GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 4051
TO BE ANSWERED ON 12.08.2026
PROPOSAL FOR VIZHINJAM PORT TUNNEL RAIL CONNECTIVITY
4051. ADV K. FRANCIS GEORGE:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government has received any proposal from the
Government of Kerala seeking enhancement of the handling capacity of
Vizhinjam International Seaport through tunnel rail connectivity and
augmentation of railway infrastructure and, if so, the details thereof;
(b) whether the Government has examined the proposal for strengthening
rail connectivity to Vizhinjam Port including construction of additional
rail lines and development of operation and maintenance infrastructure
and, if so, the details thereof;
(c) whether any Central financial assistance has been sanctioned/proposed
for the said project and if so, the details thereof and if not, the reasons
for delay; and
(d) the details of the time-frame within which the Government proposes to
take a final decision on the proposal and commence implementation of
the rail connectivity project to the said Port?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Rail connectivity to Vizhinjam International Seaport is under
execution to provide seamless integration of the Port with the Indian
Railways network and to strengthen multimodal logistics handling
capabilities of the Indian Railways as well as the port. The 10.7 km rail link
will connect Vizhinjam International Seaport with Balaramapuram (BRAM)
Station on the Southern Railway network.
Page 1 of 2
§The project is being developed at a cost of ₹1,482.92 crore under the
Public-Private-Partnership (PPP) policy of Ministry of Railways with an
agreement signed between Southern Railways and Vizhinjam International
Seaport Limited (VISL), a Special Purpose Vehicle of the Government of
Kerala. Under the provisions of this agreement, VISL undertakes
construction and maintenance of the line under Indian Railways’
supervision, while Indian Railways is responsible for train operations and
control of movements.
The land acquisition is being done by the State Government. The final
timelines of the project will depend on the full possession of land, followed
by execution undertaken by VISL.
*****