See Full Document Text
No. RW/NH-33044/02/2023-S&R (Comp No 218375)
Government of India
Ministry of Road Transport & Highways
Transport Bhawan, 1, Parliament Street, New Delhi-110001
Dated: 09th July, 2025
Office Memorandum
Sub: Invitation for Public Comments on Proposed modified Document for Request for
Proposal (RFP) for appointment of Authority's Engineer in respect of National
Highways and centrally sponsored road works proposed to be implemented on EPC
mode of contract.
The Ministry had issued Request for Proposal (RFP) for appointment of Authority's
Engineer in respect of National Highways and centrally sponsored road works proposed to
be implemented on EPC mode of contract on 15.02.2019.
The Ministry is in the process of amending the above RFP. A draft proposed RFP document
is enclosed herewith for reference.
Comments/ suggestions on the proposed RFP, if any, may kindly be submitted within
twenty one (21 ) days from the date of this communication i.e. upto 30.07.2025, to the email
address srdivisionmorth@gmail.com .
Encl: As above,
('Ak1l Ahmad)
Superintending Engineer (S&R)
For Director General (RD) & SS
To
NIC- for uploading on Ministry website under 'whats new' I any other appropriate
place, for obtaining Public comments
Copy for kind information to:
1. Sr. PPS to Secretary (RT&H)
2. Sr PPS to DG(RD)&SS
3. Sr. PPS/PPS to AS (RT&H)/ AS&FA
4. PS to all ADGs / JSsModel Tender Document
for
Consultancy Services
Authority Engineer for
supervision of *****
on EPC mode
Request for Proposal (RFP)
Government of India
Ministry of Road Transport &
Highways
< Address of Agency>
< July 2025>Table of Contents
SECTION I: R EQUEST FOR PROPOSAL LETTER (RFPL) ..................................................
Request for Proposal Letter RFPL) .................................................................................................
The RFP Document ....................................................................................................................
1.1. Consultants must read the complete ‘RFP Document’ ...............................................................
1.2. Availability of the RFP Document............................................................................................
1.3. Clarifications .......................................................................................................................
Eligibility and Qualification Criteria for Participation in this RFP ........................................................
Purchase Policies of the Government ............................................................................................
4.1. Relaxation in Prior Turnover and Experience to Startups ...........................................................
Pre-Proposal Conference .............................................................................................................
Submission of Proposals ..............................................................................................................
Proposal Opening ......................................................................................................................
APPENDIX RFPL: TENDER INFORMATION SUMMARY (TIS) .........................................
SECTION II: INSTRUCTIONS TO CONSULTANTS (ITC) ....................................................
The RFP Document ....................................................................................................................
1.1. Basic Tender Details .............................................................................................................
1.2. Interpretations, Definitions, Abbreviations and Document Conventions .......................................
1.3. Overview of Contents ...........................................................................................................
1.4. Sections of the RFP Document ...............................................................................................
1.5. Forms (To be filled, digitally signed, and uploaded by Consultants) ............................................
1.6. Other Formats .....................................................................................................................
Procuring Entity - Rights and Disclaimers ......................................................................................
2.1. The Procuring Entity .............................................................................................................
2.2. Right to Intellectual Property and confidentiality ......................................................................
2.3. Right to Reject any or all Proposals ........................................................................................
2.4. Disclaimers .........................................................................................................................
Consultants – Participation in this RFP process ............................................................................
3.1. Eligibility to Participate .........................................................................................................
3.2. Conflict of Interest ...............................................................................................................
The Terms of Reference (TOR) and Form of Contract .....................................................................
4.1. Facilities to be provided by the Procuring Entity .......................................................................
4.2. Forms of BOQ/ Contract and Selection Methods .......................................................................
4.3. Inputs of Key Experts ...........................................................................................................
Proposal Prices, Taxes and Duties ................................................................................................
5.1. Prices .................................................................................................................................
5.2. Firm/ Variable Price ..............................................................................................................
5.3. Taxes .................................................................................................................................
5.4. Payments ............................................................................................................................
Downloading the RFP Document; Corrigenda and Clarifications .......................................................
6.1. Downloading the RFP Document ............................................................................................
6.2. Corrigenda/ Addenda to RFP Document ..................................................................................
Table of Contents [i]
26.3. Clarification of the RFP Document ..............................................................................................
Pre-Proposal Conference .................................................................................................................
Preparation of Proposals .................................................................................................................
8.1. The Proposal ...........................................................................................................................
8.2. Documents comprising the Proposal: ..........................................................................................
8.3. Proposal Validity ......................................................................................................................
8.4. Bid Security - Related Documents ..............................................................................................
Signing and Uploading Proposals....................................................................................................
9.1. Relationship between Consultant and eProcurement Portal ...........................................................
9.2. Signing of Proposal ..................................................................................................................
9.3. Submission/ uploading of Proposals.
9.4. Modification, Resubmission and Withdrawal of Proposals ..............................................................
Proposal Opening ..........................................................................................................................
Evaluation of Proposals and Award of Contract...................................................................................
11.1. General norms ........................................................................................................................
11.2. Evaluation of Proposals .............................................................................................................
11.3. Techno-commercial Evaluation ..................................................................................................
11.4. Financial Proposals Evaluation and Ranking of Proposals ...............................................................
Contract Negotiation .......................................................................................................................
12.1. Invitation to Negotiate ..............................................................................................................
12.2. Verification of Original Documents .............................................................................................
12.3. Availability of Key Experts: ........................................................................................................
12.4. Technical Negotiations ..............................................................................................................
12.5. Financial Negotiations ........................................................................................................... 36
12.6. Conclusion of Negotiations
Award of Contract ..........................................................................................................................
13.1. Letter of Award (Acceptance - LoA) and Signing of Contract ..........................................................
Grievance Redressal/ Complaint Procedure ........................................................................................
Code of Integrity in Public Procurement, Misdemeanors and Penalties ...................................................
SECTION III: APPENDIX TO INSTRUCTIONS TO CONSULTANTS (AITC) ..............................
SECTION IV: GENERAL CONDITIONS CONTRACT (GCC) .............................................
General ........................................................................................................................................
1.1. Tenets of Interpretation ............................................................................................................
1.2. Definitions...............................................................................................................................
1.3. Document Conventions .............................................................................................................
1.4. Abbreviations: .........................................................................................................................
The Contract .................................................................................................................................
2.1. Language of Contract ...............................................................................................................
2.2. The Entire Agreement ..............................................................................................................
2.3. Severability .............................................................................................................................
2.4. Relationship between Parties .....................................................................................................
2.5. Contract Documents and their Precedence ..................................................................................
2.6. Modifications/ Amendments, Waivers and Forbearances ...............................................................
Governing Laws and Jurisdiction ......................................................................................................
3.1. Governing Laws and Jurisdiction ................................................................................................3.2. Changes in Laws and Regulations ..........................................................................................
Communications ..........................................................................................................................
4.1. Communications .................................................................................................................
4.2. Persons signing the Communications ......................................................................................
4.3. Address of the parties for sending communications by the other party ........................................
Consultant’s Obligations and restrictions on its Rights .......................................................................
5.1. Changes in Constitution/ financial stakes/ responsibilities of a Contract’s Business ........................
5.2. Obligation to Maintain Eligibility and Qualifications ...................................................................
5.3. Restriction on Potential Conflict of Interests ............................................................................
5.4. Consequences of breach by Constituents of a Consultant ..........................................................
5.5. Assignment and Sub-contracting ............................................................................................
5.6. Obligation to Indemnify Procuring Entity .................................................................................
5.7. Confidentiality, Secrecy and Property and IPR Rights ................................................................
5.8. Performance Bond/ Security ..................................................................................................
5.9. Permits, Approvals and Licenses ............................................................................................
5.10. Insurances ..........................................................................................................................
5.11. Accounting, Inspection and Auditing .......................................................................................
5.12. Book Examination Clause ......................................................................................................
5.13. Legal Compliance ................................................................................................................
5.14. Custody and Return of the Procuring Entity’s Assets loaned to Consultant ...................................
Procuring Entity’s Obligations .........................................................................................................
6.1. Assistance by the Procuring Entity ..........................................................................................
6.2. Facilities to be provided by the Procuring Entity .......................................................................
6.3. Counterpart Personnel ..........................................................................................................
6.4. Payment Obligation .............................................................................................................
Scope of Services and Performance Standards .................................................................................
7.1. Scope of Services .................................................................................................................
7.2. Eligible Services ...................................................................................................................
Deployment of Resources ............................................................................................................
8.1. Site and Assets thereon ........................................................................................................
8.2. Key and Non-key Personnel ...................................................................................................
8.3. Equipment and Tools of Trade ...............................................................................................
Delivery of Services and delays ....................................................................................................
9.1. Works plan ..........................................................................................................................
9.2. Commencement of Services ..................................................................................................
9.3. Contract Management ..........................................................................................................
9.4. Delivery of services, Time of Delivery and Extensions Thereof ...................................................
9.5. Damages and Deductions Thereof ..........................................................................................
9.6. Force Majeure .....................................................................................................................
Prices and Payments .......................................................................................................................
10.1. Prices .................................................................................................................................
10.2. Taxes and Duties .................................................................................................................
10.3. Terms and Mode of Payment .................................................................................................
10.4. Withholding and lien in respect of sums claimed ......................................................................
10.5. Payments to Consultant ........................................................................................................
10.6. Suspension of Payments .......................................................................................................
10.7. Payment Against Time-Barred Claims .....................................................................................10.8. Commissions and Fees .........................................................................................................
Table of Contents [iii]
Resolution of Disputes ................................................................................................................
11.1. Disputes and Excepted Matters ..............................................................................................
11.2. Excepted Matters .................................................................................................................
11.3. Adjudication .......................................................................................................................
11.4. Conciliation of disputes .........................................................................................................
11.5. Arbitration Agreement ..........................................................................................................
Defaults, Breaches, Termination, and closure of Contract ....................................................................
12.1. Termination due to Breach, Default, and Insolvency .................................................................
12.2. Termination for Default/ Convenience of Procuring Entity or Frustration of Contract .....................
12.3. Closure of Contract ..............................................................................................................
Code of Integrity in Public Procurement; Misdemeanors and Penalties ..............................................
13.1. Code of Integrity ..................................................................................................................
13.2. Obligations for Proactive Disclosures ......................................................................................
13.3. Misdemeanors ....................................................................................................................
13.4. Penalties for Misdemeanors ...................................................................................................
SECTION V: SPECIAL CONDITIONS OF CONTRACT (SCC) ...............................................
SECTION VI: TERMS OF REFERENCE .............................................................................
Section VI-A: List of Key Experts and Required Qualifications: ..............................................................
SECTION VII: EVALUATION/ SCORING CRITERIA ...........................................................
BIDDING FORMS ..........................................................................................................
TECHNICAL PROPOSAL ............................................................................................
FORM T-1: PROPOSAL FORM (COVERING LETTER) .........................................................
FORM T-1A: CONSULTANT’S COMMERCIAL INFORMATION .......................................
FORM T-2: CONSULTANT’S ORGANISATION AND EXPERIENCE .................................
FORM T-3: COMMENTS AND SUGGESTIONS ON THE TERMS OF
REFERENCE, COUNTERPART STAFF, AND FACILITIES TO BE PROVIDED BY THE
PROCURING ENTITY 114
FORM T-4: DESCRIPTION OF APPROACH, METHODOLOGY AND WORK PLAN
INRESPONDING THE TERMS REFERENCE ..................................................................
FORM T-5: WORK SCHEDULE AND PLANNING FOR DELIVERABLES ....................................
FORM T-6: TEAM COMPOSITION, ASSIGNMENT, AND KEY EXPERTS’ INPUTS ...............
Annex to Form T-6: Key Expert Curriculum Vitae (CV) ................................................................................
FORM T-7: TERMS AND CONDITIONS - COMPLIANCE ........................................................
FORM T-8: CHECKLIST FOR CONSULTANTS .................................................................
FORM T-9A: BANK GUARANTEE FORMAT FOR EARNEST MONEY DEPOSIT ....................... 5
FORM T-9B: BID SECURING DECLARATION .......................................................................
FORM T-10: INTEGRITY PACT ..........................................................................................
FORMATS ...................................................................................................................
FORMAT 1: CONTRACT FORM .....................................................................................
APPENDIX A: DESCRIPTION SERVICES ........................................................................Terms of Reference ....................................................................................................................
Approach and Methodology .........................................................................................................
Work Schedule and Planning for Deliverables ................................................................................
APPENDIX B: KEY EXPERTS ...........................................................................................
APPENDIX C – REMUNERATION COST ESTIMATES ....................................................
Annex to Appendix C: Breakdown of Agreed Fixed Rates in Consultant’s Contract ......................................
APPENDIX D-1: BANK GUARANTEE FORMAT FOR PERFORMANCE SECURITY ...................
APPENDIX D-2: BANK GUARANTEE FORMAT FOR ADVANCE PAYMENT ............................
FORMAT 2: CERTIFICATION BY PROSPECTIVE ARBITRATORS .........................................
FORMAT 3: AUTHORIZATION TO ATTEND PRE-PROPOSAL CONFERENCE ........................
Table of Contents [v]Page left blank intentionallySection I: Request for Proposal Letter (RFPL)
Request for Proposal Letter (RFPL)
The President of India through the Secretary (RT&H) / Chairman NHAI/ MD NHIDCL,
(hereinafter referred to as ‘the Authority’, ‘the Head of Procurement’, ‘the
Procuring Entity’ and ‘the Procuring Organisation’ respectively), invites proposals
(hereinafter referred as ‘the Proposal(s)’) from eligible consultants on the basis of
International Completive Bidding (please see Tender Information Summary (TIS)
appended to this letter for reference), for entering into a contract for the delivery of
Consultancy Services for engaging an Authority Engineer (AE) (hereinafter referred
to as ‘the Services’), using the selection method as specified in TIS. This Request for
Proposal (RFP) Document, reference number, RFP No./ xxxx (hereinafter referred to as
‘the RFP Document’), gives further details.
The RFP Document
2.1. Consultants must read the complete ‘RFP Document’.
This RFPL, an integral part of the RFP Document, serves the limited purpose of invitation
and does not purport to contain all relevant details for submitting Proposals. ‘Tender
Information Summary’ (TIS) appended to this letter gives a salient summary of the
relevant information, including the Type of BPQ/ Contract, basic eligibility and
Selection Method to evaluate RFP. Any generic reference to RFPL shall also imply a
reference to TIS as well. However, Consultants must go through the complete RFP
Document for details before submission of their Proposals.
2.2. Availability of the RFP Document The RFP Document shall be published on “INFRACON”
(www.infracon.nic.in)/ e-Procurement portal (https://eprocure.gov.in) for download aftert he
date and time of the start of availability till the deadline for availability as mentioned in TIS. The
Consultant who download the RFP document from the website will be required to pay the
non- refundable fee of Rs. 5,000/- towards cost of RFP at the time of the submission of the
Bid proposal through Demand Draft in favour of MoRTH/NHAI/NHIDCL/Agency. If the
Procuring Entity happens to be closed on the deadline for the availability of the R FP Document,
the deadline shall not be extended. Any query/ clarification regarding downloading RFP
Documents and uploading Proposals on the e-Procurement portal may be addressed to
…………….. (please refer to TIS for details).
As such before submitting the proposal the Consultant shall mandatorily register and
enlist themselves (the firm and all key personnel), on the MoRTH portal “INFRACON”
and furnish registration details along with its RFP. A copy of Infracon Operation
Procedure is also enclosed for bidder’s reference. All the bidders registered on Infracon
shall form a Team on Infracon and which would be assigned unique Infracon Team
ID. Bidders while submitting the proposal shall quote the Infracon Team ID. Bid must
be submitted online at e-tender portal of <Agency> https://eprocure.gov.in
2.3. Clarifications
A Consultant may seek any clarification of the RFP Document through the eProcurement
1Portal before the date and time stipulated in TIS (or, if not mentioned, before 14 days
of the deadline for the proposal submission). This deadline shall not be extended in
case of any intervening holidays. No other means of submission of queries shall be
entertained.
Eligibility and Qualification Criteria for Participation in this RFP
Consulting firms meeting the eligibility criteria as mentioned in Appendix-1
to Tender Information Summary (TIS) are only eligible for applying for this
assignment. Firms not meeting these criteria, need not apply.
Purchase Policies of the Government
1)
Central Government policies restrict the participation of entities from i) Certain
countries sharing land borders with India and ii) Countries that restrict the participation
of Bidders from India. Consulting firms shall submit the declaration regarding these
restrictions as mentioned in Appendix-1 to Tender Information Summary
(TIS). They should ensure that they continue to comply with such declarations till
completion of bidding process.
Pre-Proposal Conference:
If indicated in TIS, Consultants are requested to attend a Pre-Proposal conference to
clarify the RFP's technical requirements and commercial conditions at the time, date,
and place mentioned therein.
Submission Proposals:
1) Proposals must be uploaded by the submission deadline mentioned in TIS. If the
office happens to be closed on that date, this deadline shall not be extended. Further
details are given in ITC.
2) Integrity Pact: If indicated, in the TIS, all Consultants shall have to sign the Integrity
Pact with the Procuring Entity as per ‘Form T-10: Integrity Pact’. In such cases,
Proposals without a signed Integrity Pact shall be rejected.
Proposal Opening
Proposals received shall be opened online on or after the specified date and time in
TIS. If the office is closed on the specified date of opening of the Proposals, the opening
shall be done on the next working day at the same time.
Note: For further details, please refer to appended TIS and the complete RFP Document.
Digitally Signed by
Tender Inviting Authority (TIA)
[Insert Name, Designation, and contact details of Tender Inviting Authority]
Appendix: Tender Information Summary (TIS)Appendix to RFPL: Tender Information Summary (TIS)
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services
(Ref ITC-clause 1.4)
Tender Information Summary (TIS)
1.0 Basic Tender Details
Tender Title/
CONSULTANCY SERVICES FOR AUTHORITY’S ENGINEER
Name of
FOR SUPERVISION OF ****************** ON EPC
Assignment
Tender RFP No./ xxxx Tender ID [Fill]
Reference
Number
Tender Type International Tender Category Consultancy
Competitive Services
Bidding
No. of Covers [Two Covers] Product Category [Consultancy]
Selection [QCBS] Appointing Authority for Head of the
Method Based on Arbitration Procuring
Height The Organization
score Secretary/ The
assessed Chairman Secretary/
based on NHAI/ MD Chairman
Technical NHIDCL NHAI/ MD
NHIDCL
and
Financial
Criteria. The
financial
criteria will
consist of
Performanc
e BG and
Financial
quote
Organisation: MoRTH/NHAI/ The Procuring Entity: Procuring Entity
NIHIDCL/BRO/
PWD
Authority on President of Through the CE/RO/ General Head of
whose behalf India through Manager as the case may be Procurement
RFP is invited the secretary The
or chairman concerned
NHAI or MD RO/ General
NHIDCL as Manager as
the case may the case may
be be
3Tender Inviting Address [Fill]
Authority (TIA)
1 Based on BOQ Template: Item-wise or Mixed or Item-rate Templates2.0 Critical Dates (ITC-clauses 6, 7; 8; 9, and 10)
For the schedule of dates for the Pre-proposal Conference, if any, please refer to
Section 7.0 below
Published [Fill up] Proposal Validity (Days from [fill up both periods
Date the date of Proposal (default 120 days) in
Opening) – ITC-clause 8.3 days and the
calculated date]
Document [Normally Document Download End [Normally up to a few
Download start of Date & Time hours/ one day before
Start Date & business on the time of Proposal
Time the day Opening]
after
publishing]
Clarification [Normally Clarification End Date & [Normally not later
Start Date & start of Time than 7 days before the
Time business on Proposal submission
the day after deadline to give time
publishing] to the Procuring Entity
for a response]
Proposal [Normally Proposal Submission 45 days from date of
Submission start of Closing Date & Time invitation
Start Date & business on
Time the day after
publishing]
Proposal Opening (techno- Next date of bid closing date
commercial Proposal) Date &
Time
Proposal Opening (Financial [To be intimated later]
Proposal) Date & Time
3.0 Terms of Reference (ITC-Clause 4)
Consignee/ [Fill] GSTIN Code of Consignee [Fill]
State:
Period of Construction Period+ maintenance period
Contract of Civil contract.
