**Executive Summary**
This document is a record of discussion from the 123rd meeting of the PPPAC held on May 2nd, 2025, concerning proposals for the development of a Multi Modal Logistics Hub in Greater Noida, Uttar Pradesh, and a Multi Modal Logistics Park in Pune, Maharashtra, both on a PPP mode. The document forwards the meeting's record for information and necessary action by relevant stakeholders and contains recommendations for the competent authority's consideration.
**Key Points / Main Content**
* **Meeting Overview:**
* The 123rd PPPAC meeting occurred on May 2nd, 2025, to consider the two projects.
* The projects follow a single-stage, two-envelope bidding process.
* **Multi Modal Logistics Hub (MMLH), Greater Noida:**
* Project Details: Development of a Greenfield Multi Modal Logistics Hub on DBFOT basis.
* Location: Greater Noida, Gautam Buddh Nagar, Uttar Pradesh; area of ~334ha.
* Project components: Mechanized warehouses, specialized storage solutions, intermodal transfer facilities, and value-added services (cross-docking, customization, etc.).
* Capacity: 1.44 million TEUs containerized, 7.8 MTPA non-containerized, 3.0 million sq ft warehousing, 0.3 million sq ft cold storage.
* Concession Period: 45 years, executed in 3 phases.
* Total Project Cost: INR 5,942 crore.
* Funding: Concessionaire, except for land acquisition, leveling, external connectivity, etc., to be borne by SPV-DMIC IITGNL.
* Land Acquisition Status: Over 90% acquired by GNIDA.
* Financial Viability: Project IRR 16%, Equity IRR 20.3%, Project NPV INR 1,790 crore.
* Bidding: Highest Minimum Guaranteed Revenue Share.
* **Multi Modal Logistics Park (MMLP), Pune:**
* Project Details: Development, Operation, and Maintenance of the MMLP through Public Private Partnership on Design, Build, Finance, Operate and Transfer basis.
* Location: Pune, Maharashtra; area of ~135.6 Ha.
* Project components: Warehousing, specialized storage, freight transport, intermodal transfer, cargo aggregation, customs clearance, packaging, etc.
* Capacity: 16.3 million Ton break bulk, 0.32 million TEU container, 163,000 auto cars, 5.0 million sq ft warehousing.
* Concession Period: 45 years, executed in 3 phases.
* Total Project Cost: INR 1,362.02 crore.
* Funding: 70% Debt and 30% Equity for Concessionaire's Expenditure. The Authority's investment of INR 1,684.98 crore includes land acquisition costs, development of external road and rail infrastructure, and provision of water and power connections.
* Land Acquisition Status: 180 acres acquired, balance in progress.
* Financial Viability: Project IRR 13.45%, Equity IRR 15%, Project NPV Rs. 293.23 crores
* Bidding: Highest Minimum Guaranteed Revenue Share.
* **Recommendations for Both Projects:**
* PPPAC unanimously recommends the proposals for consideration by the competent authority for administrative approval.
* Ensure provisions to discourage gold plating and recognition of incurred TPC at COD.
* Authority to ensure the financial eligibility promotes wider participation and optimal competition.
* Any changes in date/time period, non-substantial changes in risk-allocation, or other modifications with the overall objective of project success do not require revalidation by the PPPAC.
**Impact Analysis**
**Secretary, Ministry of Road, Transport and Highways, Transport Bhawan, New Delhi; Secretary, Department of Expenditure, North Block, New Delhi; Secretary, Department for Promotion of Industry and Internal Trade, Vanijya Bhawan, New Delhi; CEO, NITI Aayog, Yojana Bhawan, New Delhi; Secretary, Department of Legal Affairs, Shastri Bhawan, New Delhi; CEO, National Industrial Corridor Development Corporation Limited, Jeevan Bharti Building, 8th Floor, Tower 1, LIC, Connaught Place, New Delhi; CEO, National Highways Logistics Management Limited, Sector 10, Dwarka, New Delhi**
* **Impact:**
These stakeholders are informed of the PPPAC's discussion and recommendations regarding the projects. They will be involved in the subsequent approval and implementation phases.
* **Action Required:**
The document is forwarded for information and necessary action, requiring these stakeholders to review the Record of Discussion and consider the recommendations for the respective projects, and to take further action that they deem necessary.
