See Full Document Text
F.No.2/12/2024-PIU
Government of India
Ministry of Finance
Department of Economic Affairs
Infrastructure Finance Secretariat
ISD Division
(PIU)
STC Building, Janpath, New Delhi
Dated: 6" June 2025
Record of Discussion
Subject: Record of Discussion of 128* meeting of the PPPAC for considering the
proposal, ‘Development and Maintenance of Land to be created in Offshore of
Vadhvan Coast by Dredging, Reclamation & Construction of Offshore Protection
Bund for Vadhvan Port on PPP to be executed on Hybrid Annuity Mode’, reg:-
Reference: PPPAC meeting held on 30.04.2025 & 31.05.2025
Sir/Madam,
The undersigned is directed to forward the Record of Discussion of the 126"
Meeting of the PPPAC held on 31.05.2025 under the Chairmanship of Finance
Secretary and Secretary (EA), for information and necessary action.
2. This issues with the approval of the Competent Authority.
Arya Balan Kumari
(Joint Director-PIU)
To,
1. Secretary, Ministry of Ports, Shipping and Waterways, Parivahan Bhavan, 1,
Parliament Street, New Delhi.
2. Secretary, Department of Expenditure, North block, New Delhi-01
3. CEO, NITI Aayog, Yojana Bhawan, New Delhi-01
4. Secretary, Department of Legal Affairs, Shastri Bhawan, New Delhi-01
Copy to:
1. Sr. PPS to Finance Secretary & Secretary (EA)
2. Sr. PPS to OSD, DEA
3. Sr. PPS to AS (IPP)
4. Sr. PPS to JS (ISD)Subject: Record of Discussion of the 128 meeting of the PPPAC for considering
the proposal, ‘Development and Maintenance of Land to be created in
Offshore of Vadhvan Coast by Dredging, Reclamation & Construction
of Offshore Protection Bund for Vadhvan Port on PPP to be executed
on Hybrid Annuity Mode’, reg: -
1. The 128 meeting of the PPPAC was held on 31% May 2025 at 16.00 hrs to consider
the proposal, ‘Development and Maintenance of Land to be created in Offshore of
Vadhvan Coast by Dredging, Reclamation & Construction of Offshore Protection
Bund for Vadhvan Port on PPP to be executed on Hybrid Annuity Mode.’
2. List of attendees is placed in Annexure-l.
3. The basic details of the project are given in the table below:
Table 1° Details of the project
. __| Development and Maintenance of Land to be created in Offshore
Project | of Vadhvan Coast by Dredging, Reclamation & Construction of
S on _ =| Offshore Protection Bund for Vadhvan Port on PPP to be executed
on Hybrid Annuity Mode.
Hybrid Annuity Mode (HAM)
| Ministry of Ports, Shipping & Waterways
Vadhvan Port Project Limited
ce | State: Maharashtra
District: Palghar
| 15 years (including 5 years of construction)
S.No. | Description | Vadhvan Port
_ | Phase-I- 3 years
_ Sora ye k As Dredging of jo The Access Channel shall be dredged to
. . Navigation a minimum level of 20 metres below
Channel Chart Datum.o The turning circle of minimum diameter
of 800 (eight hundred) metres, internal
dredged basin and inner approach
channel shall be dredged to a minimum
level of 17.5 metres below Chart Datum.
oA berth pocket with a minimum level of
19.5 metres below Chart Datum,
extending 65-meter seaward of the
berthing line is required. These depths
shall be the minimum level after the
placing of any bed scour protection.
Reclamation o Dredging of the marine borrow pit area
for extraction of sand from offshore of
Daman.
o Reclamation of offshore land parcel with
sand fill in an area of 850 Hectare in
phases at the level of + 6.8 metres below
Chart Datum excluding the protection
wall and design slopes of the Shore
protection bund.
o The finished reclamation level shall be a
minimum of + 6.8 metres below Chart
Datum.
Construction oAlong the Perimeter, a_ structure to
of Shore protect the bland fill of the land parcel for
1207 Hectares reclaimed land
protection
bund
Common o Earthworks for Sub-base preparation for
Port storage, rail yard and roads (filling to +6.8
m below Chart Datum)
Infrastructure
Phase-ll- 2 years
5. Reclamation o Dredging of the marine borrow pit area
for extraction of sand at offshore of
Daman.
o Reclamation of offshore land parcel with
sand fill in an area of 357 Hectare at thelevel of +6.8 metres below Chart Datum
excluding the protection wall and design
slopes of the Shore protection bund.
o The finished reclamation level shall be a
minimum of +6.8 metres below Chart
Datum.
Common Development of Internal Road
rant o Preparation of sub-base, sub grade over
Infrastructure ; ; :
the reclaimed land including pavements
at the finished level of +7.60mCD as
indicated in drawings.
