Date: 2020-10-12Category: Not ApplicableState: Union GovernmentCountry: India
Expression of Interest Inviting Proposals for availing incentives under Fame India Scheme Phase II for deployment of EV charging infrastructure on Highways/Expressways
Executive Summary:
This Expression of Interest (EOI), issued by the Department of Heavy Industry on October 12, 2020, invites proposals for availing incentives under Phase II of the FAME India Scheme for deploying EV charging infrastructure on Highways/Expressways. It aims to support the development of EV charging infrastructure by extending capital grants. Proposals must be submitted by December 7, 2020.
Key Points / Main Content:
* **Background:**
* Phase II of the FAME India Scheme focuses on electrifying public shared transportation and supports EV charging infrastructure development.
* This EOI follows a previous one that sanctioned 2877 EV charging stations to 22 public entities within cities.
* **Coverage:**
* Proposals are invited for building and operating public EV charging infrastructure on major Highways/Expressways for the complete stretch.
* Minimum number of charging stations is defined for specific Expressways and Highways listed in the document.
* Installation of minimum one charging station at every 25 kms on both sides of Highway/Road.
* Installation of minimum one Long Range/Heavy Duty charging station at every 100 kms on both sides of Highway/Road
* **Definitions:**
* EVSE includes equipment connecting EVs to a power source with features like smart metering and network connectivity.
* EV Charging Station: Station equipped with EVSE with advanced features capable of fast or slow charging, along with associated infrastructure.
* **EV Charger Specifications:**
* Minimum requirements include fast chargers (CCS II Minimum 50 KW) and Bharat DC001 (15 KW) at every charging station.
* Long Range/Heavy Duty EV Charger: At least one charger of minimum 100 kW 200-750 V or higher to be installed after each of three Charging stations.
* **Essential Requirements for Proposal Submission:**
* Mandatory installation of 50 KW Minimum fast charger and 15 KW Bharat DC001 charger at each proposed location.
* Installation of at least one charging station at every 25 kms on both sides of the Highway and also at least one Charging Station for Long Range/Heavy Duty EVs at every 100 kms on both sides of the Highway.
* Entities must conduct a locational assessment survey and submit a report with GPS coordinates.
* Consortiums of up to 4 members are allowed, with a lead member identified for subsidy disbursement.
* Maximum Demand incentive available from DHI under FAME India Scheme Phase II is 70% of the cost of EVSE which is capped at 70% of the Bench Mark Price of each EVSE.
* Charging stations may be connected with renewable energy sources and the Grid.
* State Nodal Agency/State Government/Appropriate Commission shall fix the ceiling for Service Charge.
* **Information to be Submitted:**
* State(s) under whose jurisdiction the highway/expressway is located.
* Detailed business plan for operation and maintenance, financial status, and capability to execute the project.
* Primary locational assessment survey report with GPS Coordinates.
* **Selection Procedure:**
* A Screening Committee will evaluate proposals based on financial status and capability.
* Top 3 entities of each highway will conduct locational assessment with GPS coordinates and submit approach/methodology.
* Entities with the lowest subsidy requirement will be considered for sanction.
* Final recommendations will be placed before the Project Implementation and Sanctioning Committee (PISC) for approval.
* **Methodology to be Followed by Selected Entities:**
* Completion of the procurement process and issuance of supply order within 12 weeks of the sanction order.
* All procured EV chargers must be supplied and operational within 9 months from the supply order date.
* EV chargers must have a comprehensive warranty of three years.
* EVSE must be type tested by a NABL-accredited agency.
* **Applicable Incentive and Incentive Disbursement Mechanism:**
* Incentive will be based on the price of charging equipment indicated in the Supply Order.
* Installment 1: 20% as mobilization advance After the issue of Supply Order
* Installment 2: 80% After commissioning of EVSEs, as per bid documents
* **Procedure for Submitting the Proposal:**
* Submit a detailed proposal to the Department of Heavy Industry with a copy to the relevant authority.
* Include a primary locational assessment survey report with GPS Coordinates.
* Use the covering letter format (Annexure A) and provide necessary information (Annexure B).
* **Performance Monitoring Mechanism**
* The selected agency has to tie up with at least one real time EVSE Network Management Software Platform Provider to enable advance remote/online booking of charging slots by EV owners and share information with DHI.