Service Consultancy Services for Authority Engineer
Details:
4.0 Obtaining the RFP Document and clarifications (ITC-Clause 6)
eProcurement https://eproc fill the contact detailsPls
and Procuring ure.gov.in/e
Entity’s Portal procure/app
and helpdesk [Fill in your organisation’s portal URL and helpdesk if the RFP
Document download/ submission facility is also provided there]Cost of RFP Rs 5000/-
Document
(INR)
Office/ [Same as TIA above]
Contact
Person/ email
for
clarifications
5.0 Pre-Proposal Conference (ITC-clause 7)
Is a Pre-Proposal Conference yes
proposed to be held?
Place, time, and date of the [Fill if it is 'Yes' above and delete the row if it is 'No'
Pre-Proposal Conference above. If only a video-conference is to be held, then
mention this fact along with credentials of the
meeting, e.g., Meeting Link, Meeting Number and
Password]
Place, time, and date before [Fill if it is ‘Yes’ above and delete the row if it is ‘No’
which Written queries for the above. ]
Pre-Proposal conference must
be received
Place, time, and date before [Fill if it is ‘Yes’ above and delete the row if it is ‘No’
which registration of above]
participants for the Pre-
Proposal conference must be
received
6.0 Preparation and Submission and Opening of Proposals (ITC-clause 8, 9 and
10)
Proposals to President of India, Through Head of Procurement, Procuring Entity
be addressed
to
Instructions for All the bidders registered on Infracon shall form a Team on Infracon and
which would be assigned unique Infracon Team ID. Bidders while
submitting the proposal shall quote the Infracon Team ID.
Online All the bidders registered on Infracon shall form a Team on Infracon and
which would be assigned unique Infracon Team ID. Bidders while
submitting the proposal shall quote the Infracon Team ID.
Bid must be submitted online at e-tender portal of <Agency>
https://eprocure.gov.in on or before <Time, Date
Proposal
Submission
Language of [English] Bid Validity [120 days Bid
Submission from
opening date]
Proposal [On e-procurement portal(s) mentioned above]
Opening
Place
7.0 Documents relating to Bid Security (ITC-clause 8.4) and Performance Security
(ITC-clause 13.1.2)Bid Security NIL Is Bid Securing yes
(EMD) Amount Declaration permitted
in INR: in lieu of Bid Security
Performance 10% of the Bid/ Performance NA
contract Amount
Security Security to be
addressed/ in favour of
Form of Bid/ NA
Performance
SecurityAppendix-1 to TIS: Eligibly Criteria
1.1 Consultants should meet the following eligibility criteria as of the date of their
RFP submission and should continue to meet these until the subsequent RFP process
and contract award. Consultants shall be required to demonstrate fulfilment of the
Eligibility Criteria in clause 1.2/ Form 1.2 (Eligibility Declarations). Consultant unless
otherwise stipulated in:
1) must be:
(a) a natural person (an individual Consultant), a private entity (a Consulting
Company/ LLP /Partnership firm/ Society registered under an applicable Act
in India), a public Entity (Government-owned enterprise or institution),
Joint Venture/ Consortium (an association of several persons, firms, or
companies - hereinafter referred to as JV/C).
(b) a Consultancy Services provider with valid registration regarding GSTIN,
PAN, EPF, ESI, Labour, or equivalent registration certificate issued by the
concerned authority/government as applicable to the subject Services.
2) must:
(a) not be insolvent, in receivership, bankrupt or being wound up, not have its
affairs administered by a court or a judicial officer, not have its business
activities suspended and must not be the subject of legal proceedings for
any of aforesaid reasons.
(b) (Including their affiliates, subsidiaries, or contractors/ sub-consultants for
any part of the contract):
i) Not stand declared ineligible/ blacklisted/ banned/ debarred by the
MoF/MoRTH/NHAI/NHIDCL/BRO/PWD from participation in its
procurement processes. The applicability of debarment of firm from
bidding shall be as per Ministry of finance OM No F.1/20/2018-PPD
dated 02.11.2021 and its modification if any, thereof ; and/ or
ii) Not be convicted (within three years preceding the last date of RFP
submission) or stand declared ineligible/ suspended/ blacklisted/
banned/ debarred by appropriate agencies of the Government of India
from participation in procurement processes of all its entities, for:
offences involving moral turpitude in business dealings under the
Prevention of Corruption Act, 1988 or any other law; and/or
offences under the Indian Penal Code or any other law for causing
any loss of life/ limbs/ property or endangering Public Health
during the execution of a public procurement contract and/ or
Suspected to be or of doubtful loyalty to the Country or a National
Security risk as determined by appropriate agencies of the
Government of India.
iii) Not have changed its name or created a new “Allied Entity”, consequent
to having declared ineligible/ suspended/ blacklisted/ banned/ debarred
as above.(c) Not have an association (as a consultant/ partner/ director/ employee in
any capacity)
of any retired employee (of Gazetted Rank) or any retired Gazetted Officer
of the Central or State Government or its Public Sector Undertakings,
if such a retired person has not completed the one- year cooling-off
period (or any other period stipulated by their erstwhile Employer) after
his retirement. However, this shall not apply if such employees/ officers
have obtained a waiver of the cooling-off period from their former
organisation.
of the near relations of executives of Procuring Entity involved/
likely to be involved in this procurement process
(d) Not have a conflict of interest (as defined in clause 4.5 below), which
substantially affects fair competition. No attempt should be made to induce
any other consultant to submit or not to submit an RFP to restrict
competition.
(e) must fulfil any other additional eligibility condition, if any, as may be
prescribed in the RFP document.
(f) Must fulfil the technical capacity requirements at the time of award.
3) from certain countries shall be eligible subject to certain conditions as detailed
in Clause 1.2 below.
4) must provide such evidence of their continued eligibility to the Procuring Entity
if requested.
1.2 Eligibility of Consultants from Restricted countries
1.2.1 Restrictions based on Reciprocity.
Entities from countries (if so, identified in Section II: Appendix) as not allowing Indian
companies to participate in their Government procurement shall not be allowed to
participate (directly or as a sub-contractor or as a member of a JV/C) on a reciprocal
basis in this RFP process under the “Public Procurement (Preference to Make in India)
Order 20171” (MII – para 10 -d) of Department for Promotion of Industry and Internal
Trade, (DPIIT). Consultants must apprise themselves of the latest version of this order.
1.2.2 Restrictions Based on Land Borders
Order2 (Public Procurement No. 1) issued by the Government of India (Ministry of
Finance Department of Expenditure Public Procurement Division) restricting
procurement from consultants from certain countries that share a land border with India
shall apply to this procurement. Consultants must apprise themselves of the latest
version of this order. Any consultant from a country that shares a land border with India3,
excluding countries to which the Government of India has extended lines of credit
or in which the Government of India is engaged in development projects (as listed on
the website of the Ministry of External Affairs4), – hereinafter called ‘Restricted
Countries’ shall be
1
No. P-45021/2/2017-PP (BE-II) dated 16th September 2020
2F.N0.6/18/2019-PPD dated 23rd July, 2020
3 https://mea.gov.in/india-and-neighbours.htm 4 http://meadashboard.gov.in/indicators/92Eligible to participate in this RFP, only if the consultant is registered 5 with the Registration
Committee constituted by the Department for Promotion of Industry and Internal Trade
(DPIIT). Consultants shall enclose the certificate in Form 1 - RFP Form.
1.3 Joint Venture/ Consortium (JV/C)6
1.3.1 In the case where a consultant is or proposes to be a Joint Venture/ Consortium
(that is, an association of several persons, firms, or companies - hereinafter
referred to as JV/C), then unless otherwise specified in Section II: Appendix, in
JV/C:
a) members should not be more than four (04)
b) no member should have less than 10% participation;
c) members having participation between 10% and 20% shall be termed as
non-substantial members.
d) Members having more than 20% participation shall be termed as substantial
members.
e) The Lead member must have at least 40% participation.
f) The lead member/consultant and various categories of members of the JV/C
must be identified.
g) Number of non-substantial members shall not be more than one (01)
1.3.2 The JV/C and all members must satisfy all the eligibility requirements in this RFP
document.
1.3.3 JV/C and its members must jointly meet the qualification criteria in Section III
– Qualification Criteria. The technical/ experience qualification of all JV/C
members (substantial members, Lead member and non-substantial members)
shall be evaluated jointly as per Evaluation Criteria. However, for financial
5 https://dipp.gov.in/sites/default/files/Revised-Application-Format-for-Registration-of-Consultants-
15Oct2020.pdf
6 the expressions "Joint Venture" or "JV" shall mean a joint venture, association, consortium, or other
unincorporated grouping of two or more persons, whether in the form of a partnership or otherwise.
Similarly, in the context of Joint Venture as the context permits, the word "leader, is synonymous with the
words "representative" and "Lead Partner"; the word "member" is synonymous with the word with "partner”.criteria of qualification, credentials of substantial and lead members (excluding
non-substantial members) shall only be considered.
1.3.4 All the members shall be jointly and severally liable for the entire contract
if selected in the RFP Process.
1.3.5 In case a Joint Venture of firms, the proposal shall be accompanied by a certified
copy of legally binding Memorandum of Understanding (MoU) on a stamp paper of
Rs. 100/- signed by all firms to the Joint Venture indicating role and share of the JV
partners in the project as per eligibility conditions.
1.4 Conflict of Interest
1.4.1 Any consultant with a conflict of interest that substantially affects fair competition
shall not be eligible to participate in this procurement process. RFPs found to have
a conflict of interest shall be rejected as nonresponsive. Consultant shall be required
to declare the absence of such conflict of interest in Form 1.2 - Eligibility Declarations.
A consultant in this procurement process shall be considered to have a conflict of
interest if the consultant:
a) directly or indirectly controls, is controlled by or is under common control
with another Consultant; or
b) receives or has received any direct or indirect subsidy/ financial stake from
another consultant; or
c) has the same correspondence address or same legal representative/
agent as another consultant for purposes of this RFP; or
d) has a relationship with another consultant, directly or through common
third parties, which puts it in a position to have access to information
about or influence the RFP of another Consultant; or
e) would be providing goods, works, or non-consulting services resulting
from or directly related to consulting services that it provided (or were
provided by any affiliate that directly or indirectly controls, is controlled
by, or is under common control with that firm) for the procurement
planning (inter-alia preparation of feasibility/ cost estimates/ Detailed
Project Report (DPR), design/ technical specifications, terms of reference
(TOR)/ Activity Schedule/ schedule of requirements or the RFP
Document etc) of this procurement process; or
f) has a close business or family relationship with a staff of the Procuring
Organization who:
i) are directly or indirectly involved in the preparation of the RFP document or
Terms of Reference of the procurement process and/or the evaluation in
RFP process; or
ii) would be involved in the implementation or supervision of the resulting
contract
Any conflict stemming from such a relationship must be reported and resolved
in a manner acceptable to the Procuring Entity throughout the RFP processes
and execution of the contract.1.4.2 Participation of only One Entity from Affiliates: Only one entity from among a Consultant
and its affiliates (that directly or indirectly control or are controlledb y or are under
common control with that firm) individually or as part of a joint venture shall be
permitted to participate in RFP.
1.4.3 The consultant shall furnish information on commissions and gratuities, if any, paid or
to be paid to agents or any other party relating to this RFP process.
1.5 Qualification Criteria:-
S. No. Experience of the firm in last 7 years Annual
Preparation of DPR Project Turnover***
(NH/SH/Expresswa Supervision/IC
y) (NH/SH/Expressw
ay)
1 (a). The firm should have The firm should have minimum Annual turnover
minimum experience of
experience of Project (updated average
preparation of detailed
Supervision/Independent of last 3 years)
Project Report/
Engineer/Consultant of of the firm from
Feasibility Study cum
Preliminary Design 2/4/6**- laning/Bridge project consultancy
Report of 2/4/6**- of aggregate length equal to 3 business related to
laning/ Bridge project of
times or more of similar category** civil Engineering
aggregate length equal
for which RFP is invited. projects should be
to 2 times or more
equal to or
of similar category for
which RFP is more than
invited 3%% of
Estimated Project
Cost.
1 (b) Firm should also have experience of
Project Supervision/ Independent
Engineer/ Authority’ Engineer of at
least one project of similar category of
two/four/six** laning/bridge work of
length equal to 40% of project length.
Additional requirement in case of
specialized projects***
** Similar project means 2/4/6 lane project of Expressway/NH/SH
standards and specification as applicable for the project for which
RFP is invited. For 2-lane projects experience of 4/6 lane also to
be considered with a multiplication factor of 1.5. Experience of
4/6 lane shall be considered interchangeably for 4/6 laning
projects. For 4/6 laning projects, experience of 2 lane will be
considered with a multiplication factor of 0.4, but only for those
2 lane projects whose cost of consultancy services was more than
Rs.3.0 crores. For standalone bridge projects, experience inbridge work (either standalone project or as a part of road
project) only be considered.
*** In case the project includes any specialized nature of work such as
tunnels, specialized structures etc. in substantial quantum, this
requirement may be suitably included.
Note to Consultant: During RFP Process, while original documents/ certificates are
called for to authenticate the qualification claimed, the following may be kept in mind:
1) When a joint venture submits the bid, in that case, all members (other than
non-substantial members) in the JV/C must submit their financial statements in
order of the member's share in the partnership, greatest to least. The figures
of members of a JV/C (other than non-substantial members) shall be added
to determine compliance with the minimum financial qualifying criteria. However, for
JV/C to qualify, the Lead member must meet at least 40 percent of those minimum
criteria for an individual Bidder and other members at least 20% of t he criteria. Failure
to comply with this requirement shall result in the rejection of the JV/C's bid.
2) The weightage given for experience of a firm would depend on the role of
the firm in the respective assignments. The firm’s experience would get full
credit if it was the sole firm in the respective assignment. If the applicant firm
has completed projects as JV with some other firms, weightage shall be given
as per the JV share***. However if the applicant firm has executed the
project as associate/ non substantial partner with some other firms,
weightage shall be given as per the Actual share subjected to maximum of
25% to the applicant firm for the projects completed under such association.
*** For weightage of experience in any past Consultancy assignment,
experience certificate from the client shall be submitted with clear
demarcation of JV share in client certificate Annual turnover duly certified by
Chartered Accountant shall be accepted. In case of non-availability of such
documents no weightage of turnover/experience will be considered.
3) In case the financial figures and values of services provided are in foreign currency
current market exchange rate (State Bank of India BC Selling rate as on last date of
submission of the bid) will be applied for the purpose of conversion of amount in
foreign currency into Indian Rupees.
4) The consultant shall submit the audited balance sheet and/or banking reference
and certificate from Statutory Auditor with UDIN certifying that turnover is from civil
engineering consultancy business with their RFP proposal. An authorised
representative of the consultant must -sign the statement.Section II: Instructions to Consultants (ITC)
The RFP Document
1.1.
This ‘RFP Document’ Document (hereinafter referred to as ‘the RFP Document’) details
the terms and conditions for entering a contract for delivery of the Consultancy Services
(hereinafter called ‘the Services’) described in Section VI: “Terms of Reference”. The
‘Services’ may include incidental Goods, Works, and other Services if so indicated. In this
RFP Document, any generic reference to ‘Services’ shall be deemed to include such
incidental Goods, Works, and other Services. Proposals are invited from the Consultants
meeting the criteria (hereinafter called ‘the Consultants') as mentioned RFPL.
1.2 Interpretations, Definitions, Abbreviations and Document
Conventions
Section IV: General Conditions of Contract (GCC), details tenets of interpretation (GCC-
clause 1.1), definitions (GCC-clause 1.2), document conventions (GCC-clause 1.3) and
abbreviations (GCC-clause 1.4), which shall also apply to the rest of the RFP Document.
1.3 Overview of Contents
1) Unless otherwise stipulated in AITC, the Sections, Forms and Formats comprising
this RFP Document are described in ITC-clauses 1.4, 1.5 and 1.6 below. A separate
BOQ file for Financial Proposal on the eProcurement Portal is also part of this RFP
Document. Any generic reference to RFP Document shall also imply a reference to
any/ all the sections, Forms, Formats and the BOQ file or other files that comprise
this RFP Document.
2) Consultants must submit the Proposal in the Forms/ Formats mentioned in ITC-
clauses 1.5 and 1.6 below (as relevant).
1.4 Sections of the RFP Document
1.4.1 Sections of the RFP Document
Unless otherwise stipulated in AITC, the RFP Document contains the following sections,
which are described in subsequent sub-clauses:
Section I: Request for Proposal Letter (RFPL) and its Appendix: Tender Information
Summary (TIS)
Section II: Instructions to Consultants (ITC)
Section III: Appendix to Instructions to Consultants
(AITC) Section IV: General Conditions of Contract
(GCC)
Section V: Special Conditions of Contract (SCC)
Section VI: Terms of Reference
a) Section VI-A: List of Key Experts and Required Qualifications
Section VII: Evaluation/ Scoring Criteria1.4.2 Section I: Request for Proposal Letter (RFPL) and its Appendix:
Tender Information Summary (TIS)
Section I – Request for Proposal Letter (RFPL) and its Appendix – Tender Information
Summary (TIS) provides a synopsis of information relevant for a Consultant to decide
on participating in the RFP. Consultants must fill up ‘Form T-7: Terms and Conditions -
Compliance’ regarding any proposed deviations from this Section.
1.4.3 Section II: Instructions to Consultants (ITC) and Section III:
Appendix to Instructions to Consultants (AITC)
Section II: “Instructions to Consultants” (ITC), along with Section III: “Appendix to
Instructions to Consultants (AITC)”, provides the relevant information as well as
instructions to assist the Consultants in preparing their proposals. It also includes the
mode and procedure adopted for receipt/ opening, evaluation of Proposals, and
contract award. In case of a conflict, provisions of AITC shall prevail over those in the
ITC. Any generic reference to ITC shall also imply a reference to AITC as well.
Consultants must fill up ‘Form T-7: Terms and Conditions - Compliance’ regarding any
proposed deviations from these Sections.
1.4.4 Section IV: General Conditions of Contract (GCC) and Section V:
Special Conditions of Contract (SCC)
Section IV – General Conditions of Contract (GCC) and Section V – Special Conditions
of Contract (SCC) describe the conditions governing the resulting contract. In case of a
conflict, provisions of the SCC shall prevail over those in the GCC. Any generic
reference to GCC shall also imply a reference to SCC as well. In case of any conflict,
provisions of GCC/ SCC shall prevail over those in ITC/ AITC. Consultants must fill up
‘Form T-7: Terms and Conditions - Compliance’ regarding any proposed deviations
from terms and conditions in these Sections.