Development of in-port Common Rail
Yard.
o The development of in-port common rail
yard shall include filling of granular fill,
sub-base and subgrade in layers. The
average finished level shall be a minimum
of +6.8 meter below Chart Datum for a
minimum area of 290 Ha.
Total Civil Construction Cost 18240.55
IC/pre-= operatij ve expenses @ 19% 182.41
of (C)
i; ren: e Cost (1:% of debt 50.44
amount i.e., 5,243.61 crore)
Interest during Construction 522.511
Estimated Project Cost
(A+B+C+D) 18997.90
GST @ 18% on(A+B+C) 3325.57
Estimated Project Cost
including GST (E+F) saean2i3aa.l4ie
Labour Cess (1% of G) 2eoL0Estimated Project Cost
|! including GST and Labour- 22546.70
Cess (G+H)
J Contingenci; es @ 1% - (on Total 182.41
Civil cost)
Ik Escalatii on @5f%e) per Year (on 3099.54
civil cost)
L O&M ones for 10 years (Shore 171.79
Protection Bund)
M Total Capital Cost (l+J+K+L) 26000.44
N Bid Project Cost 20950.00
The location of the reclamation is offshore of the Dahanu Coast and
no land acquisition is required for Port. However, the land requires
for the road and rail connectivity is being acquired by
_| NHAI/MoRTH.
| Project IRR: 12.26%
Equity IRR: 15%
NPV @12% of revenue stream: Rs. 5188.73 crore
NPV@12% of project: Rs. 254.72 crore
Avg. DSCR: 1.40
The project is proposed to be implemented as per Model
_| Concession Agreement dated 09.12.2016 uploaded on MoRTH
website with subsequent amendments issued thereafter till date,
| modified to suit Port Sector.
_| Lowest Bid Project Cost quoted by the bidders
Single Stage with two envelopes
4. The Vadhvan is a greenfield port project, approved by the Union Cabinet in June
2024 with an overall cost of Rs. 76,220 crore. The instant proposal to the tune of
Rs. 18998 crore (Estimated Project Cost) to be executed under a Hybrid Annuity
Mode (HAM) and involves the construction of offshore and nearshore land
reclamation, dredging, shore protection bund and common port infrastructure. The
project consists of two phases, with Phase 1 scheduled for completion within three
years and Phase 2 within two years, totalling a five-year construction period,
followed by ten-year operation and maintenance period. Once the construction of
port is completed, the terminals will be developed on suitable PPP mode.. The instant project was initially appraised by the PPPAC in its meeting held on 30"
April 2025. In the meeting, PPPAC directed MoPSW to provide detailed
explanations on several key aspects such as the basis of cost estimation, rationale
for adopting the HAM model, quality control mechanisms during construction
period, phase-wise responsibilities of the concessionaire, adherence to manual
standards and international benchmarks, etc. MoPSW has given a detailed
response to the queries raised by the PPPAC in its meeting held on 30" April, 2025
which are placed at Annexure II.
. On behalf of the Chair, Joint Director (ISD) welcomed the attendees to the meeting
and requested MoPSW to make a presentation to the PPPAC. With the permission
of the Chair, Chairman, JNPA & MD. Vadhvan Port Project Limited (VPPL) made a
detailed presentation to the PPPAC.
. Vadhvan Port is a deep draft port planned by JNPA (Jawaharlal Nehru Port
Authority) and MMB (Maharashtra Maritime Board) to handle the additional traffic.
This need arises owing to the increasing demand for containers and the capacity
saturation of JNPA and Mumbai port. As per the traffic demand assessment,
Vadhvan Port has potential to handle around 23.2 million twenty-foot equivalent
units (TEUs) of container traffic by FY 2040. In the port, a total of 9 container
terminals with a total quay length of 9,000 meters will be developed, featuring 18
berths and over 100 quay-side gantry cranes (QGCs) to accommodate container
ships with a length overall (LoA) of 350 meters or more. Further, liquid cargo berths,
Ro-Ro facility, general/coastal/breakbulk cargo berths, common railyard, tank farms
and storage areas will also be developed.
. After the presentation, the Chair asked the PPPAC members for their observations.
The representative of DEA, DoE and DoLA supported the proposal and stated that
they have no further comments to offer.
