**Executive Summary**
This document is an Office Memorandum containing the record of discussion from the 30th Meeting of the Empowered Committee (EC) held on March 7th, 2018 regarding the Scheme for Financial Support to PPPs in Infrastructure (Viability Gap Funding Scheme) for the Pune Metro Line-III project. It details the EC's consideration of a proposal from the Pune Metropolitan Region Development Authority (PMRDA) and the conditions under which in-principle approval for VGF was granted. The memo, dated April 2nd, 2018, directs recipients to take necessary action based on the information contained within.
**Key Points / Main Content**
* **Project Overview:**
* Proposal considered for Pune Metro Line-III (Hinjewadi-Shivajinagar) on a Design-Build-Finance-Operate-Transfer (DBFOT) basis under PPP mode.
* Project Length: 23.33 km, Total Project Cost: Rs. 6,124 crore, Concession Period: 35 years.
* VGF Sought: Up to 20% of the Total Project Cost
* **VGF Sanctioning Process:**
* VGF up to Rs.100 crore can be sanctioned by the Empowered Institution (EI).
* VGF up to Rs.200 crore can be sanctioned by the Empowered Committee (EC).
* Amounts exceeding Rs.200 crore require approval from the Finance Minister.
* **Discussion Points:**
* PMRDA clarified the decision to use PPP mode for Line-III due to private participation possibilities given the IT industry concentration in the area.
* PMRDA is undertaking a Comprehensive Traffic and Transport Study (CTTS), expected to be completed by May 2018.
* PMRDA to examine the possibility of increasing the capacity on the line by increasing frequency.
* Secretary, EA suggested that the clause providing transfer of 100% of required land prior to the Appointed Date be re-examined by PMRDA.
* **Concession Agreement:**
* Amendment suggested to indicate Concession Period reduction of 1.5% for every 1% excess in average ridership.
* Re-examine the matter of the WPI.
* Re-examine the matter of sublease period, branding clause.
* Make 4.2 and 4.3 of DCA may be amended to make it consistent with the clause 10.3.2 and clause 35.3 as suggested by NITI Aayog.
* PMRDA agreed to obtain prior written approval of the Authority for execution of the draft Financing Agreement.
* Make necessary changes in DCA to incorporate standard clauses relating to Termination Payment during construction period and Refinancing.
* Adviser, NITI Aayog suggested that scope of lease of land is much broader than license.
* MoHUA suggested that there should be design consistency while procuring Metro coaches, rolling stock etc.
* **Conditions for Approval:**
* Metro Fares charged by the Concessionaire will be in accordance of the Concession Agreement.
* Suggestion of EC to take annual average WPI.
* Re-examine the issue of no. of coaches and frequency of the rail.
* **Other Decisions:**
* The EC waived off the violation of RfQ being issued before the 'in-principle approval' of VGF.
* The EC agreed to the PMRDA’s amendment for conflict of interest limit at 15%.
* EC agreed to minimum requirement of 25% of TPC for O&M experience.
**Impact Analysis**
**PMRDA**
* **Impact:** PMRDA's proposal for VGF has been considered with specific conditions and suggestions.
* **Action Required:** PMRDA needs to address the points raised by the EC regarding the Concession Agreement, re-examine the project details, and fulfil the conditions set for in-principle approval.
**Department of Economic Affairs (Ministry of Finance)**
* **Impact:** Responsible for overseeing the Scheme for Financial Support to PPPs in Infrastructure and ensuring compliance with guidelines.
* **Action Required:** Monitor the project's progress and compliance with the EC's directives.
**NITI Aayog**
* **Impact:** Provides advisory input on the project.
* **Action Required:** Follow up on the suggested re-examinations and provide necessary assistance.
**Ministry of Housing and Urban Affairs (MoHUA)**
* **Impact:** Involved in aspects related to urban transport and infrastructure.
* **Action Required:** Follow up on the matter regarding design consistency while procuring Metro coaches, rolling stock etc.
**Concessionaire (Future Entity)**
* **Impact:** The terms and conditions discussed will ultimately affect the Concessionaire's obligations and benefits.
* **Action Required:** The future entity needs to review the Concession Agreement based on the EC's directives.
Key Entities Referenced
Scheme for Financial Support to PPPs in Infrastructure (Viability Gap Funding Scheme): The scheme under which the project received consideration for funding.
Empowered Committee (EC): Committee that considered the proposal.
Pune Metropolitan Region Development Authority (PMRDA): The authority proposing the project and seeking funding.
Pune Metro Line- III: The specific infrastructure project being discussed in the context of financial support and PPP scheme. Project is from Hinjewadi-Shivajinagar on Design-Build-Finance-Operate-Transfer (DBFOT) basis under PPP mode
Ministry of Finance: The ministry under which the Department of Economic Affairs is nested.
