis, the Authority proposes to consider FRoR as 14% for the FYs 2016-17 to
2020-21 and as 7.29% for FY 2021-22 (up 7th Oct’2021) for true up of the pre-COD period.
4.9 True up of Aeronautical Operation and Maintenance (O&M) expenses
4.9.1 The component wise break up of Aeronautical Operation and Maintenance expenses submitted by AAI
for the Second Control Period and Pre-COD period is as follows:
Table 28: O&M expenses submitted by AAI for True up of the SCP and Pre-COD Period
(₹ crores)
Particulars FY FY FY FY FY Total FY Total
2016-17 2017-18 2018-19 2019-20 2020-21 up to 2021-22* for
FY21 SCP
till
COD
Employee benefit 16.64 24.02 32.05 32.41 26.70 131.82 14.80 146.62
expenses
Administrative and 13.95 35.44 42.92 59.69 49.82 201.82 48.43 250.25
other expenses
Repairs & 7.72 15.56 12.90 13.97 12.26 62.42 7.57 69.98
Maintenance
expenses
Utilities and 4.46 5.03 6.05 6.16 5.12 26.81 3.00 29.81
Outsourcing
expenses
Other Outflows 0.73 0.91 0.78 0.94 0.09 3.44 0.08 3.53
Total 43.50 80.96 94.70 113.17 93.98 426.31 73.89 500.19
*Up to COD (Date- 08th October 2021)
4.9.2 The Authority notes that in the Tariff Order of the Second Control Period vide Order No. 38/2017-18,
it had approved the O&M expenses of ₹ 363.80 crores for LGBIA, which is as follows:
Table 29: Aeronautical O&M expenses approved by the Authority for Second Control Period
(₹ crores)
Particulars FY FY FY FY FY Total
2016-17 2017-18 2018-19 2019-20 2020-21
Employee benefit expenses 21.00 28.60 35.20 36.90 38.80 160.50
Administrative & Other expenses 15.70 16.40 18.20 19.30 20.50 90.10
Repairs & Maintenance expenses 6.00 19.00 20.50 21.30 22.20 89.00
Utility and Outsourcing expenses 3.80 3.90 4.70 4.80 4.80 22.00
Other outflows 0.30 0.40 0.40 0.40 0.50 2.00
TOTAL 46.90 68.30 79.00 82.80 86.80 363.80
4.9.3 On comparing the actual expenses incurred by AAI for the second control period till FY2020-21, with
the expenses approved in the Tariff Order for the Second Control Period, the Authority observed the
following:
Consultation Paper No. 01/2024-25 Page 53 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
a. Payroll Expenditure: For FY 2017-18 - there was an increase of 44% as against 36.19% approved
in the tariff order of Second Control Period. The Authority further noted that for FY 2018-19 – there
was an increase of 33% as against 23% Y-o-Y approved in the tariff order of Second Control Period.
The Authority sought clarification from AAI in this regard. AAI clarified that the variance is due to
pay revision as per 7th Pay Commission Report which was implemented from Jan 2017 and payment
of arrears were paid to Executives in December 2017 (FY’18) and to Non-Executives in FY’19.
The Authority also noted that the total Employee benefit expenses of ₹ 131.82 crores incurred by
AAI is lower than the approved amount of ₹ 160.50 crores for the Second Control period. Based on
the above factors, the Authority considers the payroll expenditure of LGBIA, as submitted by AAI
for the Second Control Period to be reasonable and allow the same.
b. Administrative and General Expenses: The Authority notes that the Administrative and General
expenses of ₹ 201.82 crores claimed by AAI for Second Control Period are significantly higher than
the amount approved by the Authority for the Second Control Period. The Authority on analysis
observed that variance is mainly on account of the increase in CHQ & RHQ expenses. The amount
of CHQ & RHQ expenses as per the Tariff Order of Second Control Period was ₹ 67.90 crores
whereas the actual expenses allocated by AAI up to FY21 was ₹ 172.90. Based on the above factors,
the Authority is of the view that the CHQ/ RHQ expenses need to be rationalized and the same is
explained in para 4.9.5 of this Consultation Paper.
c. Repairs and Maintenance (R&M): The Authority notes that the total Repairs & Maintenance
expenses of ₹ 62.42 crores claimed by AAI for the Second Control Period (till FY21) is significantly
lower than the amount approved in the tariff order for the Second Control Period and hence
considered reasonable.
d. Utilities and Outsourcing Expenses: The Authority notes that the Utility and Outsourcing
expenses of ₹ 26.81 crores claimed by AAI is higher than the approved expenses of ₹ 22.00 crores
as per the Tariff Order for the Second Control Period. The overall variation works out to 22 % on
the total Utility expenses. It is also observed that the actual electricity expenses of ₹ 23.86 crores
incurred till FY21, is higher than the approved amount of ₹ 19.1 crores (i.e., an increase of approx.
25%). The Authority sought clarification from AAI in this regard. AAI as part of its response
submitted that the increase in electricity expenses is attributed to the increased load due to addition
of new facilities at the airport and due to the increase in per unit cost of power supplied by third
party utility vendors.
Considering the same, the Authority proposes to consider the actual expense towards Utility and
Outsourcing expenses for true up of the pre-COD period.
e. Other Outflows: Expenses related to Other Outflows comprises of collection charges on UDF,
PSF(F), and charges paid to IATA. The Authority in its order for Second Control Period approved
₹ 2.00 crores for other outflows mainly towards collection charges on UDF. AAI as part of its true
up submission stated that the actual expense incurred was ₹ 3.44 crores under this head. This
comprised of ₹ 3.32 crores towards collection charges on PSF(F) (till FY20), and UDF. The
remaining ₹ 0.12 crores was on account of collection charges paid to IATA (facilitating collection
of airline charges on behalf of AAI). The Authority notes that prior to Second Control Period IATA
Collection Charges were included as part of CHQ/RHQ expense allocation. However, Second
Control Period onwards, expenses related to IATA collection charges have been allocated as per
actuals to LGBIA. Since these expenses were not included in “Other Outflows” prior to SCP, the
same was not envisaged as part of Tariff Order for SCP and thus correspondingly the projections
were lower. Accordingly, basis the aforementioned reasons, the higher expense on account of
Consultation Paper No. 01/2024-25 Page 54 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
“Other Outflows” found in order and has been considered by the Authority.
4.9.4 Reallocation of Common O&M expenses by the Authority
The Authority has commissioned an independent study through the Consultant appointed by AERA to
determine efficient Aeronautical Operation and Maintenance costs for the Second Control Period and
FY2021-22. The Authority used the outcome of the study to true up the O&M expenses for the pre-
COD period for AAI.
The common O&M expenses have been segregated by AAI between Aeronautical and Non-
aeronautical expenses based on a suitable ratio. This ratio has been determined based on the underlying
proportion of their expected utilisation for Aeronautical and Non-aeronautical services and activities
at the Airport.
The Authority has analyzed the submission made by AAI on allocation of Common expenses into
Aeronautical and Non-aeronautical on a case-to-case basis and applied appropriate re-classification
and re-allocation of the expenses, wherever it noted any discrepancies in the allocation of expenses by
AAI (refer Table 13 for Allocation of O&M expenses of AAI as per the Study on Efficient Operation
and Maintenance Expenses for Lokpriya Gopinath Bordoloi International Airport). Accordingly, the
following common expenses have been re-allocated by the Authority by using appropriate ratios such
as Employee Head Count ratio, Terminal Building ratio, Gross Fixed Assets ratio and Electricity ratio
(Refer para 4.5 to of the Study report on Efficient Operation and Maintenance Expenses for Lokpriya
Gopinath Bordoloi International Airport regarding the ratios used by the Authority for allocation of
common expenses.)
a) Employee benefit/Payroll expenses
b) Administrative and General expenses
c) Utility expenses
d) Repairs and Maintenance expenses
The total impact on re-allocation of each of the above expenses and other adjustments have been
summarised in the following paragraphs.
a) Employee Benefit expenses
Observation: The Authority noted that in the case of AAI, the costs directly pertaining to ANS
employees have been excluded from the O&M expenses, but the cost for ANS employees
involved in support services have not been excluded from Common expenses. Accordingly,
the Authority has considered the common expenses allocated to ANS employees as deemed
Non-aeronautical employees and has re-worked the Employee Head Count ratio. The Authority
further noted that for non-aeronautical allocation of ‘Retirement benefits of Guwahati Employees
(Provisions made at CHQ)’, AAI has not provided any direct bifurcation as part of its submission
for payroll expenditure and provisions. However, AAI has considered the applicable employee
ratios for all years in their calculations. Also, for the year FY2021-22 up to COD, AAI had not
segregated non-aeronautical portion and assumed full amount as aeronautical. This expense was
eventually segregated into Aeronautical: Non-Aeronautical basis the ratio of 95:5, as per clause
14.8 of Order No. 38/2017-18 in respect of LGBIA for Second Control Period, by the Authority.
Impact: The impact of the reallocation of Employee Benefit expenses based on revised Employee
Headcount ratio and based on other adjustment described above, results in reduction of the
aforementioned expenses by ₹ 0.18 crores for the Second Control Period till COD.
Consultation Paper No. 01/2024-25 Page 55 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Reference: Para 4.6.1 and Table 25 of the Study on Efficient Operation and Maintenance Expenses
for Lokpriya Gopinath Bordoloi International Airport.
b) Administrative and General expenses
Observation: The submissions by AAI have been analyzed and it has been observed that the
Administrative and General expenses include certain expenses such as tender, rent and rates and
taxes, which directly relate to the Aeronautical activity and certain expenses such as insurance of
vehicles, manpower hiring, printing & stationery, conveyance, employee training etc., which are
linked to Common expense. Therefore, each component of the Administrative and General
expenses has been examined and subsequently allocated as per suitable ratio.
Impact: The impact of the reallocation results in reduction of Administrative and other expenses
by ₹ 1.35 crores for the Pre- COD period.
Reference: Para 4.6.2 of the Study on Efficient Operation and Maintenance Expenses for Lokpriya
Gopinath Bordoloi International Airport.
c) Utility expenses
Observation: AAI’s submission has been analyzed for expenses related to electricity and water
charges. It was noted that AAI had made recoveries from concessionaires and the same had been
netted off from the total expenses. Expenses under the head of ‘Consumption of Stores and Spares’
included petrol for vehicles and other usage, tyres, paper glass, m-fold papers, cuss roll papers, fire
foam, PPE items, electrical spares, and other consumable items. Certain expenses among them
directly relate to Aeronautical activities while some are linked to Common expense. Therefore,
each component of these expenses have been examined and subsequently allocated as per suitable
ratio.
Impact: The impact of the reallocation results in reduction of Utility expenses by ₹ 0.11 crores for
the Pre- COD period.
Reference: Para 4.6.3 of the Study on Efficient Operation and Maintenance Expenses for Lokpriya
Gopinath Bordoloi International Airport.
d) Repairs and Maintenance expenses
Observation: AAI’s true up submission was analyzed, and it was observed that certain Repair &
Maintenance expenses such as repair of runway and maintenance of AOCC pertain only to
Aeronautical activity, while some such as repair of furniture for terminal building and maintenance
of IT hardware are related to the terminal building and airport employees respectively. Hence, a
detailed scrutiny of all expenses was undertaken, and as per norms allocation of such expenses was
done in the ratio of Gross Fixed Assets/ Terminal Building/ revised Employee ratio depending on
the nature of each ledger. Further, it was observed that the expense related to Furniture & Fixtures
for Terminal Building was allocated as 100% Aeronautical. Since the furniture and fixtures are
primarily used within the terminal building, this expense has been revised by the Authority basis
the Terminal Building ratio.
Impact: The impact of the reallocation results in reduction of Repairs and Maintenance expenses
by ₹ 0.99 crores for the period FY 2016-17 till COD.
Reference: Para 4.6.4 of the Study on Efficient Operation and Maintenance Expenses for Lokpriya
Gopinath Bordoloi International Airport.
4.9.5 Rationalization of Aeronautical O&M expenses
Consultation Paper No. 01/2024-25 Page 56 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
a. Based on the Internal benchmarking analysis performed for O&M expenses through the Study
on Efficient Operation and Maintenance Expenses for Lokpriya Gopinath Bordoloi
International Airport, the Authority proposes to rationalize the CHQ/ RHQ expense allocation
(included under Administrative and General expenses) as below:
CHQ/ RHQ expense allocation (included under Administrative and General expenses)
The Authority reviewed the basis adopted by AAI for allocation of CHQ and RHQ expenses to
LGBIA and other airports and noted the following:
• All expenses incurred by CHQ and RHQ (like staff costs, Admin and Gen. expenses,
Repairs and Maintenance, utilities, outsourcing expenses etc.) are allocated to all the AAI
airports, in the ratio of revenues earned by each Airport.
• Expenses such as legal costs, interest/ penalties are related to some specific airports.
However, these have been allocated to the common pool and apportioned to all the AAI
airports.
The Authority is of the view that the above process followed by AAI for allocating the expenses
is not correct and necessitates adoption of a scientific/ rational approach for justifiable
allocation of expenses to the Airports. Towards this objective, the Authority has examined the
major expense components of CHQ and RHQ for the FY’17 to FY’21 submitted by AAI and
has proposed the following views on allocation of CHQ/ RHQ expenses:
i. Pay and Allowances of CHQ and RHQ:
• AAI has considered pay and allowances of Commercial department at CHQ and RHQ as
Aeronautical expenses, whereas such expenses are Non-aeronautical in nature.
• AAI has excluded pay and allowances of employees involved in ATM, CNS and Cargo
departments at CHQ and RHQ while working out the allocation to the airport. However, no
exclusion has been done for support services of the departments relating to HR, Finance,
Civil, Terminal Management (Housekeeping), etc.
• Manpower of CHQ and RHQ also provide services to Non-aeronautical activities, ATC,
and CNS cadres at respective airports. Hence, pay and allowances need to be adjusted
accordingly.
Considering all the facts and figures as stated above, the Authority is of the view that 20% of
pay and allowances of CHQ and RHQ is to be excluded towards the following:
• Support services to ANS, Cargo and Commercial at CHQ, RHQ and Airports
• Officials of Directorate and Commercial
Balance 80% of pay and allowances of CHQ and RHQ can be allocated to Airports.
ii. Administration & General Expenses of CHQ and RHQ:
• AAI has incurred Legal & Arbitration Expenses at both CHQ and RHQ level. The Authority
is of the view that this expense should be analyzed and distributed to stations on a case-to-
case basis. As the above details have not been provided by AAI, the same has not been
allocated to the stations.
• AAI has paid interest/penalties to Government of India at both CHQ and RHQ levels. The
Authority is of the view that the stakeholders should not be burdened with interest/penalties
paid to Government of India, due to various lapses/delays on the part of the Airport
Consultation Paper No. 01/2024-25 Page 57 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Operator. Hence such expenses have not been allocated to the airports.
Additionally, it was observed that the CHQ/RHQ overhead expense for FY21-22 was
determined through escalation of 5% over the previous year value and the same was
considered for full year. The CHQ/RHQ overhead expense for FY21-22 up to COD was
thus recomputed through suitable ratio determined as per the actual number of days.
Based on the above methodology, the Authority has derived the revised CHQ and RHQ
expenses for the Second Control Period and Pre-COD period, which is proposed to be allocated
to LGBIA, as part of True up of the Second Control Period and Pre-COD period.
Table 30: CHQ/ RHQ expenses proposed by the Authority as part of True up of O&M expenses for the
Second Control Period and pre-COD period
(₹ crores)
Particulars FY FY FY FY FY Total FY Total
2016-17 2017-18 2018-19 2019-20 2020-21 till 2021- till
FY21 22* COD
As per AAI
CHQ/RHQ Overhead 11.13 32.28 40.22 55.83 42.54 182.00 44.67 226.67
expenses as per AAI (A)
Aeronautical component as 10.57 30.67 38.21 53.04 40.41 172.90 42.43 215.33
per AAI (95%) (B)
As per Study
Total CHQ/RHQ Overhead 20.31 25.23 30.83 45.73 34.86 156.96 19.15 176.11
expenses after rationalisation
as per Study (C)
Total Impact (D = C – B) 9.74 (5.43) (7.38) (7.31) (5.55) (15.94) (23.28) (39.22)
* Up to COD (8th OCtober 2021)
Reference: Para 4.6.2 of the Study on Efficient Operation and Maintenance Expenses for Lokpriya Gopinath
Bordoloi International Airport.
The Authority is of the view that the users should pay only for the services availed by them. Further, in
line with section 13 of the AERA Act, 2008 the Authority has a scope of determining tariff in respect
of Aeronautical services provided/ capital expenditure incurred only by that particular airport. This view
is also consistent with ICAO’s principle of ‘Cost-relatedness’. Based on the above principles, the
Authority has rationalized the CHQ/ RHQ expenses being allocated to Lokpriya Gopinath Bordoloi
International Airport. The Authority feels that the allocation of CHQ & RHQ expenses by AAI on the
basis of revenue is high, as it brings large variation in such expenses Year on Year, due to change in
revenue and is against the basic principle of cost relatedness in tariff determination. Further, as the
revenue from these airports goes up due to higher tariffs, it further leads to higher allocation of
CHQ/RHQ expenses with chain of cascading effect. The Authority, therefore, expects AAI to examine
these issues in detail and devise an effective and efficient method for allocation of CHQ & RHQ
expenses on priority.
Further, the Authority feels that AAI should exploit the potential of its non-aeronautical avenues fully
so that 30% of the same, by cross subsidisation can be used to cover Aeronautical expenses.
4.9.6 The total year-wise adjustment of AAI’s Aeronautical O&M expenses as a result of the adjustments and
reallocations proposed by the Authority in previous sections have been summarized below:
Consultation Paper No. 01/2024-25 Page 58 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Table 31: Impact of proposed reallocation of AAI’s Aeronautical O&M expenses as per the independent
study conducted by the Authority
(₹ crores)
O&M expenses FY FY FY FY FY Total FY Total
2016-17 2017-18 2018-19 2019-20 2020-21 till 2021- till
FY21
22* COD
Employee benefit
(0.02) (0.02) (0.00) (0.05) (0.07) (0.16) (0.02) (0.18)
/ Payroll
Administrative
9.60 (5.73) (7.56) (7.64) (5.79) (17.12) (23.45) (40.57)
and General
Repairs &
(0.09) (0.20) (0.09) (0.16) (0.23) (0.76) (0.23) (0.99)
Maintenance
Utilities &
(0.01) (0.01) (0.02) (0.04) (0.02) (0.09) (0.01) (0.10)
Outsourcing
Other Outflows 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total 9.48 (5.96) (7.67) (7.89) (6.11) (18.13) (23.71) (41.84)
* Up to COD (October 8, 2021)
4.9.7 Based on the recommendations, with respect to reclassification and changes in allocation ratio, of the
independent study commissioned by the Authority through Independent Consultant, the proposed
Aeronautical O&M expenses for the period FY 2016-17 up to COD is summarized in the table below:
Table 32: Aeronautical O&M expenses considered by the Authority for True up of the Second Control
Period and Pre-COD period
(₹ crores)
O&M expenses FY FY FY FY FY Total FY Total
2016-17 2017- 2018- 2019-20 2020-21 till 2021- till
18 19 FY21
22* COD
O&M Expenses as per AAI
Employee benefit / 16.64 24.02 32.05 32.42 26.69 131.82 14.80 146.62
Payroll
Administrative and 13.95 35.45 42.92 59.68 49.81 201.82 48.43 250.25
General
Repairs & 7.72 15.56 12.90 13.97 12.26 62.42 7.57 69.98
Maintenance
Utilities & 4.46 5.03 6.05 6.16 5.12 26.81 3.00 29.81
Outsourcing
Other Outflows 0.73 0.91 0.78 0.94 0.09 3.44 0.08 3.52
Total 43.49 80.97 94.70 113.17 93.97 426.29 73.88 500.19
O&M Expenses as per Study
Employee benefit / 16.62 24.00 32.05 32.37 26.62 131.66 14.78 146.44
Payroll
Administrative and 23.56 29.71 35.36 52.05 44.03 184.70 24.99 209.69
General
Repairs & 7.63 15.37 12.82 13.81 12.03 61.66 7.33 68.99
Maintenance
Utilities & 4.45 5.02 6.03 6.12 5.10 26.72 2.99 29.71
Outsourcing
Other Outflows 0.73 0.91 0.78 0.94 0.09 3.44 0.08 3.52
Total 52.97 75.01 87.03 105.28 87.86 408.16 50.17 458.34
Impact 9.48 (5.96) (7.67) (7.89) (6.11) (18.13) (23.71) (41.84)
Consultation Paper No. 01/2024-25 Page 59 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
* Up to COD (October 8, 2021)
4.10 True up of Non-aeronautical revenue
4.10.1 AAI as part of true up submission vide letter dated 6th July’2023 submitted actual Non-aeronautical
revenue earned by LGBIA for the Second Control Period and Pre-COD period. The details of head wise
Non Aeronautical Revenue achieved are as follows:
Table 33: Non-aeronautical revenue submitted by AAI for SCP and up to Pre-COD period
(₹ crores)
Particular FY’17 FY’18 FY’19 FY’20 FY’21 Total FY’22 Total
till till till
FY’21 COD COD
Trading Concessions
Restaurant/Snack Bar 1.22 1.17 7.14 16.47 4.41 30.41 0.49 30.89
TR Stalls 2.05 2.96 5.48 10.98 3.23 24.70 0.93 25.63
Hoarding & Displays 2.08 2.75 3.49 4.93 1.50 14.75 0.93 15.68
Sub Total 5.35 6.89 16.11 32.38 9.13 69.86 2.35 72.21
Rent & Services
Building Residential 0.02 0.02 0.04 0.08 0.03 0.19 0.01 0.21
Building Non-Residential 8.08 (3.06) 7.13 7.73 6.80 26.67 5.27 31.94
Hanger Rent 8.74 5.81 1.48 2.39 1.83 20.26 0.62 20.88
Land Lease 0.03 0.04 0.01 0.01 0.01 0.10 0.02 0.22
Sub Total 16.87 2.82 8.66 10.20 8.67 47.22 5.92 53.15
Miscellaneous
Car Parking 2.27 3.98 5.03 5.27 0.79 17.35 0.60 17.95
Admission ticket 0.32 0.59 0.33 0.16 0.08 1.49 0.07 1.56
Flight Catering 0.33 0.49 0.80 0.51 0.23 2.36 0.07 2.43
Interest Income 0.12 0.15 0.19 0.22 0.16 0.84 0.10 0.94
Other Misc Receipts 1.88 0.63 0.94 1.08 4.84 9.36 0.82 10.19
Sale of Scrap 0.31 0.08 0.26 0.49 0.29 1.42 0.38 1.81
Sub Total 2.96 1.94 2.53 2.46 5.59 15.48 1.44 16.92
Total 27.45 15.63 32.33 50.31 24.19 149.91 10.31 160.21
4.10.2 The Authority compared the actual Non-aeronautical revenue submitted by AAI as per Table 33 with
the projections given in the Tariff Order for the Second Control Period and the same is as follows:
Table 34: Comparison of Actual NAR with Projections submitted by AAI for the Second Control Period
and Pre-COD period
(₹ crores)
Total FY’22 Total
Particulars FY’17 FY’18 FY’19 FY’20 FY’21 till till till
FY’21 COD COD
NAR Projections as 12.20 13.30 14.50 15.80 17.30 73.10 - 73.10
per Tariff Order for the
Second Control Period
(A)
Actual NAR as per 27.45 15.63 32.33 50.31 24.19 149.91 10.31 160.21
AAI’s submission (B)
Variance (B-A) 15.25 2.33 17.83 34.51 6.89 76.81 - -
4.10.3 The Authority notes that the Non-Aero Revenue in Second Control Period is 105.10% higher than the
Consultation Paper No. 01/2024-25 Page 60 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Non-Aero Revenue approved by the Authority as part of Second Control Period Order. In this respect,
the Authority recalls its decision no. 9.c vide Tariff No. 38/ 2017-18 which states as follows: “The
Authority decides that Non-Aeronautical revenues will be trued up if it is higher than the projected
revenues. In case there is a shortfall, true up would be undertaken only if the Authority is satisfied that
there are reasonably sufficient grounds for not realizing the projected revenues”.
4.10.4 The Authority vide email dated April 10, 2024, requested AAI to share the details regarding “Space
rentals collected from Airlines”. AAI, in its response dated April 22, 2024, has provided the following
details:
Table 35: “Space rentals collected from Airlines” as submitted by AAI
(₹ crores)
SCP Pre-
Total
Particulars FY17 FY18 FY19 FY20 FY21 Total COD
(A+B)
(A) (B)
Space Rent from Airlines 0.79 1.28 1.39 1.41 1.01 5.89 0.29 6.18
4.10.5 The Authority is of the view that space rentals from agencies providing aeronautical services should be
treated as Aeronautical Revenue. Hence, the Authority proposes to consider “Space rentals collected
from Airlines” amounting to ₹ 6.18 crores as Aeronautical Revenue.
4.10.6 Based on its analysis, the Authority proposes to consider the actual Non-aeronautical Revenue as given
in the table below for true up of AAI for the Second Control Period and Pre-COD period.
Table 36: Total Non-Aeronautical revenue as per Authority for the Second Control Period and Pre-COD
period
(₹ crores)
Particular FY’17 FY’18 FY’19 FY’20 FY’21 Total till FY’22 Total
FY’21 till COD till
COD
Actual NAR as per AAI 27.45 15.63 32.33 50.31 24.19 149.91 10.31 160.21
submission
Less Space Rentals collected 0.79 1.28 1.39 1.41 1.01 5.89 0.29 6.18
from Airlines (B) (refer Para
4.11.5)
Total Non-Aero Revenue (A- 26.66 14.35 30.94 48.90 23.18 144.02 10.02 154.03
B)
4.11 True up of Aeronautical Revenue
4.11.1 AAI as part of true up submission vide letter dated 6th July’2023 submitted actual Aeronautical revenue
earned by LGBIA for Second Control Period and the Pre-COD period, following are the details of actual
Aeronautical Revenue as per AAI for true up period:
Table 37: Aeronautical revenue as per AAI for the Second Control Period and Pre-COD period
(₹ crores)
Particulars FY’17 FY’18 FY’19 FY’20 FY’21 Total FY’22 Total
till till till
FY’21 COD COD
Landing Charges -Domestic (A1) 30.30 36.56 40.74 37.88 21.56 167.05 12.73 179.78
Landing Charges- Intl. (A2) 0.60 0.40 0.55 0.63 0.02 2.20 (0.01) 2.20
Total Landing Charges (A=A1+A2) 30.90 36.97 41.29 38.52 21.58 169.25 12.72 181.97
Housing & Parking Charges (B) 0.12 0.28 0.57 0.60 1.56 3.14 0.56 3.69
Consultation Paper No. 01/2024-25 Page 61 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Particulars FY’17 FY’18 FY’19 FY’20 FY’21 Total FY’22 Total
till till till
FY’21 COD COD
PSF-Domestic (C1) 0.06 0.00 0.00 0.00 0.00 0.06 0.00 0.06
PSF-Intl.(C2) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total PSF (C=C1+C2) 0.06 0.00 0.00 0.00 0.00 0.06 0.00 0.06
Fuel Throughput (D) 1.17 1.22 1.68 1.23 0.00 5.30 0.00 5.30
Extn. Of Service Hours (E) 0.11 0.10 0.00 0.00 0.12 0.32 0.10 0.42
Ground Handling Services (F) 1.47 1.60 1.89 1.54 2.64 9.14 0.60 9.74
UDF-Domestic (G1) 59.29 74.98 106.40 107.32 44.15 392.14 25.16 417.30
UDF-Intl. (G2) 0.39 0.26 0.47 0.31 0.07 1.50 0.04 1.55
Revenue from AAICLAS (H) 0.00 0.18 0.52 0.61 0.51 1.81 0.40 2.21
Cargo Revenue (I) 0.29 0.00 0.00 0.00 0.00 0.29 0.00 0.29
Land Lease from Oil Companies (J1) 1.02 1.02 1.02 1.02 1.02 5.11 1.03 6.14
Land Lease from GHA (J2) 0.12 0.07 0.01 0.25 0.17 0.62 0.13 0.75
Cute Charges (K) 2.11 2.23 4.29 4.65 1.83 15.10 0.99 16.10
Total Revenue 97.05 118.91 158.14 156.04 73.65 603.79 41.73 645.52
4.11.2 Table 37 is compared with the Aeronautical revenue considered in the Tariff Order for the Second
Control Period and the same is as follows:
Table 38: Comparison of Actual Aeronautical revenue and Projections submitted by AAI for the Second
Control Period and Pre-COD Period
(₹ crores)
Particulars FY’17 FY’18 FY’19 FY’20 FY’21 Total FY’22 Total
till till till
FY’21 COD COD
Aeronautical revenue 96.00 122.80 140.70 161.30 184.80 705.60 - -
Projections as per Tariff
Order for the Second
Control Period (A)
Actual Aeronautical 97.05 118.91 158.14 156.04 73.65 603.79 41.73 645.52
revenue (B)
Variance (B-A) 1.05 (3.89) 17.44 (5.26) (111.15) (101.81) - -
4.11.3 The Authority notes that the Actual Aeronautical revenue in FY 2020-21 is at a significant variance
from the projected Aeronautical revenue, which is attributable to lower passenger traffic and ATM due
to the adverse impact of the COVID-19 pandemic on the Aviation sector.
4.11.4 Further, the Authority recalls its decision no. 12.e in the Tariff Order No. 38/ 2017-18, which states that
“The Authority decides to consider shortfall/ excess in revenues for the 2nd control period based on
proposed tariffs by AAI while determining aeronautical tariffs for the 3rd control period.”
4.11.5 As observed in para 4.10.5, the Authority proposes to make certain adjustments to the aeronautical
revenue by reclassifying “Space rentals collected from Airlines” as aeronautical revenue. Hence, the
Authority proposes to recompute and consider the Aeronautical Revenue for true up of AAI for the
Second Control Period and Pre COD period as shown in the following table.
Consultation Paper No. 01/2024-25 Page 62 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
Table 39: Total Aeronautical revenue as per Authority for the Second Control Period and Pre-COD
period
(₹ crores)
Particulars FY’17 FY’18 FY’19 FY’20 FY’21 Total FY’22 Total
till till till
FY’21 COD COD
Actual Aeronautical 97.05 118.91 158.14 156.04 73.65 603.79 41.73 645.52
Revenue (A)
Add: Space Rentals 0.79 1.28 1.39 1.41 1.01 5.89 0.29 6.18
collected from Airlines (B)
Total Aeronautical
97.84 120.19 159.53 157.45 74.66 609.68 42.02 651.70
revenue (A+B)
4.11.6 Based on the above, the Authority proposes to consider Aeronautical revenue inclusive of space rentals
collected from airlines for true up of the Second Control Period and pre-COD period.
4.12 True up of Taxation
4.12.1 AAI as part of true up submission submitted detail of aeronautical taxation for the Second
Control Period and Pre-COD period, same is as follows:
Table 40: Taxation submitted by AAI for the Second Control Period and Pre-COD period
(₹ crores)
Particular FY’17 FY’18 FY’19 FY’20 FY’21 Total FY’22 Total
till till till
FY’21 COD COD
Aeronautical Revenues 97.84 120.19 159.53 157.45 74.66 609.69 42.02 651.70
O&M 52.97 75.01 87.03 105.28 87.86 408.16 50.17 458.34
Interest on Working Capital - - - - - - 0.51 0.51
Depreciation as per IT Act 8.32 8.59 11.95 17.30 17.85 64.01 16.50 80.51
PBT 45.24 29.35 51.49 25.57 (38.17) 113.48 145.23 258.71
Tax for Aeronautical 15.66 10.16 17.99 6.44 0.00 50.24 0.00 50.24
Services
Corporate Tax on shortfall - - - - - - 26.95 26.95
(under recovery) to be
collected from Concessionaire
Total Tax 77.19
a. The Authority notes that AAI claimed tax of ₹ 26.95 crores on the shortfall amount of ₹ 194.40
crores which is the present value of difference between Target Revenue and Actual Aeronautical
revenue i.e. under recovery for Second Control Period and Pre-COD period (refer Table 7).
Further,in case of Jaipur International Airport, the Authority sought clarification from AAI
relating to the basis of consideration of such tax liability, AAI has provided following
clarification in this regard:
Under recovery of ARR till COD approved by AERA and thereafter recoverable from
Concessionaire will be treated as Revenue receipts and will be liable to income tax.
Jaipur Airport is one of the unit/station of AAI (Airports across India). Since AAI is dealt with
single PAN No., the tax liability of Jaipur Airport will be merged in common pool of AAI as whole
and thereafter tax liability will be paid by AAI as whole considering Income and expenses of
Airports across India including Jaipur Airport. Tax liability / tax paid computed for AAI as a whole
are not allocated to Airports.
Consultation Paper No. 01/2024-25 Page 63 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
In view of the above, the Authority observed that the AAI will be liable to pay income tax over the
under recovery reimbursed by GIAL. Since, the recovery will be of aeronautical nature, Authority
considers the same as part of ARR calculation for the true up exercise undertaken for Second Control
Period and Pre-Control Period. In corollary, the Authority also proposes to consider the reimbursement
of under recovery by the GIAL as revenue expenditure while calculating tax liability for GIAL for the
Third Control Period.
4.12.2 The Authority vide order no. 38/2017-18 dated February 16, 2018 had decided the following for taxation
in second control period:
Decision no 11.a. The Authority decides to consider the corporate tax for aeronautical activities as per
Table 45 for the 2nd Control Period.
Decision no 11.b. The Authority decides to true up the difference between the actual/ apportioned
corporate tax paid and that estimated by the Authority for the 2nd control period during determination
of tariffs for the 3rd control period.
4.12.3 In view of above, the Authority re-computed taxation amount and the same is presented in the table
below:
Table 41: Taxation proposed by the Authority for the Second Control Period and Pre-COD period
(₹ crores)
Total FY’22 Total
Particulars FY’17 FY’18 FY’19 FY’20 FY’21 till up to till
FY’21 COD COD
Revenue (A)
Aeronautical Revenue 97.84 120.19 159.53 157.45 74.66 609.68 42.02 651.70
(refer Table 39)
Total (A) 97.84 120.19 159.53 157.45 74.66 609.68 42.02 651.70
Shortfall (B)
Shortfall/ under recovery 144.31 144.31
proposed to be collected as
on COD (B) - (refer Table
41)
Expenses (C)
O&M expenses (refer Table 52.97 75.01 87.03 105.28 87.86 408.16 50.17 458.34
32)
Depreciation (as per Income 8.31 8.58 11.88 17.17 17.69 63.64 16.33 79.97
Tax Act, 1961)
Total (C) 61.28 83.59 98.91 122.45 105.55 471.79 66.50 538.29
Profit /Loss D= (A+B-C) 36.56 36.60 60.62 35.00 (30.89) 137.88 119.83 257.71
Carry forward of prior (30.89) (30.89)
period loss (E)
Net loss/profit after setting 36.56 36.60 60.62 35.00 (30.89) 137.88 88.94 226.82
off prior period losses*
(D+E)
Tax Rates 34.61% 34.61% 34.94% 25.17% 25.17% 25.17%
Tax 12.65 12.67 21.18 8.81 0.00 55.31 22.39 77.70
* The set off of prior period loss has been computed only for the purpose of determining taxes.
4.12.4 As per table above the unadjusted losses of FY’21 is adjusted while arriving taxable profit for FY’22.
The Authority proposes to consider tax as per Table 41 for True up of Second Control Period and Pre-
COD period.
Consultation Paper No. 01/2024-25 Page 64 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
4.13 True up of Aggregate Revenue Requirement (ARR) for Second Control Period and the
Pre-COD period
4.13.1 Based on its analysis of the various building blocks, the Authority has revised the Aggregate Revenue
Requirement (ARR) of LGBIA for Second Control Period and Pre-Control Period and eventually
arrived at under recovery/over recovery for LGBIA for the same period. The detailed ARR calculation
is presented in the table below:
Table 42: ARR proposed by the Authority for Second Control Period and Pre-COD Period
(₹ crores)
Total FY’22 Total
Particulars Ref FY’17 FY’18 FY’19 FY’20 FY’21 till up to till
FY’21 COD COD
Average RAB (Refer 81.41 79.55 116.71 162.13 166.43 163.23
Table 24)
Fair Rate of Return 14% 14% 14% 14% 14% 7.29%#
(FRoR)
Return on Average RAB A 11.40 11.14 16.34 22.70 23.30 84.87 11.90 96.77
@14%
Depreciation (refer Table B 7.00 7.17 9.91 13.26 13.76 51.08 7.26 58.34
24)
Operating Expenditure C 52.97 75.01 87.03 105.28 87.86 408.16 50.17 458.34
(Table 32)
Taxation (Refer Table 41) D 12.65 12.67 21.18 8.81 0.00 55.31 22.39 77.70
Carry forward of shortfall E 107.7 107.70 107.70
of First Control Period**
ARR (Sum A: E) F 191.72 105.98 134.46 150.05 124.92 707.13 91.71 798.84
Non-aeronautical revenue G 26.66 14.35 30.94 48.90 23.18 144.02 10.02 154.03
(NAR) (Refer Table 36)
Less: 30% of NAR H 8.00 4.31 9.28 14.67 6.95 43.21 3.01 46.22
Net ARR (F-H) I 183.72 101.68 125.18 135.38 117.97 663.92 88.71 752.63
Revenue from J 97.84 120.19 159.53 157.45 74.66 609.68 42.02 651.70
Aeronautical Services
(refer Table 39)
(Over recovery) / Under K 85.88 (18.51) (34.35) (22.07) 43.31 54.25 46.69 100.94
recovery (I-J)
Discount factor (@ 14%) L 1.81 1.59 1.39 1.22 1.07 1
as on October 7, 2021
PV of (Over recovery) / M 155.40 (29.38) (47.83) (26.96) 46.40 97.63 46.69 144.31
Under recovery as on
October 7, 2021* (K*L)
Discount factor @ 14% as N 1.067
on March 31, 2022
PV of (Over recovery) / O 154.00
Under recovery as on
March 31, 2022 (M*N)
Discount factor @ 12.21% P 1.122
as on March 31, 2023*
PV of (Over recovery) / Q 172.80
Under recovery as on
March 31, 2023 (O*P)
* PV factor has been derived for the FYs from FY 2016-17 till COD, by assuming the discount factor as 1 on COD
# FRoR for FY 2021-22 has been computed as 7.29% for the period up to COD
** Shortfall obtained from Tariff Order of the Second Control Period.
Consultation Paper No. 01/2024-25 Page 65 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
4.13.2 The ARR proposed by the Authority is ₹ 752.63 crores (refer Table 42), as against Rs. 794.54 crores
submitted by AAI. The variance is on account of the following:
i. Re-classification of assets, due to which there is reduction in the Return on RAB and
Depreciation derived by the Authority.
ii. Rationalization of O&M expenses, based on O&M Study report.
iii. Non-consideration of financing allowance in RAB and depreciation on financing allowance
4.14 Adjusted Deemed Initial RAB
Clause 28.11.4 of the CA states the following with respect to Adjusted Deemed Initial RAB:
“Pursuant to the payment of the Estimated Deemed Initial RAB, and upon the reconciliation, true-up
and final determination by the Regulator of the quantum of the investment under 28.11.3(a), any
surplus or deficit in the Estimated Deemed Initial RAB with respect to the Deemed Initial RAB shall
be adjusted as part of the Balancing Payment that becomes due and payable as per Clause 31.4 after
the expiry of 15 (fifteen) days from such final determination by the Regulator, with due adjustment
for the following ("Adjusted Deemed Initial RAB'"):
(a) reduced to the extent of over-recoveries, if any, of Aeronautical Revenues by the Authority until
the COD, that the Regulator would provide for as a downward adjustment while determining
Aeronautical Charges for the next Control Period; or
(b) increased to the extent of under-recoveries, if any, of Aeronautical Revenues by the Authority until
the COD, that the Regulator would provide for as an upward adjustment while determining
Aeronautical Charges for the next Control Period.
The amount(s) to be paid by the Authority or Concessionaire shall be the present value of Adjusted
Deemed Initial RAB calculated using the fair rate of return as determined by the Regulator for the
time period from the COD to the date of actual payment of the Adjusted Deemed Initial RAB.”
The Authority has derived the Adjusted Deemed Initial RAB as on COD which is as follows:
Table 43: Determination of Adjusted Deemed Initial RAB as on COD by the Authority
(₹ crores)
Particulars Ref. Amount
A. Deemed Initial RAB as on COD Table 26 158.80
B. Estimated Deemed Initial RAB Clause 28.11.3 (69.00)
(b) of CA
C. Difference (C=A-B) 89.80
D. PV of Under-recovery of AAI as on COD Table 42 144.31
E. Adjusted Deemed Initial RAB as on COD E= (C+D) 234.11
COD – 8th Oct’2021
4.14.1 In accordance with the provisions of clause 28.11.4 of the CA, AERA has computed the Adjusted
Deemed Initial RAB as on COD i.e. ₹ 234.11 crores (shown in Table 43) and derived the future value
of such Adjusted Deemed Initial RAB by applying the compounding factor of FRoR and assuming a
future expected date of payment by the Concessionaire (GIAL) to the Airports Authority of India as
follows:
i. The Authority has assumed future expected date of payment of Adjusted Deemed Initial RAB
as August 31, 2024, based on the assumption that the Tariff Order for LGBIA (wherein the
Deemed Initial RAB is finally determined by the Regulator) is issued on or before August 20,
2024.
Consultation Paper No. 01/2024-25 Page 66 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
ii. The Authority has applied a compounding factor to determine future value of the Under-
recovery as on COD by applying:
• FRoR @ 14% from COD up to March 31, 2022 and
• FRoR @ 12.21% from April 1, 2022 up to July 31, 2024 (based on the FRoR determined by
AERA for the Third Control Period for LGBIA, as discussed under Chapter 8 of this
Consultation Paper).
iii. The Adjusted Deemed Initial RAB computed as on COD, March 31, 2022, March 31, 2023,
March 31, 2024 and August 31, 2024 has been presented in the table below:
Table 44: Determination of Adjusted Deemed Initial RAB as on Specified and Future Payment Dates
(₹ crores)
Mar 31, Mar 31, Mar 31, August 31,
Particulars As on COD
2022* 2023# 2024# 2024#
Adjusted Deemed Initial RAB 234.11 249.82 280.33 314.56 330.66
*
Compounding for the period from COD up to March 31, 2022 has been done using FRoR of 14%.
# Compounding for period beyond March 31, 2022 has been done using FRoR of 12.21%, determined by AERA for
LGBIA for the First Control Period.
4.14.2 It is likely that the actual date of payment is different from August 31, 2024 as presented in the above
table. In that scenario, following formula may be used for determining the Adjusted Deemed Initial
RAB on a particular payment date:
𝐭
𝑨𝒅𝒋𝒖𝒔𝒕𝒆𝒅 𝑫𝒆𝒆𝒎𝒆𝒅 𝑰𝒏𝒊𝒕𝒊𝒂𝒍 𝑹𝑨𝑩= 𝑨 𝐱 (𝟏+𝒓 𝐱 )
𝟑𝟔𝟓
where, A = Adjusted Deemed Initial RAB computed as on March 31, 2024
r = FRoR for First Control Period, computed as 12.21% (refer Chapter 8).
t = Number of days elapsed between actual date of payment and March 31, 2024
The projection of Adjusted Deemed Initial RAB on a particular payment date is illustrated through
the following example:
Assuming that the actual date of payment is September 10, 2024, then
A = ₹ 314.56 crores
r = 12.21% or 0.1221
t = 163 days (Number of days between March 31, 2024 and September 10, 2024)
The Adjusted Deemed Initial RAB based on the above example is:
₹ 314.56 𝐱 (1+0.1221*163/ 365) = ₹ 331.71 crores.
4.14.3 The Authority has proposed the Adjusted Deemed Initial RAB as explained above and requests the
Stakeholders to provide their comments on the same.
4.14.4 The Authority proposes to consider Under recovery of ₹ 172.80 crores as on 31st March 2023 (as per
Table 41) for True up of AAI for the Pre-COD period and readjust the same in the ARR computation
of LGBIA for the Third Control Period. The under-recovery has arisen mainly on account of reduction
in aeronautical revenue resulted on account of lesser traffic due to COVID-19 pandemic in FY 2020-21
and higher allocation of CHQ/RHQ cost.
Consultation Paper No. 01/2024-25 Page 67 of 254TRUE UP OF AAI FOR THE SECOND CONTROL PERIOD FROM FY’17 TILL COD
4.15 Authority’s proposals regarding true up for SCP and pre-COD period (FY17 up to COD)
Based on the material before it and its examination, the Authority proposes the following with respect
to True up of the Pre-COD period for LGBIA:
4.15.1 To consider Deemed Initial RAB as ₹ 158.80 crores on October 8, 2021, as per Table 26
4.15.2 To consider true up of RAB for the pre-COD period as per Table 24.
4.15.3 To consider true up of depreciation for the pre-COD period as per Table 23.
4.15.4 To consider true up of FRoR for the pre-COD period as per para 4.8.
4.15.5 To consider true up of Aeronautical O&M expenses for the pre-COD period as per Table 32.
4.15.6 To consider true up of Non-aeronautical revenue for the pre-COD period as per Table 36.
4.15.7 To consider true up of Aeronautical revenue for the pre-COD period as per Table 39.
4.15.8 To consider true up of Aeronautical Taxation for the pre-COD period as per Table 41.
4.15.9 To consider true up of ARR for the pre-COD period as per Table 42.
4.15.10 To consider the present value of under recovery of ₹ 172.80 crores for True up of AAI for the Pre-COD
period as per Table 42 and readjust the same in the ARR for the Third Control Period.
4.15.11 To consider Adjusted Deemed Initial RAB as per Table 44 or based on formula provided in paragraph
4.14.2 as appropriate for actual date of payment.
Consultation Paper No. 01/2024-25 Page 68 of 254TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
5 TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
5.1 Background
5.1.1 AAI had entered into a Concession Agreement dated January 19, 2021, with Guwahati International
Airport Limited (the ‘Concessionaire’) for the Operations, Management and Development of LGBIA
for a period of 50 years from the COD, i.e. October 8, 2021. As per the Concession Agreement between
AAI and GIAL (clause 28.11.3), the amount which was due and payable by the Concessionaire to AAI,
is subject to reconciliation, true up and final determination by AERA.
5.1.2 Pursuant to the above Concession Agreement, GIAL has submitted True up workings for the period
from COD up to March 31, 2022.
5.1.3 The true up workings submitted by GIAL covers the following building blocks:
i. Traffic
ii. Capital Expenditure
iii. Aeronautical Depreciation
iv. Regulatory Asset Base
v. Fair Rate of Return
vi. Aeronautical Operation and Maintenance Expenses
vii. Non-aeronautical Revenue
viii. Aeronautical Taxes
ix. Aggregate Revenue Requirement
5.1.4 The Authority has examined GIAL’s true up submission in detail and has performed the following
analysis:
i. Recorded GIAL’s submissions for True up under different Regulatory building blocks.
ii. Provided the Authority’s examination and proposals regarding the True up calculation of each
building block of GIAL.
5.2 GIAL’s submission regarding True up for the period from COD till March 31, 2022
5.2.1 GIAL has submitted true up for the period from COD till March 31, 2022 as follows:
Table 45: True Up submitted by GIAL from COD till March 31, 2022
(₹ crores)
Particulars Amount
Opening RAB 154.77
Addition During the year 2.33
Financing Allowance -
Depreciation during the year (16.81)
Closing RAB 140.28
Average RAB 147.52
FRoR on Average RAB (@ 14% for 6 months) (A) 9.90
Operating expenses (B) 47.87
Depreciation (C) 16.81
Bank and Finance Charges (D) 0.50
Working Capital Loan Interest (E) 0.26
Independent Engineer Fee (F) -
Pre-COD Expenses (G) 9.85
Tax (H) 1.32
Consultation Paper No. 01/2024-25 Page 69 of 254TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
Particulars Amount
Gross ARR (Sum A:H) = (I) 86.51
Non-aeronautical Revenue 9.96
Less: 30% of Non-aeronautical revenue (J) (2.99)
Net ARR (I-J) = K 83.53
Actual Aero Revenues earned (L) 59.95
Shortfall/ under-recovery (K-L) = M 23.57
PV of Under-recovery 28.81
5.3 Authority’s examination of the true up submitted by GIAL for the period from COD till March
31, 2022
The Authority has examined the true up submitted by GIAL for the period from COD till March 31,
2022 as part of the tariff determination for the current Control Period.
5.4 True up of Capital Expenditure (CAPEX)
5.4.1 As part of the Concession Agreement, the Regulatory Asset Base held by AAI as on COD were
transferred to GIAL. The Authority proposes to consider the value of RAB in the hands of AAI as on
COD as Opening RAB for GIAL as per the outcome of the asset allocation study undertaken by the
Authority for Second Control Period and Pre-COD period.
5.4.2 The Authority has derived the deemed initial RAB of GIAL as on COD as ₹ 158.80 crores (refer Table
26).
5.4.3 The Authority notes that GIAL has added following additional items in RAB amounting to ₹ 2.33 crores
during the period COD till March 31, 2022:
Table 46: Additional items included in RAB by GIAL from COD till March 31, 2022
(₹ crores)
Details Amount
Software -
IT equipment 1.78
Plant and Machinery -
Furniture & fixtures 0.04
Vehicles -
Office Equipment 0.51
Total 2.33
5.4.4 Reclassification of assets of GIAL
The Authority has conducted an independent study on allocation of assets for the Second Control Period
and FY2022, and used the outcome of the study to true up the RAB for the post COD period i.e. as on
March 31, 2022 for GIAL.
The Authority has considered the adjusted RAB of GIAL as on COD (which is ₹ 158.80 crores), Capital
additions and corresponding depreciation based on the results of the Asset Allocation Study report (refer
Appendix 1 for Study on allocation of assets between Aeronautical and Non-aeronautical assets for
LGBIA).
The asset allocation study reviewed the various asset categories and developed a basis for segregation
of various assets into Aeronautical, Non-aeronautical and Common assets. Authority noted that GIAL
also procured employee related asset which needs to be allocated as per Employee Ratio. The Authority
considers the employee ratio derived as part of the Study on Efficient Operation and Maintenance
Consultation Paper No. 01/2024-25 Page 70 of 254TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
Expenses for LGBIA. As per para 5.2.3. of the said study the Employee Head Count Ratio for GIAL is
95:5 (Aeronautical: Non-aeronautical).
The Authority has reclassified assets addition made by GIAL for the period from COD till March 31,
2022, based on applicable allocation ratio. The allocation basis is detailed hereunder:
i. Furniture
Details of Asset: MS Framework and Flax
Allocation proposed by GIAL: Aeronautical
Observation: The assets such as MS Framework and Flax, have been classified as Aeronautical
assets by GIAL. However, since these assets are for the use of employees of GIAL, the same have
been reallocated in the ratio of Employee Head Count of GIAL (95:5).
Allocation proposed by the Authority: Employee Head Count Ratio
Impact: Reclassifying these assets from Aeronautical to Common decreases the RAB to the
extent of ₹ 0.002 crores.
Reference: Para 4.9 of the Asset Allocation Study report
ii. IT Equipment
Details of Asset: Laptop, Desktop, Printer, Display, Server and Storage data center, other IT
equipment, Software license and support, SITA license and project implementation
Allocation proposed by GIAL: Aeronautical
Observation: The assets such as laptops, desktops, printers, servers and storage, software license,
have been classified as Aeronautical assets by GIAL. However, since these assets are for both
aero and non-aeronautic activities of GIAL, the same have been reallocated in the ratio of
Employee Head Count of GIAL (95:5). In addition, SITA License and Project Implementation
which was classified as Aeronautical by GIAL is allowed to be considered as Aeronautical asset.
Allocation proposed by the Authority: Employee Head Count Ratio / Aeronautical
Impact: Reclassifying these assets from Aeronautical to Common decreases the RAB to the
extent of ₹ 0.05 crores.
Reference: Para 4.9 of the Asset Allocation Study report
iii. Office Equipment
Details of Asset: Video Controller, Telephone, IP Phone, Mobile, Security and Safety related
equipment and accessories, Document Tray, and other Office equipment.
Allocation proposed by GIAL: Aeronautical
Observation: All office equipment has been classified as Aeronautical assets by GIAL. However,
since these assets are for both aero and non-aeronautic activities of GIAL, the same have been
reallocated in the ratio of Employee Head Count of GIAL (95:5).
Allocation proposed by the Authority: Employee Head Count Ratio
Impact: Reclassifying these assets from Aeronautical to Common decreases the RAB to the
extent of ₹ 0.03 crores.
Reference: Para 4.9 of the Asset Allocation Study report
Consultation Paper No. 01/2024-25 Page 71 of 254TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
The following table illustrates the impact of adjustments in Asset Addition/WIP Capitalization values
due to reclassification of assets of GIAL between COD and March 31, 2022.
Table 47: Impact of Reclassification of Asset Additions by GIAL from COD till March 31, 2022
(₹ crores)
Asset Category as per MYTP Reclassification Impact
Furniture & fixtures (0.002)
IT equipment (0.05)
Office equipment (0.03)
Software -
Grand Total (0.08)
5.5 True up of Depreciation
5.5.1 For the purposes of True up submission, GIAL had calculated depreciation for the period from COD up
to March 31, 2022, based on their determination of remaining useful life.
5.5.2 The Authority has proposed to consider the same rates of depreciation as applied by AAI for the period
up to COD, on the assets transferred by AAI to GIAL for the period from COD to March 31, 2022.
Further, the assets added by GIAL have been depreciated based on the useful life prescribed under Order
No. 35/ 2017-18 dated January 12, 2018, of AERA. The Authority has proposed the useful life for all
the assets of LGBIA post COD as per Table 114
5.5.3 Depreciation has not been computed on the Intangible asset and Notional Lease Asset as the same is
excluded from the RAB.
5.5.4 Accordingly, the depreciation on Aeronautical assets of ₹ 0.33 crores as submitted by GIAL has been
revised (post reclassification) to ₹ 0.32 crores, thereby resulting a reduction in depreciation of ₹ 0.01
crores. The following table illustrates the impact on depreciation due to reclassification adjustments in
Asset Addition/WIP Capitalization values of GIAL between COD and March 31, 2022.
Table 48: Impact on Depreciation post reclassification and revised useful life by the Authority
(₹ crores)
Asset Category as per MYTP Reclassification Impact
(Period: COD till March 31, 2022)
Furniture & fixtures (0.0001)
IT equipment (0.008)
Office equipment (0.002)
Grand Total (0.010)
5.5.5 Adjustments were also made in the depreciation of the assets handed over to GIAL by AAI for the post
COD period, as per the asset reclassification carried out in the independent study conducted by the
Authority and the revised useful life as per Table 114. The total impact on depreciation in post COD
period due to reclassification of assets has been summarized in the table below.
Table 49: Depreciation impact due to Reclassification of Asset Additions (Post-COD Period)
(₹ crores)
Particulars Values Impact
Depreciation on pre-COD assets as per GIAL 16.48*
Depreciation on pre-COD assets after reclassification and revised useful life as 8.83
per the independent study conducted by the Authority
Consultation Paper No. 01/2024-25 Page 72 of 254TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
Particulars Values Impact
Impact on Depreciation for pre-COD Assets due to reclassification (7.65)
Depreciation on post-COD assets as per GIAL 0.33*
Depreciation on post-COD assets after reclassification 0.32
Impact on Depreciation for post-COD Assets due to reclassification and (0.01)
revised useful life as per the independent study conducted by the Authority
(Table 48)
Total Impact on Depreciation for all Assets in post-COD period (7.66)
*Total Depreciation of ₹ 16.81 crores split between pre-COD and post-COD assets (₹ 16.48 crores + ₹ 0.33 crores respectively)
5.5.6 The Adjusted RAB and Depreciation determined by the Authority for the period from COD till March
31, 2022, post reclassifications and other adjustments are as follows:
Table 50: Average RAB considered by the Authority from COD till March 31, 2022
(₹ crores)
Particulars Amount
Adjusted RAB as on COD, transferred to Guwahati International Airport Limited (A) (refer 158.80
Table 26)
Additions to RAB from COD to March 31, 2022, proposed by GIAL (Refer Table 46) 2.33
Sub-total (C = A + B) 161.13
Reclassifications on asset additions
Furniture & fixtures (D) (0.002)
IT equipment (E) (0.05)
Office equipment (F) (0.03)
Software (G) -
Total reclassifications (H) Sum (D : G) (0.08)
Adjusted RAB (I = C + H) 161.05
Depreciation on RAB from COD to March 31, 2022, proposed by GIAL (J) 16.81
Adjustment in Depreciation for the period from COD to March 31, 2022 (K) (Table 49) (7.66)
Total Adjusted Depreciation for the period from COD to March 31, 2022 (L=J+K) 9.15
Opening RAB as on 1st April’2022 for Third Control Period M=I –L 151.90
Average RAB M=(A+M)/2 155.35
Based on its analysis, the Authority proposes to consider CAPEX, depreciation and RAB as per Table
50 for true up of the period from COD till March 31, 2022.
5.6 True up of FRoR
5.6.1 GIAL has submitted FRoR @14% p.a. for true up of the period from COD till March 31, 2022. The
Authority proposes to consider the same, in line with the Authority’s proposal for true up of AAI from
FY 2017 to FY 2022 (up to COD) and also as approved for other similar airports. From the next Control
Period for GIAL, AERA will consider FRoR, in line with other PPP airports.
5.6.2 However, it is to be noted that GIAL has operated the Airport in FY 2021-22 only for the period from
COD till March 31, 2022. Therefore, GIAL is eligible to claim return on RAB only for the period from
COD till March 31, 2022. Hence, for FY 2021-22, the Authority proposes to pro-rate the FRoR for 175
days during which GIAL operated the Airport. The pro-rated FRoR for FY 2021-22 has been computed
as follows:
FRoR = FRoR* n/ 365
post COD
Consultation Paper No. 01/2024-25 Page 73 of 254TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
Where, FRoR is the fair rate of return for the entire FY 2021-22, FRoR is the pro-rated FRoR
post COD
for the period from COD till March 31, 2022 and n is the number of days in operation in FY 2021-22.
Based on the above approach the pro-rated FRoR for FY 2021-22 has been computed as follows:
Table 51: FRoR proposed by the Authority from COD to March 31, 2022
Particulars Value (%)
FRoR for FY’22 (A) 14%
Number of days of operations in FY’22 (B) 175
Pro-rated FRoR for FY’22 (from COD till March 31, 2022) 6.71%
(A*B/365)
5.6.3 The Authority proposes to consider FRoR for true up of the period from COD till March 31, 2022 as
6.71%, as shown in Table 51.
5.7 True up of Aeronautical O&M expenses
5.7.1 The component-wise break up of Aeronautical Operation and Maintenance expenses submitted by
GIAL for the period from COD till March 31, 2022 is as follows:
Table 52: O&M expenses submitted by GIAL for the period from COD till March 31, 2022
(₹ crores)
Expense Category Amount
Manpower expenses - AAI employees 14.19
Manpower expenses - GIAL employees 4.72
Utility expenses 2.62
IT expenses 1.49
Rates & taxes 0.32
Security expenses 1.37
Corporate Allocation 4.24
Administrative Expenses - Collection Charges on UDF 0.09
Administrative Expenses - Others 3.60
Insurance 0.99
R&M 9.71
Others 2.83
Independent Engineer Fees 1.69
Total 47.86
5.7.2 True up of Bank and Finance Charges
It is observed that GIAL has considered Bank charges as entirely Aeronautical. However, the
Authority proposes to consider the same as Common and reallocate it on Gross Fixed Assets ratio of
95.39:4.61 (Table 23 of Asset Allocation Study Report) based on the nature of expense and in line
with other similar airports. The impact of such difference is downward adjustment of ₹ 0.02 crores.
Table 53: Bank & Finance Charges considered by the Authority for Post COD Period
(₹ crores)
Consultation Paper No. 01/2024-25 Page 74 of 254TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
Particular Aero Expense
Bank and Finance Charges considered by GIAL (A) 0.50
Bank and Finance Charges considered by Authority (B) 0.48
Impact (B-A) (0.02)
5.7.3 True up of Working Capital Loan Interest
It is observed that GIAL has included Working Capital Loan Interest amount of ₹ 0.26 crores for ARR
computation as Aeronautical. As per GIAL, the working capital interest has been calculated on best
estimation basis since the ICD loan is a mix of working capital and other debt. Since, GIAL has not
provided calculations for the working capital interest, the Authority therefore proposes that cost
towards working capital loan interest cannot be considered at this stage.
5.7.4 True up of pre-COD Expenses
The Authority notes that GIAL has submitted pre-COD expenses amounting to ₹ 9.85 crores for true-
up of the post-COD period. This expense included ₹ 1.08 crores related to payroll costs.
The Authority takes cognizance of the fact that AAI deputed its staff and management personnel to
the Airport which was already in operation (being a brownfield airport) during the transition period,
including prior to the COD to ensure that the relevant knowledge and experience of the operation and
management of LGBIA is transferred to GIAL. Therefore, the deputation of such staff is relevant
towards the objective of smooth transition of the airport from AAI to GIAL, and fulfilment of the
terms of the CA.
Furthermore, the Authority also notes that as per Clause 15.1.2 of the Concession Agreement, the
Concessionaire is mandated to achieve COD within 180 days from the date of the Concession
Agreement.
Further, the Authority notes that as per clause 16.5 of the Concession Agreement, the Concessionaire
team had to work in tandem for a period of sixty (60) days prior to COD with AAI’s team to
understand the airport operations.
Based on the above factors, the Authority notes that AAI deputed its staff and management personnel
to the Airport during the transition period, including prior to the COD and the cost of such personnel
was paid by the Airport Operator. Additionally, Adani Group also deputed its own manpower from
other group entities. The Authority has accordingly decided to consider salary expenses pertaining to
such Adani Group entities for the period of six months prior to COD, i.e., from 8th April 2021 to 7th
October 2021. Further, the salary costs of GIAL’s employees for the period 8th August 2021 to 7th
October 2021 has been considered for the purpose of tariff determination.
The Authority proposes to consider only this manpower cost for true-up based on the following:
• The Authority, after making a detailed study on the provisions of the Concession Agreement,
decided that there is no provision in the Concession Agreement to include in the true up, the
remaining costs incurred by GIAL prior to Letter of Award (LoA). It is to be noted that the bid
expenses incurred prior to the date of LoA cannot be considered as pass-through expense by the
Authoirty.
• The Authority proposes that the bid expenses incurred prior to the date of Letter of Award of
GIAL, and expenses incurred between the date of Concession Agreement and COD (other than
as specifically considered above), as submitted by GIAL are not considered for tariff
determination.
Consultation Paper No. 01/2024-25 Page 75 of 254TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
Based on the above considerations, the total costs pertaining to manpower cost prior to COD, as
allowed for the purpose of true-up of LGBIA is as follows:
Table 54: Pre-COD expenses proposed by the Authority for the Third Control Period
(₹ crores)
Particular Nature of expense Total % Proposed Pre-
Allowable COD Expense
Expense till Letter of Award- Corporate Cost Allocation 1.72 NIL -
setting up Airport business
Project Cost for setup for Airport Corporate Cost Allocation 1.86 NIL -
Business - Allocation by parent
companies
Other Preliminary expense prior Incurred by GIAL 5.19 NIL -
to COD
Pre-COD Payroll Cost On roll employee cost 1.08 100% 1.08
Total 9.85 1.08
5.7.5 Reallocation of O&M expenses
The Authority has conducted an independent study to determine efficient Aeronautical Operation and
Maintenance costs for the period FY 2016-17 till FY 2021-22 and used the outcome of the study to
true up the O&M expenses for the period from COD till March 31, 2022 for GIAL.