1.4.5 Section VI: Terms of Reference (TOR) and Section VI-A: List of Key
Experts andR equired Qualifications
Section VI: Terms of Reference describe the background, purpose/ objectives,
description/ scope, deliverables/ outcomes, timelines, Procuring Entity’s inputs and
counterpart personnel, statutory requirements of Services required etc. Section VI-A: ‘List
of Key Experts and Required Qualifications’ describes the team composition, expertise,
experience and professional qualifications required for each Key Experts. Any generic
reference to TOR shall imply a reference to Section VI-A: ‘List of Key Experts and
Required Qualifications’ as well. Consultants must fill up ‘Form T-3: Comments and
Suggestions on Terms of Reference, Counterpart Staff, and Facilities to be provided by
the Procuring Entity’ regarding these Sections. Regarding this Section, Consultants must
fill out Form T-3: Comments and Suggestions on Terms of Reference, Counterpart Staff,
and Inputs to be provided by the Procuring Entity.1.4.6 Section VII: Evaluation/ Scoring Criteria
1) Section VII – Evaluation/ Scoring Criteria stipulates the scoring scheme for evaluating
various Technical criteria. These may cover scoring of criteria relating to the
Consultant’s experience, Technical Approach and Methodology, understanding of
requirements, qualification and experience of Key Experts, transfer of knowledge
etc. It may also lay down a minimum technical score to qualify for the next stage of
Financial Evaluation. In a specific evaluation scheme, instead of a scheme of
scoring, a scheme may be laid down to evaluate criteria on a pass/ fail basis.
2) Consultants must fill up the following Forms regarding this Section:
a) Form T-2: Consultant’s Organisation and Experience and past performance
b) Form 2-A Consultant’s Technical Capacity
c) Form T-3: Comments and Suggestions on Terms of Reference, Counterpart
Staff, and Inputs to be Provided by the Procuring Entity
d) Form T-4: Description of Approach, Methodology and Work Plan in
Responding to the Terms of Reference
e) Form T-5: Work Schedule and Planning for Deliverables
f) Form T-6: Team Composition, Assignment, and Key Experts’ Inputs
i) Annex to Form T-6: Key Experts’ Curriculum Vitae (CV)
1.5 Forms (To be filled, digitally signed, and uploaded by Consultants)
Please refer to ITC-clause 1.4 above to relate the following forms to the corresponding
Sections.
1)
Technical Proposal:
a) Form T-1: Proposal Form – (To serve as a covering letter to both the Techno-
commercial and Financial Proposals)
b) Form 1.2- Eligibility Declaration
c) Form T-1A: Consultant’s Commercial Information
d) Form T-2: Consultant’s Organisation and Experience
e) Form T-2A:- Consultant Technical capacity
f) Form T-3: Comments and Suggestions on Terms of Reference, Counterpart
Staff, and Inputs to be Provided by the Procuring Entity
g) Form T-4: Description of Approach, Methodology and Work Plan in
Responding to the Terms of Reference
h) Form T-5: Work Schedule and Planning for Deliverables
i) Form T-6: Team Composition, Assignment, and Key Experts’ Inputs
j) Annex to Form T-6: Key Experts’ Curriculum Vitae (CV)
k) Form T-7: Terms and Conditions - Compliance
l) Form T-8: Checklist for Consultants. The consultant must also upload the
Checklist to confirm that he has complied with all the instructions in the RFP
Document and that nothing is inadvertently left out. This checklist is only for
general guidance, is not comprehensive, and does not absolve the Consultant
from complying with all the requirements stipulated elsewhere in the RFP
Document.m) Form T-9A: Bank Guarantee Format for Earnest Money Deposit
n) Form T-9B: Bid Securing Declaration
o) Form T-10: Integrity Pact
p) Any other format/ Form if stipulated in AITC or considered relevant by the
Consultant.
2)
Financial Proposal
The financial proposal is to be submitted in a separate file available on the
eProcurement Portal.
1.6 Other Formats
Format 1: Contract Form (Required after Letter of Award)
Appendix A: Terms of Reference
Appendix B: Key Experts
Appendix C: Remuneration Cost Estimates
i) Annex to Appendix C: Breakdown of Agreed Fixed Rates in Consultant’s
Contract
Appendix D: Reimbursable Expenses Cost Estimates
Appendix E-1: Bank Guarantee Format for Performance Security
Appendix E-2: Bank Guarantee Format for Advance Payment
2) Format 2: Certification by Prospective Arbitrators
3) Format 3: Authorisation to Attend Pre-Proposal Conference. (To be filled up, if
required, by Consultant)
Procuring Entity - Rights and Disclaimers
2.1. The Procuring Entity
Proposals are to be addressed to the President of India through the Head of
Procurement/ Chairman NHAI/ MD NHIDCL, Procuring Entity in the Procuring
Organization (headed by the Head of the Procuring Organisation). The Tender Inviting
Authority (TIA) is the designated officer for uploading and clarifying this RFP Document.
The contract may designate, as required, a counterpart Contract Manager (or Contract
Management Team); and Paying authority who shall discharge the designated function
during contract execution.
2.2. Right to Intellectual Property and confidentiality:
1) The RFP Document and associated correspondence are subject to copyright laws
and shall always remain the property of the Procuring Entity and must not be shared
with third parties or reproduced, whether in whole or part, without the Procuring
Entity’s prior written consent.
2) However, Consultants may share these to prepare and submit their Proposals with
their employees, Sub-consultant(s) or holding Company after obtaining an
undertaking of confidentiality similar to that imposed on the Consultant.
3) This condition shall also apply to Consultants who do not submit a Proposal after
downloading it or are not awarded a contract.
4) The obligation of the Consultants under sub-clauses above, however, shall not apply
11to information that:
a) now or hereafter is or enters the public domain through no fault of
Consultant;
b) is legally possessed by consultant at the relevant time and was not previously
obtained, directly or indirectly, from the Procuring Entity; or
c) otherwise lawfully becomes available to Consultant from a third party with
no obligation of confidentiality.
5) The provisions of this clause shall survive completion or termination for whatever
reason of the Procurement Process or the contract.
2.3. Right to Reject any or all Proposals
The Procuring Entity reserves its right to accept or reject any or all Proposals, abandon/
cancel the Procurement Process, and issue another RFP for the same or similar
Services before the award of the contract. It would have no liability to the affected
Consultant(s) or any obligation to inform them of the grounds for such action(s).
2.4. Disclaimers
2.4.1 Regarding the Purpose of the RFP Document
The RFP Document is neither an agreement nor an offer to the prospective Consultant(s)
or any other party. The purpose of the RFP Document is to provide the Consultant(s)
with information to assist them in participation in this Procurement Process.
2.4.2 Regarding Documents/ guidelines
The RFP Document, ensuing communications, and Contracts shall determine the legal
and commercial relationship between the Consultants and the Procuring Entity. No
other Government or Procuring Entity’s document/ guidelines/ Manuals, including its
Procurement Manual (for internal and official use of its officers), notwithstanding any
mention thereof in the RFP Document, shall have any locus-standii in such a
relationship. Therefore, such documents/ guidelines/ Manuals shall not be admissible
in legal or dispute resolution or grievance redressal proceedings.
2.4.3 Regarding Information Provided
Information contained in the RFP Document or subsequently provided to the
Consultant(s) is on the terms and conditions set out in the RFP Document or subject to
which that was provided. Similar terms apply to information provided verbally, in the
documentary, or any other form, directly or indirectly, by the Procuring Entity, its
employees, or associated agencies.
2.4.4 Regarding RFP Document:
1) The RFP Document does not purport to contain all the information Consultant(s) may
require. It may not address the needs of all Consultants. They should conduct due
diligence, investigation, and analysis, check the information's accuracy, reliability,
and completeness, and obtain independent advice from appropriate sources.
Information provided in the RFP Document to the Consultant(s) is on various matters,
some of which may depend upon interpreting the law. The information given is not
an exhaustive account of statutory requirements and should not be regarded as acomplete or authoritative statement of law. The Procuring Entity, its employees and
other associated agencies accept no responsibility for the accuracy or otherwise for
any interpretation or opinion on law expressed herein.
2) The Procuring Entity, its employees and other associated agencies make no
representation or warranty for the accuracy, adequacy, correctness, completeness
or reliability of any assessment, assumption, statement, or information in the RFP
Document. They have no legal liability, whether resulting from negligence or
otherwise, for any loss, damages, cost, or expense arising from/ incurred/ suffered,
howsoever caused, to any person, including any Consultant, on such account.
Consultants – Participation in this RFP process
3.1. Eligibility to Participate
Consulting firms meeting the eligibility criteria as mentioned in
Appendix-1 to Tender Information Summary (TIS) are only eligible for
applying for this assignment. Firms not meeting these criteria, need not apply.
4) Participation in only one Proposal: The Consultant shall not participate in more
than one Proposal in this RFP Process. Participation in any capacity by a Consultant
(including the participation of a Consultant as a Sub-consultant or as a member of
a JV/C or vice-versa) in more than one Proposal shall result in the disqualification
of all Proposals in which he is a party. A Consultant shall not be allowed to
participate both as an individual Consultant and as a part of the joint venture
3.2. Conflict of Interest
The Consultant must provide professional, objective, and impartial advice, holding
the Procuring Organisation’s interests paramount at all times, and shall not try to get
benefits beyond the legitimate payments and credentials in the contract. He should
strictly avoid conflicts with other assignments or their corporate interests. Consultants
must disclose to the Procuring Entity in Form T-1 ‘Proposal Form (Covering Letter)’ any
actual or potential conflict that impacts its capacity to serve the best interest of the
Procuring Organisation. Failure to disclose such situations shall be treated as a violation
of the Code of Ethics (ITC-Clause 15) and shall attract penalties mentioned therein.
Proposals found to have a conflict of interest shall be rejected as nonresponsive. Without
limitation on the generality of the preceding, a Consultant in this Procurement Process
shall be considered to have a conflict of interest if the Consultant:
1) Conflicting Associations:`
a) directly or indirectly controls, is controlled by or is under common control
with another Consultant; or
b) receives or has received any direct or indirect subsidy/ financial stake from
another Consultant; or
c) has the same correspondence address or same legal representative/ agent
as another consultant for purposes of this proposal; or
d) has a relationship with another Consultant, directly or through common third
parties, that puts it in a position to have access to information about or
13influence the Proposal of another Consultant or influence the decisions of
the Procuring Entity regarding this Procurement Process; or
2) Unfair Competitive Advantage and Conflicting Activities: had (or any of its
Affiliates) been engaged by the Procuring Entity to provide goods, works, or
services for a project, shall be disqualified from providing consulting services
resulting from or directly related to those goods, works, or services. Conversely, a
firm (or any of its Affiliates) hired to provide consulting services for the preparation
or implementation of a project shall be disqualified from subsequently providing
goods or works or services resulting from or directly related to the consulting
services for such preparation or implementation.
3) Conflicting Assignments: would (including its Experts and Sub-consultants) or any
of its Affiliates) be or are providing consultancy services in another assignment for
the same or another Procuring Entity that, by its nature, may conflict with this
assignment.
4) Commissions and Gratuities: The Consultant shall disclose any commissions or
fees that may have been paid or are to be paid to agents, representatives, or
commission agents concerning the selection process or execution and performance
of the resulting Contract. The information disclosed must include the name and
address of the agent, representative, or commission agent, the amount and
currency, and the purpose of the commission or fee.
5) Conflicting Relationships: has close business/ family relationship with a staff of
the Procuring Organisation who are/ would be directly/ indirectly involved in any of
the following activities:
a) preparation of the RFP document or TOR of the Procurement Process
b) evaluation of Proposals or award of Contract, or
c) implementation/ supervision of the resulting Contract
The Terms of Reference (TOR) and Form of Contract
4.1. Facilities to be provided by the Procuring Entity
All inputs, relevant project data, and reports required for preparing the Consultant’s
Proposal shall be included in the TOR. Unless otherwise stipulated in the TOR, utilities
or facilities (e.g., Rooms, Furniture, Transport, and Access to IT Services etc.) shall NOT
be provided by the Procuring Entity to the Consultant.
4.2. Forms of BOQ/ Contract and Selection Methods
Evaluation of Proposals and the resulting Contract shall be based on the form of BOQ/
Contract and the Selection method applicable for the RFP, as elaborated in ITC-Clause
11 and 12 below.
4.2.1 Time-Based (Inputs Admeasurement) form of BOQ/ Contract:
Unless otherwise stipulated in the TIS form of BOQ/ Contract shall be ‘Time-Based
(Inputs Admeasurement)’. In such contracts, the Consultant shall provide services on a
timed basis according to the Terms of Reference. The Consultant’s remuneration shall
be determined based on the time spent by the Consultant in carrying out the Servicesbased on (i) agreed-upon unit rates for the Consultant’s experts multiplied by the actual
time spent by the experts in executing the assignment and (ii) reimbursable expenses
using actual expenses and/or agreed unit prices.
4.2.2 Selection Method
1) Unless otherwise specified in TIS, the selection method applicable in this RFP shall
be Quality and Cost Basis Selection (QCBS). If so stipulated in TIS/ AITC following
selection methods can also be used in this RFP:
a) Least Cost Selection (LCS)
b) Fixed Budget Selection (FBS).
c) Single Source Selection (SSS)
2) Please refer to ITC-Clause 11 and 12 for details.
4.3. Inputs of Key Experts
4.3.1 Consultant shall not propose alternative Key Experts. Only one CV shall be
submitted for each Key Expert position. Failure to comply with this requirement shall
make the Proposal non-responsive.
15Proposal Prices, Taxes and Duties
5.1. Prices
5.1.1 Competitive and Independent Prices
The prices should be arrived at independently, without restricting competition, any
consultation, communication, or agreement with any other Consultant or competitor
relating to:
i) those prices; or
ii) the intention to submit an offer; or
iii) the methods or factors used to calculate the prices offered.
The prices should not be knowingly disclosed by the Consultant, directly or indirectly,
to any other Consultant or competitor before the Financial Proposal opening unless
otherwise required by law.
5.1.2 Price Components
Consultant shall indicate in the Price Schedule prices/ rates against all the specified
components, including the unit prices and total Proposal prices.
5.1.3 Price Schedule
Consultants are to upload only the downloaded BOQ (in excel format) after
entering the relevant fields without any alteration/ deletion/ modification of other
portions of the excel sheet. All the columns in the price schedule should be filled
up as required. If any column does not apply to a Consultant, he should clarify
the same.
Consultants shall fill in rates other than zero value in the specified cells without
leaving them blank.
The quoted price shall be considered to include all relevant financial
implications, including inter-alia the scope of the Services to be delivered and
the incidental goods/ works to be supplied, location of the Consultant, site(s) of
the delivery of Services, terms of delivery, extant rules and regulations relating totaxes, duties, customs, transportation, environment, labour, Mining & Forest of
the Consultant's country and in India.
5.1.4 Provisions of GST
Break up of different price elements, i.e., as per GST Act, shall be
indicated separately, along with its associated HSN code and GST rate.
While quoting the basic rate, the Consultant should offset the input
credit available as per the GST A
ct.
Please refer to ITC-Clause 5.3 for further details.
5.1.5 Currencies of Proposal and Payment
1) Unless otherwise stipulated in the AITC, the Consultant's currency of Proposal and
payment shall be quoted entirely in Indian Rupees. All payments shall be made in
Indian Rupees only.
2) Where the AITC permits quotations in different currencies, then, for Services
performed in or sourced from India, prices shall be quoted in Indian rupees only,
and for Services performed from foreign locations, prices shall be quoted in Indian
rupees or the currency stipulated in the AITC. For evaluation, all quoted prices shall
be converted into Indian Rupees as per the procedure mentioned in ITC-clause
11.4.2 below.
5.1.6 Non-compliance
Tenders, where prices are quoted in any other way, shall be rejected as nonresponsive.
5.2. Firm/ Variable Price
5.2.1 Firm Price
Unless otherwise stipulated in the AITC, prices quoted by the Consultant shall remain
firm and fixed during the currency of the contract and not subject to variation on any
account.
5.2.2 Price Variation Clause:
1) In case the RFP Documents require/ permit offers on a variable price basis, the price
quoted by the Consultants shall be subject to adjustment during the original delivery
period to take care of the changes in the input cost of labour, material, and fuel/
power components under the price variation formula as stipulated in the RFP
Document.
5.3. Taxes
The Consultant and its Sub-consultants and Experts are responsible for meeting all tax
liabilities arising from the Contract.
175.3.1 GST Registration Status:
1) All the Consultants should ensure that they are GST compliant and that their quoted
tax structure/ rates are as per GST Act/ Rules. Consultants should be registered
under GST and furnish a GSTIN number and GST Registration Certificate in their
offer unless they are specifically exempted from registration under a specific
notification/ circular/ section/ rule issued by statutory authorities.
2) GST Registration Number (15-digit GSTIN). If the Consultant has multiple
business verticals in a state and has separate registration for each vertical, the GSTIN of
each vertical concerned with the service delivery shall be quoted. If the services
provided are from multiple states, the Consultant should mention GST registration
numbers for each state separately.
3) Composition scheme: If the Consultant has opted for a composition levy under
Section 10 of CGST, he should declare the fact while bidding along with GSTIN and
GST registration certificate.
4) Exemption from Registration: If a Consultant is not liable to take GST
registration, i.e., having turnover below threshold, he shall submit undertaking/
indemnification against tax liability. Consultant claiming exemption in this respect
shall submit a valid certificate from practicing Chartered Accountant (CA)/ Cost
Accountant with Unique Document Identification Number (UDIN) to the effect that
Consultant fulfils all conditions prescribed in notification exempting him from
registration. Such Consultant/ dealer shall not charge any GST and/ or GST Cess
in the bill/ invoice. In such case, applicable GST shall be deposited under Reverse
Charge Mechanism (RCM) or otherwise as per GST Act by the Procuring Entity
directly to concerned authorities. The consultant should note that his offer would
be loaded with the payable GST under the RCM. Further, the Consultant should
notify and submit to the Procuring Entity within 15 days of becoming liable for
registration under GST.
5.3.2 HSN Code and GST Rate:
1) If provided in this RFP Document, the HSN (Harmonized System of Nomenclature)
code shall be only indicative. It shall be the responsibility of the Consultant to ensure
that they quote the exact HSN Code and corresponding GST rate for each activity
of the Services being offered by them
a) As per the GST Act, the Proposal and contract must show the GST Tax Rates
(and GST Cess if applicable) and GST Amount explicitly and separately from
the Proposal/ contract price (exclusive of GST).
2) Applicability to Imported Goods/ Services: If imported into India, the supply
of commodities, services, or both shall be considered as supply under inter-state
commerce/ trade and shall attract integrated tax (IGST). The IGST rate and GST cessshall be applicable on the ‘Custom Assessable Value’ plus the ‘Basic Customs duty
applicable thereon’.
5.4. Payments
5.4.1 General
Unless otherwise stipulated in AITC, the usual payment term is 100% on delivery and
acceptance of Services at ‘the Site’ by the Procuring Entity and production of all required
documents. However, periodic “On Account” payments shall be made unless otherwise
stipulated as per the procedure laid down in GCC.
5.4.2 No Advance Payments
Unless otherwise stipulated in AITC, the Procuring Entity shall make no advance
payment of any type (Mobilization, secured advances, etc.). If AITC does stipulate
advance payments, these shall be subject to conditions stipulated therein.
Downloading the RFP Document; Corrigenda and Clarifications
6.1. Downloading the RFP Document
The RFP document can be downloaded as per the details given in RFPL clause 2.2.
6.2. Corrigenda/ Addenda to RFP Document
1) Before the deadline for submitting Proposals, the Procuring Entity may update,
amend, modify, or supplement the information, assessment or assumptions
contained in the RFP Document by issuing corrigenda and addenda. The corrigenda
and addenda shall be published in the same manner as the original RFP Document.
Without any liability or obligation, the Portal may send intimation of such
corrigenda/ addenda to Consultants who have downloaded the document under
their login. However, the Consultants must check the website(s) for any corrigenda/
addenda. Any corrigendum or addendum thus issued shall be considered a part of
the RFP Document.