* **Timeline**
* Last date of Submission of Proposal 7th December 2020
Impact Analysis:
* **Government Organizations/Public Sector Undertakings/State or Central Government DISCOMs/Oil Public Sector Undertakings/Public-Private Entities:**
* *Impact:* These entities have the opportunity to receive capital grants for deploying EV charging infrastructure on highways and expressways, promoting the use of electric vehicles.
* *Action Required:* Submit a detailed proposal, including a business plan, financial status, locational assessment, and other required information as per the EOI guidelines by December 7, 2020.
* **Department of Heavy Industry (DHI):**
* *Impact:* Responsible for evaluating proposals, forming a screening committee, and sanctioning the deployment of EV charging stations under the FAME India Scheme Phase II.
* *Action Required:* Establish a screening committee, evaluate proposals, and communicate decisions to applicant entities.
* **Electric Vehicle Owners:**
* *Impact:* Will benefit from increased availability of charging infrastructure on highways and expressways, making long-distance travel more feasible.
* *Action Required:* Monitor the development and deployment of charging stations and utilize the new infrastructure as it becomes available.
Key Entities Referenced
FAME India Scheme Phase II: Faster Adoption and Manufacturing of Hybrid Electric Vehicles in India, Phase II, a scheme by the Government of India to promote electric vehicle adoption.
Department of Heavy Industry: The department under the Ministry of Heavy Industries and Public Enterprises responsible for implementing the FAME India Scheme.
Ministry of Power: A ministry of the Government of India. Their revised guidelines and standards dated 1st October, 2019, are mentioned.
NITI Aayog: National Institution for Transforming India, a policy think tank of the Government of India. It is represented on the Screening Committee.
ARAI: Automotive Research Association of India, an automotive research and development organization. It is represented on the Screening Committee.
BEE: Bureau of Energy Efficiency, an agency of the Government of India. It is represented on the Screening Committee.
Mumbai Pune Expressway: A controlled-access highway in Maharashtra, India, connecting Mumbai and Pune.
Delhi Agra Yamuna Expressway: A controlled-access expressway connecting Delhi with Agra, located in Uttar Pradesh, India.
F.No. 1(06)/2019-NAB-II (Auto) (21349)
Dated 12th October 2020
Expression of Interest
Inviting
Proposals for availing incentives under Fame India Scheme Phase II
for deployment of EV charging infrastructure on
Highways/Expressways
Last date of Submission of Proposal
7th December 2020
Department of Heavy Industry
Ministry of Heavy Industries and Public Enterprises
Government of India
Udyog Bhawan
New DelhiExpression of Interest Inviting Proposals for availing incentives under Fame
India Scheme Phase II for deployment of EV charging infrastructure on
Highways/Expressways
Background:
Government of India has approved Phase-II of FAME India Scheme [Faster
Adoption and Manufacturing of (Hybrid &) Electric Vehicles in India], for 3 years
commencing from 1st April 2019. Its main focus is the electrification of public &
shared transportation. The detailed notification of the scheme is available at
www.dhi.gov.in.
Under Phase-II of the FAME India Scheme, Government of India (GoI) intends to
support the development of EV charging infrastructure by extending capital grant to
organizations for promoting the use of Electric Vehicles (EVs).
Department of Heavy Industry had invited an Expression of Interest dated
28th Aug 2019 from public and private entities for setting up EV charging
stations within cities. After evaluation of proposals received, the Government
sanctioned 2877 EV charging stations to 22 public entities.
This EOI is being issued for inviting proposals from any Govt.
Organization/Public Sector Undertaking (PSU) (State/Central)/Govt
DISCOM/ Oil Public Sector Undertaking and similar other Public/Private
entities to build and operate Public EV charging infrastructure on major
Highways/Expressways. For simplicity, these bodies/corporations are referred to as
‘entity’/ ‘entities’ in subsequent paragraphs of this EOI.