All O&M expenses have been allocated as Aeronautical by GIAL. The Authority has analyzed the
submission made by GIAL on a case-to-case basis and applied appropriate re-classification and re-
allocation of the expenses, wherever it noted any discrepancies in the allocation of expenses by GIAL
(refer Table 41 for Allocation of O&M expenses of Airport Operator as per the Study on Efficient
Operation and Maintenance Expenses for Lokpriya Gopinath Bordoloi International Airport).
Accordingly, the following expenses have been re-allocated by the Authority by using appropriate
ratios such as Terminal Building ratio, Gross Fixed Assets ratio, Employee Head Count ratio and
Electricity ratio (Refer para 5.3 of the Study report on Efficient Operation and Maintenance Expenses
for Lokpriya Gopinath Bordoloi International Airport regarding the ratios used by the Authority for
allocation of common expenses.)
i. Manpower expenses
Manpower expenses – AAI employees
Observation: The Authority notes that pursuant to Clause 6.5 of the Concession Agreement read
with Clause 28.4.3 entered into between AAI and Guwahati International Airport Limited, the
cost of AAI employees deputed at LGBIA shall be eligible for pass-through in the determination
of Aeronautical charges. The Authority notes that GIAL has considered the Manpower expenses
as 100% Aeronautical. However, the Authority proposes to re-allocate the same in the ratio of
Employee Head Count of AAI employees (99.19:0.81), resulting in a downward adjustment of ₹
0.11 crores.
Impact: The impact of the re-allocation results in reduction of Manpower expenses by ₹ 0.11
crores for the period from COD till March 31, 2022.
Reference: Para 5.4.1 of the Study on Efficient Operation and Maintenance Expenses for
Lokpriya Gopinath Bordoloi International Airport.
Manpower expenses – GIAL employees
Consultation Paper No. 01/2024-25 Page 76 of 254TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
Observation: It is observed that the total manpower expenses of the employees of GIAL have
been considered as 100% Aeronautical. However, the Authority proposes to allocate the total
manpower expenses of GIAL based on GIAL’s Employee Ratio of 95:5. The impact of such
difference is downward adjustment of ₹ 0.24 crores.
Impact: The impact of the re-allocation results in reduction of Manpower expenses by ₹ 0.24
crores for the period from COD till March 31, 2022.
Reference: Para 5.4.1 of the Study on Efficient Operation and Maintenance Expenses for
Lokpriya Gopinath Bordoloi International Airport.
ii. Corporate Allocation Cost
Observation: It is observed that the Aeronautical Corporate Allocation Cost of ₹ 4.24 crores had
been incurred by GIAL towards Corporate Support Services received from the Companies,
namely, Adani Enterprises Limited (AEL) and Adani Airports Holding Limited (AAHL) for the
period from Post-COD till March 31, 2022. This cost includes ₹ 2.07 crores from AAHL and ₹
2.17 Crore from AEL.
AAHL has been referred as one of the Concessionaire for all NAR activites and the services
provided by AAHL & AEL are mainly in the nature of provided specialised resources and
knowledge which benefits the whole airport ecosystem, therefore the cost needs to be allocated
in the same ratio as the employee cost of GIAL manpower cost has been allocated. The impact
of such difference is a decrease of ₹ 0.21 crores
Further, it is noted that the Corporate Allocation Cost claimed by GIAL includes an amount of ₹
0.03 crores allocated towards In-house Legal department, which is in addition to the cost of one
(01) employee of Legal department, already considered under the manpower expenses of GIAL
and is not justified. Hence, the Study proposes to exclude this ₹ 0.03 crores from the Corporate
Allocation cost submitted by GIAL.
Impact: The impact of the reallocation results in reduction of Corporate Allocation expenses by
₹ 0.24 crores for the period from COD till March 31, 2022.
Reference: Para 5.4.2 of the Study on Efficient Operation and Maintenance Expenses for
Lokpriya Gopinath Bordoloi International Airport.
iii. Administrative Expenses - Others
Observation: GIAL has submitted administrative expenses of ₹ 3.58 crores incurred towards
Professional & Consultancy, Travelling & Conveyance, Auditing and Miscellaneous expenses
and has considered these expenses as 100% Aeronautical. The Authority proposes to reallocate
these expenses based on Gross Fixed Asset ratio (95.39:4.61) / revised Employee Head Count
Ratio (95:5) / revised Terminal Building ratio (89.02:10.98) depending upon the nature of
expenses and also consider AOCC services as Aeronautical, in line with the ratio allocation
followed for AAI up to COD.
Impact: The impact of such reallocation is a decrease of ₹ 0.16 crores for the period from COD
till March 31, 2022.
Reference: Para 5.4.3 of the Study on Efficient Operation and Maintenance Expenses for
Lokpriya Gopinath Bordoloi International Airport.
Consultation Paper No. 01/2024-25 Page 77 of 254TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
iv. Repair and Maintenance Expenses
Observation: GIAL has incurred an amount of ₹ 9.71 crores towards Repairs & Maintenance
which includes maintenance of various assets and has considered these expenses as 100%
Aeronautical. The Authority proposes to reallocate these expenses based on Gross Fixed Asset
ratio (95.39:4.61) / revised Employee Head Count Ratio (95:5) / revised Terminal Building ratio
(89.02:10.98) depending upon the nature of expenses.
Impact: The impact of such reallocation is a decrease of ₹ 0.42 crores for the period from COD
till March 31, 2022.
Reference: Para 5.4.4 of the Study on Efficient Operation and Maintenance Expenses for
Lokpriya Gopinath Bordoloi International Airport.
v. Other Operating Expenses such as IT, Rates & Taxes, Insurance etc.
Observation: It is observed that the Other Operating expenses totalling to ₹ 7.59 crores includes
amount incurred towards IT expenses, Rates & Taxes, Security expenses, Collection Charges,
Insurance, Outsource manpower, Housekeeping, Bank & Finance Charges. GIAL has considered
Other Operating expense as 100% Aeronautical. The Authority proposes to reallocate these
expenses based on the Gross Fixed Asset ratio (95.39:4.61) / revised Employee Head Count Ratio
(95:5) / revised Terminal Building ratio (89.02:10.98) depending upon the nature of expenses.
Impact: The impact of the reallocation results in reduction of Other Operating Expenses by ₹
0.45 crores for the period from COD till March 31, 2022.
Reference: Para 5.4.5 of the Study on Efficient Operation and Maintenance Expenses for
Lokpriya Gopinath Bordoloi International Airport.
vi. The impact on the Aeronautical O&M expenses of GIAL on account of the proposed reallocation
of expenses is as follows:
Table 55: Impact of proposed reallocation of GIAL’s Aeronautical O&M expenses
(₹ crores)
Particular Net Impact
Manpower expenses - AAI employees (0.11)
Manpower expenses - GIAL employees (0.24)
Corporate Allocation (0.24)
Administrative Expenses – Others (0.16)
R&M (0.42)
Other Operating Expenses (0.45)
Total (1.65)
5.7.6 Based on the above adjustments and reclassification, the revised Aeronautical O&M expenses
considered by the Authority for the period from COD to March 31, 2022 is summarized in the table
below:
Table 56: Reallocated Aeronautical O&M expenses of GIAL from COD to March 31, 2022
(₹ crores)
Particular Aero Expense
Manpower expenses - AAI employees 14.08
Manpower expenses - GIAL employees 4.48
Utility expenses 2.62
Consultation Paper No. 01/2024-25 Page 78 of 254TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
Particular Aero Expense
IT expenses 1.41
Rates & taxes 0.31
Security expenses 1.37
Corporate Allocation 4.00
Administrative Expenses - Collection Charges on UDF 0.09
Administrative Expenses - Others 3.42
Insurance 0.94
R&M 9.29
Others 2.52
Independent Engineer Fees 1.69
Total 46.22
5.8 True up of Non-aeronautical revenue (NAR)
5.8.1 GIAL has submitted the following components of NAR for the period from COD till March 31, 2022,
which the Authority has verified with the Books of Account of GIAL.
Table 57: NAR submitted by GIAL for True up from COD till March 31, 2022
(₹ crores)
Particulars Revenue
Car parking 0.34
Lounge -
Building rent 1.99
Other Income 0.63
Revenue from other than master concessionaire -
Master Concessioner 7.00
Total Non-aero revenue 9.96
5.8.2 The Authority, on verification of the NAR of GIAL, notes that ₹ 0.16 crores relate to space rentals from
airlines. The Authority is of the view that space rentals from agencies providing aeronautical services
should be treated as aeronautical revenue. The authority, therefore, proposes to exclude Space Rentals
from airlines providing aeronautical services from the NAR for the post-COD period.
5.8.3 The Authority proposes to consider NAR for the period from COD till March 31, 2022 as per table
below:
Table 58: NAR proposed by the Authority for True up from COD till March 31, 2022
(₹ crores)
Particulars Amount
Actual Non-Aeronautical Revenue as submitted by GIAL (A) 9.96
Less: Revenue from space rentals from airlines (B) 0.16
Non-Aeronautical Revenue as per the Authority (A-B) 9.80
5.9 True up of Aeronautical Revenue
5.9.1 GIAL has submitted the following components of Aeronautical Revenue for the period from COD till
March 31, 2022, which the Authority through its independent consultant has verified with the Books of
Consultation Paper No. 01/2024-25 Page 79 of 254TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
Account of GIAL and noted the same to be in order. The same is presented in the Table below:
Table 59: Aeronautical Revenue submitted by GIAL for True up from COD till March 31, 2022
(₹ crores)
Particulars Revenue
Landing revenue 16.49
Parking & housing revenue 0.28
Ground handling charges 0.78
Passenger UDF revenue 40.17
CUTE Revenue 1.71
CGF rentals 0.52
Cargo/Fuel/Other -
Total Aero revenues 59.95
5.9.2 The Authority proposes to include space rental from airlines amounting to ₹ 0.16 crores as aeronautical
revenue. (refer para 5.8.2).
5.9.3 The Authority proposes to consider revised Aeronautical Revenue for the period from COD till 31st
March 2022 as per table given below:
Table 60: Aeronautical Revenue proposed by the Authority for True up from COD till March 31, 2022
(₹ crores)
Particulars Amount
Actual Aeronautical Revenue as submitted by GIAL (A) 59.95
Add: Revenue from space rentals from airlines (B) 0.16
Aeronautical Revenue as per the Authority (A+B) 60.11
5.10 True up of Taxation
GIAL has submitted Aeronautical Tax of ₹ 1.32 crores for the period from COD till March 31, 2022.
Based on the proposals on various building blocks, revised calculation of taxation is presented in the
table below:
Table 61: Taxation proposed by the Authority for true up (COD till 31st March 2022)
(₹ crores)
Particulars Ref. Amount
Aero Revenues (refer Table 60) A 60.11
Aero O&M Expenses (refer Table 56) B 46.22
Bank & Finance Charges (refer Table 53 ) C 0.48
Interest Expense D 2.55
Depreciation as per IT Act E 9.25
Aero Profit Before Tax G=A-(B+C+D+E) 1.61
Previous loss adjustment H -
Taxable Profit I=MAX (0, (G-H)) 1.61
Tax rate (%) J 25.17%
Aeronautical Tax K=I*J 0.41
Consultation Paper No. 01/2024-25 Page 80 of 254TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
5.11 True up of Aggregate Revenue Requirement (ARR) for period from COD till March 31, 2022
5.11.1 Based on its analysis of the various building blocks, the Authority has determined the ARR and Shortfall
(Under recovery) for True up of the Pre-COD period and same is presented in the table below:
Table 62: ARR and Shortfall proposed by the Authority (COD till March 31, 2022)
(₹ crores)
Particulars Ref. Amount
Average RAB (refer Table 50) 155.35
FRoR on Average RAB (@ 14% for 175 days) A 10.43
Operating expenses (Refer Table 56) B 46.22
Bank and Finance Charges (refer Table 53) C 0.48
Pre COD Expenses (refer Table 54) D 1.08
Depreciation (refer Table 50) E 9.15
Tax F 0.41
ARR (Sum (A:F)) G 67.76
Non-aeronautical revenue (refer Table 58) H 9.80
Less: 30% of Non-aeronautical revenue I 2.94
Net ARR (G-I) J 64.82
Actual Aeronautical Revenue (refer Table 60) K 60.11
Shortfall/ under-recovery (J-K) L 4.71
Discount factor as on March 31, 2022 M 1
PV of (Under) / Over recovery as on March 31, 2022 N 4.71
(L*M)
Discount factor (@ 12.21%) as on March 31, 2023 O 1.122
PV of (Under)/Over recovery as on March 31, P 5.29
2023= O*N
5.11.2 The Authority proposes to consider under recovery of ₹ 5.29 crores for the post-COD period. The
Authority also proposes to consider the same as a post-COD true up while calculating ARR of LGBIA
for the Third Control Period.
5.11.3 The net ARR proposed by the Authority is ₹ 64.82 crores (refer Table 62), as against ₹ 83.53 crores
(refer Table 45) submitted by GIAL. The variance is on account of the following
i. Re-classification of assets, due to which there is reduction in the Return on RAB and Depreciation
derived by the Authority.
ii. Revision in Useful Life of Assets considered by the Authority,
iii. Rationalization of O&M expenses claimed by GIAL,
iv. Exclusion of certain expenses such as working capital loan interest and Pre-COD expenses
5.12 Authority’s proposal regarding True up for the period from COD till March 31, 2022
Based on the material before it and its examination, the Authority proposes the following with respect
to True up of the period from COD till March 31, 2022 for LGBIA:
5.12.1 To consider true up of CAPEX, depreciation and RAB for the period from COD till March 31, 2022 as
per Table 50.
5.12.2 To consider true up of FRoR for the period from COD till March 31, 2022 as per Table 51.
Consultation Paper No. 01/2024-25 Page 81 of 254TRUE UP OF GIAL FOR THE PERIOD FROM COD TILL MARCH 31, 2022
5.12.3 To consider true up of Aeronautical O&M expenses for the period from COD till March 31, 2022 as
per Table 56.
5.12.4 To consider true up of Non-aeronautical revenue for the period from COD till March 31, 2022 as per
Table 58.
5.12.5 To consider true up of Taxation for the period from COD till March 31, 2022 as per Table 61.
5.12.6 To consider true up of Aeronautical revenue for the period from COD till March 31, 2022 as per Table
60.
5.12.7 To consider under recovery of ₹ 5.29 crores as per Table 62 for Post-COD period to be considered while
calculating the ARR for the Third Control Period.
Consultation Paper No. 01/2024-25 Page 82 of 254TRAFFIC PROJECTIONS FOR THE THIRD CONTROL PERIOD
6 TRAFFIC PROJECTIONS FOR THE THIRD CONTROL PERIOD
6.1 GIAL’s submission regarding Traffic projections for the Third Control Period
6.1.1 The historical passenger traffic4 and ATM at the Airport has been shown in the table below:
Table 63: Historical passenger, ATM and Cargo traffic at LGBIA
Passenger (in Nos.) ATM (in Nos.) Cargo (in MT)
Year
Domestic Internatio Combined Domestic Internatio Combined Domestic Internatio Combined
nal nal nal
Traffic
2010-11 1,920,227 14,523 1,934,750 26,715 226 26,941 8,520 - 8,520
2011-12 2,217,820 26,864 2,244,684 27,636 452 28,088 7,761 - 7,761
2012-13 2,055,128 21,810 2,076,938 26,522 416 26,938 5,919 94 6,013
2013-14 2,171,912 25,721 2,197,633 26,604 494 27,098 7,871 36 7,907
2014-15 2,206,037 27,564 2,233,601 26,397 474 26,871 10,445 15 10,460
2015-16 2,752,418 31,897 2,784,315 28,913 512 29,425 15,617 11 15,628
2016-17 3,759,494 30,162 3,789,656 37,383 490 37,873 17,283 3 17,286
2017-18 4,636,604 31,449 4,668,053 40,668 504 41,172 22,343 2 22,345
2018-19 5,714,561 31,067 5,745,628 49,845 643 50,488 23,813 27 23,840
2019-20 5,422,289 35,160 5,457,449 44,539 1,000 45,539 21,267 3 21,270
2020-21 2,188,767 368 2,189,135 23,422 20 23,442 15,933 18 15,951
2021-22 3,148,940 16 3,148,956 33,564 8 33,572 21,814 44 21,858
2022-23 5,039,315 12,165 5,051,480 45,701 208 45,909 22,823 - 22,823
6.1.2 The passenger traffic, ATM and cargo traffic along with their expected annual growth rates, as submitted
by GIAL for the Third Control Period are as given in the table below: follows:
Table 64: Traffic and growth (%) Y-o-Y proposed by GIAL
Passenger (in Nos.) ATM (in Nos.) Cargo (in MT)
Year
Domestic Internati Combined Domestic International Combined Domestic International Combined
onal
Traffic
2022-23 5,039,315 12,165 5,051,480 45,701 208 45,909 22,823 0 22,823
2023-24 6,473,222 69,797 6,543,019 58,773 1,197 59,970 24,293 3 24,296
2024-25 6,596,891 67,022 6,663,913 59,356 1,171 60,527 23,699 1,300 24,999
2025-26 7,430,971 113,091 7,544,062 66,498 1,552 68,050 27,126 1,400 28,526
2026-27 8,958,026 136,180 9,094,207 80,216 1,893 82,109 33,301 1,500 34,801
Total 34,498,425 398,255 34,896,681 310,544 6,021 316,565 131,242 4,203 135,445
Growth rates
2022-23 - - - - - - - - -
2023-24 28.45% 473.75% 29.53% 28.60% 475.48% 30.63% 6.44% - 6.45%
2024-25 1.91% -3.98% 1.85% 0.99% -2.17% 0.93% -2.44% - 2.89%
2025-26 12.64% 68.74% 13.21% 12.03% 32.54% 12.43% 14.46% 7.69% 14.11%
2026-27 20.55% 20.42% 20.55% 20.63% 21.97% 20.66% 22.76% 7.14% 22.00%
6.1.3 GIAL has also submitted that it expected to process certain cargo volumes out of the total volume at
its own cargo facility. The following table summarizes the total cargo volumes proposed to be handled
by GIAL out of the total cargo traffic at LGBIA during the Third Control Period.
4 Source: Traffic News from AAI website
Consultation Paper No. 01/2024-25 Page 83 of 254TRAFFIC PROJECTIONS FOR THE THIRD CONTROL PERIOD
Table 65: Cargo volumes to be handled by GIAL out of the total cargo traffic during the Third
Control Period
Particulars (in MT) FY 23 FY 24 FY 25 FY 26 FY 27
Domestic - Interim Facility - 3,500 4,500 5,500 -
International – Interim Facility - - - - -
New Integrated Cargo Terminal - - - - 30,000
Total by GIAL (A) - 3,500 4,500 5,500 30,000
Total Cargo Traffic at LGBIA (B) - 24,296 24,999 28,526 34,801
% Share (A/B)*100 - 14% 18% 19% 86%
6.1.4 GIAL had engaged an independent agency – M/s Mott Macdonald for assessing passenger traffic,
aircraft movement and cargo traffic for LGBIA. Based on its analysis, Mott Macdonald has provided
high, base, and low estimate scenarios of projected traffic for the Third Control Period. The traffic
projections submitted by GIAL in Table 64 is adopted from Mott Macdonald’s ‘base case scenario’.
6.1.5 The Passenger traffic and ATM projected above has been adjusted by GIAL to account for billable
passenger traffic (excluding certain categories of passengers such as Transit/transfer passengers,
Children below 2 years, Diplomatic passport holders, Airline Crew etc. for whom UDF charges are not
leviable) and billable domestic ATMs (other than ATMs pertaining to less than 80-seater capacity
flights, and flights operating under Regional Connectivity Scheme (RCS); that are exempted from
landing charges). Based on the historical trends, the exempt traffic has been submitted by GIAL as 10%
of the total passengers, and 18% of total ATMs for the Third Control Period, as shown in the table below.
Table 66: Traffic growth rates (Y-o-Y) submitted by GIAL, after adjustment of exempt traffic
Passenger (in Nos.) ATM (in Nos.)
Year
Domestic International Combined Domestic International Combined
Traffic
2022-23 4,535,384 7,907 4,543,291 37,475 208 37,683
2023-24 5,825,900 45,368 5,871,268 48,194 1,197 49,391
2024-25 5,937,202 43,564 5,980,766 48,672 1,171 49,843
2025-26 6,687,874 73,509 6,761,383 54,528 1,552 56,080
2026-27 8,062,224 88,517 8,150,741 65,777 1,893 67,670
Total 31,048,583 258,866 31,307,449 254,646 6,021 260,667
Growth rates
2022-23 - - - - - -
2023-24 28.45% 473.75% 29.23% 28.60% 475.48% 31.07%
2024-25 1.91% -3.98% 1.86% 0.99% -2.17% 0.92%
2025-26 12.64% 68.74% 13.05% 12.03% 32.54% 12.51%
2026-27 20.55% 20.42% 20.55% 20.63% 21.97% 20.67%
6.2 Authority’s examination regarding Traffic projections for the Third Control Period
6.2.1 The Authority notes that GIAL appointed Mott Macdonald as its Consultant who has derived traffic
forecast based on Regression forecast methodology, developed through econometric analysis of
historical data combined with projections of key demand drivers as given below:
Passenger forecasts were derived basis Gross Domestic Product (GDP) growth forecasts from the
International Monetary Fund (IMF) World Economic Outlook April 2021, as well as the US
Department of Agriculture (USDA) and the Organization for Economic Co-Operation and
Development (OECD).
Consultation Paper No. 01/2024-25 Page 84 of 254TRAFFIC PROJECTIONS FOR THE THIRD CONTROL PERIOD
The aircraft movement forecasts for the Airport were derived based on the historical development
of both domestic and international average passengers per ATM.
For cargo forecasts, the historical development of both domestic and international average cargo
per ATM metrics, along with the potential cargo-carrying capacity of aircraft using the airports
were considered.
6.2.2 The Authority notes that GIAL has assumed the ‘base case scenario’ estimates of traffic forecasts
submitted by Mott Macdonald for forecasting passenger traffic, ATM and cargo (both domestic and
international).
6.2.3 The Authority notes that GIAL has considered only billable ATM, after excluding ATM traffic that are
exempted from landing charges. However, the Authority is of the view that RCS scheme is promoted
by the GoI with the objective of making regional air connectivity affordable by supporting airline
operators through concessions offered by Central Government, State Government and the Airport
Operators. As this scheme is promoted to encourage small aircrafts, therefore the flights operating under
this scheme are not eligible to be claimed as a passthrough/ exemption. The Authority notes that, as per
GIAL’s submission, out of 23% of less than 80-seater capacity category ATMs handled in FY23,
approximately 8% of them falls under RCS category. Based on the above fact, the Authority has
estimated traffic projections after excluding ATMs that pertain to less than 80-seater capacity flights
which fall under non-RCS category and being exempted from landing charges. The Authority further
notes GIAL’s submission that Guwahati as capital city airport and gateway to North East states. It acts
as a hub to destinations like Pasighat (IXT), Shillong (SHL), Rupsi (RUP), Tezpur (TEI) and other small
sized airports in the vicinity. This regional connectivity model helps boost demand in the
aforementioned destinations, which have restrictions for larger aircraft to operate. Further, limited
traffic demand from regional cities restricts the seat loads on these routes and thus do not permit airlines
to operate bigger aircraft.
6.2.4 The Authority, after rationalization has derived the exempted traffic as 15% for each tariff year and has
considered the same for determining the billable domestic ATM. Based on the above factors, the exempt
traffic considered by the Authority (after excluding ATMs that pertain to less than 80-seater capacity
flights which fall under non-RCS category) for determining billable domestic ATM for the Third
Control Period for LGBIA is as follows:
Table 67: Exempt traffic considered by the Authority for the Third Control Period
Particulars FY’23 FY’24 FY’25 FY’26 FY’27
Exempt Domestic ATM 15% 15% 15% 15% 15%
considered by the Authority
Similarly, Government of India has allowed exemption of UDF to certain categories of passengers
through Order No. AIC 14/ 2019 read with AIC 20/ 2019. GIAL cannot claim any passthrough regarding
UDF on such categories and this is followed by AERA across at all Major Airports.
6.2.5 As part of its examination of traffic forecast submitted by GIAL, the Authority has calculated
Compounded Annual Growth Rate, or CAGR, for passenger traffic, ATM, and Cargo from, FY 2017-
18 to FY 2019-20 (3-year CAGR), FY 2015-16 to FY 2019-20 (5-year CAGR), FY 2010-11 to FY
2018-19 (9-year CAGR), and FY 2010-11 to FY 2019-20 (10-year CAGR)
6.2.6 The 3-year, 5-year and 10-year CAGRs have been computed for the respective periods up to FY 2019-
20, as FY 2020-21 being an exceptional event year, may not provide an appropriate basis for arriving at
CAGR. However, the computation of 9-year CAGR is based on the periods FY 2010-11 to FY 2018-
19, in order to remove certain extraneous events of FY 2019-20 as detailed in para 6.2.8 below. The
Consultation Paper No. 01/2024-25 Page 85 of 254TRAFFIC PROJECTIONS FOR THE THIRD CONTROL PERIOD
table below provides the details of the CAGR for passenger traffic, ATM, and Cargo:
Table 68: CAGR for passenger traffic, ATM, and Cargo
Passenger ATM Cargo
Year
Domestic Internati Combined Domestic Internati Combined Domestic Internati Combined
onal onal onal
3 year 8.14% 5.74% 8.13% 4.65% 40.86% 5.17% -2.44% 22.47% -2.44%
CAGR
5 year 18.47% 2.46% 18.32% 11.41% 18.22% 11.54% 8.03% -27.73% 8.01%
CAGR
9 year 14.61% 9.97% 14.57% 8.11% 13.96% 8.17% 13.71% NA* 13.73%
CAGR
10 year 12.23% 10.32% 12.21% 5.84% 17.97% 6.01% 10.70% NA* 10.70%
CAGR
* Nil international cargo in FY2010-11
6.2.7 The Authority has noted that there is a variation in traffic and volatility in data, which causes the CAGR
for 5-year and 3-year period to be inappropriate for future traffic projections.
6.2.8 The Authority notes that there has been a decrease in the Passenger and ATM traffic particularly in the
FY 2019-20, which is a pre-COVID year, mainly due to the closure of operations by Jet Airways with
no replacement for those vacant slots and the impact of COVID pandemic towards the end of the FY
2019-20.
6.2.9 It was observed that there was a de-growth of 59.63% and 98.95% in domestic passenger traffic and
international passenger traffic respectively for FY 2020-21 (compared to FY 2019-20), due to the
adverse impact of COVID-19 pandemic on the domestic and international travels (Refer Table 63).
Similarly, it was observed that there was a de-growth of 47.41% and 98.00%, respectively in domestic
ATM and international ATM for FY 2020-21 (compared to FY 2019-20) as well as a de-growth of
25.08% in domestic Cargo for FY 2020-21 (compared to FY 2019-20). (Refer Table 63)
Computation of traffic forecasts by the Authority, considering the impact of COVID-19
pandemic
The traffic forecasts have been computed by the Authority, after taking into account the analysis
by the following agencies regarding the impact of COVID-19 pandemic on the Aviation sector,
apart from the study report provided by Mott Macdonald for LGBIA.
6.2.10 Airports Council International (ACI)
ACI in its latest report available has projected the following air passenger traffic outlook:
• Prior to the COVID-19 pandemic, the global passenger volume was estimated to reach 10.5 billion
passengers in 2023. However, the current projection of global passenger volume in 2023 is
approximately 8.6 billion passengers, which is 94.2% of the 2019 level.
• The year 2024 is expected to be a milestone for global passenger traffic recovery as it reaches 9.4
billion passengers, surpassing the year 2019 that welcomed 9.2 billion passengers (102.5% of the
2019 level). Compared to the pre-COVID forecast that predicted 10.9 billion passengers in 2024,
the effects of the pandemic represent a potential loss of 13.9%.
• While the Asia-Pacific region is expected to have a substantial jump in passenger traffic in the first
half of 2023 along with the ongoing opening of the Chinese market, its recovery is predicted to slow
down significantly in the second half of the year due to challenges in overseas tourism and looming
economic concerns. By the end of the year, the region is expected to reach 2.9 billion passengers,
or 87.3% of the 2019 level. With the uncertainty from both upside and downside factors, the region
is expected to reach approximately 3.4 billion passengers, or 99.5% of the 2019 level, in 2024.
Consultation Paper No. 01/2024-25 Page 86 of 254TRAFFIC PROJECTIONS FOR THE THIRD CONTROL PERIOD
6.2.11 International Air Transport Association (IATA)
IATA in its latest market analysis report has reported the following:
• Industry-wide revenue passenger-kilometers (RPKs) increased 29.7% year-on-year (YoY) in
November and closed the gap to 2019 levels to within 1%.
• Available seat-kilometers (ASKs) rose by 28.6% YoY, recovering to 98.2% of pre-pandemic
capacity. Global passenger load factor increased over the year and compared to 2019, now
standing at 81.8%.
• Domestic RPKs grew 6.7% over pre-pandemic levels with an annual growth rate of 34.8%.
International RPKs 94.5% of pre-pandemic levels and increased 26.4% YoY.
• Air passenger traffic, measured in revenue passenger-kilometers (RPKs), continued to grow in
November with a 29.7% increase over the year. Global RPKs are now just 0.9% lower than pre-
pandemic levels. In seasonally adjusted terms, growth continued although at a slightly slower pace
compared to the previous months with 0.6% month-on-month (MoM) growth.
Conclusion on traffic forecasts based on the above assumptions
6.2.12 Considering the extraordinary adverse impact of COVID-19 pandemic on domestic and international air
travel, the Authority has taken into consideration the forecasted data published by ACI and IATA cited
in para 6.2.10 and 6.2.11 for arriving at the revised traffic projections.
6.2.13 The Authority has reviewed the actual Passenger traffic, ATM and Cargo traffic data for FY 2022-23
(from AAI website) and has considered the same for estimating traffic for the Third Control Period:
Table 69: Comparison of Passenger, ATM and Cargo traffic at LGBIA of FY2019-20 vs FY 2022-23
Traffic of FY’23 as a % of FY’20
FY’20 FY’23
traffic
Traffic
Internati Internati Internati
Domestic Total Domestic Total Domestic Total
onal onal onal
Passenger 5,422,289 35,160 5,457,449 5,039,315 12,165 5,051,480 92.94% 34.60% 92.56%
(in Nos.)
ATM (in 44,539 1,000 45,539 45,701 208 45,909 102.61% 20.80% 100.81%
Nos.)
Cargo (in 21,267 3 21,270 22,823 - 22,823 107.32% 0.00% 107.30%
MT)
6.2.14 The Authority notes that GIAL has considered the actual passenger traffic and ATM data for FY 2022-
23 available on AAI’s website (as shown in the table above). The Authority vide email dated April 20,
2024 to provide actual traffic of FY2023-24 and the same was provided by GIAL vide email dated April
20,2024. The Authority compared the same with the data available on AAI website and proposes to
consider actual traffic for FY2023-24 as per Table 70.
Table 70: Forecasted and Actual Passenger, ATM, Cargo traffic submitted by GIAL for FY’24
Year Passenger (in Nos.) ATM (in Nos.) Cargo (in MT)
Domestic Interna Combined Domestic Interna Combined Domestic Internati Combined
tional tional onal
FY24
Forecasted 6473222 69797 6543019 58773 1197 59970 24293 3 24296
by GIAL
till Mar’24
Actuals till 5927288 30321 5957609 45578 570 46148 18851 0 18851
Mar ’24
6.2.15 The Authority reviewed the CAGR (3-year, 5-year, 9-year and10-year) derived by it as per Table 68,
and considering the positive outlook provided by the Expert Agencies, the Authority proposes to
Consultation Paper No. 01/2024-25 Page 87 of 254TRAFFIC PROJECTIONS FOR THE THIRD CONTROL PERIOD
consider the passenger, ATM, and cargo traffic proposed by GIAL for the last three (3) tariff years (FY
2025-26 till FY 2026-27).
6.2.16 The Authority notes that due to comissioning and operationalization of NITB in first quarter of FY2025-
26, the terminal building area shall increase by 621% from the existing terminal area. Due to increase in
area it is expected that traffic will pick up from FY2025-26 onwards and GIAL will be able to achieve
the forecasted traffic.
6.2.17 Based on the above analysis, the Authority thus proposes to consider actual passenger traffic, ATMs,
and cargo for FY2022-23 and FY2023-24 as per Table 69 and Table 70 respectively; and GIAL’s
submission with respect to the traffic in each category, for the remaining three tariff years of the Third
Control Period. The ratio of domestic exempted and billable ATMs considered by the Authority is as
per Table 67.
6.2.18 GIAL has metioned in its MYTP submission that commisioning of new Integrated Cargo Terminal
(ICT) shall be done in FY2024-25 while operationalization shall happen in FY2025-26, and has
considered handling of cargo from the new ICT, from FY2026-27 onwards. The Authority proposes to
consider the same. The Authority also proposes to consider volumes for FY25 and FY26 as submitted
by GIAL.
The Authority has assumed the same volumes for FY24, FY25 and FY26 due to cargo being handled
from interim facility in absence of ICT. The Authority further proposes to consider 50% of the total
cargo volumes forecasted to be handled by GIAL in FY 2026-27.
6.2.19 The traffic growth rates and the corresponding traffic for passengers and ATM as considered by the
Authority for the Third Control Period are given in the table below:
Table 71: Traffic proposed to be considered by the Authority for the Third Control Period
Domestic Passengers (Lacs) FY’20 FY’23 FY’24 FY’25 FY’26 FY’27 Total
Domestic PAX submitted by GIAL 54.22 50.39 64.73 65.97 74.31 89.58 344.98
Domestic PAX proposed by the 50.39 59.27 65.97 74.31 89.58 339.52
Authority
GIAL’s submission as a % of FY 92.94% 119.38% 121.66% 137.04% 165.21%
2019-20 traffic
Proposed traffic as per the 92.94% 109.31% 121.66% 137.04% 165.21%
Authority as a % of FY 2019-20
traffic
International Passengers (Lacs) FY’20 FY’23 FY’24 FY’25 FY’26 FY’27 Total
International PAX submitted by 0.35 0.12 0.70 0.67 1.13 1.36 3.98
GIAL
International PAX proposed by 0.12 0.30 0.67 1.13 1.36 3.59
the Authority
GIAL’s submission as a % of FY 34.60% 198.51% 190.62% 321.65% 387.32%
2019-20 traffic
Proposed traffic as per the 34.60% 86.24% 190.62% 321.65% 387.32%
Authority as a % of FY 2019-20
traffic
Total passengers (Lacs) FY’20 FY’23 FY’24 FY’25 FY’26 FY’27 Total
Total PAX as per GIAL's 54.57 50.51 65.43 66.64 75.44 90.94 348.97
submission
Total PAX (Domestic and 50.51 59.58 66.64 75.44 90.94 343.11
International) proposed by the
Authority
Proposed total PAX as per GIAL's 92.56% 119.89% 122.11% 138.23% 166.64%
submission as a % of FY 2019-20
traffic
Consultation Paper No. 01/2024-25 Page 88 of 254TRAFFIC PROJECTIONS FOR THE THIRD CONTROL PERIOD
Proposed total PAX as per the 92.56% 109.16% 122.11% 138.23% 166.64%
Authority as a % of FY 2019-20
traffic
Domestic ATM (in '000) FY’20 FY’23 FY’24 FY’25 FY’26 FY’27 Total
Domestic ATM submitted by 44.54 45.70 58.77 59.36 66.50 80.22 310.54
G IAL
Domestic ATM proposed by the 45.70 45.58 59.36 66.50 80.22 297.48
A uthority (A)
AO's submission as a % of FY 102.61% 131.96% 133.27% 149.30% 180.10%
2 019-20 total ATM
Proposed ATM traffic as per the 102.61% 102.33% 133.27% 149.30% 180.10%
Authority as a % of FY 2019-20
A TM
Domestic exempted ATM % FY’20 FY’23 FY’24 FY’25 FY’26 FY’27 Total
Submitted by GIAL 18% 18% 18% 18% 18%
As per the Authority (B) 15% 15% 15% 15% 15%
Domestic Billable ATM (in '000) FY’20 FY’23 FY’24 FY’25 FY’26 FY’27 Total
Submitted by GIAL
37.47 48.19 48.67 54.53 65.78 254.65
As per the Authority C = A*(1-B)
38.85 38.74 50.45 56.52 68.18 252.75
International ATM (in '000) FY’20 FY’23 FY’24 FY’25 FY’26 FY’27 Total
International ATM submitted by 1.00 0.21 1.20 1.17 1.55 1.89 6.02
GIAL
International ATM proposed by 0.21 0.57 1.17 1.55 1.89 5.39
the Authority
GIAL's submission as a % of FY 20.80% 119.70% 117.10% 155.20% 189.30%
2019-20 ATM
Proposed ATM traffic as per the 20.80% 57.00% 117.10% 155.20% 189.30%
Authority as a % of FY 2019-20
ATM
Total ATM (in '000) FY’20 FY’23 FY’24 FY’25 FY’26 FY’27 Total
Total ATM (Domestic and 45.54 45.91 59.97 60.53 68.05 82.11 316.57
International) as per GIAL’s
submission
Total ATM (Domestic and 45.91 46.15 60.53 68.05 82.11 302.74
International) proposed by the
Authority
AO's submission as a % of FY 100.81% 131.69% 132.91% 149.43% 180.30%
2019-20 total ATM
Proposed total ATM as per the 100.81% 101.34% 132.91% 149.43% 180.30%
Authority as a % of FY 2019-20
ATM
Domestic Cargo traffic (in MT in
FY’20 FY’23 FY’24 FY’25 FY’26 FY’27 Total
’000)
Domestic cargo submitted by 21.27 22.82 24.29 23.70 27.13 33.30 131.24
GIAL
Domestic cargo proposed by the 22.82 18.85 23.70 27.13 33.30 125.80
Authority
GIAL's submission as a % of FY 107.32% 114.23% 111.44% 127.55% 156.59%
2019-20 total Domestic Cargo
Proposed total ATM as per the 107.32% 88.64% 111.44% 127.55% 156.59%
Authority as a % of FY 2019-20
Domestic Cargo
International Cargo (MT in ’000) FY’20 FY’23 FY’24 FY’25 FY’26 FY’27 Total
International cargo submitted by 0.003 0.00 0.003 1.30 1.40 1.50 4.20
GIAL
Consultation Paper No. 01/2024-25 Page 89 of 254TRAFFIC PROJECTIONS FOR THE THIRD CONTROL PERIOD
International cargo proposed by 0.00 0.00 1.30 1.40 1.50 4.20
the Authority
Total Cargo (MT in '000) FY’20 FY’23 FY’24 FY’25 FY’26 FY’27 Total
Total cargo submitted by GIAL 21.27 22.82 24.30 25.00 28.53 34.80 135.44
Total cargo proposed by the 22.82 18.85 25.00 28.53 34.80 130.00
Authority
GIAL's submission as a % of FY 107.30% 114.23% 117.53% 134.11% 163.62%
2019-20 total Cargo
Proposed Cargo traffic as per the 107.30% 88.63% 117.53% 134.11% 163.62%
Authority as a % of FY 2019-20
Cargo
GIAL's share of Cargo Traffic
FY’23 FY’24 FY’25 FY’26 FY’27 Total
(MT in '000)
As per GIAL
Domestic cargo 3.50 4.50 5.50 13.50
International cargo
Integrated Cargo Terminal 30.00 30.00
Total cargo handled 3.50 4.50 5.50 30.00 43.50
GIAL Market Share 14% 18% 19% 86%
As per the Authority
Domestic 3.50 4.50 5.50 13.50
International
Integrated Cargo Terminal 17.40 17.40
Total cargo handled 3.50 4.50 5.50 17.40 30.90
GIAL Market Share 14% 18% 19% 50%
6.2.20 The Authority has considered the traffic proposed in Table 71 above, to assess the need for the Capital
expenditure proposed by GIAL for the Third Control Period and accordingly, the Authority has
rationalized the CAPEX submitted by GIAL for the Third Control Period for LGBIA.
6.3 Authority’s Proposal regarding Traffic for the Third Control Period
Based on the available facts and analysis thereupon, the Authority proposes the following with regard to
traffic forecast for the Third Control Period:
6.3.1 To consider the ATM, Passenger traffic and Cargo traffic for the Third Control Period for LGBIA as per
Table 71.
6.3.2 To true up the traffic volume (ATM, Passengers and Cargo) on the basis of actual traffic in the Third
Control Period while determining tariffs for the Fourth Control Period.
Consultation Paper No. 01/2024-25 Page 90 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
7 CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE
(RAB) FOR THE THIRD CONTROL PERIOD
7.1 Background
7.1.1 RAB is one of the essential elements in the process of tariff determination. The return to be provided on
the RAB constitutes a considerable portion of the Aggregate Revenue Requirement for an Airport
Operator. To encourage the participation of the private sector in airport development and operations,
investors must be fairly compensated for the capital outlays involved. At the same time, to safeguard the
interests of the airport users, it must be ensured that the capital additions are efficient, their needs
justified, and the return on investment provided solely on the assets related to the core operations (i.e.,
Aeronautical services) of the airport.
7.1.2 The Authority notes that as part of the Concession Agreement (CA), GIAL needs to develop LGBIA in
a phased manner during the Concession period, as well as cater to the annual passenger throughput
capacity (domestic and international) and annual cargo handling capacity, along with ancillary facilities
as per its demand projections. Further, development of the airport includes construction and procurement
of various assets as described in the Concession Agreement such as:
• Runways, taxiways, apron, aircraft parking bays, air traffic control tower, Cargo facilities, Parking,
flight kitchens, MRO facilities, warehousing facilities, airline offices, administrative offices and
associated facilities.
• Construction and procurement of Terminal Building and facilities and
• Construction of required approach roads.
7.1.3 The Authority notes that GIAL is mandated to develop an integrated terminal building which is
efficiently planned, flexible for phase-wise development, sustainable and economical, as stipulated in
Schedule B of Annex I of the CA. Further, as per Clause 23.7.1 of the CA -" The Concessionaire shall
participate in the user survey of ASQ undertaken by Airports Council international ("ACI") or any
substitute thereof, conducted every quarter and shall ensure that the Airport achieves and maintains a
rating of at least 4.5 (four point five) out of 5.0 (five) and/ or shall appear within top 20 (twenty)
percentile of all airports, in its category in the world in such survey within 5 (five) years from the COD
and maintain the same throughout the rest of the Concession Period."
7.1.4 The Authority understands that as part of the Concession Agreement (CA), GIAL shall be liable to pay
AAI the amount incurred by AAI as on the COD in respect of works-in-progress as set forth in Schedule
T of the CA. As per section 3.5 of the MYTP submitted by GIAL, the AAI has raised an invoice of
₹430.89 Crore (excluding GST). As per GIAL, these assets are capitalized in the books of account as
and when completed. Accordingly, the Authority notes that these assets are captured in Fixed Asset
Register and forms part of Regulatory Asset Base.
7.1.5 The Independent Consultant appointed by the Authority has performed an in-depth analysis of the
submissions made by GIAL towards Aeronautical Capital Additions, Depreciation and RAB. In this
respect, the Independent Consultant has performed the following functions:
i. Reviewed construction plan submitted by GIAL in view of various technical studies undertaken
by GIAL, Airport Master Plans, BOQs (wherever provided), Copies of Letter of Intent (LOI),
Letter of Award (LOA), Purchase Orders and Work Orders etc., wherever provided. The
Independent Consultant also considered the responses of GIAL to the clarification sought in
relation with CAPEX plan from time to time.
ii. Sought documentary evidence and the process of approval of capital addition projects including
competitive bidding process for award of various work orders to the contractors, if applicable.
Consultation Paper No. 01/2024-25 Page 91 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
iii. The consultants also visited LGBIA for a site visit on 10th October’2023 and 21st-22nd March 2024
focusing specifically on review of current airport operation and proposed airport development
plans.
Based on the review of documents as stated above and the essentiality and necessity for Airport
operations, the Authority has rationalized the CAPEX projects submitted by GIAL, by shifting the
capitalization date of some of the projects in view of the project progress, verification of item rates and
optimization of the capacity augmentation proposed by GIAL for various assets.
7.1.6 In the background of the facts stated above, the Authority through its independent consultant has
examined the capital expenditure proposed by GIAL, considering the historical traffic trends and future
traffic estimates such that only essential, reasonable and efficient CAPEX is considered as part of RAB
for the Third Control Period. This is done with a view to encourage the investment and maintain a
balanced approach between sustainable operations of the GIAL and the interest of the airport users.
Further, the Authority take cognizance of the fact that, if any excessive capex is allowed in this Control
Period, it would be against the regularity framework, as tariff would have no link to the services/facilities
created at the Airport and the resultant high aeronautical charges would be unfair to the end users.
Hence, the Authority through its independent consultant has examined the entire CAPEX plan in detail
including CWIP projects and the New CAPEX for LGBIA, considering the historical traffic trends and
future traffic estimates such that only essential, reasonable and efficient CAPEX is considered as part of
RAB for the Third Control Period with a view to encourage the investors and maintain a balanced
approach between the sustainable operations of GIAL and the interest of the airport users.
7.1.7 Based on the above, the Authority has rationalized the capital expenditure for all the projects and
accordingly proposed capital additions for the Third Control Period. Further, the Authority has adjusted
the capitalization timelines for some of the project based on project progress.
7.1.8 Towards this objective, the Authority has examined in detail the Aeronautical Capital Expenditure,
Depreciation and RAB submitted by GIAL and has presented its views in the following order:
i. Capital Additions initiated by AAI during the pre-COD period and transferred to GIAL as part
of the Concession Agreement and Capital expenditure proposed by GIAL for the Third
Control Period.
ii. Interest during Construction/financing allowance
iii. Aeronautical allocation of capital expenditure for the Third Control Period
iv. Aeronautical Depreciation for the Third Control Period
v. Regulatory Asset Base for the Third Control Period
7.1.9 The Authority observes that GIAL has submitted various Minor Projects/works under different heads
consisting of numerous sub-projects/procurements planned to be carried out over the Third Control
Period. The Authority notes that for certain minor projects, GIAL has provided POs and BOQs for only
portion of the cost. For the remaining amounts, which consist of multiple line items, cost estimates have
not been submitted by GIAL to justify the proposed costs.
7.1.10 The Authority’s Independent Consultant, interacted with the technical team of GIAL on the aspects of
airport planning, traffic estimation and its short, mid and long term impact on Airport Economics as
provided in the Concession Agreement.
Based on the response provided by GIAL, the Authority observed that prima facie, GIAL has not
demonstrated desired understanding of optimal planning and execution of capex projects related to
airport. This is evident from the fact that the proposed CAPEX has not been linked with expected outturn
of traffic and is multifold as compared to other airports which handle similar traffic levels. GIAL has
projected a CAPEX to the tune of ₹ 6107 crores (including soft cost and CWIP project) for passenger
Consultation Paper No. 01/2024-25 Page 92 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
traffic of 6.66 MPPA in FY’25 (forecasted by GIAL) to 13.1 MPPA, which has no rational justification.
This approach of the Airport Operator is not in the overall interest of the stakeholders of the airport. It
appears that the CAPEX has been projected by GIAL without linking it with the mandate provided under
Schedule B of the Concession Agreement.
In view of these facts, the Authority notes that the Capital Expenditure estimates submitted by GIAL are
not reasonable / their need is not justifiable. Therefore, the Authority has considered various applicable
factors such as current capacity, traffic estimates, normative cost benchmarks, need assessment etc.
together with the need for modular development of facilities as mandated by the Concession Agreement
and has rationalized the Capital Expenditure.
7.2 GIAL’s submission regarding Capital Expenditure proposed for the Third Control Period
7.2.1. As per the MYTP, GIAL has submitted following Aeronautical Capital addition for the third control
period:
Table 72: Asset-wise Aero Capitalisation submitted by GIAL for the Third Control Period
(₹ crores)
Particular FY'23 FY'24 FY'25 FY'26 FY'27 Total
Terminal Building 1.98 7.88 3073.68 0.00 0.00 3083.54
Runway, Taxiway & Apron 10.04 3.31 496.21 1234.85 0.04 1744.45
Boundary walls 0.00 0.24 0.00 180.62 0.00 180.86
Software 1.58 1.58
IT equipment 9.11 15.72 1.60 1.66 1.66 29.75
Security Equipment 0.00 0.80 25.86 7.74 7.01 41.41
Plant & Machinery 8.28 12.93 49.06 124.22 27.78 222.27
Other Buildings 6.14 7.53 34.82 44.88 113.95 207.32
Access Roads 0.05 0.05
Furniture 2.35 0.74 0.37 0.26 0.56 4.28
Vehicle 2.55 17.22 21.89 6.15 5.56 53.37
Office equipment 4.98 0.00 0.00 0.00 0.00 4.98
Cargo 0.57 3.77 0 28.45 0 32.79
Fuel 0 15.84 0 397.13 0 412.97
47.63 85.98 3703.49 2025.96 156.56 6019.62*
Total
*excluding runway strengthening works of ₹ 87.28 crores considered as part of opex
7.3 Authority’s examination regarding Capex, Depreciation and RAB for the Third Control
Period
The Authority as part of its examination of the Aeronautical Capital Expenditure submitted by GIAL for
the Third Control Period, had raised various queries and sought clarification on the essentiality of the
capital expenditure and enquired for necessary documents such as project cost estimates, Technical
Consultant’s report and inspection report issued by various authorities etc., substantiating the capital
expenditure proposed by GIAL in the MYTP. The aforementioned documents and clarifications were
provided in a phased manner by GIAL. The Consultation Process is an exhaustive exercise which
involves analysis of significant data and facilitates, in reaching conclusions and recording the resultant
proposals keeping in mind the interest of all stakeholders. Accordingly, the Authority had relied on the
information made available by GIAL and made appropriate analysis and changes wherever necessary.
7.3.1 The Authority has noted that out of total Aeronautical CAPEX submitted by GIAL as part of MYTP,
around 47% pertains to terminal works which was taken over from AAI and the balance 53% pertains
to the new CAPEX proposed by GIAL for the Third Control Period. While analyzing the MYTP of
Consultation Paper No. 01/2024-25 Page 93 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
LGBIA regarding Capital Expenditure for the Third Control Period, the Authority has taken into
consideration the traffic as per Table 71. The capex has been rationalized based on various factors viz.
normative cost, demand, inflation adjustment etc.
7.3.2 The capital additions as stated in para 7.2 above are further explained as project wise in the table below
and evaluated by the Authority in the same sequence:
Table 73: Project wise Capital Expenditure submitted by GIAL for the Third Control Period
(₹ crores)
Year of
Capex with
S. N o. Particular Capitalization Base Cost
Indexation
(as per GIAL)
Passenger Terminal and Associated Works
A NITB (Including Opening CWIP 2025
A.1 2,194.38 2194.38
as per financials)
A.2 Kerbside Development 2025 138.60 138.60
Existing Terminal Building 2024-2025
A.3 9.05 9.64
development/modification
Total 2,342.03 2,342.62
Runways, Taxiway & Aprons
Apron-2 (Demolition and new-
B.1 2026 410.55 466.21
construction)
Airside Storm Water Drainage
B.2 2025 192.68 208.38
works
Construction of Part Parallel
B B.3 2026 178.66 199.02
Taxiway and Link Taxiways
B.4 Land Development works 2026 167.90 189.73
B.5 Widening of Runway Strip 2025 79.06 87.17
Construction of Second Part
B.6 2026 71.37 81.64
Parallel Taxiway
B.7
Extension of Runway 02–20
2025 47.96 51.61
towards RWY 20
Construction of new Isolation Bay
B.8 2025 28.01 30.89
(Rigid Pavement)
Construction of Rapid Exit
B.9 2026 17.21 19.73
Taxiway
B.10 Other Minor Airside Capex
Construction of Runway End
B.10.1 Safety Area (RESA) after RWY 2025 3.97 4.21
20 Threshold
Extension of Blast Pad for RWY
B.10.2 02 and Construction of new Blast 2025 3.94 4.24
Pad for RWY 20
Relocation of Simple Approach
B.10.3 2025 0.70 0.78
Lighting System for Runway 20
Installation of Category-I
B.10.4 Approach Lighting System 2025 6.99 7.38
towards Runway 02
B.10.5 Off-Stand GSE 2026 4.05 4.60
Apron stand surface revamping
B.10.6 2024 0.30 0.32
work in old apron
Manhole chamber covers for all
B.10.7 manholes or pits at apron area, 2025 0.20 0.22
strip area as per ICAO standard
Consultation Paper No. 01/2024-25 Page 94 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Year of
Capex with
S. N o. Particular Capitalization Base Cost
Indexation
(as per GIAL)
Provision of new Earthing system
B.10.8 for Runway and other associated 2025 0.17 0.19
works at Guwahati Airport
SITC of Inset fittings for Runway-
B.10.9 Taxiway intersection at Guwahati 2024 0.38 0.40
Airport
Upgradation of flexible pavements
B.10.10 2026 0.75 0.87
in Operational area
Runway Graded Strip and RESA
B.10.11 strengthening (up to 300mm 2024 0.17 0.18
Depth)
Airside works (Apron surface
revamping works, Provision of
B.10.12 2024-2026 1.58 1.73
new Airfield signages, Joint filling
and cleaning of old apron)
B.10.13 Apron Control 2024 0.20 0.21
B.10.14 Airside Equipments 2024-2026 1.54 1.65
B.11 Runway strengtheing works 2026 65.00 75.25
Total 1,283.36 1,436.60
Construction of Boundary Wall
New construction of Airside
Perimeter & Service Roads and
C.1 demolition of existing Airside 2026 33.75 38.33
Roads due to widening of Runway
Strip
New construction of Airside
C
Boundary Wall & demolition of
C.2 2026 68.13 77.37
existing Airside Boundary Wall
due to widening of Runway Strip
C.3 PIDS System 2026 22.88 26.24
C.4 Boundary Wall 2024 0.20 0.21
Total 124.97 142.14
Cargo Complex
D.1 Interim Cargo Facility 2024 3.07 3.22
D
D.2 New Cargo Terminal 2026 20.00 23.15
Total – Cargo Complex 23.07 26.37
Fuel Farm Infrastructure
E.1 Fuel storage farm 2026 119.97 135.07
E.2 Fuel hydrant line 2026 142.72 160.68
Equipment cost 2024 3.00 3.15
E
Cost of procurement of IOCL and
E.3 2024 10.00 10.50
RIL assets
Dead Stock 2026 13.94 16.14
Total – Fuel 289.63 325.55
Vehicles
F.1 Vehicles 2024-2027 11.00 12.58
F Modified vehicle for BDDS
F.2 2025-2026 3.00 3.39
equipment
F.3 Vehicle recovery Van 2024 0.15 0.16
Consultation Paper No. 01/2024-25 Page 95 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Year of
Capex with
S. N o. Particular Capitalization Base Cost
Indexation
(as per GIAL)
2 Nos.Tractor withTrolleys &
F.4 electric buggies to shuttle nursery 2025-2027 0.20 0.23
between the two terminals
F.5 Ambulance 2025 , 2027 0.75 0.87
F.6 Crash Fire Tender 2024 , 2025 23.98 25.81
Quick Reaction Team (QRT)
F.7 2025 0.70 0.77
Vehicle
Total – Vehicles 39.78 43.81
Plant and Machinery
G.1 5 nos. OWS 2026 23.60 26.80
G.2 Triturator 2025 3.47 3.83
G.3 Hazardous Waste Storage 2026 0.49 0.55
Reticulation of utilities to new
G.4 2027 8.39 9.78
facilities
SITC of LED type SPOL System
at Sajanpara, Borsilla & Mirza
G.5 2024 0.06 0.06
Hills near LGBI Airport,
Guwahati.
Laying of GLF light cables
G.6 2025 0.85 0.94
approximate 6500 mtrs
G.7 Laser unit for AVDGS-2NO 2025 0.40 0.44
G.8 SITC of A-VDGS at Bay no. 4 2025 0.71 0.78
Energy saving projects (hymus
perimeter lights, hymus solar
G.9 lights, other energy saving 2024 1.52 1.60
projects) (Reduced from 2.7 to
1.52)
SITC of Repair and Maintenance
G.10 2024 0.30 0.32
work for Airside
G
Miscellaneous Plant and
Machinery (Boom lift, Chiller
plant cooling tower development,
G.11 Breath Analyser Equipment, 2024-2027 3.07 3.36
Expansion of existing electrical
office, Modification of Existing
DG set controller etc)
PVC coated Chain net for
G.12 2025 1.00 1.10
Operation area drains
Environmental Projects (R22
based will be replaced by R32,
G.13 2024-2027 6.60 7.34
carbon offset projects, ACI 4 +
certification, RE 100 etc)
EV Charging Stations for E Buses
G.14 , Apron Cars , Tugs along with 2024-2027 5.70 6.48
their installation .
G.15 carbon sequestration 2024-2027 3.40 3.95
G.16 Biodiversity preservation projects 2024-2027 2.15 2.50
G.17 Fire Fighting Equipment 2024-2027 3.55 3.86
G.18 Disable Aircraft Removal Kit 2025 17.69 19.50
Hand Baggae X-Ray -
G.19 2025, 2026 2.55 2.89
60cmX40cm
Consultation Paper No. 01/2024-25 Page 96 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Year of
Capex with
S. N o. Particular Capitalization Base Cost
Indexation
(as per GIAL)
G.20 Explosive Trace Detector(ETD) 2024-2026 1.35 1.49
Hand Held Metal
G.21 2024-2027 0.18 0.21
Detector(HHMD)
Door Frame Metal
G.22 2024-2027 0.59 0.68
Detector(DFMD)
Security Operation Control Center
G.23 2025-2027 2.77 3.29
(CISF)
Security Surveillance Centre
G.24 2025 1.50 1.65
(SSC)
Close Circuit Television (CCTV)
G.25 2025-2027 3.20 3.71
Setup
G.26 Access Control system, Adani 2025-2027 2.40 2.78
G.27 Container Tubular shooting Range 2025 1.30 1.43
G.28 Video Surveillance system 2024-2027 3.59 4.23
G.29 Body Scanner 2025-2026 44.57 51.49
G.30 VDGS 2026 12.00 13.89
Total – Plant and Machinery 158.95 180.93
Other Buildings
H.1 Relocation of Localiser 02 2024 0.20 0.21
H.2 CCR Building new construction 2026 12.86 14.46
H.3 5 Airside Gates 2026 5.79 6.51
SMR Facilities (New
H.4 2025 0.91 1.00
Construction)
H.5 Fuel/ EV Charging Station 2026 2.49 2.76
Satellite ARFF Station (New
H.6 2025 12.35 13.61
Construction)
Modification of MT workshop
H.7 into Admin office building 2025 2.14 2.36
(Interim arrangement)
Integrated Building for Airport
H.8 Police Station, Airport Health 2027 8.84 10.34
Office and Airport Post Office
Airport Administration Building
H.9 2027 47.52 55.57
H (5,000 Sqm)
Airport Maintenance Office
H.10 2027 11.41 13.34
(1,200 Sqm)
H.11 Solid Waste Facility 2026 2.50 2.82
H.12 Water Supply system 2027 4.66 5.43
H.13 Sewerage System 2027 1.16 1.35
Modification of watch tower at
H.14 operational area L.G.B.I. Airport 2024 0.35 0.37
Guwahati
Earth filling of low using areas
and other miscellaneous works at
H.15 operational area related to DGCS 2025 0.40 0.44
compliance from time to time at
L.G.B.I. Airport Guwahati
H.16 Fire Station Improvement 2024-2025 4.20 4.57
H.17 Other Building - Admin Office 2024 1.50 1.58
H.18 Sewage Treatment Plant 2025 0.36 0.40
Consultation Paper No. 01/2024-25 Page 97 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Year of
Capex with
S. N o. Particular Capitalization Base Cost
Indexation
(as per GIAL)
Misc Other Buildings -
H.19 Upgradation works at RED, ATC, 2024-2025, 2027 2.89 3.26
CISF and BCAS building
H.20 Installation of LGB Statue 2024 0.15 0.16
H.21 CISF accommodation 2025-2027 13.50 15.64
H.22 Nursery Development 2027 0.60 0.73
H.23 Misc Horticulture Improvements 2024-2027 1.46 1.64
H.24 Administrative Building 2024-2026 3.64 3.91
Anti Hijacking Control Room
H.25 2025-2026 1.22 1.40
(AHCR) upgradation
Total – Other Buildings 143.09 163.85
IT equipment
I I.1 IT Equipments 2024-2027 16.57 17.80
Total – IT equipment 16.57 17.80
Furniture & fixtures
Furniture & Fixtures for Terminal,
J J.1 2024-2027 1.48 1.66
Office, Security etc.
Total – Furniture & fixtures 1.48 1.66
Security equipment
Procurement of Security
Equipments (Bullet Proof Jackets,
K.1 Bullet Proof Helmet, Bullet Proof 2024-2027 2.62 2.96
Shield, Bullet Proof Morcha,
Binocular Device etc)
K.2 Threat Containment Vessel (TCV) 2025 14.00 15.44
K K.3 BDDS 2025-2027 4.00 4.61
Misc Security Equipments (Quick
Reaction Team Equipments,
Radiological Detection
K.4 2024-2027 10.99 12.70
Equipment, Network Switch and
Cabling Tec Refresh, OFC
network CCTV etc)
Total – Security equipment 31.61 35.70
Sustaining capex already spent
L 47.64 47.64
(FY22-23)
Total Project Cost as submitted by GIAL 4,502.17 4,765.00
Apart from the base cost, GIAL has proposed soft cost, IDC and Financing allowance as part of total
capex. The details of total capex are as follows:
Table 74: Details of Total CAPEX as submitted by GIAL
(₹ Crore)
S. No. Particular Cost
Basic cost (Including indexation) as
I 4765.00
tabled above
II Soft Cost 682.00
III Interest During Construction 412.00
IV Financing Allowance 248.00
Grand Total 6107.00
Consultation Paper No. 01/2024-25 Page 98 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Note: The above amount includes Runway Recarpeting expenses which is claimed as OPEX by AO, balance
amount of ₹ 6019.64 crores is considered as capital expenditure.
7.3.3 Airport User Consultation Committee (AUCC)
i. The Authority notes that GIAL conducted Airport User Consultation Committee (AUCC)
Meetings on July 06, 2023 and March 27, 2023. The AUCC meeting held on July 06, 2023 which
was for proposed capex including related to fuel farm capex for the third control period. The
meeting held on March 27, 2023 is for the capital expenditure planned toward Air Cargo Facilities.