Key Entities Referenced
Public Private Partnership Appraisal Committee (PPPAC): Committee responsible for appraising public-private partnership projects.
Multi Modal Logistics Hub, Greater Noida: Proposed development of a logistics hub in Greater Noida, Uttar Pradesh.
Multi Modal Logistics Park, Pune: Proposed development of a logistics park in Pune, Maharashtra.
Design Build Finance Operate Transfer (DBFOT): A common public-private partnership model for infrastructure projects.
Ministry of Finance: Primary government body under which the Infrastructure Finance Secretariat and ISD Division operate.
F.No.1/36/2024-PIU
Government of India
Ministry of Finance
Department of Economic Affairs
Infrastructure Finance Secretariat
ISD Division
(PIU)
STC Building, Janpath, New Delhi
Dated: 10‘ May 2025
Record of Discussion
Subject: Record of Discussion of the 123 meeting of the PPPAC for considering
the proposals for the ‘Development of Multi Modal Logistics Hub, Greater Noida’
and ‘Development of Multi Modal Logistics Park, Pune’ on PPP mode.
Reference: 123" meeting held on 24 May 2025.
Sir/Madam,
The undersigned is directed to forward the Record of Discussion of the 123” meeting
of the PPPAC held on 2" May 2025, under the Chairmanship of Finance Secretary &
Secretary (EA) for information and necessary action.
2. This issues with the approval of the Competent Authority.
Rahul Singh
To,
1. Secretary, Ministry of Road, Transport and Highways, Transport Bhawan, New
Delhi
2. Secretary, Department of Expenditure, North Block, New Delhi
3. Secretary, Department for Promotion of Industry and Internal Trade, Vanijya
Bhawan, New Delhi
os CEO, NITI Aayog, Yojana Bhawan, New Delhi
Secretary, Department of Legal Affairs, Shastri Bhawan, New Delhi
6. CEO, National Industrial Corridor Development Corporation Limited, Jeevan
Bharti Building, 8" Floor, Tower 1, LIC, Connaught Place, New Delhi
7. CEO, National Highways Logistics Management Limited, Sector 10, Dwarka,
New Delhi
Copy to:
1. Sr. PPS to Finance Secretary & Secretary (EA)
2. Sr. PPS to JS (ISD)
Page 1 of 15Subject: Record of Discussion of the 123 meeting of the PPPAC for considering the
following project proposals: -
(i) Development of a Multi Modal Logistics Hub at Greater Noida, Uttar Pradesh,
and
(ii) Development of a Multi Modal Logistics Park, at Pune, Maharashtra.
1. The 123 meeting of the PPPAC was held on 2"! May 2025 at 17:00 Hours to consider
the above-mentioned two projects.
2. List of attendees is placed at Annexure-l.
|. Development of Multi Modal Logistics Hub (MMLH) at Greater Noida, Uttar Pradesh
1. Joint Secretary (JS) (ISD) welcomed the attendees to the meeting and informed that as
these two project proposals do not have the RfQ stage and follow a single stage, two
envelope bidding process, the PPPAC may consider these proposals for ‘In-Principle’ and
‘Final Approval’ simultaneously. With the permission of the Chair, JS (ISD) requested the
Chief Executive Officer (CEO), National Industrial Corridor Development Corporation
(NICDC) to make a presentation to the PPPAC. The CEO (NICDC) made a detailed
presentation on the Development of MMLH, Greater Noida project proposal submitted to
the PPPAC.
2. The basic details of the project are given in the table below:
Table 1: Details of the project
Development of Greenfield Multi Modal Logistics Hub on
Design, Build, Finance, Operate and Transfer basis at
Greater Noida, Gautam Buddh Nagar, Uttar Pradesh
Design Build Finance Operate Transfer
National Industrial Corridor Development Corporation
National Industrial Corridor Development Corporation
Dadri, Greater Noida, Gautam Buddha Nagar, Uttar
Pradesh
The proposed MMLH, Greater Noida, is spread over an
area of ~ 334ha.
The proposed development is characterized as a freight
handling facility comprising of world-class facilities such
as mechanised warehouses, specialized storage
solutions and mechanized handling & intermodal transfer
of container/bulk/break-bulk cargo.
The MMLH is also expected to additionally provide value-
added services such as cross-docking, customization,
stacking and labelling.