2. Coverage:
Proposals for installation of charging stations are invited from entities that intend to
build and operate charging infrastructure in any of the following
highways/expressway for the complete stretch of the highway/expressway (Full
Coverage):List of Expressways/Corridors, as defined in Ministry of Power’s revised
guidelines/standards dated 1st October, 2019
Total KM of the Minimum no of
Sr. No. Name of Corridor/Expressway
Highway (approx) charging stations*
1 Mumbai - Pune Expressway 100 10
Ahmadabad - Vadodara
2 100 10
Expressway
Delhi Agra Yamuna
3 200 20
Expressway
Bengaluru Mysore
4 150 14
Expressway
Bengaluru Chennai
5 300 30
Expressway
6 Surat - Mumbai Expressway 300 30
7 Agra - Lucknow Expressway 300 30
8 Eastern Peripheral expressway 150 14
9 Hyderabad ORR Expressway 175 16
Total
1775 174
List of Highways as defined by Ministry of Road Transport and Highways
National Total KM of
Minimum no
Highway the Highway
Sr. No. Name of Highways of charging
(approx)
stations*
1 Delhi - Srinagar Highway NH 44 800 80
2 Delhi – Kolkata Highway NH 19 1600 160
3 Agra - Nagpur Highway NH 44 800 80
Meerut to Gangotri Dham
4 NH-34 400 40
Highway
5 Mumbai - Delhi Highway NH 48 1250 124
6 Mumbai-Panaji Highway NH 66 600 60
NH 53 &
7 Mumbai - Nagpur Highway 700 70
NH 60
Mumbai - Bengaluru
8 NH 48 1000 100
Highway
Kolkata - Bhubaneswar
9 NH 16 450
Highway 44National Total KM of
Minimum no
Highway the Highway
Sr. No. Name of Highways of charging
(approx)
stations*
10 Kolkata - Nagpur Highway NH 6 1200 120
11 Kolkata - Gangtok Highway NH 12 700 70
12 Chennai-Bhubaneswar
NH 16 1200
Highway 120
13 Chennai - Trivendram NH 44,
750 74
Highway NH 32
14 Chennai-Ballary Highway NH 716 500 50
15 Chennai - Nagpur Highway NH 44 1150 114
16 Mangaldai (Assam) –Wakro
NH-15 670
(Arunachal Pradesh) 64
Total 13370 1370
*Installation of Minimum one charging station at every 25 kms on both sides of
Highway/Road and minimum one Long Range/Heavy Duty charging station at every
100 kms on both sides of Highway/Road, as mentioned under para 4.
The Expressways/Highways are also shown in the Map of India at Annexure-C
3. Definitions:
a. Electrical Vehicle Supply Equipment (EVSE): Electric Vehicle Supply
Equipment (EVSE) includes the electrical equipment external to the electric
vehicle that provides a connection for an electric vehicle to a power source for
charging and is also equipped with advanced features like Smart Metering,
Cellular Capability and Network Connectivity.
b. EV Charging Station: For this EOI, EV Charging Station is defined as a
station with a set of Electrical Vehicle Supply Equipment (EVSE) equipped
with advanced features like Smart metering, Cellular capability and Network
connectivity capable of fast charging or slow charging of electrical vehicles,
along with associated upstream electrical infrastructure and conforming to
National or International standards in force.
4. EV Public charging stations, identified to be installed as in Para 2 and as
defined in Ministry of Power’s revised guidelines/standards dated 1st
October, 2019, are earmarked for deployment on Highways/Expressways, as
per the coverage stated above. These charging stations will be considered forsanction to different entities after evaluation of the proposals received under
this EOI.
Type of EV Chargers mandatory at each Type of EV Chargers
charging station (atleast one at every 25 kms on Optional
both sides of Highway/Roads)
Fast chargers -
Bharat AC-001
At least one CCS II (Minimum 50 KW) or (10 KW)
CHAdeMO (Minimum 50 KW) or higher Type 2 AC (22
capacity and one DC 001 (15 KW) KW)
At least one charging station comprising of at least one CCS II (Minimum 50 KW)
Charger & one DC001 (15KW) and at least one charging station comprising of at
least one CHAdeMO (Minimum 50 KW) Charger & one DC001 (15KW) is to be
installed in each interval of four Charging Stations.
Long Range/Heavy Duty EV Charger: At least one charger of minimum 100 kW
(200-750 V or higher), each of different specification if more than one,
(CCS/CHAdeMO or any fast charger as approved by DST/BIS for above capacity)
with single connector gun to be installed after each of three Charging stations as
mentioned in the table above.