F. No. 2/1/2018-PPP
Ministry of Finance
Department of Economic A ffairs
(PPP Cell)
North Block, New Delhi
Dated 2" April, 2018
OFFICE MEMORANDUM
Subject: Record of Discussion of 30" Meeting of the Empowered Committee (EC) for the
Scheme for Financial Support to PPPs in Infrastructure (Viability Gap Funding Scheme) —
reg.
The undersigned is directed to enclose a copy of Record of Discussion on 30"Meeting of
the EC for the grant of VGF under the Scheme for Financial Support to PPPs in Infrastructure
held on 7" March 2018 under the Chairmanship of Secretary (EA) for information and necessary
action. ING \\
Encl: as stated above Vo
\\\w
(Manoj dholia)
Deputy Director
Ph: 23095232
To,
4. Shri. Ajay Narayan Jha, Secretary, Department of Expenditure, North Block, New Delhi
2. Shri. Amitabh Kant, CEO, NITI Aayog, Yojna Bhawan, New Delhi
3. Shri. Durga Shankar Mishra, Secretary, Ministry of Housing and Urban A ffairs
4. Shri. Kiran Gitte, CEO& MC, Pune Metropolitan Region Development Authority
Copy to:
1. Chairman, PMRDA, Pune
2. Sr. PPS to Secretary (EA)
3. Sr. PPS to Special Secretary (EA)
4. PS to JS (IPF)-@ F. No. 2/1/2018-PPP
Government of India
Ministry of Finance
Department of Economic Affairs
PPP Cell
Record of Discussion of 30" meeting of Empowered Committee (EC) for the ‘Scheme
for Financial Support to Public Private Partnerships in Infrastructure’
The 30" meeting of Empowered Committee (EC) for the Scheme for Financial
Support to Public Private Partnerships in Infrastructure chaired by Secretary, Economic
Affairs, was held on 7March 2018. The list of participants is annexed.
The EC considered the proposal from Pune Metropolitan Region Development
Authority (PMRDA) for in-principle approval of Viability Gap Funding (VGF) under the
Scheme for Financial Support to Public Private Partnerships in Infrastructure.
The EC noted that the Scheme for Support to PPPs in Infrastructure prescribes that VGF up
to Rs.100 crore for each project may be sanctioned by the Empowered Institution (EI).
proposal for VGF up to Rs.200 crore may be sanctioned by the Empowered Committee (EC).
and amounts exceeding Rs.200 crore may be sanctioned by the EC, with the approval of
Finance Minister.
Proposal from Pune Metropolitan Region Development Authority (PMRDA),
Government of Maharashtra for “in-principle” Approval
Agenda Item: Development of Pune Metro Line- II] from Hinjewadi-Shivajinagar on
Design-Build-Finance-Operate-Transfer (DBFOT) basis under PPP mode.
Project Details: Length: 23.33 km; Total Project Cost: Rs. 6,124 crore; Concession Period:
35 (including 3 years construction period) from the appointed date (extendable by another 25
years as per the provisions of the Concession Agreement)
Major Development Work / Structures: Alignment & Formation, Station Buildings, Depot,
P-Way, Traction & Power Supply, Signaling and Telecom, Rolling Stock, CPD
VGF Sought: Up to 20% of the Total Project Cost
1. Joint Secretary (IPF) informed the EC that a proposal for “in-principle” approval has
been received from Pune Metropolitan Region Development Authority (PMRDA) for
Pune Metro Line- II] from Hinjewadi- Shivajinagar on Design-Build-Finance-
Operate-Transfer (DBFOT) basis and explained the salient features of the project.
2. Secretary, EA enquired from PMRDA about the reasons for taking up Pune Metro
Line-III on PPP Mode while the other two lines of Pune Metro have been taken up on
EPC Mode. CEO, PMRDA (Project Authority) clarified that due to concentration of
IT industry in the area,there is a scope of private participation. JS(IPF) added that
Hyderabad Metro Rail Project has also been developed on PPP mode. CEO, PMRDA@ also informed that the Authority has followed the bid documents of erstwhile
Planning Commission as the base document.
3. CEO, PMRDA made a presentation on Pune Metro Line- III and explained that in the
proposed Metro network of the city, Shivaji Nagar is the junction of three lines and
until the 3“ line is operational, integration of lines will not take place. It was also
informed that Project Authority has already floated RfQ and 3 bidders have been
shortlisted. He also informed EC that Comprehensive Mobility Plan (CMP) was
initially prepared for Pune City in 2008. JS (IPF) pointed out that as per new Metro
Rail Policy, fresh CMP is required if it is older than five years. On this, CEO,
PMRDA informed EC that Comprehensive Traffic and Transport Study (CTTS) is
under process and is expected to be completed by May, 2018 which may serve the
purpose of CMP.