Page 2 of 15The Capacity of major components is as follows:
e Containerized: 1.44 million TEUs (in 3 phases)
e Non-containerized: 7.8 MTPA (in 3 Phases)
e Warehousing (Mandatory): 3.0 million square feet
e Cold Storage (Mandatory): 0.3 million square feet
45 years (Including 2 years of construction period for|
Phase-| and 43 years of O&M). The project will be
executed in 3 phases.
e Phase |: 2 years from Appointed Date.
e Phase Il: 5th year after COD or 80% of Phase |
capacity, whichever is earlier.
e Phase Ill: 10th year after COD or 80% of Phase |!
Capacity, whichever is earlier.
Concessionaire
S.N| Major Project Components Cost
(INR in crore)
1 | Land development 41
Roads and Signage and Utility
2 Buildings ace
Equipment costs, warehouse
8 and commercial area 4: 194
4 | Equipment replacement cost 304
Other Capex items 399
Other costs including general
consultancy, project
6 management services, quality 718
control, construction — safety,
contingency, IDC and equipment
replacement costs
Total cost for the MMLH Project 5,942
e Container Cargo
e Bulk Cargo
e Warehousing
e¢ Commercial Development
e Funding towards construction costs is to be done by
Concessionaire, except for land acquisition (for the
entire land area), land levelling for rail yard, external
connectivity, boundary wall & power connectivity to the
Page 3 of 15project boundary. The Concessionaire will meet the
elie ee ee expenses of the Project in the debt-equity ratio of
SE aoe 70:30.
---~—~— | ~-* ~Funding towards the above aspects, such as land
acquisition (for the entire land area), land levelling for,
rail yard, external connectivity, boundary wall & power
connectivity to the project boundary to be borne by the
ie SPV - DMIC IITGNL.
Land Acquisition Status | More than 90% of land acquired by GNIDA as on date
ay | Project IRR: 16%
Financial Viability Equity IRR: 20.3%
ee ee Project NPV: INR 1,790 crore
Bidding parameter _ Highest Minimum Guaranteed Revenue Share (in INR)
Pe (on XNPV basis adjusted on the Appointed Date)
Bidding process Single stage Two Envelop Bid
3. The primary purpose of the proposed project is to establish an MMLH in Greater Noida,
Uttar Pradesh, strategically located at the confluence of the Eastern and Western
Dedicated Freight Corridors. By providing an integrated dry-port facility for efficient storage
and transhipment of goods to and from the Uttar Pradesh segment of the National Capital
Region, the hub will help these corridors realise their full operational potential. Equipped
with advanced storage and aggregation capabilities, export/import services and value-
added amenities, the MMLH will enhance regional industrial efficiency and attract
investment. The proposed project shall be implemented on a Design Build Finance
Operate Transfer (DBFOT) basis. The concession period is 45 years, including the 2 years
of construction period for Phase |.
4. Under this logistics facility, the concessionaire will develop, operate, maintain, and manage
the entire logistics hub, including the commercial area and ancillary facilities. Beyond
Standard container handling, the hub will offer value-added services. The Total Project
Cost (TPC) is estimated at INR 5,942 crore, with the bidding parameter being the Highest
Minimum Guaranteed Revenue Share.
5. After the presentation, the Chair asked the PPPAC members for their observations.
Department of Expenditure and Department of Legal Affairs supported the proposal and
stated that they have no further comments to offer.
6. PD, NITI Aayog raised the following observations:
a) Schedule B of the draft concession agreement is broadly defined, which may allow
gold-plating of the TPC and potentially give rise to disputes between the Authority and
the Concessionaire over TPC recognition after the commercial operation date (COD).
b) The road and rail connectivity are intrinsic to the project proposals. However, they are
not part of the Condition Precedent. Secondly, why can't the road and rail connectivity
be part of the concessionaire's scope of work?
Page 4 of 157. JS (ISD) raised the following observations:
a) Non-mandatory components are not included in the TPC, as their implementation is
optional.
b) The capex estimated in Annexure-VI and the Financial model are different. For
example, the capex cost considered for utilities is INR 127 crore in Annexure-VI of the
DPR. However, as per the financial model, the same is considered as INR 137.16
crore. It is suggested to reconcile the above documents.
The Authority, in the estimation of the TPC, has included the replacement cost of INR
304 crore. However, the same is to be considered as O&M expenses. It is suggested
to remove the replacement cost from the TPC.