The meeting was attended by various airport stakeholders including but not limited to International
Airport Transport Association (IATA), Federation of Indian Airlines (FIA), The Associated
Chambers of Commerce & Industry of India (ASSOCHAM), Indigo, Spicejet, FlyBig, Vistara,
Akasa Air, AirAsia, BAOA, Blue Dart, IOCL, HPCL, BPCL, Reliance, AAI, Immigration, Local
Trade Bodies among others. As per the minutes of the meeting, the Authority observed that the
GIAL had broadly discussed the following with the stakeholders:
a. Background of the projects and GIAL future strategy
b. Traffic forecast
c. Existing infrastructure and proposed master plan.
d. Capex project including passenger terminal improvement and kerbside development
works, ancillary building works, airside improvement work and other minor projects.
ii. From the perusal of the minutes, it turns out that the stakeholders made important observations in
relation to the aspects of normative costing, cost estimates for the capex projects, fuel farm, airside
works and drainage system.
iii. Some of the key observations made by the stakeholders are as below:
a. IATA insisted on adoption of AERA normative norms for capital projects and maximise
airside capacity of the Airport efficiently.
b. Indigo inquired about GIAL plans in increasing airside capacity, possibility of CAT-III
operations and following normative approach with respect to project cost.
c. FIA insisted upon increasing non-aero revenue to optimize airport charges.
d. IMD inquired about the drainage system in and around the airport.
e. Fuel farm operator inquired about the availability of open access facility, hydrant line. IOCL
mentioned that considering remote location of Guwahati, the AO should plan 7-10 days
storage capacity. The stakeholder also enquired about fuel farm cost as same seem to be on
higher side which may lead to higher fuel farm charges.
iv. The Authority notes from the Minutes of the AUCC meeting that, stakeholders have emphasized to
improvisation of airside capacity, terminal building space and fuel farm facility. The Authority also
notes that certain observations were made by some of the stakeholders relating to the aspects of
normative costing, cost estimates projected for the capex projects, improvement of existing facilities,
and to bring economy of scale in its overall operation, costing etc.
v. The Authority also notes GIAL response to the stakeholder comments, some of the responses to the key
observations raised by the stakeholders are as below:
a. GIAL has planned comprehensive airside improvement works including drainage system.
b. The project cost has been estimated at a particular time and same will be submitted to the
Authority for their review.
c. GIAL will take appropriate steps to increase non-aero revenue.
d. In case of fuel farm, GIAL has planned 8-10 days storage capacity, the cost has been
benchmarked with market rates and the work already carried out by at other airports.
vi. The Authority has examined the capital expenditure projects submitted by GIAL and has rationalized it
based on present and future designated capacity of the Airport to handle the forecasted traffic and with
Consultation Paper No. 01/2024-25 Page 99 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
the perspective of keeping the tariff rates at a reasonable level.
7.3.4 Inflation-adjusted normative cost for capital projects
i. The Authority vide its Order No. 07 / 2016-17 dated June 6, 2016 (Normative Order), had considered
normative cost of ₹ 65,000/- per Sqm. for Terminal Building. The normative cost specification provided as
Annexure-1 of Normative Order. This mainly includes cost toward structural works of the terminal building,
air conditioning, fire-fighting system, water supply, sanitary, substation equipment for power supply including
stand by system, passenger facilities viz FIDS, Furniture, Signages and Security surveillance, airlines related
services viz Check-in, CUTE, CUSS and Baggage Reconciliation System, In-line X ray screening, Standalone
screening , BHS for arrival and departure, Escalators, Elevators, Travellators and PBB. The cost of other items
required for terminal building such as elevated road connection to the terminal building etc. is not covered in
the aforementioned list. The cost of such items will be derived separately and added to the overall cost of the
project.
ii. In this respect, the Authority notes that it has considered a normative cost of ₹ 1,00,000 per sqm for FY 2020-
21 in some of the recent tariff orders based on the superior specifications, processes and the architectural
features of modern Terminal Buildings. In view of the same, the Authority in case of GIAL, proposes to
consider ₹ 100,000 per sqm in the base year FY’2021 for terminal building works.
iii. The proposed capital expenditure for third control period is spread across the control period. GIAL has applied
the inflation index of 5% over the base cost to capture inflationary impact. As per GIAL the 5% YoY growth
has been considered based on RBI forecaster survey Dec 2022. The Authority has reviewed the same and
observed that same needs to be aligned as per latest inflation index data issued by RBI Forecaster Survey (refer
Table 126)
iv. The Authority has derived the inflation adjusted normative rates for the proposed capex in the current Control
Period by considering the rate of inflation as follows:
• FY 2021-22 –The Authority observes that FY 2021-22 was an exceptional year due to COVID -19
pandemic, wherein the inflation rate was 12.97%. However, during the period FY 2016-17 to FY 2020-
21, the rate of inflation was in the range of 1.31% to 4.26%. Considering this extraordinary situation, the
Authority feels that the inflation rate of FY 2021-22 needs to be rationalized. Hence, instead of considering
the inflation rate of 12.97% for FY 2021-22 (as per press release dated April 18’2022, by Dept. for
Promotion of Industry and Internal Trade, Government of India), the Authority has considered the average
rate of inflation of FY 2020-21 (1.29%) and of FY 2021-22 (12.97%), which works out to 7.14%. The
Authority has considered this average rate of inflation for FY 2021-22, in order to smoothen out the
volatility in commodity price caused by COVID-19 pandemic and the supply side disruptions.
• FY 2022-23 – 9.42% (considered as per the data published by the Office of the Economic Advisor,
Department for Promotion of Industry and Internal Trade) and
• FY 2023-24 to FY 2026-27 – (-)0.70% in FY 2023-24, 3.10% for FY 2024-25 and 3.70% thereafter
(considered as per 87th Round of Survey of Professional Forecasters on macroeconomic indicators).
In the Order No.07/2016-17 dated 13th June 2016 on “In the matter of Normative Approach to Building blocks
in Economic Regulation of Major Airports – Capital costs Regarding” the ceiling cost mentioned is inclusive of
taxes applicable at that time i.e. 12%. Subsequently, GST has been introduced wherein the GST rate is 18%.
Hence, the inflation adjusted normative cost is worked out below by considering the additional 6% resulting in a
total GST rate of 18%. The Authority, in this regard notes that the proposed normative cost of ₹ 1,00,000 per sqm
is inclusive of GST, Accordingly, the Authority first arrived normative cost excluding of GST and then applied
18% GST which comes to ₹ 1,05,357 per sqm, the amount so arrived is indexed with inflation to arrive normative
rates for following years.
The inflation adjusted normative costs, thus derived is presented in the below table:
Consultation Paper No. 01/2024-25 Page 100 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Table 75: Inflation Adjusted normative rates computed for the Terminal Building by the
Authority
Financial Inflation rate Inflation adjusted Inflation adjusted normative
Year normative rates cost @18% GST
(in ₹ per sqm) (in ₹ per sqm)
FY’21 - 100000 105357
FY’22 7.14% 107140 112880
FY’23 9.42% 117233 123513
FY’24 -0.70% 116412 122648
FY’25 3.10% 120021 126451
FY’26 3.70% 124462 131130
FY’27 3.70% 129067 135981
*Note
Inflation adjusted base amount (inclusive of 12% GST) (A) = Rs. 1,00,000 per sqm
Inflation adjusted base amount (exclusive of 12% GST) (B=A*100/112) = Rs. 89,286 per sqm
Add GST @ 18% (C=B*18%) = Rs. 16,071 per sqm
Normative cost including GST (D = B+C) = Rs. 1,05,357 per sqm
The Authority has considered normative cost for the terminal expansion projects considered in this control
period. In view of the above, the Authority has considered the applicable normative cost as per the project
schedule submitted by GIAL.
Further, the Normative Order also provide normative cost for pavement related works for Apron,
taxiway, runway. The normative cost for the Runway/taxiway/Apron (excluding earthwork up to sub
grade level) was ₹ 4700/- per sqm based on the project executed in FY 2015-16. The Authority has
adjusted the normative cost on account of additional tax impact of 6% on account of GST in line with
the adjustment made in arriving normative cost for terminal cost across all Airports uniformly. The
inflation adjusted normative rate for Runway/taxiway/Apron excluding earthwork up to sub grade level
proposed to be as follows:
Table 76: Inflation adjusted Normative rates computed for runway/taxiway/apron by the
Authority
Financial Year Inflation rate Inflation adjusted Inflation adjusted normative
normative rates cost @18% GST
(in ₹ per sqm) (in ₹ per sqm)
FY’16-Base Year 4700 4952
FY’17 1.73% 4781 5038
FY’18 2.96% 4923 5187
FY’19 4.26% 5133 5408
FY’20 1.67% 5219 5498
FY’21 1.31% 5286 5570
FY’22 7.14% 5664 5968
FY’23 9.42% 6198 6530
FY’24 -0.70% 6155 6484
FY’25 3.10% 6346 6685
FY’26 3.70% 6543 6932
FY’27 3.70% 6746 7188
*Note
Inflation adjusted base amount (inclusive of 12% GST) (A) = Rs. 4700 per sqm
Inflation adjusted base amount (exclusive of 12% GST) (B=A*100/112) = Rs. 4196 per sqm
Consultation Paper No. 01/2024-25 Page 101 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Add GST @ 18% (C=B*18%) = Rs. 756 per sqm
Normative cost including GST (D = B+C) = Rs. 4952 per sqm
7.3.5 The Authority notes that there are capital projects initiated by AAI during the Pre-COD period and
subsequently handed over to GIAL as part of the Concession Agreement (Schedule T and U of the
Concession Agreement). The Authority has considered the capital additions of such projects also.
7.3.6 The Authority’s examination of the Capital Expenditure projected for the Third Control Period has been
explained in detail in the ensuing paragraphs:
A. Passenger Terminal and Associated works
A.1 New Integrated Terminal Building (NITB) (₹ 2194.38 crores)
i. Project Background
The LGBIA currently has only one operational Terminal (T1), which caters to both domestic and
international traffic. T1 was constructed in 1998 over approx. 20,000 sqm of area with peak hour
capacity of 850 passengers (departure + arrival) and designated capacity of approx. 2 million
passengers per annum. However, it has handled about 5.96 million passengers in FY 2023-24
which was highest traffic handled by LGBIA.
The Authority in the Second Control Period Tariff order no. 38/2017-18 dtd. 16th February’2018
for LGBIA has in principle allowed capex towards new terminal building. However, as per the
order, same would be considered on incurrence while determining tariff for third control period.
In view of constraint capacity, AAI initiated construction of NITB in 2018. As on COD, AAI
achieved 34% project progress. Further, owing to operate LGBIA on PPP mode, AAI had to
transfer the asset to new airport operator i.e. GIAL. As per clause 6.4.5 of the Concession
Agreement, the under-construction projects as on COD (majorly NITB and its associated works)
were novated to GIAL.
The NITB is currently under construction since March 2018. The planned area for NITB is
1,46,292 sqm area against the initial estimate of terminal building by AAI as 130,333 sqm. The
new terminal building is expected to have peak hour passenger handling capacity (arrival
+departure, domestic and international put together, segregated peaks) of approx. 4,527 PHP (from
4,500 PHP) with increase in area. The new terminal building will have design capacity of 13.1
MPPA.
The NITB has two main operational levels, with arrivals at the lower / apron level and departures
at the upper level. A mezzanine floor is proposed, part of which is proposed to serve as the airside
arrival corridor for passengers alighting from the PBBs and the other part is proposed to act as a
service floor for the baggage handling system used for outbound baggage. Following are the
salient features of NITB:
• Efficient design with all modern facilities and amenities;
• Centrally air-conditioned building with provision of Building Management System (BMS)
to ensure energy efficiency;
• Features designed to comply with Green Buildings norms;
• Dedicated toilets and drinking water facility in Departure, Arrival, Security Hold and
Concourse Areas;
• Baggage conveyer with inline X-ray inspection and other equipment and facilities will be
provided in departure area and inclined carousels at Arrival Hall;
• Adequate Escalators, Elevators, Automatic Sliding Doors, Passengers Boarding Bridges
etc.;
Consultation Paper No. 01/2024-25 Page 102 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
• Fire detection, alarm and protection system with fire control room;
• Public Address System, CCTV System, Flight Information Display System (FIDS) for
passenger convenience;
• Security equipment as per requirement specified by BCAS; and interventions for unique
user experience such as adequate landscaping, etc.
ii. Design improvement or changes undertaken by GIAL:
As per GIAL, AAI design required certain modification in view of stakeholders requirements,
environmental sustainability and technological interventions. As per GIAL, the proposed
interventions will significantly contribute to achieving the Service quality requirements specified
in the Concession Agreement. Following are the floor wise changes as proposed by GIAL:
a. Improvement in layout- Arrival floor
Figure 2: Proposed layout for Arrival Floor
Notes:
1. Domestic Bus Gate Lounge more area relocated for seating.
2. International Arrival Hand baggage screening (X Ray) provided more immigration
counter.
3. Domestic Arrival Bus Gate location changed for streamlined flow.
4. Domestic loading and unloading area redesigned, goods elevators added.
5. International Bus Gate Lounge proposed.
6. Increase area for Ceremonial Lounge along with dedicated parking.
7. International loading and unloading platform area increased.
8. New Restrooms are proposed for Domestic and International
9. Swing gates proposed between reclaim belts 4 & 5 as provision to cater to Peak Demand.
10. Reserve Lounge proposed.
11. Façade 20 m away compliant with BCAS norms.
b. Improvement in layout – Mezzannine Floor at 5.5 meter
Consultation Paper No. 01/2024-25 Page 103 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Figure 3: Proposed layout for Mezannine Floor
Note:
1. Swing gate for Contact stands 9 & 10 for domestic arrival peak operations proposed, in
addition to arrival corridor.
2. Area increased for AOCC, SOCC, IT, ALCR Room, Toilet modifications etc.
3. BOH Store added, SHA circulation added for last boarding bridge (FLB#1)
4. Baby Care Room Added.
5. Landside canteen, Staff Lockers added.
6. Re-arrangement of X-Ray, AHU Rooms, addition of Central Screening Room.
7. Storage space & garbage storage (cold store) added.
8. Mobile network control, IT rooms added, AHU room shifted.
c. Improvement in layout – Departure Floor at 10 meter
Figure 4: Proposed layout for Departure Floor
Notes:
1. SHA Gate seating and circulation added for Gate 1 boarding bridge (FLB#1)
2. Boarding gate rearrangement proposed, by rearranging seating.
3. Addition of Visual Level-4 check rooms for domestic & international.
4. Introduction of ATRS Machines, Modifications in emigration area.
5. New Restrooms, drinking water facility proposed to reduce walking distance.
6. Airline ticketing counter with passenger seating space, reserve lounge, Airport Operator
Seating added.
Consultation Paper No. 01/2024-25 Page 104 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
7. Check-in Island -Dual takeaway conveyors with set of power curves to offset the distance
from cutout.
8. Compliance with BCAS norms (façade distance from alighting point).
9. Vestibule –5 Nos.
d. Improvement in layout – Departure Mezzanine Floor at 15 meter
Figure 5: Proposed layout for Departure Mezzanine Floor
Notes:
1. Proposed the Day/ Retiring room along with services.
2. Storage space & garbage storage (cold store) added.
iii. A comparison of previous design and proposed design by GIAL for NITB
The proposed change in the design will lead to marginal increase in Peak Hour Capacity (PHP)
of the terminal. As per GIAL submission, Following is the area wise comparison between
previous and proposed design:
Table 77 : Details of Change in area proposed by GIAL over previous design
S. Floor/Component Built up area (sqm) Remarks
No. wise
Previous Revised
design
design
1. Basement 8240 9471 In order to adhere to fire safety
regulations, there is a proposal
to expand the fire corridor.
2 Arrival 43144 54418 In the proposal by GIAL,
compliance with BCAS Norm
w.r.t. maintaining the Arrival
Façade 20m away from
alighting point has been
maintained.
3 Arrival Mezzanine 19775 21000 For better passenger
experience, gate lounge area
has been included. Storage area
has been proposed (Goods,
Cold storage, Garbage etc.).
4 Departure 39410 41052 For better passenger
experience, gate lounge area
has been proposed. Further the
Consultation Paper No. 01/2024-25 Page 105 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
S. Floor/Component Built up area (sqm) Remarks
No. wise
Previous Revised
design
design
compliance with the BCAS
norm, as mentioned at Sl. No. 2
of this Table above, is proposed
to be complied with.
5 Departure 14406 14993 Enhanced facilities for better
Mezzanine Floor user experience.
6 Utility Block 5358 5358 No Change in area from
previous design
Total Area-NITB 130333 146292
The Authority, through its independent consultant has reviewed the additional area
requirement. GIAL team has also demonstrated the requirement of the additional area during
site visit. In view of the above, the Authority notes that the additional area will improve
passenger facility and also it is required to comply with applicable norms. Accordingly, the
Authority proposes to consider additional area proposed by GIAL for NITB.
iv. Cost proposal of NITB
AAI has awarded contract for New Integrated Terminal Building to M/s. Shapporji Pallonji
Company Limited (SPCL). The scope of work of SPCL included civil and structural works.
As part of MYTP, GIAL submitted that the contract for construction of NITB was awarded
by the AAI on 26th Mar’2018, i.e. before COD. As per the MYTP submission of GIAL, the
cost of the project has increased significantly post award of works on account of increase in
quantities in reinforced cement concrete owing to difference in initial drawing at the time of
contract and the Good for Construction (GFC) drawings, time overrun on account of COVID-
19 pandemic and supply chain disruption owing to pandemic. Also, the design changes
proposed by GIAL led to increase in project cost towards NITB. The Authority observed that
GIAL has submitted a revised cost of NITB as ₹ 2333 crores. A cost comparison of original
sanctioned cost of AAI vis-à-vis project awarded by AAI and the cost projected by GIAL is
provided below:
Table 78: Cost comparison of NITB sanctioned originally, awarded and project by GIAL
(₹ crores)
AAI
Awarded Projected
S. No. Project detail sanctioned Remarks
by AAI by GIAL
cost
A Civil & structural works
The cost is revised on
account of area increase
Civil & structural from 90000 sqm to
works by M/s SPCL 146000 sqm (including
includes CIVIL and design related changes of
(i) 1166 1007 1541
MEP contract for 15,959 sqm), GFC
Terminal and Elevated drawings, increase in
Road quantity, rate escalation
due to COVID pandemic
etc.
Sub-Total - A 1166 1007 1541
Consultation Paper No. 01/2024-25 Page 106 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
AAI
Awarded Projected
S. No. Project detail sanctioned Remarks
by AAI by GIAL
cost
B Packages considered in AAI design but not awarded
Baggage Handling
(i) - 120
System
Passenger Boarding These equipment are
(ii) 66 - 41
Bridge required for airport
(iii) VDGS - 5 operation. AAI has
Augmentation of considered these in
(iv) - 41
power supply design however, not
Interior decoration, - awarded due to expected
(v) furnishing & furniture - 4 PPP arrangement.
(excluding art work)
(vi) Signages - - 24
Sub-Total - B 66 - 235
Costs/Scope less considered/not considered by AAI but which are essential for Airport
C
operations
(i) IT packages - - 149
(ii) Security package - - 166
Further augmentation
of Power is required to These projecs are subject
cater additional load to anticipated overall
(iii) - - 115
demand for Business airport operation plan
Lounges, Airport and stakeholder
Villages & F&B requirement, accordingly
(iv) Artwork - - 30 could not be planned by
(v) ORAT Cost - - 30 AAI at initial stage.
Trolleys, furniture,
(vi) - - 22
dustbin etc.
(vii) Misc. item - - 33
Sub-Total -C - - 545
D Culvert Work -D - - 12 Initial estimate
Total (A+B+C+D) 1232 1007 2333
v. The Authority notes that the NITB work has been awarded by AAI in 2018 and owing to
operation of LGBIA through PPP mode, the ongoing works have been novated to GIAL.
The construction progress and cost has been impacted due to change in design, COVID-19
and supply chain disruption. Further, GIAL has undertaken some of the modification in the
previous design which resulted into increase in terminal area by 15,959 sqm. The Authority
through its independent consultant has reviewed GIAL MYTP and conducted site visit of
LGBIA. In view of the GIAL submission and site visit, the Authority observed that the
proposed area would improve passenger facility and also will be required to comply with
statutory compliances. Accordingly, the Authority proposes to accept the 146,292 sqm
terminal area proposed by GIAL.
The Authority notes that the works towards terminal building are still underway and not yet
capitalized. As per GIAL, terminal building is expected to be completed in the FY’25
(Jan’25). However, during the site visit, the Authority observed that significant work is
pending towards terminal building. The project progress of NITB is ~57 % as on 31st
Mar’2024. Further, ORAT testing will also require 1-2 month before commissioning of the
terminal. In view of the above, the Authority believe that the terminal capitalization may be
achieved in FY’26 (April’25) instead of FY’25 (Jan’25) proposed by GIAL.
Consultation Paper No. 01/2024-25 Page 107 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Further, The Authority is of the view that the cost of terminal building should be completed
within the inflation adjusted normative cost basis on its normative order i.e. order no.
7/2016-17 dated June 6, 2016. Accordingly, the Authority proposes terminal cost as per
applicable normative rates plus the cost towards the works which doesn’t form part of
normative cost. As per the normative order, the normative cost proposed is excluding land
cost, diversion of facilities and site development activities namely earther filling cost and
Electricity Board Deposit. Following are the additional cost component evaluated by the
Authority through its independent consultant for the purpose of determination of cost of
NITB:
• Kerbside road – GIAL has proposed ₹ 138.60 crores towards this works. The Authority
through its Independent Consultant has evaluated the estimates of the cost proposed and
found reasonable. The Authority proposes to consider this cost.
• Electricity Board Deposit – As per the applicable electricity regulation, GIAL has to pay
mandatory deposit to DISCOM to avail additional load. Considering the mandatory
requirement, the Authority proposes to consider the same.
• Earth filling and piling works- GIAL has proposed ₹ 77 crores towards earth work and
piling works to be considered extra over normative cost. The Authority believes that the
site preparation works including earthwork was already undertaken by AAI and the cost
as proposed by AAI was within normative cost. Accordingly, this cannot be considered
separately now.
• Artwork – GIAL has proposed ₹ 30 crores towards art works. The Authority notes that
Artwork is not a mandatory expense and can be done in phases. Accordingly, the Authority
proposes to consider ₹ 5 crores towards Artworks at this stage.
• ORAT – GIAL has proposed ORAT cost of ₹ 30 crores. In view of the decision taken at
other Airports, the Authority proposes not to allow any cost towards ORAT.
Following is the proposed normative cost for the terminal building:
Table 79 : Details of cost of Terminal Building proposed by the Authority.
(₹ crores)
Particular Amount
Proposed Terminal Area (in sqm) 146,292
Normative Cost (FY’25-26) (Refer Table 75) 131,130
Terminal cost as per Normative Order-A 1918.33
Component over and above Normative cost
Kerbside road 138.60
Artwork 5.00
Sub-Total (B) 143.60
Total (C=A+B) 2061.93
Additional allowance due to North-East region
Disturbed area allowance @ 5% over (C)* 103.10
Extra labour cost component @ 12.5% (It is 64.44
assumed that project cost comprises 25% labour
cost) over (C)*
Sub-Total (D) 167.54
Electricity Board deposit (E) 41.00
Cost proposed by the Authority towards NITB 2270.46
F=(C+D+E)
Consultation Paper No. 01/2024-25 Page 108 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
*Also Considered in the Second Control Period Tariff order no. 38/2017-18 dtd. 16th February’2018 for LGBIA
(refer para 9.20)
vi. In view of the above, the Authority proposes to consider the NITB cost based on normative
benchmarks. Thereby, the cost of NITB is proposed to be ₹ 2131.86 crores (Indexed to
FY’26) excluding kerb side (₹ 2270.46 crores - ₹ 138.60 crores) against ₹ 2194.40 crores
(₹ 2333.00 crores - ₹ 138.60 crores) submitted by GIAL. As on Mar’22, the CWIP towards
NITB was ₹ 453.67 crores. The Authority accordingly considers balance cost of NITB to be
incurred during the Third Control Period as ₹ 1678.19 crores (₹ 2131.86 crores -₹ 453.67
crores).
A.2 Kerbside Development works (₹ 138.60 crores)
GIAL to facilitate smooth traffic circulation, has proposed grade separation between departure and
arrival. The overall general arrangement has been worked out to ensure smooth traffic circulation
and to cater to the estimated traffic (peak hour traffic on the main access road is estimated as
approx. 3,058 Passenger Car Unit (PCU).
At the Arrival Access level, peak hour traffic is estimated as approx. 1,080 PCUs. To cater to this
demand, three lane road is proposed as main entry road. This three lane road is proposed to flare
up to total six lane road to form about 300 mtr of Kerb to facilitate smooth passenger transition
from vehicles to the New Integrated Terminal Building (NITB). Out of the six lanes, two lanes are
proposed to be reserved for VIPs separated by 5.2 mtr of raised platform from four lanes open for
public.
At Departure Ramp (elevated), peak hour traffic is estimated as approx. 1,079 PCUs. To cater to
this demand, two lanes are proposed to be reserved for the VIP movement with an additional
dedicated Stop Lane. The Stop Lane will ensure that parked vehicles do not affect traffic circulation
in the two dedicated lanes for the VIP movement. For public, three dedicated lanes are provided
for traffic circulation with one dedicated Stop Lane.
As per MYTP, the project was awarded by AAI and carried forward by GIAL. The Authority has
reviewed the project cost and benchmarked it with similar works at another Airport. Further, the
Authority has sought detailed BoQ for the work by GIAL, GIAL has submitted Basis of rate and
following details:
Table 80: Details of cost for kerbside development
Guwahati Airport
Particular FY’25 Amount in
Area
indexed rates ₹/crores
Elevated Road 10726 84200 90.31
At-Grade road 50582 7400 37.43
Sub-Total 127.74
Add: Culvert cost 11.00
Total Cost 138.74
Note: As part of clarification, GIAL has submitted above BoQ which provides ₹ 138.74 crores cost towards
kerbside development instead of ₹ 138.60 crores submitted initially.
The Authority notes that the Culvert is outside airport boundary and the connectivity should be
provided by the State Government. As part of subsequent clarification it is understood that the state
govt already initiated the construction of culvert. In view of the same, the Authority proposes to
exclude cost considered towards culvert. Further, the project cost proposed by GIAL is compared
with the cost allowed for similar work at other Airport, the Authority observed that same is in line
Consultation Paper No. 01/2024-25 Page 109 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
considering northeast region (refer Table 79) . In view of the above, the Authority proposes to
consider kerb side development cost as ₹ 127.74 Crore (inflation adjusted cost) against GIAL
submission of ₹ 138.60 crores (inflation adjusted cost).
A.3 Existing Terminal Building Development (₹ 9.64 crores)
GIAL as part of improvement in existing terminal building proposed capex is towards fire hydrant
system, replacement of old ACs, AHU modification, fire control room related repair, upgradation
of BBA, BMA, BHS and Check in counters for smooth passenger operation, signages, terminal
refurbishment activities etc.. The Authority, through its independent consultant has reviewed the
list of capex proposed by GIAL under this head and have following observations:
- GIAL has estimated ₹ 1.50 crores worth of terminal auxiliary equipment. However has not
shared any detailed list of BoQ against this item. Since the AO has not shared any detail against
this capex and the new terminal building is expected shortly at LGBIA, the AO should
optimize any capex on existing terminal building which is not going to be used post
commissioning of NITB.
- GIAL has estimated ₹ 2.50 crores worth of facelift & refurbishment works of existing
terminal. In view of the ongoing development of NITB, the Authority believe that this capex
should not be planned.
- GIAL has considered some of the routine repair and modification works as capex, same should
be considered as part of normal repair works. These include:
i. Shifting of Repeater panel to fire control room and minor repair of existing Fire
alarm and Fire Detection system - ₹ 0.10 crores
ii. Upgradation of retiring room in terms of tiling, painting, furnishing etc. - ₹ 0.10
crores
In view of above, the Authority proposes inflationary adjusted cost as ₹ 4.82 crores (lower than
the estimated base cost on account of de-growth in inflation factor) against ₹ 9.64 crores submitted
by GIAL.
B. Runways, Taxiways & Aprons:
Following are the details of work towards Runway, Taxiway and Apron:
B.1 Apron-2 (Demolition and new-construction) (₹ 466.21 crores)
At present LGBIA has 20 nos. of Code-C equivalent stands, this comprises (Apron-1: 9 Nos. and
Apron 2: 11 Nos.). In view of the estimated demand, total 34 nos. of Code C equivalent stands are
proposed on Apron-2, considering that all commercial aircraft operation will be facilitated from the
NITB post commissioning.
As per GIAL, the existing Apron-2 is non-compliant and need to be demolished entirely (total
approx. 1,18,088 Sqm including rigid and flexible pavements) and re-construct the same. GIAL has
envisaged total Apron area of 2,66,535 Sqm of area, including approx. 34,196 Sqm of Head of Stand
Road considering future traffic demand.
Consultation Paper No. 01/2024-25 Page 110 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Figure 6: Proposed layout for Apron 2 at LGBIA
The Authority along with its independent consultant has conducted site visit of LGBIA and believes
that GIAL should explore innovative ways to revive Apron 2 for operational use. The Authority
believes that the Apron-2 can be made fit for use by applying a PQC overlay, adopting new drainage
technology with pre-fabricated drains and adopting trenchless technology for underground utilities
and pipelines. These advices were agreed in-principle by the AO for necessary examination and
consideration, as otherwise dismantling in operational area could have posed an operational hazard
and created many operational constraints/issues. Accordingly, the Authority after site visit along with
its Consultant and AO has considered re-examining the restoration of existing Apron by providing
pre-cast drains, recasting the apron wherever required, and constructing an additional apron area of
only 148,447 sqm.
In term of cost, The Authority, through its consultant also verified the estimate provided by GIAL.
The Authority notes that the rates adopted by GIAL are more than the inflation adjusted normative
rates provided at para 7.3.4. The inflation adjusted normative rates of FY’2026 (based on expected
start date of works) has been considered by the Authority for completion of new Apron Area. In case
of repair works, the Authority has considered 50% of the rates adopted for new construction. While
arriving the normative cost, the Authority has adjusted the normative cost as per para 7.3.4 on account
of disturbed area allowance of 5% and extra labour cost component of 12.5% on account of north
east region. Following is the adjusted normative cost for FY’2026:
Table 81: Details of normative cost for Runway/Taxiway/Apron works
Particular Amount in
Rs/Sqm
Inflation adjusted normative cost for FY’26 6932
Additional allowance due to North-East region
Disturbed Area allowance @ 5% 347
Extra labour cost component @ 12.5% (It is assumed 217 564
that project cost comprises 25%* labour cost)
Inflation and NER adjusted normative cost 7496
Add: Airside working area constraints @ 5% 375
Propose normative cost per sqm 7871
Consultation Paper No. 01/2024-25 Page 111 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Similarly, in case of drainage works, the Authority proposes GIAL to optimise cost by adopting
innovative technology and design to minimise cost. The Authority for the purpose of drainage works
proposes to consider 50% of the rates proposed by GIAL. Further, the Authority notes that as per the
normative order the normative cost excludes earth work cost upto sub-grade level and AGL works.
Accordingly, these have been considered over and above the normative cost. As per GIAL
submission the estimated base cost of the project is ₹ 410.55 crores and inflation adjusted cost is ₹
466.21 crores. The summary of the Authority’s proposal in this regard is detailed below vis a vis
GIAL submission:
Table 82: Details of the cost submitted by GIAL and proposed by the Authority towards
Apron works
(₹ crores)
As pre GIAL As per the Authority
Particular UoM Rate Qty Amount Rate Qty Amount
Demolition of Sqm 1400 7086* 0.99 - - -
flexible Pavement
Demolition of Sqm 4070 111002* 45.18 - - -
Rigid Pavement
New Pavement
(Apron)
Rigid Pavement Sqm 13800 232339 320.63 7871 121337 95.50
Flexible Sqm 7800 34196 26.67 7871 27110 21.34
Repair works
Rigid Pavement Sqm - - - 3936 111002 43.68
Flexible Sqm - - - 3936 7086 2.79
Drainage Rmt 125000 1366 17.08 60000 1366 8.20
Sub-Total (A) 410.55 171.51
Cost towards Included 52.15
earthwork upto above
sub-grade level
AGL cost @15% Included 17.53
towards new apron above
works
Inflation adjustment 55.66 Factored
in
normative
cost
Total Cost 466.21 241.19
*As discussed during site visit, the existing apron dismantling can be avoided by usage of
prefabricated drains to optimize this expenditure.
In view of the above, the Authority proposes to rationalise the cost and the scope of this project. The
Authority proposes to consider inflation adjusted cost of ₹ 241.19 crores against ₹ 466.21 crores
submitted by GIAL towards Apron-2 works.
B.2 Airside Storm Water Drainage work (₹ 208.38 crores)
GIAL as part of MYTP and during site visit submitted that existing drainage system is insufficient
to runoff storm water. Some of the section of the Airport has temporary drainage system and there is
no operational airside drainage system. Additionally, the existing airside drainage system lacks
Consultation Paper No. 01/2024-25 Page 112 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
continuity, and GIAL intends to establish connectivity and create a closed-loop system. Following
are few pictures of drainage system available at GIAL:
Figure 7: Existing drainage system at LGBIA
The Authority has noted the points raised by GIAL in MYTP proposal. The Authority through its
independent consultant has taken a note of the drainage condition at LGBIA and believes that in
order to have faster run off of storm water it is necessary to have robust storm water drainage system
in place. However, the Authority also raised a point to GIAL that the drainage system will be
successful only if the airport system is connected to well-planned external drainage system outside
Airport. The GIAL has clarified that the AO is already working/coordinating with local body to make
integrated drainage system so that the storm water does not push back to the Airport. In view of the
above, the Authority proposes to consider the capex towards storm water drainage system. During
the cost analysis, the Authority observed that some of the rates proposed by GIAL consider 10%
overhead on account of airside working area constraints. The same has been revised by the Authority
to 5%. Rates considered by GIAL are in line with rates allowed by the Authority at other Airports.
Following is the basis of the base cost considered by the Authority towards this project:
Table 83: Authority’s examination of Airside Storm Water Drainage cost
(₹ crores)
Particular GIAL submission Authority Examination
Quantity Rate Amount Quantity Rate Amount
Drainage 16632 96000 159.67 16632 92000 153.01
Culvert 2220 138125 30.66 2220 138125 30.66
Pipe 460 51000 2.35 460 51000 2.35
crossing
Base Cost 192.67 186.02
Inflation 15.71 8.66
adjustment
Total 208.38 194.68
Further, during the site visit it was observed that no work has started against this project. Accordingly,
the capitalisation of the project is proposed to be shifted by one year from FY’25 to FY’26.
The Authority has further adjusted cost on accounf of inflation, in view of above analysis proposes
to consider ₹ 194.68 crores as inflation adjusted cost as against ₹ 208.38 crores submitted by GIAL
towards this project.
B.3 Construction of Part Parallel Taxiway and Link Taxiways (₹ 199.02 crores)
Consultation Paper No. 01/2024-25 Page 113 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
The existing peak capacity of the Runway 02-20 is 18 ATMs (Arrival & Departure) per hour. The
peak ATM per hour is estimated to be 22 (Arrival & Departure) in FY 2026-27. To facilitate this
increase in ATM and ensure operational efficiency, it is proposed that a Part Parallel Taxiway of total
1,00,861 Sqm including shoulders. Further, GIAL has also proposed additional three link taxiways,
with total area of 15,845 sqm. As per GIAL the additional three link taxiways will improve
operational efficiency.
The Authority has noted GIAL submission and as per site visit as well as GIAL presentation it is
observed that additional link taxiways are proposed at both side of the runways 02 and 20. This will
enable faster exit of aircrafts from the runway and increasing runway availability for airport
operation. Also, one of the link taxiways towards runway 20 end will be required to give additional
access to Apron 2 in front of NITB. In view of the operational requirement, the Authority proposes
to consider the capex towards part parallel taxiway and link taxiways.
The Authority through it’s independent consultant analysed the cost proposed by GIAL towards this
capex and observed that the cost proposed is higher than the normative cost provided under order no.
07/2016-17 dtd. 6th June,2016. In view of this, the Authority proposes to consider inflation adjusted
normative cost as derived under 7.3.4 above to arrive the cost of the project. The Authority, further
adjusted inflation adjusted normative cost on account of disturbed area allowance of 5%, extra labour
cost component of 12.5% of 25% labour cost on account of north east region and 5% on account of
airside working area constraints and arrive at a normative cost of ₹ 7871 per sqm (refer Table 81).
Further, the Authority notes that as per the normative order the normative cost excludes earth work
cost upto sub-grade level and AGL works. Accordingly, these have been considered over and above
the normative cost. Following is the basis of the cost considered by the Authority towards this project:
Table 84: Authority’s examination of Part Parallel Taxiway and Link Taxiway cost
(₹ crores)
Particular GIAL submission Authority Examination
Quantity Rate Amount Quantity Rate Amount
Main Pavement 81275 15400 125.16 81275 7871 63.97
(Flexible)
Shoulder (Flexible) 35431 15100 53.50 35431 7871 27.89
Total 178.66 91.86
Add: Excavation till Included 48.11
subgrade above
Add: AGL@ 15% Included 13.78
base cost above
Inflation adjustment 20.36 Factored in
normative
cost
Total Cost 199.02 153.75
Further, during the site visit it was observed that no work has started against this project, accordingly,
the capitalisation of the project is proposed to be shifted by one year from FY’25 to FY’26.
In view of the above, the Authority proposes ₹ 153.75 crores as inflation adjusted cost against GIAL
submission of ₹ 199.02 crores inflation adjusted cost.
B.4 Land Development Works (₹ 189.73 crores)
As per GIAL, a significant portion of the LGBIA lies at lower elevation. Accordingly, GIAL has
proposed filling and site grading area of around 605,750 sqm to prevent the risk of flooding and to
Consultation Paper No. 01/2024-25 Page 114 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
make these areas suitable for various airside and associated facilities. A figure below provides details
of low-lying area at LGBIA:
Figure 8: Low lying area at LGBIA
As per GIAL submission and the site visits of LGBIA Airport, the Authority notes that the identified
low-lying areas are required in airside works in this control period and may be required for future
expansions. GIAL has divided the low-lying areas in four zones. The Authority notes from GIAL
submission and also on the basis of the site visit, that the proposed land development work can be
done in phased manner and also the AO need to optimise on the proposed cost towards land
development. Further, the Airport Operator has not demonstrated the concrete plan to overcome this
low lying area, no topographical analysis was shared and possibility of phasing of the proposed plan
have not been shared. Upon reviewing the site-level charts, the approach to filling low-lying areas
remains unclear. Consequently, the consultant independently identified these areas, as marked in
Figure 8. Accordingly, the Authority proposes to consider 25% cost for land development works for
the purpose of third control period. AO can plan the land development for the balance portion after
assessing the critical operational requirements. Following is the basis of the base cost considered by
the Authority towards this project:
Table 85: Authority’s examination of cost pertaining to land development works:
(₹ crores)
Particular GIAL submission Authority Examination
Quantity Rate Amount Quantity Rate Amount
A. Earth Work Package-Site
Clearance
Clearing and Grubbing Airfield 605750 70.80 4.29 151438 70.80 1.07
Land. (Clearing and grubbing
airfield land by dozer and grader
including uprooting vegetation,
grass, bushes, shrubs and saplings
etc, removal of slush including top
soil not exceeding 150 mm in
thickness and disposal of organic
unserviceable soil/materials at
designated location & spreading in
the low lying areas approved by
engineer in charge within project
site and stacking of serviceable
Consultation Paper No. 01/2024-25 Page 115 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Particular GIAL submission Authority Examination
Quantity Rate Amount Quantity Rate Amount
material to be used or auctioned with
all lifts and lead. Item includes the
compaction of ground surface as per
specifications section 201 of
MORTH specification for Road and
Bridge works (5th Revision) [Item
no. 1.02 shall be operative for
removal of slush/sludge having
depth more than 300 mm]
Removal of slush/sludge including 122065 300.90 3.67 30516 300.90 0.92
dewatering and disposal of the same
in designated areas conforming
environmental norms with all
labours, equipments, consumables,
tool tackles, leads and lifts etc.
complete as per instruction of the
Engineer In charge.
Providing, installing and 25000 129.80 0.32 6250 0.08 0.08
maintaining required capacity
dewatering pumps with all
accessories, pipelines, labour,
materials, consumables, tools tackles
etc. complete along with
construction of temporary
trenches/ditches (if require any) for
draining out water from the project
battery limits, including obtainment
of all statutory permissions from the
concerned authorities.
B. Earth work package-
Earthwork
Excavation in all types of soil 138850 282 3.91 34713 282 0.98
(excluding soft and hard rock) for
airfield work upto a depth of 500
mm, including cutting and loading,
trimming bottom and side slopes, in
accordance with requirements of
lines, grades and cross sections as
per drawings and Technical
Specifications section 301 of
MORTH specification for Road and
Bridge works (5th Revision) and
disposal of the excavated earth to the
designated location(s) with an
average lead of 4 Km or as directed
by the Engineer in charge.
Supplying, filling, spreading and 218070 1392 30.35 54518 1392 7.59
compacting of Moorum borrowed
from outside approved sources, in
uniform layers to the required
alignment , grades and cross-
sections, not exceeding 250 mm
compacted thickness of each
layer and compacted to 95% of
MDD & the requirements of
technical specifications. Borrowed
Consultation Paper No. 01/2024-25 Page 116 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Particular GIAL submission Authority Examination
Quantity Rate Amount Quantity Rate Amount
moorum shall comply CBR value ≥
8% and other parameters in
accordance with drawings,
Technical Specifications section 305
of MORTH for Road and Bridge
works (5th Revision) or as per
direction of the Engineer In
Charge.The unit rate shall be
deemed to include cost of all
material, labour, equipments, tools
tackles, royalty, transportation and
sampling, testing and supervision
required for the work.
Supplying, filling, spreading and 545175 1392 75.87 136294 1392 18.97
compacting of River sand borrowed
from outside approved sources, in
uniform layers to the required
alignment , grades and cross-
sections, not exceeding 250 mm
compacted thickness of each
layer and compacted to 90% of
MDD & the requirements of
technical specifications. Borrowed
river sand shall comply CBR value ≥
8% and other parameters in
accordance with drawings,
Technical Specifications section 305
of MORTH for Road and Bridge
works (5th Revision) or as per
direction of the Engineer In Charge.
The unit rate shall be deemed to
include cost of all material, labour,
equipments, tools tackles, royalty,
transportation and sampling, testing
and supervision required for the
work.
Supplying, filling, spreading and 327105 1392 45.52 81776 1392 11.38
compacting of Hilly soil borrowed
from outside approved sources, in
uniform layers to the required
alignment , grades and cross-
sections, not exceeding 250 mm
compacted thickness of each
layer and compacted to 95% of
MDD & the requirements of
technical specifications. Borrowed
Hilly soil shall comply CBR value ≥
8% and other parameters in
accordance with drawings,
Technical Specifications section 305
of MORTH for Road and Bridge
works (5th Revision) or as per
direction of the Engineer In Charge.
The unit rate shall be deemed to
include cost of all material, labour,
equipments, tools tackles, royalty,
Consultation Paper No. 01/2024-25 Page 117 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Particular GIAL submission Authority Examination
Quantity Rate Amount Quantity Rate Amount
transportation and sampling, testing
and supervision required for the
work.
Providing & Laying of Geotextile 215798 183 3.95 53949 183 0.99
(specs as per Dhamra Airport)
Base Cost 167.88 41.97
Inflation adjustment 21.85 1.80
Total Cost 189.73 43.77
The Authority has further adjusted the base cost derived above on account of inflation. Accordingly,
the Authority proposes to revise the inflation adjusted cost to ₹ 43.77 crores against GIAL
submission of ₹ 189.73 crores respectively.
B.5 Widening of Runway Basic Strip (₹ 87.17 crores)
GIAL as part of MYTP submitted that the width of existing runway strip is 75m on both sides from
the center line of the Runway. Existing runway width does not meet DGCA compliance standards.
As per the standards for Precision Approach Runway, the Runway Strip shall, wherever practicable,
be extended laterally to a distance of at least 140m on each side of the centre line of the runway and
its extended centre line throughout the length of the strip. Accordingly, to comply with the statutory
requirement, widening of the Runway Basic Strip to 140m is proposed. For this, site grading works
will be required to be carried out over approx. 5,41,530 Sqm of area.
The Authority, in view of the safety and compliance with applicable standards proposes to consider
this capex. However, the Authority observed that while calculating of the cost for the works, GIAL
has considered 10% additional cost on account of airside working area constraints. This has been
revised by the Authority to 5% while arriving cost for this work. Following is the basis of the base
cost considered by the Authority towards this project:
Table 86: Authority’s examination of widening of Runway Basis Strip
(₹ crores)
Particular GIAL submission Authority Examination
Quantity Rate Amount Quantity Rate Amount
Site Grading 541530 1460 79.06 541530 1390 75.27
Base Cost 79.06 75.27
Inflation 8.11 1.79
adjustment
Total Cost 87.17 77.06
The Authority further adjusted the above cost on account of inflation. Accordingly, the Authority
proposes inflation adjusted cost of widening of Runway Basic Strip as ₹ 77.06 crores against GIAL
submission of ₹ 87.17 crores.
B.6 Construction of Second Part Parallel Taxiway (₹ 81.64 crores)
Second Part Parallel Taxiway of Code C (total area: approx. 46,546 Sqm) is proposed to ensure safety
and operational efficiency. The Second Part Parallel Taxiway will facilitate seamless operation, i.e.
movement of departing aircrafts can take place irrespective of movement of arriving aircrafts, which
is imperative to facilitate the projected ATMs.
The Authority notes that LGBIA is a gateway to eastern India and keeping in view the expected
growing demand, it is important to increase airside capacity. GIAL submitted that in lieu of Second
Consultation Paper No. 01/2024-25 Page 118 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Part parallel taxiway the Apron 2 will have only one connection due to which departing aircraft has
to wait for pushback until clearance of parallel taxiway by the arriving aircraft.
Figure 9: Proposed aircraft movement at part parallel taxiway
In view of this Authority proposes to consider this capex. However, the Authority observed that the
cost proposed is higher than the normative cost provided under order no. 7/2016-17 dtd. 6th
June,2016. In view of this, the Authority proposes to consider inflation adjusted normative cost as
derived under 7.3.4 above to arrive the cost of the project and additional adjustment as per Table 81.
The normative cost thus arrived is ₹ 7871 per sqm.
In view of the above, the Authority proposes inflation adjusted cost as ₹ 60.84 crores against ₹ 81.64
crores submitted by GIAL.
B.7 Extension of Runway 02-20 towards RWY 20 (₹ 51.61 crores)
LGBIA has a single runway, 02-20, which is 3,103 meter in length and 45 meter in width. GIAL
proposes to extend it by 557 meter (admeasuring total 33,420 Sqm, out of which 25,065 Sqm is
runway pavement and 8,355 Sqm is shoulder), to ensure compliance and improve operational
efficiency of the proposed Apron-2.
The Authority notes that this capex is required in line with newly constructed NITB. The Authority,
through its independent consultant reviewed the BoQ submitted by GIAL. The cost of the project is
derived considering demolition of 600 sqm pavement area and construction of 33420 flexible
pavement area. While doing rate analysis, it is observed that the rates considered by GIAL for
pavement works are higher than the rates provided under order no. 7/2016-17 dtd. 6th June,2016. In
view of this, the Authority proposes to consider inflation adjusted normative cost as derived under
7.3.4 above to arrive the cost of the project and additional adjustment as per Table 81. The normative
cost thus arrived is ₹ 7871 per sqm. Further, during the site visit it was observed that no work has
started against this project. Accordingly, the capitalisation of the project is proposed to be shifted by
one year from FY’25 to FY’26. Following is the basis of the cost considered by the Authority towards
this project:
Table 87: Authority’s examination of Extension of Runway cost
(₹ crores)
Particular GIAL submission Authority Examination
Quantity Rate Amount Quantity Rate Amount
Demolition of Flexible 600 1400 0.08 600 1340 0.08
Pavement
New Pavement
Consultation Paper No. 01/2024-25 Page 119 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Main Pavement 25065 15400 38.60 25065 7871 19.73
(Flexible)
Shoulder Pavement 8355 11100 9.27 8355 7871 6.58
(Flexible)
Total 47.96 26.39
Add: Excavation till Included 9.39
subgrade above
Add: AGL@ 15% Included 3.95
base cost (excluding above
demolition if any)
Inflation Adjustment 3.65 Factored in
normative
cost
Total 51.61 39.72
In view of the above, the Authority proposes inflation adjusted cost of ₹ 39.72 crores against GIAL
submission of ₹ 51.61 crores.
B.8 Construction of new Isolation Bay (Rigid Pavement) (₹ 30.89 crores)
At LGBIA, currently, the Isolation Bay is accommodated on the Apron-2, in front of existing Hangar.
As per the MYTP the area of isolation bay will be required for aircraft stands. Accordingly, GIAL
has proposed to construct a new Isolation Bay beside the Apron-1, towards RWY 02 end (vacant
land) to meet the regulatory requirement. As per GIAL, this is also in line with the AAI proposal.
Isolation bay is a mandatory parking space required at the Airport to handle aircraft facing an
exigency like hijack or bomb threat, In view of the statutory requirement and compliance, the
Authority proposes to consider this capex. However, it is observed that the cost proposed is higher
than the normative cost provided under order no. 7/2016-17 dtd. 6th June,2016. In view of this, the
Authority proposes to consider inflation adjusted normative cost as derived under 7.3.4 above.
Further, it is noted that the proposed work is expected to complete in FY’25, Accordingly, the
Authority considered the normative cost as arrived for FY’25. Following is the adjusted normative
cost proposed for isolation bay related works:
Table 88: Normative cost for Apron (FY’25)
Particular Amount in
Rs/Sqm
Inflation adjusted normative cost for FY’25 6685
Additional allowance due to North-East region
Disturbed Area allowance @ 5% 334
Extra labour cost component @ 12.5% (It is assumed that 209 543
project cost comprises 25%* labour cost)
Inflation and NER adjusted normative cost 7228
Add: Airside working area constraints @ 5% 361
Propose normative cost per sqm 7589
The Authority proposes to consider ₹ 7589 per sqm to arrive cost towards isolation bay. Following is
the detailed basis of the cost considered by the Authority towards this project:
Consultation Paper No. 01/2024-25 Page 120 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Table 89: Authority’s examination of Cost towards new isolation bay
(₹ crores)
Particular GIAL submission Authority Examination
Quantity Rate Amount Quantity Rate Amount
New Pavement
Main Pavement (Flexible) 20300 13800 28.01 20300 7589 15.41
Add: Excavation till Included 4.13
subgrade above
Add: AGL@ 15% base Included 2.31
cost (excluding above
demolition if any)
Inflation adjustment 2.88 Factored in
normative
cost
Total 30.89 21.84
In view of the above, the Authority proposes inflation adjusted cost of ₹ 21.84 crores for this project
against GIAL submission of inflation adjusted cost as ₹ 30.89 crores.
B.9 Construction of Rapid Exit Taxiway (₹ 19.73 crores)
To improve operational efficiency through reduction in Runway Occupancy Time (ROT), a Rapid
Exit Taxiway (RET) is proposed at Chainage 1,970m measured from the threshold of RWY 02 till
point of curvature of RET [length: about 305m, area: approx. 11,238 Sqm]. The proposed chainage
will facilitate exit of maximum number of Code C aircrafts.
The Authority notes that RET will be an important project to improve runway efficiency as they
allow faster exit of aircrafts and thus minimise runway occupancy. Accordingly, proposes to consider
this project. While doing rate analysis, it is observed that the cost proposed is higher than the
normative cost provided under order no. 7/2016-17 dtd. 6th June,2016. In view of this, the Authority
proposes to consider inflation adjusted normative cost as derived under 7.3.4 above to arrive the cost
of the project and additional adjustment as per Table 81. The normative cost thus arrived is ₹ 7871
per sqm.
Table 90: Authority’s examination of cost towards Rapid Exit Taxiway project
(₹ crores)
Particular GIAL submission Authority Examination
Quantity Rate Amount Quantity Rate Amount
New Pavement
Main Pavement (Flexible) 7935 15400 12.22 7935 7871 6.25
Shoulders Pavement 3303 15100 4.99 3303 7871 2.60
(Flexible)
Total 17.21 8.85
Add: Excavation till Included 4.62
subgrade above
Add: AGL@ 15% base Included 1.33
cost (excluding above
demolition if any)
Inflation adjustment 2.52 Factored in
normative
cost
Total 19.73 14.79
Consultation Paper No. 01/2024-25 Page 121 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
In view of the above, the Authority proposes ₹ 14.79 crores inflation adjusted cost for RET against
GIAL submission of ₹ 19.73 crores.
B.10 Other Minor Airside Capex (₹ 26.98 crores)
GIAL has proposed various minor capital expenditure at airside. Following are the details of the
capex proposed:
i. RWY 02-20 is proposed to be extended, as elaborated above. Accordingly, fresh
construction of RESA for RWY 02 (after reserving 60m for Blast Pad from new RWY 20
threshold) is proposed. GIAL has proposed RESA area in line with CAR which is 21,600
sqm [240 m (L) X 90 m (W)]. The Authority proposes to consider the same. However, cost
has been adjusted on account of revision of airside working area constraint overhead from
10% to 5%.
ii. Currently, Blast Pad of 30m (length, i.e. along runway centerline) x 60m (lateral) after
RWY 02 threshold is provided. To reduce the erosive effects of jet blast and propeller wash
from aircrafts, it is proposed to increase the length of the Blast Pad after RWY 02 to make
the final dimension of the Blast Pad to 60m x 60m. Additional construction works of 1,800
Sqm is proposed in this regard. This is to comply with the specifications / guidelines as
stipulated in the Aerodrome Design Manual (Doc 9157, Fifth Edition, 2020, Part 2), which
is referred to at para 3.4.11 of the CAR.
As regards RWY 20, it is proposed to construct new Blast Pad of 60m x 60m (fresh
construction of 3,600 Sqm) after the new proposed threshold of RWY 20 (i.e. after
extension of the runway).
In view of the operational requirement, the Authority proposes to consider extension of
blast pad area of 5400 sqm. The rate for the work has been adjusted on account of revision
of working area constraint allowance from 10% to 5%.
iii. GIAL need to relocate simple approach lighting system for runway 20. The proposed work
will be required due to extension of RWY 20. GIAL has submitted detailed BoQ. The
Authority reviewed the same and proposes to consider the same subject to inflationary
adjustment towards cost while indexation.
iv. Runway 02 is equipped with CAT-I Instrument Landing System (ILS) and accordingly,
the Runway is treated as ‘Precision Approach Runway’. However, currently, Simple
Approach Lighting System is installed over a distance of approx. 152m from the RWY 02
threshold. Accordingly, to comply with the Civil Aviation Requirements, ‘Precision
Approach Category I Lighting System’ is proposed over a distance of 900m from RWY
02 threshold.
The Authority during site visit has sought clarification from GIAL on the feasibility of this
project as the approach lighting need to be installed in a lake. GIAL has confirmed that the
feasibility assessment has already taken place and the project is feasible. In view of the
operational requirement, the Authority proposes to consider this capex. The Authority has
proposed to consider the capex based on the detailed BoQ submitted by GIAL subject to
inflationary adjustment while arriving at indexed cost.
v. In order to serve proposed new stand GIAL has proposed additional area of 3935 sqm for
GSE staging. GIAL has proposed Rigid pavement for the proposed GSE area. In view of
the operational requirement, the Authority proposes to consider the cost proposed by GIAL
against this head subject to inflationary adjustment while arriving indexed cost.
vi. In certain capex GIAL has not shared detailed BoQ. In view of the same, the Authority
proposes 50% of the capex proposed against these heads. These capital expenditures
include SITC of Inset fittings for Runway-Taxiway intersection at Guwahati Airport,
Consultation Paper No. 01/2024-25 Page 122 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Runway Graded Strip and RESA strengthening (up to 300mm Depth) and Apron Control.
Table 91: Details of other minor works proposed by GIAL and the Authority
(₹ crores)
S. No. Particular Year of Inflation Inflation
Capitalization adjusted cost as adjusted cost as
per GIAL per the
Authority
Construction of 2024-2025 4.21 3.80
Runway End Safety
B.10.1
Area (RESA) after
RWY 20 Threshold
Extension of Blast Pad 4.24 3.89
for RWY 02 and
B.10.2 2024-2025
Construction of new
Blast Pad for RWY 20
Relocation of Simple 0.78 0.72
B.10.3 Approach Lighting 2025
System for Runway 20
Installation of 7.38 7.18
Category-I Approach
B.10.4 2024-2025
Lighting System
towards Runway 02
B.10.5 Off-Stand GSE 2025-2026 4.60 3.50
Apron stand surface 0.32 0.31
B.10.6 revamping work in old 2024
apron
Manhole chamber 0.22 0.20
covers for all manholes
B.10.7 or pits at apron area, 2025
strip area as per ICAO
standard
Provision of new 0.19 0.17
Earthing system for
B.10.8 Runway and other 2025
associated works at
Guwahati Airport
SITC of Inset fittings 0.40 0.19
for Runway-Taxiway
B.10.9 2024
intersection at Guwahati
Airport
Upgradation of flexible 0.87 0.80
B.10.10 pavements in 2026
Operational area
Runway Graded Strip 0.18 0.09
B.10.11 2024
and RESA
Consultation Paper No. 01/2024-25 Page 123 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
S. No. Particular Year of Inflation Inflation
Capitalization adjusted cost as adjusted cost as
per GIAL per the
Authority
strengthening (up to
300mm Depth)
Airside works (Apron 1.73 1.64
surface revamping
works, Provision of new
B.10.12 2024-2026
Airfield signages, Joint
filling and cleaning of
old apron)
B.10.13 Apron Control 2024 0.21 0.10
B.10.14 Airside Equipment 2024-2026 1.65 1.58
Total 26.98 24.17
The inflation adjusted cost for minor airside capex is proposed to be ₹ 24.17 crores against ₹ 26.98
crores submitted by GIAL.
B.11 Runway Strengthening works (₹ 75.25 crores)
GIAL has proposed Runway strengthening works for the Third Control Period. As per the MYTP, the
runway re-carpeting work was undertaken by AAI in the Second Control Period. During the site visit,
the Authority, along with its Independent Consultant, observed that the Runway does not require
immediate re-carpeting except turning pad area for continued operation and runway strengthening
work can be done in next control period. However, if the condition of the runway deteriorates, GIAL
may undertake runway strengthening works in which case the Authority will consider the same on
incurrence basis subject to the reasonableness and efficiency at the time of tariff determination of next
control period.
C. Construction of Boundary Wall
C.1 Construction of Airside perimeter and service road (₹ 38.33 crores)
As per GIAL, due to widening of the Runway Strip, the existing airside roads at certain stretches (that
fall within the area proposed for widening of the Runway Strip) will require to be demolished and
new airside roads will require to be constructed. Total area of flexible pavement to be demolished
works out as approx. 23,728 Sqm and that of rigid pavement works out as approx. 1,975 Sqm,
whereas area of new airside roads works out as 47,989 Sqm.
GIAL as part of MYTP has submitted indexed cost of ₹ 38.33 crores with base cost of ₹ 33.75 crores.
The Authority as part of clarification of MYTP has sought detailed BoQ for the project. As per the
BoQ shared by GIAL, the base cost of the project has been revised to ₹ 32.13 crores. The Authority
through its independent consultant has reviewed the BoQ shared by GIAL and observed that the
quantity proposed by GIAL is in line with the proposal and the rates adopted is in line with the
applicable standards. The Authority notes that the capex will be required owing to extension of
airside and thus proposes to consider this capex. However, adjusted the cost on account of inflation
factor. The inflation adjusted cost is proposed to be ₹ 33.63 crores instead of ₹ 38.33 crores initially
submitted by GIAL.
C.2 Construction of Airside Boundary Wall (₹ 77.37 crores)
Consultation Paper No. 01/2024-25 Page 124 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
As per GIAL, owing to widening of the Runway Strip and other airside proposals, the existing airside
boundary wall at certain stretches will require to be demolished and new airside boundary wall will
require to be constructed. The proposed stretches for demolition and new airside boundary wall. Total
approx. 11,692m of existing boundary walls are proposed to be demolished and 10,450m of new
airside boundary wall is proposed to be constructed. Widening of the airside roads to 7.5m (5.5m
carriageway and 1m earthen shoulder on both sides) is proposed on stretches where airside roads are
not required to be demolished but width of the carriageway is less than 5.5m.
GIAL as part of MYTP has submitted ₹ 68.13 crores as base cost. The Authority as part of
clarification sought detailed BoQ of the proposed capex. As per the BoQ submitted by GIAL, the
base cost comes to ₹ 64.96 crores. The Authority through its independent consultant has reviewed
the BoQ. GIAL has adopted CPWD rates which have been verified and found in line. The Authority
notes that due to inclusion of new area within airside, the AO need to construct new boundary wall
and demolish existing at selected areas. Accordingly, it is proposed to consider this capex.
In view of the above, the Authority proposes inflation adjusted cost of ₹ 67.98 crores against GIAL
of ₹ 77.37 crores.
C.3 Perimeter Intrusion Detection System (PIDS) system (₹ 26.24 crores)
As per MYTP, the Authority notes that LGBIA currently does not have Perimeter Intrusion Detection
System (PIDS) along / on its airside boundary wall. As per GIAL, the airport requires PIDS as part
of its airport security infrastructure. Therefore, installation of PIDS is proposed for a stretch of
10,450m on the boundary wall.
GIAL as part of MYTP has submitted base cost as ₹ 22.88 crores. The Authority has sought detailed
BoQ against this capex. As per GIAL submission, the cost of PIDS at LGBIA is estimated based on
Lucknow Airport. GIAL has adjusted Lucknow Airport cost with inflation at 5% YoY and airside
working area constraint allowance.
In view of the security requirement, the Authority proposes to consider this capex. However, adjusted
the cost by considering correct inflation factors and removed airside working area constraint premium
as this has already been considered in reference rate adopted from Lucknow Airport.
In view of the above, the Authority proposes inflation adjusted cost ₹ 20.50 crores against GIAL
submission of ₹ 26.24 crores.
C.4 Boundary Wall (₹ 0.21 crores)
GIAL as per MYTP submitted that at some places boundary walls need to be made to protect airport
land from illegal encroachment and fencing work needs to be done. GIAL has proposed ₹ 0.20 crores
capex against this. The Authority notes that GIAL has not submitted any BoQ against this line item.
Accordingly it is proposed to consider only 50% of the capex proposed by GIAL.
D. Cargo Facility
As per AAI traffic news, LGBIA handled around 21,270 MT of Cargo in FY 2019-20 (Pre-Covid)
level. This comprises of 21,267 MT domestic volume and 3 MT international volume. Prior to the CoD
the cargo volumes are handled by AAICLAS (carved out facility).
Further, the Authority notes that as per clause 19.4.1 (a) of the Concession Agreement, Following is
relevant provision for the Cargo facility at LGBIA:
The Concessionaire shall upgrade, develop. operate and maintain the Cargo Facilities in
accordance with the provisions of this Agreement, Applicable Laws, Applicable Permits, relevant
ICAO Documents and Annexes and Good Industry Practice.
Consultation Paper No. 01/2024-25 Page 125 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
GIAL as part of the MYTP has proposed following capex phasing with respect to cargo facility:
D.1 Interim Cargo Facility (₹ 3.22 crores)
GIAL has started processing domestic cargo with capacity of 2,750 MT p.a. from June 2023 onwards.