4. Ona question about the present mode of travel, CEO, PMRDA informed that majority
of the commuters travel by private vehicles or buses. Secretary, EA also enquired
about the rationale of preferring 3 coach metro trains when the projected ridership is
on the higher side. CEO, PMRDA clarified that with latest technology, the capacity
on the line can be augmented by increasing the frequency of trains to 90 seconds in
each direction at peak hours without increasing the number of coaches. Regarding
capacity at this frequency, PMRDA informed that it can reach upto 60,000 Peak Hour
Peak Direction Traffic (PHPDT). However, JS, Expenditure stated that at this
frequency, the maximum capacity would approximately be 40,000 PHPDT. CEO;
PMRDA assured the EC to look into the matter.
5. CEO, PMRDA highlighted that the fare structure of Line —III is on the higher side in
comparison to other two Pune Metro lines being developed under EPC mode. JS (IPF)
stated that the fares should be in consonance with the Schedule-R of draft Concession
Agreement. JS(Exp) explained that as per the Metro Railway (Operation and
Maintenance) Act, 2002, concessionaire has the right of issue fare notification at the
time of initial opening and Fare Fixation Committee (FFC) will fix all fares for any
further revision. CEO, PMRDA assured that Basic Fares and annual escalation will be
in accordance of the Schedule-R of the Concession Agreement. OSD (UT), MoHUA
added that Metro Railway Act is being amended, which will inter-alia also address
the issue of discretionary powers of FFC vis-a-vis the tariff stipulations in the
Concession Agreement for PPP projects.
6. CEO, PMRDA informed the EC about charging differential tariffs at Peak Hours. In
this regard, Secretary, EA suggested PMRDA to clearly define Peak Hours and the
extent to which fare can be different from fares of non-peak hours. Regarding land
acquisition, CEO, PMRDA explained that 90% of required land will be available to
the Concessionaire before the date of signing of Concession Agreement and the
remaining 10% before the Appointed Date. Currently, around 80% of required land is
in possession of Project Authority. Secretary, EA suggested that the clause providing
transfer of 100% of required land prior to the Appointed Date may lead to delay in
starting of the project and suggested PMRDA to re-examine the matter.
;
30" EC: March 7. 2018
Record of Discussion@ 7 While giving an overview of the draft Concession Agreement, CEO, PMRDA
explained that as a measure of risk mitigation for the Concessionaire, for every 1%
shortfall in average ridership compared to target ridership, the Concession Period is to
be extended by 1.5%. Similarly, for every 1% excess in average ridership compared to
target ridership, the Concession Period is to be reduced by 1.5%. (However, in the
draft CA submitted by PMRDA, under clause No.29.2.2, in case of 1% excess in
average ridership compared to target ridership, the Concession Period reduction has
been indicated as 1%; CEO, PMRDA informed that it is typographic error and would
be corrected to 1.5% in DCA). Adviser, NITI Aayog explained that generally target
date for traffic sampling is about the 15" year from the date of signing of Concession
Agreement and the traffic sampling is undertaken for a continuous period of 7 days
during 15 days prior to the target date. However, EC suggested that the moving
average of 3 years may be taken including two years preceding the target year.
s. PMRDA informed that a platform length of 75 meter is being planned under the
project instead of the standard 140 meter. This is because only 3-coach trains will
initially be plied on the route. JS (Exp) informed that the cost difference between the
75 and 140 meter platform is not significant. Secretary, EA opined that the standard
140 meter platform could be a better choice keeping the long-term perspective.
9. JS (Exp) pointed out that it has been proposed that the WPI for the week ending Jan
31° of each year will be reckoned for fare calculations. EC suggested that since WPI
varies significantly in 12 months, therefore the possibility of using moving average of
WPI for the past 6 or 12 months instead of point to point may be examined. PMRDA
agreed to reexamine the matter.
10. JS (Exp) further stated that, as per clause 5.2.4 of DCA, Concessionaire may not grant
any sublease for cumulative period of more than 3 years whereas normally
commercial businesses expect leases to be available for at least 5 to 10 years.
Secretary, EA suggested that leases may not be restricted to 3 years. JS (IPF)
suggested that the lease should, at the most, be co-terminus with the Concession
Period. PMRDA agreed to make the required changes. JS (Exp) also pointed out that,
Branding (as defined in clause 5.11.2 of DCA) may be allowed in rule based manner
rather than by making an Application to Authority. PMRDA clarified that it will be in
accordance with the local bye-laws and other applicable laws. EC suggested PMRDA
to re-examine the matter.