5. Essential requirements for submitting a proposal under this EOI:
a. In order to promote fast charging at major highways/expressways, installation
of 50 KW (Minimum) fast charger and 15 KW Bharat DC-001 charger is
mandatory at each location proposed by the entity; however, installation of 10
KW Bharat AC 001 and 22 KW Type 2 AC charger is optional and would
depend upon actual site requirements and business potential to ensure best use
of resources and maximization of ease of charging for the EV owners. The
proposed Charging Stations can start their operations with the minimum
number of chargers to cater to the initial requirements specified in Para-4
above; and can add more number of chargers of appropriate capacities as and
when new makes of EVs are introduced and business volume increases.
b. Each entity shall install at least one charging station at every 25 kms on both
sides of the Highway and also atleast one Charging Station for Long
Range/Heavy Duty EVs at every 100 kms on both sides of the Highway, inaccordance with the Ministry of Power’s revised guidelines/standards for
charging infrastructure for Electric Vehicles (EVs), dated 01st October, 2019.
c. Entities shall conduct locational assessment survey and identify feasible
locations / stretches along the identified highways to set up charging stations.
Bidders are required to submit primary locational assessment survey report
(with GPS Coordinates) along with their proposal to DHI.
d. Entities may submit their proposal in a consortium. Such a consortium may
have a maximum of 4 members and the consortium shall be required to
identify a lead member which may be a Govt. Organization/PSU/DIS
COM/Oil PSU or a Private Entity. In such a case, subsidy shall be disbursed
to the lead member of the consortium on behalf of the consortium as a whole.
e. The maximum Demand incentive available from DHI under FAME India
Scheme Phase II is 70% of the cost of EVSE which is capped at 70% of the
Bench Mark Price of each EVSE, (will be communicated separately).
Note: Cost of upstream electrical infrastructure, including the cost of
transformer required for bringing power supply to EV charging station, will
not be covered as cost of EVSE.
f. It is advised that, where feasible, charging stations may be connected with
renewable energy source of required capacity, as per MNRE guidelines, so as
to ensure grid stability and green energy for electric vehicles. Such Public
Charging Stations (PCSs) may also be connected to the Grid to ensure round
the clock operation.
g. In such cases where the Public Charging Stations (PCSs)/Fast Charging
Stations (FCSs) have been installed with Government Incentive (Financial or
otherwise), State Nodal Agency /State Government/Appropriate Commission
shall fix the ceiling for Service Charge to be charged by such PCSs/FCSs as
per “Charging Infrastructure for Electric Vehicles (EVs)-Revised Guidelines
and Standards” dated 01.10.2019 issued by MoP.
6. Information to be submitted:
6.1 State/States under whose jurisdiction the highway/expressway is located.
6.2 Detailed business plan for operation and maintenance of the proposed
charging stations; Financial Status of the entity; brief write up about capability
of the entity to execute the project in minimum timeframe.
6.3 Primary locational assessment survey report (with GPS Co-ordinates) of the
proposed site for installation of the charging station.7. Selection Procedure:
a. DHI will form a Screening Committee for evaluation of the proposals
submitted by the entities under the chairmanship of Joint Secretary, DHI, with
members from NITI Aayog, M/o Power, ARAI, BEE etc.
b. Entities are required to submit the proposal for the full stretch of a highway.
c. The proposals would be evaluated based on the information sought in para 6,
in the following two stages:
Stage-I –
S.No Information Maximum Evaluation criteria
score
1 Financial 50 Turnover of over Rs. 50 crore – 100%
status of entity score. Turnover between Rs. 1-50
crore – proportional score keeping Rs.
50 crore as denominator
2 Capability 50 More than 20 public charging stations
deployed –100% score. 01-20 charging
stations – proportional score with 20 as
denominator
The top 3 entities of each highway are to be empaneled for Stage-II.
Stage-II- final selection: The empaneled entities for each highway will be
given 8 weeks time to conduct locational assessment with GPS coordinates.