2) To give reasonable time to the prospective Consultants to take such corrigendum/
addendum into account in preparing their Proposals, the Procuring Entity may
suitably extend the deadline for the Proposal submission as necessary. After the
procuring entity makes such modifications, any Consultant who has submitted his
Proposal in response to the original invitation shall have the opportunity to either
withdraw his Proposal or re-submit his Proposal superseding the original Proposal
within the extended time of submission as per ITC-clause 9.4.1 below.
3) The Procuring Entity may extend the deadline for the RFP submission by issuing an
amendment. In this case, all rights and obligations of the Procuring Entity and the
consultants previously subject to the original deadline shall then be subject to the
new deadline for the RFP submission.
6.3. Clarification of the RFP Document
As detailed in RFPL clause 2.3, a Consultant requiring any clarification regarding the
RFP Document may seek clarification through the eProcurement Portal. The Procuring
19Entity shall respond no later than seven days before the deadline for RFP submission.
The query and clarification shall be shared with all Consultants on the portal without
disclosing its source. If a modification of the RFP document is warranted due to such
clarification, an addendum/ corrigendum shall be issued as per ITC-Clause 6.2 above.
Pre-Proposal Conference
1) If a Pre-Proposal conference is stipulated in the TIS, prospective Consultants
interested in participating in this tender may attend a Pre-Proposal conference to
clarify the techno- commercial conditions of the RFP at the venue, date and time
specified therein.
2) Participation is not mandatory: However, if a Consultant chooses not to (or fails to)
participate in the Pre-Proposal conference or does not submit a written query, it shall
be assumed that they have no issues regarding the techno-commercial conditions.
3) The date and time by which the written queries for the Pre-Proposal must reach the
authority and the last date for registration for participation in the Pre-Proposal
conference are also mentioned in the TIS. If the dates are not mentioned, such date
and time shall be 7 days before the date and time of the pre-Proposal conference.
4) Delegates participating in the Pre-Proposal conference must provide a photo identity
and an authorization letter as per Format 3: "Authorization to attend a Pre-Proposal
Conference" from their Company/ principals; else, they shall not be allowed to
participate. The pre-Proposal conference may also be held online at the discretion
of the Procuring Entity.
5) After the Pre-Proposal Conference, Minutes of the Pre-Proposal conference shall be
published on the Procuring Entity’s portal within seven days from the Pre-Proposal
Conference. If required, a clarification letter and corrigendum to RFP Document
shall be issued, containing amendments to various provisions of the RFP Document.
As per ITC-clause 6.2 above, to give reasonable time to the prospective Consultants
to consider such clarifications in preparing their Proposals, the Procuring Entity may
suitably extend, as necessary, the deadline for the Proposal submission.
Preparation of Proposals
8.1. The Proposal
8.1.1 Language of the Proposal
Unless otherwise stipulated in the AITC, the Proposal submitted by the Consultant and
all subsequent correspondence and documents relating to the Proposal exchanged
between the Consultant and the Procuring Entity shall be written in the language
specified in the AITC /SCC (hereinafter referred to as the ‘Proposal Language’. If
nothing is specified, the language shall be English). However, the language of any
printed literature furnished by the Consultant in connection with its Proposal may be
written in any other language provided a certified translation accompanies it in the
Proposal language. For purposes of interpretation of the Proposal, translation in the
language of the Proposal shall prevail.8.1.2 Acquaintance with Local Conditions and Factors
At his own cost, responsibility, and risk, the Consultant is encouraged to visit, examine,
and familiarise himself with the local conditions and factors. The Consultant
acknowledges that before the submission of the Proposal, he has, after a complete and
careful examination, made an independent evaluation of the local conditions,
infrastructure, logistics, communications, legal, environmental, and any other
conditions or factors which would have any effect on the performance of the contract.
Consultants shall be responsible for compliance with Rules, Regulations, Laws and Acts
in force from time to time at relevant places. On such matters, the Procuring Entity shall
have no responsibility and not entertain any request from the Consultants.
8.1.3 Cost of preparation and submission of Proposals
The Consultant(s) shall bear all direct or consequential costs, losses and expenditures
associated with or relating to the preparation, submission, and subsequent processing
of their Proposals, including but not limited to preparation, copying, postage, delivery
fees, expenses associated with any submission of samples, demonstrations, or
presentations which the Procuring Entity may require, or any other costs incurred in
connection with or relating to their Proposals. All such costs, losses and expenses shall
remain with the Consultant(s), and the Procuring Entity shall not be liable in any manner
whatsoever for the same or any other costs, losses and expenses incurred by a
Consultant(s) for participation in the Procurement Process, regardless of the conduct or
outcome of the Procurement Process.
8.1.4 Interpretation of Provisions of the RFP Document
The RFP document's provisions must be interpreted in the context in which these appear.
Any interpretation of these provisions far removed from such context, contrived, or
between-the-lines interpretation is unacceptable.
8.1.5 Alternate Proposals are not allowed.
Unless otherwise stipulated in the AITC, conditional offers, alternative offers, and
multiple Proposals by a Consultant shall not be considered. The Portal shall permit only
one Proposal to be uploaded.
8.2. Documents comprising the Proposal:
8.2.1 Techno-commercial Proposal/ Cover
"Technical Proposal" shall include inter-alia the scanned copies of duly signed or
digitally signed copies of forms as per ITC-Clause 1.6 in pdf format. The Technical
Proposal shall not include any financial information. A Technical Proposal containing
material financial information shall be declared non-responsive.
8.2.2 Financial Proposal/ Cover
"Financial Proposal" shall comprise the Price Schedule (Submitted separately as an excel
sheet) available on the eProcurement Portal. Any additional information may be
uploaded as a pdf under "Additional Documents" in the "Proposal Cover Content." It
should be filled considering all financially relevant details, including Taxes and Duties,
21as per ITC-clause 5.3. It shall list all costs associated with the assignment, including (a)
remuneration for Key Experts and Non-Key Experts, (b) reimbursable expenses in the
RFP Document. No additional technical details which have not been brought out in the
Technical Proposal shall be brought out in the Financial Proposal. A Financial Proposal
containing material Technical Information not disclosed in the Technical Proposal shall
be declared non-responsive.
8.3. Proposal Validity
1) Unless specified to the contrary in the TIS, Proposals shall remain valid for a period
not less than 90120 days from the deadline for the Proposal submission stipulated
in TIS. A Proposal valid for a shorter period shall be rejected as nonresponsive.
2) In case the day upto which the Proposals are to remain valid falls on/ subsequently
declared a holiday or closed day for the Procuring Entity, the Proposal validity shall
automatically be deemed to be extended upto the next working day.
3) In exceptional circumstances, before the expiry of the original time limit, the
Procuring Entity may request the Consultants to extend the validity period for a
specified additional period. The request and the Consultants' responses shall be
made in writing or electronically.
a) The Consultant has the right to refuse to extend the validity of its Proposal,
in which case such Proposal shall not be further evaluated.
b) If the Consultant agrees to extend the validity of its Proposal, it shall be done
without any change in the original Proposal and with the confirmation of the
availability of the Key Experts.
c) If any Key Experts become unavailable for the extended validity period, the
Consultant shall seek permission to substitute another Key Expert. The
Consultant shall provide adequate written justification and evidence to the
Procuring Entity with the substitution request. In such case, a substitute Key
Expert shall have equal or better qualifications and experience than the
originally proposed one. The technical evaluation score, however, shall
remain based on the evaluation of the CV of the original Key Expert.
d) If the Consultant fails to provide a substitute Key Expert with equal or better
qualifications, or if the provided reasons for the replacement or justification
are unacceptable to the Procuring Entity, such Proposal shall be rejected.
8.4. Bid Security - Related Documents
1) EMD/ BSD as Bid Security: The Consultant shall provide Bid Security as Earnest
Money Deposit (EMD) for the amount shown in the TIS (or if permitted in TIS, a Bid
Securing Declaration as Form T-9B in lieu of EMD).
2) Modalities of EMD: Unless otherwise provided in TIS, the earnest money shall be
denominated in Indian Rupees. Wherever relevant, it shall be in favour of the
Account specified in TIS and shall be furnished in one of the following modalities
valid for forty-five days beyond the validity of the proposal:
a) E- Bank Guarantee
b) Insurance Surety Bondsc) Account Payee Demand Draft or
d) Fixed Deposit Receipt or
e) Banker’s cheque
f) Bank Guarantee from/ confirmed by any of the commercial banks in the
format specified in Form T-9A, or
g) Payment online in an acceptable form
3) Forfeiture of EMD (Enforcement of BSD): EMD shall be forfeited (or in case BSD is
permitted, the declaration2 shall be enforced from the date of such decision) if the
Consultant breaches any of the following obligation(s) under the RFP:
(a) withdraws or amends his Proposal or impairs or derogates from the Proposal in
any respect within the period of validity of its Proposal; or
(b) after having been notified within the period of Proposal validity of the
acceptance of his Proposal by the Procuring Entity:
i) refuses to or fails to submit the original documents for scrutiny or the
required Performance Security within the stipulated time as per the RFP
document's conditions.
ii) fails or refuses to sign the contract.
4) Return of EMD (Expiry of BSD): Unsuccessful Consultants’ EMD shall be returned to
them without any interest (or if BSD is permitted, it shall stand expired) not later than
thirty days after the conclusion of the resultant contract. Successful Consultant’s EMD
shall be returned without any interest (or if BSD is permitted, it shall stand expired)
after receipt of performance security from them.
Signing and Uploading Proposals
9.1. Relationship between Consultant and eProcurement Portal
The Procuring Entity is neither a party nor a principal in the relationship between the
Consultant and the organisation hosting the e-procurement portal (hereinafter called
the Portal). Consultants must comply with the rules, regulations, procedures, and
implied conditions/ agreements of the eProcurement portal, including registration,
compatible Digital Signature Certificate (DSC) etc. Consultants shall settle clarifications
and disputes, if any, regarding the Portal directly with them. In case of conflict between
provisions of the Portal with the RFP Document, provisions of the Portal shall prevail.
Consultants may study the resources provided by the Portal for Consultants.
9.2. Signing of Proposal
The individual signing/ digitally signing the Proposal or any other connected documents
should submit an authenticated copy of the document(s), which authorizes the signatory
2
The BSD provides for automatic suspension of the Consultant (all members individually and jointly in case of
JV/C) from being eligible for bidding in any procurement in the Ministry/ Department of Procuring Organization for 2
years from the date of such enforcement.
23to commit and submit Proposals on behalf of the Consultant along with Form T-1:
Proposal Form (Covering Letter).
9.3. Submission/ uploading of Proposals.
9.3.1 Submission/ Uploading to the Portal
Further to details mentioned in RFPL clause 6:
1) Proposals must be uploaded on the eProcurement Portal mentioned in the TIS until
the deadline for the Proposal submission as notified therein. If the office happens to
be closed on the deadline to submit the Proposal as specified above, this deadline
shall not be extended. No manual Proposals shall be made available or accepted
for submission. Proposals submitted through modalities other than those stipulated
in TIS shall be liable to be rejected as nonresponsive.
2) In the case of downloaded documents, the Consultant must not make any changes
to the contents of the documents while uploading, except for filling in the required
information– otherwise, the Proposal shall be rejected as nonresponsive. Uploaded
Pdf documents should not be password protected. Consultants should ensure the
clarity/ legibility of the scanned documents uploaded by them.
3) The date and time of the e-Procurement server clock (also displayed on the
dashboard of the consultants) shall be the reference time for deciding the closing
time of the Proposal submission. Consultants are advised to ensure they submit their
Proposal within the deadline of submission, taking the server clock as a reference,
failing which the portal shall not accept the Proposal. No request on the account
that the server clock was not showing the correct time and that a particular
consultant could not submit their Proposal because of this shall be entertained.
Failure or defects on the internet or heavy traffic at the server shall not be accepted
as a reason for a complaint. The Procuring Entity shall not be responsible for any
failure, malfunction or breakdown of the electronic system used during the e-Tender
process.
4) Only one copy of the Proposal can be uploaded, and the Consultant shall digitally
sign all statements, documents, and certificates uploaded by him, owning sole and
complete responsibility for their correctness/ authenticity as per the IT Act 2000 as
amended from time to time. A proposal submitted by a Joint Venture shall be
digitally signed by an authorized representative with a written power of attorney
signed by each member’s authorized representative to legally bind all members.
5) Unless otherwise instructed in the RFP Document, the consultant need not sign or
up-load the Sections in ITC-clause 1.4 above while uploading his Proposal.
However, they must declare in his Proposal Form (Form T-1: Proposal Form) that
they have read, understood, complied with, and stand bound by all requirements of
these sections:
6) Unless otherwise specified, in TIS, originals of the EMD/ Bid Security instrument must
be physically submitted sealed in double cover and acknowledgement be obtained
before the bid submission deadline at the venue mentioned in TIS. Failure to do sois likely to result in the bid being rejected. If the office is closed on the deadline for
such physical submission, the physical submission deadline shall stand extended to
the next working day at the same time and venue.
7) The Procuring Entity reserves its right to call for verification, at any stage of
evaluation, especially from the successful Consultant(s) before the issue of a Letter
of Award (LoA), originals of uploaded scanned copies of documents (in the RFP
stages). If a consultant fails at that stage to provide such originals or, in case of
substantive discrepancies in such documents, it shall be construed as a breach of
the Code of Integrity (see clause 15 below). Such RFP proposals shall be liable to
be rejected as nonresponsive and other punitive actions for such a breach.
8) Regarding the protected Price Schedule (excel format, Cover-2), the Consultant shall
only enter his name in the space provided in the specified location. Consultant shall
type rates in the figure only in the rate column of respective service(s) without any
blank cell or Zero values in the rate column, without any alteration/ deletion/
modification of other portions of the excel sheet. If space is inadequate, the
Consultant may upload additional documents under "Additional Documents" in the
"Proposal Cover Content."
9) All Proposals uploaded by the Consultant to the portal shall get automatically
encrypted. The encrypted Proposal can only be decrypted/ opened by the authorised
persons on or after the due date and time. The Consultant should ensure the
correctness of the Proposal before uploading and take a printout of the system-
generated submission summary to confirm the successful Proposal upload.
10) The selected bidder shall use he Link Data Lake Portal' available on website to
communicate with Authority and EPC Contractor correspondence.
11) No Physical document shall be accepted unless and until the same is specifically
stated so in Ithe RFP or it is a legal requirement
9.3.2 Implied acceptance of procedures by Consultants
Submission of Proposal in response to the RFP Document is deemed to be
acceptance of the procedures and conditions of e-Procurement and the RFP
Document.
9.4. Modification, Resubmission and Withdrawal of Proposals
9.4.1 Modification & Resubmission
Once submitted in e-Procurement, the Consultant cannot view or modify his Proposal
since it is locked by encryption. However, resubmission of the Proposal by the
Consultants for any number of times superseding earlier Proposal(s) before the
submission date and time is allowed. Resubmission of a Proposal shall require
uploading all documents, including the financial Proposal, afresh. The system shall
consider only the last Proposal submitted.
9.4.2 Withdrawal
1) The Consultant may withdraw his Proposal before the Proposal submission deadline,
and it shall be marked as withdrawn and shall not get opened during the Proposal
25opening.
2) No Proposal should be withdrawn after the Proposal submission deadline and
before the Proposal validity period expires. If a Consultant withdraws the Proposal
during this period, the Procuring Entity shall be within its right to forfeit the Bid
Security (or enforce the Bid Securing Declaration, if it was allowed in lieu of Bid
Security), in addition to other punitive actions provided in the RFP Document for such
misdemeanour as per clause 8.4 above.
Proposal Opening
The Proposals shall be opened on or after the date & time of the opening stipulated in
TIS. Proposals cannot be opened before the specified date & time, even by the Tender
Inviting Officer, the Procurement Officer, or the Publisher. If the specified date of
Proposal opening falls on is subsequently declared a holiday or closed day for the
Procuring Entity, the Proposals shall be opened at the appointed time on the next
working day.
Evaluation of Proposals and Award of Contract
11.1. General norms
11.1.1 Evaluation is based only on declared criteria.
1) The evaluation shall be based upon scrutiny and examination of all relevant data
and details submitted by the Consultant in its/ his Proposal and other allied
information deemed appropriate by Procuring Entity. Evaluation of Proposals shall
be based only on the criteria/ conditions included in the RFP Document. The
Selection Method to be used for evaluation shall be QCBS as mentioned in the TIS.
2) The determination shall not consider the qualifications of other firms, such as the
consultant's subsidiaries, parent entities, affiliates, or any other firm(s) different from
the consultant.
3) Consultants planning to subcontract any Key Activities indicated in Section VI: terms of
Reference and its sub-sections must ensure compliance with ITC-Clause 3 above.
4) Information relating to the evaluation of RFPs and evaluation results shall not be
disclosed to any participant or any other persons not officially concerned with such
process until the notification of shortlisting is made in accordance with clause 13.1
below.
11.1.2 Deviations/ Reservations/ Omissions - Substantive or Minor
During the evaluation of Proposals, the following definitions apply:
a) “Deviation” is a departure from the requirements specified in the RFP
Document;
b) “Reservation” is the setting of limiting conditions or withholding from
complete acceptance of the requirements specified in the RFP Document;
and
c) “Omission” is failing to submit part or all of the information or
documentation required in the RFP Document.A deviation/ reservation/ omission from the requirements of the RFP Document
shall be considered a substantive deviation as per the following norm, and the
rest shall be considered a Minor deviation:
a) which affects in any substantive way the scope, quality, or performance
standards of the Services;
b) which limits in any substantive way, inconsistent with the RFP Document, the
Procuring Entity's rights, or the Consultant's obligations under the contract;
or
c) Whose rectification would unfairly affect the competitive position of other
Consultants presenting substantively responsive Proposals.
The decision of the Procuring Entity shall be final in this regard. Proposals with
substantive deviations shall be rejected as nonresponsive.
Variations, deviations, and other offered benefits (Techno-commercial or
Financial) above the scope/ quantum of Services stipulated in the RFP Document
shall not influence evaluation Proposals. If the Proposal is otherwise successful,
such benefits shall be availed by the Procuring Entity, which would become part
of the contract.
The Procuring Entity reserves the right to accept or reject Proposals with minor
deviations. Wherever necessary, the Procuring Entity shall convey its observation
as per ITC-clause 11.1.3 below on such ‘minor’ issues to the Consultant by
registered/ speed post/ electronically etc., asking Consultant to respond by a
specified date. If the Consultant does not reply by the specified date or gives an
evasive reply without clarifying the point at issue in clear terms, that Proposal
shall be liable to be rejected as nonresponsive.
11.1.3 Clarification of Proposals and shortfall documents
1) During the evaluation of Techno commercial or Financial Proposals, the Procuring
Entity may, at its discretion, but without any obligation to do so, ask the Consultant
to clarify its Proposal by a specified date. The consultant should answer the
clarification within that specified date (or, if not specified, 7 days from receiving such
a request). The request for clarification shall be submitted in writing or electronically,
and no change in prices or substance of the Proposal shall be sought, offered, or
permitted that may grant any undue advantage to such Consultant. Any clarification
submitted by a Consultant regarding its Proposal that is not in response to a request
by the Purchasing Entity shall not be considered.
2) The Procuring Entity reserves its right to, but without any obligation to do so, seek
any shortfall information/ documents only in case of historical documents which pre-
existed at the time of the Proposal Opening and which have not undergone change
since then and do not grant any undue advantage to any Consultant. There is a
provision on the portal for requesting Short-fall documents from the Consultants.
The system allows taking the shortfall documents from consultants only once after
the technical Proposal opening.
273) If the consultant fails to provide satisfactory clarification and/or missing information,
its RFP shall be evaluated based on available information and documents.