The Authority has included 0.5% of the TPC for quality control and construction safety
charges. Quality control and safety charges are part of the independent engineer's
cost. Therefore, it is suggested to remove the same.
e) As per the Model Concession Agreement (MCA) of the Multi Modal Logistics Park, the
lock-in period for the equity is 6 months; however, in the current project proposal, it is
taken as 2 years.
As per the Model RfP of Multi Modal Logistics Park, the time period considered for
technical capacity evaluation is 5 years; however, in the current project proposal, it is
taken as 10 years.
8. The Chair made the following observations:
a) How is the connectivity of the proposed MMLH?
b) What is the rationale for assigning the Authority for the construction of the rail siding,
and which party will be responsible for its ongoing maintenance?
Cc) What is the bid parameter, and what are the consequences if actual gross revenue
deviates from the projected amount?
d) As payment made by the customers to the sublicensee is not covered under the
present Gross Revenue definition, would it discourage the concessionaire from directly
operating the facilities?
What are the provisions for competing facilities?
How will efficient utilization of land be ensured, and what mechanisms will be
implemented to achieve this?
Page 5 of 159. CEO (NICDC) submitted the following to the queries raised by the PPPAC Members: -
a) Gold Plating of TPC: To prevent gold plating, audit provisions will be incorporated into
the draft concession agreement. The project’s capacity shall be developed in
accordance with the minimum development obligations and prescribed standards and
specifications. This, inter alia, forms the basis for estimating the TPC. Furthermore,
the Authority will ensure that no disputes arise at the time of TPC recognition.
b) Road and Rail Connectivity: The MCA of Multi Modal Logistics Park provides road
and rail connectivity in the scope of the Authority. In addition, during the stakeholder's
consultation, the developers were of the view that the Authority is in a better position
to undertake connectivity risk. As per the MCA of Multi Modal Logistics Park, road
connectivity is to be provided before the COD and rail connectivity within four years
from the appointed date. However, in this MMLH project, both road and rail connectivity
are being provided one month prior to the COD.
TPC: DEAs comments on the non-mandatory components, changes in capex
estimation, replacement cost, and consultancy charges are noted, and appropriate
changes will be incorporated.
Equity lock-in and Technical Capacity: In view of the project’s scale and complexity,
an enhanced lock-in period and technical capacity have been included.
Connectivity of proposed MMLH: The proposed MMLH benefits from integrated
connectivity across all major transport modes. It is situated at the junction of the
Western and Eastern Dedicated Freight Corridors. The MMLH hub links directly to NH-
34 and the Eastern Peripheral Expressway. It is also connected with Jewar
International Airport. Together, these linkages make MMLH a one-stop freight
destination for the National Capital Region and its hinterland.
f) Rail Siding: The Authority will develop the rail siding to ensure uninterrupted, high-
capacity connectivity within the MMLH. Delhi-Mumbai Industrial Corridor (DMIC) will
construct 17 internal tracks and all associated systems (e.g. signalling), and the
concessionaire will be responsible for the maintenance of the siding.
9) Bidding Parameter: The bid parameter is the highest Minimum Guaranteed Revenue
(MGR) Share over the 45-year concession period. If actual gross revenue in any year
exceeds the projected MGR, the concessionaire pays the Authority the agreed
revenue-share percentage on the surplus; if it falls short, the concessionaire still remits
the full MGR, guaranteeing the Authority at least the floor revenue. Periodic payment
milestones will reconcile actual versus projected revenues and trigger any additional
revenue-share payments.
h) Gross Revenue: The current definition of the ‘Gross Revenue’ is based on the duly
approved MCA of the Multi Modal Logistics Park. ‘Gross Revenue’ mean only the
amounts actually remitted to the Concessionaire by its sublicensee and excludes any
Page 6 of 15further collections received by the sublicensee from its own customers. Consequently,
the Authority’s revenue-share entitlement is calculated solely on the Concessionaire’s
direct receipts. To further ensure it the sublicensing is limited to warehouse and
commercial activities (i.e. ~ 19 % of the revenue stream) only.
Competing Facility: The draft concession agreement provides a competing clause.
According to the clause, the Authority will not establish any competing facility within a
100 km radius of MMLH until 10 years from the appointed date.