The information that needs to be submitted at this stage is as below:
S. No Information to be submitted Remarks
1 Locational assessment Detailed location assessment of the
entire highway (on both sides) for
which empaneled, with GPS
coordinates. MoU/in principle
agreement for land indicated in the
location assessment with the land
owning entityS. No Information to be submitted Remarks
2 Approach and methodology -Land acquisition/ renting
arrangements- Execution plan to meet
the timelines indicated in stage-I
3 Capital subsidy asked for per Any bid with subsidy requirement
charging station – benchmark more than benchmark price is liable to
subsidy to be indicated and be rejected.
charging fee cap indicated in
the bidding document
d. The entities with the lowest requirement of subsidy will be considered for
sanction for installation and operation of charging stations at the
Expressways/Highways. Final recommendations of the Screening committee
will be placed before the Project Implementation and Sanctioning Committee
(PISC) for approval.
e. With the approval of PISC, the proposal will be processed in the Department
of Heavy Industry for approval of competent authority.
f. After the approval of competent authority, each applicant entity will be
informed about the total number of charging stations sanctioned for the
selected highways / expressways, with a request to initiate the procurement
process.
g. DHI reserves the full right regarding sanction of total number of Charging
Stations to the entity depending upon their detailed business plan for operation
and maintenance of proposed Charging Stations.
8. Methodology to be followed by selected entities
a. Each entity should ensure completion of the procurement process for the the
approved number of EV Chargers and issue supply order to the selected bidder
within 12 weeks from the issue of sanction order. Failure to stick to this
timeline may result in cancellation of the sanction order without any further
notice.
b. Each entity will be responsible for ensuring that all procured EV chargers are
supplied and put in operation within a maximum period of 9 months from the
date of issue of supply order.
c. The EV Charger (EVSE) shall carry comprehensive warranty of three years.
d. Electric Vehicle Supply Equipment (EVSE) shall be type tested by an
agency/lab accredited by National Accreditation Board for Testing andCalibration Laboratories (NABL) from time to time. Further, the entities must
comply with technical and safety standards/measures, and meter Regulations
of Central Electricity Authority (CEA) for charging station of electric vehicle.
9. Applicable Incentive and incentive disbursement mechanism
The applicable incentive will be decided based on the price of the charging
equipment as indicated in the Supply Order issued by the entity/entities. However,
Department of Heavy Industry reserves the right to further restrict the incentives
based on pricing of different types of chargers discovered through competitive
bidding, (to be informed separately). Once the applicable incentive is finalized and
conveyed, the Department of Heavy Industry will release the same as per following:
Installment No The Milestone to be completed Percentage of Demand
Incentive to be Released by
DHI
After the issue of Supply Order
1 20%
as mobilization advance
After commissioning of
2 80%
EVSEs, as per bid documents
The PISC shall have full powers to alter the percentage of incentive,
depending upon the availability of funds under the Union Budget.
10. Procedure for submitting the proposal under this EOI:
a. Each entity is required to submit a detailed proposal to the Department of
Heavy Industry, with a copy to the respective authority under whose
jurisdiction the highway/expressway is located, to avail incentives under
phase II of FAME India scheme.
b. Each entity is required to submit a primary locational assessment survey
report (with GPS Co-ordinates), along with their proposal, to DHI. The
entity/entities, before submitting the proposal, are required to identify suitable
locations (with GPS Co-ordinates) for installation of EV charging stations,
and the same should be included in the proposal. It will be the responsibility
of the concerned entity to arrange the land/place/location for installation of
EV Charging Stations, in collaboration with respective authority, under whose
jurisdiction the highway/expressway pertains, or owner of such land.c. The proposal submitted by the entity/entities should have a covering letter, as
mentioned at Annexure-A, along with other necessary information, as
mentioned at Annexure-B.
d. The complete proposal, along with relevant documents, shall be submitted to
the Under Secretary (AEI), D/o Heavy Industry at the following address:
The Under Secretary (AEI)
Department of Heavy Industry
Room No. 387, Udyog Bhawan, New Delhi – 110011
Tel. No. 011-23061340
And complete proposal, along with relevant documents may also be sent to
the email thanglian.lal@gov.in, aei-dhi@nic.in
11.Performance monitoring mechanism
The selected agency for the development of charging station has to tie up with at
least one real time EVSE Network Management Software Platform Provider to
enable advance remote/online booking of charging slots by EV owners. Such real
time information to EV owners should also include information regarding location,
type, the number of chargers installed, cost of charging, available slots, etc. (cost has
to be borne by the entity itself).