In this regard, AERA vide order no. 41/2023-24 dated 15th March 2024 allowed GIAL to levy the
existing charges for Domestic Cargo Handling Services as per the approved Tariff for the other Cargo
Service Provider at LGBIA till 30st September 2024 or tariff determination of third control period,
whichever is earlier.
GIAL has proposed ₹ 2.31 crores towards procurement of Cargo equipment and ₹ 0.76 crores towards
minor refurbishment of old cargo building. The Authority notes that the proposed capex is largely
towards equipment and refurbishment. Further, in view of the interim cargo facility developed at
similar airport, the Authority proposes to consider the proposed capex however adjusted on account
of inflationary impact. The inflation adjusted cost comes to ₹ 3.05 crores, the Authority proposes to
consider the same.
D.2 Integrated Cargo Terminal (ICT) (₹ 23.15 crores)
GIAL has planned a new Integrated Cargo Terminal (ICT) of approx. 8652 sq, mtr. with handling
capacity of 43260 MT p.a. The planned facility is proposed to be made operational in FY25-26. The
proposed ICT facility will house both domestic inbound and outbound, International Export & Import
operations and will efficiently support regional distributions, besides facilitating the processing of
special cargo such as perishables, pharma etc.
According to GIAL, the existing terminal building shall be refurbished and converted into a new
Integrated Cargo Terminal (ICT). The estimated base cost for the refurbishment and equipment is ₹
19.95 crores.
As per GIAL, the capacity planned is correlated with the market demand. As part of MYTP, GIAL
proposed to commission this facility in FY’26. The Authority notes that there is an existing cargo
facility operated by AAICLAS at Guwahati Airport. However, in view of the Concession requirement
and encouraging market competition, the Authority proposes to consider second cargo terminal at
LGBIA. GIAL has estimated 86% market share in first year. However, considering the AAICLAS
facility, the Authority has considered 50% market share. At 50% market share, GIAL is able to utilize
40% of its facility in the first year (2026-27). Considering the long-term horizon, the Authority
proposes to allow 43260 MT cargo facility to GIAL. Following is the market share and corresponding
capacity submitted by GIAL and proposed by the Authority:
Table 92: Air Cargo demand projections, capacity of LGBIA
Particular 2020 2021 2022 2023 2024 2025 2026 2027
Volume in MT at
21270 15951 21858 22823 24296 24999 28526 34801
LGBIA
ATMs in No. 44539 23442 33572 45909 59970 60527 68050 82109
Ton/ATM 0.44 0.68 0.65 0.50 0.41 0.41 0.42 0.42
As per GIAL
Market share 14% 18% 19% 86%
GIAL expected
3500 4500 5500 30000
Volume (In MT)
GIAL capacity
(In MT)
Domestic-Interim 2750 2750 2750
Integrated Cargo
- - - 43260
Complex
Consultation Paper No. 01/2024-25 Page 126 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Particular 2020 2021 2022 2023 2024 2025 2026 2027
GIAL Capacity 2750 2750 2750 43260
As per the
Authority
GIAL Market
14% 18% 19% 50%
Share
GIAL expected
3500 4500 5500 17400
volume (In MT)
GIAL Capacity
2750 2750 2750 43260
(In MT)
As per GIAL, the cost of new cargo facility of similar size costs much higher than the proposed cost
of T-I refurbishment. Since, the cargo terminal is refurbished, GIAL has considered ₹ 10.10 crores as
part of infrastructure changes towards existing terminal building:
Table 93: Cost proposed by GIAL towards ICC Facility
(₹ crores)
Particular Amount
Other Infrastructure change at Terminal 10.10
Additional Equipment for ICT 5.20
Site Circulation/Vehicle Movement Area
4.71
(10,000 sqmt @ ₹ 4700/Sqm)
Total 19.95
The Authority notes that an additional air cargo facility/complex at Guwahati Airport will bring in
more competition which will lead to better service quality and price discovery. It will benefit north
east region and aviation stakeholders. The Authority through its independent consultant evaluated the
proposed cargo capex in line with the similar projects undertaken at other Airports and noted that the
proposed project is line with the airport requirement. in view of the same, the Authority proposes to
consider the proposed capex towards Cargo facility. However, the cost has been adjusted on account
of inflationary impact. The inflation adjusted cost proposed to be ₹ 3.05 crores for interim cargo
facility and ₹ 21.18 crores for new cargo terminal against ₹ 3.22 crores and ₹ 23.15 crores submitted
by GIAL respectively.
E. Fuel Farm Infrastructure
At present various Oil Marketing Companies (OMCs) (IOCL, RIL, BPCL and HPCL with storage
facility of 800KL, 140KL, 800KL and 200KL respectively) have their respective fuel tanks and
refuelling facilities at Guwahati Airport. OMCs manage the operations on their own, and currently
operating expenditure and other charges are embedded in Aviation Turbine Fuel (ATF) fuel price.
Therefore, as on date there is no concept of open access facility at the Airport. IOCL and RIL are
located within the Airport premises whereas BPCL and HPCL are located outside. GIAL in line with
the Concession Agreement has planned open access facility for fuel farm. It has proposed following
capital expenditure for Fuel Farm infrastructure at LGBIA during third control period:
Table 94: Details of Fuel farm capex submitted by GIAL
(₹ crores)
S. No. Particular Base Cost as per Remarks
GIAL
E.1 Fuel Storage tank 119.97 New facility proposed by GIAL
E.2 Fuel Hydrant line 142.72
Consultation Paper No. 01/2024-25 Page 127 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
S. No. Particular Base Cost as per Remarks
GIAL
E.3 Equipment Cost 3.00 GIAL planned to procure three refueller
as part of interim arrangement
E.4 Procurement of 10.00 GIAL has estimated procurement of
IOCL and RIL IOCL and RIL asset in line with AMD
assets and LKO.
E.5 Dead Stock 13.94 Required for operating new facility
Total 289.63
GIAL planned new Fuel Farm Facility near to Apron 1 which is very far from upcoming Apron 2. This
will require construction of approximately 7 Km hydrant system.
Figure 10: Proposed Hydrant System at LGBIA
The Authority, during the site visit asked GIAL to evaluate alternate location for fuel farm which can
be closer to the Apron 2. In case the facility is planned closer to Apron 2, there will be significant
saving toward construction of hydrant line. However, GIAL has not proposed any alternative plan or
cost benefit analysis.
Secondly, there is a proposal by Petroleum & Natural Gas Regulatory Board (PNGRB) to connect
Brown field and Green field Airports with dedicated ATF pipeline network. On such connection, Fuel
Tank requirements will reduce substantially.
GIAL is directed to examine shifting of fuel farm near to Apron 2 and proposal of PNGRB. Hence, the
Authority proposes not to consider any capital expenditure towards new facility for the fuel farm at this
stage. However, if fuel facility is developed after examining both the issues, cost will be trued up in
next control Period, subject to reasonability and efficiency.
As CAPEX has been allowed on incurrence basis, subject to reasonability and efficiency,
corresponding revenue and OPEX has been considered. In order to support operational requirement,
the Authority proposes to consider capex toward procuring of three refueler and procurement of IOCL
and RIL assets. GIAL has considered the cost in line with the similar cost in case of Lucknow and
Ahmedabad Airport. The Authority, through its independent consultant has verified the same and
found in order. GIAL has estimated ₹ 13.00 crores as base cost and ₹ 13.65 crores inflation adjusted
cost. The Authority has adjusted the base cost considering the proposed work will get completed in
FY’25. The inflation adjusted cost as per inflation factors considered in para 7.3.4 comes to ₹ 13.31
Consultation Paper No. 01/2024-25 Page 128 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
crores. The Authority proposes to consider ₹ 13.31 crores towards this project against ₹ 13.65 crores
estimated by GIAL.
F. Vehicles (₹ 39.78 crores)
As part of MYTP, GIAL has proposed to procure various vehicles during third control period for
operational requirement. The Authority has reviewed the list of vehicles provided by GIAL and have
following observations:
i. GIAL has planned conversion of diesel cars to electric vehicles. It is estimated that total 17
vehicles will be required by GIAL including one large EV i.e. Bus. GIAL has shared online
quotation of electric bus which is around ₹ 2.00 crores. GIAL has estimated total cost of ₹
11.00 crores for these 17 vehicles. The Authority believes that same is on higher side,
accordingly, the estimated cost of E-vehicles other than large EV considered to be 50%, i.e.
₹ 4.5 crores. The cost is thus proposed to be ₹ 6.50 crores against ₹ 11.00 crores requested
by GIAL.
ii. GIAL estimated two tractors for shifting from nursery and other site-based work
requirements. Also, added two electrical buggies with loader attachment and trolleys for
plants movement. The base cost estimated to be ₹ 0.20 crores. Same seem to be on higher
side compared to market rates. Thus, the Authority proposes to consider ₹ 0.10 crores.
iii. GIAL has planned to procure two ambulances during third control period to replace existing
ones. GIAL has proposed ₹ 0.75 crores for two ambulances. The Authority, in line with the
market rates proposes to consider ₹ 0.50 crores for these ambulances.
iv. In case of CFT, GIAL submitted that LGBIA has 3 Rosenbauer CFTs which are more than
12 years old. Hence, it is planned to procure two new CFTs in FY-24 and FY-25 to replace
2 CFTs. GIAL has proposed base cost of ₹ 23.98 crores for two CFTs and shared supporting
purchase order and custom duty details. The Authority through its independent consultant
reviewed the same and found in order. In view of the operational requirement, the Authority
proposes to consider this capex.
v. For other vehicles, cost and requirement, as submitted by GIAL has been accepted, subject
to inflationary adjustment.
vi. In view of the above, the Authority proposes ₹ 34.93 crores as base cost toward vehicles
proposed to be procured during third control period against the cost of ₹ 39.78 crores
estimated by GIAL. The proposed cost is also adjusted on account of inflation adjustment
indexation. Following is the asset wise comparison of GIAL proposal vis a vis cost proposed
by the Authority:
Table 95: Cost proposed toward Vehicles by the Authority for the Third Control Period
(₹ crores)
S. No. Year of GIAL Authority
capitalization
Particular Indexed Base Indexed
Base cost Cost cost Cost
F.1 Vehicles 2024-2027 11.00 12.58 6.50 6.73
F.2 Modified vehicle for 2025-2026
3.00 3.39 3.00 3.13
BDDS equipment
F.3 Vehicle recovery Van 2024 0.15 0.16 0.15 0.15
F.4 2 Nos. tractor with
trolleys & electric 2025-2026
buggies to shuttle 0.20 0.23 0.10 0.10
nursery between the two
Terminals
Consultation Paper No. 01/2024-25 Page 129 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
S. No. Year of GIAL Authority
capitalization
Particular Indexed Base Indexed
Base cost Cost cost Cost
F.5 Ambulance 2025 0.75 0.87 0.50 0.52
F.6 Crash Fire Tender 2024-2025 23.98 25.81 23.98 25.00
F.7 Quick Reaction Team 2025
0.70 0.77 0.70 0.72
(QRT) Vehicle
Total 39.78 43.81 34.93 36.36
G. Plant & Machinery (₹ 180.93 crores)
GIAL has proposed procurement of various equipment for operational requirements. The Authority notes
that GIAL has planned for the procurement of machinery and equipment towards achievement of green
initiatives norms and to ensure safety and security of operations and the fulfilment of regulatory
requirements mandated by agencies like BCAS. Following are the key capital items proposed in third
control period:
Oil Water Separator (OWS) – As part of environment compliance, GIAL has proposed to install oil
water separator at select locations on the airside. It separates oil from the wastewater from aprons, hangar,
cargo facility, GA & GSE workshop etc.. GIAL has planned 5 units of oil water separator. Keeping in
view the tariff level, the Authority believes that there is a need to rationalize capital expenditure.
Accordingly, the Authority proposes to consider three OWS instead of five OWS sought by GIAL.
Triturator- As per GIAL, this facility is required for safe and hygienic disposal of waste from aircraft
toilets to ensure compliance with safety and environment regulations. Liquid waste from aircraft shall be
treated at Triturator as a primary treatment & further will be pumped to STP for secondary treatment.
This facility is proposed on the northeast side of T2. The Authority through its independent consultant
has evaluated the capex submitted by GIAL and observed that GIAL has considered 15% additional mark
up over the base cost of Triturator which is not supported by any requirement. The Authority, in view of
the capex optimization proposes to remove 15% mark up and proposes base cost of ₹ 3.06 crores against
₹ 3.47 crores initially submitted by GIAL.
Body Scanner – GIAL has estimated requirement of 13 body scanner at LGBIA. The Authority notes
that GIAL estimates on higher side as even the major Airport hub in India doesn’t have such magnitude
of body scanner. In view of this, the Authority proposes to consider only 5 body scanners at LGBIA. In
terms of costing, GIAL has considered ₹ 3.40 crores each. The Authority has examined the cost estimated
by GIAL. The Authority notes that in case of Lucknow Airport, the cost towards body scanner has been
allowed as ₹ 3.00 crores each. In view of the same, the Authority proposes to consider rates allowed in
case of Lucknow Airport with inflationary adjustment. The inflation adjusted cost comes to ₹ 3.21 crores
each at FY’23 level and the overall cost for the project during third control period proposed to be ₹ 16.99
crores against ₹ 51.49 crores submitted by GIAL.
Safety and Security related project – GIAL has submitted various projects related to safety and security
of the Airport. This includes firefighting equipment, disable aircraft removal kit, X-Ray, HHMD, DFMD,
ETDs. In view of the safety and security requirement, the Authority proposes to consider this capital
expenditure. However, the cost of these items have been corrected on account of inflationary adjustments.
Further, GIAL has also proposed capital expenditure towards Security Operational Control Center
(CISF), Security Surveillance Centre (SSC), CCTV set up, Container Tubular Shooting range and Video
Surveillance system. The Authority notes that GIAL has not shared any further break up or basis against
this capex. Further, it is believed that there is scope of cost optimization against these capex. Accordingly,
minimize impact on tariff, the Authority proposes 50% cost against GIAL submission.
Repair & Maintenance work - GIAL has considered repair and maintenance work of airside amounting
Consultation Paper No. 01/2024-25 Page 130 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
to ₹ 0.32 crores as capital expenditure. The Authority proposes to not consider the same as part of capex
as it is not in the nature of capital expenditure.
Miscellaneous works – GIAL has provided list of minor plant & machinery works. The Authority has
reviewed the list of minor works shared by GIAL and noted that these are mainly for upgradation and
modification of existing facility. In view of the operational requirement, the Authority proposes to
consider the same.
Visual Docking Guidance System (VDGS) – GIAL has estimated 24 nos of new VDGS and supported
cost of VDGS with price quotation. As per the document the VDGS is expected to cost ₹ 0.50 crores
each. In view of the price discovery document submitted by GIAL, the Authority proposes to consider
this capex. The proposed inflation adjusted cost is ₹ 12.74 crores against GIAL submission of ₹ 13.89
crores.
Others – GIAL has also estimated various equipment. However, has not shared any details for the
estimates. In view of the absence of further details and optimisation of tariff levels, the Authority proposes
50% cost towards this capex. Further, in view of the project priority and minimal impact on tariff, the
Authority proposes not to consider some of the environment related project related to carbon sequestration
and biodiversity preservation projects.
Further, the cost proposed by the Authority towards plant & machinery is further adjusted on account of
inflation while arriving indexed cost. Following is the comparison of capex proposed by the Authority
vis a vis GIAL:
Table 96: Details of Plant and Machinery submitted by GIAL and proposed by the Authority
(₹ crores)
Year of GIAL Authority
S. No. Particular Capitalization
(as per GIAL) Base Indexed Base Indexed
Cost Cost Cost Cost
G.1 Oil Water Separator-5 nos. 2025, 2026 23.60 26.80 13.50 14.13
G.2 Triturator 2025 3.47 3.83 3.06 3.13
G.3 Hazardous Waste Storage 2025, 2026 0.49 0.55 0.24 0.25
Reticulation of utilities to
G.4 2026, 2027 8.39 9.78 4.19 4.48
new facilities
SITC of LED type SPOL
System at Sajanpara, Borsilla
G.5 2024 0.06 0.06 0.03 0.03
& Mirza Hills near LGBI
Airport, Guwahati.
Laying of GLF light cables
G.6 2025 0.85 0.94 0.43 0.44
approximate 6500 mtrs
G.7 Laser unit for AVDGS-2NO 2025 0.40 0.44 0.20 0.20
SITC of A-VDGS at Bay no.
G.8 2025 0.71 0.78 0.35 0.36
4
Energy saving projects
(hymus perimeter lights,
G.9 hymus solar lights, other 2024 1.52 1.60 0.76 0.78
energy saving projects)
(Reduced from 2.7 to 1.52)
SITC of Repair and
G.10 2024 0.30 0.32 0.0 0.0
Maintenance work for Airside
Miscellaneous Plant and
Machinery (Boom lift, Chiller
G.11 2024-2027 3.07 3.36 3.07 3.19
plant cooling tower
development, Breath
Consultation Paper No. 01/2024-25 Page 131 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Year of GIAL Authority
S. No. Particular Capitalization
(as per GIAL) Base Indexed Base Indexed
Cost Cost Cost Cost
Analyser Equipment,
Expansion of existing
electrical office, Modification
of Existing DG set controller
etc)
PVC coated Chain net for
G.12 2025 1.00 1.10 0.50 0.51
Operation area drains
Environmental Projects (R22
based will be replaced by
G.13 R32, carbon offset projects, 2024-2027 6.60 7.34 4.05 4.22
ACI 4 + certification, RE 100
etc)
EV Charging Stations for E
G.14 Buses , Apron Cars , Tugs 2024-2027 5.70 6.48 2.85 2.97
along with their installation .
G.15 carbon sequestration 2024-2027 3.40 3.95 0.00 0.00
Biodiversity preservation
G.16 2024-2027 2.15 2.50 0.00 0.00
projects
G.17 Fire Fighting Equipments 2024-2027 3.55 3.86 3.55 3.63
G.18 Disable Aircraft Removal Kit 2025 17.69 19.50 17.69 18.11
Hand Baggage X-Ray -
G.19 2025, 2026 2.55 2.89 2.55 2.66
60cmX40cm
Explosive Trace
G.20 2024-2025 1.35 1.49 1.35 1.40
Detector(ETD)
Hand Held Metal
G.21 2024-2027 0.18 0.21 0.18 0.19
Detector(HHMD)
Door Frame Metal
G.22 2024-2027 0.59 0.68 0.59 0.62
Detector(DFMD)
Security Operation Control
G.23 2025-2027 2.77 3.29 1.38 1.47
Center (CISF)
Security Survilience Centre
G.24 2025 1.50 1.65 0.75 0.77
(SSC)
Close Circuit Television
G.25 2025-2027 3.20 3.71 1.60 1.66
(CCTV) Setup
G.26 Access Control system, Adani 2025-2027 2.40 2.78 1.20 1.24
Container Tubular shooting
G.27 2025 1.30 1.43 0.65 0.67
Range
G.28 Video Surveillace system 2024-2027 3.59 4.23 1.80 1.89
G.29 Body Scanner 2025-2027 44.57 51.49 16.07 16.99
G.30 VDGS 2026 12.00 13.89 12.00 12.74
Total 158.95 180.93 94.59 98.74
H. Other Buildings (₹ 163.85 crores)
GIAL has proposed construction of various building owing to security requirements, new expansion,
administrative building, police station and various utilities etc. The Authority has reviewed the same and
have following observations:
i. In case of administrative building, the GIAL has proposed to construct 5000 Sqm office
building. As part of clarification the Authority has sought further detail and business case for
Consultation Paper No. 01/2024-25 Page 132 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
requirement of this much area for an administrative office. However, as part of response, no
further clarity was shared by GIAL. In view of this, the Authority noted that a significant part
of staff requirement of GIAL will be operational such as airport operation, screening, security,
runway operation etc. which will be deployed at respective work location outside
administrative building. Accordingly, considering the staff strength there is significant
optimization required in the administrative office space area. In absence of adequate plan, the
Authority proposes to consider 50 % of the admin building i.e. 50% of employee which are
expected to deployed at admin building to overall staff. The Authority has accordingly revised
the building area to 2500 sqm. However, the Authority has maintained the same quantities
related to demolition works, landside road and site circulation. Further, GIAL has considered
the rates as per the rates derived in case of some of the office building at Ahmedabad Airport.
The Authority has reviewed the rates submitted by GIAL with the comparable statistics issued
by CBRE5 and found the same in the range of similar kind of construction. Following is the
comparison of the cost details submitted by GIAL and proposed by the Authority:
Table 97: Cost of administrative building as per GIAL and proposed by the Authority
(₹ crores)
Particular UoM GIAL Authority
Rate Qty Amount Rate Qty Amount
New Pavement
Perimeter Road Sqm 5100 770 0.39 4800 770 0.37
Structure
New Building Sqm 92000 5000 46.00 69200 2500 17.30
Site circulation Sqm 4700 2405 1.13 4700 2405 1.13
Total 47.52 18.80
ii. GIAL has proposed an integrated building for Airport Police Station, Airport Health Office and
Airport Post Office. An integrated building is planned with an area of approx. 925 sqm. The
Authority, through its consultant has sought further detailed BoQ against this capex. However,
GIAL has shared a blended rate against this building. The Authority notes that these building will
be largely office like structure and accordingly in absence of further details proposes to consider the
rate equivalent to admin building. Following is the summary of the Authority proposal:
Table 98: Details of Integrated building submitted by GIAL and proposed by the Authority
(₹ crores)
Particular UoM GIAL Authority
Rate Area Amount Rate Area Amount
Police Station Sqm 98940 260 2.57 69200 260 1.80
Airport Health Office Sqm 94219 600 5.65 69200 600 4.15
Airport Post Office Sqm 95046 65 0.62 69200 65 0.45
8.84 6.40
iii. The Authority, while reviewing cost for CCR Room observed that GIAL has considered 10%
overhead on account of airside constraints. The Authority has revised the same to 5% in view
of public works guidelines (generally where NOTAM is issued).
iv. GIAL has proposed new ARFF satellite building on account of proposed airside and associated
development. As per GIAL, it is required to meet the response time as the current fire station
is almost 5 KM away from the edge of the new runway and will not be able to meet the response
5 India Construction Cost Trends 2023 issued by CBRE
Consultation Paper No. 01/2024-25 Page 133 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
time. In view of the safety requirement, the Authority proposes to consider this capex.
However, the rates have been revised on account of adjustment of airside working area
constraint overhead from 10% to 5%.
v. GIAL has proposed various other office building such as airport maintenance office, other
building-admin office and administrative building. The total base cost proposed against these
structures is ₹ 16.54 crores. The Authority notes that GIAL has already proposed new office
building and terminal building. The existing structure of office building and terminal building
will be idle once these have been shifted to new premises. GIAL should evaluate and consider
utilization of these building for additional proposed offices. Accordingly, the Authority
proposes not to consider any capex for additional offices.
vi. GIAL has further considered various other building and structures such as airside gates, SMR
facilities, fuel/EV station, Modification of MT shop into interim office, Solid waste facility, water
supply system, sewerage system, watch tower, earth filling, CISF accommodation, nursery
development, horticulture, Anti hijacking Control Room etc. The Authority notes that GIAL has not
shared any further details on these capex. There is scope in cost optmisation and also in view of
keeping tariff at optimum level, the Authority proposes 50% of the proposed capex.
vii. In view of the above, the Authority proposes inflation adjusted cost of ₹ 77.28 crores against GIAL
submission of ₹ 163.85 crores. Following is the asset wise comparison of GIAL proposal vis a vis
inflation adjusted (indexed) cost proposed by the Authority:
Table 99: Capex proposed toward Other Buildings by the Authority for Third Control Period
(₹ crores)
Year of GIAL The Authority
S.
Particular Capitalization Base Indexed Base Indexed
No.
(as per GIAL) Cost Cost Cost Cost
H.1 Relocation of Localiser 02 2024 0.20 0.21 0.10 0.10
H.2 CCR Building new construction 2025-2026 12.86 14.46 12.11 12.58
H.3 Airside Gates – 5 nos. 2025-2026 5.79 6.51 2.90 3.01
SMR Facilities (New
H.4 2025-2026 0.91 1.00 0.45 0.47
Construction)
H.5 Fuel/ EV Charging Station 2025-2026 2.49 2.76 1.24 1.28
Satellite ARFF Station (New
H.6 2025 12.35 13.61 11.65 11.92
Construction)
Modification of MT workshop
H.7 into Admin office building 2025 2.14 2.36 1.07 1.09
(Interim arrangement)
Integrated Building for Airport
H.8 Police Station, Airport Health 2026-2027 8.84 10.34 6.40 6.85
Office and Airport Post Office
Airport Administration Building
H.9 2026-2027 47.52 55.57 18.80 20.11
(5,000 Sqm)
Airport Maintenance Office
H.10 2026-2027 11.41 13.34 0.00 0.00
(1,200 Sqm)
H.11 Solid Waste Facility 2025-2026 2.50 2.82 1.25 1.30
H.12 Water Supply system 2026 4.66 5.43 2.33 2.48
H.13 Sewerage System 2026 1.16 1.35 0.58 0.62
Modification of watch tower at
H.14 operational area L.G.B.I. Airport 2024 0.35 0.37 0.18 0.18
Guwahati
Consultation Paper No. 01/2024-25 Page 134 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Year of GIAL The Authority
S.
Particular Capitalization Base Indexed Base Indexed
No.
(as per GIAL) Cost Cost Cost Cost
Earth filling of low using areas
and other miscellaneous works at
H.15 operational area related to DGCS 2025 0.40 0.44 0.20 0.20
compliance from time to time at
L.G.B.I. Airport Guwahati
H.16 Fire Station Improvement 2024-2025 4.20 4.57 4.20 4.41
H.17 Other Building - Admin Office 2024 1.50 1.58 0.00 0.00
H.18 Sewage Treatment Plant 2025 0.36 0.40 0.36 0.37
Misc Other Buildings -
2024-2025,
H.19 Upgradation works at RED, 2.89 3.26 1.45 1.48
2027
ATC, CISF and BCAS building
H.20 Installation of LGB Statue 2024 0.15 0.16 0.08 0.08
H.21 CISF accommodation 2025-2027 13.50 15.64 6.75 7.04
H.22 Nursery Development 2027 0.60 0.73 0.30 0.33
H.23 Misc Horticulture Improvements 2024-2027 1.46 1.64 0.73 0.75
H.24 Administrative Building 2024-2026 3.64 3.91 0.00 0.00
Anti Hijacking Control Room
H.25 2025-2026 1.22 1.40 0.61 0.63
(AHCR) upgradation
Total 143.09 163.85 73.72 77.28
I. IT Equipment (₹ 17.80 crores)
As part of MYTP, GIAL has submitted proposal to procure various IT equipment for operational requirement
and upgradation. The Authority has reviewed the same and have following observations:
i. GIAL has proposed ₹ 13.12 crores worth of IT Strategic projects towards passenger flow
management, queue monitoring system to provide advance information to operation team for better
flow management, wheelchair tracking, trolley tracking, IOT & Digiyatra. The Authority notes that
the cost proposed for the planned project are very high. Also the technology like IoT, trolley tracking
are still to be implement at major airport in India. In view of the insufficient details, the Authority
proposes to consider 20% of the cost proposed by GIAL.
ii. GIAL has estimated ₹ 0.35 crores toward other IT projects and shared no further details. Since there
are no details provided, the Authority proposes not to consider this capex. Also, GIAL has proposed
₹ 0.20 crores for innovation lab. The Authority notes that GIAL is supported by corporate team which
are involved in strategy formulation, have access to various industry information and expertise and
the cost of this already been allocated to GIAL as part of corporate allocation. In view of the
duplication of cost, the Authority proposes to not consider this capex.
iii. Following are the details of capex along with corrected cost by the Authority:
Table 100: Capex proposed toward IT equipment by the Authority for Third Control Period
(₹ crores)
Year of GIAL The Authority
S.
Particular Capitalization Base Indexed Base Indexed
No.
(as per GIAL) Cost Cost Cost Cost
Active component (Network
I.1 2024-2027 0.10 0.11 0.10 0.10
Switches, Firewall, Router)
Consultation Paper No. 01/2024-25 Page 135 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Year of GIAL The Authority
S.
Particular Capitalization Base Indexed Base Indexed
No.
(as per GIAL) Cost Cost Cost Cost
Passive Components (Network
I.2 2024-2027 0.45 0.45 0.45 0.42
CAT-6 and OFC cabling)
Data center Infrastructure and Wi-Fi
I.3 2024-2027 0.41 0.44 0.41 0.41
setup
I.4 Cyber Security 2024-2027 0.10 0.11 0.10 0.10
Voice Infra (EPABX & IP Phone) &
I.5 2024-2027 0.05 0.05 0.05 0.05
Recording Solutions
I.6 New User - Laptop / Desktop 2024-2027 0.26 0.28 0.26 0.26
I.7 SAP licenses 2024-2027 0.44 0.47 0.44 0.44
I.8 Other IT Cost 2024-2027 0.35 0.38 0.00 0.00
1. FIDS: Flight Information Display
System
2. PA (Public Announcement
I.9 2024-2027 0.10 0.11 0.10 0.10
System
3. LED Walls,
4. Video Walls
Strategic Projects (Pax Count, Flow
& Queue Monitoring. Wheelchair,
I.10 2024-2027 13.12 14.11 2.62 2.97
Buggy & Trolley Tracking (IOT),
OT) & Digi Yatra
I.11 Innovation & Technology Lab 2024-2027 0.20 0.22 0.00 0.00
I.12 SMS Software 2024-2027 1.00 1.08 1.00 1.01
Total 16.57 17.80 5.53 5.87
iv. In view of the above, the Authority proposes ₹ 5.87 crores inflation adjusted cost toward IT project
against GIAL submission of ₹ 17.80 crores.
J. Furniture & fixtures (₹ 1.66 crores)
GIAL has proposed to procure various furniture & fixtures for terminal operations during third
control period. The Authority in view of the new proposed terminal and office complex proposes
to consider the capex and the cost estimated by GIAL. The base cost proposed the Authority is ₹
1.48 crores which is in line with the submission made by GIAL. The indexed cost has been adjusted
on account of inflationary adjustment. The Authority proposes to consider inflation adjusted cost
of ₹ 1.56 crores against ₹ 1.66 crores submitted by GIAL.
K. Security Equipment’s (₹ 35.70 crores)
i. GIAL has proposed procurement of bullet proof jackets, bullet proof helmet, bullet proof
shield, bullet proof morcha, binocular device etc. In this regard GIAL has collectively
estimated an amount of ₹ 2.62 crores as base cost and ₹ 2.96 crores as inflation adjusted cost.
The Authority notes that there is no justification provided by GIAL for the amount estimated.
In view of the security requirement and absence of supporting details, the Authority proposes
to consider 50% of the capex proposed by GIAL. The inflation adjusted cost proposed to be ₹
1.34 crores.
ii. Threat Containment Vehicle (TCV) – GIAL has proposed to procure TCV for LGBIA at ₹
15.44 crores. In this regard GIAL has shared a quotation of USD 1.3 Mn plus duty/taxes. In
view of the security requirement and available quotation, the Authority proposes to consider the
same. However, the cost of the proposed vehicle is adjusted on account of inflationary
Consultation Paper No. 01/2024-25 Page 136 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
adjustment in 2025 i.e. ₹ 14.33 crores.
iii. As per MYTP, GIAL has estimated ₹ 4.00 crores as base cost (₹ 4.61 crores indexed cost)
towards BDDS which are required as per security requirements. GIAL has not shared any
further supporting details against this line item. In view of the same, the Authority proposes to
consider 50% of the proposed cost by GIAL, the inflation adjusted cost comes to ₹ 2.09 crores.
iv. GIAL as part of MYTP has submitted requirement of miscellaneous security equipment such
as quick reaction team equipment, radiological detection equipment, network switch and
cabling tech refresh, OFC network CCTV etc.. GIAL has estimated ₹ 10.99 crores as base cost
for these items collectively. GIAL has shared following list of security equipment:
Table 101: Details of miscellaneous security equipment
(₹ crores)
S. No. Particulars ₹/Cr Justification / Remarks
1 RT Sets 2.91 Considering cost of Tetra Set
Requirement as per AVSEC Order 06/2018
2 Server and Storage 2.90 Tech refresh of Video Surveillance system at
Tech Refresh terminal building. Replacement of EOL camera
(AvSec Circular 05/2017)
3 Network Switch and 3.69 Tech refresh of Video Surveillance system,
Cabling Tec Refresh, network cable, city side camera. Installation of
OFC network CCTV, AI facility camera. Installation of bar coded
Other building scanner for labor at Cargo gate as per AEP
connectivity's Guidelines 2022
(AvSec Circular 05/2017, AEP Guidelines 2022)
4 Centralized Access 0.29 Installation of Bio Metric Access Control System
Control System at existing terminal building
(CACS) (Avsec Circular 02/2007, Appendix-J)
5 Quick Reaction Team 0.21 QRT equipment for CISF
Equipment (Avsec Order 06/2018)
6 Radiological Detection 1.00 1. BCAS regulatory compliance & CISF
Equipment. requirements
2. Avsec Circular 01/2020. Radiological
Detection Equipment will be operationalized by
Aviation Security Group (ASG) with immediate
effect and upkeep & maintenance will lie with
Airport Operator.
Total 10.99
The inflation adjusted cost for the above projects is ₹ 12.70 crores as per GIAL submission. In
view of the security requirement, the Authority proposes to consider this capex however the
cost has been adjusted on account of inflationary adjustment. The cost is accordingly revised
to ₹ 11.66 crores.
In view of the security requirement and compliance, the Authority proposes to consider inflation
adjusted cost of ₹ 29.43 crores against GIAL submission of ₹ 35.70 crores.
L. Sustaining capex (₹ 47.64 crores)
As per MYTP, GIAL has incurred sustaining capex of ₹ 47.64 crores in FY’23. The capex is mainly
on account of earth filling work at runway strip as required by DGCA, stamp duty payment as required
under Concession Agreement, SAP license, administrative buildings, IT networking, terminal
building works, X-ray, security, furniture & fixture and office equipment. Following are the details
of capex incurred during FY’23:
Consultation Paper No. 01/2024-25 Page 137 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Table 102: Details of sustaining capex for FY'23
(₹ crores)
Amount in
Particular Remarks
(₹ crores)
Earth filling works as per DGCA, Apron
Runway, Taxiway and Apron 10.04
refurbishment works, Stamp duty allocation
SAP license, IT networking, workstation,
IT equipment 9.11
laptops and other office related IT equipment
Passenger trolleys, electrical installation, X-ray
Plant and Machinery 8.28 baggage, rubber removal machine, STP, stamp
duty allocation etc.
Office building, horticulture, parking, stamp
Other Buildings 6.14 duty allocation etc.
FIDS, Trace detector, LED displays, UG water
Office equipment 4.98 system, CCTV, office equipments
Notional Lease Asset 3.95 Right of Use of leashold building
QRT vehicles, Electric vehicle, stamp duty
2.55
allocation etc.
Vehicles
Furniture & fixtures 2.35 Office and terminal related furniture
Intangilble Assets 2.13 Airport Concession Rights
Terminal roof waterproofing, refurbishment
Terminal Building 1.98 work at existing terminal, stamp duty
allocation etc.
Software 1.58 Various enterprise software, SITA license
Cargo building 0.57 Civil works towards domestic cargo
Access Road 0.05 Improvement of internal roads
Total 53.73
Less: Notional asset &
intangible assets 6.08 Right of use and airport concession rights
Net Amount 47.64
The Authority has reviewed the capital expenditure incurred by GIAL in FY’23 for sustainable
operation. It is noted that the capital expenditure is mainly related to airside works, stamp duty payable
as per concession requirement, IT licenses like SAP, SITA etc, office building, equipment and
furniture, terminal related refurbishment works, borrowing cost etc.. In view of the operational
requirement, the Authority proposes to consider this capex.
7.3.7 Based on above proposals, the summary of New Capital Expenditure projects proposed by the Authority
for the Third Control Period is as follows:
Table 103: Capital Expenditure proposed by the Authority for the Third Control Period
(₹ crores)
Financial Year of
Cost as Cost as
Capitalization
per per the Difference
S. No. Particular Proposed Remarks
As per GIAL Authority C=(A-B)
by the
GIAL (A) (B)
Authority
Passenger Terminal Building and Associated Works
NITB (Including
Cost adjusted as per
A.1 Opening CWIP 2025 2026 2194.38 2131.86 (62.52)
Normative
A as per financials)
A.2 Kerbside 2025 2026 138.60 127.74 (10.86) Reduction of culvert
Development cost and
Consultation Paper No. 01/2024-25 Page 138 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Financial Year of
Cost as Cost as
Capitalization
per per the Difference
S. No. Particular Proposed Remarks
As per GIAL Authority C=(A-B)
by the
GIAL (A) (B)
Authority
benchmarking with
other airports
Exisiting
Terminal Adjusted cost in view
A.3 2024-2025 2024-2025 9.64 4.82 (4.82)
Building of NITB and repair
Development related works
Total 2342.62 2264.41 (78.20)
Runways, Taxiway & Aprons
Cost adjusted as per
Apron-2
Normative &
B.1 (Demolition and 2025-2026 2025-2026 466.21 241.19 (225.02)
inflationary
rew-construction)
adjustment
Airside Storm
B.2 Water Drainage 2025 2026 208.38 194.68 (13.70) Inflationary
works adjustment
Construction of Cost adjusted as per
Part Parallel Normative &
B.3 2025 2026 199.02 153.75 (45.27)
Taxiway and inflationary
Link Taxiways adjustment
Land
B.4 Development 2026 2026 189.73 43.77 (145.97) Cost optimisation and
works phase wise work
Adjusted on account
of reduction in
Widening of
B.5 2025 2025 87.17 77.06 (10.10) working area
Runway Strip
constraint factor from
10% to 5%
Cost adjusted as per
Construction of
Normative &
B.6 Second Part 2026 2026 81.64 60.84 (20.80)
inflationary
Parallel Taxiway
adjustment
B
Cost adjusted as per
Extension of
Normative &
B.7 Runway 02–20 2025 2026 51.61 39.72 (11.90)
inflationary
towards RWY 20
adjustment
Construction of Cost adjusted as per
new Isolation Normative &
B.8 2025 2025 30.89 21.84 (9.04)
Bay (Rigid inflationary
Pavement) adjustment
Cost adjusted as per
Construction of
Normative &
B.9 Rapid Exit 2026 2026 19.73 14.79 (4.94)
inflationary
Taxiway
adjustment
Other Minor
B.10
Airside Capex
Construction of
Adjusted on account
Runway End
of reduction in
Safety Area
B.10.1 2025 2026 4.21 3.80 (0.41) working area
(RESA) after
constraint factor from
RWY 20
10% to 5%,
Threshold
inflationary
Extension of
adjustment or
B.10.2 Blast Pad for 2025 2026 4.24 3.89 (0.36)
adjusted cost to 50%
RWY 02 and
Consultation Paper No. 01/2024-25 Page 139 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Financial Year of
Cost as Cost as
Capitalization
per per the Difference
S. No. Particular Proposed Remarks
As per GIAL Authority C=(A-B)
by the
GIAL (A) (B)
Authority
Construction of in absence of
new Blast Pad for BoQ/details.
RWY 20
Relocation of
Simple Approach
B.10.3 2025 2025 0.78 0.72 (0.06)
Lighting System
for Runway 20
Installation of
Category-I
Approach
B.10.4 2025 2026 7.38 7.18 (0.19)
Lighting System
towards Runway
02
B.10.5 Off-Stand GSE 2026 2026 4.60 3.50 (1.10)
Apron stand
surface
B.10.6 2024 2024 0.32 0.31 (0.01)
revamping work
in old apron
Manhole
chamber covers
for all manholes
B.10.7 or pits at apron 2025 2025 0.22 0.20 (0.02)
area, strip area as
per ICAO
standard
Provision of new
Earthing system
for Runway and
B.10.8 2025 2025 0.19 0.17 (0.01)
other associated
works at
Guwahati Airport
SITC of Inset
fittings for
B.10.9 Runway-Taxiway 2024 2024 0.40 0.19 (0.20)
intersection at
Guwahati Airport
Upgradation of
flexible
B.10.10 2026 2026 0.87 0.80 (0.07)
pavements in
Operational area
Runway Graded
Strip and RESA
B.10.11 2024 2024 0.18 0.09 (0.09)
strengthening (up
to 300mm Depth)
Airside works (
Apron surface
revamping
works, Provision
B.10.12 of new Airfield 2024-2026 2024-2026 1.73 1.64 (0.10)
signages, Joint
filling and
cleaning of old
apron)
B.10.13 Apron Control 2024 2024 0.21 0.10 (0.11)
Consultation Paper No. 01/2024-25 Page 140 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Financial Year of
Cost as Cost as
Capitalization
per per the Difference
S. No. Particular Proposed Remarks
As per GIAL Authority C=(A-B)
by the
GIAL (A) (B)
Authority
Airside
B.10.14 2024-2026 2024-2026 1.65 1.58 (0.08)
Equipments
As per existing
Runway runway condition and
B.11 strengthening 2026 - 75.25 0.00 (75.25) other planned work, it
works is propose to defer
this work.
Sub-Total 1436.60 871.81 (564.79)
Construction of Boundary Wall
New construction
of Airside
Perimeter &
Service Roads
C.1 and demolition of 2025-2026 2025-2026 38.33 33.63 (4.70)
existing Airside
Roads due to
Cost adjusted on
widening of
account of revised
Runway Strip
submission by GIAL
New construction
C of Airside and inflationary
adjustment
Boundary Wall
& demolition of
C.2 2025-2026 2025-2026 77.37 67.98 (9.38)
existing Airside
Boundary Wall
due to widening
of Runway Strip
C.3 PIDS System 2025-2026 2025-2026 26.24 20.50 (5.74)
C.4 Boundary Wall 2024 2024 0.21 0.10 (0.11) In absence of BoQ
adjusted cost to 50%
Sub-Total 142.14 122.21 (19.94)
Cargo Complex
Interim Cargo Adjusted cost on
D.1 2024 2024 3.22 3.05 (0.17)
Facility account of
D
New Cargo inflationary
D.2 2026 2026 23.15 21.18 (1.97)
Terminal adjustment
Sub-Total 26.37 24.23 (2.14)
Fuel Farm Infrastructure
E.1 Fuel storage farm 2025-2026 - 135.07 0.00 (135.07)
It is proposed to re-
E.2 Fuel hydrant line 2025-2026 - 160.68 0.00 (160.68) evaluate fuel farm
Equipment cost 2024 2025 3.15 3.07 (0.08) location and fuel
storage tank capacity
E Cost of
due to dedicated line.
procurement of
E.3 2024 2025 10.50 10.24 (0.26) Project has been
IOCL and RIL
allowed on incurrence
Assets
b asis.
Dead Stock 2026 - 16.14 0.00 (16.14)
Sub-Total 325.55 13.31 (312.24)
Vehicles
F
F.1 Vehicles 2024-2027 2024-2027 12.58 6.73 (5.85)
Consultation Paper No. 01/2024-25 Page 141 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Financial Year of
Cost as Cost as
Capitalization
per per the Difference
S. No. Particular Proposed Remarks
As per GIAL Authority C=(A-B)
by the
GIAL (A) (B)
Authority
Modified vehicle
F.2 for BDDS 2025-2026 2025-2026 3.39 3.13 (0.26)
equipment
Vehicle recovery
F.3 2024 2024 0.16 0.15 0.00
Van
2 Nos.Tractor
withTrolleys &
electric buggies Adjustment in
F.4 2025-2026 2025-2026 0.23 0.10 (0.13)
to shuttle nursery rates/qty and inflation
between the two adjustment
Terminals
F.5 Ambulance 2025 2025 0.87 0.52 (0.35)
Crash Fire
F.6 2024-2025 2025-2026 25.81 25.00 (0.80)
Tender
Quick Reaction
F.7 Team (QRT) 2025 2025 0.77 0.72 (0.06)
Vehicle
Sub-Total 43.81 36.36 (7.46)
Plant and Machinery
G.1 5 nos. OWS 2026 2026 26.80 14.13 (12.67)
G.2 Triturator 2025 2025 3.83 3.13 (0.70)
Hazardous Waste
G.3 2026 2026 0.55 0.25 (0.30)
Storage
Reticulation of
G.4 utilities to new 2027 2027 9.78 4.48 (5.30)
facilities
SITC of LED
type SPOL
System at
Sajanpara,
G.5 2024 2024 0.06 0.03 (0.03)
Borsilla & Mirza
Hills near LGBI Adjustement on
Airport, account of
Guwahati. inflationary
adjustment, 50%
G Laying of GLF
consideration of work
light cables
G.6 2025 2025 0.94 0.44 (0.50) where BoQ is not
approximate
provided, project
6500 mtrs
need assessment and
Laser unit for
G.7 2025 2025 0.44 0.20 (0.24) Cost optimization.
AVDGS-2NO
SITC of A-
G.8 VDGS at Bay no. 2025 2025 0.78 0.36 (0.42)
4
Energy saving
projects (hymus
perimeter lights,
hymus solar
G.9 lights, other 2024 2024 1.60 0.78 (0.82)
energy saving
projects)
(Reduced from
2.7 to 1.52)
Consultation Paper No. 01/2024-25 Page 142 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Financial Year of
Cost as Cost as
Capitalization
per per the Difference
S. No. Particular Proposed Remarks
As per GIAL Authority C=(A-B)
by the
GIAL (A) (B)
Authority
SITC of Repair
G.10 and Maintenance 2024 2024 0.32 0.00 (0.32)
work for Airside
Miscellaneous
Plant and
Machinery
(Boom lift,
Chiller plant
cooling tower
development,
G.11 Breath Analyser 2024-2027 2024-2027 3.36 3.19 (0.17)
Equipment,
Expansion of
existing electrical
office,
Modification of
Existing DG set
controller etc)
PVC coated
Chain net for
G.12 2025 2025 1.10 0.51 (0.59)
Operation area
drains
Environmental
Projects (R22
based will be
replaced by R32,
G.13 2024-2027 2024-2027 7.34 4.22 (3.12)
carbon offset
projects, ACI 4 +
certificationn, RE
100 etc)
EV Charging
Stations for E
Buses , Apron
G.14 2024-2027 2024-2027 6.48 2.97 (3.51)
Cars , Tugs along
with their
installtion .
carbon
G.15 2024-2027 - 3.95 0.00 (3.95)
sequestration
Biodiversity
G.16 preservation 2024-2027 - 2.50 0.00 (2.50)
projects
Fire Fighting
G.17 2024-2027 2024-2027 3.86 3.63 (0.23)
Equipments
Disable Aircraft
G.18 2025 2025 19.50 18.11 (1.39)
Removal Kit
Hand Baggae X-
G.19 Ray - 2025, 2026 2025, 2026 2.89 2.66 (0.22)
60cmX40cm
Explosive Trace
G.20 2024-2026 2024-2025 1.49 1.40 (0.09)
Detector(ETD)
Hand Held Metal
G.21 2024-2027 2024-2027 0.21 0.19 (0.02)
Detector(HHMD)
Door Frame
G.22 Metal 2024-2027 2024-2027 0.68 0.62 (0.05)
Detector(DFMD)
Consultation Paper No. 01/2024-25 Page 143 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Financial Year of
Cost as Cost as
Capitalization
per per the Difference
S. No. Particular Proposed Remarks
As per GIAL Authority C=(A-B)
by the
GIAL (A) (B)
Authority
Security Opration
G.23 Control Center 2025-2027 2025-2027 3.29 1.47 (1.82)
(CISF)
Security
G.24 Survilience 2025 2025 1.65 0.77 (0.89)
Centre (SSC)
Close
G.25 CircuitTelevision 2025-2027 2025-2027 3.71 1.66 (2.05)
(CCTV) Setup
Access Control
G.26 2025-2027 2025-2027 2.78 1.24 (1.54)
system, Adani
Container
G.27 Tubular shooting 2025 2025 1.43 0.67 (0.77)
Range
Video
G.28 Surveillace 2024-2027 2024-2027 4.23 1.89 (2.34)
system
G.29 Body Scanner 2025-2027 2025-2027 51.49 16.99 (34.50)
G.30 VDGS 2026 2026 13.89 12.74 (1.15)
Sub-Total 180.93 98.74 (82.19)
Other Buildings
Relocation of
H.1 2024 2024 0.21 0.10 (0.11)
Localiser 02
CCR Building
H.2 2026 2026 14.46 12.58 (1.88)
new construction
H.3 5 Airside Gates 2026 2026 6.51 3.01 (3.50)
SMR Facilities
H.4 (New 2025 2025 1.00 0.47 (0.54)
Construction)
Fuel/ EV
H.5 2026 2026 2.76 1.28 (1.48)
Charging Station Adjustement on
Satellite ARFF account of working
H.6 Station (New 2025 2025 13.61 11.92 (1.69) area constraint,
Construction) inflationary
Modification of adjustment, 50%
MT workshop consideration of work
H into Admin where BoQ is not
H.7 2025 2025 2.36 1.09 (1.26)
office building provided, project
(Interim need assessment,
arrangement) Cost optimisation on
Integrated account of reduction
Building for in area of admin and
Airport Police other associated
H.8 Station, Airport 2027 2027 10.34 6.85 (3.49) buildings
Health Office and
Airport Post
Office
Airport
Administration
H.9 2027 2027 55.57 20.11 (35.46)
Building (5,000
Sqm)
Airport
H.10 2027 - 13.34 0.00 (13.34)
Maintenance
Consultation Paper No. 01/2024-25 Page 144 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Financial Year of
Cost as Cost as
Capitalization
per per the Difference
S. No. Particular Proposed Remarks
As per GIAL Authority C=(A-B)
by the
GIAL (A) (B)
Authority
Office (1,200
Sqm)
Solid Waste
H.11 2026 2026 2.82 1.30 (1.52)
Facility
Water Supply
H.12 2026 2026 5.43 2.48 (2.94)
system
H.13 Sewerage System 2027 2027 1.35 0.62 (0.73)
Modification of
watch tower at
H.14 operational area 2024 2024 0.37 0.18 (0.19)
L.G.B.I. Airport
Guwahati
Earth filling of
low using areas
and other
miscellaneous
works at
H.15 operational area 2025 2025 0.44 0.20 (0.24)
related to DGCA
compliance from
time to time at
L.G.B.I. Airport
Guwahati
Fire Station
H.16 2024-2025 2024-2025 4.57 4.41 (0.15)
Improvement
Other Building -
H.17 2024 2024 1.58 0.00 (1.58)
Admin Office
Sewage
H.18 2025 2025 0.40 0.37 (0.03)
Treatment Plant
Misc Other
Buildings -
Upgradation 2024- 2024-
H.19 3.26 1.48 (1.78)
works at RED, 2025, 2027 2025, 2027
ATC, CISF and
BCAS building
Installation of
H.20 2024 2024 0.16 0.08 (0.08)
LGB Statue
CISF
H.21 2025-2027 2025-2027 15.64 7.04 (8.60)
accomodation
Nursery
H.22 2027 2027 0.73 0.33 (0.40)
Development
Misc Horticulture
H.23 2024-2027 2024-2027 1.64 0.75 (0.90)
Improvements
Administrative
H.24 2024-2026 - 3.91 0.00 (3.91)
Building
Anti Hijacking
Control Room
H.25 2025-2026 2025-2026 1.40 0.63 (0.77)
(AHCR)
upgradation
Sub-Total 163.85 77.28 (86.57)
IT equipment
I
I.1 IT Equipments 2024-2027 2024-2027 17.80 5.87 (11.92) Adjustment toward
strategic project and
Consultation Paper No. 01/2024-25 Page 145 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Financial Year of
Cost as Cost as
Capitalization
per per the Difference
S. No. Particular Proposed Remarks
As per GIAL Authority C=(A-B)
by the
GIAL (A) (B)
Authority
inflationary
adjustment
Sub-Total 17.80 5.87 (11.92)
J Furniture & fixtures
Furniture &
Fixtures for
J.1 2024-2027 2024-2027 1.66 1.56 (0.10)
Terminal, Office,
Security etc.
Sub-Total 1.66 1.56 (0.10)
Security equipment
Procurement of
Security
Equipments
(Bullet Proof
Jackets, Bullet
K.1 Proof Helmet, 2024-2027 2024-2027 2.96 1.34 (1.61)
Bullet Proof
Shield, Bullet
Proof Morcha,
Binocular Device
etc)
Threat
Cost adjusted to 50%
K.2 Containment 2025 2025 15.44 14.33 (1.10)
where insufficient
Vessel (TCV)
K details provided;
K.3 BDDS 2024-2027 2024-2027 4.61 2.09 (2.52)
inflationary
Misc Security
adjustment
Equipments
(Quick Reaction
Team
Equipments,
Radiological
K.4 Detection 2025-2026 2025-2026 12.70 11.66 (1.04)
Equipment,
Network Switch
and Cabling Tec
Refresh, OFC
network CCTV
etc)
Sub-Total 35.70 29.43 (6.27)
Sustaining capex
L already spent 47.64 47.64 0.00
(FY22-23)
Total Capex 4764.66 3592.84 (1171.83)
Note: The variation in the capex (excluding soft cost) allowed by the Authority vis a vis submitted by GIAL is mainly on
the account of adjustment of cost towards airside works, inflation adjustment, adoption of rates based on industry
benchmarks and capacity optimization.
7.3.8 Capital Work in Progress (CWIP)
i. In terms of the clause 6.4.5 of the Concession Agreement, GIAL has to take over CWIP from AAI
and reimburse the cost of such CWIP to AAI. Following is the relevant extract of the Concession
Agreement:
Consultation Paper No. 01/2024-25 Page 146 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
“6.4.5 Notwithstanding anything to the contrary in this Clause 6.4, the Concessionaire shall be
liable to pay to the Authority such amounts as may have been incurred by the Authority as on the
COD in respect of the contracts relating to works-in-progress as have been set forth in Schedule
T. Such amounts shall be intimated by the Authority with supporting documents and details within
30 (thirty) days of COD and shall be due and payable by the Concessionaire to the Authority within
a period of 90 (ninety) days thereon.
The Parties shall constitute a committee comprising representatives of the Concessionaire,
Authority and each of the counterparties under such contracts, which committee shall be
responsible for: (a) facilitating any discussions and/ or interactions amongst AAI, the
Concessionaire and the counterparties under such contracts, including in respect of any
modifications to the works, and (b) coordinating, facilitating, and monitoring the progress of such
works-in-progress. The Concessionaire shall be responsible to incur any additional cost towards
completion of such work-in-progress assets after COD.
Upon reimbursement by the Concessionaire to the Authority, of amounts as may have been incurred
by the Authority as on the COD for such work-in-progress assets as provided for above, and
completion of such works-in-progress by the Concessionaire, such works-in-progress assets shall
form part of the Airport.
The amounts reimbursed by the Concessionaire to the Authority and additional amounts incurred
by the Concessionaire for completion of such work-in-progress assets shall be considered as
investments made by the Concessionaire in creation of such assets for the purpose of determination
of Aeronautical Charges by the Regulator. In the event that any part of the amounts reimbursed by
the Concessionaire to the Authority pursuant to this Clause 6.4.5 are not considered for pass-
through by the Regulator due to any act or omission on the part of the Authority, the adjustment
towards any differences in the amounts reimbursed by the Concessionaire to the Authority and the
amounts considered for pass-through by the Regulator shall be undertaken as part of the Balancing
Payment that becomes due and payable as per Clause 31.4 immediately after the determination of
the Aeronautical Charges by the Regulator.”
ii. As per MYTP for third control period, GIAL received CWIP invoices from AAI totaling ₹ 430.89
crores. As on 31st Mar’22 the GIAL CWIP was ₹ 453.67 crores. The Authority understands from
the MYTP submission made by GIAL that these CWIP will be capitalized along with terminal
building. The Authority has accordingly considered the capitalization of this CWIP along with
terminal building.
iii. The Authority notes that GIAL has not paid any GST amount (on the value of RAB and CWIP
invoices) to AAI. Further, in future, if AAI is required to bear the GST, then based on the indemnity
bond provided by GIAL, the same will be recovered by AAI from GIAL. As the GST amount has
not been paid by GIAL, the Authority has not considered the same for determining RAB for the
Third Control Period. However, the Authority will consider the statutory payments relating to GST
amount on RAB and CWIP invoices, on actual incurrence basis, at the time of true up of the Third
Control Period, while determining tariff of the next Control Period.
7.3.9 The Authority notes that GIAL would be eligible to claim GST Input Tax Credits on procurement of
certain movable property. The Authority expects that GIAL would properly account for such credits in its
submissions in accordance with Chapter V of The Central Goods And Services Tax Act, 2017 at the time
of true up of the RAB for the Third Control Period. The Authority may examine the accounting of input
tax credits and make necessary adjustments in this regard at the time of determination of tariffs for the
Fourth Control Period.
7.3.10 Soft Cost – Technical Consultancies, Contingencies, Pre-Operative cost, design cost, PMC,
Consultation Paper No. 01/2024-25 Page 147 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Preliminary expenses
i. GIAL as part of proposed project cost for third control period has considered soft cost of ₹ 682
crores. GIAL has considered 16% of capital expenditure as soft cost on account of technical
consultancies, contingencies, preoperative Cost, design cost, PMC, preliminary expenses.
ii. The Authority upon review of GIAL’s explanation and relevant documents has the following
views with respect to soft cost:
a. The Authority notes that for other PPP airports such as HIAL, BIAL, DIAL etc. the above-
mentioned costs had been considered in the past in the range of 8% - 11% of the project costs.
The Authority is of the view that 16% claimed by GIAL is on the higher side, as compared to
other PPP Airports and hence not justified.
b. Many of the capex allowed to GIAL are bought out items, wherein orders are placed on Supply,
installation, Testing & Commissioning (SITC) basis, Hence, soft cost such as Project
Management Consultancy (PMC), Design etc. need not be incurred on such items.
c. New Capital Expenditure allowed to GIAL includes works on airside. On airside works such as
Apron, Taxiway, Runway overlay, Fuel farm etc. PMC charges are normally in the range of 1%
to 3% maximum.
d. Soft cost claimed by the GIAL includes, contingencies also, which do not come as a separate
line item while capitalizing the assets and is not to be claimed without any contingent activity.
e. GIAL has considered 16% soft cost unilaterally on overall capex items. However, the
consideration of soft cost vary asset wise. Following are the observations of the Authority in
this regard:
Table 104: Asset head wise analysis and observation regarding soft cost
Asset Head Items Analysis and Observations
Airside/landside drain works, On airside works, PMC charges are in
Earth filling, Basic strip the range of 1% to 3%
development with earth
Air Side works boundary wall, Apron, taxiways,
airside improvement work,
security gates and other airside
works etc.
BDDS equipment, Tractor, Items are purchased on Supply,
Ambulance, Crash Fire Tender, Installation, Testing & Commissioning
QRT vehicles, Fuel Farm (SITC) basis. Soft costs are bare
Equipment, ETD, HHMD, minimum (i.e., in the range of 1%-3%)
DFMD, CCTV, VDGS, Fire and are mostly not applicable on such
Bought Out
Fighting equipment, Bullet items.
Items
Proof Jackets, Bullet Proof
Helmet, Bullet Proof Shield,
Bullet Proof Morcha, Binocular
Device, Threat containment
vehicle etc.
GIAL has included contingencies also in
soft cost, Contingencies are not
Contingencies
applicable after commissioning of
Assets.
In view of the above, the Authority proposes to consider the aforementioned costs to the extent of
8% of the Aero CAPEX of the projects allowed by the Authority for the current Control Period. The
Consultation Paper No. 01/2024-25 Page 148 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Authority has thus derived the amount proposed to be allowed towards the aforementioned costs as
₹ 283.62 crores against ₹ 682 crores proposed by GIAL.
7.3.11 The Authority proposes to readjust (reduce) 1% of the uncapitalised project cost from the ARR / target
revenue as re-adjustment in case any particular capital project is not completed/ capitalized as per the
approved capitalisation schedule. It is further proposed that if the delay in completion of the project is
beyond the timeline given in the capitalization schedule, due to any reason beyond the control of GIAL
or its contracting agency and is properly justified, the same would be considered by the Authority while
truing up the actual cost at the time of determination of tariff for the next Control Period. The re-
adjustment in the ARR/ Target Revenue is to protect the interest of the stakeholders who are paying for
services provided by GIAL and is also encouragement for GIAL to commission/ capitalize the proposed
assets as per the approved CAPEX plan/schedule.
7.3.12 Financing Allowance/Interest During Construction
As part of the MYTP, GIAL had considered 65% debt funding for the proposed capex and balance 35%
from equity portion. GIAL has considered Interest During Construction at the rate of 12% over debt
portion and financing allowance at the rate of 12% over equity portion. As per MYTP, GIAL has
considered IDC over 65% of funding source and financing allowance over balance funding source. The
details of FA and IDC submitted by GIAL is given below:
Table 105: FA and IDC submitted by GIAL
(₹ crores)
Particular FY’22 FY’23 FY’24 FY’25 FY’26 FY’27 Total
IDC 18.30 113.68 187.76 90.52 1.73 412.00
Financing Allowance 26.25 9.86 61.21 101.10 48.74 0.93 248.10
Total 26.25 28.16 174.90 288.86 139.26 2.67 660.10
The Authority examined GIAL’s claim as well as the justification provided for the same in detail and
has summarized its view as shown below:
i. The Authority considered that providing return on capital expenditure from the very beginning
of construction will significantly lower the risks for an airport operator and may require
revisiting the return on equity allowed to airport operators as the investment in the asset class
will then be equated to risk free rate of return.
ii. Further, provision of Financing Allowance will disincentivize the Airport Operators from
ensuring timely completion of projects and delivery of services to the users. Therefore, the
Authority is of the view that a return should be provided only when the assets are made available
to the airport users except in the case of certain costs like IDC that will have to be incurred in
case debt is used for funding of projects.
iii. Furthermore, the future returns from the project should generate adequate returns to cover the
cost of equity during the construction stage. GIAL is adequately compensated for the risks
associated with the equity investments in a construction project once the project is capitalized
by means of a reasonable cost of equity.
iv. Developments at greenfield airports inherently take longer durations to commission and
operationalize. Thus, airport operators would have to wait for a considerable duration before
getting returns on large capital projects. Keeping this in view, the Authority had earlier
provisioned for financing allowance in initial stages to such airports. It may be further noted that
the Authority has never provided financing allowance in the case of brownfield airports in its
any of the Tariff Orders. Further, financing allowance for greenfield airports of BIAL, HIAL,
Consultation Paper No. 01/2024-25 Page 149 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
CIAL etc. was allowed only for the initial stages of their development, after which IDC was
permitted on the debt portion of the proposed capital expenditure.
v. It is pertinent to note that in case of a greenfield airport, investment in regulatory blocks by the
Airport Operator would not make the airport facilities available to the passengers. Brownfield
and Greenfield airports can’t be equated on this issue. In greenfield airports, the tariff is not
applicable, and no revenue is available to the Airport Operator till the aeronautical services have
been created and put to use. However, in the case of brownfield airports, where GIAL brings in
additional investments, the airport facilities are mobilized and enabled to other functional parts
of the airport, which remains functional and GIAL keeps on enjoying the charges from the users.