)) Better utilization of land: In line with the master plan and demand assessment, the
concessionaire can propose better land utilization, entailing higher initial capital
expenditure but yielding greater revenues and lower lifecycle costs. This enhanced
efficiency allows the Concessionaire to offer an increased revenue share to the
Authority, thereby improving the project’s overall financial returns.
Recommendations:
10. After detailed deliberations, the PPPAC unanimously recommended the proposal for
“Development of Greenfield Multi Modal Logistics Hub on DBFOT basis at Greater Noida,
Gautam Buddh Nagar, Uttar Pradesh” for consideration of the competent authority for
giving administrative approval. The overall recommendation is subject to the following
specific recommendation.
a) The appraised Total Project Cost is INR 5,942 crore. The Total Capital Cost, including
the Authority cost, is INR 8,279 crore.
b) The authority will ensure to incorporate provisions which discourage gold plating and
recognition of incurred TPC at the Commercial Operation Date (COD).
The Authority will ensure that the eligibility criteria promote wider participation and
optimal competition.
11. Revalidation of its recommendation by the PPPAC is not required for the following post
recommendation changes in the project costs/bid documents: -
a) Any change in the date/time period for any time-bound actions like appointed date,
financial close, construction period etc.
b) Non-substantial change in risk-allocation.
Cc) Any other changes/modifications in the project proposal with the overall objective of
making the project successful.
Page 7 of 15d) Further, NICDC may decide whether the changes proposed post recommendations of
the project proposal by the PPPAC fall within the threshold criteria as stated above. Alll
such changes falling within the threshold criteria shall be appraised at the level of the
CEO (NICDC) / Secretary (DPIIT) as the case may be, without any further need of
revalidation by the PPPAC and shall proceed with the approval process accordingly.
kK
Page 8 of 15Development of a Multi Modal Logistics Park (MMLP) at Pune, Maharashtra
. With the permission of the Chair, JS (ISD) requested the CEO, National Highways
Logistics Management Limited (NHLML) to make a presentation. The CEO, NHLML made
a detailed presentation on the Development of MMLP. Pune project proposal to the
PPPAC.
. The basic details of the project are given in the table below:
Table 2: Details of the project
Development, Operation and Maintenance of the Multi
Modal Logistics Park Pune at village Pawalewadi, Maval
Taluka, District Pune in the State of Maharashtra through
Public Private Partnership on Design, Build, Finance,
Operate and Transfer basis
| Design Build Finance Operate Transfer
Ministry of Road, Transport and Highways
| SPV comprising of:
e National Highways Logistics Management Limited, a
100% owned company of NHAI
e Maharashtra Industrial Development Corporation
(MIDC) on behalf of the Government of Maharashtra
e Rail Vikas Nigam Limited (RVNL) on behalf of the
Ministry of Railways
| Pune, Maharashtra
The proposed MMLP, Pune, is spread over an area of
~'| 35.6 Ha.
Core Logistics Services: Includes warehousing,
Specialized storage, freight transport, intermodal transfer,
Cargo aggregation, container/bulk terminals, Customs
EDI, cargo scanning, and other authority-mandated
services.
Value-Added Services: Encompasses customs
clearance, packaging, labelling, assembly/disassembly,
product mixing, oil application, and advanced IT services
for booking, tracking, and documentation.
Supporting Services: Covers truck parking and O&M, staff
recreational amenities, office space, user parking with
ample maneuvering space, and building information
modelling services.
Page 9 of 15The Capacity of major components is as follows (in three
phases):
e Break bulk: 16.3 million Ton
e Container: 0.32 million TEU
e Auto Cars: 163000 cars
e Warehousing 5.0 million square feet
45 years. (Including 2 years of construction period for
Phase-| and 43 years of O&M). The project will be
executed in 3 phases.
e Phase |: 2 years from Appointed Date.
e Phase Il: Completion on or before 10th year from the
Appointed Date
e Phase III: Completion on or before 15th year from the
Appointed Date.