11.1.4 Contacting Procuring Entity during the evaluation
From Proposal submission to awarding of the contract, no Consultant shall contact the
Procuring Entity on any matter relating to the submitted Proposal. If a Consultant needs
to contact the Procuring Entity for any reason relating to this tender and/ or its Proposal,
it should do so only in writing or electronically. Any effort by a Consultant to influence
the Procuring Entity during the processing of Proposals, evaluation, Proposal
comparison or award decisions shall be construed as a violation of the Code of Integrity,
and the Proposal shall be liable to be rejected as nonresponsive in addition to other
punitive actions for violation of Code of Integrity as per the RFP Document.
11.2. Evaluation of Proposals
11.2.1 Preliminary Examination of Proposals - Determining Responsiveness
A substantively responsive Proposal is complete and conforms to the RFP Document's
essential terms, conditions, and requirements without substantive deviation, reservation,
or omission. Proposals with substantive techno-commercial deviations or other essential
aspects of the RFP shall be rejected as nonresponsive. Only substantively responsive
Proposals shall be considered for further evaluation. Procuring entity reserves its right
to consider and allow minor deviations in technical and Commercial Conditions. Unless
otherwise stipulated in the AITC, the following are some of the crucial aspects for which
a Proposal shall be rejected as nonresponsive:
1) The Proposal is not in the prescribed format or is not submitted as per the stipulations
in the RFP Document.
2) Failure to provide and/ or comply with the required information, instructions etc.,
incorporated in the RFP Document or evasive information/ reply against any such
stipulations.
3) Required Bid Security (EMD) (or Bid Securing Declaration BSD if permitted) has not
been provided.
4) Consultant no longer complies with the eligibility criteria in the RFP;
5) The Services offered are not eligible as per the provision of this tender.
6) The consultant has quoted conditional Proposals or more than one Proposal or
alternative Proposals unless permitted explicitly in the AITC.
7) The Proposal validity is shorter than the required period.
8) The Proposal departs from the essential requirements stipulated in the bidding
document;
9) The consultant has quoted ‘Nil’ Service charges/ margin/overhead over the minimum
wages
in Personnel Deployment Schedule.
10) Non-submission or submission of illegible scanned copies of stipulated documents/
declarations11) Furnishing wrong and/ or misguiding data, statement(s) etc. In such a situation,
besides rejecting the Proposal as nonresponsive, it is liable to attract other punitive
actions under relevant provisions of the RFP Document for violating the Code of
Integrity.
11.2.2 The evaluation process
Unless otherwise stated, only the techno-commercial Proposals shall be opened on the
stipulated date of opening of Proposals. After that, the techno-commercial evaluation
shall ascertain whether these Proposals meet the requirements of the Terms of
Reference, Technical Criteria and Minimum Score. Subsequent opening of financial
Proposals and financial evaluation shall be done only of Proposals declared successful
in techno-commercial evaluation. The evaluators of the Technical Proposals shall have
no access to the Financial Proposals until the technical evaluation results are declared
and financial proposals are opened.
11.3. Techno-commercial Evaluation
11.3.1Evaluation of Technical Proposals/ Score
1) Procuring Entity shall evaluate the Technical proposal and assign scores as per the
Scheme of criteria and sub-criteria as laid down in ‘Section VII: Evaluation/ Scoring
Criteria’. This determination shall, inter-alia, consider the Consultant’s (i) “Specific
experience of the Consultant (as a firm) relevant to the Assignment”; ii) “Adequacy and
quality of the proposed methodology, and work plan”; iii) “Key Experts’
qualifications and competence for the Assignment”.
2) In the case of JV/C, the evaluation of the Technical proposal shall include the
credentials of all members, including non-substantial members.
3) If it is established that any Key Expert nominated in the Consultant’s Proposal was
included in the Proposal without his/her confirmation, such Proposal shall be
disqualified and rejected for further evaluation and shall be treated as a violation of
the Code of Ethics and would be liable for penalties thereunder.
4) All Key Experts (including the Team Lead) must meet the minimum requirements
specified in Section VI-A: List of Key Experts and Required Qualifications. If any Key
Expert fails to meet these minimum requirements, his score shall be evaluated as
Nil. If any Key Expert or Team Lead of the successful consultant scores less than the
50% 75% the maximum score, Procuring Entity shall be entitled to ask for a better
replacement before the negotiations as per ITC-Clause 12 below.
11.3.2 Evaluation of Conformity to Commercial and Other Clauses
Consultants must comply with all the Commercial and other clauses of the RFP
Document as per submissions in Form T-7: ‘Terms and Conditions – Compliance’. The
Procuring Entity shall also evaluate the commercial conditions quoted by the Consultant
to confirm that all essential terms and conditions stipulated in the RFP Document have
been accepted without substantive omissions/ reservations/exceptions/ deviation by the
Consultant. Deviations from or objections or reservations to critical provisions such as
29those concerning (but not limited to) Governing laws and Jurisdiction (GCC Clause 3),
Consultant’s Obligations and Restrictions of its Rights (GCC Clause 5), Performance
Bond/ Security (GCC Clause 5.8), Force Majeure (GCC Clause 9.6), Taxes & Duties
(GCC Clause 10.2), and Code of Integrity (GCC Clause 13) shall be deemed to be a
substantive deviation and treated as unresponsive as per clause 11.1.2 (3) above.
11.3.3 Evaluation of Techno-commercially Suitable Consultants and
Opening Financial Proposals
Each responsive Proposal shall be given a technical score applying the evaluation
criteria, sub-criteria, and scoring system specified in Section VII: Evaluation/ Scoring
Criteria. A Proposal shall be rejected if it fails to achieve the minimum 80% technical
score. Proposals that succeed in the above techno-commercial evaluation shall be
considered techno-commercially suitable. The list of such techno-commercially suitable
Consultants shall be declared on the Portal announcing a date/time and venue for
opening their financial Proposals (not less than 10 days from this declaration, in linew ith
ITC-Clause 14 below). The Procuring Entity shall notify all Consultants whether their
proposal was found responsive/ non-responsive to the RFP and TOR and whether they
met the minimum qualifying technical score. Financial proposals of successful
Consultants only shall be opened online. The financial proposals of unsuccessful
Consultants shall remain encrypted and unopened.
11.4. Financial Proposals Evaluation and Ranking of Proposals
11.4.1Financial Proposals Evaluation
1) Financial Proposals of all Techno-commercially suitable Proposals are evaluated
based on the selection method declared in the RFP Document (LCS/QCBS/FBS)
and ranked accordingly. The financial proposal will be in 2 parts consisting of (i)
the amount of Performance Bank Guarantee offered by the bidder, (ii) the financial
quote of the services quoted by the bidder.
2) Unless otherwise stipulated, the evaluation of prices shall be on total outgo from the
Procuring Entity’s pocket, to be paid to the Consultant or any third party, including
all elements of costs as per the terms of the proposed contract, duly delivered, as
the case may be, including any taxes, duties, levies etc.
3) In the case of JV/C, the financial credentials of non-substantial members shall not
be considered in the financial evaluation.
4) As per policies of the Central Government, from time to time, the Procuring Entity
reserves its option to give purchase preferences to eligible categories of Consultants as
indicated in the RFP Document.
5) evaluation of Proposals shall include and consider the following taxes/ duties, as
per ITC-clause 5.3 above:
a) in the case of Services performed in India or incidental goods of foreign
origin already located in India, GST & other similar duties shall be
contractually payable on the Services and incidental Goods if a contract is
awarded to the Consultant;
b) The offers shall be evaluated based on the GST rate quoted by eachConsultant, and the same shall be used for determining the inter-se ranking.
The Procuring Entity shall not be responsible for any misclassification of the
HSN number or incorrect GST rate quoted by the Consultant. Any increase
in GST rate due to misclassification of HSN number shall have to be
absorbed by the supplier; and
c) If GST is quoted extra but with the provision that it shall be charged as
applicable at the time of delivery, the offer shall be evaluated for comparison
purposes by loading the maximum existing rate of GST for the product/ HSN
code.
d) If a bidder enters “zero/blank” GST or an erroneous GST, the financial
evaluation will be done considering the “Zero” or quoted GST rate, as the
case may be. In cases where the successful bidder quotes the wrong GST
rate for releasing the order, the following methodology will be followed:
i) If the actual GST rate applicable is lower than the quoted GST rate, the
actual GST rate will be added to the quoted basic prices. The final cash
outflow will be based on the actual GST rate.
ii) If the actual GST rate applicable is more than the quoted GST rate, the
basic prices quoted will be reduced proportionately, keeping the final
cash outflow the same as the overall quoted amount.
6) Correction Errors/ adjustments:
a) Loading for Deviations: Unless announced beforehand, the quoted price
shall not be loaded based on deviations in commercial conditions. If it is so
declared, such loading of a financial Proposal shall be done as per the
relevant provisions;
b) Discrepancies between Technical and Financial Proposal:
i) Activities and items described in the Technical Proposal but not priced in
the Financial Proposal shall be assumed to be included in the prices of
other activities or items, and no corrections are made to the Financial
Proposal.
ii) If a Lump-Sum contract selection method is declared in the RFP, the
Consultant is deemed to have included all prices in the Financial
Proposal, so neither arithmetical corrections nor price adjustments shall
be made.
iii) If a Time-Based contract selection method is declared in the RFP, in case
of discrepancy between the Technical and Financial Proposals in
indicating quantities of input, any higher quantities in Technical Proposal
shall prevail, and the quoted total prices shall be assumed to apply to
this higher quantum. The unit rate for such activity shall be accordingly
adjusted. No such correction shall be done if quantities are lower in the
Technical proposal.
c) Discounts and Rebates: If any Consultant offers conditional discounts/
rebates in his Proposal or suo-motu discounts and rebates after the Proposal
Opening (techno-commercial or financial), such rebates/ discounts shall not
31be considered for ranking the offer. But if such a Consultant gets selected as
per the selection method, without discounts/ rebates, such discounts/ rebates
shall be availed and incorporated in the contracts;
d) Price Variation: If the tenders have been invited on a variable price basis, the
tenders shall be evaluated, compared, and ranked based on the position as
prevailing on the last deadline for techno-commercial Proposal submission
and not on any future date.
7) Ambiguous Financial Proposal: If the financial Proposal is ambiguous and leads
to two equally valid total price amounts, it shall be rejected as nonresponsive.
8) Time-Based (Input Admeasurement) Contracts: The Consultant’s Proposal
must include the Key Experts’ time-input person-months not less than the minimum
specified in Section VI-A: List of Key Experts and Required Qualifications.
a) Minimum Time Inputs: if a Proposal includes less or more than the required
minimum person-month time input, the proposal shall be considered as per
sub-clause 6. b)-iii) above for that key-position
b) The proposal shall be evaluated based on remuneration cost plus
reimbursable expenses as quoted by the consultants in the prescribed
financial forms. The travel expense (TA/DA for authorized travel outside the
home station) shall be reimbursed by the Procuring Entity on an actual basis.
It shall be limited to the entitlement in Appendix D to the Contract Form.
Therefore, travel expenses (TA/DA for authorized travel outside the home
station) need not be quoted in the financial proposal for evaluation.
9) Quality and Cost-Based Selection (QCBS): In the case of QCBS, the total
score is calculated by 60% weightage to the technical, 20 % Weightage to the
performance security Quoted by the bidder and 20% weightage to financial quote
submitted by bidder and adding them to obtain a combined QCBS (Technical cum
Financial) score, as explained in the sub- clauses below. The proposal obtaining the
highest total combined score in evaluating quality and cost will be ranked as H-1,
followed by the proposals securing lesser marks as H-2, H-3 etc. The proposal
securing the highest combined marks and ranked H-1 will be invited for
negotiations as per ITC-Clause 12 below. If two or more bids have the same highest
score in the final ranking, the bid with a higher financial score will be H-1.
a) The Technical Proposals are given an absolute technical score (Ta out of max
100) based on the evaluation criteria in Section VII: Evaluation/ Scoring
Criteria. However, to normalise this w.r.t. Financial Score Sf below, a relative
Technical Score (St) based on their relative ranking shall be calculated. Thehighest evaluated Technical Score (Ta-max) is assigned the maximum
relative Technical Score (St) of 100 (Hundred). The formula for determining
the relative Technical scores (St) of all other Proposals is as follows:
St = 100 x Ta/ Ta-max,
in which "Ta-max" is the highest evaluated absolute Technical Score, "St" is
the relative Technical score calculated, and "Ta" is the absolute Technical
Score of the proposal under consideration. This normalisation would avoid
any unintended magnification of weightage to the financial score due to
different scales of Technical Scores and Financial Scores.
b) The Financial Proposals shall be evaluated in two parts :-
i) The relative ranking of performance security, with the highest performance
Security (PBGm) being assigned the maximum financial score (PBGf) of
100(Hundred). The formula for determining the financial scores (PBGf) of all
other Proposals is as follows:
PBGf = 100 x PBG/ PBGm,
in which "PBGm" is the highest bid security offered, "PBGf" is the financial score
calculated, and "PBG" is the amount of PBG of the proposal under consideration.
ii) The cost-score based on the relative ranking of prices, with the lowest
evaluated Financial Proposal (Fm) being assigned the maximum financial score
(Sf) of 100(Hundred). The formula for determining the financial scores (Sf) of
all other Proposals is as follows:
Sf = 100 x Fm/ F,
in which "Fm" is the price of the lowest offer, "Sf" is the financial score
calculated, and "F" is the price of the proposal under consideration.
c) The weights given to the Technical (T), Performance BG (PBG) and Financial (P) Quote
Proposals are specified in TIS/ AITC:
T (the weight given to the Technical Proposal) = 60%, and
PBG (the weight given to the PBG Financial Proposal) = 20% %
Sf (the weight given to the Financial Quote of services by bidder) = 20% % (with
T + PBGf+Sf = 100%)
d) Proposals would be ranked according to their combined QCBS (weighted
technical, St and financial, Sf ( which will include of PBG and financial
Quote)) scores as follows:
S = (St x T + PGBf x PBG +Sf x P)/100.
in which "S" is the combined QCBS score, "St" is the relative technical score
calculated as per sub-clause a) above and "Sf" is the financial score
calculated as per sub-clause b) above.
e) All scores shall be calculated up to two decimal places only.
11.4.2 Global Tender Enquiry (GTE, International Competitive Bidding)
The following additional aspects of the evaluation of the financial offer shall also apply:
1) Currency of Tender
33In GTE tenders, if permitted in AITC, the Proposal price may be in foreign
currencies, except for expenditure incurred in India (including incidental Works/
Goods/ Services delivered in India and agency commission, if any) should be
stated in Indian Rupees.
2) Evaluation of Offers
All financial Proposals shall be converted to Indian Rupees based on the “Bill for
Collection (BC) selling” exchange rate on the last deadline for the Proposal
submission (Techno-commercial offer) from a source as specified (State Bank of
India, if not so specified) in the tender document. The offers would be compared
based on the principle of the total outgo from Procuring Entity’s pockets,
including all applicable taxes and duties (Customs duty, GST, and GSTC ess). For
Proposals with Letter of Credit (LC) payment, the likely LC charges (as ascertained
from the Procuring Entity’s bankers) should also be loaded. Import of Goods or
services or both attract integrated tax (IGST). The IGST rate and GST cess shall be
applicable on the ‘Custom Assessable Value’ plus the ‘Basic Customs duty
applicable thereon’.
The terms FOB, FAS, CIF, DDP etc., shall be governed by the rules & regulations
prescribed in the current edition of INCOTERMS, published by the International
Chamber of Commerce, Paris
Contract Negotiation
12.1. Invitation to Negotiate
The negotiations shall be held at the date and address announced after the selection of
the successful Consultant with their representative(s), who must have written power of
attorney to negotiate and sign a contract on behalf of the Consultant. During the
negotiations, it shall be ensured that no undue advantage accrues to the Consultant
and that nothing shall vitiate the basis on which he has been declared successful. The
minutes of negotiations shall be signed by the Procuring Entity and the Consultant’s
authorized representative.
12.2. Verification of Original Documents
Before issuing a Letter of Award (LoA) to the successful Consultant(s), the Procuring
Entity may, at its discretion, ask the Consultant to present the originals of all such
documents whose scanned copies were submitted online during shortlisting process and
this RFP process. If so decided, the photocopies of such self-certified documents shall
be verified and signed by the competent officer and kept in the records as part of the
contract agreement. If the Consultant fails to provide such originals or in case of
substantive discrepancies in such documents, it shall be construed as a violation of the
Code of Integrity. Such Proposal shall be liable to be rejected as nonresponsive in
addition to other punitive actions in the Code of Integrity.12.3. Availability of Key Experts:
As a pre-requisite to the negotiations, the invited Consultant shall make the all Key
Experts included in the Proposal available for interaction/interview at given date and time before
the Authority or the committee so constituted for this purpose. Failure to present Key Experts’
for interaction/interview before the Authority at given date and time may result in the
Consultant’s Proposal being declared non-responsive and the Procuring Entity proceeding
to negotiate the Contract with the next-ranked responsive Consultant. However,
Authority may finalise a scheme of empanelment of key personnel and finding their
suitability for a specific job profile and update the suitability/ empaneled status on
Infracon. Those key personnel who have been declared suitable on Infracon for a
particular role shall not be interviewed again at the time of negotiation. Only those
key personnel will be interviewed at negotiation stage who has not been empaneled
for a particular post on Infracon portal shall be interviewed at negotiation stage to
find their suitability for the assignment.
Notwithstanding the above, the substitution of Key Experts at the negotiations may be
considered if due solely to circumstances outside the reasonable control of and not
foreseeable by the Consultant, including but not limited to death or medical incapacity
or as per the conditions specified in this RFP.I n such case, the Consultant shall offer a
substitute Key Expert within the period specified in the invitation letter to negotiate the
Contract, who shall have equivalent or better qualifications and experience than the
original candidate.
As per ITC-Clause 11.3.1-4), Procuring Entity reserves its right to seek during
negotiations the replacement of the Team Leader/ other Key Experts who found not
suitable for assignment during interaction/interview.
12.4. Technical Negotiations
The negotiations include discussions of the Terms of Reference (TORs), the proposed
methodology, the Procuring Entity’s inputs, the special conditions of the Contract, and
finalizing the ‘Appendix A: Terms of Reference’ part of the Contract. These discussions
shall not substantially alter the original scope of services under the TOR or the terms of
the contract lest the quality of the final product, its price, or the initial evaluation be
vitiated.
12.5. Financial Negotiations - :-
Deleted
12.6. Conclusion of Negotiations
The negotiations are concluded with a review of the finalized draft Contract, which shall
be initiated by the Procuring Entity and the Consultant’s authorized representative.
If the negotiations fail, the Procuring Entity shall inform the Consultant in writing of all
pending issues and disagreements and provide a final opportunity for the Consultant
to respond. If disagreement persists, the Procuring Entity shall declare the proposal non-
responsive, informing the Consultant of the reasons for doing so. The Procuring Entity
35shall invite the next-ranked responsive Consultant to negotiate a Contract. Once the
Procuring Entity commences negotiations with the next-ranked Consultant, the Procuring
Entity shall not reopen the earlier negotiations.
Award of Contract
13.1. Letter of Award (Acceptance - LoA) and Signing of Contract
13.1.1Letter of Award (LoA)
After 10 days from the conclusion of negotiations (in line with ITC-Clause 14 below),
the Consultant whose Proposal has been accepted shall be notified of the award by the
Procuring Entity before the expiration of the Proposal validity period by written or
electronic means. This notification (hereinafter and in the Conditions of Contract called
the "Letter of Award - LoA") shall state the sum (hereinafter and in the contract called
the "Contract Price") that the Procuring Entity shall pay the Consultant in consideration
of delivery of Services. The Letter of Award (LoA) shall constitute the legal formation of
the contract, subject only to the furnishing of performance security as per the provisions
of the sub-clause below. The Procuring Entity, at its discretion, may directly issue the
contract subject only to the furnishing of performance security, skipping the issue of
LoA.