In the case of LGBIA, since new projects have included mobilization of existing operations, the
said Airport is ought to be considered as a brownfield airport, which in the opinion of the
Authority would not be eligible for an allowance on the equity portion of newly funded capital
projects.
vi. Financing Allowance is a notional allowance and different from interest during construction.
Therefore, the provision of Financing Allowance on the entire capital work in progress would
lead to a difference between the projected capitalization and actual cost incurred, especially
when the Airport Operator funds the projects through a mix of equity and debt. Further, the
Authority opines that only IDC should be provided on the debt borrowings availed for execution
of a project.
vii. AERA Guidelines, 2011 does not specifically state that Financing Allowance is to be provided
on equity portion of the capital expenditure. The proviso to Section 13 (1) (a) of the AERA Act
states that “different tariff structures may be determined for different airports having regard to
all or any of the above considerations specified at sub-clauses (i) to (vii) of Section 13 (1) (a)”.
viii. In respect of IDC, the Authority is inclined to allow the same and accordingly, the Authority
has considered IDC to be provided on the debt portion of the value of average CWIP derived on
the basis of revised Capitalization schedule proposed by the Authority. Further, the Authority
proposes to consider the notional gearing ratio (debt-equity ratio of 48:52) followed for other
PPP airports and cost of debt @ 9% (refer para 8.2.5 onwards) for the Third Control Period for
calculating the value of IDC. Based on the same, the Authority has derived an amount of ₹
179.42 crores and proposes to allow the same as against ₹ 660.10 crores (as Financing
Allowance and IDC) claimed by GIAL for the Third Control Period. Following is the asset
category wise IDC for the proposed capex programme.
Table 106: Asset category wise details of Interest During Construction as per the Authority
(₹ crores)
Particular FY’23 FY’24 FY’25 FY’26 FY’27 Total
Land Development Works - - 0.38 1.14 - 1.52
Airside Improvement Works - 0.04 7.78 25.32 5.03 38.17
Ancillary Building - - - 0.46 0.27 0.73
Development Works
ATF storage and distribution - - 0.13 - - 0.13
system
Development of Cargo - 0.01 - 0.49 - 0.50
Facilities
Environment Related - - 0.17 0.56 0.02 0.75
Passenger Terminal & - 23.46 50.03 64.02 - 137.51
Associated works
Utilities - - - 0.08 0.03 0.11
Total - 23.51 58.49 92.08 5.34 179.42
Consultation Paper No. 01/2024-25 Page 150 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
ix. GIAL estimated IDC of ₹ 412.00 crores against which the Authority proposes ₹ 179.42 crores
for IDC. The reduction in IDC amount is on account of adjustment towards cost of debt, change
in gearing ratio, optimization in capex amount and revised phasing.
x. The IDC proposed by the Authority towards the capital expenditure for the Third Control Period
is given below:
Table 107: IDC proposed by the Authority for the Third Control Period
(₹ crores)
Particular FY’23 FY’24 FY’25 FY’26 FY’27 Total
IDC - 23.51 58.49 92.08 5.34 179.42
7.3.13 Summary of the Capital expenditure proposed by the Authority for Third Control Period:
a. With reference to above following is the summary of the capex proposed by the Authority for
the purpose of regulatory asset base for third control period in case of LGBIA:
Table 108: Summary of the CAPEX proposed by the Authority for Third Control Period
(₹ crores)
S. No. Project Name Reference Amount in ₹ Crore
GIAL Authority
A Basic cost (Including Para 7.3.7 4717.36 3545.20
indexation) as tabled
above
B Soft Cost Para 7.3.10 682.00 283.62
C Interest During Para 7.3.12 412.00 179.42
Construction
D Financing Allowance Para 7.3.12 248.00 0
Total – New Capex 6059.36 4008.24
E FY’23 as per actual 47.64 47.64
capex incurred
Grand Total 6107.00 4055.88
7.3.14 Allocation of capital expenditure into Aeronautical and Non-Aeronautical
a. GIAL has submitted following with respect to RAB allocation methodology for third control period:
9.1 As per AERA Order No 14/2016-17 and as mandated under the Concession Agreement, the
Hybrid-Till with 30% cross subsidization of non-Aeronautical revenues is the applicable
methodology. The relevant extract from AERA order and Concession Agreement is as follows:
9.1.1 Extract from AERA order:
The authority, in exercise of powers conferred by Section 13(1)(a) of the Airports Economic
Regulatory of India Act 2008 and after careful consideration of the comments of the stakeholders
on the subject issue, decides and orders that: -
(i) The Authority will in future determine the tariffs of major airports under “Hybrid Till” where
in 30% of non-aeronautical revenues will be used to cross-subsidize aeronautical charges.
Accordingly, to that extent the airport operator guidelines of the Authority shall be amended. The
provisions of the Guidelines issued by the Authority, other than regulatory till, shall remain the
same.
(ii) In case of Delhi and Mumbai airports, tariff will continue to be determined as per the SSA
entered into between Government of India and the respective airport operators at Delhi and
Mumbai.
9.1.2 Extract from Concession Agreement:
28.3.2 The GOI has, through the National Civil Aviation Policy dated June 15,2016, approved,
(“Shared-Till Approval”) the 30% (thirty percent) shared-till framework for the determination
and regulation of the Aeronautical Charges for all airports in India, and the same shall be
Consultation Paper No. 01/2024-25 Page 151 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
accordingly considered by the Regulator for the purposes of the determination of the Fees/
Aeronautical Charges pursuant to the provisions of this Agreement. It is clarified that, for the
purposes of this Agreement, the Shared-Till Approval shall apply as on the date of this Agreement
notwithstanding any subsequent revision or amendment of such Shared-Till Approval.
28.3.3 The Aeronautical Charges shall be regulated and set/ re-set, in accordance with the
Shared-Till Approval, terms of this Agreement including the terms set out in Schedule R
(Memorandum of Understanding) and the Applicable Laws.
9.1.3 Extract from Schedule R of the Concession Agreement:
2.2 Principles for Determination and Revision of Fees
2.2.1 The GOI has, through the National Civil Aviation Policy dated June 15, 2016 approved the
30% (thirty percent) shared-till framework for the determination and regulation of the
Aeronautical Charges for all Airports in India (“Shared-Till Approval”), and the same shall be
accordingly considered by AERA, for the purposes of the determination of the Fees/ Aeronautical
Charges pursuant to the provisions of this Agreement.
2.2.2 The Aeronautical Charges shall be regulated and set/ re-set, in accordance with the Shared-
Till Approval, the terms of the Concession Agreement and the Applicable Laws.
9.2 As per Clause 5.2 of the AERA Guidelines:
5.2.1. Scope of the RAB
(a) In normal course, all airport fixed assets will come under the scope of the RAB. However, the
Authority may, based on due consideration of relevant factors, include or exclude certain fixed assets
from the scope of RAB.
(b) The relevant RAB assets shall be all the fixed assets proposed by the Airport Operator(s), after
providing for such exclusions therefrom or such inclusions therein, as may be determined by the
Authority in respect of specific assets based on following principles:-
(i) The assets that substantially provide amenities / facilities/ services that are not related to, or not
normally provided at an airport, may be excluded from the scope of RAB;
(ii) The assets that in the opinion of the Authority do not derive any material commercial advantage
from the airport (for example from being located close to the airport) may be excluded from the scope
of RAB;
(iii) Responses by stakeholders in relation to their inclusion or exclusion during consultations.
(iv) Specification of, to the Authority's satisfaction, sufficient accounting separation to ensure
that the costs and revenues associated with the assets shall be clearly identified for the
preparation and audit of regulated airport accounts;
(v) Specification of, to the Authority's satisfaction wherever appropriate (where the Authority
considers there may be substantial financial risks associated with any asset), sufficient legal
separation to protect the Airport Operators, and thus airport Users, in the event of any substantial
financial risks materialising. The Authority shall require the Airport Operator(s) to insulate the
Users by suitably ring fencing the assets excluded from the scope of RAB. The principles
governing the ring fencing are mentioned in the paragraph 7.5 of Order Number 13/2010-11 of
the Authority issued on 12-Jan-2011.
(vi) Notwithstanding the principles mentioned under points (i) to (v) above, assets with fixed
locations inside terminal buildings shall be considered within the scope of RAB.
(c) Any exclusion/ inclusion shall only be considered if it is proposed to be executed in the Control
Period for which the Multi Year Tariff Proposal is submitted.
(d) The Authority may also, in its discretion, consider any other relevant factors for exclusion or
inclusion of assets.
(e) The assets related to any service(s) provided by the Airport Operator that are subject to
separate control and regulated as per Clause 5.7, shall be excluded from the scope of RAB.
Consultation Paper No. 01/2024-25 Page 152 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
9.2.1 It is observed that as per AERA Guidelines, 5.2.1 (b) (vi) all the assets which are part of the
terminal building shall be considered as part of RAB. Therefore, terminal building as a whole
should be considered as RAB /Aeronautical asset and not required to be allocated into Aero and
Non-Aero.
b. The Authority has examined GIAL submission and have following observations:
i. As per tariff guidelines 2011 for Airport Operators the tariff for an Airport needs to be
calculated as per single till methodology. According to which all building block of ARR
considered 100% as aeronautical.
ii. The Authority in order to adopts uniform tariff policy across all major airports had amended
its tariff guideline to the extent of adoption of Hybrid Till instead of Single Till prescribed
in the guidelines vide order 14/2016-17. The Hybrid Till in principle considers only
aeronautical portion of OPEX and CAPEX as pass through in tariff with 30% cross subsidy
from Gross Non-Aero Revenue.
iii. The revenue, cost and asset are interlinked and should be aligned in accordance with the till
methodology adopted for tariff determination. Thus, as part of asset allocation exercise, we
would require identification and allocation of Assets and OPEX into Aero and Non-Aero
iv. The Authority has adopted following basis for allocation of RAB addition during third
control period:
Terminal Building Ratio - It was observed that GIAL has classified the entire area of the
terminal building as aeronautical. Upon enquiry, GIAL stated that this was done in accordance
with the AERA Act.
Terminal Building Area is planned in an airport considering the facilities to be provided for
Aeronautical activities and provision of space for certain Non-Aeronautical activities such
as Food & Beverage, Duty Free etc. Also, in case of PPP airports, the focus on Non-
Aeronautical activities is expected to be more as these would generate revenues and a part
of the same would also cross subsidize the Aeronautical charges. The Non-Aeronautical
activities are over 10% of terminal building area at other similar size PPP airports.
Prescriptions of IMG norms also provide for non-aeronautical area to be between 8% and
12%, with the range being higher for larger airports. Considering the above, the Authority
proposes to consider the ratio of 90:10 towards Aeronautical and Non-Aeronautical in line
with its decision in Order No. 03 /2017-18 dated 2nd June 2017 for GIAL for the Third
Control Period and recommendation in independent study on asset allocation.
Employee Ratio- GIAL has submitted expected deployment of employees during third
control period. Basis on employment schedule and rationalization, the employee ratio has
been calculated at operating expense chapter (please refer Table 140 of O&M chapter of this
consultation paper for detailed calculation). The effective employee ratio for third control
period comes to 96.01%.
Gross Block Asset Ratio – As per the asset allocation study the gross block asset ratio is
95.39% as on 31st Mar’2022, same has been considered for third control period for the
purpose of asset allocation.
v. It is to be further noted that the Authority has considered above ratios to allocate assets
planned to be procured as part of third control period, the allocation ratio will be revised as
per asset allocation exercise undertaken by the Authority in the next control period.
Following is the asset wise allocation for asset addition proposed in third control period:
Consultation Paper No. 01/2024-25 Page 153 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Table 109: Asset wise allocation for asset addition proposed in third control period
Particular Allocation Basis Aeronautical portion
Terminal Building Terminal Ratio 90.00 %
Runway, Taxiway and Apron Aeronautical 100.00 %
Cargo building Aeronautical 100.00 %
Cargo Equipment Aeronautical 100.00 %
Boundary wall Aeronautical 100.00 %
Software Employee Ratio 96.01 %
IT equipment Employee Ratio 96.01 %
Security equipment Aeronautical 100.00 %
Plant and Machinery Gross Block Asset 95.39 %
Other Buildings Gross Block Asset 95.39 %
Access Road Aeronautical 100.00 %
Fuel Aeronautical 100.00 %
Furniture & fixtures Gross Block Asset 95.39%
Vehicles Employee Ratio 96.01%
Office equipment Employee Ratio 96.01%
7.4 Capital addition for the Third Control Period
Total capital addition as per the Authority for third control period is ₹ 4055.89 Crore. The Authority considers
following capitalization schedule for the purpose of third control period.
Table 110: Capitalization schedule proposed by the Authority for the Third Control Period
(₹ crores)
Particular FY'23* FY'24 FY'25 FY'26 FY'27 Total
Terminal Building 1.98 5.20 - 2,431.96 - 2,439.15
Runway, Taxiway and Apron 10.04 - 113.78 861.88 - 985.71
Cargo Facility 0.57 3.30 - 23.37 - 27.24
Boundary wall - - 0.11 136.50 - 136.61
Software 1.58 - - - - 1.58
IT equipment 9.11 - 2.04 2.11 2.19 15.46
Security equipment - - 22.27 5.25 4.26 31.78
Plant and Machinery 8.28 - 44.03 58.11 5.23 115.65
Other Buildings 6.14 0.11 23.85 27.68 33.63 91.41
Access Road 0.05 - - 145.92 - 145.97
Fuel - - 14.50 - - 14.50
Furniture & fixtures 2.35 - 0.99 0.22 0.47 4.03
Vehicles 2.55 - 21.27 17.99 - 41.81
Office equipment 4.98 - - - - 4.98
Total 47.65 8.61 242.86 3,710.99 45.77 4,055.89
*actual
Capital addition proposed above is further allocated into Aeronautical asset for the purpose of Regulatory
Asset Base for third control period. The year wise details for Regulatory Asset Base are as follows:
Table 111: Year wise details for Aeronautical capex proposed by the Authority for the Third
Control Period
(₹ crores)
Aero Capitalisation
S. No. Particular Total
FY'23* FY'24 FY'25 FY'26 FY'27
Passenger Terminal and Associated Works
Consultation Paper No. 01/2024-25 Page 154 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Aero Capitalisation
S. No. Particular Total
FY'23* FY'24 FY'25 FY'26 FY'27
NITB (Including Opening
A.1 0.00 0.00 0.00 2188.77 0.00 2188.77
CWIP as per financials)
A A.2 Kerbside Development 0.00 0.00 0.00 145.92 0.00 145.92
Exisiting Terminal Building
A.3 0.00 4.68 0.00 0.00 0.00 4.68
Development
Sub-Total – (A) 0.00 4.68 0.00 2334.68 0.00 2339.36
Runways, Taxiway & Aprons
Apron-2 (Demolition and
B.1 0.00 0.00 0.00 269.89 0.00 269.89
rew-construction)
Airside Storm Water
B.2 0.00 0.00 0.00 217.40 0.00 217.40
Drainage works
Construction of Part Parallel
B.3 0.00 0.00 0.00 174.76 0.00 174.76
Taxiway and Link Taxiways
B.4 Land Development works 0.00 0.00 0.00 48.79 0.00 48.79
B.5 Widening of Runway Strip 0.00 0.00 84.88 0.00 0.00 84.88
Construction of Second Part
B.6 0.00 0.00 0.00 68.07 0.00 68.07
Parallel Taxiway
Extension of Runway 02–20
B.7 0.00 0.00 0.00 44.61 0.00 44.61
towards RWY 20
Construction of new Isolation
B.8 0.00 0.00 24.06 0.00 0.00 24.06
Bay (Rigid Pavement)
Construction of Rapid Exit
B.9 0.00 0.00 0.00 16.55 0.00 16.55
Taxiway
B.10 Other Minor Airside Capex
Construction of Runway End
B.10.1 Safety Area (RESA) after 0.00 0.00 0.00 4.23 0.00 4.23
RWY 20 Threshold
Extension of Blast Pad for
B
B.10.2 RWY 02 and Construction of 0.00 0.00 0.00 4.32 0.00 4.32
new Blast Pad for RWY 20
Relocation of Simple
B.10.3 Approach Lighting System 0.00 0.00 0.79 0.00 0.00 0.79
for Runway 20
Installation of Category-I
B.10.4 Approach Lighting System 0.00 0.00 0.00 7.90 0.00 7.90
towards Runway 02
B.10.5 Off-Stand GSE 0.00 0.00 0.00 3.92 0.00 3.92
Apron stand surface
B.10.6 0.00 0.00 0.33 0.00 0.00 0.33
revamping work in old apron
Manhole chamber covers for
all manholes or pits at apron
B.10.7 0.00 0.00 0.22 0.00 0.00 0.22
area, strip area as per ICAO
standard
Provision of new Earthing
system for Runway and other
B.10.8 0.00 0.00 0.19 0.00 0.00 0.19
associated works at Guwahati
Airport
SITC of Inset fittings for
Runway-Taxiway
B.10.9 0.00 0.00 0.21 0.00 0.00 0.21
intersection at Guwahati
Airport
Consultation Paper No. 01/2024-25 Page 155 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Aero Capitalisation
S. No. Particular Total
FY'23* FY'24 FY'25 FY'26 FY'27
Upgradation of flexible
B.10.10 pavements in Operational 0.00 0.00 0.00 0.86 0.00 0.86
area
Runway Graded Strip and
B.10.11 RESA strengthening (up to 0.00 0.00 0.09 0.00 0.00 0.09
300mm Depth)
Airside works (Apron surface
revamping works, Provision
B.10.12 of new Airfield signages, 0.00 0.00 1.19 0.57 0.00 1.77
Joint filling and cleaning of
old apron)
B.10.13 Apron Control 0.00 0.00 0.11 0.00 0.00 0.11
B.10.14 Airside Equipments 0.00 0.00 1.70 0.00 0.00 1.70
B.11 Runway strengtheing works 0.00 0.00 0.00 0.00 0.00 0.00
Sub-Total – (B) 0.00 0.00 113.78 861.88 0.00 975.66
Construction of Boundary Wall
New construction of Airside
Perimeter & Service Roads
C.1 and demolition of existing 0.00 0.00 0.00 37.62 0.00 37.62
Airside Roads due to
widening of Runway Strip
New construction of Airside
C Boundary Wall & demolition
C.2 of existing Airside Boundary 0.00 0.00 0.00 76.05 0.00 76.05
Wall due to widening of
Runway Strip
C.3 PIDS System 0.00 0.00 0.00 22.84 0.00 22.84
C.4 Boundary Wall 0.00 0.00 0.11 0.00 0.00 0.11
Sub-Total (C) 0.00 0.00 0.11 136.50 0.00 136.61
Cargo Complex
D.1 Interim Cargo Facility 0.00 3.30 0.00 0.00 0.00 3.30
D
D.2 New Cargo Terminal 0.00 0.00 0.00 23.37 0.00 23.37
Sub-Total (D) 0.00 3.30 0.00 23.37 0.00 26.67
Fuel Farm Infrastructure
E.1 Fuel storage farm 0.00 0.00 0.00 0.00 0.00 0.00
E.2 Fuel hydrant line 0.00 0.00 0.00 0.00 0.00 0.00
Equipment cost 0.00 0.00 3.35 0.00 0.00 3.35
E
Cost of procurement of IOCL
E.3 0.00 0.00 11.16 0.00 0.00 11.16
and RIL assets
Dead Stock 0.00 0.00 0.00 0.00 0.00 0.00
Sub-Total (E) 0.00 0.00 14.50 0.00 0.00 14.50
Vehicles
F
Sub-Total (F) (F1-F5) 0.00 0.00 20.42 17.27 0.00 37.70
Plant and Machinery
G
Sub-Total (G) (G1-G30) 0.00 0.00 42.00 55.43 4.99 102.42
Other Buildings
H
Sub-Total (H) (H1-H25) 0.00 0.10 22.75 26.40 32.08 81.34
IT equipment
I
I.1 IT Equipment 0.00 0.00 1.96 2.03 2.10 6.09
Consultation Paper No. 01/2024-25 Page 156 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Aero Capitalisation
S. No. Particular Total
FY'23* FY'24 FY'25 FY'26 FY'27
Total – IT equipment 0.00 0.00 1.96 2.03 2.10 6.09
Furniture & fixtures
Furniture & Fixtures for
J.1 Terminal, Office, Security 0.00 0.00 0.95 0.21 0.45 1.60
J
etc.
Total – Furniture &
0.00 0.00 0.95 0.21 0.45 1.60
fixtures
Security equipment
Procurement of Security
Equipment (Bullet Proof
Jackets, Bullet Proof Helmet,
K.1 0.00 0.00 1.45 0.00 0.00 1.45
Bullet Proof Shield, Bullet
Proof Morcha, Binocular
Device etc)
Threat Containment Vessel
K.2 0.00 0.00 15.48 0.00 0.00 15.48
(TCV)
K
K.3 BDDS 0.00 0.00 1.11 1.15 0.00 2.25
Misc Security Equipment
(Quick Reaction Team
Equipment, Radiological
K.4 Detection Equipment, 0.00 0.00 4.24 4.10 4.26 12.60
Network Switch and Cabling
Tec Refresh, OFC network
CCTV etc)
Total – Security equipment 0.00 0.00 22.27 5.25 4.26 31.78
Sustaining capex already
L 45.95 45.95
spent (FY22-23)
Total 45.95 8.09 238.76 3463.03 43.87 3799.70
Note-Above cost is aeronautical and includes inflation, soft cost, IDC
*as per actuals
7.5 Depreciation for the Third Control Period
GIAL’s submission
7.5.1 GIAL follows the policy of determining the rates of depreciation based on the ‘useful life’ of different
asset classes. While submitting the Multi-Year Tariff Proposal for the Third Control Period for LGBIA,
GIAL has taken cognizance of the rates of depreciation approved by the Authority in its order vide Order
No. 35 dated January 12, 2018, and Amendment No. 01 to Order No. 35 / 2017-18 on ‘Determination of
Useful Life on Airport Assets’. However, GIAL has considered different rates for certain asset classes
based on the recommendations by independent technical evaluation for Lucknow and Ahmedabad
Airports and the same are as per the table given below -:
Table 112: Depreciation rates determined by GIAL for the Third Control Period
Asset Class Depreciation as per GIAL’s submission
Terminal Building 4.00%
Runway, Taxiway and Apron 5.00%
Cargo Building 4.00%
Cargo Equipment 13.33%
Boundary wall 20.00%
Computer Servers, networks, etc. 33.33%
Computer End-user devices 33.33%
Consultation Paper No. 01/2024-25 Page 157 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Asset Class Depreciation as per GIAL’s submission
Security equipment 13.33%
Plant and Machinery 13.33%
Other buildings 3.33%
Access road 10.00%
Fuel farm facility assets 13.33%
Furniture & fixtures 14.29%
Vehicles 20.00%
Office Equipment 20.00%
7.5.2 Depreciation has been computed separately on opening block of assets and on the proposed additions.
For the additions to RAB, GIAL has calculated the depreciation during year of capitalization on 50% of
the asset value (assuming that the asset is capitalized in the middle of the financial year).
7.5.3 The depreciation amount submitted by GIAL for the Third Control Period has been presented in the table
below.
Table 113: Depreciation submitted by GIAL for the Third Control Period
(₹ crores)
Particular FY'23 FY'24 FY'25 FY'26 FY'27 Total
Terminal Building 0.26 0.45 62.07 123.53 123.53 309.85
Runway, Taxiway and Apron 5.38 5.73 18.21 61.48 92.35 183.16
Cargo Facillity 0.01 0.10 0.17 0.74 1.31 2.34
Boundary wall 2.86 0.70 0.12 18.18 36.17 58.02
Software - 0.53 0.53 0.53 0.00 1.58
IT equipment 1.23 6.86 9.45 9.68 4.49 31.70
Security equipment - 0.05 1.83 4.07 5.05 11.01
Plant and Machinery 9.24 9.71 12.34 22.74 30.18 84.21
Other Buildings 1.38 1.62 2.32 3.64 6.29 15.25
Access Road 0.03 0.03 0.03 0.01 0.01 0.11
Fuel - 1.06 2.11 28.58 55.05 86.79
Furniture & fixtures 0.38 0.76 0.83 0.77 0.75 3.51
Vehicles 2.10 3.99 6.51 8.95 10.12 31.67
Office equipment 0.24 1.24 1.23 1.22 1.15 5.08
Total 23.11 32.83 117.76 284.13 366.46 824.29
Authority’s examination regarding Depreciation for the Third Control Period
7.5.4 The Authority duly examined the recommendations of the Technical Study Report on ‘useful life of
assets’ submitted by GIAL and observed that the expert appointed by GIAL has prescribed the useful
lives of assets component wise after technical assessment.
7.5.5 The Authority noted the methodology adopted by the Valuer to evaluate the useful lives of assets is as
follows:
• “Physical inspection of some of the assets
• Detailed discussions with the Projects, Finance & Engineering and Maintenance team of MIA and
the General Manager (Engineering – Civil) of Airports Authority of India pertaining to usage of the
assets.
• Guidance for determination of Useful Life given in Depreciation under Companies Act, 2013
Consultation Paper No. 01/2024-25 Page 158 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Schedule 2, Airports Economic Regulatory Authority of India (“AERA”), Marshall & Swift
Valuation Service (MVS) and American Society of Appraisers (ASA)
• Our understanding and experience as qualified engineers "
7.5.6 The Authority has observed the recommendations given in the study report for adopting shorter useful
life and noted the following:
• The Independent Expert appointed by GIAL has considered the various components of the Terminal
Building such as False Ceiling, Sanitation works, Glass façade, Flooring works etc. for assessing the
useful life of the Terminal Building. The Expert has calculated the contribution of each of the
components to the overall structure of the Terminal Building along with the estimated useful life of
such components wherein shorter useful lives have been adopted for False Ceiling, Sanitation works,
Glass façade and Flooring works due to frequent renovation works in the building, weather
conditions, wear and tear, etc., and arrived at the weighted average useful life of the entire structure
of Terminal Building as approximately 25 years Further, the Authority notes that GIAL has adopted
the same shorter useful life of 25 years for the projected capital expenditure on construction of new
Cargo Terminal Building.
• Similarly, the Independent Expert has recommended shorter useful life for Runways, Taxiways and
Apron based on the useful life followed by various international regulators and associations.
• Further, in respect of Plant and machinery items, as per the technical report, these items are broadly
used at LGBIA for 24 hours per day as the Airport is working all three shifts and hence, as prescribed
under the Companies Act 2013, Schedule II for assets used during the year for double shift or triple
shift, the Expert has recommended to adopt useful life of 7.5 years instead of 15 years. The Authority
also notes that GIAL has adopted the same shorter useful life of 7.5 years for Cargo and Security
Equipment.
• GIAL has adopted shorter useful life of 3 years for Flight Information Display System (FIDS) and
AOCC Equipment (included under the category of ‘Information and Technology equipment’) in its
MYTP submission.
7.5.7 Apart from the above, the Authority notes that in respect of Fuel Farm facility, GIAL has adopted
‘weighted average’ useful life of 7.5 years. Since the major portion of the assets are in the nature of Plant
and Machinery, GIAL has estimated the useful life of the Fuel facility as 7.5 years and adopted higher
depreciation of 13.33% for the entire capital expenditure projected for this facility.
7.5.8 The Authority on perusal of all the above, has summarized its view as under:
Asset class - Building: The Expert has recommended shorter life for False Ceiling, Sanitation works,
Glass façade and Flooring works which appear to be integral part of the Airport Terminal Building. The
Authority's Order No.35 does not provide for reducing the life of assets under Asset class -Buildings.
The Authority observes that various components mentioned above are also an integral part of the
Terminal Building and should be added to the Terminal Building cost by applying the same rate of
depreciation as that of buildings. While the technical report provided by GIAL has determined the
shorter life to be adopted, it has not provided sufficient rationale for adopting such shorter useful life.
Since these assets are all part of the building, the Authority is of the view that the same rate applicable
to building should be applied to these assets and no reduction in life of these assets are called for. Further,
the Authority notes that adequate maintenance expenditure is allowed to enable GIAL to maintain the
assets in good working condition during its entire life. The Authority has issued Order No.35 as part of
its normative approach to various Building Blocks in Economic regulation of Major Airports where it
has stated that, “The Authority has been of the considered view, that it would be preferable to have as
far as practicable, a broad year to year consistency in what Depreciation is charged by the companies as
Consultation Paper No. 01/2024-25 Page 159 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
certified by the relevant statutory auditors and what the Authority would take into account in its process
of tariff determination. Issue of a notification will ensure this objective." In view of all the above, the
Authority is not inclined to deviate from ensuring this objective and therefore proposes not to consider
the shorter useful life of 25 years claimed by GIAL for both the Terminal Building and newly projected
Cargo terminal building.
Asset Class -Runways, Taxiways and Aprons: The Expert has recommended adopting a shorter life of
20 years based on useful life followed by certain international associations and regulators, like,
Federation Aviation Administration -US Department of Transportation, Civil Aviation Authority – UK,
Australian Airports Association – Australia etc., which the Authority feels does not provide proper
justification for adopting a shorter useful life. Therefore, the Authority finds no reason to reduce the life
of the Runway which enhances the burden of Airport users by increasing the tariff.
Other Asset Classes: Order No.35 provides for specific determination of life through technical
evaluation for specific assets other than those listed in the Order based on specific requirement of the
Airport. The Authority finds that none of the asset in these classes where a shorter life has been adopted
as specific assets are based on specific requirement of the Airport. Therefore, the Authority finds no
merit in reducing the life of such asset for tariff purposes.
7.5.9 Based on all the above, the Authority has proposed the following useful life for all the assets of LGBIA
during the Third Control Period:
Table 114: Useful Life proposed by the Authority for all the assets in the Third Control Period
(In Years)
Useful life submitted by Useful life proposed by
Asset Class
GIAL the Authority
Terminal Building 25 30
Runway, Taxiway and Apron 20 30
Cargo Building 25 30
Cargo Equipment 7.5 15
Boundary wall 5 5
Computer Servers, networks, etc. /
3 3
Software
Computer End-user devices / IT
3 3
equipment
Security equipment 7.5 15
Plant and Machinery 7.5 15
Other buildings 30 30
Access road 10 10
Furniture & fixtures 7 7
Vehicles 5 8
Office Equipment 5 5
7.5.10 Considering the above changes in depreciation rates, revision in the value of opening gross block of assets
and proposed capital expenditure, the Authority proposes the following depreciation for the Third
Control Period.
Table 115: Aeronautical depreciation proposed by the Authority for the Third Control Period
(₹ crores)
Particular FY'23 FY'24 FY'25 FY'26 FY'27 Total
Terminal Building 0.17 0.27 0.35 36.83 73.31 110.94
Runway, Taxiway and Apron 2.97 3.15 5.04 21.30 35.66 68.12
Consultation Paper No. 01/2024-25 Page 160 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Cargo building 0.01 0.07 0.13 0.52 0.91 1.64
Boundary wall 2.85 0.66 0.06 13.72 27.32 44.62
Software - 0.51 0.51 0.51 0.00 1.52
IT equipment 1.18 4.06 4.11 4.47 2.46 16.28
Security equipment - - 0.74 1.66 1.98 4.38
Plant and Machinery 3.62 4.00 5.35 8.41 10.18 31.56
Other Buildings 1.47 1.58 1.95 2.77 3.75 11.53
Access Road 0.03 0.03 0.03 7.31 14.60 22.00
Fuel - - 0.36 0.73 0.73 1.81
Furniture & fixtures 0.37 0.68 0.74 0.72 0.69 3.20
Vehicles 1.02 1.17 2.43 4.76 5.81 15.19
Office equipment 0.23 1.19 1.18 1.17 1.11 4.88
Total 13.93 17.37 22.99 104.88 178.51 337.68
7.5.11 The depreciation claimed by GIAL in comparison with that proposed by the Authority for each financial
year is shown in the table below:
Table 116: Depreciation claimed by GIAL and proposed by the Authority for the Third Control
Period
(₹ crores)
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
Depreciation claimed by 23.11 32.83 117.76 284.13 366.46 824.29
GIAL
Less: Adjustments made by -9.18 -15.46 -94.77 -179.25 -187.95 -486.61
the Authority on account of
change in useful life and
revision in asset addition.
Depreciation proposed by 13.93 17.37 22.99 104.88 178.51 337.68
the Authority
The Authority proposes to consider depreciation for LGBIA for the Third Control Period as ₹ 337.68
crores.
7.6 Regulatory Asset Base (RAB) for the Third Control Period
GIAL has submitted RAB for the Third Control Period as follows:
Table 117: RAB proposed by GIAL for LGBIA for the Third Control Period
(₹ crores)
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
Opening RAB (1) 140.28 164.82 217.99 3803.72 5545.53
Additions (2) 47.65 86.01 3703.48 2025.95 156.55 6019.64
Disposal/Transfers (3) 23.11 32.83 117.76 284.13 366.46
Depreciation (4) 164.82 217.99 3803.72 5545.53 5335.63 824.29
Closing RAB (5) = [(1) +(2) – (3) – (4)] 152.55 191.41 2010.86 4674.63 5440.58
Average RAB = [(1) + (5)]/2 140.28 164.82 217.99 3803.72 5545.53
Consultation Paper No. 01/2024-25 Page 161 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Authority’s examination regarding RAB for the Third Control Period
7.6.1 Opening RAB
The Authority notes that the Opening RAB amounting to ₹ 140.38 crores (as submitted by GIAL) has
been revised to ₹ 151.90 crores based on the adjustments made to the RAB as mentioned in Table 50 of
this Consultation Paper. Following are the key consideration in revision of opening RAB:
• Adjustment on account of revision in asset classification as detailed in asset allocation study.
• GIAL has considered higher useful life of asset which has been aligned to the useful life
recommended as per order no 35/2017-18 dated 12th Jan’2018. This is resulted into reduction in
depreciation and increase in regulatory asset base.
• As part of asset transfer to GIAL, AAI has to pay ₹ 5.94 crores towards payment of vacation of
quarters from CPWD. Since, CPWD asset handed over to GIAL as part of transition process, same
has been considered by the Authority as part of opening RAB.
• The Authority in line with above consideration proposed following Regulatory Asset Base schedule
for the Third Control Period:
Table 118: RAB proposed by the Authority for LGBIA for the Third Control Period
(₹ crores)
Particulars Ref. FY FY FY FY FY Total
2022-23 2023-24 2024-25 2025-26 2026-27
Opening RAB (1) Table 50 151.90 183.92 174.64 390.40 3748.55
Capital Additions (2) Table 111 45.95 8.09 238.76 3463.03 43.87 3799.70
Depreciation (3) Table 116 13.93 17.37 22.99 104.88 178.51 337.68
Closing RAB (4) = 183.92 174.64 390.40 3748.55 3613.92
[(1) +(2) – (3)]
Average RAB = 167.91 179.28 282.52 2,069.48 3,681.24
[(1) + (4)]/2
7.6.2 The Authority proposes to consider RAB for the LGBIA for the Third Control Period as detailed in
Table 118.
7.7 Authority’s proposal regarding CAPEX, Depreciation and RAB for the Third Control Period
Based on the material before it and based on its analysis, the Authority proposes the following with regard
to CAPEX, depreciation and Regulatory Asset Base for the Third Control Period.
7.7.1 To consider the revised Terminal Building ratio of 90:10 in line with the Study on allocation of assets
between Aeronautical and Non-aeronautical assets for LGBIA, IMG norms and as approved for other
similar Airports.
7.7.2 To allow IDC during the Third Control Period and not to allow Financing Allowance as mentioned in
Para 7.3.12.
7.7.3 To adopt the capitalization of Aeronautical Expenditure for the Third Control Period in accordance with
Table 111.
7.7.4 To reduce (adjust) 1% of uncapitalized project cost from the ARR in case any particular capital project
is not completed/capitalized as per approved capitalization schedule, as mentioned in para 7.3.11. The
same will be examined at the time of tariff determination of next Control Period.
7.7.5 To examine the accounting of input tax credits in accordance with Chapter V of The Central Goods and
Consultation Paper No. 01/2024-25 Page 162 of 254CAPEX, DEPRECIATION AND RAB FOR THE THIRD CONTROL PERIOD
Services Tax Act, 2017 and make necessary adjustments at the time of determination of tariffs for the
Third Control Period.
7.7.6 To true up the Aeronautical Capital expenditure based on actuals subject to, cost efficiency and
reasonableness at the time of determination of tariff for the Fourth Control Period.
7.7.7 To adopt Aeronautical Depreciation as per Table 115 for the Third Control Period.
7.7.8 To true up the Depreciation of the Third Control period based on the actual asset additions and actual
date of capitalization during the tariff determination of the Fourth Control Period.
7.7.9 To consider average RAB for the Third Control Period for LGBIA as per Table 118.
7.7.10 To true up the RAB based on actuals at the time of tariff determination for the Fourth Control period.
Consultation Paper No. 01/2024-25 Page 163 of 254FAIR RATE OF RETURN (FRoR) FOR THE THIRD CONTROL PERIOD
8 FAIR RATE OF RETURN (FRoR) FOR THE THIRD CONTROL PERIOD
8.1 GIAL’s submission regarding FRoR for the Third Control Period
Cost of equity
8.1.1 GIAL has considered the Cost of equity as 17.30% based on a report by PwC.
8.1.2 GIAL has submitted the following assumptions for estimating the Cost of equity:
• Risk-free rate was calculated by taking 10-year average yield on a daily basis, for 10-year
Government of India securities.
• Asset beta was derived based on five-year weekly regressed beta computed for comparable listed
airports (weighted), and adjusted for appropriate leverage to determine the levered Equity beta
• Although various debt-equity (leverage or gearing) ratios had been analyzed, the assumed leverage
for computation of Cost of equity was the normative approach and standard adopted in earlier tariff
determination exercises of the Authority, i.e., debt-equity ratio of 48:52. For such leverage ratio,
the Equity beta was computed to be in the range of 1.35 – 1.38.
• Equity risk premium over risk-free rate was computed as 7.06%, based on an average of equity risk
premiums computed by a list of studies and standard market indices taken for the analysis.
Table 119: Cost of equity computation as per GIAL’s submission
Parameter Value
Risk-free rate 7.57%
Equity Risk Premium 7.06%
Debt-equity ratio (leverage) 48:52
Equity beta 1.35 - 1.38
Cost of equity (rounded off) 17.11% – 17.28%
Cost of debt
8.1.3 GIAL has submitted that Cost of debt assumed for the Third Control Period was 12%, based on actual
debt taken as of date.
8.1.4 In May 2022, Adani Airport Holdings Limited had raised a 3-year External Commercial Borrowing
facility from a consortium of Standard Chartered Bank and Barclays Bank PLC. The all-in borrowing
cost of this facility is 12.10% p.a., the breakdown of which is provided in the table below:
Table 120: Breakdown of all-in External Commercial Borrowing cost of Adani Airport Holdings Limited
Particulars Value
Secured Overnight Financing Rate (SOFR) reference 2.28%
Spread over SOFR 4.25%
Withholding tax gross up (at 5% of SOFR + spread) 0.33%
One-year forward Dollar-Rupee hedge cost (mandatory as per RBI guidelines) 4.51%
Upfront fees (annualised) 0.73%
All-in Cost of External Commercial Borrowing 12.10%
8.1.5 It was mentioned that a part of the proceeds raised from this facility are being on-lent to GIAL for the
purpose of financing its capital expenditure at the rate of 12.25% p.a. For the purposes of computation
of weighted average cost of capital, cost of debt has been assumed as 12% p.a.
Weighted average cost of capital
8.1.6 Based on the Cost of equity, Cost of debt and gearing ratio, GIAL has submitted the following FRoR
for the Third Control Period:
Consultation Paper No. 01/2024-25 Page 164 of 254FAIR RATE OF RETURN (FRoR) FOR THE THIRD CONTROL PERIOD
Table 121: FRoR computation submitted by GIAL
Parameter Value
Cost of equity 17.30%
Cost of debt 12.00%
Weighted average gearing of equity 52.00%
Weighted average gearing of debt 48.00%
FRoR 14.76%
8.2 Authority’s Examination regarding FRoR for the Third Control Period
Cost of equity
8.2.1 The Authority had commissioned independent studies for the evaluation of cost of capital separately, in
case of each PPP Airport, namely DIAL, MIAL, GHIAL, BIAL and CIAL through a premier institute,
namely IIM Bangalore and proposes to use these study reports as a basis, to the extent applicable and
relevant, to ascertain the Cost of equity of LGBIA for the Third Control Period.
8.2.2 The independent study reports have drawn from the international experience of airports and their
conclusions have been evaluated to the extent comparable with LGBIA in terms of hybrid till, ownership
structure, size, scale of operations and regulatory framework. The median and average Cost of equity
arrived at by the independent study reports are 15.16% and 15.18%, respectively, as shown in the table
below:
Table 122: Computation of Cost of equity as per IIM Bangalore independent study reports
Particulars CIAL MIAL BIAL DIAL GHIAL Average
Risk-free rate (A) 7.56% 7.56% 7.56% 7.56% 7.56% 7.56%
Equity beta (B) 0.9427 0.9391 0.9262 0.9732 0.9442 0.94508
Equity risk 8.06% 8.06% 8.06% 8.06% 8.06% 8.06%
premium (C)
Cost of equity 15.16% 15.13% 15.03% 15.41% 15.17% 15.18%
A + (B * C)
Average Cost of equity 15.18%
8.2.3 The Authority notes that the Cost of Equity for the purpose of determination of FRoR has to be fairly
consistent in case of PPP airports across India as the factors considered by the Independent Study in
CAPM formula such as Risk Free Rate, Market premium are in Indian context and do not vary
significantly among the Airports as these are operated under similar environment. Further, the averaging
out exercise normalises the risk factors across Airports in Cost of Equity computation.
8.2.4 Based on the above reports, the Authority proposes the Cost of equity of 15.18% for LGBIA for the
Third Control Period. This is also in line with the considerations of the Authority for other similar
airports including Lucknow.
Cost of debt
8.2.5 GIAL has considered Cost of Debt for the Third Control Period at 12% based on its current borrowing
rate from a related party and based on Adani Airport Holdings Limited’s all-in borrowing cost of
12.10%.
8.2.6 Since the Airport has not obtained any credit rating from an external rating agency, there is no direct
comparable entity or market data for determining cost of debt for LGBIA.
8.2.7 The Authority recommends that the Airport bring in further efficiencies in its cost of borrowing by
leveraging its parent entity’s financial strength in order to reduce the interest rates. This suggestion is
also in keeping with the spirit of PPP whereby it is expected that the financial strength of PPP airports
Consultation Paper No. 01/2024-25 Page 165 of 254FAIR RATE OF RETURN (FRoR) FOR THE THIRD CONTROL PERIOD
will be maintained at an optimal level and their cost of capital will be within reasonably allowable limits.
GIAL should avail the synergies and benefits owed to it by its strong shareholding and balance sheet of
its Parent companies and therefore work towards bringing down the cost of debt to the same level as
other PPP airports.
8.2.8 The Authority also notes that the cost of debt for airport operators forms vital part of the Return on
Capital Employed / Fair Rate of Return provided to the airport operators on the investment towards
creation of the capital assets w.r.t the airport project.
It is imperative that the cost of debt that is considered in the calculation of FRoR is reflective of the
current cost of debt that the airport operator incurs towards debt financing the airport infrastructure.
The following aspects, in this regard has been considered while arriving at the efficient cost of debt to
be provided as part of the FRoR:
i. Cost of debt financing in the Indian / International context is usually linked to the External Credit
Rating of the Airport Operator/ Project SPV. As a result, any cost of debt actually incurred if it
must be deemed efficient should be factoring in the External Credit Rating (ECR) of the entity.
Usually Banks/ FIs mark a spread over and above their benchmark lending rate (usually
published as Marginal Cost of Lending Rate i.e. MCLRs) as the interest rate for funding specific
projects. This spread is linked to the ECR of the Borrower which in this case is the airport
operator. AERA has follow a similar assessment to arrive at the cost of debt to be provided to
the airport operator.
ii. Debt must be a senior secured debt raised from financial institutions/ banks private /public or
foreign at an arm’s length basis. There could be instances wherein the debt raised is subordinated
to senior debt and would hence incur a higher cost and thereby deemed inefficient. Such
inefficient cost may not be the right indicator of the actual cost of debt and hence appropriate
adjustment has to be carried out while allowing such cost in the tariff determination process.
iii. There have also been instances wherein senior secured debt have been advanced by promoter/
promoter entities in which case the arm’s length criteria could be questioned. It is pertinent to
note that similar to the above case such costs also could not be deemed to be efficient and hence
adequate adjustments to be carried out to ensure that the costs considered is reflective of the
efficient cost. AERA doesn’t encourage related party transactions and insists transparency and
arm’s length criteria in the interest of public.
iv. Airport Operators currently in the country baring a few exceptions have managed to retain an
ECR of A and above. In some cases where the airport is yet to establish a steady stream of
positive cash flows on account of emerging nature of operations, the debt servicing is backed by
the strength of the promoter entities which is also factored by the ECR rating agencies. As a
result, considering the prevalent MCLRs which are in the range of 8.45%- 8.55%, an interest
rate of 9% is usually considered as the cost of debt for these airport operators. However, given
the expected softening of rates globally, and the impetus to promote economic growth as
inflations fears have slowed down, the MCLRs are expected to gradually reduce over the next
2-3 years bringing down the cost of borrowing further. AERA want Airport Operators to
improve ECR by bringing in efficiency and transparency which in turn will reduce MCLRs.
v. Arriving at the cost of debt through assessment of the debt raising capacity of the airport operator
rather than providing the actual cost of debt as submitted by the airport operator would benefit
the airport stakeholders in the long run. The Airport operators would strive to be more efficient
in their fund-raising endeavours rather than taking comfort from the true up option available to
them considering the actual cost of debt.
Consultation Paper No. 01/2024-25 Page 166 of 254FAIR RATE OF RETURN (FRoR) FOR THE THIRD CONTROL PERIOD
AERA has already been following a similar exercise while arriving at the leverage ratios wherein a D:E
ratio of 48:52 has been considered rather than the actual debt: equity (D:E) ratio which is in the range of
80:20 for most of the airport operators. Considering an efficient cost of debt rather than the actual cost
of debt will be consistent with the stand taken for the leverage ratios used to calculate the FRoR. Further,
it may also be noted that as the traffic growth and associated revenue from Aeronautical & Non-
Aeronautical services improve; and the timely execution of capital projects, approved by the Authority,
are completed and start to yield benefits. It is expected that the debt profile of LGBIA is bound to
improve and its inherent financial risk, as reflected in the cost of debt will reduce to the levels of other
PPP airports.
8.2.9 The Authority expects GIAL to exercise its best endeavor to undertake the financing towards capital
expenditure at competitive rates as in other PPP airports and take all steps as detailed above, with support
from its Parent company to optimize the cost of debt and follow all requisite procedures of financing
including following all Government guidelines, obtaining efficient credit rating etc. in order to ensure
that debt is contracted at optimum rates to ensure that the users of the airport are not burdened.
8.2.10 The Authority also notes that the average cost of debt of the other five PPP airports viz., DIAL, MIAL,
GHIAL, BIAL and CIAL is 8.96%.
8.2.11 Accordingly, the Authority has considered the Cost of Debt of 9% for the computation of Fair Rate of
Return. The Authority also directs GIAL to ensure that Related Party transactions, if any, with respect
to borrowing of funds are benchmarked with most optimum rates available and is well justified.
Fair Rate of Return
8.2.12 Based on the above, the Authority proposes to consider the following FRoR for the Third Control Period
for LGBIA:
Table 123: Fair Rate of Return proposed by the Authority for the Third Control Period
Parameter Value
Cost of equity 15.18%
Cost of debt 9.00%
Weighted average gearing of equity 52.00%
Weighted average gearing of debt 48.00%
Fair Rate of Return 12.21%
8.2.13 The above independent study reports have used the Capital Asset Pricing Model (CAPM) and a notional
gearing (Debt: Equity) ratio of 48:52 to determine the levered Equity beta and accordingly, derive the
Cost of equity. The Authority would like to mention that FRoR is computed on the basis of Cost of
Equity and Cost of Debt. It has determined the CoE based on the IIM Bangalore independent study
reports for the other PPP Airports whereas, the Cost of Debt has been computed as per the 3-month SBI
MCLR along with spread and the Cost of Debt of other five PPP airports viz., DIAL, MIAL, GHIAL,
BIAL and CIAL.
8.2.14 The Authority notes that the actual gearing deployed by Airport Operators of PPP airports are usually
higher than the notional gearing adopted by the Authority, which ultimately benefits the AO. However,
since the debt equity mix has been proposed by the Authority considering the efficient capital structure
and the interest of all the Stakeholders, the notional gearing ratio of 48: 52 will not be trued up during
the tariff determination for the next Control Period.
Consultation Paper No. 01/2024-25 Page 167 of 254FAIR RATE OF RETURN (FRoR) FOR THE THIRD CONTROL PERIOD
8.3 Authority’s proposals regarding FRoR for the Third Control Period
Based on the materials before it and based on its analysis, the Authority proposes the following:
8.3.1 To consider the Cost of equity at 15.18%.
8.3.2 To consider the notional debt to equity (gearing) ratio of 48%:52% in line with target gearing ratio being
considered in case of other PPP airports.
8.3.3 To consider cost of debt of 9% for the Third Control Period.
8.3.4 To consider FRoR of 12.21% for the Third Control Period based on above mentioned Cost of equity,
Cost of debt and gearing ratio as per Table 123.
Consultation Paper No. 01/2024-25 Page 168 of 254INFLATION FOR THE THIRD CONTROL PERIOD
9 INFLATION FOR THE THIRD CONTROL PERIOD
9.1 GIAL’s submission regarding Inflation for the Third Control Period
9.1.1 GIAL has submitted inflation as 5% from FY23-24 onwards every year, while projecting capital
expenditure and operating expenditure for LGBIA for the Third Control Period.
9.1.2 The inflation rate has been submitted by GIAL based WPI inflation forecasts as summarized in the table
below:
Table 124: WPI inflation rate submitted by GIAL
Financial Year WPI All Commodities Source
FY23-24 onwards Mean as 5% RBI Forecaster Survey 79th
round dated 07th Dec 2022
9.2 Authority’s examination regarding Inflation for the Third Control Period
9.2.1 The Authority has examined the submission made by GIAL on inflation to be considered for the Third
Control Period.
9.2.2 The Authority proposes to consider mean of WPI inflation forecasts (All Commodities) for FY 2023-
24, FY2024-25 and FY 2025-26 as per the recent “Results of the Survey of Professional Forecasters on
Macroeconomic Indicators – Round 87” released on April 5, 2024, by the Reserve Bank of India (RBI).
An extract of the results is reproduced below:
Table 125: WPI inflation rates as per RBI’s annual forecast
Financial Year WPI All Commodities Source
FY22-23 9.42% Index Numbers of Wholesale Price in India for the
(Cumulative YoY) Month of March, 2023 (Base Year: 2011-12)
published by Ministry of Commerce & Industry
FY23-24 Mean as -0.7%
FY24-25 Mean as 3.1% RBI Forecaster Survey 87th round dated April 5,
2024
FY25-26 Mean as 3.7%
9.2.3 The Authority has considered the inflation rate of FY 2025-26 for the subsequent tariff year of the Third
Control Period. Accordingly, the following table shows the inflation rates as proposed by the Authority
for the Third Control Period.
Table 126: Inflation rates proposed by the Authority for Third Control Period
Particulars FY’23 FY’24 FY’25 FY’26 FY’27
WPI inflation 9.42% -0.7% 3.1% 3.7% 3.7%
9.3 Authority’s proposal relating to inflation for the Third Control Period
Based on the material before it and its analysis, the Authority proposes the following:
9.3.1 To consider WPI inflation as per Table 126.
Consultation Paper No. 01/2024-25 Page 169 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
10 OPERATION AND MAINTENANCE (O&M) EXPENSES FOR THE THIRD CONTROL
PERIOD
10.1 GIAL’s submission regarding Operation and Maintenance (O&M) Expenses for the Third
Control Period
10.1.1 GIAL in its MYTP submission has stated that the Aeronautical Operation and Maintenance (O&M)
expenses for the Third Control Period has been estimated based on the following assumptions:
• Expansion of LGBIA: GIAL is constructing a New Integrated Terminal Building (NITB) as
obligated under Concession Agreement and is proposed to be commissioned by FY 2024-25. After
commissioning of NITB operations from the existing Terminal 1 will be moved to NITB. Year wise
increase in operational terminal area is tabled below.
Table 127: Details of increase in the Terminal Building area projected by GIAL
YoY % increase in
Financial Year T1 (sq. m.) NITB (sq. m.) Total (sq. m.)
area
FY’23 20,300 20,300
FY’24 20,300 20,300 0%
FY’25 20,300 20,300 0%*
FY’26 1,46,300 1,46,300 621%
FY’27 1,46,300 1,46,300 0%
*NITB shall be operational from Feb’25 onwards. Hence for projection of expenses, area increase has been assumed from
FY25-26 onwards
Considering the expansion of the Terminal Building area, as shown in the above table, GIAL has
projected proportionate increase in various expenses such as Utilities, IT expenses, Rates & Taxes,
Security and Other Operating expenses.
• Inflation: GIAL has considered inflationary increase based on 79th Round of RBI forecaster
survey Dec-2022, towards all expenses for the Third Control Period.
• Base Year: FY 2022-23 has been considered as the base year and relevant growth percentages have
been applied over the same to estimate expenses for other Financial Years.
• Fuel Operating Expenses: The operations of Fuel facility are to be outsourced to a third-party
vendor in FY 2023-24 on a ‘Cost plus margin’ basis, which includes employee cost, repairs and
maintenance expenses and facility operating expenses. Annual inflation of 5% is considered in the
O&M fee increase.
• Cargo Operating Expenses: Cargo expenses have been estimated for the Third Control Period
based on the assumption of an interim cargo facility from FY2023-24 onwards and a new Integrated
Cargo Terminal (ICT) facility by refurbishing / retrofitting the existing passenger Terminal-1
building from FY 2026-27. Further, Cargo expenses have been increased by 10% per annum for the
Third Control Period.
10.1.2 GIAL has submitted the following categories of O&M expenses in its MYTP submission:
Table 128: O&M expenses (category wise) claimed by GIAL for the Third Control Period
Type of O&M Expense Expense Category
Manpower Expenses – AAI employees
Manpower Expenses – GIAL employees
Aeronautical Operating Expenses Utility Expenses
IT Expenses
Rates and Taxes
Consultation Paper No. 01/2024-25 Page 170 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Type of O&M Expense Expense Category
Security Expenses
Corporate Allocation
Administrative Expenses – Collection Charges on UDF
Administrative Expenses - Others
Insurance
Repair and Maintenance Expenses
Other Operating Expenses
Independent Engineer Fee
Amortisation of Runway recarpeting expenses
O&M Expenses
Fuel Operating Expenses
Bowser Rental
GIAL Staff Salary
Cargo Operating Expenses O&M expenses
Customs cost recovery
10.1.3 The above expenses do not include Concession Fee, since it is not considered as part of Aeronautical
O&M expenses, as per Clause 27.1.2 of the CA, which states that:
“The Monthly Concession Fee paid/ payable by the Concessionaire to the Authority under and pursuant
to the terms of this Agreement shall not be included as a part of costs for provision of Aeronautical
Services and no pass-through would be available in relation to the same.”
10.1.4 GIAL has allocated all O&M expenses as Aeronautical.
Table 129: Segregation of O&M expenses and basis of allocation as per GIAL’s submission
Expense Category Expense classification Aeronautical
Manpower expenses – AAI employees Aeronautical 100 %
Manpower expenses – GIAL employees Aeronautical 100 %
Utility expenses Aeronautical 100 %
IT expenses Aeronautical 100 %
Security expenses Aeronautical 100 %
Corporate Allocation Cost Aeronautical 100 %
Administrative expenses Aeronautical 100 %
Insurance expenses Aeronautical 100 %
Rates and taxes Aeronautical 100 %
Repairs and Maintenance expenses Aeronautical 100 %
Other Operating expenses Aeronautical 100 %
Independent Engineer Fee Aeronautical 100 %
Runway recarpeting Aeronautical 100 %
Fuel Operating expenses Aeronautical 100 %
Cargo Operating expenses Aeronautical 100 %
10.1.5 The total Aeronautical O&M expenses including Fuel and Cargo Operating Expenses submitted by
GIAL for the Third Control Period have been presented as follows:
Table 130: Total Aeronautical Operation and Maintenance expenses submitted by GIAL
(₹ crores)
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
Aeronautical Operating Expenses
Manpower expenses - AAI 27.64 32.52 31.85 30.26 33.28 155.55
Manpower expenses - GIAL 9.57 14.38 28.52 44.92 53.07 150.46
Consultation Paper No. 01/2024-25 Page 171 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
Utility expenses 6.70 8.24 8.65 65.49 68.76 157.85
IT expenses 2.50 7.00 19.78 41.09 44.02 114.39
Rates and Taxes 0.31 0.75 0.79 5.71 6.00 13.56
Security expenses 3.75 6.00 6.11 9.97 12.02 37.86
Corporate Allocation Cost 12.89 15.00 42.39 45.65 48.91 164.85
Administrative expenses (excluding 0.98 1.64 1.67 1.89 2.27 8.45
Collection charges on UDF)
Administrative expenses – Others 13.56 34.00 37.40 41.14 45.25 171.35
Insurance 2.31 2.89 6.68 9.03 9.52 30.43
Repairs and Maintenance 19.51 23.74 28.29 136.31 200.51 408.36
Other Operating expenses 13.43 22.00 23.10 167.63 176.02 402.18
Independent Engineer Fees 3.91 3.91 3.91 4.11 4.31 20.16
Runway recarpeting - - - 22.61 26.47 49.08
Financing Charges and Others 2.52 47.81 10.87 16.24 18.50 95.94
Aeronautical Operating Expenses (A) 119.58 219.87 250.01 642.06 748.94 1,980.47
Fuel Operating Expenses
O&M Expenses - 2.95 9.33 10.27 11.73 34.28
Bowser Rental - 0.66 0.99 - - 1.65
Fuel Operating Expenses (B) - 3.61 10.32 10.27 11.73 35.93
Cargo Operating Expenses
Insourced salary - 0.50 0.55 0.61 0.67 2.32
O&M Expenses - 1.05 1.49 2.00 11.98 16.51
Customs Cost Recovery - - - - 1.80 1.80
Cargo Operating Expenses (C) - 1.55 2.04 2.60 14.44 20.63
Total Aeronautical O&M Expenses 119.58 225.03 262.36 654.93 775.11 2,037.03
(A+B+C)
10.1.6 The growth rates assumed by GIAL for total Aeronautical O&M expenses have been presented in the
tables below:
Table 131: Growth rates for Aeronautical O&M expenses submitted by GIAL for the Third Control Period
Particulars Cost Driver FY’23 FY’24 FY’25 FY’26 FY’27
Escalated
Aeronautical Operating Expenses
Manpower Expenses – AAI Salary Cost - 10% 10% 10% 10%
employees
Manpower Expenses – GIAL Salary Cost - 10% 10% 10% 10%
employees
Utility expenses (Power) Per unit rate - 5.0% 5.0% 5.0% 5.0%
IT expenses Total Expense - 75.9% 71.1% 7.7% 14.3%
Rates and Taxes Total Expense - 35.3% 182.6% 7.7% 7.1%
Security expenses Total Expense - 29.5% 1.8% 13.2% 20.5%
Corporate Allocation Cost Total Expense - 35.3% 182.6% 7.7% 7.1%
Administrative expenses (UDF) - 29.5% 1.8% 13.2% 20.5%
Administrative expenses (Others) Total Expense - 10.0% 10.0% 10.0% 10.0%
Insurance – on Opening Net Total Expense - 10.0% 10.0% 10.0% 10.0%
block of Assets
Repairs and Maintenance – on Total Expense - 10.0% 10.0% 10.0% 10.0%
Opening Net block of Assets
Consultation Paper No. 01/2024-25 Page 172 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Particulars Cost Driver FY’23 FY’24 FY’25 FY’26 FY’27
Escalated
Other Operating expenses Total Expense - 5.0% 5.0% 5.0% 5.0%
Independent Engineer Fees - - - 5.0% 5.0%
Fuel Operating Expenses
O&M Expenses Total Expense - - 5% 5% 5%
Bowser Rental Total Expense - - - - -
Cargo Operating Expenses
Insourced salary Total Expense - - 10% 10% 10%
O&M Expenses Total Expense - - 10% 10% 10%
Customs Cost Recovery Total Expense - - 10% 10% 10%
Table 132: One-time Escalation rates for Aeronautical O&M expenses submitted by GIAL for the
Third Control Period
Particulars Cost Driver FY’23 FY’24 FY’25 FY’26 FY’27
Escalated
Electricity Charges Billable Units - - - 621 % -
Rates & taxes Total Expense - - - 621 % -
IT Expenses Total Expenses - - - 100% -
Security expenses Total Expense - - - 50 % -
Other Operating Expenses Total Expense - - - 621% -
It can be seen from Table 132 above, that GIAL has claimed one-time escalation rates in Utilities,
Rates and Taxes, IT Expenses, Security expenses and Other Operating expenses in FY 2025-26
based on projected increase in the area of Terminal Building (i.e., NITB commissioning).
10.1.7 GIAL while estimating runway recarpeting amortization has also considered carrying cost on the
unamortized balance of the expense incurred on re-carpeting of runways at the rate of FRoR i.e.
14.76%.
10.2 Authority’s examination regarding Operation and Maintenance (O&M) Expenses for the
Third Control Period
10.2.1 The Authority has examined the Operation and Maintenance expenses based on the following
parameters:
A. Consideration of actual expenses for FY 2022-23 and FY2023-24, and revision in growth rates of
various expenses
B. Re-allocation of the expenses into aeronautical, non-aeronautical and common.
C. Rationalization of Employee Head Count
10.2.2 GIAL, in their submission proposes 100% of the operating expenses as Aeronautical. The tariff
methodology adopted by the Authority, segregates O&M expenses into Aeronautical, Non-
Aeronautical and Common considering the nature and purpose of the services for which these expenses
are incurred. However, in the absence of any specific information regarding segregation of expenses,
due clarifications were sought from GIAL regarding calculation of various allocation ratios such
as terminal area. GIAL has maintained that as per the AERA guidelines, airside assets are to be
considered as Aeronautical and the Terminal Building is considered as Aeronautical as per the
AERA Act. However, if GIAL so desires, they may adopt Single Till methodology wherein all
assets and operating expenses are considered as Aeronautical.
10.2.3 The Authority also notes that LGBIA is a brownfield airport and was established in 1958. The Authority
has accordingly considered rationalization of costs in certain categories considering that these were
Consultation Paper No. 01/2024-25 Page 173 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
operated at optimal level of costs by AAI earlier.
Manpower Expenses of AAI employees
10.2.4 GIAL has considered the Manpower Expenses of AAI employees as 100% aeronautical, as this expense
is considered as pass through in the determination of Aeronautical charges, as per the Clause 6.5 read
with Clause 28.4.3 of the Concession Agreement. The Authority, in this regard examined the extract of
the relevant clauses of the Concession Agreement which reads as under:
• Clause 6.5.1. states that:
(i) “Select Employees” shall mean those employees of the Authority as set forth in Schedule S (of the
rank of assistant general manager and below) who are posted at the Airport by the Authority and shall
be deployed at the Airport for the duration of the Joint Management Period and Deemed Deputation
Period. The Select Employees shall stand reduced to the extent of employees who retire, are deceased
or otherwise separated from Authority's services during the Joint Management Period or Deemed
Deputation Period. It is clarified that the Select Employees shall not be reduced to the extent of
employees who are transferred by AAI.