11. Adviser. NITI Aayog stated that as per clause 4.2 of the draft Concession Agreement,
damages payable shall be the sole remedy available to the Concessionaire for delay by
the Authority which is inconsistent with clause 35.3. EC suggested PMRDA to re-
examine the matter and make clause 4.2 and 4.3 consistent with clause 35.3 and
10.3.2 of draft Concession Agreement. PMRDA also agreed to incorporate the latest
clauses from the Concession Agreements of Road Sector with respect to Termination
Payment during the Construction Period and Refinancing. Adviser, NITI Aayog also
suggested PMRDA to re-examine clause 5.2.2 of the DCA in which it is mentioned
that Concessionaire shall be required to obtain the prior written approval of the
Authority for execution of the draft Financing Agreement. CEO, PMRDA agreed to
the same.@ 12. Adviser, NITI Aayog pointed out that scope of lease of land is much broader than
license and lease gives additional rights to concessionaire compared to license.
Special Secretary (EA), added that as the lease gives substantial rights to the
Concessionaire, Project Authority should ensure that there should be no problem in
Transfer of land to the Authority after the expiry of concession period.
13. MoHUA suggested that there should be design consistency while procuring Metro
coaches, rolling stock etc.
14. JS (IPF) pointed out that RfQ of the Project has been issued before the “in-principle
approval’ of VGF, which is a violation of the Scheme and Guidelines for Financial
Support to PPPs in Infrastructure. After discussion, EC decided to waive off this
violation. JS (IPF) also pointed out that Model RfQ and Model Rf{P documents issued
by MoF stipulate the limit of shareholding in case of conflict of interest at 5%.
However the PMRDA had increased the limit to 15%. EC agreed to this amendment
given that RfQ has already been issued by PMRDA. It was also suggested that option
of common tariff card for public transport could be explored for the Pune Metro
project (same metro card may be used in all lines of Pune Metro, Bus, etc.) to make
inter-modal public transport easier. Such a system is in place for the Kochi Metro
project.
15. JS (IPF) also highlighted that in the RfQ, O&M Experience with respect to Estimated
Project Cost has been reduced to 25% from 100% of Total Project Cost. PMRDA
responded that this clause has been taken from the RfQ of Hyderabad Metro Rail.
OSD (UT), MoHUA also added that requirement of 100% O&M experience will
make the bid very restrictive. EC agreed to the minimum requirement of 25% of TPC
for O&M experience.
16. EC granted ‘in-principle approval’ for VGF for the Project subject to the following
conditions:
¢ Metro Fares charged by the Concessionaire will be in accordance of the Concession
Agreement and for the purpose of Fare calculation, annual average WP! will be taken
as suggested by EC.
« The need to take approval of Govt. agencies for fare fixation/revision may be
relooked.
e The issue of number of coaches and frequency of the Rail will be re-examined.
e Clause 29.2.2 of the DCA would be amended to the effect that in case of every 1%
ridership in excess of target ridership, the Concession Period would be reduced by
1.5% (instead of 1%). Likewise, for every 1% shortfall in average ridership compared
to target ridership, the Concession Period is to be extended by 1.5% under clause
29.2.1. Suggestion of EC that the moving average of 3 years may be taken for traffic
sampling including two years preceding the target year would also be incorporated.
e Clause 5.2.4 of the DCA may be amended with regard to the period of sub-leasing.
e Clause 5.11.2 of the DCA may be amended to allow for Branding in rule-based
manner.
e Clause 4.2 and 4.3 of DCA may be amended to make it consistent with the clause
10.3.2 and clause 35.3 as suggested by NITI Aayog.
« Make necessary changes in DCA to incorporate standard clauses relating to
Termination Payment during construction period and Refinancing.
30" EC: March 7, 2018
Record of DiscussionList of Participants
Department of Economic Affairs. Ministry of Finance
Shri Subhash Chandra Garg, Secretary, Economic Affairs (In Chair)
Dr. M.M.Kutty, Special Secretary, Economic Affairs
Shri Kumar V Pratap, Joint Secretary (IPF), Economic Affairs
Shri Manoj Kumar Madholia, Deputy Director
Shri Shubham Goyal, Assistant Director (PPP)
Shri Rajesh Gupta. Section Officer (PPP)
Department of Expenditure, Ministry of Finance
vii. | Shri K. Rajaraman, Joint Secretary
ies) NITI Aayog
viii. Shri Praveen Mahto, Adviser, (PPPAU)
Ministry of Housing and Urban Affairs
1X: Shri Mukund Kumar Sinha, OSD(UT)
x. Shri Janardan Prasad,Director (UT)
Xi. Shri Ambuj Bajpai, Under Secretary (UT)
Government of Maharashtra
xii. Shri Kiran Gitte, Metropolitan Commissioner and CEO, PMRDA
xiii. Shri Chandrakant Jawale, Superintendent Engineer, PMRDA