. PD, NITI Aayog raised the following observations:
a) The project is currently divided into two phases. The possibility of combining
the two phases into a single phase may be explored.
b) The road connectivity is very critical for the project and therefore, it should be
made as a condition precedent.10.The Chair raised the following observations:
a) Have the rates used for the cost estimation been properly vetted and verified?
b) The sand borrow pit for the project is identified at Daman offshore,
approximately 60 Km away from project site. What is the reason for selecting
such a distant location?
c) Have the cost of transporting sand from the borrow pit to the project site been
included in the cost estimate?
d) Have appropriate standards and specifications been adopted for dredging and
reclamation, considering the large-scale nature of the work and the need for
timely completion?
e) What techniques and methods will be used during the reclamation work to
prevent settlement issues?
f) Whether any specialized agency shall be deployed to ensure proper execution
of work in accordance with the specification of the standards?
g) Has forest clearance been obtained for the identified quarry sites?
h) What is the status of the road connectivity to the proposed site?
i) What is the rationale for adopting 60:40 cost sharing ratio under the HAM
model?
j) Does the Draft Concession Agreement include provisions for penalties in case
of delay in completion of the project?
k) Why has the sand filling process been divided into phases?
11,MoPSW submitted the following to the queries raised by the PPPAC Members: -
a) The phasing of the project into Phase | and Phase II has been planned based
on the design parameters and the operational requirements of terminal
operators. This sequencing shall ensure optimal utilization of reclaimed land
and aligns with the targeted commissioning of Phase | terminals by 2030.Therefore, the current phased approach is essential to maintain project
efficiency and ensure synchronized development with future concessionaire
activities.
Road connectivity to the site will be provided by the Authority as per Schedule
b)
T of the Draft Concession Agreement which states that the road connectivity to
be within 1.5 years from Appointed Date.
The JNPA has undertaken various port expansion works in last 5 years, which
helped to gain valuable in-house expertise over the years. The rates arrived as
per the DPR by the consultant M/s. Royal Haskoning DHV was also examined
by JNPA. The rates have been adopted from the Schedule of Rates (SOR) of
PWD, State Govt. of Maharashtra. Thereafter, the cost estimates were also
vetted by IIT, Madras for all Marine Works. The rate for dredging & reclamation
from Daman to Vadhvan area is based on the CIRIA method, an international
method, which is also verified by National Technologies Centre for Ports,
Waterways and Coasts (NTCPWC).
The site at Daman was selected based on a detailed field survey, which revealed
extensive sand dunes. Tests confirmed that the sand is suitable for reclamation
due to its silty composition and approximately 6% clay content, providing good
binding and consolidation properties. The site was recommended by ONGC
and IIT Madras. No other high-quality sea sand is available near the proposed
port location. The Ministry of Mines granted permission for sand mining on 24th
February 2025. Dredging and dumping operations will begin only after the
construction of a shore protection wall to prevent sand washout.
The transportation costs are included in the cost estimates to the tune of Rs.
570 per m%. This includes the sand dredging by dredger, transporting &
dumping at site by suitable method and also compaction by standard method.
The standards and specification have been incorporated in the Schedule D of
Draft Concession Agreement for dredging and reclamation work at site.
g)
Initially, sand is deposited into the waterbed, where natural liquefaction
facilitates primary consolidation. Once the area transitions to a dry state, vibro-
compaction is employed to aciieve a compaction level of up to 90%, which
meets the required standards for site handover and subsequent construction.
Additionally, to prevent soil erosion and loss of reclaimed material, a geotextilelayer will be installed. This layer acts as a filtration barrier, effectively retaining
sand particles and preventing washout through the voids in the shore protection
structure.
The external agency in the form of Independent Engineer (IE) shall monitor the
h)
entire project with respect to quality control & proper execution in accordance
with concession agreement. The selection of IE shall be as per the guidelines
issued by DoE for selection of Consultants with experience on similar works.
The two quarry sites have been identified and Geophysical survey was carried
out through National Institute Rock Mechanics (NIRM). The survey indicates
adequate availability of suitable rock for breakwater and shore protection works.
Further, the NOC for mining was obtained in May, 2025. Tree enumeration for
mining was completed and lana for compensatory afforestation is identified in
Parbhani District of Maharashtra. The online application to get the forest
clearance will be made within two days and it is understood that the clearance
shall be received within 60 days.
MoRTH has recommended to initially go for the 22 km 2-lane road which will
be used by the Vadhvan port Project for transportation of Quarry material to
construction site. Tender to be invited by NHAI initially on EPC basis as there
are no generation of toll revenues in the initial years. The land acquisition for
Road & Rail connectivity is at final stage and 3D notification is likely to be issued
at the earliest. Once the possession of land is obtained, NHAI will float the
tender.
This is a first-of-its-kind PPP prcject where dredging and reclamation will be
k)
carried out on PPP. To make the project attractive, a 60:40 HAM payment
structure—60% by the Authority and 40% by the Concessionaire—has been
adopted. This split is also based on market feedback from 15 prospective
bidders. Additionally, this model promotes competitive bidding, shares risk with
private players, minimizes long-term maintenance costs, and ensures timely
completion of Phase-| by 2030.