13.1.2 Performance Security
1) The performance security shall be criteria for financial evaluation. The consultants
are required to quote the amount of performance Security only. The Cost of
proposal shall be fixed by the Authority.
2) Within the number of days stipulated in AITC (or 21 days if not specified) of receipt
of the Letter of Award (LoA, or the contract if LoA has been skipped), performance
Security as per details in GCC-5.8 shall be submitted by the Consultant to the
Procuring Entity.
3) If the Consultant, having been called upon by the Procuring Entity to furnish
Performance Security, fails to do so within the specified period, it shall be lawful for
the Procuring Entity at its discretion to annul the award and forfeit EMD (or enforce
Bid Securing Declaration if it was permitted to be submitted in lieu of Bid Security),
besides taking any other administrative punitive action like ‘Removal from List of
Registered Suppliers’ etc.
13.1.3 Signing of Contract
1) Publication of Results: The Procuring Entity shall send to each techno-commercially
suitable Consultant the Notification of Intention to Award the Contract to the
successful Consultant. The Notification of Intention to Award shall contain, at a
minimum, the following information:
a) the name and address of the Consultant with whom the Procuring Entity
successfully negotiated a contract;
b) the contract price of the successful Proposal;
c) the names of all Consultants included in the short list for RFP, indicatingthose that submitted Proposals;
d) the final combined scores and the final ranking of the Consultants
e) The name and address of the successful Consultant(s) receiving the
contract(s) shall be published in the Portal and notice board/
bulletin/website of the Procuring Entity.
2) After the award notification, the Procuring Entity shall share a copy of the Contract
Agreement (as per Format 1: Contract Form along with sub-formats) to a successful
Consultant for review. The Consultant may point out to the Procuring Entity, in
writing/ electronically, any anomalies noticed in the contract within seven days of
receipt. The Contract Agreement shall be executed within 21 days after the date of
issue of the Letter of Acceptance and after submission and verification of the
Performance Security.
3) If asked by the Procuring Entity, the successful Consultant shall return the original
copy of the contract, duly signed, and dated, within seven days from the date of
receipt of the contract, to the Procuring Entity by registered/ speed post or by a
suitable digital means.
Grievance Redressal/ Complaint Procedure
1) The consultant has the right to submit a complaint or seek de-briefing regarding the
rejection of his proposal, in writing or electronically, within 10 days of the
declaration of techno-commercial or financial evaluation results. The complaint
shall be addressed to the Head of Procurement.
2) Within 5 working days of receipt of the complaint, the Tender Inviting Officer shall
acknowledge the receipt in writing to the complainant, indicating that it has been
received, and the response shall be sent in due course after a detailed examination.
3) The Tender Inviting Officer shall convey the final decision to the complainant within
15 days of receiving the complaint. No response shall be given regarding the
confidential process of evaluating Proposals and awarding the contract before the
award is notified, although the complaint shall be kept in view during such a
process. However, no response shall be given regarding the following topics
explicitly excluded from such complaint process:
a) Only a Consultant who has participated in the procurement process, i.e.,
pre-qualification, Consultant registration or bidding, as the case may be,
can make such representation.
b) Only a directly affected Consultant can represent in this regard.
c) In the case of RFP, before the bidding of Technical/ financial Proposals, an
application for review concerning the technical/ financial Proposal may be
filed only by a Consultant who has qualified in the RFP;
d) If a technical Proposal has been evaluated before the opening of the
financial Proposal, an application for review concerning the financial
Proposal may be filed only by a Consultant whose technical Proposal is found
to be acceptable.
374) No third-party information (RFPs, evaluation results) can be sought or included in
the response.
5) The following decisions of the Procuring Entity shall not be subject to review:
a) Determination of the need for procurement.
b) Complaints against Terms of Reference except under the premise that they
are either vague or too specific to limit competition
c) Selection of the mode of procurement or bidding system;
d) Choice of the selection procedure.
e) Provisions limiting the participation of Consultants in the Procurement
Process, in terms of policies of the Government
f) Provisions regarding purchase preferences to specific categories of
Consultants in terms of policies of the Central Government
g) Cancellation of the Procurement Process except where it is intended to
subsequently re-tender the same Services.
Code Integrity in Public Procurement, Misdemeanors and
Penalties:
Procuring authorities, Consultants, suppliers, contractors, and consultants should
observe the highest standard of integrity and not indulge in prohibited practices or other
misdemeanors, either directly or indirectly, at any stage during the Procurement
Process or the execution of resultant contracts. GCC-clause 13 (including the penalties
prescribed therein) shall be considered part of this clause of ITC (even though it is not
being reproduced here for brevity) and shall apply mutatis mutandis during the pre-
award Procurement Process.Section III: Appendix to Instructions to Consultants (AITC)
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services
(Ref ITC-clause 1.4)
{Note for Procuring Entity: Text in grey italics font within square bracket [e.g., Mention
…] are just suggestions/ directions and must be replaced by applicable text - remove
brackets and convert the font to regular and black. Delete the rows not required. Clauses
other than those mentioned below may also be mentioned if these need to be changed}
Note for Consultants: Following clauses (in column 1), wherever these appear in ITC,
shall be taken to be negated or additional provisions be added to, or existing provisions
be altered as per column 2. Whenever there is any conflict between the provision in the
ITC and that in the AITC, the provision contained in the AITC shall prevail.
ITC- To be read as
Clauses
ITC 1: Contents of RFP
ITC 1.3, [Mention any additional Sections, Forms or Formats in the RFP]
1.4, 1.5
ITC 3 Consultants - Eligibility and Preferential Policies
ITC 3.2 [Mention if shortlisted Consultants are not allowed to associate
with other shortlisted/non-shortlisted Consultants]
ITC 3.2 Mention if the participation of Sub-consultants, Key Experts and Non-
Key Experts in more than one Proposal is not allowed]
ITC 4 The Terms of Reference and Form of Contract
ITC 4.1 [Mention facilities, if any, to be provided by the Procuring Entity
to Consultant]
ITC 5. Proposal Prices, Taxes and Duties
ITC 5.1.5 [If prices are permitted to be quoted in currencies other than INR
also, as in the case of Global Tenders]
ITC 5.2.2 [Mention if the Price Variation Clause is applicable. Also, mention the
formula and indices]
ITC 5.4.1 [Mention payment terms, if different]
ITC 5.4.2 [Mention if Advance Payments are allowed – including types and %age]
ITC 6 to 10 Downloading, Preparation, Submission and Opening of Proposals
ITC 8.1.1 [Language in which Proposals are to be submitted – English or
otherwise]
ITC 8.2.1 [Mention if Integrity Pact is to be Signed and Submitted along with
Proposal. Include the Name and Contact Details of the Independent
External Monitor (IEM) for Integrity Pact]ITC 11 and 12 Evaluation of Proposals and Award of Contract
ITC 11.2.1 [Mention if additional criteria for responsive Proposals are proposed]
ITC 11.4.2 [Customise by indicating here whether this is a Global Tender Enquiry
(International Competitive Bidding) and the foreign currencies
permitted]
ITC 13.1.2 [Mention the period for submission of Performance Security if
different from 21 days]Section IV: General Conditions of Contract (GCC)
General
1.1. Tenets of Interpretation
Unless where the context requires otherwise, throughout the contract:
1) The headings of these conditions shall not affect the interpretation or construction
thereof.
2) Writing or written includes matter either whole or in part, in digital communications,
manuscript, typewritten, lithographed, cyclostyled, photographed, or printed under
or over signature or seal or digitally acceptable authentication, as the case may be.
3) Words in the singular include the plural and vice-versa.
4) Words importing the masculine gender shall be taken to include other genders, and
words importing persons shall include any company, association, or body of
individuals, whether incorporated or not.
5) Terms and expressions not herein defined shall have the meanings assigned to them
in the contract Act, 1872 (as amended) or the Sale of Goods Act, 1930 (as
amended) or the General Clauses Act, 1897 (as amended) or of INCOTERMS,
(current edition published by the International Chamber of Commerce, Paris) as the
case may be.
6) Any reference to ‘Services’ shall also be deemed to include the incidental Works/
Goods.
7) Any reference to any legal Act, Government Policies or orders shall be deemed to
include all amendments to such instruments, from time to time, to date.
1.2. Definitions
In the contract, unless the context otherwise requires:
1) “Allied Firm” are all business entities that are within the ‘controlling ownership
interest’ (ownership of or entitlement to more than twenty-five per cent of the
company's shares or capital or profits) or ‘control’( including the right to appoint a
majority of the directors or to control the management or policy decisions including
by virtue of their shareholding or management rights or shareholder agreements or
voting agreements) of the principal firm acting alone or together or through one or
more juridical persons. All successor firms or assigns of the principal firm shall be
considered allied firms;
2) “Bill of Quantities” (including the term Price Schedule or BOQ) means the priced
and completed Bill of Quantities forming part of the Proposal;
3) "Commercial Bank" means a bank, defined as a scheduled bank under section 2(e)
of the Reserve Bank of India Act, 1934;
4) “Contract” (including the terms ‘Purchase Order’ or ‘Supply Order’ or ‘Withdrawal Order’
or ‘Work Order’ or ‘Consultancy Contract’ or ‘Contract for Services’, ‘ratecontract’ or ‘framework contract’ or ‘Letter of Award – LoA’ (letter or memorandum
communicating to the Consultant the acceptance of his Proposal) or ‘Agreement’ or a
‘repeat order’ accepted/ acted upon by the Consultant in specific contexts), means a
formal legal agreement in writing relating to the subject matter of procurement,
entered into between the Procuring Entity and the Consultant on mutually acceptable
terms and conditions and which are in compliance with all the relevant provisions
of the laws of the country;
5) "Consultant" (as a participant in a Procurement Process - including the term
'contractor', ‘bidder’, ‘tenderer‘, participant’ or 'service provider' in specific contexts)
means any person or firm or company, including any member of a consortium or
joint venture, every artificial juridical person not falling in any of the descriptions of
Consultants stated hereinbefore, including any agency branch or office controlled
by such person, participating in a Procurement Process;
6) “Consultant” (as a contract holder - including the terms ‘Supplier’ or ‘Service
Provider’ or ‘Contractor’ or ‘Firm’ or ‘Vendor’ or ‘Successful Consultant’ in specific
contexts) means the person, firm, company, or Joint Venture with whom the contract
is entered into and shall be deemed to include the Consultant's successors (approved
by the Procuring Entity), agents, Sub-consultant, representatives, heirs, executors,
and administrators as the case may be unless excluded by the terms of the contract;
7) “Contract Manager” means (as distinct from Team Leader of the Consultant) the
Procurement Officer or any other officer or a third-party agency who has been
assigned the authority to take all actions on behalf of the Procuring Entity during the
execution of the contract by the Consultant;
8) “Day”, “Month”, and “Year” shall mean respectively calendar day, month or year
(unless reference to financial year is apparent from the context);
9) “Effective Date” means the date on which this Contract comes into force and effect
as per the Contract;
10) “Experts” means, collectively, Key Experts, Non-Key Experts, or any other personnel of
the Consultant, Sub-consultant or JV member(s) assigned by the Consultant to
perform the Services or any part thereof under the Contract;
11) "Goods" (including the terms ‘Stores’, and ‘Material(s)’ in specific contexts) includes all
articles, materials, commodities, livestock, medicines, furniture, fixtures, raw
material, consumables, spare parts, instruments, machinery, equipment, industrial
plant, vehicles, aircraft, ships, railway rolling stock assemblies, sub-assemblies,
accessories, a group of machines comprising an integrated production process or
such other categories of goods or intangible, products like technology transfer,
licenses, patents or other intellectual properties (but excludes books, publications,
periodicals, etc., for a library), in specific contexts, procured or otherwise acquired
by a Procuring Entity. Any reference to Goods shall be deemed to include small work
or some services that are incidental or consequential to the supply of such goods;12) “Government" means the Central Government or a State Government, as the case
may be and includes agencies and Public Sector Enterprises under it in specific
contexts;
13) “Intellectual Property Rights” (IPR) means the intellectual property owner's rights
concerning possession/ exploitation of such property by others of tangible or
intangible intellectual property, including rights to Patents, Copyrights, Trademarks,
Industrial Designs, Geographical indications (GI);
14) “Joint Venture (JV or JV/C)” means an association or a Consortium with or without a
legal personality distinct from that of its members, of more than one entity where
one member has the authority to conduct all businesses for and on behalf of any
and all the members of the JV, and where the members of the JV are jointly and
severally liable to the Procuring Entity for the performance of the Contract.;
15) “Key Expert(s)” means an individual professional (usually identified by name) whose
skills, qualifications, knowledge, and experience are critical to the performance of
the Services under the Contract and whose Curricula Vitae (CV) was considered in
the technical evaluation of the Consultant’s proposal;
16) “Non-Key Expert(s)” means an individual professional (usually not identified by
name) provided by the Consultant or its Sub-consultants to perform the Services or
any part thereof under the Contract;
17) “Parties”: The parties to the contract are the "Consultant" and the “Procuring Entity”, as
defined in GCC clause 2.4;
18) “Performance Security” (includes the terms ‘Security Deposit’ or ‘Performance Bond’
‘Performance Bank Guarantee’ or other specified financial instruments in specific
contexts) means a monetary guarantee to be furnished by the successful Consultant
or Contractor in the form prescribed for the due performance of the contract;
19) “Procurement” (in the context of Public/ Government ‘procurement’ or ‘Purchase’, or
‘Acquisition’ including an award of Public-Private Partnership projects, in specific
contexts) means the acquisition of Goods/ Services/ works or a combination thereof
by way of purchase, lease, license or otherwise, either using public funds or any
other source of funds (e.g. grant, loans, gifts, private investment etc.) by a Procuring
Entity, whether directly or through an agency with which a contract for procurement
is entered into, but does not include any acquisition without consideration. The term
“procure”/ “procured” or “purchase”/ “purchased” shall be construed accordingly;
20) “Procuring Entity” means the entity in The Procuring Organization procuring Goods,
Works, or Services;
21) “Procurement Officer” means the officer signing the Letter of Award (LoA) and/or
the contract on behalf of the Procuring Entity;
22) “Procurement Process” (or “Tender”; “RFP”; “RFP”, “Tender Enquiry” in specific
contexts): ‘Procurement Process’ is the whole process from the publishing of the RFP
Document to the resultant award of the contract. ‘RFP Document’ means the
document (including all its sections, appendices, forms, formats, etc.) published by
the Procuring Entity to invite Proposals in a Procurement Process. The RFP Document
44and Procurement Process may be generically and interchangeably referred to as
“Bid Document”, “Tender" or " Tender Enquiry, " which would be clear from context
without ambiguity;
23) "Proposal" (including the term ‘tender’, ‘offer’, ‘quotation’ or ‘bid’ in specific
contexts) means an offer to supply goods, services or execution of works made as
per the terms and conditions set out in a document inviting such offers;
24) “Services” means the activities to be performed by the Consultant under this
Contract, as described in Appendix A thereto;
25) “Signed” means ink signed or digitally signed with a valid Digital Signature as per IT
Act 2000 (amended from time to time). It also includes stamped, except in the case
of a Letter of Award or amendment thereof;
26) “Sub-consultant” means a person or corporate body with an agreement with the
Consultant to carry out a specific part of the ‘Services’ while the Consultant remains
solely liable for the execution of the Contract;
27) “Variation” means an instruction given by the Contract Manager, which varies the
scope, quantum or performance standards of the Service performed;
28) “Works” refer to any activity involving construction, fabrication, repair, overhaul,
renovation, decoration, installation, erection, excavation, dredging, and so on,
which make use of a combination of one or more engineering designs, architectural
design, material and technology, labour, machinery, and equipment.
1.3. Document Conventions
All words and phrases defined in GCC-clause 1.2 are written as ‘Capitalised words’ and
shall have the defined meaning. The rest of the words shall be as per grammar, inter-
alia ‘Services’ shall indicate the definition given in the GCC, while ‘services’ shall have the
usual dictionary meaning.
1.4. Abbreviations:
AITC Appendix to Instructions To Consultants
BOQ Bill of Quantities
BSD Bid Securing Declaration
CV Curriculum Vitae
EMD Monetary guarantee to be furnished by a Consultant along
with its proposal
FBS Fixed Budget Selection
GCC General Conditions of Contract
GST Goods and Services Tax
GSTIN GST Identification NumberGTE Global Tender Enquiry (International Competitive Bidding)
HSN Harmonized System of Nomenclature
IEM Independent External Monitor
IPR Intellectual Property Rights
ITC Instructions To Consultants
JV/C Joint Venture/ Consortium
LCS Least Cost Selection
LoA Letter of Award (Acceptance)
QCBS Quality and Cost-Based Selection
RFP Request for Proposal
RFPL Request for Proposal Letter
SCC Special Conditions of Contract
TIA Tender Inviting Authority
TIS Tender Information Summary
TOR Terms of Reference
The Contract
2.1. Language of Contract
The contract and all subsequent correspondence documents, during its execution,
between the consultant and the Procuring Entity shall be written in the Language
(hereinafter called the contract’s language) as stipulated in the Contract (or, if not so
specified, in English). However, the language of any printed literature furnished by a
Consultant may be written in any other language provided a certified translation
accompanies the same in the contract’s language. For purposes of interpretation,
translation in the contract’s language shall prevail.
2.2. The Entire Agreement
This Contract and its documents (referred to in GCC-clause 2.5 below) constitute the
entire agreement between the Procuring Entity and the Consultant and supersede all
other communications, negotiations, and agreements (whether written or oral) of the
Parties made before the date of this Contract. No agent or representative of either Party
has the authority to make, and the Parties shall not be bound by or be liable for, any
statement, representation, promise or agreement not outlined in this Contract.
462.3. Severability
If any provision or condition of this Contract is prohibited or rendered invalid or
unenforceable, such prohibition, invalidity or unenforceability shall not affect the validity
or enforceability of the Contract or any of its other provisions and conditions.
2.4. Relationship between Parties
1) The parties to the contract are the Consultant and the Procuring Entity, as nominated
in the contract.
2) Nothing contained herein shall be construed as establishing a relationship in the
nature of master and servant or principal and agent between the Procuring Entity
and the Consultant. The Consultant, subject to this Contract, is legally the main
principal/ master of the Experts and Sub-consultants, if any, performing the Services
and shall be fully responsible for the Services performed by them or on their behalf
hereunder.
3) Authority of Member in Charge: In case the Consultant is a Joint Venture, the
members hereby authorize the member specified in the contract to act on their
behalf in exercising all the Consultant’s rights and obligations towards the Procuring
Entity under this Contract, including without limitation the receiving of instructions
and payments from the Procuring Entity.
4) Authorised Representative: Any action required or permitted to be taken and
any document required or permitted to be executed under this Contract by the
Procuring Entity or the Consultant may be taken or executed by the officials
specified in the contract.
5) Good Faith: The Parties shall act in good faith concerning each other’s rights under
this Contract and adopt all reasonable measures to ensure the realization of the
objectives of this Contract. The Consultant shall always act, in respect of any matter
relating to this Contract or the Services, as a faithful adviser to the Procuring Entity
and shall at all times support and safeguard the Procuring Entity’s legitimate
interests in any dealings with the third parties.
2.5. Contract Documents and their Precedence
The following conditions and documents in indicated order of precedence (higher to
lower) shall be considered an integral part of the contract, irrespective of whether these
are not appended/ referred to in it. Any generic reference to ‘Contract’ shall imply
reference to all these documents as well:
1) Valid and authorized Amendments issued to the contract.