[INR 1,362.02 crore
Concessionaire
S.N| Major Project Components Cost (INR in
crore)
Civil Cost for Developer 1067.67
2 |GST @ 18% 196.05
3 |Design @ 1.18% of (1) 12.60
4 Pre-ai operatij ve expenses @ 19%, 10.68
of (1)
Cost of Independent Engineer
> | @ 1.18% of (1) 266
6 | Insurance @ 0.15% of (1) 1.60
7 |Finance Charges @ 1.0% 4.26
Interest During Construction @
8 | 41.60% of phase 1 oe. le
9 Escalation for Phase —- 1 @ 5% 91.47
PA
Total Project Cost 1362.02
e Container Business
e Bulk and break-bulk business
e Roll-On/Roll-Of (RORO) business
e Revenue from rakes
e Other revenue (Truck parking charges, Weight
Bridge Charges, Lease Rental)
Page 10 of 15| The Concessionaire’s Expenditure of Rs. 1362.02 Cr.
| has been assumed with 70% Debt and 30% Equity.
| The Authority's Expenditure of Rs 1684.98 consists of
| e NHLML’s expenditure of Rs. 964.97 Cr for 57.27%
equity in the Authority SPV as a grant.
e MIDC’s expenditure of Rs. 281.93 Cr for 16.73%
equity and in the Authority SPV
e RVNL's expenditure of Rs. 438.08 Cr for 26% equity
in the Authority SPV
| 180 acres of land is already been acquired by MIDC, and
| the acquisition of the balance land is under progress by
| MIDC.
Project IRR: 13.45%
Equity IRR: 15%
Project NPV: Rs. 293.23 crores
Highest Minimum Guaranteed Revenue Share
Single stage Two Envelop Bid
. The primary purpose of the proposed project is to establish, operate and maintain an
MMLP in Pune, Maharashtra. This holistic logistics park will create employment
opportunities across the region, while generating revenue for NHLML, the Maharashtra
Industrial Development Corporation (MIDC) and Rail Vikas Nigam Limited (RVNL).
Equipped with advanced storage and aggregation capabilities, export/import services and
value-added amenities, the MMLP will enhance regional industrial efficiency and attract
investment. The project will be implemented on a DBFOT basis, with a 45-year concession
period and a 15-year construction timeline divided into three phases.
Under this logistics facility, the concessionaire will develop, operate, maintain, and manage
the entire logistics park, including the commercial area and ancillary facilities. Beyond
standard container handling, the hub will offer value-added services. The TPC is estimated
at INR 1,362.02 crore, with the bidding parameter being the Highest Minimum Guaranteed
Revenue Share.
. After the presentation, the Chair asked the PPPAC members for their observations.
Department of Expenditure and Department of Legal Affairs supported the proposal and
stated that they have no further comments to offer.
PD, NITI Aayog raised the following observations:
a) The observations made for MMLH Noida are also applicable to this project.
Page 11 of 15b) The concession agreement provides that the proposed site will be given to the
concessionaire on a license basis. however, there are also provisions for further
subleasing of the land. It is suggested to remove this discrepancy.
As per the RfP, financial eligibility criteria include Assets Under Management (AUM).
As AUM does not accurately reflect net worth, therefore, it is recommended that AUM
may be replaced with Available Capital for Investment (ACI).
7. JS (ISD) raised the following observations:
a) In the proposed TPC, the escalation of capex and soft costs for Phase II and III has
not been included. It is suggested to incorporate the same.
b) As per the Model RfP of MMLP the Technical Capacity threshold (for Group A) should
be equal to the TPC of the project. However, in the RfP of the proposed MMLP, the
threshold level is kept equal to the TPC of Phase | only. It is suggested to remove this
discrepancy.
Cc) As per the Model RfP of MMLP, the Average annual turnover (for Group B) during the
last three financial years shall not be less than two times the TPC. However, in the RfP
of the proposed MMLP., the threshold level is kept equal to two times the TPC of Phase
| only. It is suggested to remove this discrepancy.
8. The Chair made the following observations:
a) How is the connectivity of the proposed MMLP?
b) What is the current status of land acquisition?
What is the Authority's investment in the project?
How has the project been planned and designed to ensure better utilization of the
available land?
How can the Authority verify the revenue of the concessionaire? Is any auditing
mechanism proposed for the same?
CEO (NHLML) submitted the following to the queries raised by the PPPAC Members: -
a) Gold Plating of TPC: To prevent gold plating, audit provisions will be incorporated into
the draft concession agreement. The project's capacity shall be developed in
accordance with the minimum development obligations and prescribed standards and
specifications. This, inter alia, forms the basis for estimating the TPC. Furthermore,
the Authority will ensure that no disputes arise at the time of TPC recognition.