There are standard clauses in the concession agreement for liquidity damage
of 0.2% of Performance Guarantee per day and provision for termination for
delay for longer period.m) The reclamation has been planned in phases based on the projected land use
requirements. In the initial phase, 850 hectares will be reclaimed and
subsequently four container terminals will be developed. The remaining 350
hectares are not immediately required and will be developed in the second
phase, with full reclamation expected to be completed within the overall five-
year construction period.
42. After detailed deliberations, the PPPAC unanimously recommended the proposal,
“Development and Maintenance of Land to be created in Offshore of Vadhvan
Coast by Dredging / Reclamation & Construction of Offshore Protection Bund
for Vadhvan Port on Hybrid Annuity Mode for consideration of the competent
authority for giving administrative approval. The project is recommended with the
following observation for consideration of the Competent Authority for
administrative approval: -
a. The appraised estimated project cost is Rs. 18,998 crore with a total
construction cost of Rs. 18,241 crore.
b. With no direct source of revenue generation from dredging and reclamation,
HAM is the only preferred mode of implementation. Hence, the project will be
implemented on HAM model with a payment structure in the ratio of 45:55
where 45% of the upfront payment shall be made by the Authority and 55% by
the concessionaire. A higher upfront payment is not recommended as that
would reduce the concessionaire’s stake in proper construction and take the
project towards the EPC mode.
c. Given that the project involves offshore reclamation through dredging and
filling, it is essential to adhere to proper benchmarking and established
standards. An Independent Engineer with appropriate qualifications may be
engaged to monitor the project in accordance with the provisions of the
Concession Agreement. Additionally, JNPT has developed in-house technical
expertise, which has already vetted the cost estimates will also carry out
parallel monitoring to ensure compliance and quality.
d. As per the Concession Agreement, a 2-lane permanent road is to be developed
and made operational by NHAI within six months from the Appointed Date to
facilitate transportation of materials from the quarry site to the project site. The
land for road development should be acquired fully before the bid submission
date. Further, the road should be designed in a manner that allows for future
10expansion to a 4-lane configuration without dismantling or disturbing the new
2-lane structure, ensuring its continued usability.
All clearances including forest clearance for quarry sites to be obtained before
the bid due date.
A well-defined risk-sharing matrix must be implemented during execution to
ensure clear accountability and prevent any breach of contractual obligations.
Considering the complexity of the project, the total concession period has been
kept for 15 years including 05 years for construction and 10 years for operation
and maintenance.
Penalty provisions in case of delay in completing the project should be
structured in a telescopic manner, starting at 0.2% and _ increasing
progressively over time.
43.Revalidation of its recommendation by the PPPAC is not required for following post
recommendation changes in the project costs/bid documents: -
Any change in the date/time period for any time-bound actions like appointed
a.
date, financial close, construction period etc.
b. Non-substantial change in risk -aiiocation.
Any other changes/modification in the project proposal with the overall
Cc.
objective of making project successful.
Further, MoPSW/VPPL may decide whether the changes proposed post
recommendations of the project proposal by the PPPAC fall within the
threshold criteria as stated above. All such changes falling within the threshold
criteria shall be appraised at the level of Secretary (PSW)/ BoD of VPPL as the
case may be, without any further need of revalidation by the PPPAC and shall
proceed with the approval process accordingly.
14.The meeting ended with a vote of thanks to the Chair.
KKKKKKKK
11Annexure-|
List of the attendees of the 128 meeting of the PPPAC for the Development and
Maintenance of Land to be created in Offshore of Vadhvan Coast by Dredging,
Reclamation & Construction of Offshore Protection Bund for Vadhvan Port on PPP
to be executed on Hybrid Annuity Mode.
a. Department of Economic Affairs, Ministry of Finance
1. Shri Ajay Seth, Secretary, EA- In Chair
oakon Shri Aman Garh, Director
Ms. Arya Balan Kumari, Joint Director
Ms. Anmol Wariach, Assistant Director
Shri Rajender Singh, Section Officer
Shri Manjeet, Assistant Section Officer
b. Department of Expenditure
1. Ms. Preeti, Joint Director
c. NITI Aayog
1. Shri. Partha Reddy, Programme Director
d. DoLA
1. Dr. RJR Kasibhatla, Joint Secretary & Legal Adviser
e. Ministry of Ports, Shipping and Waterways
1. Shri T K Ramachandran, Secretary
2. Shri R Lakshamanan JS (Ports)
3. Shri Rituraj Director Ports- PPP
f. Vadhvan Port Project Limited
Shri Unmesh Sharad Wagh (IRS), Chairman JNPA
il
Shri Sunilkumar Vishnu Madabhavi, Director (Technical) VPPL
Shri Vishwanath Gajanan Gharat, Dy. General Manager JNPA
Shri Sagar Mukund Dhok, Assistant Engineer VPPL
Shri Amit Magadum, Team Leader Consultant Royal Haskoning DHV
12Annexure Il
The queries raised by the PPPAC in its meeting held on 30.04.2025 and the response
of MoPSW.