2) The Agreement consisting of the initial paragraphs, recitals, and other clauses,
including the appendices annexed to it and signatures of Procuring Entity, set forth
immediately before the GCC;
3) Appendix A: Terms of Reference;
4) Appendix B: Key Experts;
5) Appendix C – Remuneration Cost Estimates;a) Annex to Appendix C: Breakdown of Agreed Fixed Rates in Consultant’s
Contract;
6) Appendix D – Reimbursable Expenses Cost Estimates;
7) the Letter of Award (LoA), if issued
8) the SCC
9) the GCC
10) the Consultant’s Proposal;
11) any other document listed in the contract as forming part of this Contract.
12) Integrity Pact, if any
2.6. Modifications/ Amendments, Waivers and Forbearances
2.6.1 Modifications/ Amendments of Contract
1) After the contract documents have been signed, no modified provisions shall be
applicable unless the Procuring Entity suo-moto or, on request from the Consultant,
by written order, amend the contract, at any time during the currency of the contract,
by making alterations and modifications within the general scope of the Contract.
Requests for changes and modifications in the Contract may be submitted in writing by
the Consultant to the Procuring Entity.
2) If the Consultant does not agree to the suo-moto modifications/ amendments made by
the Procuring Entity, he shall convey his views within 14 days from the date of
amendment/ modification. Otherwise, it shall be assumed that the Consultant has
consented to the amendment.
3) Any verbal or written arrangement abandoning, modifying, extending, reducing, or
supplementing the contract or any of the terms thereof shall be deemed conditional
and shall not be binding on the Procuring Entity unless and until the same is
incorporated in a formal instrument and signed by the Procuring Entity, and till then
the Procuring Entity shall have the right to repudiate such arrangements.
2.6.2 Waivers and Forbearance
The following shall apply concerning any waivers, forbearance, or similar action taken
under this Contract:
1) Any waiver of a Procuring Entity’s rights, powers, or remedies under this Contract
must be in writing, dated, and signed by an authorized representative of the
Procuring Entity granting such a waiver and must specify the terms under which the
waiver is being granted.
2) No relaxation, forbearance, delay, or indulgence by Procuring Entity in enforcing
any of the terms and conditions of this Contract or granting of an extension of time
by Procuring Entity to the Consultant shall, in any way whatsoever, prejudice, affect,
or restrict the rights of Procuring Entity under this Contract, neither shall any waiver
by Procuring Entity of any breach of Contract operate as a waiver of any subsequent
or continuing breach of Contract.
48Governing Laws and Jurisdiction
3.1. Governing Laws and Jurisdiction
1) This Contract, its meaning and interpretation, and the relation between the Parties
shall be governed by the Laws of India for the time being in force.
2) Irrespective of the place of delivery, the place of performance or the place of
payments under the contract, the contract shall be deemed to have been made at
the place from which the Letter of Award (LoA, or the contract Agreement, in the
absence of LoA) has been issued. The courts of such Delhi shall alone have
jurisdiction to decide any dispute arising out or in respect of the contract.
3.2. Changes in Laws and Regulations
Unless otherwise stipulated in the contract, if after the deadline for the Proposal
submission (Techno-commercial), any law, regulation, ordinance, order or bye-law
having the force of law is enacted, promulgated, abrogated, or changed in India (which
shall be deemed to include any change in interpretation or application by the competent
authorities) that subsequently affects the Delivery Date and/ or the contract Price, then
such Delivery Date and/ or Contract Price shall be correspondingly increased or
decreased as per GCC clause 2.6, by agreement between the Parties hereto, to the
extent that the Consultant has thereby been affected in the performance of any of its
obligations under the contract. Notwithstanding the foregoing, such additional or
reduced cost shall not be separately paid or credited if the same has already been
accounted for in the applicable price adjustment provisions.
Communications
4.1. Communications
All communications under the contract shall be served by the parties to each
other in writing, in the contract's language, and served in a manner customary
and acceptable in business and commercial transactions. Any notice, request
or consent required or permitted to be given or made pursuant to this contract
shall be routed through Data Lake only unless the law required to send such
notices requests etc through physical/any other specified mode only. Any such
notice, request or consent shall be deemed to have been delivered when given
or made on the Data Lake to an authorized representative of the Party specified
in the SC.
The effective date of such communications shall be either the date when
delivered to the recipient or the effective date mentioned explicitly in the
communication, whichever is later.
No communication shall amount to an amendment of the terms and conditions
of the contract, except a formal letter of amendment of the Contract expressly so
designated.
Such communications would be an instruction, a notification, an acceptance, a
certificate from the Procuring Entity, or a submission or a notification from the
Consultant. A notification or certificate required under the contract must becommunicated separately from other communications.
4.2. Persons signing the Communications
For all purposes of the contract, including arbitration, thereunder all communications
to the other party shall be signed by:
1) On behalf of the Consultant: The person who has signed the contract on behalf
of the Consultant shall sign all correspondences. A person signing communication
in respect of the contract or purported to be on behalf of the Consultant, without
disclosing his authority to do so, shall be deemed to warrant that he has authority
to bind the Consultant. If it is discovered at any time that the person so signing has
no authority to do so, the Procuring Entity reserves its right, without prejudice to any
other right or remedy, to terminate the contract for default in terms of the contract
and/ or avail any or all the remedies thereunder and hold such person personally
and/ or the Consultant liable to the Procuring Entity for all costs and damages
arising from such misdemeanors.
2) On behalf of the Procuring Entity: Unless otherwise stipulated in the contract, the
Contract Manager signing the contract shall administer the contract and sign
communications on behalf of the Procuring Entity. Paying Authorities mentioned in
the contract shall also administer respective functions during Contract Execution.
4.3. Address of the parties for sending communications by the other party.
For all purposes of the contract, including arbitration, thereunder, the address of parties
to which the other party shall address all communications and notices shall be:
1) The Consultant's address as mentioned in the contract, unless the Consultant has
notified change by a separate communication containing no other topic to the
Procuring Entity. The Consultant shall be solely responsible for the consequence of
an omission to notify a change of address in the manner aforesaid, and
2) The Procuring Entity's address shall be the one mentioned in the contract. The
Consultant shall also send additional copies to officers of the Procuring Entity
presently dealing with the contract.
3) In case of communications from the Consultant, copies of communications shall be
marked to the Contract Manager and the Procuring Entity’s officer signing the
contract and as relevant to the Paying Authorities mentioned in the contract. Unless
specified before the contract's start, the Procuring Entity and the Consultant shall
notify each other if additional copies of communications are to be addressed to
additional addresses.
Consultant’s Obligations and restrictions on its Rights
5.1. Changes in Constitution/ financial stakes/ responsibilities Business and Contract’s
the Consultant must proactively keep the Procuring Entity informed of any changes in
its constitution/ financial stakes/ responsibilities during the execution of the contract.
1) Where the Consultant is a partnership firm, the following restrictions shall apply to
changes in the constitution during the execution of the contract:
50a) A new partner shall not be introduced in the firm except with the previous
consent in writing of the Procuring Entity, which shall be granted only upon
execution of a written undertaking by the new partner to perform the contract
and accept all liabilities incurred by the firm under the contract before the
date of such undertaking.
b) On the death or retirement of any partner of the Consultant firm before the
complete performance of the contract, the Procuring Entity may, at his
option, terminate the contract for default as per the contract and/ or avail
any or all remedies thereunder.
c) If the contract is not terminated as provided in Sub-clause (b) above,
notwithstanding the retirement of a partner from the firm, that partner shall
continue to be liable under the contract for acts of the firm until a copy of
the public notice given by him under Section 32 of the Partnership Act, has
been sent by him to the Procuring Entity in writing or electronically.
5.2. Obligation to Maintain Eligibility and Qualifications
The contract has been awarded to the Consultant based on evaluation and scoring
criteria stipulated in the RFP process based on eligibility and qualifications criteria
stipulated therein. The Consultant is contractually bound to maintain compliance with all
such criteria during the execution of the contract. Any change which would vitiate the
basis on which the Consultant was shortlisted or awarded the contract should be pro-
actively brought to the notice of the Procuring Entity within 7 days of it coming to the
Consultant’s knowledge.
5.3. Restriction on Potential Conflict of Interests
1) Neither the Consultant nor its Sub-consultants nor the Personnel shall engage, either
directly or indirectly, in any of the following activities:
a) During this Contract's term, any business or professional activities in India
that would conflict with the activities assigned to them.
b) After this Contract's termination, such other activities as may be stipulated in
the contract.
2) Furthermore, if the Consultant, as part of the Services, has the responsibility of
advising the Procuring Entity on the procurement of goods, works or services, the
Consultant shall at all times exercise such responsibility in the best interest of the
Procuring Entity. Any discounts or commissions obtained by the Consultant in the
exercise of such procurement responsibility shall be for the account of the Procuring
Entity.
3) During the term of this Contract and after its termination, the Consultant and its
affiliates, as well as any Sub-consultant and any of its affiliates, shall be disqualified
from providing goods, works, or Services (other than the subject Service of this
Contract and any continuation thereof) for any project resulting from or closely
related to the subject Services of this Contract.4) The payment of the Consultant according to (GCC Clause 10.5) shall constitute the
Consultant’s only payment in connection with this Contract. The Consultant shall not
accept for its benefit any trade commission, discount, or similar payment in
connection with activities under this Contract or the discharge of its obligations
hereunder. The Consultant shall use its best efforts to ensure that any Sub-
consultants and the Experts and agents of either shall not receive any additional
payment.
5) The Consultant has an obligation and shall ensure that its Experts and Sub-
consultants shall have an obligation to disclose any actual or potential conflict that
impacts their capacity to serve the best interest of the Procuring Entity, or that may
reasonably be perceived as having this effect. Failure to disclose said situations may
lead to the disqualification of the Consultant and/ or the termination of the Contract.
5.4. Consequences of breach by Constituents of a Consultant
Should the Consultant or any of its partners, its Sub-consultants, any of its members in
case of JV/C, or their Personnel commit a default or breach of GCC-clause 5.1 to 5.7,
the Consultant (in case of JV, by the Lead Member, or in the case of the Lead Member
being the defaulter, by the member nominated as Lead Member of the remaining JV/C)
shall remedy such breaches within 21 days, keeping the Procuring Entity informed.
Procuring Entity may call upon the Lead Member to assign the work of the defaulting
member to any other equally competent party acceptable to the Procuring Entity.
However, at its discretion, the Procuring Entity shall be entitled, and it shall be lawful on
his part, to treat it as a breach of contract and avail any or all remedies thereunder.
The decision of the Procuring Entity as to any matter or thing concerning or arising out
of GCC-clause 5.1 to 5.7 or on any question whether the Consultant or any partner of
the Consultant firm has committed a default or breach of any of the conditions shall be
final and binding on the Consultant.
5.5. Assignment and Sub-contracting- Deleted
1) the Consultant shall not, save with the previous consent in writing of the Procuring
Entity, sublet, transfer, or assign the contract or any part thereof or interest therein
or benefit or advantage thereof in any manner whatsoever to any Sub-consultant.
2) The Consultant shall notify the Procuring Entity in writing of all such Sub-consultants,
if not already stipulated in the contract, in its original Proposal or later. Such
notification shall not relieve the Consultant from any of its liability or obligation
under the terms and conditions of the contract. Sub-consultants must comply with
and should not circumvent the Consultant’s compliance with its obligations under
GCC-clause 5.1 to 5.7.
3) If the Consultant sublets or assigns this Contract or any part thereof without such
permission, the Procuring Entity shall be entitled, and it shall be lawful on his part,
to treat it as a breach of contract and avail any or all remedies thereunder.
525.6. Obligation to Indemnify Procuring Entity
5.6.1 For breach of IPR Rights
1) the Consultant shall indemnify and hold harmless, free of costs, the Procuring Entity
and its employees and officers from and against all suits, actions or administrative
proceedings, claims, demands, losses, damages, costs, and expenses of any nature,
including attorney’s fees and expenses, which may arise in respect of the Services
provided by the Consultant under this Contract, as a result of any infringement or
alleged infringement of any patent, utility model, registered design, copyright, or
other Intellectual Proprietary Rights (IPR) or trademarks, registered or otherwise
existing on the date of the contract arising out of or in connection with:
a) Any design, data, drawing, specification, or other documents or Services
provided or designed by the Consultant for or on behalf of the Procuring
Entity.
b) The sale by the Procuring Entity in any country of the services/ products
produced by the Services delivered by Consultant, and
c) The delivery of the Services by the Consultant or the use of the Services at
the Procuring Entity’s Site
2) Such indemnity shall not cover any use of the Services or any part thereof other than
for the purpose indicated by or to be reasonably inferred from the contract, neither
any infringement resulting from the use of the Services or any part thereof, or any
service/ products produced thereby in association or combination with any other
service, equipment, plant, or materials not delivered by the Consultant.
3) If any proceedings are brought, or any claim is made against the Procuring Entity
arising out of the matters referred above, the Procuring Entity shall promptly notify
the Consultant. At its own expense and in the Procuring Entity’s name, the Consultant
may conduct such proceedings and negotiations to settle any such proceedings or
claim, keeping the Procuring Entity informed.
4) If the Consultant fails to notify the Procuring Entity within twenty-eight (28) days after
receiving such notice that it intends to conduct any such proceedings or claim, then
the Procuring Entity shall be free to conduct the same on its behalf at the risk and
cost to the Consultant.
5) At the Consultant’s request, the Procuring Entity shall afford all available assistance to
the Consultant in conducting such proceedings or claims and shall be reimbursed by
the Consultant for all reasonable expenses.
5.6.2 For Losses and Damages Caused by Consultant
1) the Consultant shall indemnify and keep harmless the Procuring Entity, from and
against, all actions, suit proceedings, losses, costs, damages, charges, claims, and
demands of every nature and description brought or recovered against the
Procuring Entity because of any act or omission or default or negligence or trespass
of the Consultant, his agents, or employees despite all reasonable and proper
precautions may have been taken, during the execution of the Services. TheConsultant shall make good at his own expense all resulting losses and/ or damages
to:
the Services themselves or
any other property of the Procuring Entity or
the lives, persons, or property of others
2) In case the Procuring Entity is called upon to make good such costs, loss, or damages
or to pay any compensation, including that payable under the provisions of the
Workmen's Compensation Act or any statutory amendments thereof, the amount of
any costs or charges including costs and charges in connection with legal
proceedings, which the Procuring Entity may incur about it, shall be charged to the
Consultant. All sums payable by way of compensation under any of these conditions
shall be considered reasonable compensation to be applied to the actual loss or
damage sustained and whether or not any damage shall have been sustained.
3) The Procuring Entity shall have the power and right to pay or to defend or
compromise any claim of threatened legal proceedings, or in anticipation of legal
proceedings being instituted consequent on the action or default of the Consultant,
to take such steps as may be considered necessary or desirable to ward off or
mitigate the effect of such proceedings, charging to Consultant, as aforesaid, any
sum or sums of money which may be paid and any expenses whether for
reinstatement or otherwise which may be incurred and the propriety of any such
payment, defence or compromise, and the incurring of any such expenses shall not
be called in question by the Consultant.
5.7. Confidentiality, Secrecy and Property and IPR Rights
5.7.1 Property Rights
1) Physical assets, e.g., Equipment, vehicles and materials made available to the
Consultant by the Procuring Entity or purchased by the Consultant wholly or partly
with funds provided by the Procuring Entity, shall be the property of the Procuring
Entity and shall be marked accordingly. Upon termination or expiration of this
Contract, the Consultant shall make an inventory of such equipment, vehicles, and
materials available to the Procuring Entity and dispose of such equipment, vehicles,
and materials in accordance with the Procuring Entity’s instructions. While in
possession of such equipment, vehicles and materials, the Consultant, unless
otherwise instructed by the Procuring Entity in writing, shall insure them at the
expense of the Procuring Entity in an amount equal to their total replacement value.
2) Intangible assets, e.g., license agreements, Software Packages, and memberships
for purposes of performance of this contract provided by the Procuring Entity or
purchased by the Consultant wholly or partly with funds provided by the Procuring
Entity, shall be the property of the Procuring Entity and shall be registered
accordingly., These shall be obtained in the name of the Procuring entity after
obtaining the Procuring Entity’s prior written approval. The Procuring entity shall have
an encumbered right to use such assets, even after the termination of the
54Contract. Any restrictions about the future use of these documents and software shall
be specified in the Contract.
5.7.2 IPR Rights
All deliverables, outputs, plans, drawings, specifications, designs, reports, and other
documents and software submitted by the Consultant under this Contract shall become
and remain the property of the Procuring Entity and shall be subject to laws of copyright
and must not be shared with third parties or reproduced, whether in whole or part,
without the Procuring Entity’s prior written consent. The Consultant shall, not later than
upon termination or expiration of this Contract, deliver all such documents and software
to the Procuring Entity, together with a detailed inventory thereof. The Consultant may
retain a copy of such documents and software but shall not use it for commercial
purposes.
5.7.3 Confidentiality
All documents, drawings, samples, data, associated correspondence or other
information furnished by or on behalf of the Procuring Entity to the Consultant in
connection with the contract, whether such information has been furnished before,
during or following completion or termination of the contract, are confidential and shall
remain the property of the Procuring Entity and shall, without the prior written consent
of Procuring Entity neither be divulged by the Consultant to any third party, nor be used
by him for any purpose other than the design, procurement, or other services and
activities required for the performance of this Contract. If advised by the Procuring Entity,
all copies of all such information in original shall be returned on completion of the
Consultant’s performance and obligations under this contract.
5.7.4 Secrecy
If the contract declares the subject matter of this Contract as coming under the Official
Secrets Act, 1923 or if the contract is marked as “Secret”, the Consultant shall take all
reasonable steps necessary to ensure that all persons employed in any connection with
the contract, have acknowledged their responsibilities and penalties for violations under
the Official Secrets Act and any regulations framed thereunder.
5.7.5 Restrictions on the Use of Information
1) Without the Procuring Entity’s prior written consent, the Consultant shall not use the
information mentioned in the sub-clauses above except for performing this contract.
2) The Consultant shall treat and mark all information as confidential (or Secret – as
the case may) and shall not, without the written consent of the Procuring Entity,
divulge to any person other than the person(s) employed by the Consultant in the
performance of the contract. Further, any such disclosure to any such employed
person shall be made in confidence and only so far as necessary for such
performance for this contract.
3) Notwithstanding the above, the Consultant may furnish to its holding company or
its Sub-consultant(s) such documents, data, and other information it receives fromthe Procuring Entity to the extent required for performing the contract. In this event,
the Consultant shall obtain from such holding company/ Sub-consultant(s) an
undertaking of confidentiality (or secrecy – as the case may be) similar to that imposed
on the Consultant under the above clauses.
4) The obligation of the Consultant under sub-clauses above, however, shall not apply
to information that:
a) the Consultant needs to share with the institution(s) participating in the
financing of the contract;
b) now or hereafter is or enters the public domain through no fault of
Consultant;
c) can be proven to have been possessed by the Consultant at the time of
disclosure and which was not previously obtained, directly or indirectly, from
the Procuring Entity; or
d) otherwise lawfully becomes available to the Consultant from a third party
with no obligation of confidentiality.
5) The above provisions shall not in any way modify any undertaking of confidentiality
(or Secrecy – as the case may be) given by the Consultant before the contract date
in respect of the contract, the RFP Document, or any part thereof.
6) The provisions of this clause shall survive completion or termination for whatever
reason of the contract.