(ii) “Joint Management Period” shall mean the period commencing from the COD and ending on the
date which is I (one) calendar year after the COD.
(iii) “Deemed Deputation Period” shall mean the period commencing from the expiry of the Joint
Management Period and ending on the date which is 2 (two) calendar years therefrom.”
• Clause 6.5.4 states that:
“The Concessionaire shall bear the Select Employee Costs for the Joint Management Period and
Deemed Deputation Period.”
• Clause 6.5.10 states that:
“If, at the expiry of the Deemed Deputation Period, the number of Accepting Employees is less than
60% (sixty) percent of the Select Employees (the ·'Deficit Employees"), the Concessionaire shall,
commencing from the expiry of the Deemed Deputation Period pay to the Authority, on a monthly basis,
such amounts as may be indicated in an invoice to be raised by the Authority on the Concessionaire
with regard to the emoluments payable by the Authority in respect of such Deficit Employees (the
"Deficit Employee Costs").
(ii) The Deficit Employee Costs shall be considered for pass-through in the determination of the
Aeronautical Charges.”
• Clause 28.4.3. states that:
“The Parties agree and acknowledge that the Concessionaire expressly waives its right to seek as
pass-through in the Aeronautical Charges such costs and/ or expenses which the Concessionaire is
restrained under this Agreement from seeking to be passed-through thereunder.”
10.2.5 The Authority, on review of the above clauses of the CA, proposes to consider the Manpower Expenses
of AAI employees up to ‘Deemed Deputation Period’ as Common since the Manpower of AAI is used
for both Aeronautical and Non-aeronautical activities. Accordingly, the Authority proposes to apportion
the Manpower Expenses of AAI employees up to ‘Deemed Deputation Period’ to Aeronautical activities
based on the Employee Headcount Ratio of AAI employees as of March 2024 (refer Table 140).
10.2.6 In respect of the Manpower Expenses of AAI employees relating to ‘Deficit Employees’ after the expiry
of the Deemed Deputation Period (expires in October 2024), the Authority proposes to consider these
Consultation Paper No. 01/2024-25 Page 174 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
expenses as 100% pass through as mandated by Clause 6.5.10. of the CA.
Manpower Expenses of employees of GIAL
10.2.7 GIAL has allocated the Manpower Expenses of GIAL employees as 100% Aeronautical. The Authority
observes that since total manpower strength includes staff which provides non-aeronautical services also,
the aeronautical Employee Headcount of GIAL needs to be suitably derived for appropriate allocation
of costs. The Aeronautical Headcount and Employee Headcount Ratio (ECHR) for each tariff year, as
well as 5-year average of such ECHR for the entire Third Control Period has been provided in Table
140 below.
Utility Expenses
10.2.8 GIAL has segregated the expenses towards Utilities after netting off the recoveries proposed to be made
from the Concessionaires for Non-aeronautical activities and has considered the net Utilities expenses
as 100% Aeronautical. The Authority finds this allocation to be in line with that followed in other similar
airports and proposes to consider the same.
IT expenses and Insurance expenses
10.2.9 GIAL in its MYTP submission has considered the expenses towards IT expenses as 100% Aeronautical.
The Authority, however, proposes to apportion the IT expenses in the Terminal Building ratio of 90:10
as prescribed in para 7.3.14 considering the utility and nature of IT services being provided at the Airport
which is also in line with the allocation considered for other similar airports.
10.2.10 GIAL has considered the Insurance expenses as 100% Aeronautical. However, the Authority proposes
to consider the Insurance expenses as Common on the basis that these expenses encompass all assets
including Non-Aeronautical assets. The Authority, thus proposes to apportion as per the Gross Fixed
Asset Ratio i.e., 95.39:4.61 as proposed by the Study on Efficient Operation and Maintenance Expenses
of LGBIA, and also considered for other similar airports.
Security Expenses
10.2.11 The Authority observes that GIAL has considered the expenses towards Security as 100% Aeronautical.
The Authority, however proposes to consider the Gross Fixed Asset Ratio i.e., 95.39:4.61, as prescribed
by the Study on Efficient Operation and Maintenance Expenses of LGBIA, for allocating Security
expenses.
Administrative Expenses
10.2.12 The Authority observes that GIAL has segregated Administrative expenses including expenses towards
Professional & Consultancy, Sales & Marketing, Travelling & Communication, Printing & stationery
etc. and considered all as 100% Aeronautical. The Authority apportioned the Administrative Expenses
in Gross Fixed Asset Ratio i.e., 95.39:4.61, as proposed by the Study on Efficient Operation and
Maintenance Expenses of LGBIA undertaken for Second Control Period.
10.2.13 The Authority observes that GIAL has considered Collection charges on UDF as 100% Aeronautical
on the basis that these charges have been paid towards collection of aeronautical revenue and
accordingly the Authority has considered the same as Aeronautical which is in line with the approach
adopted for other airports.
Corporate Cost Allocation
10.2.14 GIAL has considered expenses towards Corporate Allocation Cost as 100% Aeronautical in its
MYTP submission. GIAL has engaged an Independent Consultant for conducting a Study on
allocation of Corporate Costs of both AEL and AAHL. GIAL has further shared a Note on the
Consultation Paper No. 01/2024-25 Page 175 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Study report which provides the types of services / costs that have to be allocated to GIAL, along
with the basis of allocation of such costs. As per the details shared by GIAL, the corporate costs
have been allocated based on applicable costs or revenue drivers such as Ratio of Number of
Employees of a SPV to Total Adani Group Employees, Ratio of Per Pax Revenue of SPV to total
Per Pax Revenue, Ratio of Debt raised for a SPV to total Debt raised for Airport Group, Ratio of
Turnover of a SPV to Total Group Turnover etc. GIAL has further shared details of the total
corporate cost allocated to each airport, which is 5.43% for FY23, as apportioned to GIAL.
GIAL has derived the allocable corporate expense based on the aforementioned study. However,
the basis for allocation of the costs towards Aeronautical and Non-aeronautical activities has not
been provided in the Study report. In the absence of an appropriate basis, the Authority allocated
the cost in the ratio of revised Total Employee Headcount Ratio i.e., Employee Head Count of both AAI
and GIAL for each tariff year as is shown in Table 140.
Expenses towards Repairs & Maintenance, Rates & Taxes and Other operating expenses
10.2.15 The Authority observes that GIAL in its MYTP submission has considered expenses towards
Repairs and Maintenance as 100% Aeronautical. The Authority has treated R&M expenses as
Common expense, since it pertains to assets providing Aeronautical and Non-Aeronautical services.
The Authority thus proposes to apportion these expenses as per the Terminal Building Ratio i.e., 90:10.
10.2.16 The Authority observes that GIAL has considered expenses towards Rates and Taxes as 100%
Aeronautical. The Authority treated the same as Common expense and apportioned it as per the Gross
Fixed Asset Ratio i.e., 95.39:4.61.
10.2.17 The Authority observes that GIAL has considered expenses towards Other Operating expenses as
100% Aeronautical. The Authority considers treating such expenses as Common expense and
proposes to allocate as per the Terminal Building ratio of 90:10.
10.2.18 The Authority observes that GIAL has considered expenses towards Independent Engineer Fees as
100% Aeronautical. In accordance with the CA, GIAL has to appoint an Independent Engineer. As per
Clause 24.3.1, the cost associated with such Independent Engineer shall be considered as pass-through
for determination of Aeronautical Charges by the Regulator. Relevant extract of the CA has been
reproduced below:
Clause 24.3.1.
The remuneration, cost and expenses of the Independent Engineer shall be paid by the Authority, and
all such remuneration, cost and expenses shall be reimbursed by the Concessionaire to the Authority
within 15 (fifteen) days of receiving a statement of expenditure from the Authority. Any amounts paid to
the Independent Engineer shall be considered for a pass-through for the determination of the
Aeronautical Charges by the Regulator.
Considering the concession provisions quoted above, IE expenses has been considered as 100%
Aeronautical by the Authority.
Amortization of runway recarpeting expenses, Fuel and Cargo Operating expenses
10.2.19 GIAL has considered the expense towards Amortization of runway recarpeting, Fuel and Cargo
Operating expenses as 100% Aeronautical. The Authority finds the classification of the aforementioned
expenses to be reasonable and proposes to consider the same. Further, the Authority notes that the
classification of Fuel and Cargo expenses as 100% Aeronautical is as per Section 2(a) of the AERA Act
Consultation Paper No. 01/2024-25 Page 176 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
2008.
10.2.20 The Authority’s proposal for allocation of Total Aeronautical O&M expenses of LGBIA as compared
to that submitted by GIAL has been summarized in the table below:
Table 133: Allocation of O&M expenses submitted by GIAL and proposed by the Authority for the
Third Control Period
O&M expense allocation as
per
Allocation ratio proposed by
Particulars The
GIAL’s the Authority
Authority’s
Submission
Proposal
Manpower Expenses – AAI employees (up to Employee Headcount ratio of
100.00% 99.12%
Deemed Deputation Period) AAI employees
Manpower Expenses – AAI employees (Deficit
100.00% 100.00% Aeronautical
Employee Cost)
Employee Headcount ratio of
Manpower Expenses – GIAL employees 100.00% 96.01%
GIAL’s employees
Utility expenses 100.00% 100.00% Aeronautical
IT expenses 100.00% 90.00% Terminal Building ratio
Rates and Taxes 100.00% 95.39% Gross Fixed Asset ratio
Security expenses 100.00% 95.39% Gross Fixed Asset ratio
Security Others 100.00% 95.39% Gross Fixed Asset ratio
Corporate Allocation Cost 100.00% 97.29% Total Employee Headcount ratio
Administrative Expenses – Others 100.00% 95.39% Gross Fixed Asset ratio
Administrative Expenses – Collection Charges on
100.00% 100.00% Aeronautical
UDF
Insurance 100.00% 95.39% Gross Fixed Asset ratio
Repairs and Maintenance 100.00% 95.39% Gross Fixed Asset ratio
Other Operating expenses 100.00% 90.00% Terminal Building ratio
Independent Engineer Fee 100.00% 100.00% Aeronautical
Amortization of Runway recarpeting expenses 100.00% 100.00% Aeronautical
Fuel Operating Expenses 100.00% 100.00% Aeronautical
Cargo Operating Expenses 100.00% 100.00% Aeronautical
One time escalation claimed by GIAL
10.2.21 One-time escalation claimed by GIAL for various Operating expenses in FY 2025-26 have been
analyzed by the Authority. In this regard, the Authority considers Capitalization schedule proposed by
it (refer Table 110), in which commissioning of NITB has been considered during the Third Control
Period. Accordingly, the Authority proposes to consider proportionate increase for determining the one-
time escalation in the expenses for the current Control Period. Further, the Authority notes that the
escalation in operating expenses such as Utilities, Housekeeping and Upkeep expenses, Horticulture
expenses and Outsourced manpower / Hiring expenses may not be directly proportional to the increase
in the Terminal Building area due to technological innovation, advancements, and economies of scale.
Hence the Authority proposes to consider 2/3rd (i.e. 66.67%) of the increase in total terminal area (2/3*
621%) for one-time escalation of expenses related to Terminal Building. The details of escalation rates
submitted by GIAL and that proposed by the Authority for are shown in the table below:
Table 134: One-time escalation claimed by GIAL and Increase % Proposed by the Authority
Increase % proposed by the
Type of Expense Increase % Claimed by GIAL
Authority
Electricity Charges FY 2025-26: One-time 414%*
FY2025-26: 621 % (NITB commissioning)
(Terminal Area increase)
Rates & taxes FY 2025-26: One-time 414%*
FY2025-26: 621 % (NITB commissioning)
(Terminal Area increase)
Consultation Paper No. 01/2024-25 Page 177 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Increase % proposed by the
Type of Expense Increase % Claimed by GIAL
Authority
IT Expenses FY 2025-26: One-time 100%
FY2025-26: 100 % (NITB commissioning)
(Terminal Area increase)
Security expenses FY 2025-26: One-time 50%
FY2025-26: 50 % (NITB commissioning)
(Terminal Area increase)
Other Operating Expenses FY 2025-26: One-time 414%*
FY2025-26: 621 % (NITB commissioning)
(Terminal Area increase)
*Refer Table 127 (2/3* 621%)
The Authority has evaluated the submission made by GIAL relating to various operational expenses and
their growth over the Third Control Period and the analysis of such expenses is elaborated below:
Manpower Expenses
10.2.22 The Authority, on its examination of GIAL’s submission towards Manpower expenses, observes the
following:
i. Manpower Expenses of AAI employees - GIAL has projected the expense towards specified
number of AAI employees across all the five (5) tariff years in the Third Control Period as per
clause 6.5.1 of the Concession Agreement entered into between AAI and GIAL, the extract of
which has already been provided under paragraph 10.2.4.
a. GIAL has claimed Manpower Expenses for ‘Select employees’ till the end of Deemed
Deputation Period (refer table below for the department wise list) and also ‘Deficit Employee
Cost’ for 104 employees (calculated at 60% of ‘Select employee’ number as stated in Clause
6.5.10 of the Concession Agreement) for the remaining portion of the Third Control Period.
GIAL has also projected a growth rate of 10% year-on-year towards Manpower Expenses of
AAI employees.
The cadre wise details of AAI employee have been provided as part of Schedule S of the signed
Concession Agreement. Further, the department wise detail has been provided by GIAL at section
13.2.15 as part of their MYTP submission.
Table 135: Department-wise Select employees of AAI deputed to LGBIA as submitted by GIAL
No. of Employees as on No. of Employees as on March
Department
March 31, 2023 31, 2024
Commercial 1 1
Engineering & Maintenance 43 41
Finance 6 6
Fire Services 51 51
Human Resource and Admin 19 18
Security 1 1
Terminal Management 12 12
Grand Total 133 130
b. The Authority observes that the Manpower Expense of AAI employees are accounted by
GIAL, based on the invoice raised by AAI for the ‘Select Employees’ deputed at LGBIA, on
a monthly basis. GIAL has arrived at the average annual employee cost of ₹ 24.09 lacs per
annum. However, basis the actual expenses submitted by GIAL vide email dated April 22,
2024, the average annual employee cost has been calculated as ₹ 21.77 lacs in FY24, which
the Authority proposes to consider.
Consultation Paper No. 01/2024-25 Page 178 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
c. The Authority also observes that the Manpower Expenses of AAI employees were considered as
100% Aeronautical expenses by GIAL.
d. The Authority proposes to consider the Manpower Expenses – AAI employees up to ‘Deemed
Deputation Period’ and after the expiry (October 2024) of such period relating to ‘Deficit
Employee cost’ according to the explanation provided in the relevant Clauses of the
Concession Agreement for such expenses and accordingly, treat the same which has been
explained in paragraph 10.2.5 and 10.2.6
e. The Authority observes that GIAL has submitted vide e-mails dated April 2, 2024 and April
22, 2024, that they have incurred actual Total Manpower expenses of AAI employees
amounting to ₹ 27.64 crores for the FY 2022-23 and ₹ 28.30 crores in FY2023-24 respectively.
In this respect, the Authority notes that GIAL has considered the same as 100% Aeronautical
which the authority proposes to re-allocate based on the prescribed allocation ratio of 99.25%
(FY23) and 99.06% (FY 24 and FY25) (refer Table 140) which works out to ₹ 27.43 crores for
the FY 2022-23 and ₹ 28.03 crores for FY 2023-24. Further, the Authority proposes to consider
the average annual employee cost as ₹ 21.77 lacs per annum basis the actual expenses incurred
in FY24 as the base to forecast salaries for the remaining three tariff years, i.e., FY 2024-25 to
FY 2026-27.
f. Further, the Authority proposes to revise the 10% Y-o-Y increase in Payroll costs claimed by
GIAL to 6% for the remaining three (03) tariff years of the Third Control Period, as approved
by the Authority for other similar airports.
g. The Authority further observes that post completion of Deemed Deputation period, GIAL
needs to bear the costs of Deficit Employees (60% of Select Employees) and shall be
considered for pass-through in the determination of the Aeronautical Charges and the same has
been appropriately accommodated.
h. The details of Manpower expenses – AAI employees claimed by GIAL and proposed by the
Authority are summarized in the table below:
Table 136: Manpower cost of AAI employees claimed by GIAL and proposed by the Authority
Particulars Unit FY’23 FY’24 FY’25 FY’26 FY’27 Total
As per GIAL
AAI – employee’s salary % 10 10 10 10 10
growth rate claimed by GIAL
AAI – employees Manpower ₹ in 27.64 32.52 31.85 30.26 33.28 155.55
Cost claimed by GIAL crores
As per the Authority
AAI – employee’s salary % - - 6 6 6
growth rate proposed by the
Authority
AAI – Employees Manpower ₹ in 27.64* 28.30** 15.78# + 25.39 26.91
Cost derived by the Authority crores 11.35^
Allocation ratio proposed by % 99.25 99.06 99.06# / 100 100
the Authority (Refer Table 100^
140)
AAI – Aero Employees ₹ in 27.43 28.03 26.98 25.39 26.91 134.75
Manpower Cost proposed by crores
the Authority
*as per actuals submitted by GIAL for FY 2022-23
**as per actuals submitted by GIAL for FY 2023-24
#for Deemed Deputation Period
^for Deficit Period
Consultation Paper No. 01/2024-25 Page 179 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
ii. Manpower Expenses of Employees of GIAL
GIAL has submitted the following regarding projected salary cost per employee per annum and
increase in the total employee headcount:
a. Salary cost projected per employee per annum - GIAL has submitted a weighted average
employee cost of ₹ 14.00 lacs per annum (₹ 20.00 lacs per annum for executives and ₹ 5.00 lakhs
per annum for non-executives) in FY 2023-24 and also projected an increase of 10% year-on-
year (Y-o-Y) for each tariff year in the Third Control Period. As per the submission of GIAL,
the average employee cost of ₹ 14.00 lacs per annum has been derived after considering the
salary cost of projected recruitments for Senior-level positions like Chief Airport Officer, Chief
Security Officer and Heads of Departments for Procurement, Legal, Customer Care, Experts for
Quality, Corporate Communications and also the salary cost of other-level positions in various
departments like Airside management, Security, Terminal Operations, Engineering &
Maintenance, HR, Finance, etc.
GIAL has further submitted that as per Clause 6.5.3. of the Concession Agreement, the Senior
Personnel of AAI deputed to LGBIA shall remain only for a period not exceeding 3 months from
the COD and shall be transferred on expiry of three months.
The Authority examined Clause 6.5.3 of the Concession Agreement which states that:
“The senior management staff of the Authority of the rank of deputy general manager and above
(“Senior Personnel”) shall remain deputed at the Airport for a period not exceeding 3
(three) months from the COD.
(i) On the expiry of such 3 (three) month period, the Senior Personnel shall be transferred
out of the Airport and redeployed by the Authority.
(ii) It is clarified that the Concessionaire shall not be liable to bear any costs in respect of
the Senior Personnel, which costs shall be borne entirely by the Authority.”
The Authority finds the average employee cost submitted by GIAL to be reasonable and proposes
to consider the same. Further, the Authority proposes to rationalise the growth rate by considering
only 6% Y-o-Y for all the remaining three (3) FYs, starting from FY 2024-25 in line with what
has been considered for Manpower Expenses of AAI employees.
The Authority observes that GIAL has submitted vide e-mail dated April 2, 2024 that they
have incurred actual Total Manpower Expenses of GIAL’s employees amounting to ₹ 9.57
crores for the FY 2022-23. Further, GIAL vide email dated April 22, 2024 has submitted the
actual expenses as ₹ 11.50 crores for FY2023-24. The Aeronautical portion of such expenses
works out to ₹ 9.23 crores for the FY 2022-23 and ₹ 10.70 crores, which the Authority, proposes
to consider for FY 2022-23 and FY 2023-24 respectively.
b. Increase in Employee Headcount – GIAL has projected an increase in Employee Headcount
from 85 as at the end March 2023 to 375 as at the end the Third Control period. The table below
depicts increase in the total Headcount Y-o-Y with department wise break-up of employees.
GIAL in its submission has considered the allocation as 100% Aeronautical.
Consultation Paper No. 01/2024-25 Page 180 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Table 137: Dept. wise Head Count of Employees as per GIAL’s submission for the Third Control Period
Departments FY23 FY24 FY25 FY26 FY27 Justification
(Nos) (Nos) (Nos) (Nos) (Nos)
Chief Airport Office 2 3 4 4 5 As per Concession Agreement, Clause 6.5.3. AAI employees
(CAO office) with designation over DGM and above have been transferred
out by AAI and they are not associated with the Airport after
3 months from CoD. Accordingly, Airport Director and all
HoDs have been transferred out and are not working at
Guwahati Airport.
CAO stands for Chief Airport Officer. He is responsible for
overall operations and management of the Airport.
Department is akin to erstwhile Office of Airport Director.
He is supported by relevant staff for analysis, reviews, KPI
management, regular review, action taken follow-ups,
stakeholder management, etc. Composition includes CAO, 1
EA, 1 ES, & 1 ORAT Manager.
Techno Commercial 6 8 9 10 11 AAI do not have any local purchase department at site. All
(Procurement) the procurement at AAI is done centrally through tendering
process.
Techno commercial function is responsible for procurement
of various requirement of user department, management of
contract, RFP issue, onboarding of vendor, etc.
Composition includes 1 HoD, 5 Support staff
Corporate 1 2 2 2 3 As per Clause 18.1.1 (q), GIAL is requirement to have public
communication relation officer who will interface with various stakeholders.
GIAL has assumed to place one position to fulfill the
mandated requirement along with 1 support staff
Corporate Affairs 1 1 2 2 2 Position required to interact with various state government,
local municipalities, utility boards, local police, land
department etc. on day-to-day basis. Composition is 1 lead &
1 support staff
Security 6 8 17 17 20 Currently there was one person deputed for carrying out
Security function at the Airport. At present AAI was only
performing pass section function with his support. However
there are various activities which need to be performed by
GIAL like CISF Documentation, Airport Security Program,
Kerb Side Management, Traffic Management, Airport
Operator Security Control Room, Tout Management,
Security System Maintenance, Encroachment outside and
perimeter area, Intelligence and Vigilance Gathering, Avsec
Training and Compliances, Landside Operations, BCAS
Compliance requirements.
GIAL will be carrying out functions with a combination of
on roll and outsourced employees.
Sovereign agencies and security set up of the airport
operator have clearly defined mandates. NACASP 2018
vide Para4.2.2(xxii) stipulates that the Airport Operator is
responsible for implementation of security controls at the
airports through the CSO. The Asset CSO is bestowed with
all the powers to implement security controls at the airport
level and overall coordination with other agencies at the
airport(Para5.2.1(ii) of NCASP refers).
GIAL has assumed 20 employees on rolls is a composition
of 1 CSO, 6 Pass Section, 1 Avsec Audit and Compliances,
7 Loss Prevention and Automation, 5 landside operations
and others.
Other operations like Kerb side, Tout Management, Traffic
Management, Encroachment Prevention, Security System
Maintenance etc. are expected to be outsourced.
Consultation Paper No. 01/2024-25 Page 181 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Departments FY23 FY24 FY25 FY26 FY27 Justification
(Nos) (Nos) (Nos) (Nos) (Nos)
Legal 1 1 2 2 2 AAI does not have legal positions at the Airport.
Composition includes 1 HoD and 1 department supporting
staff.
Safety - 1 2 2 2 As per Concession Agreement clause 18.15.4, GIAL is
expected to create Airport Safety Management Unit
(ASMU) and designate one of its officers to be in-charge of
the ASMU.
Composition includes 1 Aviation Safety Expert and 2
support staff & OHS staff.
Quality 1 1 2 2 2 Under clause 23.1 of concession Agreement, GIAL is
obligated to monitor and measure quality of service on the
parameters prescribed in the Concession Agreement.
Further as per Concession Agreement, GIAL is expected to
maintain relevant ISO certification and other quality
certifications for all the facilities controlled and managed
by GIAL.
Composition includes 1 Quality Expert 2 associates
Information 2 5 8 9 10 AAI does not have Information technology team to support
Technology the IT functioning of the Airport. IT is a backbone of the
Aviation, and all the critical systems need to be running
with zero downtime. Critical systems includes AODB,
FIDS, PDAs, SAP, Business Analytics, Integration with
ATC, VGDS, Radio Sets, Desktops, Laptops, Billing
Software's, Document Management System, Access Control
System etc.
Composition includes 1 HoD, 9 Support staff.
Airside Management 16 23 30 35 40 As per Clause 18.1.1 (d), (f) and (g), GIAL is responsible to
maintain and operate Airside including Runway, Taxiways,
Apron, Approach Areas etc. Also, it is mentioned in the
CNS-ATM Agreement about the airside obligations to be
performed by GIAL.
GIAL is responsible to establish Apron Management
Service, Airside safety, aerodrome safeguarding and
aeronautical information services.
Previously some of these services were performed by ANS
team of AAI and some of the services were not done at all.
Post CoD all these functions are to be performed by GIAL.
Further these activities are strictly regulated by DGCA as
part of legal framework of Aerodrome Operating License
under CAR section 4, series F part 1.
Lastly as a part of capex expansion plan there are new
Airside facilities need to be made like Part Parallel Taxi
Track, Second Part Parallel Taxi Track, Expansion of
Apron 2, Extension of Runway, New Isolation Bay, etc.
There will be requirement for additional manpower to
operate these facilities.
The composition includes In Charge Airside, Duty
Managers, Duty Officers, Airside Executive, Airside
Ground Maintenance, Aerodrome Licensing, Aerodrome
Safeguarding, Wildlife Hazard Management
Regulatory - - 1 1 2 New position to support in regulatory filing with AERA.
Terminal and 22 23 44 44 46 NITB project is ongoing and is supposed to be commissioned
Operation by Q4 FY 24-25. It is expected that there will be requirement
for additional duty managers, duty officers, facilities,
Terminal E&M, ORAT team, horticulture, ESG staff to cater
to the increased area demand.
Non-Aero Commercial 3 4 7 7 7 GIAL is expected to deploy various strategies/innovations to
monitor the Non-Aeronautical Income and development of
Consultation Paper No. 01/2024-25 Page 182 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Departments FY23 FY24 FY25 FY26 FY27 Justification
(Nos) (Nos) (Nos) (Nos) (Nos)
city side area. There is likelihood of increase in Manpower
over time.
Human Resources and 5 5 6 6 6 GIAL is expected to consolidate and automate various
Admin positions/functions, and will employee limited staff which
will be comprising of HoD, HR Operations Talent
Acquisition 2 person, Learning & OD, Admin, ER &
Compliances
Finance 5 5 8 8 8 Composition includes 1 HoD, and support staff for various
functions under finance and accounts.
Engineering & 3 13 30 30 30 Currently AAI has approx. 10-15 people each in Civil,
Maintenance Technical and Engineering sections.
GIAL is expected to outsource some of the non-core
activities. Second there will be increase in Terminal Area by
5x in NITB. Increase in Airside Facilities, increase in
landside facilities, Utilities etc, there will be requirement of
more manpower in Engineering and Maintenance
department to cater to these increased facilities.
Considering all the above factor, GIAL is expected to
consolidate the function and will have only 30 people on-
rolls.
Airline Marketing - 1 2 2 2 Specialized marketing personnels required to bring in
additional airlines with increase in the capacity of the airport.
Aviation Rescue and 8 8 84 84 88 As per AAI manual 2015, and TRA done there is requirement
Fire Fighting (ARFF) of 92 Fire People (23 nos x 4 shifts) for Category 8 Airport
for 24/7 shift operation, emergency response.
TRA attached (Please refer Annexure R of MYTP for TRA).
Environment & 1 1 2 2 2 As per ICAO/DGCA/MoEF guidelines to operate/maintain
Sustainability Eco Friendly and sustainable Airport, manpower is required
for meeting the regulatory compliances. ACI IV plus
accreditation and target of Carbon neutral asset is to be
achieved for addition executive is required for maintaining
all the records in addition to the lead position.
Horticulture 1 1 3 3 3 To maintain world class Passenger Experience and to
maintain eco-friendly Airport. To increase green cover at the
airport as per statutory guidelines.
Land department 1 1 1 1 1 Personnel will be responsible for land matters
ILHBS Screeners - - 59 77 83 New NITB New online baggage screening will be
introduced. So certified screeners will be required
Total Manpower 85 115 325 350 375
Requirement
The Authority does not agree with GIAL’s contention that all employees cost is Aeronautical in nature.
The Authority has referred the Study on the Efficient Operation and Maintenance Expenses of LGBIA,
and accordingly reallocated employees between aeronautical, common, and non-aeronautical.
The Authority observes that GIAL has estimated this increase in number of employees mainly towards
functions relating to Security, Firefighting, Airside management, Terminal operations, Engineering
and Maintenance and ILHBS Screeners, considering the commissioning of NITB in FY 2025-26 and
that the deemed deputation period of the Select Employees deputed by AAI expires in the FY 2024-
25 (October 2024).
In this background, the Authority examined the Aeronautical Employee Head Count of LGBIA for
the period from FY 2016-17 to FY 2019-20 (Pre-COVID year) and notes that the 4-year average
employee headcount is 149 and the same is given in below table:
Consultation Paper No. 01/2024-25 Page 183 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Table 138: Headcount of Aeronautical employees of LGBIA for the Period from FY’17 to FY’20
4 – Year
Particulars FY’17 FY’18 FY’19 FY’20
Average
Employee Headcount * 139 145 164 149 149
* Refer Table 19 of paragraph 4.4.3.e. of Study on Efficient Operation and Maintenance Expenses for LGBIA
The Authority further observes that the Passenger traffic and ATM during the Third Control Period
for LGBIA (refer Table 71) has crossed Pre-COVID level during FY 2023-24. The same has been
presented in the following table:
Table 139: Estimated Passenger and ATM traffic of LGBIA
FY’20
Particulars (Pre- FY’23 FY’24 FY’25 FY’26 FY’27
COVID)
Passenger Traffic (in lacs) 54.57 50.51 59.58 66.64 75.44 90.94
ATM Traffic (In ‘000s) 45.54 45.91 46.15 60.53 68.05 82.11
However, the Authority also considers the following pertinent factors such as:
NITB is expected to be commissioned in last quarter of FY24-25 as per GIAL submission.
There are existing employees of AAI i.e., ‘Select Employees’ deputed to LGBIA and
The previous airport operator, namely, AAI had been maintaining the prescribed ASQ rating of
LGBIA with the aforementioned employee headcount (refer Table 164).
Considering the growth projected in Passenger traffic and ATM and the current scale of operations,
the Authority is of the view that, the Aeronautical Employee Head Count projected by GIAL which is
at 375 towards the end of the Third Control Period, is not justified and the same needs to be
rationalized. Further the Authority noted the GIAL headcount shared vide email by GIAL dated April
2, 2024 and compared it with the projections submitted during MYTP submission. Accordingly, the
Authority has rationalized the headcount projections.
Based on the above, the Authority has analyzed the Employee Headcount projected vis-à-vis the
functions of each department mentioned in Table 137. The Authority proposes to consider actual
headcount for FY2022-23 and FY 2023-24 as submitted by GIAL.
Further, the Authority proposes the following revision in Aeronautical Employee Headcount projected
by AO for the remaining three (3) tariff years of Third Control Period:
(i) Security department: The Authority observes that certain security and safety activities may be
suitably outsourced by GIAL, barring specific activities such as coordination with CISF, BCAS
compliance etc. The Authority thus proposes to consider only 50% of the Employee Headcount
projected by GIAL in the 3rd tariff year (FY 2024-25) onwards.
(ii) Airside Management: The Authority observes that the headcount projected by GIAL for all the
tariff years is not justified considering the projected traffic levels at the airport. The Authority
also observes that ground handling activities at the airport have been outsourced. Based on the
above factors, the Authority proposes to consider twenty five (25), thirty (30), and thirty five (35)
employees in the last three tariff years of the Control Period as against 30 / 35 / 40 employees
respectively, claimed by GIAL.
(iii) Terminal Operations: The Authority observes that the number of Employee Headcount
projected by GIAL is not justifiable as there are existing employees of AAI (i.e., Select employees
deputed to LGBIA) at the Airport till the deemed deputation period. Hence, the Authority has
Consultation Paper No. 01/2024-25 Page 184 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
rationalized the manpower for Terminal Operations for the FY2024-25 from 44 employees to 35
employees. The Authority further observes that since NITB shall be commissioned by FY2025-
26, as per the CAPEX plan proposed by the Authority for Third Control Period, the manpower
may be increased in a staggered manner. The Authority proposes to consider forty (40) employees
in FY2025-26 as against 44 employees claimed by GIAL, and forty six (46) employees in
FY2026-27 as proposed by GIAL.
(iv) Engineering & Maintenance Department: The Authority observes that there are existing
employees of AAI (i.e., ‘Select Employees’ deputed to LGBIA) at the Airport during the deemed
deputation and hence the Authority proposes to consider 75% of the Aeronautical Employee
Headcount of Engineering & Maintenance department, projected by GIAL, for the third tariff
year of the Third Control Period. For the remaining two tariff years of TCP, the Authority
proposes to consider the number of employees as submitted by GIAL as the Deemed Deputation
Period will end in FY 2024-25.
(v) Aircraft Rescue and Fire Fighting (ARFF): The Authority observes that the employee
headcount projected by the AO is not justified, with the fact that the same services are being
delivered by existing employees of the AAI (i.e., Select employees to LGBIA) at the airport, at a
lower manpower strength. The Authority thus proposes to rationalize the manpower in this
department for FY2024-25 on the basis of historical manpower deployment. For next two tariff
years, manpower has been increased in a staggered manner. Based on the above factors, the
Authority proposes to consider sixty (60), seventy (70), and eighty (80) employees in the last
three years of the Control Period as against 84 / 84 / 88 employees respectively, claimed by GIAL.
(vi) Inline Hold Baggage Screening System (ILHBS): GIAL had proposed screeners with effect
from FY2024-25 considering that NITB will be commissioned in FY2024-25. However, the
Authority has proposed commissioning of NITB in FY2025-26. ILHBS will be operationalized
along with the commissioning of NITB. Further, the Authority has rationalized the number of
screeners and proposes to consider an headcount of fifty (50) and sixty (60) employees in FY
2025-26 and FY 2026-27 repsectively.
Based on the above factors, the Aeronautical Employee Headcount proposed to be considered by the
Authority for the Third Control Period is shown in the table below:
Table 140: Employee Head Count of GIAL and revised EHCR proposed by the Authority for the Third
Control Period
GIAL The Authority’s
Particulars FY’23 FY’24 FY’25 FY’26 FY’27
Classification Classification
Aeronautical Employee Head 85 115 325 350 375
count claimed by GIAL as per
MYTP
Employee Headcount proposed by the Authority
Chief Airport Office (CAO Aeronautical 2 2 4 4 5
Aeronautical
office)
Techno Commercial Aeronautical 3 4 9 10 11
Aeronautical
(Procurement)
Corporate communication Aeronautical Aeronautical 1 1 2 2 3
Corporate Affairs Aeronautical Aeronautical 4 3 2 2 2
Security Aeronautical Aeronautical 6 7 9 9 10
Legal Aeronautical Aeronautical 1 1 2 2 2
Safety Aeronautical Aeronautical - 1 2 2 2
Quality Aeronautical Aeronautical - 2 2 2
Information Technology Aeronautical Aeronautical 2 3 8 9 10
Consultation Paper No. 01/2024-25 Page 185 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
GIAL The Authority’s
Particulars FY’23 FY’24 FY’25 FY’26 FY’27
Classification Classification
Airside Management Aeronautical Aeronautical 16 19 25 30 35
Regulatory Aeronautical Aeronautical 1 1 2
Terminal and Operation Aeronautical Aeronautical 22 20 35 40 46
Non-Aero Commercial Aeronautical Non-Aeronautical 3 5 7 7 7
Human Resources and Admin Aeronautical Common 5 5 6 6 6
Finance Aeronautical Common 6 6 8 8 8
Engineering & Maintenance Aeronautical Aeronautical 3 12 23 30 30
Airline Marketing Aeronautical Aeronautical 2 2 2
Aviation Rescue and Fire Aeronautical 8 7 60 70 80
Aeronautical
Fighting (ARFF)
Environment & Sustainability Aeronautical Aeronautical 1 1 2 2 2
Horticulture Aeronautical Aeronautical 1 1 3 3 3
Land department Aeronautical Non-Aeronautical 1 1 1 1
ILHBS Screeners Aeronautical Aeronautical 50 60
Air Cargo Aeronautical Aeronautical 1 1
Total Employee Head Count of GIAL rationalized by the Authority 85 100 213 292 329
Direct Aeronautical Employees of GIAL 71 83 191 270 307
Direct Non-Aeronautical Employees of GIAL 3 6 8 8 8
Common Employees of GIAL 11 11 14 14 14
Total Aeronautical Employees of GIAL 82 93 204 284 321
Total Non-Aeronautical Employees of GIAL 3 7 9 8 8
Revised Employee Headcount ratio of GIAL derived by the Authority 96.47% 93.00% 95.77% 97.26% 97.57%
5-yr average of Revised EHCR of GIAL 96.01%
Total AAI Employees 133 130 130 - -
Direct Aeronautical Employees of AAI 107 105 105 - -
Direct Non-Aeronautical Employees of AAI 1 1 1 - -
Common Employees of AAI 25 24 24 - -
Total Aeronautical Employees of AAI 132 129 129 - -
Total Non-Aeronautical Employees of AAI 1 1 1 - -
Revised Employee Headcount ratio of AAI derived by the Authority 99.25% 99.06% 99.06% - -
Total Aeronautical Employees of AAI and GIAL 214 222 333 284 321
Total Non-Aeronautical Employees of AAI and GIAL 4 8 10 8 8
Total Employee Headcount (i.e., both AAI and GIAL employees) derived 218 230 343 292 329
by the Authority
Revised Employee Headcount ratio of total AAI and GIAL derived by the 98.17% 96.43% 97.02% 97.26% 97.57%
Authority
5-year Average of Revised Total Employee Headcount Ratio (both 97.29%
AAI and GIAL employees) derived by the Authority
*till Deputation Period (October 2024)
The employee cost proposed by the Authority for GIAL’s own employees, based on the revised
aeronautical employee headcount is shown below:
Table 141: Manpower cost of Aero employees proposed by the Authority for the Third Control Period
Particulars Unit FY’23 FY’24 FY’25 FY’26 FY’27 Total
As per GIAL
Employee Headcount claimed No. 85 115 325 350 375
by GIAL
Consultation Paper No. 01/2024-25 Page 186 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Particulars Unit FY’23 FY’24 FY’25 FY’26 FY’27 Total
Salary Growth % claimed by % 10% 10% 10% 10% 10%
GIAL
Manpower Cost of GIAL’s ₹ in 9.57 14.38 28.52 44.92 53.07 150.46
employees claimed by GIAL crores
As per the Authority
Employee Head count proposed No. 85* 100** 213 292 329
by the Authority
Salary Growth % proposed by % - - 6% 6% 6%
the Authority
GIAL – Employees Manpower ₹ in 9.57* 11.50** 19.84 31.21 40.68
Cost derived by the Authority crores
Allocation ratio proposed by % 96.47% 93.00% 95.77% 97.26% 97.57%
the Authority
Aero Manpower Cost of ₹ in 9.23 10.70 19.00 30.35 39.69 108.97
GIAL proposed by the crores
Authority
*as per actuals submitted by GIAL for FY 2022-23
**as per actuals submitted by GIAL for FY 2023-24
Utility Expenses
10.2.23 The Authority examined the expenses towards Utilities and noted the following:
i. Power expenses: The Authority observes that GIAL in its submission has considered the expenses
towards Utilities after netting off the recoveries to be made from the Concessionaires for Non-
aeronautical activities. The net utilities expenses thus arrived is considered as 100% Aeronautical.
• The Authority observes that GIAL has assumed 16% of the total electricity cost as recoveries to be
made from the Concessionaires. The Authority further observes that the power recovery percentage is
significantly lower than that of comparable airports and proposes that the non-aeronautical operations
should increase the power recovery from the Concessionaires, in a gradual manner. Accordingly, the
Authority proposes that GIAL shall constitute a Committee to verify the bills relating to Power expenses
and submit a report on the same to the Authority as part of Stakeholder comments / feedback. In case
such report is not submitted by GIAL, the Authority proposes to consider power recoveries at a notional
rate while issuing the tariff order of the Third Control Period.
• The Authority observes that the actual Electricity costs incurred by GIAL for FY 2022-23 of ₹ 6.70
crores (after recovery) and proposes to consider the actual expenses of FY 2022-23. Further, GIAL
has submitted the actual expenses as ₹ 9.20 crores (after recovery) for FY 2023-24, which seems to
be on higher side and thus suitable justification was sought for the same from the AO. GIAL vide email
dated April 15, 2024 stated that, the base rate for electricity which is charged as energy charges in
monthly bill, was increased from ₹ 7.70 per unit to ₹ 8.10 per unit. Further, APDCL (Assam Power
Distribution Company Limited) had increased FPPCA ((Fuel and Power Purchase Cost Adjustment) to
₹ 1.29 per unit in FY24 from ₹ 0.30 per unit in FY23. The Authority in view of the aforementioned
response of GIAL proposes to consider the actual expenses for FY2023-24.
• GIAL has proposed to increase the billable units by 621% in FY 2024-25 on account of increase in
terminal area. The Authority as part of its review notes that for other similar airports, it had allowed the
increase claimed by the respective AO which was in proportion to the increase in the area of the
Terminal Building. Based on the same, the Authority proposes to consider as per the capitalization
schedule an additional increase of 414% in billable units only for FY 2024-25 (refer growth rates
Consultation Paper No. 01/2024-25 Page 187 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
mentioned in Table 134).
• The Authority observes that GIAL, has claimed an inflationary increase of 5% on the per unit rate.
The Authority proposes Y-o-Y increase of per unit rate towards inflationary effect as per Table 126.
The details of Utility expenses claimed by GIAL and allowed the Authority are summarized in the table
below:
Table 142: Utility expenses claimed by GIAL and proposed by the Authority for the Third Control Period
(₹ crores)
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
As per GIAL
Total Utility Expenses 6.70 8.24 8.65 65.49 68.76 157.85
As per the Authority
Total Utility Expenses 6.70* 9.20** 9.49 50.54 52.41 128.33
*as per actuals submitted by GIAL for FY 2022-23
**as per actuals submitted by GIAL for FY2023-24
The increase in Utility Expenses in FY26 is due to increase in terminal area (commissioning of NITB) and inflation effect.
IT expenses, Rates & Taxes and Security expenses
10.2.24 GIAL as per the concession agreement is required to upgrade the existing IT capacity
infrastructure. GIAL has based its expense projections on the basis of proportionate increase in
GIAL’s own employee headcount. Further the Authority notes that GIAL has treated the cost as
100% Aeronautical. In respect of the Y-o-Y growth claimed by GIAL, the Authority proposes to
revise the same as per inflation rate proposed in Table 83 above and also reallocate the expense
based on the Terminal Building ratio of 90% Aeronautical (refer para 10.2.9).
i. The Authority observes that the actual expenses incurred by GIAL on IT expenses for FY 2022-23
and FY2023-24 are ₹ 2.50 crores and ₹ 3.40 crores respectively, and proposes to consider the same.
Further, the Authority proposes to consider actual IT expenses for FY 2023-24 as base for future
projections Further, the Authority shall consider a one-time increase of 100% on account of
increase in Terminal Area. The Authority further proposes to apply Y-O-Y increase towards
inflation for the remaining three (3) tariff years on the derived expenses of FY 2023-24 (refer
growth rates mentioned in Table 157).
Table 143: IT expense of GIAL as proposed by the Authority for the Third Control Period
Particulars Units FY’23 FY’24 FY’25 FY’26 FY’27 Total
As per GIAL
IT expenses claimed by ₹ in 2.50 7.00 19.78 41.09 44.02 114.39
GIAL crores
As per the Authority
IT expense proposed by the ₹ in 2.50* 3.40** 3.51 7.14 7.40 23.95
Authority crores
Allocation Ratio proposed by % 90% 90% 90% 90% 90%
the Authority
Aero IT expense proposed ₹ in 2.25 3.06 3.15 6.43 6.66 21.56
by the Authority crores
*as per actuals submitted by GIAL for FY 2022-23
**as per actuals submitted by GIAL for FY 2023-24
10.2.25 With respect to Rates and Taxes, GIAL has assumed a 5% y-o-y increase on account of inflation and a
Consultation Paper No. 01/2024-25 Page 188 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
one-time increase of 621% on account of increase in terminal area. Further the Authority observes
that the AO has treated the cost as 100% Aeronautical. The Authority proposes to reallocate the
expense based on the Gross Fixed Asset ratio (95.39%).
i. The Authority has noted the actual expenses of ₹ 0.31 crores incurred by GIAL on Rates and Taxes
for FY 2022-23 and proposes to consider the same. Further, GIAL has submitted the actual
expenses as ₹ 0.10 crores for FY2023-24. The Authority proposes to consider ₹ 0.10 crores towards
Rates and Taxes for FY 2023-24 and use the same as base for future projections. The Authority
notes that GIAL, has claimed 621% increase in FY 2024-25 on account of increase in Terminal
area. The Authority finds the increase to be unreasonable and proposes an increase of 414% as per
the justification provided in para 10.2.21. The Authority further proposes to apply Y-O-Y increase
towards inflation for the next three (3) tariff years on the derived expenses of FY 2023-24 (refer
growth rates mentioned in Table 157).
Table 144: Rates and Taxes of GIAL as proposed by the Authority for the Third Control Period
Particulars Units FY’23 FY’24 FY’25 FY’26 FY’27 Total
As per GIAL
Rates and Taxes claimed by ₹ in 0.31 0.75 0.79 5.71 6.00 13.56
GIAL crores
As per the Authority
Rates & Taxes expense ₹ in 0.31* 0.10** 0.10 0.53 0.55 1.60
considered by the Authority crores
Allocation Ratio proposed by % 95.39% 95.39% 95.39% 95.39% 95.39%
the Authority
Aero Rates & Taxes proposed ₹ in 0.30 0.10 0.10 0.51 0.53 1.53
by the Authority crores
*as per actuals submitted by GIAL for FY 2022-23
**as per actuals submitted by GIAL for FY 2023-24
10.2.26 As per GIAL’s submission expenses related to security includes outsourced manpower, security
guards, security operation maintenance, surveillance vehicles, access controls and expenses related
to other automation systems. GIAL has based their security cost increase in line with the forecasted
growth in passenger traffic. In addition, GIAL has considered a one-time increase of 50% in
expense on account of commissioning of NITB leading to increase in the terminal area. Further the
Authority notes that GIAL has treated the cost as 100% Aeronautical. The Authority notes the dual
escalation in the expenses wherein GIAL has considered both increase in traffic and terminal area.
The Authority proposes to revise the Y-o-Y growth in security expenses, as per inflation rate
proposed in Table 126 and also reallocate the expense based on the Gross Fixed Asset ratio of
95.39% Aeronautical (refer para 10.2.11 ) in line with similar airports.
i. The Authority has noted the actual expenses on Security of ₹ 3.75 crores incurred by GIAL for FY
2022-23 and proposes to consider the same. Further, GIAL has submitted the actual expenses as ₹
6.00 crores for FY 2023-24. The Authority proposes to consider ₹ 6.00 crores towards Security
expenses for FY 2023-24 and use the same as base for future projections. The Authority notes that
GIAL, has claimed 50% increase in FY 2024-25 on account of increase in Terminal area, which
the Authority finds to be reasonable and justified. Hence, the Authority proposes to allow the same.
Consultation Paper No. 01/2024-25 Page 189 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Table 145: Security expense of GIAL as proposed by the Authority for the Third Control Period
Particulars Units FY’23 FY’24 FY’25 FY’26 FY’27 Total
As per GIAL
Security expense claimed by GIAL ₹ in 3.75 6.00 6.11 9.97 12.02 37.86
crores
As per the Authority
Security expense proposed by the ₹ in 3.75* 6.00** 6.19 9.51 9.86 35.30
Authority crores
Allocation Ratio proposed by the 95.39% 95.39% 95.39% 95.39% 95.39%
%
Authority
Aero Security expense proposed by ₹ in 3.58 5.72 5.90 9.07 9.41 33.68
the Authority crores
*as per actuals submitted by GIAL for FY 2022-23
**as per actuals submitted by GIAL for FY 2023-24
Corporate Allocation Cost
10.2.27 GIAL has claimed Corporate Allocation Cost of ₹ 12.89 crores towards Corporate Support Services
received from the Holding Companies, namely, AEL and AAHL for the FY 2022-23 and has
considered the employee headcount growth of GIAL as basis for Y-o-Y escalation.
i. The Airport Operator (GIAL) had engaged an independent consultant, to conduct a study on Corporate
Cost allocation. The Authority has noted the following points submitted by GIAL in support of their
claim for Corporate cost allocation:
• AEL provides various strategic functions/activities like corporate finance, legal, central
procurement, green initiative, ESG, Information technology, human resource management,
etc., and also includes various leadership functions. AAHL through its corporate structure,
provides expertise and specialist domain knowledge in Airports Operation, Airside
Management, Master Planning, Designing, Airport Development, Airport Regulatory,
Hospitality, Customer management, Cargo Development and management, Airline Marketing,
Non-Aeronautical etc.
• AEL and AAHL incur costs at the corporate level to provide these services and support to
various Group Companies (including Airports) and Airport companies. The major composition
of these costs includes salaries and administrative costs. These costs (except shareholders
services and non-Aeronautical services) are recovered by AEL and AAHL through a pre-
determined, appropriate allocation method.
• Similar corporate cost allocation process is used by other private airport operators’ holding
entities, which provide corporate administration services to their respective Airport Operators,
and their costs are allocated based on suitable drivers. Similarly, AAI also allocates its Central
Head Quarters (CHQ) / Regional Head Quarters (RHQ) costs to various airports based on
appropriate cost drivers.
ii. The Authority observes that AEL on overall basis, extends support and guidance to various Group
Companies and AAHL provides expertise and specialist domain knowledge to the Airport Companies,
which are essential for the sustainable operations of the business. The major composition of the costs
of these services includes salaries and administrative costs that are recovered by AEL and AAHL
through an appropriate allocation method (refer para 10.2.14 ). Further, this process is consistent with
the approach followed by other PPP airports for allocation of Corporate costs to the Airports. Based on
the above factors, the Authority considers the apportionment of costs of AEL and AAHL to GIAL as
Consultation Paper No. 01/2024-25 Page 190 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
reasonable.
iii. The Authority notes that the actual expenses incurred by GIAL on Corporate Cost expenses for FY
2022-23 is ₹ 12.89 crores and its detailed break-up along with the basis of allocation as submitted by
GIAL is as follows:
Table 146: Actual Corporate Cost incurred with allocation basis submitted by GIAL for FY’23
(₹ crores)
Admin Salary
Particulars Department Allocation Key (Basis) Total
Cost Cost
AEL HR and Admin Ratio of Number of Employees of a SPV to 0.52 1.05 1.57
Total Adani Group Employees
Finance, Tax and Ratio of Debt raised for a SPV to total Debt 0.27 0.54 0.81
Internal Audit raised for Adani Group, Ratio of Turnover of
a SPV to Total Group Turnover and Ratio of
Full Time Equivalents (FTE) allocated to a
SPV to total FTEs
IT Ratio of Number of IT users in a SPV to total 0.35 0.70 1.05
Group users
Legal Ratio of Legal Budget of a SPV to Total 0.01 0.02 0.03
Legal Budget of all airports
CMD Office & Ratio of a SPV PBT to Group PBT and 0.58 1.17 1.75
Support Staff Airport budgeted expenditure to Total
budgeted expenditure
Total (A) 1.72 3.49 5.21
AAHL HR & Admin Ratio of Number of Employees of a SPV to 0.28 1.11 1.39
Total Adani Group Employees
Finance Ratio of Debt raised for a SPV to total Debt 0.17 0.67 0.84
raised for Airport Group
Operations (Airline Ratio of Per Pax Revenue of SPV to total Per 0.77 3.09 3.86
Marketing, Operation, Pax Revenue
Security, HSE,
Regulatory)
IT Ratio of Number of IT users in a SPV to total 0.09 0.34 0.43
IT users in all airports
Inhouse Legal Team Ratio of Legal Budget of a SPV to Total 0.03 0.12 0.15
Legal Budget of all airports
Cargo Development Ratio of Per Pax Revenue of a SPV to total 0.01 0.03 0.04
Per Pax Revenue of all airports
CEO Office Ratio of Per Pax Revenue of SPV to total Per 0.20 0.79 0.98
Pax Revenue
Total (B) 1.54 6.15 7.68
Total (A) + (B) 3.26 9.64 12.89
iv. Considering all the above, the Authority proposes to consider the actual expenses of ₹ 12.89 crores for
FY 2022-23.
v. However, the Authority observes that the aforementioned actual cost includes the costs of inhouse legal
team, which is in addition to the cost of employees of Legal department, already considered under the
manpower expenses of GIAL (refer Table 146 above) and is not justified. Hence, the Authority proposes
to exclude ₹ 0.15 crores from the Corporate Allocation cost submitted by GIAL and consider the
remaining amount of ₹ 12.74 crores for FY 2022-23.
vi. Further, GIAL has submitted the actual expenses as ₹ 11.80 crores for FY 2023-24. The Authority finds
the same to be reasonable and proposes to consider ₹ 11.80 crores towards Corporate Cost expenses for
FY 2023-24.
Consultation Paper No. 01/2024-25 Page 191 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
vii. GIAL has escalated expenses related to corporate allocation YoY basis growth in employee count. The
Authority observed that salary cost constitutes the major portion of the Corporate cost and hence,
proposed to rationalize the increase claimed by GIAL to 6% Y-o-Y across the last three (3) tariff years
of the Third Control Period which is in line with the increase proposed for manpower expenses of AAI
and GIAL.
viii. The Authority observed that GIAL has considered corporate cost allocation as 100% aeronautical
without any supporting basis for such allocation. In the absence of such basis and in line with the
methodology followed by the Authority for similar airports, the Authority proposes to reallocate the
expense basis the Total Employee Headcount ratio. Further, as the services provided by AAHL & AEL
are mainly in the nature of provided specialized resources and knowledge and also it benefits whole
airport ecosystem, the Authority is of the view that the cost needs to be allocated basis the Total
Employee Headcount ratio.
ix. The details of Corporate Allocation Expense claimed by GIAL and allowed by the Authority are
summarized in the table below:
Table 147: Corporate Cost Allocation expenses claimed by GIAL and Proposed by the Authority
Particulars Units FY’23 FY’24 FY’25 FY’26 FY’27 Total
As per GIAL
Corporate Allocation expense ₹ in 12.89 15.00 42.39 45.65 48.91 164.85
claimed by GIAL crores
As per the Authority
Corporate allocation cost ₹ in 12.74* 11.80** 12.51 13.26 14.05 64.36
considered by the Authority crores
Allocation Ratio proposed by the % 98.17% 96.43% 97.02% 97.26% 97.57%
Authority
Aero Corporate Cost expense ₹ in 12.51 11.38 12.14 12.90 13.71 62.63
proposed by the Authority crores
*as per actuals submitted by GIAL for FY 2022-23
**as per actuals submitted by GIAL for FY 2023-24
Administrative Expenses
10.2.28 GIAL has projected an inflationary increase of 5% Y-o-Y for Administrative Expenses (Others) towards
Professional & Consultancy, Sales & Marketing, Travelling & Communication, Printing & Stationery
etc. In addition, a 5% Y-o-Y increase is provisioned as Contingency. For expenses related to collection
charges on UDF, GIAL has escalated the same as per forecasted passenger growth.
• In respect of UDF Collection charges, the Authority has observed that the actual expenses incurred
by GIAL for FY 2022-23 and FY2023-24 are ₹ 0.98 crores and ₹ 1.45 crores respectively, and
proposes to consider the same. The Authority proposes to consider increase in Collection charges
for UDF in line with the growth in Passenger traffic proposed for the Third Control period for
LGBIA, as per Table 71. The Authority proposes to apply such rates for the next three (3) tariff
years on the actual expenses of FY 2023-24.
• In respect of Other Administrative charges, the Authority observes that the actual expenses
submitted by GIAL i.e., ₹ 13.56 crores includes recovery of electricity expenses amounting to ₹
1.33 crores. The Authority proposes to exclude such expenses which have been recovered by the
Airport Operator. Further, GIAL has submitted the actual expenses as ₹ 27.00 crores for FY2023-
24. The estimated expense value seemed to be on the higher side, and thus suitable justification was
Consultation Paper No. 01/2024-25 Page 192 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
sought for the same from GIAL. GIAL vide email dated April 15, 2024 stated that, “the increase in
administrative expenses is due to increase in professional fees for various activities for improvement in
passenger experience and operations.” The Authority while acknowledging the aim to enhance
passenger experience, also considers the financial impact on passengers given that such expenses
may be ultimately passed through to passengers; and thus, proposes to not consider the actual
expenses for FY24. Further, considering that LGBIA is a brownfield airport, the Authority
proposes to consider inflationary effect as per Table 126 for the growth in Administrative expenses
(other than Collection charges for UDF), across all the remaining four (4) tariff years in the Third
Control Period. Further, the Authority is of the view that these expenses which are administrative
in nature should be apportioned in the Gross Fixed Asset Ratio i.e., 95.39.
Table 148: Admin expenses claimed by GIAL and proposed by the Authority for the Third Control
Period
Particulars Units FY’23 FY’24 FY’25 FY’26 FY’27 Total
As per GIAL
Collection charges on UDF ₹ in 0.98 1.64 1.67 1.89 2.27 8.45
crores
Other Administrative Expenses ₹ in 13.56 34.00 37.40 41.14 45.25 171.35
crores
Total Administrative Expenses ₹ in 14.54 35.64 39.07 43.03 47.53 179.80
crores
As per the Authority
i. Admin expenses (UDF Collection ₹ in 0.98* 1.45** 1.62 1.84 2.21 8.11
charges) proposed by the Authority (A) crores
ii. Admin expenses Others considered by ₹ in 12.23* 12.14 12.52 12.98 13.46 63.3
the Authority (B) crores
Allocation Ratio proposed by the % 95.39% 95.39% 95.39% 95.39% 95.39%
Authority
Admin expenses Others proposed by the ₹ in 11.67 11.58 11.94 12.39 12.84 60.42
Authority (B1) crores
Total Admin expenses proposed by the ₹ in 12.65 13.03 13.57 14.22 15.06 68.53
Authority (A+B1) crores
*as per actuals submitted by GIAL for FY 2022-23
**as per actuals submitted by GIAL for FY 2023-24
Insurance expenses
10.2.29 The Authority examined the expense claimed by GIAL towards Insurance and notes the following:
• Insurance on Initial Asset Base – GIAL has considered insurance expense of ₹ 2.26 crores on
existing assets in FY 2022-23 and an increase of 10% Y-o-Y on the same. Further, GIAL has
submitted the actual expenses as ₹ 1.44 crores for FY2023-24. The Authority, on review of the
actual expenses incurred proposes to consider the same, i.e., ₹ 2.26 crores for FY 2022-23 and ₹
1.44 crores for FY2023-24. The Authority also proposes to consider Y-o-Y increase towards
inflationary effect as per Table 126 on such actual expenses for the entire Third Control Period.
Further, the Authority has derived the Aeronautical expenses by applying Gross Fixed Assets ratio
(95.39%) as per Table 133.
• Insurance on New Asset Base – GIAL has also claimed Insurance expense at the rate of 0.10% on
new additions to the gross block based on market rates for each tariff year. The Authority reviewed
the same and proposes to consider the expense at the same rate of 0.10% on the revised cumulative
value of Capitalized Aeronautical Assets that are forming part of RAB (Table 96).
Consultation Paper No. 01/2024-25 Page 193 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
• The Authority further proposes to compute insurance expenses on New Asset Base as per
revised gross block additions determined in this Consultation Paper.
Table 149: Insurance expenses claimed by GIAL and proposed by the Authority for the Third
Control Period
(₹ crores)
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
As per GIAL
Insurance expenses claimed by GIAL 2.31 2.89 6.68 9.03 9.52 30.43
As per the Authority
Insurance expense considered by the Authority 2.26 1.44 1.49 1.54 1.60 8.33
on Initial Asset Base (A)
Allocation ratio proposed by the Authority
95.39% 95.39% 95.39% 95.39% 95.39%
Insurance on opening net block of assets (A1)
2.16 1.38 1.42 1.47 1.52 7.94
Insurance on New Asset Base (B)
0.05 0.06 0.30 4.01 4.06 8.48
Insurance expenses allowed by the Authority
2.21 1.43 1.72 5.48 5.58 16.42
(A1 + B)
Repairs and Maintenance expenses
10.2.30 The Authority examined the expenses towards Repairs and Maintenance and noted that the same
has been projected towards Civil, Electrical, Plant and machinery, Electronics and Others.
i. Repairs and Maintenance on Exisitng Asset Base - GIAL has submitted actual expenses
of ₹ 19.51 crores and ₹ 19.76 crores in FY 2022-23 and FY 2023-24 repectively, towards Repairs
and Maintenance for Opening Net block of Assets and an increase of 10% Y-o-Y (including
expected increase in inflation by 5% and another 5% allowance provided for any contingency
for change in scope, overtime, escalation etc.).
ii. Repairs and Maintenance on New Capital Expenditure – GIAL has also claimed Repairs
and Maintenance expense at the rate of 3% on the cumulative value of Capitalized Total Assets
for each tariff year.
iii. The Authority proposes to consider the actual R&M expenses incurred by GIAL in FY
2022-23 and FY 2023-24. The Authority proposes to consider inflationary increase as per Table
126 for FY2024-25. For FY2025-26 and FY2026-27, the Authority proposes to consider R&M
expenses equivalent to 50% and 70% respectively of the amount proposed by the AO since new
CAPEX being incurred by the AO will have Defect Liability Period and there will be blend of
old and new CAPEX. Further, the Authority has derived the Aeronautical expenses for R&M
expense, by applying the Gross Fixed Asset ratio (95.39% Aeronautical). The amount claimed
by GIAL, and the estimate proposed by the Authority is shown in the table below:
Table 150: R&M on Opening Net block of Assets claimed by GIAL and Proposed by the Authority for the
Third Control Period
(₹ crores)
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
As per GIAL
Repairs and Maintenance – For Initial Asset Base 19.51 22.00 24.20 26.62 29.28 121.61
claimed by GIAL (A)
Repairs and Maintenance – New Capital Additions - 1.74 4.09 109.69 171.23 286.75
claimed by GIAL (B)
Consultation Paper No. 01/2024-25 Page 194 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
Total Repairs and Maintenance – claimed by 19.51 23.74 28.29 136.31 200.51 408.36
GIAL (C = A + B)
As per the Authority
19.51* 21.50** 22.17 68.16 140.36 271.69
Repairs and Maintenance Expenses – (D)
95.39% 95.39% 95.39% 95.39% 95.39%
Allocation Ratio (E)
R&M expenses considered by the Authority 18.61 20.50 21.14 65.01 133.89 259.14
(F=D*E)
*as per actuals submitted by GIAL for FY 2022-23
**as per actuals submitted by GIAL for FY 2023-24
Other Operating expenses
10.2.31 GIAL has submitted the Other Operating Expenses and claimed an increase of 5% Y-o-Y for all
five (5) tariff years and an additional increase 621% in FY 2025-26 on account of increase in
Terminal Building area. GIAL has further submitted that the other Operating Expenses largely
incudes Cleaning & Housekeeping Services, Pest Control Services, Cleaning of Public Toilet,
providing biomedical waste management services, garbage collection services etc. The major
agreements were entered during FY22-23 and hence in order to provide its annualized impact, a
necessary increase factor of ~64% has been considered in FY23-24.