Observations
S.No. Response by Ministry of Ports, Shipping and Waterways
by PPPAC
What is the The cost estimates for the Vadhvan project have been firmed
basis of the with significant due diligence and has also been vetted by IIT
Cost Madras.
Estimation?
e Rates have been adopted from the Schedule of Rates of
State Government of Maharashtra PWD basis 2023 (Q1).
e Wherever the marine work is involved the Rate have been
arrived from Rate Analysis.
e Unit rates of Marine works have been taken based on the
past projects carried out by rates analysis, current market
rates and vendors.
e Cost towards the reclamation for the project is based on
the international methods for construction design.
e Cost estimation was vetted by IIT Madras for all Marine
Works.
e Verification of unit rate for Dredging works for reclamation
was done by National Technology Centre for Ports
Waterways and Coasts (NTCPWC, MoPSW).
Details of Cost Breakup is attached as Enclosure-1.
Whether Industry / International benchmarks:
industry The costing f.; the reclamation is based on the large
benchmarking dredgers proposed for carrying out the works. It is proposed
been done to carry out the reclamation using trailer suction hopper
with respect to dredgers of 24,000 cum capacity which are available with the
dredging and large dredging companies. The costing is based on the
reclamation, proposed methodology, type of dredger, location of marine
and what is the borrow pit. The costing includes the equipment charges, its
international mobilisation, fuel, barges, manpower and other associated
best practices equipment. The cost arrived has been compared with the
in this regard? similar ongoing projects elsewhere in the world. The project
was discussed with various dredging companies who
provided the methodology for executing the reclamation
13Observations Response by Ministry of Ports, Shipping and Waterways
S.No.
by PPPAC
works. The costing has also been reviewed and vetted by
NTCPWC.
The cost towards the shore protection work is based on the
quarrying of the rocks, its transportation to site, sorting,
weighing, barge loading, placement and profiling of the bund.
The cost of the rocks is based on the CPWD rates provided
by the Government of India for the region. The cost towards
the transportation is based on the lead charges and
prevailing fuel rates. The quarrying of the rock would be
based on the mining plan which will be provided by NIRM.
Details of Consultation/ discussion with potential
bidders:
In order to gauge the market and get feedback from potential
bidders Expression of Interest was invited for the said work
and discussions were held with these bidders. All the large
dredging companies participated in the EOI discussion held
on 1% Aug 2024. Applications were submitted by all the
potential bidders.
The Connectivity to site is at presently through the state
How is Site
highway and village roads and the dedicated road to Port is
Connectivity
being developed for cargo movement & the same will be
be ensured for
utilised for transportation of construction materials in initial
the project?
years.
The Port Road connectivity is being developed by NHAI and
land acquisition for 34 km is in progress and will be
completed by July2025. The work of road connectivity to
stone quarry is being taken up on priority by NHAI/MoRTH.
The road connectivity will be available for transportation of
boulders within 12 months of commencement of road works.
The permission / license for quarrying of stone / material from
forest land is being obtained by VPPL and the application for
14-No. Observations Response by Ministry of Ports, Shipping and Waterways
leasing of land from forest department of Govt of
Maharashtra is in process.
Site will be handed over to the Concessionaire for mining
after approval process.
4. The Cabinet The Cabinet, while approving the project investment, had
while directed that the VPPL shall undertake reclamation and
providing dredging activities through a suitably structured PPP model
approval, (PPP Component-1) with appropriate risk sharing and
suggested to financial support arrangement between VPPL_ and
structure the
concessionaire (for instance, Hybrid Annuity Models, Gap
project Funding by VPPL, etc.).
through a
suitable PPP It is submitted that the present project primarily involves
model. MoPSW preparatory package of development (through reclamation)
has opted for of land for development of Vadhvan project. It may be
HAM Model. appreciated that preparation of land for development of
What is the terminals is critical preparatory activity and does not entail
justification for any revenue stream as such. The primary revenue
considering generating activity for port shall be from terminal operations
HAM Model of mainly on account of Cargo handling charges which can be
PPP? leveraged only after terminals have been developed.
Key reasons for adoption of HAM model are as under:
a) The Viability Gap Funding (VGF) model assumes
partial commercial viability, requiring the private partner to
recover a significant portion of the investment through user-
based revenue streams. However, in the case of this project,
the scope is iimited to land reclamation and development,
which by itself does not generate any direct revenue.