Page 12 of 15b) Road and Rail Connectivity: The MCA of MMLP provides road and rail connectivity
in the scope of the Authority. In addition, during the stakeholder's consultation, the
developers were of the view that the Authority is in a better position to undertake
connectivity risk. As per the MCA of MMLP, road connectivity is to be provided before
the COD and rail connectivity within four years from the appointed date. In the
proposed project, the road and rail connectivity are to be provided accordingly by the
authority.
c) The suggestions made by NITI Aayog and DEA regarding Subleasing of the Land, use
of ACI, incorporation of Escalation for TPC calculations, and Eligibility Criteria are
noted and appropriate changes will be incorporated.
d) Authority Investment: The Authority's investment of INR 1,684.98 crore includes land
acquisition costs, development of external road and rail infrastructure, and provision
of water and power connections.
e) Land utilization: The project is proposed at a strategic location, identified through a
demand-based assessment and the logistical requirements of the region. During the
bidding stage, the Concessionaire will conduct a detailed demand assessment to
determine the actual market potential, thereby enabling better utilization of the
available land.
f) Revenue: Provisions for auditing the revenue generated by the Concessionaire are
currently under consideration of MoRTH. These provisions are expected to be
incorporated into the MCA following deliberations and approval by the Inter-Ministerial
Committee.
g) Land Acquisition: The State Government is responsible for land acquisition. As of
now, Phase | land has been acquired (~ 54 hectares). The land for Phases II and III
will be initiated post approval of the Competent Authority.
Recommendations:
10. After detailed deliberations, the PPPAC unanimously recommended the proposal for
“Development, Operation and Maintenance of the Multi Modal Logistics Park Pune at
village Pawalewadi, Maval Taluka, District Pune in the State of Maharashtra through Public
Private Partnership on DBFOT basis” for consideration of the competent authority for
giving administrative approval. The overall recommendation is subject to the following
specific recommendation.
a) The appraised Total Project Cost is INR 1,362.02 crore. The Total Capital Cost,
including the Authority cost, is INR 3,047 crore.
Page 13 of 15b) The authority will ensure to incorporate provisions which discourage gold plating and
recognition of incurred TPC at the Commercial Operation Date (COD).
The Authority shall ensure that land acquisition for Phase II and III is before the trigger
for Phase II and III construction.
d) The Authority to ensure that the financial eligibility promotes wider participation and
optimal competition.
11. Revalidation of its recommendation by the PPPAC is not required for the following post
recommendation changes in the project costs/bid documents: -
a) Any change in the date/time period for any time-bound actions like appointed date,
financial close, construction period etc.
b) Non-substantial change in risk-allocation.
Any other changes/modifications in the project proposal with the overall objective of
making the project successful.
Further, MoRTH may decide whether the changes proposed post recommendations of
the project proposal by the PPPAC fall within the threshold criteria as Stated above. All
such changes falling within the threshold criteria shall be appraised at the level of
Secretary (MoRTH), without any further need of revalidation by the PPPAC and shall
proceed with the approval process accordingly.
12. The meeting ended with a vote of thanks to the Chair.
KKK
Page 14 of 15Annexure-|
List of the participants of the 123" meeting of the PPPAC
a) Department of Economic Affairs, Ministry of Finance
1. Shri Ajay Seth, Finance Secretary & Secretary, EA- In Chair
Oak Ms. Anuradha Thakur, OSD(EA)
Shri Baldeo Purushartha, JS (ISD)
Shri Rahul Singh, Director (PIU)
Shri Rajender Singh, SO (PIU)
Shri Manjeet Yadav, ASO (PIU)
WN
b) Department for Promotion of Industry and Internal Trade
1. Shri Amardeep Singh Bhatia, Secretary
c) Ministry of Road, Transport and Highways
1. Shri. Puneet Agarwal, AS&FA
2. Shri Vinay Kumar, AS
3. Shri. Manoj Kumar, CE
4. Shri Sumit Kumar, SE
d) NITI Aayog
1. Shri. Partha Reddy, Programme Director
e) Department of Legal Affairs
1. Shri Kasibhatla, Deputy Legal Adviser
f) NICDC
1. Shri. Rajat Saini, CEO
g) GNDA
1. Shri. Sreelakshmy, CEO
h) NHLML
1. Shri. Prakash Gaur, CEO
i) Department of Expenditure
1. Shri. Ranganath Audam, DD
RK
Page 15 of 15