• The Authority has observed the actual expenses incurred by GIAL on Other Operating
expenses for FY 2022-23 as ₹ 13.43 crores and proposes to consider the same. Further, GIAL
has submitted the actual expenses as ₹ 17.40 crores for FY2023-24 and the Authority
proposes to consider and use the same as base for forecasting future expenses. In respect of
Y-o-Y growth rate claimed by GIAL, the Authority proposes that the increase towards
inflationary effect as per Table 126 should only be considered, instead of 5% increase Y-o-Y
claimed by GIAL.
• In respect of additional increase of 621% claimed by GIAL in FY26, the Authority proposes
to consider increase of 414%, with regard to increase in Terminal Building area due to
commissioning of NITB. Further, the Authority considering the nature of expenses proposes
to allocate the cost as per Terminal Building ratio of 90% Aeronautical (refer para 10.2.17).
Table 151: Other Opex claimed by GIAL and proposed by the Authority for the Third Control
Period
Particulars Units FY’23 FY’24 FY’25 FY’26 FY’27 Total
As per GIAL
Other Operating expenses ₹ in 13.43 22.00 23.10 167.63 176.02 402.18
claimed by GIAL crores
As per the Authority
Other Operating expenses ₹ in 13.43* 17.40** 17.94 92.84 96.27 237.87
considered by the Authority crores
Allocation ratio proposed by the % 90 90 90 90 90
Authority
Other Operating expenses ₹ in 12.09 15.66 16.15 83.55 86.64 214.09
proposed by the Authority crores
*as per actuals submitted by GIAL for FY 2022-23
**as per actuals submitted by GIAL for FY 2023-24
Consultation Paper No. 01/2024-25 Page 195 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Independent Engineer Cost
10.2.32 GIAL has claimed Independent Engineer Cost of ₹ 3.91 crores from FY23 till FY25 and claimed
an increase of 5% Y-o-Y from FY26 onwards. As per the information provided, AAI appointed
M/s IRCON International Limited as the Independent Engineer for 3 years with a total cost of ₹
11.74 crores (₹ 3.91 crores annually). The extract of the relevant clauses is as below:
Clause 24.1.2 states
“The appointment of the Independent Engineer shall be made within 90 (ninety) days of the date of
execution of this Agreement, and such appointment shall be valid for a period of 3 (three) years. On
the expiry or termination of the said appointment, the Authority shall appoint an Independent Engineer
for a further term of 3 (three) years in accordance with the provisions of Schedule K, and such
procedure shall be repeated after expiry of each appointment.”
Clause 24.3.1 states
“The remuneration, cost and expenses of the Independent Engineer shall be paid by the Authority, and
all such remuneration, cost and expenses shall be reimbursed by the Concessionaire to the Authority
within 15 (fifteen) days of receiving a statement of expenditure from the Authority. Any amounts paid
to the Independent Engineer shall be considered for a pass-through for the determination of the
Aeronautical Charges by the Regulator.”
10.2.33 The Authority notes that AAI had appointed M/s IRCON International Limited as the Independent
Engineer with effect from 22nd October 2021 with the responsibility of reviewing the projects being
carried out by GIAL on site and submitting necessary reports to GIAL.
10.2.34 The Authority also notes that as per Clause 24 and Schedule K of the Concession Agreement, AAI
is required to appoint the Independent Engineer initially for a period of 3 years and thereafter for
every 3 years. AAI has executed the contract with the Independent Engineer at a fee of ₹ 11.74
crores. GIAL has projected the Independent Engineer Cost based on the same and together with
considering an inflation of 5% for the last two tariff years for the Third Control Period.
10.2.35 However, the Authority proposes not to allow inflation of 5% and retain the amount originally
awarded by AAI proportionately for the last two tariff years. The Authority also examined the
actual expense of ₹ 3.91 crores and ₹ 3.52 crores for FY 2022-23 and FY 2023-24 respectively,
and proposes to consider the same.
Amortization of Runway recarpeting expenses
10.2.36 GIAL has claimed amortization of ₹ 49.08 crores projected towards expenditure on Runway
Recarpeting works over a period of five (5) FYs starting from FY 2025-26 and based on the
Depreciation Order No. 35 / 2017-18 dated January 12, 2018. Further, GIAL has submitted that the
expense is inclusive of carrying cost on the unamortized balance of the expense incurred on re-carpeting
of runway.
10.2.37 During the site visit, the Authority observed that the runway condition is appropriate, except turning
pad areas which can be set right by repair of runway, for continued operation and in view of cost
optimisation the AO should do cost benefit analysis. In view of the cost optimisation and existing
runway condition, the Authority proposes not to consider any OPEX towards runway strengthening
works during third control period, and if desired the Authority may consider such OPEX on incurrence
basis subject to the reasonableness and efficiency of the OPEX at the time of tariff determination of
next control period.
Consultation Paper No. 01/2024-25 Page 196 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Fuel Operating Expenses
10.2.38 Clause 19.3. of the Concession Agreement stipulates GIAL’s obligations towards providing aircraft
fueling services (refer to paragraph 17.3.7 of Annexure 3 of Chapter 17 of this Consultation Paper)
10.2.39 GIAL has submitted the following assumptions regarding Fuel facility Operating expenses:
• GIAL has projected that the open access facility operations will commence from December 2023
onwards (i.e., 3-month period in FY 2023-24) and continue till end of FY2024-25. Further, GIAL
has proposed to build a new facility of approx. 4,000 KL with hydrant system of approx. 7 Kms.
The new facility will be operational from FY25-26 onwards.
• GIAL has estimated the Fuel Throughput volume at the rate of approximately 2.0 KL per ATM for
the Total ATM traffic projected in each tariff year.
• Further GIAL has submitted that they planned to outsource the Fuel facility operations to a third-
party vendor who will manage the facility on Cost plus margin basis.
• The charges payable to the Vendor by GIAL have been projected based on a ‘Minimum Guarantee’
amount up to specified quantity of 80,000KL (i.e., fixed amount per year) and beyond the specified
quantity of 80,000KL, on the basis of agreed Rate/ KL (i.e., variable rate). The vendor rates
projected by GIAL, based on experience of Lucknow Airport in FY22, are as follows:
Table 152: Fuel O&M expenses claimed by GIAL for each FY for the Third Control Period
Particulars Unit Quantity Rate (₹) Amount (₹ in Cr.)
Fixed amount for up to 80,000KL per year Month 12 64,10,000 7.69
Fee beyond 80,000KL Per KL - 290.00 -
• Additionally, GIAL had projected an increase of 5% towards inflation Y-o-Y on both the fixed amount
and variable rate /KL payable to the vendor.
• Apart from the above, GIAL had projected Rental cost of refuellers amounting to ₹ 0.66 crore in FY
2023-24 and ₹ 0.99 crores in FY 2024-25. The rental cost had been estimated for 4 month period in FY
2023-24 and half year period in FY 2024-25 after which, GIAL expects to have sufficient number of
own refuellers to run the operations.
The Authority examined all the above and summarised its view as under:
a) The Authority has ascertained that GIAL till March 2024 is yet to commence open fuel
access facility operations and has till date incurred zero costs on fuel operating expenses.
GIAL vide email dated April 2, 2024 has stated that Fuel farm Operations at GIAL is
expected to be commenced from July 2024. The Authority thus proposes to consider
expenses for fuel operations from July 2024 onwards.
b) The Authority proposes to consider the Fuel throughput Volume and related Operations
and Maintenance Costs of LGBIA for the Third Control Period based on the growth rate
proposed by the Authority for ATM traffic as per Table 71 and correspondingly derive the
O&M expenses.
c) The Authority proposes to undertake the growth rate towards inflationary effect as
prescribed in Table 126 above, for both fixed and variable expenses during each year of the
Third Control Period.
Consultation Paper No. 01/2024-25 Page 197 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Table 153: Fuel Opex claimed by GIAL and allowed by the Authority for the Third Control Period
Particulars Unit FY’23 FY’24 FY’25 FY’26 FY’27 Total
As per GIAL
Fuel O&M expenses ₹ in
- 3.6 10.3 10.3 11.7 35.93
claimed by GIAL crores
As per the Authority
ATM traffic in Nos. - 45395* 68050 82109 195554
-
Fuel throughput per ATM in KL - 2 2 2
-
Fuel throughput volume KL - 90,791 136,100 164,218 391,109
-
(A)
Fixed Fuel throughput KL - 60,000* 80,000 80,000 220,000
-
volume (B)
Variable Fuel throughput KL - 30,791 56,100 84,218 171,109
-
volume (C = A -B)
Growth rate proposed by the In % - 3.10% 3.70% 3.70%
-
Authority towards inflation
Fixed Fuel O&M expenses ₹ in - 5.95 8.22 8.53 22.70
-
(up to 80,000 KL) (D) crores
Variable O&M expenses ₹ in - 0.91 1.73 2.69 5.33
-
(above 80,000KL) (E) crores
Fuel O&M expenses (F = D - 6.86 9.95 11.22 28.03
+ E)
Refuelers rentals Charges ₹ in - 1.98 0.00 0.00 1.98
-
(G) crores
Total Fuel expenses ₹ in 8.84 9.95 11.22 30.01
proposed by the Authority crores - -
(H = F + G)
*For 9 month period
Cargo Operating Expenses
10.2.40 Clause 19.4.1. of the Concession Agreement stipulates GIAL’s obligations towards upgrading,
developing, operating and maintaining the Cargo facilities in accordance with the provisions of the
Concession Agreement.
10.2.41 GIAL has claimed Cargo Operating Expenditure of ₹ 20.63 crores for third control period towards
in-house salary cost, outsourced O&M expenses and customs cost recovery by considering the FY 2023-
24 as base year of operations and on the assumption of commencing Cargo Operations from June 2023
onwards. GIAL has projected the Insourced salary and Customs Cost recovery based on the Manpower
required and the Cargo O&M expenses on the basis of estimated Cargo Volume and Cargo cost / MT
for each FY. GIAL has also claimed an increase of 10% Y-o-Y for all the expenses for the next three
(3) FYs in the Third Control Period.
10.2.42 The Authority observes that GIAL has considered approximately ₹ 3,000 per tonne as basis for
determining the O&M cost for LGBIA. This rate was estimated based on the experience of Ahmedabad
and Lucknow airports. The Authority has examined the actual per tonne fee in Ahmedabad and
Lucknow airports and proposes to accept the average of the said fees for the two airports, i.e., ₹ 2,860
as the per tonne fee for FY 2023-24. The Authority also proposes to escalate this fee at inflationary
growth rate (refer Table 126) as against the increase of 10% submitted by GIAL for arriving at the O&M
expenses for the remaining three (3) years of the current control period. The Authority further proposes
to consider the cargo volume processed by GIAL as per Table 71 for the determination of O&M
Consultation Paper No. 01/2024-25 Page 198 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
expenses.
10.2.43 The Authority observes that GIAL has projected salary costs for six (6) of their own employees
comprising supervisory staff and duty managers at an average annual salary of ₹ 8 lakhs per employee
which works out to a total in-house salary cost of approximately ₹ 0.5 crore per annum starting from
FY 2023-24. Further, this cost has been projected to increase 10% Y-o-Y in each tariff year. The
Authority notes that for the period June 2023 till March 2024, GIAL has incurred own staff expenses
of ₹ 0.15 crores. The Authority proposes to consider the same and also to increase the annual average
salary by 6% Y-o-Y (as against 10% claimed by GIAL) in line with that allowed for Manpower expense
of AAI and GIAL for the remaining three (3) tariff years of the Third Control period.
10.2.44 The Authority examined the submission of GIAL and notes that apart from the salary cost of their own
employees, GIAL has projected reimbursement of salary cost of Customs officials who will be handling
the international cargo operations, under the head ‘Customs cost recovery’. The Authority notes that
GIAL has estimated the salary cost of 5 Customs officials as per Para 7 of the Circular issued by the
Department of Revenue, Ministry of Finance vide Circular No. 02/2021-Customs dated January 19,
2021 and arrived at ₹ 1.80 crores per annum. GIAL has estimated commencement of international cargo
operations from new Integrated Cargo Terminal (ICT) facility from FY 2026-27, and thus considered
salary cost only for that respective FY. The Authority notes that Customs Cost recovery is waived off
based on achievement of certain volume threshold. While the Authority has currently considered the
cost estimate provided by GIAL, the Authority directs GIAL to ensure that waiver of charges is obtained
as soon as the volume limits are reached.
10.2.45 The Authority’s proposal as compared to GIAL’s submission is summarized in the table below:
Table 154: Cargo O&M expenses claimed by GIAL and proposed by the Authority for the Third
Control Period
(₹ crores)
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
Claimed by GIAL
Insourced Salary - 0.50 0.55 0.61 0.67 2.32
O&M expenses - 1.05 1.49 2.00 11.98 16.51
Customs cost recovery - - - - 1.80 1.80
Total Cargo O&M expenses - 1.55 2.04 2.60 14.44 20.63
Considered by the Authority
Insourced Salary - 0.15 0.16 0.17 0.18 0.66
O&M expenses - 1.00 1.33 1.69 5.55 9.57
Customs cost recovery - - - - 1.80 1.80
Total Cargo O&M expenses - 1.15 1.49 1.86 7.53 12.03
Finance Charges, Working Capital Loan Interest and Annual Fee on Performance Bank Guarantee
10.2.46 GIAL has included a claim for Working Capital Loan Interest and Finance charges as a separate
line item than the other operating expenses. The Authority notes that GIAL has computed working
capital interest based on the forecasted recovery of revenue and payment of expenses and has
considered the entire expense as aeronautical. As per the calculation by GIAL, there is a
requirement for working capital for all tariff years of the Third Control Period.
Financing Charges
10.2.47 The Authority has reviewed the computation of Financing Charges and notes that GIAL has
Consultation Paper No. 01/2024-25 Page 199 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
considered finance charges at the rate of 1.50% of the debt drawn down during the current control
period. GIAL has considered 65% of the total capital addition as being funded through debt for
arriving at the debt draw down during the current control period. For the FY2022-23, financing
charges as per the audited accounts submitted by GIAL was ₹ 0.59 crores. For the remaining four
(4) tariff years, the Authority has recomputed the Finance Charges by considering 48% (refer para
8.3.2) of the revised total capital addition, i.e. ₹ 3799.70 crores (refer Table 111) as being funded
through debt. As per this revised computation, the estimated finance charges amounted to ₹ 27.08
crores for the remaining four (4) years of the Third Control Period. The Authority proposes to
consider ₹ 0.59 crores as financing charges for FY 2022-23 and ₹ 27.62 crores as financing charges
for the FY2023-24 to FY2026-27.
Working Capital Loan Interest
10.2.48 The Authority has reviewed the computation of interest on working capital loan. The Authority
also reworked the cash flows based on the revised aeronautical operating expenses, traffic, and
aeronautical revenues. As per this revised computation, the estimated interest on working capital
loan amounts to ₹ 7.67 crores for the Third Control Period. The Authority, therefore, proposes to
consider ₹ 7.67 crores during computation of ARR for the Third Control Period.
Annual Fee on PBG
10.2.49 The Authority notes that GIAL has taken a Performance Bank Guarantee (PBG) of ₹ 115 crores
for which GIAL has to pay an annual fee at 0.50% of the guaranteed amount. The Authority
considers the same as part of the costs for the control period.
10.2.50 GIAL has submitted PBG expenses amounting to ₹ 0.58 crores for each tariff year of the Third
Control Period and the Authority proposes to consider the same. The Authority further proposes to
true-up the same based on actuals at the time of determination of Tariff for the next control period.
10.2.51 The Authority also proposes to consider the allocation of these expenses as given below:
• Finance Charges based on the revised Gross Block Ratio
• Working Capital Interest to be considered as Aeronautical as the expense is computed based on
aeronautical operating expenses and aeronautical revenues.
• PBG charges to be considered as Aeronautical based on the Clause 9.1.1 of the Concession
Agreement which states that “The Concessionaire shall, for the performance of its obligations during
Phase I hereunder, provide to the Authority, no later than 120 (one hundred and twenty) days from
the date of this Agreement, an irrevocable and unconditional guarantee from a Bank for a sum
equivalent to Rs. 115,00,00,000 (Rupees One Hundred and Fifteen crores) in the form set forth in
Schedule E ("Performance Security"). Until such time the Performance Security is provided by the
Concessionaire pursuant hereto and the same comes into effect, the Bid Security shall remain in
force and effect, and upon such provision of the Performance Security, the Authority shall release
the Bid Security to the Concessionaire.”
10.2.52 The Authority’s proposal as compared to GIAL’s submission is summarized in the table below:
Table 155: Working Capital Interest, Annual Fees for PBG and Finance Charges claimed by GIAL and
proposed by the Authority for the Third Control Period
(₹ crores)
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
As per GIAL
Finance Charges - 44.77 - - - 44.77
Consultation Paper No. 01/2024-25 Page 200 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
Annual Fees for Performance BG 0.58 0.58 0.58 0.58 0.58 2.88
Working Capital Interest - 2.46 10.29 15.66 17.93 46.34
As per the Authority
Finance Charges 0.59* 0.06 1.72 24.93 0.32 27.62
Annual Fees for Performance BG 0.58* 0.58 0.58 0.58 0.58 2.90
Working Capital Interest - - 3.56 1.92 2.19 7.67
*as per actuals submitted by GIAL
10.2.53 After incorporating the above observations by the Authority, the revised Total Aeronautical O&M
expenses including Fuel and Cargo Operating Expenses of LGBIA have been presented in the tables
below:
Table 156: Total Aeronautical O&M expenses proposed by the Authority for the Third Control Period
(₹ crores)
Reference
Particulars FY’23* FY’24** FY’25 FY’26 FY’27 Total
Table
Operating Expenses
Manpower expenses – AAI employees Table 136 27.43 28.03 26.98 25.39 26.91 134.75
Manpower expenses – GIAL employees Table 141 9.23 10.70 19.00 30.35 39.69 108.97
6.70 9.20 9.49 50.54 52.41 128.33
Utility expenses
Table 142
IT expenses Table 143 2.25 3.06 3.15 6.43 6.66 21.56
Rates and Taxes Table 144 0.30 0.10 0.10 0.51 0.53 1.53
3.58 5.72 5.90 9.07 9.41 33.68
Security expenses
Table
145
Corporate Allocation Cost Table 147 12.51 11.38 12.14 12.90 13.71 62.63
Administrative Expenses - Others Table 148 11.67 11.58 11.94 12.39 12.84 60.42
Admin Expenses – Collection Charges on Table 148 0.98 1.45 1.62 1.84 2.21 8.11
UDF
Insurance Table 149 2.21 1.43 1.72 5.48 5.58 16.42
Repairs and Maintenance Table 150 18.61 20.50 21.14 65.01 133.89 259.15
Other Operating expenses Table 149 12.09 15.66 16.15 83.55 86.64 214.09
Para 3.91 3.52 3.91 3.91 3.91 19.17
Independent Engineer Fee
10.2.35
Total Operating Expenses (A) 111.46 122.33 133.24 307.36 394.41 1068.80
Fuel Operating Expenses
Fuel O&M Expenses - - 6.86 9.95 11.22 28.03
Table 153
Refuellers Rentals - - 1.98 0.00 0.00 1.98
Table 153
Total Fuel Operating Expenses (B) - - 8.84 9.95 11.22 30.01
Cargo Operating Expenses
Insourced salary Table 154 - 0.15 0.16 0.17 0.18 0.66
O&M Expenses Table 154 - 1.00 1.33 1.69 5.55 9.57
Customs Cost Recovery Table 154 - 0.00 0.00 0.00 1.80 1.80
Total Cargo Operating Expenses (C) - 1.15 1.49 1.86 7.53 12.03
Consultation Paper No. 01/2024-25 Page 201 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
Reference
Particulars FY’23* FY’24** FY’25 FY’26 FY’27 Total
Table
Finance Charges (D) Table 155 0.59 0.06 1.72 24.93 0.32 27.62
Annual Fees for Performance BG (E) Table 155 0.58 0.58 0.58 0.58 0.58 2.90
Working Capital Interest (F) Table 155 - - 3.56 1.92 2.19 7.67
Total Aeronautical O&M expenses 112.63 124.12 149.43 346.61 416.24 1149.03
(A+B+C+D+E+F)
*as per actuals submitted by GIAL for FY 2022-23
**as per actuals submitted by GIAL for FY 2023-24
Note: The surge in O&M expenses in FY2026 and FY2027 is attributed to operationalization of NITB and increase in
manpower due to completion of deemed deputation period.
10.2.54 It is to be noted that as per the true up of Second Control Period, AAI has incurred OPEX of ₹ 408.16
crores and handled maximum traffic of 5.05 MPPA in FY19-20. On the other hand GIAL for Third
Control Period has forecasted OPEX amounting to ₹ 2037.03 crores and after rationalization the
Authoity has allowed ₹ 1149.03 allowing appropriate inflationary increase and other factors. The
Authority still bears that the proposed O&M expenses are substantially higher than the actual expenses
incurred in Second Control Period . Therefore, the Authority expects GIAL to bring in further
efficiencies in their overall O&M expenses so as not to burden the airport users. This would also be a
direct violation of cost relatedness principle of ICAO.
10.2.55 Based on above considerations, the Authority proposes the following growth rates in Operation and
Maintenance (O&M) expenses for Aeronautical Operating expenses, Fuel Operating expenses and
Cargo Operating expenses, as compared to the projections submitted by GIAL.
Table 157: Growth rates in Aeronautical O&M expenses proposed by the Authority for the Third Control
Period
Particulars FY’23 FY’24 FY’25 FY’26 FY’27
Operating Expense (A)
Manpower Expenses – AAI employees - - 6% 6% 6%
Manpower Expenses – GIAL’s employees - - 6% 6% 6%
Utility expenses^ - - 3.10% 3.7% + 3.70%
414%*
IT expenses - - 3.1% 3.7%+ 3.7%
100%*
Rates and Taxes - - 3.1% 3.7% + 3.7%
414%*
Security expenses - - 3.1% 3.70% + 3.7%
50%*
Corporate Allocation Cost - - 6% 6% 6%
Administrative Expenses - Others - - 3.1% 3.7% 3.7%
Administrative Expenses – UDF Collection Charges# - - 11.86% 13.21% 20.55%
Insurance – on Initial Asset Base - - 3.1% 3.7% 3.7%
R&M Expenses - - 3.1% 207.48%@ 105.93%@
Other Operating expenses - - 3.1% 3.7% + 3.7%
414%*
Amortization of Runway recarpeting - - - - -
Fuel operating expense (B)
Fuel O&M Expenses - - 3.1% 3.7% 3.7%
Cargo operating expense (C)
Cargo Operating Expenses – Insourced Salary cost - - 6% 6% 6%
Cargo Operating Expenses – Other expenses - - 3.1% 3.7% 3.7%
Consultation Paper No. 01/2024-25 Page 202 of 254OPERATION AND MAINTENANCE EXPENSES FOR THE THIRD CONTROL PERIOD
* linked to terminal area increase
# linked to passenger traffic
^ linked to per unit charge and billable units
@ linked to gross block additions
10.3 Authority’s proposal regarding Aeronautical O&M expenses for Third Control
Period
Based on the material before it and on its examination, the Authority proposes the following with regard
to the O&M expenses for the Third Control Period:
10.3.1 To consider total Aeronautical O&M Expenses including Operating Expenses, Fuel Operating
Expenses and Cargo Operating Expenses for the Third Control Period for LGBIA as per Table 156.
10.3.2 To consider the actual total Aeronautical O&M expenses incurred by GIAL during the Third Control
Period subject to reasonableness and efficiency, at the time of True up in the Fourth Control period.
10.3.3 Considering the size and scale of operations of the Airport, the Authority expects GIAL to bring in
efficiencies in the incurrence of O&M expenses.
Consultation Paper No. 01/2024-25 Page 203 of 254NON-AERONAUTICAL REVENUE FOR THE THIRD CONTROL PERIOD
11 NON-AERONAUTICAL REVENUE FOR THE THIRD CONTROL PERIOD
11.1 GIAL’s submission of Non-aeronautical revenue for the Third Control Period
11.1.1 GIAL in its submission dated July 28, 2023 to AERA had stated that it follows a Master Concessionaire
model for managing commercial activities at the Airport.
11.1.2 GIAL had submitted that it outsourced all Non-aeronautical businesses (mentioned below) to the Master
Concessionaire, Adani Airport Holdings Limited, vide Master Services Agreement executed on October
25, 2021, and effective from December 2021. As per the Agreement, the scope of the Master
Concessionaire is to develop, operate, maintain, manage the Non-aeronautical businesses at LGBIA, in
accordance with best-in-class standards and good industry practices, and at par with facilities at
comparable airports as below:
• Duty free stores
• Food and beverages outlets
• Retail outlets
• Lounges
• Advertising, sponsorship, and promotion opportunities
• Car parks and ground transportation facilities
• Airport hotels and transit hotels
• Preferred partners association for including but not limited to pouring rights, services in air (Wi-
Fi, Bluetooth, aroma etc.), music and video rights, mobile wallet, payment gateway and other as
may be approved by GIAL
• Business Center
• City side development
• Flight catering services
• Foreign exchange services
• Freight consolidators/forwarders or agents
• Left luggage, lost and found, excess baggage
• Messenger services
• Porter service
• Special assistance services (such as paid wheelchair services)
• Vending machines
• Meet and assist services
• Provision of land and space for various stakeholders at Airport
• Various passenger amenities, including but not limited to, banks, foreign exchange, SIM card,
child-care room, kids play areas, car rental and hotel reservation counters, digital wallet tie-ups,
ATMs, spas, and entertainment areas
• Airport village comprising of various retail, food and beverage, entertainment and amenities
Consultation Paper No. 01/2024-25 Page 204 of 254NON-AERONAUTICAL REVENUE FOR THE THIRD CONTROL PERIOD
options; and
• Any other services as may be mutually agreed by the parties or permitted pursuant to the
Applicable Laws.
11.1.3 As per the terms of the Master Services Agreement, the Service provider (Adani Airport Holdings
Limited) shall pay to GIAL an amount which is higher of the following:
a) Minimum Guarantee amount of ₹ 21 crores per annum or
b) The amount arrived at by multiplying the Revenue Share Percentage (10%) with Gross Revenue
in that year.
Further, it is stated in the Agreement that the Minimum Guarantee amount of ₹ 21 crores per annum
shall remain unchanged for the first five years from the date of signing the Master Services Agreement.
Thereafter, this Minimum Guarantee amount shall be increased at the rate of 50% of the Delta Consumer
Price Index (CPI) every year.
11.1.4 Based on the above, the Non-aeronautical revenue submitted by GIAL for LGBIA is given in the table
below:
Table 158: Non-aeronautical revenue submitted by GIAL for the Third Control Period
(₹ crores)
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
1. Revenue from Master 21.00 21.00 21.00 21.00 21.00 105.00
Concession
2. Other revenues (not 2.28 0.53 0.55 0.58 0.61 4.54
covered under Master
Service Agreement)
Total 23.28 21.53 21.55 21.58 21.61 109.54
11.2 Authority’s examination regarding Non-aeronautical revenue for the Third Control Period
11.2.1 As per FY2022-23 financials submitted by GIAL, it had earned non-aeronautical revenue to the tune of
₹ 23.32 crores. The Authority proposes to consider the same. Further, GIAL has submitted actual NAR
amounting to ₹ 22.07 crores for FY2023-24 which the Authoirty proposes to consider.
11.2.2 The Authority has examined the Non-aeronautical revenue submitted by GIAL for the Third Control
Period and reviewed the Master Services Agreement entered into by GIAL with the Master
Concessionaire - Adani Airport Holdings Limited with respect to scope of services outsourced to the
Master Concessionaire and the revenue sharing arrangement.
11.2.3 The Authority notes that GIAL undertook a two-stage tendering process through e-tender mode vide
Request for Proposal (RFP) dated August 17, 2021.
11.2.4 The Authority, in this regard examined the extract of the relevant clauses of the RFP which read as
under:
“6.2 Qualifying Eligibility Criteria
Each Bidder shall satisfy the following qualifying Eligibility Criteria:
(a) Technical Eligibility Criteria
The Bidder must have:
(i) (a) experience in operations or management or development of at least 4 (four) out of the
following 6 (six) non-aero businesses at airports at the time of submission of the Technical
Proposal, i.e. (I) in-flight catering; (II) duty-free retail; (III) retail and services; (IV) food and
Consultation Paper No. 01/2024-25 Page 205 of 254NON-AERONAUTICAL REVENUE FOR THE THIRD CONTROL PERIOD
beverage services; (V) car parking; and (VI) advertisement; or (b) is an operator of an airport
where 4 (four) out of the 6 (six) non-aero businesses (as mentioned above) are being
undertaken.
(ii) experience of leasing out and/ or development and/ or management of commercial real estate
with a built up area of at least 1,00,000 (one lakh) square meters.
(b) Financial Eligibility Criteria
Basis the audited balance sheet and profit and loss account along with schedules (“Audited
Financial Statements”), the Bidder should have:
(i) an average annual turnover of at least Rs. 750,00,00,000 (Rupees Seven Hundred and Fifty
crores only) in the last 3 (three) financial years; and
(ii) net worth as on March 31, 2021 of Rs. 250,00,00,000 (Rupees Two Hundred and Fifty crores
only). “Net Worth” shall have the meaning as defined under the Companies Act, 2013.
11.2.5 From the qualifying criteria specified by GIAL, the Authority observes that:
Technical Eligibility Criteria
• GIAL has specified in their technical eligibility criteria that bidder is an operator of an airport
where 4 (four) out of the 6 (six) non-aero businesses (as mentioned above) are being undertaken.
o AERA observation of restrictive criteria: As per Govt. of India Guidelines for PPP
development, the criteria to ask airport experience even for leasing out the airport has
been dispensed with. Therefore, asking airport operator experience for Master Service
Agreement is totally restrictive in nature.
• GIAL has specified experience of leasing out and/or development and/or management of
commercial real estate with a built-up area of at least 100000 (one lakh) square meters.
o AERA observation of restrictive criteria: Specifying 100000 sqm commercial space is
too high with respect to present scope of work. The total area of NITB is 1,46,000 sq.m.,
out of which the area allocated for NAR activites is around 15,000 sq.m. only.
Financial Eligibility Criteria
(i) Turnover
• GIAL has specified Average annual turnover of at least ₹ 750 crores in the last 3 financial
years and net worth as on 31.03.2021 of ₹ 250 crores.
• AERA observation of restrictive criteria: As per Public Procurement Guidelines average
financial turnover should be 30% of the estimate cost. So in place of ₹ 30 crores average
annual turnover, GIAL has specified a turnover of ₹ 750 crores (which is 25 times).
(ii) Net Worth
Asking net worth of ₹ 250 crores is very restrictive for a work value of ₹ 100 crores (Approx.)
as many Airport Operators like AAI etc. are specifying only Positive Net Worth.
11.2.6 Due to such restrictive criteria, only 2 agencies (out of these 2, one was related party), participated in the
tender and work was awarded to agency quoting 10% revenue share percentage.
11.2.7 In fact, now a days other Airport Operators have dispensed with technical eligibility criteria in Non-
Aeronautical activities tenders to attract more and more agencies and to encourage healthy competition.
Consultation Paper No. 01/2024-25 Page 206 of 254NON-AERONAUTICAL REVENUE FOR THE THIRD CONTROL PERIOD
11.2.8 Pursuant to the above RFP, only two prospective bidders (domestic and global) had submitted their
proposals to GIAL. The number of prospective bidders was low due to restrictive technical and financial
criteria as mentioned in para 11.2.4. Based on technical qualification, financial parameters and
evaluation criteria provided under the RFP, Adani Airport Holdings Limited (parent company of GIAL)
was selected as the Service Provider, with whom GIAL had entered into a Master Services Agreement.
The Authority notes that the revenues projected by GIAL are in line with the said Agreement.
11.2.9 The Authority notes that the total Non-aeronautical revenue projected by GIAL for the Third Control
Period is only ₹ 109.54 crores (refer Table 158) which is substantially lower than the actual Non-
aeronautical revenue earned by AAI in Second Control Period (FY 2016-17 till FY2020-21) which was
₹ 144.03 crores, and ₹ 154.05 crores till COD (FY 2016-17 till COD).
11.2.10 The following table and chart show the year wise NAR earned by AAI during the Second Control Period
and the projections of GIAL for the Third Control Period:
Table 159: Year wise NAR earned by AAI and projected by GIAL
(₹ crores)
Financial Year AAI GIAL
FY’17 26.66 -
FY’18 14.35 -
FY’19 30.94 -
FY’20 48.90 -
FY’21 23.18 -
Total (5 years) 144.03 -
FY’23 - 23.28
FY’24 - 21.53
FY’25 - 21.55
FY’26 - 21.58
FY’27 - 21.61
Total (5 years) - 109.54
Figure 11: Year wise NAR earned by AAI and projected by GIAL
(₹ crores)
48.9
30.94
26.66
23.18 23.28
21.53 21.55 21.58 21.61
14.35
FY’17 FY’18 FY’19 FY’20 FY’21 FY’23 FY’24 FY’25 FY’26 FY’27
AAI GIAL
Consultation Paper No. 01/2024-25 Page 207 of 254NON-AERONAUTICAL REVENUE FOR THE THIRD CONTROL PERIOD
Figure 12: Year-wise NAR per passenger earned by AAI and projected by GIAL
(₹ per pax)
105.89
89.60
70.35
53.85
46.09
36.14
30.74 32.34 28.61
23.76
FY’17 FY’18 FY’19 FY’20 FY’21 FY’23 FY’24 FY’25 FY’26 FY’27
AAI GIAL
11.2.11 The Authority also observed that the NAR projected by GIAL for the Third Control Period is
significantly lower as compared to that of other PPP airports (DIAL, MIAL, BIAL, GHIAL, CIAL),
wherein the NAR projected by such PPP airports are at least 50% of the total O&M expenses projected
by them for the respective Control Period. Whereas in the case of the GIAL, the Authority notes that the
NAR projected by GIAL for the Third Control Period is ₹ 109.54 crores, which is significantly lower as
compared to the O&M expenses submitted by GIAL, which is ₹ 2,037.03 crores (refer Chapter 10), and
eventually defeats the ultimate purpose of PPP.
11.2.12 Guwahati, being the gateway airport for the tourist destinations of north-eastern states, witnesses high
tourist footfall. The tourists at this airport thus have a natural propensity to purchase/spend on non-
aeronautical activities at the airport. This behavior is reflected in the passenger’s spending pattern and
have direct bearing on the NAR of the airport. Hence, there is a significant potential for non-aeronautical
revenues and the aspect of appropriately harnessing the same by the AO and has been taken into
consideration by the Authority in the non-aeronautical projections as brought out in Table 161.
11.2.13 LGBIA has been given on PPP mode to bring efficiencies in operations by increasing the non-
aeronautical revenues by the Airport Operator so that the benefits may be passed on to the users through
cross-subsidization.
11.2.14 The Authority takes cognizance of the fact that non aeronautical revenues projected for the Third Control
Period by GIAL considers the pandemic and economic conditions on traffic which will reduce the
consumer spending at the airport. However, the Authority is not convinced that the revenue from Master
Services Agreement is remaining constant for the period, while all the other costs are increasing
substantially across the Third Control Period. Further, the Terminal Building space will increase
considerably as is planned in FY 2025-26 (due to commissioning of NITB) adding more area for Non-
aeronautical services.
11.2.15 The Authority takes cognizance of the fact that there would be a gradual increase in Non-aeronautical
operations through increase in the Non-aeronautical area within the Terminal Building in FY 2025-26,
which will lead to increase in the Non-aeronautical revenues for the airport. Further, it is the
responsibility of GIAL to ensure to achieve higher NAR in the Third Control Period than was achieved
by AAI during the Second Control Period. In this context, there was no obligation on GIAL to accept
the bid of Master Concessionaire offering such low revenue share.
11.2.16 When an airport operator takes an initiative, such as undergoing an open global competitive bidding
Consultation Paper No. 01/2024-25 Page 208 of 254NON-AERONAUTICAL REVENUE FOR THE THIRD CONTROL PERIOD
process, it is for the betterment of the airport and is in the interest of the airport users. The Holding
Company (Group entity of Adani Enterprises Limited itself) was selected as the Master Concessionaire.
However, this does not result in enhancing the material gains to the airport users by higher cross
subsidization of NAR. It is pertinent to note that GIAL could have leveraged the technical know-how to
bring in efficiencies in generating NAR without the Master Concessionaire. No advantages have been
provided to the airport users due to the Master Concession Agreement.
11.2.17 Moreover, considering the positive outlook provided by the Expert Agencies, the outlook of the GDP
growth predicted by the GoI and the encouraging trend in the traffic numbers reported in FY 2022-23
(5.05 MPPA) and FY 2023-24 (5.96 MPPA), the Authority noted that the passenger traffic has reverted
to pre-covid levels in FY 2023-24. Further the traffic is expected to progressively increase during the
Third Control Period (as also discussed in Chapter 6).
11.2.18 With the steady increase in passenger traffic and expansion of Terminal Building area (commissioning
of NITB), the Authority foresees an increase in passenger related Non-aeronautical revenue across the
Third Control Period. Further, the Authority expects GIAL to bring in efficiencies in Non-aeronautical
operations as being followed by other PPP airports wherein the proportion of Non-aeronautical revenue
projected by GIAL is equal or comparable to the quantum of O&M expenses, whereas, in the case of
LGBIA the situation is peculiar wherein the projection of NAR is substantially lesser than O&M
expenses. Further, this will impact the interest of the airport users as 30% of the Non-aeronautical
revenue is used for cross subsidization. The Authority urges GIAL that it should make efforts to generate
non-aeronautical revenue higher than that was earned by AAI during the Second Control Period.
11.2.19 The Authority noted that GIAL in its MYTP submission has estimated Revenues from space rentals to
be ₹ 0.50 crores. GIAL has considered a 5% increase in these rates Y-o-Y. The Authority notes that the
actual revenue from space rentals in FY 2022-23 is ₹ 0.44 crores. Further, GIAL has not provided any
information about space rental from airlines for the FY2022-23.
11.2.20 The Authority further observes that out of the total actual non-aeronautical revenue ₹ 23.32 crores in FY
2022-23, ₹ 0.58 crores relate to Fair Value of Financial Instrument and proposes to not consider the same
while determining NAR for FY 2022-23 as it is an IND AS adjustment.
11.2.21 Based on the above discussion the adjustment to the actual Non-Aeronautical Revenue for FY 2022-23
is as given below
Table 160: Adjustment to Revenue from Non-Aeronautical Services considered by the Authority
for FY 2022-23
(₹ crores)
Particulars FY23
Actual Non-Aeronautical Revenue as submitted by GIAL (A) 23.32
Adjustment:
Fair Value of Financial Instrument as per Ind AS (B) 0.58
Non-Aeronautical Revenue as per the Authority (A - B) 22.74
11.2.22 Based on the above considerations, the Authority has estimated the total Non-aeronautical revenues for
the Third Control Period for LGBIA as follows:
i. The NAR earned by AAI in FY 2019-20, which is a pre-COVID year, is considered as the base
for estimating the NAR for LGBIA for the Third Control Period from FY2024-25 onwards.
ii. The Authority has considered the actual revenue earned by GIAL for FY 2022-23 and FY2023-
24 as these FYs have already passed.
iii. The Authority proposes not to consider ₹ 0.58 crores of Fair Value of Financial Instrument in
Consultation Paper No. 01/2024-25 Page 209 of 254NON-AERONAUTICAL REVENUE FOR THE THIRD CONTROL PERIOD
FY2022-23 as it relates to IND AS adjustment.
iv. The NAR of ₹ 48.90 crores of FY 2019-20 of AAI has been assumed as base for FY 2024-25,
since the traffic has reached the pre-COVID level of FY 2019-20 by the close of FY 2023-24.
v. The Authority proposes to consider the impact of inflation as prescribed in Chapter 9 of the
Consultation Paper.
vi. The Authority proposes to consider the impact of terminal area increase with respect to NAR from
FY2026-27 onwards. Further, the Authoirty proposes to consider an increase of one-third of the
total terminal area increase due to operationalization of NITB, i.e. (1/3)*621% = 207%
Table 161:Total Non-aeronautical revenues proposed by the Authority for Third Control Period
(₹ crores)
NAR of
Particulars AAI for FY’23 FY’24 FY’25 FY’26 FY’27 Total
FY’20
Total NAR 48.90* 22.74 22.07 48.90 50.71 157.55 301.97
% increase
Inflation 3.70% 3.70%
Terminal Area 207%
* Refer Table 36 of this Consultation Paper
Note: As submitted by GIAL, there is no space rent from airlines in the actual non-aeronautical revenue submitted
by them for the FY2022-23 and FY2023-24. Non-Aeronautical revenue for the FY2025 – FY2027 has been projected
on the basis of non-aeronautical revenue of AAI for the FY2019-20 (pre-COVID year)
11.3 Authority’s proposal relating to Non-aeronautical revenue for the Third Control Period
Based on the material before it and its analysis, the Authority proposes the following with regard to
Non-aeronautical revenue for the Third Control Period:
11.3.1 To consider Non-aeronautical revenues for the Third Control Period for LGBIA as per Table 161.
11.3.2 Non-Aeronautical Revenue will not be trued up at the time of tariff determination of next control period
if it is lower than that proposed by the Authority in Table 161.
Consultation Paper No. 01/2024-25 Page 210 of 254TAXATION FOR THE THIRD CONTROL PERIOD
12 TAXATION FOR THE THIRD CONTROL PERIOD
12.1 GIAL’s submission regarding Taxation for the Third Control Period
12.1.1 GIAL has submitted that the computation of income tax on aeronautical income, has been made on the
prevailing Income Tax laws and rules.
12.1.2 GIAL has calculated the revenue generated from Regulated services, Non-aeronautical revenue
Aeronautical operating expenses, interest and financing charges, and depreciation on written down
value (WDV) of assets as per the Income Tax Act. After calculating the Profit Before Tax (PBT), a tax
rate of 25.17% was applied, after setting off prior losses. The Aeronautical taxes submitted by LGBIA
are shown in the table below:
Table 162: Taxation submitted by GIAL for the Third Control Period
(₹ crores)
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
Aeronautical Revenue with Revised Rates 154.58 430.04 1,204.91 1,426.73 1,811.14 5,027.39
Add: 30% of Non-aeronautical revenue 6.98 6.46 6.47 6.47 6.48 32.86
Less: O&M expenses 119.58 225.03 262.36 654.93 775.11 2,037.03
Less: Tax Depreciation 20.27 26.83 216.80 496.19 566.72 1,326.82
Aero Profit Before Tax 21.70 184.63 732.21 282.07 475.78 1,696.41
Tax rate (%) 25.17% 25.17% 25.17% 25.17% 25.17%
Tax 5.46 46.47 184.30 71.00 119.76 426.99
12.2 Authority’s examination regarding Taxation for the Third Control Period
12.2.1 The Authority notes that GIAL has considered 30% Non-aeronautical revenues in the estimation of
Aeronautical PBT, which was then used in the computation of Aeronautical taxes. The fact that a part
of Non-aeronautical revenues is used for cross subsidization as per the Hybrid Till mechanism, doesn’t
change the nature of such revenues to Aeronautical. Further, the cross subsidization as per the Hybrid
till mechanism is done in order to reduce tariff pressure on passengers and to incentivize GIAL to make
effective investments in Non-aeronautical generating sources.
12.2.2 Therefore, the Authority is of the view that:
• 30% Non-Aeronautical revenues should not be treated as a subsidy for the Airport Operator as the
airport operator has already earned it from Non-Aeronautical services and is meant as a cross
subsidy to the airport user.
• The consideration of 30% Non-Aeronautical revenues as part of revenues from Aeronautical
services would result in undeserved enrichment to the Airport Operator effectively reducing the
cross-subsidy benefit to the airport user from the present 30% Non-Aeronautical income.
12.2.3 The Authority thus proposes to consider only Aeronautical revenues and expenses in the calculation of
Aeronautical PBT.
12.2.4 The Authority has also noted that GIAL has not considered the interest expense on the long-term
borrowings while computing the Aeronautical PBT for the Third Control Period. This has resulted in
estimating higher Aeronautical Profit and consequently, higher Aeronautical taxes. The Authority
proposes to consider actual interest expense in FY23 as a base for forecasting expenses for future tariff
years in the Third Control Period. This expense has been deducted for estimating the Aeronautical P&L.
12.2.5 The Authority has recomputed taxes of GIAL based on the changes proposed to the other building
Consultation Paper No. 01/2024-25 Page 211 of 254TAXATION FOR THE THIRD CONTROL PERIOD
blocks and based on the proposal discussed above on exclusion of Non-aeronautical revenue.
12.2.6 The Authority notes that as per clause 28.11.4 of the CA, the Adjusted Deemed Initial RAB will be
reduced for over-recoveries of Aeronautical Revenues, or increased for under-recoveries, impacting
Aeronautical Charges for the next Control Period. The Authority has considered that the compensation
paid to AAI by GIAL for shortfall, will be claimed as a deduction in the Income Tax computation of
GIAL and the same has been considered accordingly in the Income Tax computations.
12.2.7 The following table summarizes the Aeronautical taxes proposed by the Authority for the Third Control
Period.
Table 163: Taxation proposed by the Authority for the Third Control Period
(₹ crores)
Particulars Ref. FY’23 FY’24 FY’25 FY’26 FY’27 Total
Aeronautical Revenue* A 154.62 176.00 572.06 671.61 839.64 2,413.93
Less: O&M expenses (refer B 112.63 124.12 149.43 346.61 416.24 1,149.03
Table 156)
Less: Tax Depreciation C 20.51 21.47 33.61 219.02 373.36 667.97
Less: Interest Expense D 13.30 13.65 23.96 173.57 175.46 399.94
Less: Payment to AAI – PV of E 172.80 172.80
recovery as on March 31, 2023
(refer Table 42)
Profit Before Tax F=A- (164.63) 16.75 365.06 (67.57) (125.43) 24.19
SUM(B:E)
Previous Loss Adjustment G - 16.75 147.87 - - 164.63
Taxable profit H=F-G - - 217.19 - -
Tax rate (%) I 25.17% 25.17% 25.17% 25.17% 25.17%
Aeronautical Tax J=H*I - - 54.67 - - 54.67
Opening Losses K - (164.63) (147.87) - (67.57)
Current period (loss)/profit L=F (164.63) 16.75 365.06 (67.57) (125.43)
Closing Losses M=K+L (164.63) (147.87) - (67.57) (193.00)
*This is subject to revision based on tariff rate card which is to be submitted by GIAL (refer para 14.2.8). For FY 2022-23 and FY2023-
24, actual revenues have been considered.
**Computed using WDV method considering useful lives as per IT Act.
12.3 Authority’s proposal regarding Taxation for the Third Control Period
Based on the material before it and based on its analysis, the Authority proposes the following with regard to
Taxation for the Third Control Period.
12.3.1 To consider the Taxation for the Third Control Period for LGBIA as per Table 163.
12.3.2 To true up the aeronautical tax amount appropriately taking into consideration all relevant facts at the
time of tariff determination for the Fourth Control Period.
Consultation Paper No. 01/2024-25 Page 212 of 254QUALITY OF SERVICE FOR THE THIRD CONTROL PERIOD
13 QUALITY OF SERVICE FOR THE THIRD CONTROL PERIOD
13.1 GIAL’s submission relating to Quality of Service
13.1.1 GIAL has submitted that it will abide by the ASQ performance indicators mentioned in Annexure I to
Schedule H in the Concession Agreement.
Clause 23.7.1 of the CA states:
“The Concessionaire shall participate in the user survey of ASQ undertaken by Airports Council
International (ACI) or any substitute thereof, conducted every quarter and shall ensure that the Airport
achieves and maintains a rating of at least 4.5 out of 5.0 and/ or shall appear within top 20 percentile
of all airports, in its category in the World in such survey within 5 years from the COD and maintain
the same throughout the rest of the Concession Period.”
Clause 23.7.2 of the CA states:
“The Concessionaire shall, within 21 days of the end of each calendar quarter, provide to the Authority
a written report on the results of the user survey of ASQ for the immediately preceding quarter, together
with its analysis of the results and the action, if any, that it proposes to take for improvement in User
satisfaction.”
13.1.2 GIAL has further submitted that adherence and maintenance of these standards will require creation of
significant infrastructure, ramp-up of human resource and increase in operations and maintenance costs
and that GIAL has considered the cost implications, while preparing future projections as part of its
MYTP submission.
13.2 Authority’s examination regarding Quality of Service for the Third Control Period
13.2.1 The Authority notes that:
As per section 13 (1) (d) of the AERA Act, 2008, the Authority shall “monitor the set performance
standards relating to quality, continuity and reliability of service as may be specified by the Central
Government or any Authority authorized by it in this behalf.”
As per section 13(1)(a)(ii), the Authority is required to determine the tariff for Aeronautical
services taking into consideration “the service provided, its quality and other relevant factors.”
13.2.2 The Authority noted that the ACI ASQ survey results for LGBIA for the years 2020 to 2024 (Q3) is in
the range of 4.48 to 4.95.
Table 164: ASQ rating for LGBIA
Year ASQ rating
2020 4.48
ASQ was not conducted due to lockdown on account
2021 – Q1 & Q2
of COVID-19 pandemic
2021- Q3 4.84
2021- Q4 4.86
2022 -Q1 4.88
2022- Q2 4.90
2022-Q3 4.78
2022-Q4 4.87
2023 -Q1 4.90
2023- Q2 4.90
2023-Q3 4.91
2023-Q4 4.95
2024 -Q1 4.92
Consultation Paper No. 01/2024-25 Page 213 of 254QUALITY OF SERVICE FOR THE THIRD CONTROL PERIOD
Year ASQ rating
2024- Q2 4.94
2024- Q3 4.93
13.2.3 The Authority also notes that as per the Concession Agreement, GIAL is required to maintain an ASQ
rating of at least 4.5 out of 5. In this regard, the Authority notes that GIAL has achieved ASQ rating for
FY 2023 in the range of 4.90 to 4.95 which is above the prescribed rating of 4.5 as mentioned in the CA.
13.2.4 Based on the above factors, the Authority does not propose any adjustment towards tariff determination
for the Third Control Period on account of quality of service maintained by the LGBIA.
13.3 Authority’s proposal relating to Quality of Service for the Third Control Period
Based on the material before it and its analysis, the Authority proposes the following with regard to
Quality of Service for the Third Control Period:
13.3.1 Not to consider any adjustment towards tariff determination for the Third Control Period with regard to
Quality of Service of LGBIA.
13.3.2 GIAL should ensure that service quality at LGBIA conforms to the performance standards as indicated
in the Concession Agreement over the Third Control Period.
Consultation Paper No. 01/2024-25 Page 214 of 254AGGREGATE REVENUE REQUIREMENT (ARR) FOR THE THIRD CONTROL PERIOD
14 AGGREGATE REVENUE REQUIREMENT (ARR) FOR THE THIRD CONTROL PERIOD
14.1 GIAL’s submission regarding ARR for the Third Control Period
14.1.1 GIAL has submitted ARR and Yield per Passenger (YPP) for the Third Control Period as per the
regulatory building blocks discussed.
14.1.2 The summary of ARR and YPP has been presented in the table below.
Table 165: ARR submitted by GIAL for the Third Control Period
(₹ crores)
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
Average RAB 152.55 191.40 2,010.85 4,674.63 5,440.58
Fair Rate of Return 14.76% 14.76% 14.76 % 14.76 % 14.76 %
Return on average RAB 22.51 28.24 296.72 689.79 802.81 1,840.07
Total O&M expenses
(including interest on
119.58 225.03 262.36 654.93 775.11 2,037.03
working capital & financing
charges)
Depreciation 23.11 32.83 117.76 284.13 366.46 824.29
Tax expense 5.46 46.47 184.30 71.00 119.76 426.99
Less: 30% NAR (6.98) (6.46) (6.47) (6.47) (6.48) (32.86)
Add: True up for the period
28.81 28.81
from COD till March 31,
2021
ARR per year (₹ crores) 192.49 326.12 854.67 1,693.38 2,057.65 5,124.32
Discount factor (@ 14.76%) 1.00 0.87 0.76 0.66 0.58
PV of ARR 192.49 284.19 649.01 1,120.54 1,186.51 3,432.74
Sum Present value of ARR
3,432.74 3,432.74
(₹ crores)
14.2 Authority’s examination of Aggregate Revenue Requirement (ARR) for the Third Control Period
14.2.1 The observations and proposals of the Authority across the regulatory building blocks impact the
computation of ARR and Yield. With respect to each element of the regulatory building blocks
considered by GIAL in computation of ARR and Yield in the table above, the Authority proposes to
consider the regulatory building blocks as discussed in the above chapters.
14.2.2 The Authority notes that GIAL has on-going capital expenditure projects and other planned works,
which have resulted in a higher ARR for the Third Control Period. The existing traffic base is not
sufficient for the complete recovery of ARR in the current Control Period and this would require a
significant increase in tariff. Further, a significant increase in Aeronautical tariff, is also attributable
on account of the fact that the new Aeronautical tariff proposed by the Authority may be implemented
only by August 2024, thereby resulting in only lesser tariff years being available for recovery of the
ARR.
In this regard, the Authority would like to draw reference to the guiding principles issued by the
International Civil Aviation Organization (“ICAO”) on charges for Airports and Air Navigation Services
(ICAO DoC 9082), which lays down the main purpose of economic oversight which is to achieve a
balance between the interest of Airports and the Airport Users. This policy document categorically
specifies that caution be exercised when attempting to compensate for shortfalls in revenue considering
its effects of increased charges on aircraft operators and end users. The said policy document also
Consultation Paper No. 01/2024-25 Page 215 of 254AGGREGATE REVENUE REQUIREMENT (ARR) FOR THE THIRD CONTROL PERIOD
emphasizes on balancing the interests of airports on one hand and aircraft operators, end users on the
other, in view of the importance of the air transport system to States. This should be applied particularly
during periods of economic difficulty. Therefore, the policy document recommends that States
encourage increased cooperation between airports and aircraft operators to ensure that the economic
difficulties facing them all are shared in a reasonable manner.
This may also be read in conjunction with the objectives of the National Civil Aviation Policy (NCAP)
2016, which intends to provide affordable and sustainable air travel for passengers/masses. As per para
12 (c) of the NCAP, “In case the tariff in one particular year or contractual period turns out to be
excessive, the Airport Operator and the Regulator will explore ways to keep the tariff reasonable and
spread the excess amount over the future.” The above has also been conveyed by AERA vide its Order
No. 14/2016-17 dated January 12, 2017.
Further, it is pertinent to note that considerable investments in capacity have already been made which
would be sufficient for the foreseeable future. Therefore, the subsequent control periods are expected to
witness lower capital expenditure requirements while catering to a larger traffic base.
Determination of Aeronautical charges and UDF requires a delicate balance between cost recovery and
its potential impact on air traffic demand. This balance is crucial for the financial viability of the airport
and its ability to sustain operations while also ensuring that the tariffs remain competitive enough to
attract and retain airlines and passengers. Therefore, the Authority, based on the Tariff Rate Card to be
submitted by GIAL would decide the balance between cost recovery and its potential impact on air traffic
demand.
Air Freight Station (AFS)
14.2.3 The Authority notes the Policy Guidelines on ‘Air Freight Station’ (AFS) issued by MoCA in
October 2014. This Policy shall create an off Airport Common User facility equipped with fixed
installations of minimum requirements and offering services for handling International Air Cargo
in the form of Air Freight Stations with a mandate to enable the Cargo Industry as follows:
• Off-Airport common user facility equipped with fixed installations of minimum requirements and
offering services for handling and temporary storage of import/ export goods, loaded and empty Unit
Load Devices (ULD) and Cargo in bulk/ loose for outright export.
• Create an enabling environment for promoting International Air Cargo operations by reaching out to
hinterland regions of the Country besides de-congesting the congested Air Cargo terminals in some
gateway International Airports that face high dwell time.
• Authorizing some of the Inland Container Depots (ICD) to cater to the International Air Cargo
operations, the existing facilities in these ICDs could be fully utilized.
14.2.4 The Authority notes that the above Policy Guidelines on AFS has larger national intent and it aims
to strengthen and develop air cargo logistics in the Country and the same is expected to reduce the
bottlenecks in air cargo logistics and help in ease of doing business, particularly for exporters.
14.2.5 The Authority directs GIAL to submit a separate tariff rate in case the cargo is received from the
approved AFS and factor it in the Tariff Rate Card.
14.2.6 The Authority also seeks comments from the stakeholders on application of tariff on AFS Cargo,
as the Authority feels that the tariff on AFS Cargo should be significantly lesser than the tariff
Consultation Paper No. 01/2024-25 Page 216 of 254AGGREGATE REVENUE REQUIREMENT (ARR) FOR THE THIRD CONTROL PERIOD
levied on the General Cargo.
14.2.7 After considering the above, the Authority proposes the following ARR and YPP:
Table 166: ARR proposed by the Authority for the Third Control Period
(₹ crores)
Table/
Particulars FY’23 FY’24 FY’25 FY’26 FY’27 Total
Para Ref.
Average RAB (A) Table 118 167.91 179.28 282.52 2,069.48 3,681.24
Fair Rate of Return (B) Table 123 12.21% 12.21% 12.21% 12.21% 12.21%
Return on average RAB (C= 20.51 21.90 34.51 252.76 449.61 779.28
A*B)
O&M expenses (D) Table 156 112.63 124.12 149.43 346.61 416.24 1,149.03
Depreciation (E) Table 116 13.93 17.37 22.99 104.88 178.51 337.68
Taxation (F) Table 163 - - 54.67 - - 54.67
Add: PV of Under-recovery of Table 41 172.80 172.80
AAI as on March 31, 2023 (G)
Add: PV of Under-recovery of Table 62 5.29 5.29
GIAL as on March 31, 2023 (H)
ARR (I = SUM (C:H)) 325.16 163.39 261.59 704.24 1,044.36 2,498.75
NAR (J) Table 161 22.74 22.07 48.90 50.71 157.55 301.97
Less: 30% NAR (K) 6.82 6.62 14.67 15.21 47.27 90.59
Net ARR (L = I – K) 318.34 156.77 246.92 689.03 997.09 2,408.15
Discount factor (@ 12.21%) (M) 1.00 0.89 0.79 0.71 0.63
PV of ARR/ Target Revenue as 318.34 139.71 196.10 487.64 628.86 1,770.64
on 31 March 2023 (N=L*M)
Sum Present value of ARR (O) 1,770.64
Total Traffic (million Table 71
34.30
passengers) (P)
Yield per passenger on Total
516.21
Traffic (YPP) (₹) (Q=O/P)
Total Departing Passenger
17.15
traffic (R)
Yield per Departing Passenger
1,032.42
(₹) (S=O/R)
14.2.8 The Authority notes that, it is necessary to have the individual year wise tariff card laying down the
different aeronautical charges and the workings for the aeronautical revenues, in order to have a
constructive stakeholder discussion and hence GIAL is directed to submit the detailed Annual Tariff
proposals in line with the ARR and Yield arrived at by the Authority within 7 days of issue of this
Consultation Paper.
14.3 Authority’s proposal regarding Aggregate Revenue Requirement (ARR) for the Third Control
Period
Based on the material before it and based on its analysis, the Authority proposes the following with regard
to ARR for the Third Control Period:
Consultation Paper No. 01/2024-25 Page 217 of 254AGGREGATE REVENUE REQUIREMENT (ARR) FOR THE THIRD CONTROL PERIOD
14.3.1 To consider the ARR and YPP for the Third Control Period for LGBIA in accordance with Table 166.
14.3.2 To direct GIAL to submit the Annual Tariff Proposal (Tariff Rate Card) within 7 days from issue of this
Consultation Paper which will be put up for stakeholder consultations.
Consultation Paper No. 01/2024-25 Page 218 of 254SUMMARY OF THE AUTHORITY’S PROPOSALS
15 SUMMARY OF THE AUTHORITY’S PROPOSALS PUT FORTH FOR STAKEHOLDER
CONSULTATION
Chapter 4: True up of AAI for the Second Control period from FY 2017 till COD
4.15.1 To consider Deemed Initial RAB as ₹ 158.80 crores on October 8, 2021, as per Table 26
4.15.2 To consider true up of RAB for the pre-COD period as per Table 24.
4.15.3 To consider true up of depreciation for the pre-COD period as per Table 23.
4.15.4 To consider true up of FRoR for the pre-COD period as per para 4.8.
4.15.5 To consider true up of Aeronautical O&M expenses for the pre-COD period as per Table 32.
4.15.6 To consider true up of Non-aeronautical revenue for the pre-COD period as per Table 36.
4.15.7 To consider true up of Aeronautical revenue for the pre-COD period as per Table 39.
4.15.8 To consider true up of Aeronautical Taxation for the pre-COD period as per Table 41.
4.15.9 To consider true up of ARR for the pre-COD period as per Table 42.
4.15.10 To consider the present value of under recovery of ₹ 172.80 crores for True up of AAI for the Pre-COD
period as per Table 42 and readjust the same in the ARR for the Third Control Period.
4.15.11 To consider Adjusted Deemed Initial RAB as per Table 44 or based on formula provided in paragraph
4.14.2 as appropriate for actual date of payment.
Chapter 5: True up of GIAL for the period from COD till March 31, 2022
5.12.1 To consider true up of CAPEX, depreciation and RAB for the period from COD till March 31, 2022 as
per Table 50.
5.12.2 To consider true up of FRoR for the period from COD till March 31, 2022 as per Table 51.
5.12.3 To consider true up of Aeronautical O&M expenses for the period from COD till March 31, 2022 as
per Table 56.
5.12.4 To consider true up of Non-aeronautical revenue for the period from COD till March 31, 2022 as per
Table 58.
5.12.5 To consider true up of Taxation for the period from COD till March 31, 2022 as per Table 61.
5.12.6 To consider true up of Aeronautical revenue for the period from COD till March 31, 2022 as per Table
60.
5.12.7 To consider under recovery of ₹ 5.29 crores as per Table 62 for Post-COD period to be considered while
calculating the ARR for the Third Control Period.
Chapter 6: Traffic Projections for the Third Control Period
6.3.1 To consider the ATM, Passenger traffic and Cargo traffic for the Third Control Period for LGBIA as per
Table 71.
6.3.2 To true up the traffic volume (ATM, Passengers and Cargo) on the basis of actual traffic in the Third
Control Period while determining tariffs for the Fourth Control Period.
Chapter 7: Capital Expenditure (Capex), Depreciation and RAB for the Third Control Period
7.7.1 To consider the revised Terminal Building ratio of 90:10 in line with the Study on allocation of assets
between Aeronautical and Non-aeronautical assets for LGBIA, IMG norms and as approved for other
Consultation Paper No. 01/2024-25 Page 219 of 254SUMMARY OF THE AUTHORITY’S PROPOSALS
similar Airports.