Revenue generation will only begin in subsequent phases,
such as terminal development and port operations, which are
not part of the current project's scope.
15Observations
S.No.
Response by Ministry of Ports, Shipping and Waterways
by PPPAC
b) Scale, complexity & criticality of the project-
This project involves offshore reclamation of an
unprecedented scale and complexity, making it the first-of-
its-kind in India, particularly for the purpose of port
development. Traditionally, projects of this nature have been
executed under EPC mode, with limited private risk exposure
and no long-term operational responsibility. Further, such
works has not been carried out in revenue-risk model like
VGF. Therefore, to ensure greater market participation, risk
mitigation, and long-term interest alignment, the HAM has
been adopted.
Has Summary of consultation with Stakeholders:
Stakeholder
consultation VPPL/JNPA had invited Expression of Interest (EOI) from
been done interested parties for the purpose of assessing the interest
with potential among parties in the market. Based on the responses from
bidders? If yes, 15 Firms and the same is listed below. Out of the 15 firms, 10
then details of firms are from major Dredging and Terminal & Port Operators
Consultation/ and balance have small time construction firms.
Discussion
held with The majority of the firms have evinced the interest and
potential submitted various suggestions. The following are the gist of
bidders may suggestions which can be of considered for analysis of the
be provided. PPP Financial Model.
(i) Concession period : The concession period to be 10
years instead of 15 years, this will enable the Contractor to
reduce the cost associated with the longer period. This
adjustment will help mitigate the costs involved in the longer
period.
(ii) Payment Conditions : To consider making 60%
payment funding during construction period and 40% as
variable annuity amount after the completion of the project
depending upon the value of assets created instead of 40%
and 60%as proposed in MoRTH-HAM.
16Observations Response by Ministry of Ports, Shipping and Waterways
S.No.
by PPPAC
(iii) | The O & M shall be in percentage of the Project cost
instead of fixed amount to be quoted and the maintenance of
dredging shall be the responsibility of Authority as the
dredging in initial years would not predictable.
(iv) | Prequalification Conditions : Consider last 10 years in
place of last 5 years for demonstrating Technical Capacity
and experience and consider preceding 3 years instead of
preceding one year for demonstrating the Financial capacity.
(v) | Obligations by Authority : The breakwater and
dredging works shall be started together in order to reduce
the accretion / erosion & to have protected waters.
List of Stakeholders:
Sse Adani Ports & Logistics Ltd
Boskalis India Private Limited
Hindustan Infralog Private Limited
Hyundai Engineering & Construction Co., Ltd.
International Seaport Dredging Private Ltd
Jan De Nul Dredging India Private Limited
Larsen and Toubro Limited
National Marine and Infrastructure India Pvt. Ltd.
Rail Vikas Nigam Limited
Van Oord Dredging and Marine Contractors B.V.
Vishwa Samudra Engineering Private Limited.
COON oop ehy>
- Oo
17S.No. Ob bs ye r Pv Pa Pt Aio Cn s Response by Ministry of Ports, Shipping and Waterways
6. What is the The pre-constriiction activities and clearances for the project
status of pre- are completed through key preparatory stages. Land
construction acquisition is in process and nearing completion, ensuring
activities and that the site is ready for development. Environmental
clearances? clearances, including the Environmental Impact Assessment
(EIA), have been obtained by the relevant authorities. Overall,
the project is steadily advancing through the pre-
construction phase, with most critical clearances and
activities are completed.
7. How will the For quality control of the project:
project’s
e Concession is DBFOT which includes investigations,
quality be design, construction, provision, erection, setting to work,
assured; and material, construction method, selection of equipment
how the and plant, quality control testing, deployment of
testing of personnel and supervisory _ staff monitoring and
material, plant maintenance etc.
and equipment e Shall be executed under the control of a quality
assurance system which satisfies the requirements of
will be done
ISO-9001:2015, ISO-14001:2015 and ISO-45001:2018
for quality
which will be monitored by the IE/PMC appointed by the
control?
Employer.
e Engineer (IE) appointed by Authority will supervise and
monitor Quality Management Plan.
e Quality Management Plan will also be approved by
Authority Engineers.
e Quality Assurance Plan will demonstrate in detail that all
the requirements of the Contract and all relevant codes,
standards and regulations are being met.
For quality control of material, plant and equipment:
18Observations Response by Ministry of Ports, Shipping and Waterways
S.No.
by PPPAC
An Independent Engineer (IE) will be appointed with
responsibility as per Concession Agreement.
As part of tender document for construction by the
contractor, the Employer’s requirement clearly mentions
the testing schedule requirements and details that the
contractor has to submit to the IE.
Tests under the relevant codes and standards and in
these empleyer’s requirement, the contractor shall carry
out further tests required by the engineer, at its own cost.