All such entities are also mandatorily required to share this information with the
Department of Heavy Industry for a common Charging Station App being developed
by DHI for all charging Stations in the country.
12. Timeline to be followed by selected agencies for deployment of charging
infrastructure
All selected agencies will be required to follow the following timeline for the
deployment of charging infrastructure:
S.No Activity Timeline
1 Issue of EOI for charging Infrastructure T
0
Last date of submission of interest in response to EOI
2 T +8 weeks
0
, to DHIS.No Activity Timeline
Finalization of selection process and issue of sanction T +20 weeks, say
0
3
letter by DHI T
4 Issue of Tender for inviting bid T + 3 weeks
5 Last date of submission of bid by the interested
T + 9 weeks
bidder/supplier
6 Finalization of Bidding Process and issue of supply T + 12 weeks
order Say M
7 Completion of installation of all chargers as per the M+9
approved DPR(s) months(Maximum)
13.Resolution of Disputes
Any dispute shall be resolved by mutual discussion and reconciliation. In case
of difference of opinion, the decision of the Department of Heavy Industry shall
be final.ANNEXURE- A
Format of Covering Letter
(To be given on the letterhead of the organization)
To
The Under Secretary (AEI)
Department of Heavy Industry
Room No. 379, Udyog Bhawan, New Delhi – 110011
Subject: Proposal for setting up EV charging stations in response to EOI issued by
DHI dated ________
Sir,
Please refer to Expression of Interest issued by Department of Heavy Industry's
dated XX/XX/XXXX for inviting proposals for extending demand incentives for
deployment of charging stations under FAME India scheme Phase II.
In response to this EoI, we are hereby submitting our proposal, in the prescribed
format, for consideration of the Department of Heavy Industry.
We agree to abide by the conditions outlined in the said EOI.
We hereby declare that our proposal submitted in response to this EOI is made
in good faith and the information contained is true and correct to the best of our
knowledge and belief. If any of the information provided here is found to be
misleading, we are liable to be disqualified from the EOI selection process.
Sincerely,
Name:
Designation:
Signature:
AUTHORISED SIGNATORY’S SIGNATURE WITH SEALANNEXURE-B
Format for proposals to be submitted by tan entity in response to EOI
A. General details, along with documentary proof:
Vehicular density on highway (No of vehicles passing on the highway per
day)
Details about the existing tariff of electricity for charging of Electric
vehicles.
B. Description of Project Proposal: Detailed business plan for operation and
maintenance of the proposed charging stations; Financial Status of the
entity/Consortium (details of each entity of the consortium); brief write up
about capability of the entity to execute the project in minimum timeframe.
C. State/States under whose jurisdiction the highway/expressway is located.
D. Primary locational assessment survey report (with GPS Co-ordinates) of the
proposed site for installation of the charging station.
E. The number of EV chargers for which funding is sought under the scheme:
Maybe attached as a separate sheet.
Name of Charging Type of Location Power Number
Corridor/Expressway/Highways Station EV requirement of EV
Number charger and its chargers
availability
----------
- no of
Total
EV
chargersFor example:
Charging Type of EV charger Location Number of EV
Station chargers
Number
1 CCS &Chademo- 1Nos 2
DC-001 1 nos
2 CCS & Chademo - 1Nos 3
DC-001 1 nos
Ac001 1 nos
3 CCS & Chademo - 1Nos 7
DC-001 5 nos
Type 2 AC-1 nos
4 Total 12
F. Funding commitment:
The selected agency needs to inform as to how they plan to arrange the remaining
fund required for the project over and above the demand incentive available from
DHI.
G. Details about the arrangement of upstream electricity supply for EV charging.
H. Any other information in support of proposal
I. Details of Annexures
Based on the information collected, the final allotment of EV chargers to selected
entities will be informed by the Department of Heavy Industry. Once the entity
receives the allotment letter, it needs to initiate the procurement process,
which needs to be completed in a time bound manner, as per the timelines
mentioned, and supply order issued to the selected bidder.
Name:
Designation:
Signature:
AUTHORISED SIGNATORY’S SIGNATURE WITH SEALANNEXURE-C