7.7.2 To allow IDC during the Third Control Period and not to allow Financing Allowance as mentioned in
Para 7.3.12.
7.7.3 To adopt the capitalization of Aeronautical Expenditure for the Third Control Period in accordance with
Table 111.
7.7.4 To reduce (adjust) 1% of uncapitalized project cost from the ARR in case any particular capital project
is not completed/capitalized as per approved capitalization schedule, as mentioned in para 7.3.11. The
same will be examined at the time of tariff determination of next Control Period.
7.7.5 To examine the accounting of input tax credits in accordance with Chapter V of The Central Goods and
Services Tax Act, 2017 and make necessary adjustments at the time of determination of tariffs for the
Third Control Period.
7.7.6 To true up the Aeronautical Capital expenditure based on actuals subject to, cost efficiency and
reasonableness at the time of determination of tariff for Fourth Control Period.
7.7.7 To adopt Aeronautical Depreciation as per Table 115 for the Third Control Period.
7.7.8 To true up the Depreciation of the Third Control period based on the actual asset additions and actual
date of capitalization during the tariff determination of the Fourth Control Period.
7.7.9 To consider average RAB for the Third Control Period for LGBIA as per Table 118.
7.7.10 To true up the RAB based on actuals at the time of tariff determination for the Fourth Control period.
Chapter 8: Fair Rate of Return (FRoR) for the Third Control Period
8.3.1 To consider the Cost of equity at 15.18%.
8.3.2 To consider the notional debt to equity (gearing) ratio of 48%:52% in line with target gearing ratio being
considered in case of other PPP airports.
8.3.3 To consider cost of debt of 9% for the Third Control Period.
8.3.4 To consider FRoR of 12.21% for the Third Control Period based on above mentioned Cost of equity,
Cost of debt and gearing ratio as per Table 123.
Chapter 9: Inflation for the Third Control Period
9.3.1 To consider WPI inflation as per Table 126.
Chapter 10: Operation and Maintenance Expenses for the Third Control Period
10.3.1 To consider total Aeronautical O&M Expenses including Operating Expenses, Fuel Operating
Expenses and Cargo Operating Expenses for the Third Control Period for LGBIA as per Table 156.
10.3.2 To consider the actual total Aeronautical O&M expenses incurred by GIAL during the Third Control
Period subject to reasonableness and efficiency, at the time of True up in the Fourth Control period.
10.3.3 Considering the size and scale of operations of the Airport, the Authority expects GIAL to bring in
efficiencies in the incurrence of O&M expenses.
Chapter 11: Non-aeronautical revenue for the Third Control Period
11.3.1 To consider Non-aeronautical revenues for the Third Control Period for LGBIA as per Table 161.
11.3.2 Non-Aeronautical Revenue will not be trued up at the time of tariff determination of next control period
if it is lower than that proposed by the Authority in Table 161.
Consultation Paper No. 01/2024-25 Page 220 of 254SUMMARY OF THE AUTHORITY’S PROPOSALS
Chapter 12: Taxation for the Third Control Period
12.3.1 To consider the Taxation for the Third Control Period for LGBIA as per Table 163.
12.3.2 To true up the aeronautical tax amount appropriately taking into consideration all relevant facts at the
time of tariff determination for the Fourth Control Period.
Chapter 13: Quality of Service for the Third Control Period
13.3.1 Not to consider any adjustment towards tariff determination for the Third Control Period with regard to
Quality of Service of LGBIA.
13.3.3 GIAL should ensure that service quality at LGBIA conforms to the performance standards as indicated
in the Concession Agreement over the Third Control Period.
Chapter 14: Aggregate Revenue Requirement (ARR) for the Third Control Period
14.3.1 To consider the ARR and YPP for the Third Control Period for LGBIA in accordance with Table 166.
14.3.2 To direct GIAL to submit the Annual Tariff Proposal (Tariff Rate Card) within 7 days from issue of this
Consultation Paper which will be put up for stakeholder consultations.
Consultation Paper No. 01/2024-25 Page 221 of 254STAKEHOLDERS’ CONSULTATION TIMELINE
16 STAKEHOLDERS’ CONSULTATION TIMELINE
16.1 In accordance with the provision of Section 13(4) of the AERA Act, 2008, the proposals contained
in the Chapter 15 – Summary of the Authority’s proposals read with the relevant discussion in the
other chapters of the Paper is hereby put forth for Stakeholders’ Consultation.
16.2 For removal of doubts, it is clarified and explained that the contents of this Consultation Paper may
not be construed as any Order or Direction by the Authority. The Authority shall pass an order, in
the matter, only after considering the submissions of the stakeholders in response hereto and by
making such decisions fully documented and explained in terms of the provisions of the Act.
16.3 The Authority welcomes written evidence-based feedback, comments and suggestions from
stakeholders on the proposals made in this Consultation Paper, latest by 06th July 2024.
Secretary,
Airports Economic Regulatory Authority of India
Udaan Bhawan, 3rd Floor
D Block, Rajiv Gandhi Bhawan
Safdarjung Airport
New Delhi – 110003
(Chairperson)
Consultation Paper No. 01/2024-25 Page 222 of 254ANNEXURES
17 ANNEXURES
17.1 Annexure 1 – Summary of study on allocation of assets between Aeronautical and Non-
aeronautical assets
Background
17.1.1 RAB is one of the fundamental elements in the process of tariff determination. The return to be
provided on the RAB constitutes a considerable portion of the Aggregate Revenue Requirement
for an airport operator. To encourage the participation of the private sector in airport development
and operations, investors must be fairly compensated for the capital outlays involved. At the same
time, to safeguard the interests of the airport users, it must be ensured that the capital additions
are efficient, their needs justified, and the return on investment provided solely on the assets
related to the core operations (i.e., Aeronautical services) of the airport. Assets not directly related
to provision of Aeronautical services, if considered as Aeronautical assets, would result in
increased charges for the passengers, stakeholders and other users. Therefore, the diligent
allocation of assets into Aeronautical and Non-aeronautical assets becomes an important part of
the tariff determination process.
17.1.2 RAB evolves on a continuous basis, primarily due to the addition of capital assets required to
meet the growing demand and ensure optimal level of service, replacement of obsolete assets at
end of their useful life, sales or transfers of assets and depreciation. The allocation of an asset
towards RAB depends upon the type of asset (building & civil works, plant & machinery,
equipment, etc.), usage (provision of various services such as Aeronautical, Non-aeronautical, or
Common), ownership (by airport operator, concessionaire or other entities) and useful life of the
asset. Based on these factors, the rationale for allocation of each asset into the appropriate
classification needs to be determined diligently.
17.1.3 Towards this objective, AERA has decided to conduct an independent study on allocation of assets
and segregation between Aeronautical and Non-aeronautical components in respect of assets
appearing in the Fixed Asset Register (FAR) of Guwahati International Airport Limited as on
March 31, 2022, based on the audited financial statements for the year ended March 31, 2022 and
the True up workings as submitted by AAI to the AERA up to COD (October 8, 2021).
Classification of Assets
17.1.4 The study based on the analysis, classified the aggregate assets of LGBIA under the following
categories:
a. Aeronautical assets: All assets that are exclusively used for the provision of Aeronautical
services/ activities have been classified as ‘Aeronautical assets’. Such assets would include
runway(s), taxiways, drainage, culverts, aprons, etc.
b. Non-aeronautical assets: All assets that are exclusively used for the provision of Non-
aeronautical services/ activities have been classified as ‘Non-aeronautical assets’. Such
assets would include land side development, commercial projects, etc.
c. Common assets: All assets that cannot be directly allocated to either Aeronautical assets or
Non-aeronautical assets have been classified as ‘Common assets’. Such assets as the name
suggests, get utilised for both Aeronautical and Non-aeronautical activities. They would
include terminal building, select terminal equipment, etc.
Principles for segregation of assets
17.1.5 The study reviewed the various asset categories and developed a basis for classification of assets
Consultation Paper No. 01/2024-25 Page 223 of 254ANNEXURES
into aeronautical and non – aeronautical activities. The study also determined the appropriate
proportion of the Common Assets that may be included as part of Aeronautical activity in order
to determine the Aeronautical asset base. The principles of segregation used by the study are as
follows:
Aeronautical Assets
• Assets required for the performance of the Aeronautical services at the airport.
• Classification of aeronautical assets are taken as defined in the AERA Act.
• Assets necessary to maintain the service quality of the airport are proposed to be considered
as aeronautical except those located in the Non-aeronautical area.
Non-aeronautical Assets
• Assets required for the performance of the Non-aeronautical activities at the airport.
Examples include car parking, advertisement, retail etc.
Common Assets
• Common assets are assets which are not directly attributable to either Aeronautical or Non-
aeronautical services. These assets include the terminal building, air conditioning,
furniture, administrative office of airport company, etc.
• Common assets are bifurcated between Aeronautical and Non-aeronautical assets based
upon Terminal Building ratio or Employee Head Count ratio or Staff Quarters ratio. The
ratio of Aeronautical to Non-aeronautical as considered by the Study for the period from
FY 2016-17 to FY 2020-21 are as follows:
Table 167: The ratio of Aeronautical to Non-aeronautical considered by the Study for the
period from FY’17 to FY’22
Particulars Ratio (Aeronautical: Non-aeronautical)
Terminal Building ratio 89.02 : 10.98
Employee Head Count ratio (up to October 7, 2021) 90.45 : 9.55
Employee Head Count ratio (from October 8, 2021) 95 : 5
17.1.6 Details of adjustment to RAB
The asset allocation study reviewed the various asset categories and developed a basis for segregation
of various assets into Aeronautical, Non-aeronautical and Common. Based on the same, the Authority
has reclassified some portion of assets submitted by AAI for true up of the Pre-COD Period.
(i) Terminal building:
Details of Asset: Expansion and Modification of Existing Terminal Building
Allocation proposed by AAI: Aeronautical
Observation: The assets pertaining to development of terminal building have been considered as
Aeronautical assets by AAI. However, as these assets are within / pertaining to the terminal
building, wherein both Aeronautical and Non-aeronautical activities are carried out, the same is
Consultation Paper No. 01/2024-25 Page 224 of 254ANNEXURES
reclassified as Common asset and segregated in the Terminal Building ratio (89.02:10.98).
Allocation proposed by the Authority: Common
Impact: Reclassifying these assets from Aeronautical to Common reduces the Capital Additions to
the extent of ₹ 0.91 crores.
(ii) Plant & Machinery:
Details of Asset: VRV System, Solar plant, AC plant, Water Softening plant,
Allocation proposed by AAI: Aeronautical
Observation: The assets pertain to various machinery at several locations in the airport terminal
have been classified as Aeronautical assets by AAI. As these assets are used for servicing both
Aeronautical and Non-aeronautical activities within the terminal building, these are reclassified as
Common assets and have been reallocated in the ratio of the Terminal Building (89.02:10.98).
Allocation proposed by the Authority: Common
Impact: Reclassifying these assets reduces the Capital Additions to the extent of ₹ 0.57
crores.
(iii) Furniture & Fixtures:
Details of Asset: Furniture and Fixtures at Administrative offices
Allocation proposed by AAI: Aeronautical
Observation: The furniture at the administrative offices in the terminal building have been
classified as Aeronautical assets by AAI. As these assets are used by staff who perform both
Aeronautical and Non-aeronautical activities, these assets are reclassified as Common assets and
have been reallocated using the Employee ratio.
Allocation proposed by the Authority: Common
Impact: Reclassifying these assets reduces the Capital Additions to the extent of ₹ 0.09
crores.
(iv) Tools and Equipment:
Details of Asset: Sub-station equipment, DG set, Split AC, Lights, Fan, Baggage disinfectant
system, Radio communication equipment, Breath analyzer.
Allocation proposed by AAI: Aeronautical
Observation: The assets pertaining to the various equipment at several locations in the airport have
been classified as Aeronautical assets by AAI. As these assets are used for servicing both
Aeronautical and Non-aeronautical activities within the terminal building, these are reclassified as
Common assets and have been reallocated in the ratio of the Terminal Building (89.02:10.98).
Radio communication equipment and Breath analyzer equipment at ATC Building have been
classified as Aeronautical asset by AAI. However, since these assets are for ANS staff use, they
have been reclassified as ANS assets.
Allocation proposed by the Authority: Common / ANS
Impact: Reclassifying these assets reduces the Capital Additions to the extent of ₹ 0.10 crores.
(v) Office Appliances:
Consultation Paper No. 01/2024-25 Page 225 of 254ANNEXURES
Details of Asset: Computer, Printer, Scanner, DVD, Fox screen, DSLR Camera, Xerox machine,
Handheld Multimeter
Allocation proposed by AAI: Aeronautical
Observation: Computers, Laptop, Printers, and DVD used in the terminal building have been
classified as Aeronautical asset by AAI. As these assets are used by staff who perform both
Aeronautical and Non-aeronautical activities, these assets are reclassified as Common assets and
have been reallocated using the Employee ratio.
Computers, Scanner, Fox screen, Xerox machine, DSLR Camera, DVD, and Handheld multimeter
at the ATC tower and CNS section have been classified as Aeronautical assets by AAI. As these
assets are for CNS use, the assets have been reclassified as ANS assets.
Allocation proposed by the Authority: Common, ANS
Impact: Reclassifying these assets reduces the Capital Additions to the extent of ₹ 0.05 crores.
17.1.7 The following table presents the impact of adjustments in Asset Addition/WIP Capitalization
values due to reclassification of assets of AAI for the period April 1, 2016 to COD.
Table 168: Impact due to reclassification of AAI assets as per Study
(₹ in crores)
Tariff Total
Tariff Tariff Tariff Tariff Tariff
Additions - WIP Year 6
Year 1 Year 2 Year 3 Year 4 Year 5
Capitalization (FY22 till
(FY17) (FY18) (FY19) (FY20) (FY21)
COD)
Terminal - - (0.91) - - - (0.91)
Building
Computers (0.01) - - (0.03) - - (0.04)
Machinery (0.03) (0.03) (0.05) (0.03) (0.43) - (0.57)
Tools & - - (0.06) - (0.03) - (0.10)
Equipment
Furniture-Office - (0.08) (0.01) - - - (0.09)
Office - - - - (0.01) - (0.01)
Equipment
Total Impact on (0.04) (0.11) (1.03) (0.07) (0.47) - (1.71)
Additions
17.1.8 Accordingly, the year-wise impact on depreciation on asset additions as determined by the Study
(due to reclassification and other adjustments) is summarized in the table below:
Table 169: Impact on depreciation due to reclassification of AAI assets
(₹ in crores)
Depreciation on Tariff Tariff Tariff Tariff Tariff Tariff Total
Additions during Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
the Year (FY17) (FY18) (FY19) (FY20) (FY21) (FY22 till
COD)
Terminal Building - - - (0.03) (0.03) (0.02) (0.08)
Computers (0.001) (0.001) (0.002) (0.004) (0.011) (0.006) (0.03)
Machinery (0.001) (0.003) (0.006) (0.008) (0.022) (0.020) (0.06)
Tools & Equipment - - (0.004) (0.004) (0.005) (0.003) (0.02)
Furniture-Office - (0.001) (0.012) (0.013) (0.013) (0.007) (0.05)
Consultation Paper No. 01/2024-25 Page 226 of 254ANNEXURES
Depreciation on Tariff Tariff Tariff Tariff Tariff Tariff Total
Additions during Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
the Year (FY17) (FY18) (FY19) (FY20) (FY21) (FY22 till
COD)
Office Equipment - - - - (0.002) (0.001) (0.003)
Total Impact of (0.002) (0.005) (0.025) (0.060) (0.083) (0.052) (0.23)
Adjustments on
Depreciation on
Additions
17.1.9 Subsequent to the reclassifications and revisions in allocation ratios, the adjusted RAB has been
derived by the Authority as under:
Table 170: Adjusted RAB derived by the Authority post reclassification
(₹ crores)
FY’22
Particulars FY’17 FY’18 FY’19 FY’20 FY’21 till Total
COD
As per AAI
Opening RAB (A) 84.00* 78.85 80.44 154.28 172.29 163.26
Additions to RAB during the year (B) 9.77# 8.84 83.77 31.33 4.82 10.26 148.79
Deletions from RAB during the year (C) 7.92 0.08 8.00
Depreciation for the year (D) 7.00 7.17 9.93 13.32 13.84 7.31 58.57
Closing RAB for the year (E=A+B-C- 78.85 80.44 154.28 172.29 163.27 166.21
D)
As per Authority
Opening RAB (F) 84.00* 78.81 80.30 153.13 171.13 161.73
Reclassification adjustments
- Reclassification impact (0.04) (0.11) (1.03) (0.07) (0.47) (1.71)
(other than depreciation) (G)
- Depreciation impact on reclassification (0.00) (0.01) (0.03) (0.06) (0.08) (0.05) (0.23)
(H)
Total reclassification impact (I=G+H) (0.04) (0.12) (1.06) (0.13) (0.55) (0.05) (1.95)
Additions as per Study^ (J=B+G) 9.73 8.73 82.74 31.26 4.35 10.26 147.07
Deletions as per Study (K=C) 7.92 0.08 0.00 0.00 0.00 0.00 8.00
Depreciation as per Study^ (L=D+H) 7.00 7.17 9.91 13.26 13.76 7.26 58.34
Closing RAB (M=F+J-K-L) 78.81 80.30 153.13 171.13 161.73 164.73
Average RAB (N=(F+M)/2 81.41 79.55 116.71 162.13 166.43 163.23
^ does not include financing allowance
* includes left out assets worth ₹ 16.59 crores and cost apportionment worth 1.90 crores in First Control Period
# excludes left out asset and cost apportionment as the same has been included in Opening RAB
17.1.10 Reclassification of assets of GIAL as on March 31, 2022
The Authority has conducted an independent study on allocation of assets for the period FY 2016-17
till FY 2020-21 and used the outcome of the study to true up the RAB for the post COD period i.e.as
on March 31, 2022 for GIAL.
The Authority has considered the adjusted RAB of GIAL as on COD (which is ₹ 158.80 crores), Capital
additions and corresponding depreciation based on the results of the Asset Allocation report (refer
Consultation Paper No. 01/2024-25 Page 227 of 254ANNEXURES
Annexure III & V for the detailed report on Study on allocation of assets between Aeronautical and
Non-aeronautical assets for Guwahati International Airort).
The asset allocation study reviewed the various asset categories and developed a basis for segregation
of various assets into Aeronautical, Non-aeronautical and Common assets. Based on the same, the
Authority has reclassified some portion of assets submitted by the AO for true up of the period from
COD till March 31, 2022 which has been detailed hereunder:
i. Furniture
Details of Asset: MS Framework and Flax
Allocation proposed by GIAL: Aeronautical
Observation: The assets such as MS Framework and Flax, have been classified as Aeronautical
assets by GIAL. However, since these assets are for the use of employees of GIAL, the same
have been reallocated in the ratio of Employee Head Count of GIAL (95:5).
Allocation proposed by the Authority: Employee Head Count Ratio
Impact: Reclassifying these assets from Aeronautical to Common decreases the RAB to the
extent of ₹ 0.002 crores.
Reference: Para 4.9 of the Asset Allocation Study report
ii. IT Equipment
Details of Asset: Laptop, Desktop, Printer, Display, Server and Storage data center, other IT
equipment, Software license and support, SITA license and project implementation
Allocation proposed by GIAL: Aeronautical
Observation: The assets such as laptops, desktops, printers, servers and storage, software license,
have been classified as Aeronautical assets by GIAL. However, since these assets are for both
aero and non-aeronautic activities of GIAL, the same have been reallocated in the ratio of
Employee Head Count of GIAL (95:5). In addition, SITA License and Project Implementation
which was classified as Aeronautical by GIAL is allowed to be considered as Aeronautical asset.
Allocation proposed by the Authority: Employee Head Count Ratio / Aeronautical
Impact: Reclassifying these assets from Aeronautical to Common decreases the RAB to the
extent of ₹ 0.05 crores.
Reference: Para 4.9 of the Asset Allocation Study report
iii. Office Equipment
Details of Asset: Video Controller, Telephone, IP Phone, Mobile, Security and Safety related
equipment and accessories, Document Tray, and other Office equipment.
Allocation proposed by GIAL: Aeronautical
Observation: All office equipment has been classified as Aeronautical assets by GIAL.
However, since these assets are for both aero and non-aeronautic activities of GIAL, the same
have been reallocated in the ratio of Employee Head Count of GIAL (95:5).
Allocation proposed by the Authority: Employee Head Count Ratio
Impact: Reclassifying these assets from Aeronautical to Common decreases the RAB to the
extent of ₹ 0.03 crores.
Consultation Paper No. 01/2024-25 Page 228 of 254ANNEXURES
Reference: Para 4.9 of the Asset Allocation Study report
The following table illustrates the impact of adjustments in Asset Addition/WIP Capitalization values
due to reclassification of assets of GIAL between COD and March 31, 2022.
Table 171: Impact of Reclassification of Asset Additions by GIAL from COD till March 31, 2022
(₹ crores)
Asset Category as per MYTP Reclassification Impact
Furniture & fixtures (0.002)
IT equipment (0.05)
Office equipment (0.03)
Software -
Grand Total (0.08)
17.1.11 The Authority has proposed to consider the same rates of depreciation as applied by AAI for the
period up to COD, on the assets transferred by AAI to GIAL for the period from COD to March
31, 2022. Further, the assets added by GIAL have been depreciated based on the useful life
prescribed under Order No. 35/ 2017-18 dated January 12, 2018, of AERA. The Authority has
proposed the useful life for all the assets of LGBIA post COD as per below table.
Table 172: Useful Life proposed by GIAL and the Authority
Useful life
Useful life proposed by
Asset Class submitted by
the Authority*
GIAL*
Terminal Building 25 30
Runway, Taxiway and Apron 20 30
Cargo Building 25 30
Cargo Equipment 8 15
Boundary wall 5 5
Computer Servers, networks, etc. / Software 3 3
Computer End-user devices / IT equipment 3 3
Security equipment 7.5 15
Plant and Machinery 7.5 15
Other buildings 30 30
Access road 10 10
Furniture & fixtures 7 7
Vehicles 5 8
Office Equipment 5 5
*All numbers in years
17.1.12 Accordingly, the depreciation on Aeronautical assets of ₹ 0.33 crores as submitted by GIAL has
been revised (post reclassification) to ₹ 0.32 crores, thereby resulting a reduction in depreciation
of ₹ 0.01 crores. The following table illustrates the impact on depreciation due to reclassification
adjustments in Asset Addition/WIP Capitalization values of GIAL from COD till March 31, 2022.
Consultation Paper No. 01/2024-25 Page 229 of 254ANNEXURES
Table 173: Impact on Depreciation due to Reclassification of Asset Additions by GIAL and
Revised Useful Life as per the Authority from COD till March 31, 2022
(₹ crores)
Asset Category as per MYTP Reclassification Impact
Furniture & fixtures (0.0001)
IT equipment (0.008)
Office equipment (0.002)
Grand Total (0.010)
17.1.13 Adjustments were also made in the depreciation of the assets handed over to GIAL by AAI for
the post COD period, as per the asset reclassification carried out in this Study and the revised
useful life as per Table 114. The total impact on depreciation in post COD period due to
reclassification of assets has been summarized in the table below.
Table 174: Total Impact on Depreciation due to Reclassification of Asset Additions from COD
till March 31, 2022
(₹ crores)
Particulars Values Impact
Depreciation on pre-COD assets as per GIAL 16.50
Depreciation on pre-COD assets after reclassification as per Study 8.83
Impact on Depreciation for pre-COD Assets due to reclassification (7.67)
Depreciation on post-COD assets as per GIAL 0.33
Depreciation on post-COD assets after reclassification 0.32
Impact on Depreciation for post-COD Assets due to reclassification and (0.01)
revised useful life as per Study
Total Impact on Depreciation for all Assets in post-COD period (7.68)
17.1.14 The Adjusted RAB and Depreciation determined by the Authority for the period from COD till
March 31, 2022, post reclassifications and other adjustments are as follows:
Table 175: Average RAB considered by the Authority from COD till March 31, 2022
(₹ crores)
Particulars Amount
Adjusted RAB as on COD, transferred to Guwahati International Airport Limited (A)* 158.80
Additions to RAB from COD to March 31, 2022, proposed by GIAL (Refer Para 5.4.3) 2.33
(B)
Sub-total (C = A + B) 161.13
Reclassifications on asset additions
Furniture & fixtures (D) (0.002)
IT equipment (E) (0.049)
Office equipment (F) (0.025)
Consultation Paper No. 01/2024-25 Page 230 of 254ANNEXURES
Particulars Amount
Software (G) -
Total reclassifications (H) Sum (D : G) (0.08)
Adjusted RAB (I = C + H) 161.05
Depreciation on Initial RAB from COD to March 31, 2022, proposed by GIAL (J) 16.83
Adjustment in Depreciation for the period from COD to March 31, 2022 (K) (7.68)
Total Adjusted Depreciation for the period from COD to March 31, 2022 (L= J + K) 9.15
Opening RAB as on 1st April’2022 for Third Control Period (M = I – L) 151.90
Average RAB N = (A+M)/2 155.35
* includes Aeronautical assets worth ₹ 155.64 crores and ANS assets worth ₹ 3.16 crores determined as per Study
of Asset Allocation for Lokpriya Bordoloi International Airport, Guwahati.
17.1.15 Based on the revision of asset allocation methodology adopted for assets of LGBIA, a revision in
the Aeronautical Gross block has been proposed. The year-wise revised value of assets from FY
2016-17 to FY 2020-21 has been summarized in the tables below:
Table 176: Revised Gross block of Assets up to COD as per the Study report
(₹ in crores)
FY22
Particulars FY17 FY18 FY19 FY20 FY21
(up to COD)
Aeronautical Gross block (opening) 183.50 273.19 281.84 364.58 395.84 400.19
(A)
Non-aeronautical Gross block 23.00 25.39 25.53 27.04 27.64 27.65
(opening) (B)
Left Out Assets-Aero (C) 87.88 - - - - -
Left Out Assets-Non-Aero (D) 1.88 - - - - -
Aeronautical Asset Additions (E)* 9.74 8.73 82.74 31.26 4.35 10.26
Aeronautical Asset Disposals (F)* 7.92 0.08 0.00 0.00 0.00 0.00
Non-Aeronautical Asset Addition 0.50 0.14 1.51 0.60 0.01 0.39
(G)#
Aeronautical Gross block (closing) 273.19 281.84 364.58 395.84 400.19 410.44
(H=A+C+E-F)
Non-aeronautical Gross block 25.39 25.53 27.04 27.64 27.65 28.04
(closing) (I=B+D+G)
Total Gross block (J = H + I) 298.58 307.37 391.61 423.48 427.84 438.48
Aeronautical Ratio - (H/J) 91.50% 91.70% 93.10% 93.47% 93.54% 93.61%
Non-Aeronautical ratio - (I/J) 8.50% 8.30% 6.90% 6.53% 6.46% 6.39%
* Refer Study of Asset Allocation for Lokpriya Bordoloi International Airport, Guwahati
# Refer Annexure V
Table 177: Revised Gross block of Assets as on March 31, 2022 as per the Study
(₹ in crores)
ANS assets Additions
Assets transferred Total as on
Particulars transferred – Post
from AAI on COD March 31, 2022
by AAI COD
Aeronautical Gross block (A) 155.64 3.16 2.25 161.05
Non-aeronautical Gross block (B) 7.70 0.08 7.78
Total Gross block (C = A + B) 168.83
Aeronautical ratio 95.39%
Non-Aeronautical ratio 4.61%
Consultation Paper No. 01/2024-25 Page 231 of 254ANNEXURES
17.1.16 The Gross block of Aeronautical and Non-aeronautical assets as per AAI’s submission, as on
October 8, 2021 was ₹ 412.17 crores and ₹ 25.47 crores, respectively. The revised Aeronautical
and Non-aeronautical Gross block as on October 8, 2021 for AAI, after the proposed adjustments
and reclassifications as per the Study, are ₹ 410.44 crores and 28.04 crores, respectively.
17.1.17 The Net block of the Aeronautical and Non-aeronautical assets transferred by AAI to GIAL as on
COD, were considered as addition to the Gross block as on COD for GIAL as per the Study. The
Gross Aeronautical assets and Non-aeronautical assets as on March 31, 2022 has been determined
as ₹ 161.05 crores and 7.78 crores, respectively.
Consultation Paper No. 01/2024-25 Page 232 of 254ANNEXURES
17.2 Annexure 2 - Summary of study on efficient Operation and Maintenance expenses
Background
17.2.1 Establishing efficient Operation and Maintenance (O&M) expenses is an essential component in tariff
determination for Aeronautical services. The allocation of O&M expenses as Aeronautical and Non-
aeronautical expenses depends on the nature of expenses, type of assets which they service, the
business function which they are deployed for, the end-user that benefits or avails services from those
expenses, and reasonableness of the quantum of such expenses.
17.2.2 Towards this objective, AERA has decided to conduct an independent study on efficient Operation
and Maintenance expenses, and their allocation as Aeronautical and Non-aeronautical components in
respect of O&M expenses appearing in the extract of the audited trial balance of AAI for the period
from FY 2016-17 to October 7, 2021 and the audited financial statements of Guwahati International
Airport Limited for the period from October 8, 2021 (Commercial Operation Date (COD)) to March
31, 2022, and the True up workings as submitted to AERA by AAI up to October 7, 2021 and by the
GIAL up to March 31, 2022.
Comparison of Aeronautical O&M expenses approved as per Tariff Order for the Second
Control Period vis-à-vis the actual expenses incurred by AAI and GIAL
17.2.3. The Study compared the Aeronautical O&M expenses as per approved tariff order of Second Control
Period (SCP) with actual expenses incurred by both AAI and GIAL and analyzed the reasons for
deviation in such O&M expenses. The details of O&M expenses approved as per tariff order and the
actuals incurred during the Second Control Period, are shown in the table below:
Table 178: Aeronautical O&M expenses of LGBIA for the Second Control Period - Approved vs.
Actuals
(₹ in crores)
Particulars O&M Actuals as Variance Variance Total Actuals as Total
Expenses per true-up (D = B-A) (%) Actuals as per true-up Actuals as
as per submission (E = D / A) per true-up submission per true-up
Tariff of AAI up to submission of GIAL submission
Order for FY 21 of AAI till post COD of AAI and
SCP (B) COD* till Mar’22 GIAL for
(A) SCP till
Mar ’22
Employee
160.5 131.82 -28.68 -18% 146.62 18.91 165.53
benefit expenses
Administrative
& Other 90.1 201.82 111.72 124% 250.25 16.53 266.78
expenses
Repairs &
Maintenance 89.0 62.42 -26.58 -30% 69.98 9.71 79.69
expenses
Utility
(Operating) 22.0 26.81 4.81 22% 29.81 2.62 32.44
expenses
Other outflows 2.0 3.44 1.44 72% 3.52 0.09 3.62
Total
Aeronautical
O&M expense 363.6 426.31 62.51 17% 500.19 47.87 548.06
for Second
Control Period
Consultation Paper No. 01/2024-25 Page 233 of 254ANNEXURES
17.2.4. The Aeronautical O&M expenses approved by the Authority in the Tariff Order for Second Control
Period amounted to ₹ 363.80 crores. The actual Aeronautical O&M expenses incurred as per AAI’s
True up submission aggregates to ₹ 426.31 crores for Second Control Period. Aeronautical O&M
expenses incurred by AAI in FY22 till COD stood at ₹ 73.89 crores. Thereby, the total Aeronautical
O&M Expense incurred by AAI in SCP till COD amounted to ₹ 500.19 crores. The total Aeronautical
O&M expenses as per GIAL’s True up submission for the period from post COD i.e., October 8. 2021
to March 31, 2022, aggregates to ₹ 47.87 crores. The total Aeronautical O&M expenses of ₹ 548.06
crores incurred as per true up submissions for the Second Control Period excluding FY2021-22, is
drastically higher than the amount of ₹ 363.80 crores approved in the Tariff Order, indicating a deviation
of 51%.
i. It is noted that the major reason for the overall deviation of 51% in the total Aeronautical O&M
expenses for the Second Control period, is the increase in the actual CHQ & RHQ expenses
incurred by AAI which is higher by 155% till FY21.
ii. On an overall basis, the actual employee benefit expenses for second control period are well within
the range of values approved by AERA in the Tariff Order for the Second Control Period.
Therefore, the employee expenses of AAI for the Second Control Period seem to be reasonable as
part of this Study.
iii. The A&G expenses incurred during the period significantly exceeded the projections of the Tariff
Order. This expense has been examined in detail, and the underlying factors have been
rationalized.
iv. The Utility expenses expenses have exceeded the projections, primarily due to the rise in electricity
expenses. Electricity expenses have increased since power tariff is determined by third-party utility
vendors. Given the criticality of these expenditures to the core operations and the external factors
influencing them, the actual utility expenses incurred has been considered reasonable for the
purposes of this study.
v. Repairs & Maintenance expenses, does not include any runway recarpeting expenses and are
significantly lower compared to the corresponding expense approved by the Authority for the
Second Control Period and hence is proposed to be allowed by the Study.
Principles for segregation of costs
17.2.5 This Study segregates the O&M expenses of LGBIA into the following:
• Aeronautical expenses: Expenses which are incurred for operation and maintenance of
Aeronautical assets have been categorized as Aeronautical expenses.
• Non-aeronautical expenses: Expenses which are incurred for operation and maintenance of
non-aeronautical assets have been categorized as Non-aeronautical expenses.
• Common expenses: Expenses for which the benefits or use cannot be exclusively linked to
either Aeronautical or Non-aeronautical activities have been segregated as Common expenses.
Expenses primarily incurred for provision of Aeronautical services but are also used for
provision of non-aeronautical services are segregated as Common Expenses. Expenses which
are used for general corporate purposes including legal, administration, and management affairs
are treated as Common Expenses.
17.2.6 The Segregation of the various O&M expenses as per AAI’s submission is as below:
Consultation Paper No. 01/2024-25 Page 234 of 254ANNEXURES
Table 179: Segregation ratio for O&M expenses as per AAI’s submission
Particulars FY 2016- FY 2017- FY 2018- FY 2019- FY FY 2021-
17 18 19 20 2020-21 22 till
COD
Employee Ratio 98.65:1.35 98.08:1.9 98.84:1.1 98.10:1.9 98.03:1.9 98.60:1.4
(Aeronautical : Non- 2 6 0 7 0
aeronautical)
Year-wise specific allocation 95:5 95:5 95:5 95:5 95:5 95:5
ratio for CHQ & RHQ
allocation of Admin Expenses
(Aeronautical : Non-
aeronautical)
Year-wise specific allocation 98.65:1.35 98.08:1.9 98.84:1.1 98.10:1.9 98.03:1.9 98.60:1.4
ratio for CHQ allocation of 2 6 0 7 0
Retirement Benefits
(Aeronautical : Non-
aeronautical)
Terminal Building ratio 89.67:10.3 90.5:9.5 90.6:9.4 92.32:7.6 92.81:7.1 92.58:7.4
(Aeronautical : Non- 3 8 9 2
aeronautical)
Electricity ratio 84.79: 84.76: 84.74: 84.77: 84.75: 84.52:
(Aeronautical : ANS : Non- 15.00: 15.05: 15.08: 15.08: 15.05: 15.19:
aeronautical) 0.21 0.19 0.18 0.16 0.20 0.29
Staff Quarters ratio 49.11: 52.94: 60.83: 65.81: 64.58: 59.21:
(Aeronautical : ANS : Non- 50.89: 46.08: 38.33: 33.33: 35.42: 40.79:
aeronautical) 0 0.98 0.83 0.85 0 0
Vehicle Ratio 74.07: 75.86: 77.14: 82.6 : 83.33: 80.00:
(Aeronautical : ANS : Non- 18.52: 17.24: 17.14: 13.04: 12.50: 15.00:
aeronautical) 7.41 6.90 5.71 4.35 4.17 5.00
Details of adjustment to O&M expenses
17.2.7 The study on the basis of the expense classification and principles of segregation adopted, as can be
seen in the above paragraphs, has considered re-segregation of Operation and Maintenance expenses
to determine Aeronautical O&M costs. The study has proposed the following ratios:
Table 180: Revised segregation ratio for O&M expenses as per the study
FY’22-
Particulars FY’17 FY’18 FY’19 FY’20 FY’21
COD
Terminal Building Ratio 89.02% 89.02% 89.02% 89.02% 89.02% 89.02%
Gross Fixed Assets ratio 91.50% 91.70% 93.10% 93.47% 93.54% 93.61%
Employee Ratio 90.35% 89.53% 91.56% 90.59% 90.59% 90.10%
17.2.8 Based on the reclassification and change in allocation ratio, the Study has proposed the revised
Aeronautical O&M expenses for the period FY 2016-17 up to COD as summarized in the table below:
Consultation Paper No. 01/2024-25 Page 235 of 254ANNEXURES
Table 181: O&M expenses submitted by AAI and as per Study for the SCP and pre-COD Period
(₹ in crores)
O&M expenses FY FY FY FY FY Total FY Total
2016-17 2017- 2018- 2019-20 2020-21 till 2021- till
18 19 FY21
22* COD
O&M Expenses as per AAI
Employee benefit / 16.64 24.02 32.05 32.42 26.69 131.82 14.80 146.62
Payroll
Administrative and 13.95 35.45 42.92 59.68 49.81 201.82 48.43 250.25
General
Repairs & 7.72 15.56 12.90 13.97 12.26 62.42 7.57 69.98
Maintenance
Utilities & 4.46 5.03 6.05 6.16 5.12 26.81 3.00 29.81
Outsourcing
Other Outflows 0.73 0.91 0.78 0.94 0.09 3.44 0.08 3.52
Total 43.49 80.97 94.70 113.17 93.97 426.29 73.88 500.19
O&M Expenses as per Study
Employee benefit / 16.62 24.00 32.05 32.37 26.62 131.66 14.78 146.44
Payroll
Administrative and 23.56 29.71 35.36 52.05 44.03 184.70 24.99 209.69
General
Repairs & 7.63 15.37 12.82 13.81 12.03 61.66 7.33 68.99
Maintenance
Utilities & 4.45 5.02 6.03 6.12 5.10 26.72 2.99 29.71
Outsourcing
Other Outflows 0.73 0.91 0.78 0.94 0.09 3.44 0.08 3.52
Total 52.97 75.01 87.03 105.28 87.86 408.16 50.17 458.34
Impact 9.48 (5.96) (7.67) (7.89) (6.11) (18.13) (23.71) (41.84)
* Up to COD (October 8, 2021)
17.2.9 The table below provides a summary of submission of GIAL, revision of OPEX as part of this study
and net impact for the period 8th October 2021 to 31st March 2022:
Table 182: Impact of proposed reallocation of GIAL’s Aeronautical O&M expenses
(₹ in crores)
Particular GIAL Submission Study Net Impact
Total Aero % Aero Allocation Aero
Expense Expense Basis Expense
Manpower expenses - AAI 14.19 100% 14.19 Common (ER- 14.08 (0.11)
employees AAI)
Manpower expenses - 4.72 100% 4.72 Common (ER- 4.48 (0.24)
GIAL employees GIAL)
Utility expenses 2.62 100% 2.62 Aeronautical 2.62 0.00
IT expenses 1.49 100% 1.49 Common (ER- 1.41 (0.08)
GIAL)
Rates & taxes 0.32 100% 0.32 Common (GB) 0.31 (0.01)
Security expenses 1.37 100% 1.37 Aeronautical 1.37 0.00
Corporate Allocation 4.24 100% 4.24 Common (ER- 4.00 (0.24)
GIAL)
Less: Legal
Expenses
Consultation Paper No. 01/2024-25 Page 236 of 254ANNEXURES
Particular GIAL Submission Study Net Impact
Total Aero % Aero Allocation Aero
Expense Expense Basis Expense
Administrative Expenses - 0.09 100% 0.09 Aeronautical 0.09 0.00
Collection Charges on UDF
Administrative Expenses - 3.58 100% 3.58 Common 3.42 (0.16)
Others (TB/ER/GB)
Insurance 0.99 100% 0.99 Common (GB) 0.94 (0.05)
R&M 9.71 100% 9.71 Common 9.29 (0.42)
(TB/ER/GB)
Others 2.83 100% 2.83 Common (TB) 2.52 (0.31)
Independent Engineer Fees 1.69 100% 1.69 Aeronautical 1.69 0.00
Total 47.87 47.87 46.22 (1.65)
TB – Terminal Building Ratio
ER – Employee Ratio
GB – Gross Block Ratio
Rationalisation of O&M expenses
17.2.10 Based on the Internal Benchmarking analysis, it was observed that the Operation and Maintenance
expenses for LGBIA for the period from FY 2017-18 to FY 2020-21 are higher than normal operating
efficiency levels, as mentioned below:
i. The key reason of such higher growth in O&M expenses is mainly due to pay scale revision and arrears
disbursement to Guwahati Airport employees as per 7th Pay Commission report and increase in
CHQ/RHQ allocation due to pay revision, inflation, and increase in revenues of Guwahati station.
17.2.11 It is proposed to rationalize such expenses to determine the efficient Aeronautical O&M expenses for
the period from FY 2016-17 to FY 2021-22.
Efficient Aeronautical O&M expenses
17.2.12 The year-wise summary of the reclassification and other adjustments to O&M expenses is provided
in the table below.
Table 183: Year-wise summary of reclassification and other adjustments to Aero O&M expenses
(₹ crores)
Particulars FY FY FY FY FY FY Total FY Total
2016-17 2017-18 2018-19 2019-20 2020-21 2021- till 2021- till
22* COD 22# Mar’22
O&M expenses
as per true up
submission of 43.50 80.96 94.70 113.17 93.98 73.89 500.19 47.87 548.06
AAI and GIAL
(A)
O&M expenses as per Study
Employee 16.62 24.00 32.05 32.37 26.62 14.78 146.44 18.56 165.00
benefit expenses
Administrative 23.56 29.71 35.36 52.05 44.03 24.99 209.69 13.20 222.89
and other
expenses
Consultation Paper No. 01/2024-25 Page 237 of 254ANNEXURES
Particulars FY FY FY FY FY FY Total FY Total
2016-17 2017-18 2018-19 2019-20 2020-21 2021- till 2021- till
22* COD 22# Mar’22
Utilities and 4.45 5.02 6.03 6.12 5.10 2.99 29.71 2.62 32.33
Outsourcing
expenses
Repairs & 7.63 15.37 12.82 13.81 12.03 7.33 68.99 9.29 78.28
Maintenance
expenses
0.73 0.91 0.78 0.94 0.09 0.08 3.52 2.55 6.07
Other Outflows
52.99 75.01 87.04 105.29 87.87 50.17 458.34 46.22 504.57
Total (B)
Impact (B - A) 9.49 (5.95) (7.66) (7.88) (6.11) (23.72) (41.84) (1.65) (43.49)
* Up to the date of COD (October 8, 2021)
# From COD till March 31. 2022
17.2.13 Based on the reallocation of the O&M expenses, the downward adjustment in the Aeronautical O&M
expenses for the period from FY2016-17 to FY2020-21 is ₹ 41.84 crores, and for the period from
April 01, 2021 till October 8, 2021 (COD) is ₹ 1.65 crores. The total downward adjustment in the
Aeronautical O&M expenses for the period from FY2016-17 till COD is ₹ 43.49 crores and the
reallocated Aeronautical O&M expenses for the period FY 2016-17 to October 8, 2021, has been
determined as ₹ 504.57 crores. The Aeronautical O&M expenses for the period from FY 2016-17 till
COD is reduced by 7.93%.
17.2.14 As per the submission of GIAL the total Aeronautical O&M expenses for the period from COD to
March 31, 2022, was ₹ 47.87 crores. Based on the reallocation of the O&M expenses, the downward
adjustment in the Aeronautical O&M expenses for the aforesaid period is ₹ 1.65 crores and the
reallocated Aeronautical O&M expenses (prior to rationalization) for the period from COD to March
31, 2022 has been determined as ₹ 46.22 crores. The Aeronautical O&M expenses for the period from
COD up to March 31, 2022 is reduced by 3.45%.
Consultation Paper No. 01/2024-25 Page 238 of 254ANNEXURES
17.3 Annexure 3 – Clauses of the Concession Agreement entered between AAI and GIAL
17.3.1. The Airports Authority of India (AAI) entered into a Concession Agreement with Guwahati
International Airport Limited (GIAL) on January 19, 2021, for the Operation, Management and
Development of LGBIA for a period of 50 years from the Commercial Operation Date (COD)
i.e., October 8, 2021 in accordance with the terms and conditions mentioned in the Concession
Agreement.
17.3.2. The relevant Clause of the Concession Agreement may be read as under:
3.1.1. “Subject to and in accordance with the provisions of this Agreement, Applicable
Laws and the Applicable Permits, the Authority hereby grants to the
Concessionaire, the concession set forth herein including the exclusive right,
lease and authority to operate, manage and develop the Airport
("Concession") for a period of 50 (fifty) years commencing from the COD, and
the Concessionaire hereby accepts the Concession and agrees to implement the
Project subject to and in accordance with the terms and conditions set forth
herein”.
3.1.2. Subject to and in accordance with the provisions of this Agreement, the
Authority, Applicable Laws and the Applicable Permits, the Concession hereby
granted shall oblige or entitle (as the case may be) the Concessionaire to:
(a) the Right of Way, access and lease to the Site for the purpose of and to the
extent conferred by the provisions of this Agreement.
(b) finance the development and expansion of the Airport.
(c) operate, maintain and manage the Airport and regulate the use thereof by
third parties.
(d) demand, collect and appropriate Fee from Users liable for payment of Fee for
using the Airport or any part thereof and refuse entry of any such User if
the Fee due is not paid.
(e) perform and fulfil all of the Concessionaire' s obligations under and in
accordance with this Agreement.
(f) save as otherwise expressly provided in this Agreement, bear and pay all
costs, expenses, Taxes and charges in connection with or incidental to the
performance of the obligations of the Concessionaire under this
Agreement; and
(g) neither assign, transfer or create any lien or encumbrance on this
Agreement, or the Concession hereby granted or on the whole or any part of
the Airport nor trans fer, or part possession thereof, save and except as
expressly permitted by this Agreement or the Substitution Agreement.
27.1.1. Subject to Clause 27.3, the Concessionaire agrees to pay to the Authority, during
the Concession Period, a monthly concession fee calculated as follows (the
"Monthly Concession Fee"):
Consultation Paper No. 01/2024-25 Page 239 of 254ANNEXURES
Where:
"Per Passenger Fee for Domestic Passengers" means ₹ 160 (Rupees One
Hundred and Sixty), as may be revised pursuant to Clause 27.3;
"Per Passenger Fee for International Passengers" means 2 (two) times the Per
Passenger Fee for Domestic Passengers;
"Domestic Passenger Throughput" for any month shall mean the total domestic
Passenger Traffic (embarking and disembarking passengers) as provided by the
Authority by the 7th (seventh) day of the subsequent month in the form and
manner as may be specified by the Authority from time to time.
"International Passenger Throughput" for any month shall mean the total
International Passenger Traffic (embarking and disembarking passengers) as
provided by the Authority by the 7th (seventh) day of the subsequent month in the
form and manner as may be specified by the Authority from time to time.
Provided further that, in the first and that last month of the Concession Period,the
International Passenger Throughput and Domestic Passenger Throughput shall
be pro-rated by the number of the days in such months as reckoned with respect
to the COD or Transfer Date, as relevant.
27.1.2. The Monthly Concession Fee paid/ payable by the Concessionaire to the Authority
under
and pursuant to the terms of this Agreement shall not be included as a part of
costs for provision of Aeronautical Services and no pass-through would be
available in relation to the same.
20.1.1 The Concessionaire acknowledges and agrees that only the Designated GOI
Agencies are authorized to undertake the following services ("Reserved
Services") at the Airport:
(a) CNS/ATM Services;
(b) security services;
(c) meteorological services;
(d) mandatory health services;
(e) customs control;
(f) immigration services;
(g) quarantine services;
(h) any other services, as may be notified by GOI;
Provided that, subject to the Applicable Laws and the Applicable Permits,
Consultation Paper No. 01/2024-25 Page 240 of 254ANNEXURES
nothing in this Agreement shall restrict the Authority from requiring the
Concessionaire to undertake any or all of the Reserved Services on such terms
and conditions as may be mutually agreed between the Parties.
17.3.3. The relevant portion of Schedule T which pertains to the list of capital expenditure contracts
already awarded by AAI and handed over to GIAL and Schedule U which pertains to the list of
capital expenditure projects proposed / planned by AAI but not yet awarded and forming part of
the terms of the Concession Agreement are given below:
SCHEDULE T
EXISTING CONTRACTS
Consultation Paper No. 01/2024-25 Page 241 of 254ANNEXURES
OPERATIONS CONTRACTS
MAINTENANCE CONTRACTS
Consultation Paper No. 01/2024-25 Page 242 of 254ANNEXURES
Consultation Paper No. 01/2024-25 Page 243 of 254ANNEXURES
DETAILS OF ONGOING CAPITAL WORK-IN-PROGRESS AND THEIR LIKELY
POSITION IN 30.06.2019 AT THE AIRPORT
Consultation Paper No. 01/2024-25 Page 244 of 254ANNEXURES
Consultation Paper No. 01/2024-25 Page 245 of 254ANNEXURES
OTHER WORKS (CIVIL)
LAND LEASES AT THE AIRPORT
Consultation Paper No. 01/2024-25 Page 246 of 254ANNEXURES
SCHEDULE U
List of Works Proposed by the Authority:
Consultation Paper No. 01/2024-25 Page 247 of 254ANNEXURES
17.3.4. Carved-out Area - Annexure IV of Schedule A to the Concession Agreement provides details
of the carved-out area for Cargo Terminal.
Annex IV
(Schedule A)
(See Clause 10.1)
Carved Out Assets and Areas
It is clarified that the Site and Project Assets shall not include the following:
SL. ASSET AREA OF LAND
NO. IN SQ.M. (Approx.)
1. ATC TOWER 1,650
2. AAI OFFICES (OLD AAI OFFICE + INTEGRATED 21,00
OFFICE COMPLEX)
3. IOCL STAFF QUARTERS 15,100
4. MET OFFICE 6,100
5. TEMPORARY CARGO SHED 850
6. COMMON USE DOMESTIC CARGO TERMINAL 2,400
(CUDCT)
7. PROPOSED CUDCT -2 COMPLEX 6,000
8. AIDC CENTRE FOR PERISHABLE CARGO (CPC) 4,050
(Assam Industrial Development Corp.)
9. ADDITONAL LAND REQUIRED FOR CPC 4,050
10. EXISTING AIRLINE CARGO 1,300
11. MSSR (RADAR) 3,400
12. PROPOSED ATC CUM TECHNICAL BLOCK 8,150
13. PROPOSED AAI COLONY 40,500
TOTAL 1,14,750 Sq.m. (28.40 Acres.)
17.3.5. Clause 19.4.1. of the Concession Agreement relating to obligations of GIAL towards cargo
facilities is reproduced below-
(a) The Concessionaire shall upgrade, develop, operate and maintain the Cargo Facilities
in accordance with the provisions of this Agreement, Applicable Laws, Applicable
Permits, relevant ICAO Documents and Annexes and Good industry Practice.
(b) Notwithstanding anything to the contrary provided in this Clause 19.4 and Clause 23.5,
it is clarified that, where Cargo Facilities have been earmarked for AAICLAS in
Schedule A (i) the Concessionaire will not be responsible for operations, development,
maintenance and management thereof, nor shall the Concessionaire be bound by the
obligations set out elsewhere in this Clause 19.4; and (ii) AAICLAS shall be granted
access to the airside by the Concessionaire free of cost.
(c) It is further clarified that, where Cargo Facilities have been earmarked for AAICLAS
Consultation Paper No. 01/2024-25 Page 248 of 254ANNEXURES
in Schedule A, there shall be no restriction on the upgradation and/ or development of
Cargo Facilities by the Concessionaire, including on grounds of quantum of cargo
volumes at the Airport, business potential or impact of such additional facilities on
Cargo Facilities earmarked for AAICLAS.
17.3.6. Clause 19.2. relating to GIAL’s obligation towards Ground Handling Services is given below:
“The Concessionaire shall provide or cause to be provided as per Applicable Laws and Good
Industry Practice, at its own cost and expense, the infrastructure required for operation of
the ground handling services required at the Airport for and in respect of the Users, like
aircrafts, passengers and cargo, which shall include ramp handling, traffic handling, aircraft
handling, aircraft cleaning, loading and unloading ("Ground Handling Services"). Such
infrastructure shall include luggage conveyor belts, computer terminals, information
technology backbone and associated facilities in accordance with the provisions of this
Agreement, Applicable Laws and Good Industry Practice.”
17.3.7. The Clause 19.3. of the Concession Agreement is related to GIAL’s obligations towards
providing aircraft fueling services, which has been reproduced below:
“The Concessionaire shall provide, or cause to be provided, the infrastructure
required for operation of fuelling services on equal access basis for all the aircrafts at
the Airport in a transparent and non-discriminatory manner. Such infrastructure shall
include tank farms and associated facilities in accordance with the provisions of this
Agreement, Applicable Laws and Good Industry Practice.”
17.3.8. As per the Concession Agreement, the Estimated Deemed Initial RAB as on March 31, 2018,
was determined to be ₹ 69 crores, which was due and payable by the Concessionaire to AAI. The
terms of the Concession Agreement also provide for the value of ₹ 69 crores to be subject to
reconciliation, True up and final determination by AERA. The extract of the relevant clauses
from the Concession Agreement shall be read as under:
Clause 28.11.3 states that:
a) It is agreed by the Parties that the Concessionaire shall be liable to pay to the Authority
an amount equivalent to the investments made by the Authority in the Aeronautical assets
as of the COD and considered by the Regulator as part of the Regulatory Asset Base,
subject to requisite reconciliation, true-up and final determination by the Regulator of the
quantum of such investment (“Deemed Initial RAB”).
b) The estimated depreciated value of investments made by the Authority in the Aeronautical
assets at the Airport as on March 31, 2018, is ₹ 69,00,00,000 (Rupees Sixty Nine Crore)
(“Estimated Deemed Initial RAB”). It is agreed by the Parties that the Estimated Deemed
Initial RAB shall be due and payable by the Concessionaire to the Authority within 90
(ninety) days of COD.
Clause 28.11.4 states that:
Pursuant to the payment of the Estimated Deemed Initial RAB, and upon the reconciliation,
true-up and final determination by the Regulator of the quantum of the investment under
28.11.3(a). any surplus or deficit in the Estimated Deemed Initial RAB with respect to the
Deemed Initial RAB shall be adjusted as part of the Balancing Payment that becomes due and
payable as per Clause 31.4 after the expiry of 15 (fifteen) days from such final determination
by the Regulator, with due adjustment for the following ("Adjusted Deemed Initial RAB'"):
Consultation Paper No. 01/2024-25 Page 249 of 254ANNEXURES
a) reduced to the extent of over-recoveries, if any, of Aeronautical Revenues by the
Authority until the COD, that the Regulator would provide for as a downward
adjustment while determining Aeronautical Charges for the next Control Period;
or
b) increased to the extent of under-recoveries, if any, of Aeronautical Revenues by the
Authority until the COD, that the Regulator would provide for as an upward adjustment
while determining Aeronautical Charges for the next Control Period.
The amount(s) to be paid by the Authority or Concessionaire shall be the present value of
Adjusted Deemed Initial RAB calculated using the fair rate of return as determined by the
Regulator for the time period from the COD to the date of actual payment of the Adjusted
Deemed Initial RAB.
Clause 28.11.5 states that:
Upon reimbursement of such amount by the Concessionaire to the Authority, the Deemed
Initial RAB will, in addition to the investments made by the Concessionaire, be considered for
the purpose of determination of Aeronautical Charges by the Regulator.
a) The Authority undertakes to make any required supporting submissions to the Regulator
towards such consideration and determination by the Regulator.
b) The Parties shall submit to and request the Regulator to separately identify the Deemed
Initial RAB in future determinations of Aeronautical Charges with regard to consideration
of depreciation, required returns, etc.
17.3.9. Clause 5.1.1 of the Concession Agreement which states that “Subject to and on the terms and
conditions of this Agreement, the Concessionaire shall, at its own cost and expense, procure
finance for and undertake the operations, management and development of the Airport, in
accordance with the provisions of the Applicable Permits, Applicable Laws, this Agreement
and observe, fulfil, comply with and perform all its obligations set out in this Agreement or
arising hereunder”.
17.3.10. The relevant clause (6.4.5) of the Concession Agreement relating to GIAL’s obligation
regarding CWIP handed-over by AAI as on COD and as set forth in Schedule T, has been
reproduced below-
“Notwithstanding anything to the contrary in this Clause 6.4, the Concessionaire shall
be liable to pay to the Authority such amounts as may have been incurred by the
Authority as on the COD in respect of the contracts relating to works-in-progress as
have been set forth in Schedule T. Such amounts shall be intimated by the Authority
with supporting documents and details within 30 (thirty) days of COD and shall be due
and payable by the Concessionaire the Authority within a period of 90 (ninety) days
thereon.
The Parties shall constitute a committee comprising representatives of the
Concessionaire, Authority and each of the counterparties under such contracts, which
committee shall be responsible for: (a) facilitating any discussions and/ or interactions
amongst AAI, the Concessionaire and the counterparties under such contracts,
including in respect of any modifications to the works and (b) coordinating,
facilitating, and monitoring the progress of such works-in-progress. The
Consultation Paper No. 01/2024-25 Page 250 of 254ANNEXURES
Concessionaire shall be responsible to incur any additional cost towards completion of
such work-in-progress assets after COD.
Upon reimbursement by the Concessionaire to the Authority, of amounts as may have
been incurred by the Authority as on the COD for such work-in-progress assets as
provided for above, and completion of such works-in-progress by the Concessionaire,
such works-in-progress assets shall form part of the Airport.
The amounts reimbursed by the Concessionaire to the Authority and additional
amounts incurred by the Concessionaire for completion of such work-in-progress
assets shall be considered as investments made by the Concessionaire in creation of
such assets for the purpose of determination of Aeronautical Charges by the Regulator. In
the event that any part of the amounts reimbursed by the Concessionaire to the
Authority pursuant to this Clause 6.4.5 are not considered for pass-through by the
Regulator due to any act or omission on the part of the Authority, the adjustment
towards any differences in the amounts reimbursed by the Concessionaire to the
Authority and the amounts considered for pass-through by the Regulator shall be
undertaken as part of the Balancing Payment that becomes due and payable as per
Clause 31.4 immediately after the determination of the Aeronautical Charges by the
Regulator.”
17.3.11. The relevant clause 4.1.3. (h) of the Concession Agreement relating to GIAL’s obligation
regarding Conditions Precedent required to be satisfied within 180 days of the agreement
relating to works proposed by AAI and as set forth in Schedule U, has been reproduced below-
Except as may have been specifically otherwise provided in this Agreement, the
Conditions Precedent required to be satisfied by the Concessionaire within a period of
180 (one hundred and eighty) days from the date of this Agreement shall be deemed to
have been fulfilled, when the Concessionaire shall, subject to the satisfaction of the
Authority, have -
(h) delivered to the Authority –
(a) a list of Construction works it proposes to undertake in the first 7 (seven)
Concession years having due regard to the works:
a. Currently being implemented by the Authority; and
b. Proposed to be implemented by the Authority as on the date of signing the
Agreement and (as set forth in Schedule U),
(b) the scheduled date for completion of such Construction works.
17.3.12. The relevant Clauses relating to the Independent Engineer’s appointment, duties & functions
and remuneration are reproduced below:
Clause 24.1 Appointment of Independent Engineer
24.1.1 The Authority (AAI) and the Concessionaire shall appoint a consulting
engineering firm substantially in accordance with the selection criteria set forth in
Schedule K, to be the independent consultant under this Agreement ("Independent
Engineer"). The Independent Engineer shall be appointed in accordance with the
provisions of Schedule K.
24.1.2 The appointment of the Independent Engineer shall be made within 90 (ninety)
Consultation Paper No. 01/2024-25 Page 251 of 254ANNEXURES
days of the date of execution of this Agreement, and such appointment shall be
valid for a period of 3 (three) years. On the expiry or termination of the said
appointment, the Authority shall appoint an Independent Engineer for a further term
of 3 (three) years in accordance with the provisions of Schedule K, and such
procedure shall be repeated after expiry of each appointment.
Clause 24.2. Duties and Functions
24.2.1 The Independent Engineer shall discharge its duties and functions substantially
in accordance with the terms of reference set forth in Schedule L.
24.2.2 The Independent Engineer shall submit regular periodic reports (at least once
every month) to the Authority in respect of its duties and functions set forth in
Schedule L.
24.2.3 A true copy of all communications sent by the Authority to the Independent
Engineer and by the Independent Engineer to the Authority shall be sent forthwith
by the Independent Engineer to the Concessionaire.
24.2.4 All communications required to be sent by the Independent Engineer to the
Concessionaire shall be undertaken through the Authority.
Clause 24.3 Remuneration
24.3.1 The remuneration, cost and expenses of the Independent Engineer shall be paid by
the Authority, and all such remuneration, cost and expenses shall be reimbursed
by the Concessionaire to the Authority within 15 (fifteen) days of receiving a
statement of expenditure from the Authority. Any amounts paid to the
Independent Engineer shall be considered for a pass-through for the
determination of the Aeronautical Charges by the Regulator.
17.3.13. The relevant Paras relating to Role and functions of the Independent Engineer as stated in Schedule
L of the Concession Agreement are reproduced below:
3. Role and functions of the Independent Engineer
3.1 The role and functions of the Independent Engineer shall include the following:
(a) review of the designs, drawings, and documents as set forth in Paragraph 4.
(b) review, inspection and monitoring of Construction Works as set forth in Paragraph 4.
(c) reviewing and witnessing the Tests on completion of construction and assisting
the Authority in issuing Completion Certificate/ provisional certificate as set
forth in Paragraph 4.
(d) review, inspection and monitoring of O&M as set forth in Paragraph 5.
(e) review, inspection and monitoring of Divestment Requirements as set forth in
Paragraph 6.
(f) determining, as required under the Agreement, the costs of any works or services and/or
their reasonableness.
(g) determining, as required under the Agreement, the period or any extension thereof, for
Consultation Paper No. 01/2024-25 Page 252 of 254ANNEXURES
performing any duty or obligation.
(h) assisting the Parties in resolution of Disputes as set forth in Paragraph 8.
(i) undertaking all other duties and functions in accordance with the Agreement; and
(j) assisting the Concessionaire in determining the Scheduled Completion Dates and Phase
Milestones.
3.2 The Independent Engineer shall discharge its duties in a fair, impartial and efficient
manner, consistent with the highest standards of professional integrity and Good Industry
Practice.
Consultation Paper No. 01/2024-25 Page 253 of 254APPENDICES
18 APPENDICES
I. Appendix I - Study on Allocation of Assets for Lokpriya Gopinath Bordoloi International
Airport, Guwahati (Second Control Period: FY 2016-17 – FY 2020-21 & FY 2021-22)
II. Appendix II – Study on Efficient Operation and Maintenance Expenses for Lokpriya
Gopinath Bordoloi International Airport, Guwahati (Second Control Period: FY 2016-17 –
FY 2020-21 & FY 2021-22)
Consultation Paper No. 01/2024-25 Page 254 of 254