Compliance of Materials with Specifications shall be
confirmed by sampling and testing.
Acceptance criteria is stipulated in the Schedule D of the
Concession.
How are the Responsibility/ risk sharing:
responsibilities
Vadhvan Port is an SPV _ incorporated under the
shared and
Companies Act 2013 to implement this project.
what are the Widely accepted port model balances investment risks
responsibilities associated with greenfield port development.
of PPP-1 and In this model, basic and common port infrastructure such
PPP-2 as, breakwater, rail and road linkages, power supply,
components? water supc'y lines and common infrastructure and
services will be developed by the port/ SPV
Dredging, reclamation and shore protection bund is
proposed to be developed under suitable PPP i.e. HAM.
All cargo handling infrastructure will be developed and
operated by the private operators which will be awarded
on concessions.
Cargo or container handling operations which would be
entirely in the hands of developer cum operator on public
private partnership (PPP) mode.
Responsibility of PPP-1 and PPP-2:
Reclamation of land and access will be developed by
PPP-1 under HAM.
19Observations Response by Ministry of Ports, Shipping and Waterways
S.No.
by PPPAC
O&M for the asset created under PPP-1 will be
maintained by PPP-1 Concessionaire for 10 Year or until
allotted to PPP-2 Concessionaire (Container Terminal).
Container Terminal Operator will invest in development
berthing place, on-Shore handling and storage facilities
under Concession.
O&M responsibility for the asset created under PPP-2 will
for 30 years.
Land created under PPP-1 will be handed over as is
where is basis and all ground improvement program etc.
will be responsibility of PPP- 2 Concessionaire.
Once Project site as defined under PPP-1 is handed over
to PPP-2, the O&M responsibility ceases for PPP-1.
O&M for another portion of not allotted will continue to be
maintained for O & M period, as well as Shore protection
Bund which is common infrastructure will be maintained
by PPP-1 for 10 years.
Status of construction works -near shore reclamation
What is the
current status work:
of near shore Award of EPC Tender Package 2 (A) for Nearshore
works? reclamation and shore protection works.
The EPC Tender invited on 22th Oct, 2024 Estimated Cost
~Rs.1770 crore excluding GST. The contract Period is for
18 months.
Awarded to the lowest bidder, M/s ITD Cementation India
Ltd., at their quoted price of 1648 crore (excluding GST)
which is 6.892% below of the estimated cost on 31st Dec,
2024. (Two month before schedule i.e. Before end of Feb
2025/March 2025).
Contract Agreement was signed on 29th January 2025.
Notice to proceed with work issued on 15th March 2025.
The work will commence from May 2025 and expected to
be Completed by November 2026.
Status of construction of breakwater:
The contract period is for 52 months.
20Observations Response by Ministry of Ports, Shipping and Waterways
S.No.
by PPPAC
The Forest Department of Maharashtra has granted
permission for prospecting proposal for the survey of the
quarry on 26th Aug 2024 by conducting Geo-Physical
Survey in Khanivade & Gargaon sites to know suitability
of rock with size & strength.
NIRM completed field survey in 27th Dec, 2024 &
submitted report in 8th April, 2025.
Application to Forest for Licensing of Land for Stone
Quarry is submitted on 2nd April, 2025 & under
verification by DCF, Dahanu.
Tenders on EPC mode for Breakwater will be invited by
July, 2025.
For Stone, Aggregate and Murrum, quarry site is located
10. What are the
at Khanivade, located 20 km from Vadhvan. 74 million
sources of the
tons of rock, murrum & aggregate will be traported from
construction
this quarry.
materials? Additionally, few identified hillocks are also situated in
villages of Palghar Taluka.
Cement - Manufactured cement from market.
Steel — will be procured from open Market.
Road: Murrum & Aggregate will be procured from the
identified quarry following SoP issued by MoEF.
For Railway: Murrum & Stone for embankment and ballast
shall be procured from the identified quarry site following
SoP issued by MoEF.
Reclamation fill material sea sand will be sourced from the
Marine borrow Pit located north of Vadhvan port along the
Daman coast.
Borrow pit is 50 km from Vadhvan at a depth of 20 to 25
m.
Sand Mining Composite license under OAMDR Act 2002
for reservation is received from Ministry of Mines through
extraordinary Gazette of India on 21st Dec, 2023.
21Enclosure-1: Details of Cost Breakup
Vadhvan Port - Detailed Cost Estimates for PPP-1 Proposal under HAM
Ss. ITEM QUANTITY UNIT RATE AMOUNT
No. (Rs.) (Rs.)
1 DREDGING (Ph 1)
1.1 Inner Approach
Channel &
Harbour Basin (-
17.5 m CD and
19.5 mCD at
berth)
a. | Soil Cum 300 825,000,000
dredging 2,750,000
b. | Rock Cum 2,350 8,319,000,000
dredging 3,540,000
12 Outer Approach
Channel (-20 m
CD)
a. | Soil Cum 300 216,000,000
dredging 720,000
b. | Rock Cum 2,350
dredging
Total (1)
9,360,000,000
RECLAMATION
2. Offshore land
(Ph 1) upto +5.0
m CD
a. | Reclamation 151,170,000 Cum 570 86,166,900,000
through
22marine
borrow pit
b. | Reclamation 7,010,000 Cum 300 2,103,000,000
through
dredged
material
Dts Offshore land
(Ph 1) upto +5.0
to +6.8 m CD
(Terminal areas)
a. | Reclamation 4,917,559 Cum 570 2,803,008,402
through
marine
borrow pit
2.3 Offshore land
(Ph 2) upto +5.0
m CD
a. | Reclamation 37,420,725 Cum 570 21,329,813,250
through
marine
borrow pit
b. | Reclamation 20,056,511 Cum 300 6,016,953,300
through
dredged
material
2.4 Offshore land
(Ph 2) upto +5.0
to +6.8 m CD
(Terminal Areas)
23a. | Reclamation 5,205,712 Cum 570 2,967,255,612
through
marine
borrow pit
121 ,386,930,564
Total (2)
3.0 SHORE PROTECTION
WORKS
3.1 | Offshore reclaimed land
protection works (Ph 1 - 17 km
of bund with crest level @ +7.0
m CD)
a. | Rock
Rock 866,800 MT 1,729 1,498,265,808
Armour
0.06-0.3T
Rock 0.3 to 501,183 MT 1,763 883,587,128
41 MT
Rock 1 to 3 697,040 MT 1,809 1,260,946,961
MT
b | Core and
Bedding
Toe 156,352 MT 1,300 203,258,052
Protection -
1-500 Kg
Core 10 to 10,430,453 MT 1,300 13,559,588,850
100 kg
Geotextile 1,220,298 Sq. 211 257,482,959
24c. | Crown Wall, 41,543 10,000 415,433,750
Cast-In-Situ Cum
M40 Mass
Concrete
3.2 Offshore reclaimed land
protection works (Ph 2 - 5.5 km
of bund with crest level @ 7.0
m CD)
a. | 5T - 35,122 Cum 13,750 482,927,500
Accropode
b. | Rock 201,376 MT 1,729 348,079,024
Armour
0.06-0.3T
c. | Rock 0.3 to 606,348 MT 1,763 1,068,993,354
4 MT
d. | Quarry run 6,956,184 MT 1,300 9,043,039,200
bund
e. | Geotextile 734,383 Sq. 225 165,236,175
29,186,838,760
Total (3)
COMMON PORT
INFRASTRUCTURE
4.1 Earthworks for
Sub-base
preparation
(Filling from +5.0
mCD to
+6.8mCD)
Borrowed earth 3,177,666 Cum 570 1,811,269,620
254.2 | Roads (at 7.6 m)
Primary roads 1,105,013 |. Sq. 6,225 6,878,846,124
within the port m
Asphalt roads 168,626 | Sq. 3,262 550,027,203
within the port m
Parking Area 438,472 | Sq. 4,281 1,877,100,173
m
4.3 | Drainage and 1/ LS | 1,788,888,292 1,788,888,292
sewerage
4.4 | Utilities
Utility Trenches 1; LS 396,105,796 396,105,796
Cabling 1; LS 20,000,000 20,000,000
Illumination and 1; LS 110,577,000 110,577,000
lighting
Total (4) 13,432,814,207
RAILWAYS
5.1 | Earthworks for 5,233,875 | Cum 850 4,448,793,750
Sub-base
preparation
(Filling from +5.0
mCD to
+6.8mCD)
5.2 | Rail yard ground
development -
(Filling from
26+6.8m CD to
+7.6m CD)
a. | Granular Fill 870,000 | Cum 1,839 1,599,930,000
300mm thk
b. | Sub Grade 870,000 | Cum 2,200 1,914,000,000
300mm thk
c. | Crushed 435,000 | Cum 2,474 1,076,190,000
Rock Sub
Base
150mm thk
Total (5) 9,038,913,750
Total (1+2+3+4+5) 182,405,497,281
Total in crores 18,241
IC/Pre-operative expenses @1% of 182.41
(A)
Financing Cost (1% of debt amount) 52.44
Interest during Construction (@ 522.51
11.10%)
Estimated Project Cost (A+B+C+D) 18,997.90
GST @ 18% on (A+B+C) 3a20.0F
Estimated Project Cost including 22,323.47
GST (E+F)
KkRKK
27