5.7.6 Protection and Security of Personal Data
1) Where the Consultant is processing Personal Data for the Procuring Entity (as part
of Services), the Consultant shall:
a) Process the Personal Data only as per instructions from Procuring Entity
(which may be specific instructions or instructions of a general nature) as set
out in this Contract or as otherwise notified by Procuring Entity;
b) Comply with all applicable laws;
c) Process the Personal Data only to the extent and in such manner as is
necessary for the discharge of the Consultant’s obligations under this
Contract or as is required by Law or any Regulatory Body;
d) Implement appropriate technical and organisational measures to protect
Personal Data against unauthorized or unlawful Processing and accidental
loss, destruction, damage, alteration, or disclosure. These measures shall be
appropriate to the harm which might result from any unauthorized or
unlawful Processing, accidental loss, destruction, or damage to the Personal
Data and having regard to the nature of the Personal Data which is to be
protected;
e) Take reasonable steps to ensure the reliability of its staff and agents who
may have access to the Personal Data;
f) Obtain prior written consent from the Authority to transfer the Personal Data
to any Sub-consultant for the provision of the Services;
56g) Not cause or permit the Personal Data to be transferred, stored, accessed,
viewed, or processed outside of India without the prior written consent of the
Procuring Entity.
h) Ensure that all staff and agents required to access the Personal Data are
informed of the confidential nature of the Personal Data and comply with the
obligations set out in this clause.
i) Ensure that none of the staff and agents publishes or disclose any personal
data to any third parties unless directed in writing to do so by the Procuring
Entity.
j) Not disclose Personal Data to any third parties in any circumstances other
than with the written consent of the Procuring Entity or compliance with a
legal obligation imposed upon the Procuring Entity;
2) Notify the Procuring Entity (within five Working Days) if it receives the;
a) a request from an employee of Procuring Entity to have access to his or other
employees’ Personal Data; or
b) a complaint or request relating to the Procuring Entity’s obligations under the
law;
3) The provision of this clause shall apply during the contract period and indefinitely
after its expiry.
5.8. Performance Bond/ Security
1) Within twenty-one days (or any other period mentioned in RFP Document or
Contract) after the issue of the Letter of Award (LoA or the contract, if LoA is skipped)
by the Procuring Entity, the Consultant shall furnish to the Procuring Entity
performance security, valid up to sixty days (or any other period mentioned in RFP
Document or Contract) after the date of completion of all contractual obligations by
the Consultant.
2) The amount of Performance security as quoted by bidder in his financial proposal in
Indian Rupees or the currency of the contract and shall be in one of the following
forms:
a) Unless otherwise stipulated in the RFP Document or the Contract, Insurance
Surety Bonds, Account Payee Demand Draft, Fixed Deposit Receipt from any
commercial bank in India, or online payment in an acceptable form
safeguarding the Procuring Entity’s interest, or
b) Bank Guarantee (including an e-Bank Guarantee) issued by a commercial
bank in India, in the prescribed form provided in Appendix E-1 to Format 1:
Contract Form.
3) If the Consultant, having been called upon by the Procuring Entity to furnish
Performance Security, fails to do so within the specified period, it shall be lawful for
the Procuring Entity at its discretion to annul the award and forfeit the EMD (or
enforce Bid Securing Declaration, if that was submitted in lieu of Bid Security),besides taking any other administrative punitive action like ‘Removal from List of
Registered Suppliers’ etc.
4) If the Consultant fails to maintain the quoted Performance Security during the
Contract's currency, it shall be lawful for the Procuring Entity at its discretion.
(a) treat it as a breach of contract and avail any or all contractual remedies
provided for breaches/ default, including termination of the Contract for
Default, or
(b) without terminating the Contract, recover from the Consultant the amount of
such security deposit by deducting the amount from the pending bills of the
Consultant under the contract or any other contract with the Procuring Entity or
the Government or any person contracting throught he Procuring Organisation
or otherwise, howsoever as per GCC-clause 10.4.
5) If a contract is amended, the Consultant shall furnish amended Performance Security
with revised value and validity within twenty-one days of the issue of such an
amendment.
6) The Procuring Entity shall be entitled, and it shall be lawful on his part,
(a) to deduct from the performance securities or to forfeit the said security in whole
or in part in the event of:
i) Any default, failure, or neglect on the part of the Consultant in the
fulfilment or performance in all respect of this contract or any other
contract with the Procuring Organisation or any part thereof
ii) for any loss or damage recoverable from the Consultant which the
Procuring Entity may suffer or be put to for reasons of or due to the above
defaults/ failures/ neglect
(b) and in either of the events aforesaid to call upon the Consultant to maintain the
said performance security at its original limit by making further deposits,
provided further that the Procuring Entity shall be entitled, and it shall be lawful
on his part, to recover any such claim from any sum then due or which at any
time after that may become due to the Consultant for similar reasons.
7) Subject to the sub-clause above, the Procuring Entity shall release the performance
security without any interest to the Consultant on completing all contractual
obligations. Alternatively, upon the Consultant submitting a suitable separate Defect
Liability Security for the duration of Defect Liability obligations, the original
Performance Guarantee Security shall be released mutatis mutandis.
8) No claim shall lie against the Procuring Entity regarding interest on cash deposits,
Government Securities, or depreciation thereof.
5.9. Permits, Approvals and Licenses
Whenever the Services and incidental Goods/ Works delivery requires the Consultant
to obtain permits, approvals, and licenses from local public authorities or any third
58party, it shall be the Consultant's sole responsibility to obtain these and keep them
current and valid. Such requirements may include but not be restricted to licences or
environmental clearance if required. If requested by the Consultant, the Procuring Entity
shall make its best effort to assist the Consultant in complying with such requirements
in a timely and expeditious manner without diluting the Consultant’s responsibility in
this regard.
5.10. Insurances
The Consultant (s) shall take out and maintain, and shall cause any Sub-consultants tot ake out
and maintain, at its (or the Sub-consultants’, as the case may be) own cost but on terms and
conditions approved by the Procuring Entity, insurance against the risks,a nd for the coverage,
as stipulated in the contract or any applicable law including Labour Codes; and at the
Procuring Entity’s request, shall provide evidence to the Procuring Entity showing that such
insurance has been taken out and maintained andt hat the current premiums have been paid.
The Consultant shall ensure that such insurances are in place before commencing the Services
as stated in GCC clause 9.2.A lterations to the terms of insurance shall not be made without
the approval of the Contract Manager. The risks and the coverageof insurance shall be as
follows
(a) Third Party motor vehicle liability insurance as required under
Motor Vehicles Act,1988 in respect of motor vehicles operated
in India by the Consultants or their Personnel or any Sub-
consultants or their Personnel for the period of consultancy.
(b) Third Party liability insurance with a minimum coverage, of Rs.
1.0 million for the period of consultancy.
(c) Professional liability insurance as per 3.4 (a) (ii) of SC of the
consultancy, with a minimum coverage equal to estimated
remuneration and reimbursable.
(d) Employer's liability and workers' compensation insurance in
respect of the Personnel of the Consultants and of any Sub-
consultant, in accordance with the relevant provisions of the
Applicable Law, as well as, with respect to such Personnel, any
such life, health, accident, travel or other insurance as may be
appropriate; and
(e) Insurance against loss of or damage to(i) equipment purchased
in whole or in part with funds provided under this Contract, (ii)
the Consultants' property used in the performance of the
Services, and(iii)any documents prepared by the Consultants in
the performance of the Services.
5.11. Accounting, Inspection and Auditing
The Consultant shall keep and make all reasonable efforts to cause its Sub-consultants
to keep accurate and systematic accounts and records in respect of the Services and in
such form and detail as shall identify relevant time changes and costs and as peraccounting principles prescribed in India.
5.12. Book Examination Clause
If explicitly invoked in the contract, the Procuring Entity reserves the right for 'Book
Examination' as follows:
1) The Consultant shall, whenever called upon and required to produce or cause
to be produced, for examination by any Government Officer duly authorised on
that behalf, any cost or other book of account, voucher, receipt, letter,
memorandum, paper or writing or any copy of or extract from any such document.
The Consultant shall also furnish information relating to the execution of this
contract or relevant for verifying or ascertaining the cost of execution of this
contract to such Government Officer in such manner as may be required. This
Government Officer’s decision on the relevancy of any document or information of
return shall be final and binding on the parties. The obligation imposed by this
clause is without prejudice to the Consultant's obligations under any other statute,
rules or orders which shall be concurrently binding on the Consultant.
2) The Consultant shall, if the authorised Government Officer so requires (whether
before or after the prices have been finally fixed), afford facilities to the
Government Officer concerned to visit the Consultant's premises to examine the
processes of delivery of Services and estimate or ascertain the cost of performance
of Contract. The authorised Government Officer shall have the power, mutatis
mutandis, to examine all the relevant books of the Consultant’s Sub-consultant or
any subsidiary or allied firm or company, If any portion of the contract is entrusted
or carried out by such entities.
3) If, on such examination, it is established that the contracted price is more than
the actual cost-plus reasonable profit margin, the Procuring Entity shall have the
right to reduce the price and determine the amount to a reasonable level.
4) The Consultant or its agency is bound to allow examination of its books within
60 days from the date the notice is received by the Consultant or its agencies
calling for the production of documents under sub-clause (1) above. In the event
of the Consultant's or his agency's failure to do so, the contract price would be
reduced and determined according to the best judgment of the Procuring Entity,
which would be final and binding on the Consultant and his agencies.
5.13 Legal Compliance
The Consultant shall perform the Services in accordance with the Contract and the
Applicable Law and shall take all practicable steps to ensure that any of its Experts
and Sub-consultants comply with the Applicable Law.
5.14 Custody and Return of the Procuring Entity’s Assets loaned to Consultant
1) The contractors shall sign accountable receipts for all documents and materials or
other assets/ properties made over to them by the Contract Manager on behalf of
the Procuring Entity. All such assets shall be deemed in good condition when
received by the Consultant unless he has notified the Procuring Entity to the contrary
within twenty-four hours of receipt. Otherwise, he shall be deemed to have waived
the right to do so at any subsequent stage.
602) These assets shall remain the property of the Procuring Entity, and the Consultant
shall take all reasonable care of all such assets. The Consultant shall be responsible
for all damage or loss from whatever cause while assets are possessed or controlled
by the Consultant, staff, workmen, or agents.
3) Where the Consultant insures such assets against loss or fire at the request of the
Procuring Entity, such insurance shall be deemed to be by way of additional
precaution and shall not prejudice the Consultant's liability as aforesaid.
4) The Consultant shall return all such assets in good order and repair, reasonable
wear and tear excepted, before the completion/ closure/ termination of the contract
and shall be responsible for any failure to account for the same or any damage
done to that as assessed by the Procuring Entity whose decision shall be final and
binding.
Procuring Entity’s Obligations
6.1. Assistance by the Procuring Entity
Unless otherwise specified in the contract, the Client shall use its best
efforts to:
• provide the Consultants, Sub-consultants and Personnel with work permits and such
other documents as shall be necessary to enable the Consultants, Sub- consultants
or Personnel to perform the Services;
• assist for the Personnel and, if appropriate, their eligible dependents to be provided
promptly with all necessary entry and exit visas, residence permits, exchange
permits and any other documents required for their stay in Government's country;
• Facilitate prompt clearance through customs of any property required for the
Services and of the personal effects of the Personnel and their -eligible dependents;
• Issue to officials, agents and representatives of the Government all such
instructions as may be necessary or appropriate for the prompt and effective
implementation of the Services;
• assist the Consultants and the Personnel and any Sub-consultants and or Associates
employed by the Consultants for the Services from any requirement to register or
obtain any permit to practice their profession or to establish themselves either
individually or as a corporate entity according to the Applicable Law;
• grant to the Consultants, any Sub-consultants and or Associates and the Personnel
of either of them the privilege, pursuant to the Applicable Law, of bringing into
Government's country reasonable amounts of foreign currency for the purposes of
the Services or for the personal use of the Personnel and their dependents and of
withdrawing any such amounts as may be earned therein by the Personnel in the
execution of the Services: and• Provide to the Consultants, Sub-consultants and or Associates and Personnel any
such other assistance as may be specified in the SC.
2) Issue instructions and information to its officials, agents, and stakeholders for
prompt and effective implementation of the Services.
3) Access to Project Site: The Procuring Entity warrants that the Consultant shall have,
free of charge, unimpeded access to the project site if such access is required for the
performance of the Services.
6.2. Facilities to be provided by the Procuring Entity
1) The Procuring Entity shall make available to the Consultant and the Experts, for the
performance of the contract, free of any charge (unless otherwise stated therein),
the services, facilities, and property described in the ‘Terms of Reference’ (Appendix A)
as per terms and conditions and against appropriate safeguards (including
Insurances, Bank Guarantee, Indemnity Bonds, Retention Money etc.) specified
therein. The Consultant shall use such property for the execution of the contract and
no other purpose whatsoever.
2) In case such services, facilities and property shall not be made available to the
Consultant as and when specified in Appendix A, the Parties shall agree on (i) any
time extension that it may be appropriate to grant to the Consultant for the
performance of the Services, (ii) how the Consultant shall procure any such services,
facilities and property from other sources, and (iii) the additional payments, if any,
to be made to the Consultant as a result thereof according to GCC clause 10.1.1.
6.3. Counterpart Personnel
1) The Procuring Entity shall make professional and support counterpart personnel
available to the Consultant, as specified in Appendix A.
2) If counterpart personnel are not provided by the Procuring Entity to the Consultant
as and when specified in Appendix A, the Procuring Entity and the Consultant shall
agree on (i) how the affected part of the Services shall be carried out, and (ii) the
additional payments, if any, to be made by the Procuring Entity to the Consultant as
a result thereof.
3) Professional and support counterpart personnel, excluding Procuring Entity’s
Contract Management and liaison personnel, shall work under the exclusive
direction of the Consultant. If any member of the counterpart personnel fails to
perform any work assigned to such member by the Consultant that is adequately
consistent with the position occupied by such member, the Consultant may request
the replacement of such member, and the Procuring Entity shall not unreasonably
refuse to act upon such request.
6.4. Payment Obligation
Considering the Services performed by the Consultant under this Contract, the
Procuring Entity shall pay the Consultant for the deliverables specified in Appendix A
and in such manner as is provided in the Contract.
62Scope of Services and Performance Standards
7.1. Scope of Services
1) Services: This contract is for the performance/ delivery of Services of the description,
scope/ quantum outlined in Appendix A: ‘Terms of Reference’ during the contract
period specified therein.
2) Incidental Works/ Goods/ Other Services: If so stipulated, the Consultant
shall be required to perform/ deliver specified incidental Works/ Goods/ other
Services as an integral part of the Services in the contract.
3) Location: The Services shall be performed at such locations as are specified in
Appendix A and, where the location of a particular task is not so specified, at such
locations, whether in the Procuring Entity’s country or elsewhere, as the Procuring
Entity may approve.
4) Reporting Requirements: The Consultant shall deliver to the Procuring Entity
the reports, deliverables, outputs, and documents specified in Appendix A: ‘Terms
of Reference’, in the form, in the numbers and within the periods outlined in the
said Appendix, besides progress reports as per GCC Clause 9.3.
5) Standard of Performance:
a) The Consultant shall perform and carry out the Services with all due diligence,
efficiency, and economy, in accordance with generally accepted professional
standards and practices, observe sound management practices, and employ
appropriate technology and safe and effective equipment, machinery,
materials and methods.
b) Unless otherwise specified, the performance standards and quality of the
Services shall conform to the Terms of Reference as stipulated in the contract or
as per best standards in the market, where not so specified.
c) Defects in Services: The Procuring Entity shall promptly notify the Consultant
of any identified defects, lapses/deficiencies in services requesting the correction
of the notified defect within a reasonable time. If the Consultant has not
corrected notified defect within the time stipulated in the Procuring Entity’s notice,
the Procuring Entity may suspend payments as per GCC clause 10.6 and terminate
the agreement as per GCC clause 12.1 of contract agreement.
6) Consultants' Actions Requiring Client's Prior Approval;- The Consultants
shall obtain the Client's prior approval in writing before taking any of the
following actions:
(a) appointing such members of the Personnel as are listed in Appendix ‘C’
("Consultants' Sub-consultants' Key Personnel") merely by title but not by
name;
(b) entering into a subcontract for the performance of any part of the Services,
it being understood (i) that the selection of the Sub-Consultant and the terms
and conditions of the subcontract shall have been approved in writing by the
63Client prior to the execution of the subcontract, and (ii) that the Consultants
shall remain fully liable for the performance of the Services by the Sub-
Consultant and its Personnel pursuant to this Contract; and
(c) taking any action under a civil works contract designating the Consultants as
"Authority’s Engineer", for which action, pursuant to such civil works
contract, the written approval of the Client as "Employer" is required".
7.2. Eligible Services
Unless otherwise stipulated in the Contract, the country of origin of ‘Services’ and
related ‘Goods’ under the contract shall have their origin in India or other countries (if
specified in the Contract). It must conform to the declaration made by the Consultant
during regarding Central Government policies restricting the participation of entities
from i) Certain countries sharing land borders with India and ii) Countries that restrict the
participation of Bidders from India on a reciprocal basis. They should ensure that they
continue to be free from such restrictions.
Deployment of Resources
8.1. Site and Assets thereon
8.1.1 Site of Service Delivery
1) The site for Service delivery shall be the lands, spaces, and other places on, under,
in or through which the Services are to be carried out and any other lands or places
provided by the Procuring Entity for the contract.
2) No land or building or any other asset belonging to or in possession of the Procuring
Entity shall be occupied/ used by the Consultant without the permission of the
Procuring Entity. The Consultant shall not use or allow the site to be used for any
purposes other than executing or concerning the execution of the services.
3) Prohibition of Smoking and Intoxicants: The Consultant shall exercise
influence and authority to the utmost extent to secure strict compliance by his staff
or any labour employed through Sub-consultants or petty contractors with all the rules
and regulations stipulated by the Procuring Entity relating to the access to the project site,
including but not limited to
a) Prohibition of Smoking in ‘No Smoking Zone’ and in Public Places
b) Prohibition of the use of any intoxicating substances including, but not limited
to, intoxicating beverages during the service period or on-site or near the site
or in any of the facilities, sites, buildings, encampments, or tenements
owned, occupied by or within the control of the Consultant or any of his
employees.
c) Safety practices relating to Procuring Entity’s staff, Public and third parties
d) Maintenance of peace and business-like ambience
8.1.2 Clearance of Site on Completion
1) On completion of the services, the Consultant shall hand over the whole project site
to the procuring Entity on ‘as it was’ basis. No final payment in settlement of the
64accounts for the Services shall be paid to the Consultant till, in addition to any other
condition necessary for final payment, site clearance shall have been affected by
him.
2) In the event of failure on the part of the Consultant to comply with this provision
within 7 days after receiving notice for clearance of Procuring Entity’s site and lands, the
Contract Manager shall cause them to be removed in such a way as deemed fit and
convenient and cost as increased by supervision and other incidental charges shall
be recovered from the Consultant. The Procuring Entity shall not be held liable for
any loss or damage to the Consultant's property as may be on the site and due to
such removal.
8.2. Key and Non-key Personnel
8.2.1 General Requirements
1) Restrictions on the Employment of Retired Staff or Officers or Managers of
Procuring Entity within One Year of their Retirement: the Consultant shall
not himself be a retired Government employee of Gazetted rank or engage any
employee or associate who is a retired Government employee of Gazetted rank, if
such persons have not completed one year (or any other period prescribed by the
relevant authority) from the date of retirement, in connection with this Contract in any
manner whatsoever without obtaining prior permission of the relevant authority. If
the Consultant is found to have contravened this provision, it shall constitute a
breach of contract, and Procuring Entity shall be entitled to terminate the contract
and/ or avail any or all the remedies thereunder.
2) Team Lead: The Consultant, when he is not personally present on the workplace
site, shall nominate a Team Lead during working hours, which shall, on receiving
reasonable notice, present himself to the Contract Manager. Orders given by the
Contract Manager or his representative to the Team Lead shall be deemed to have
the same force as if given to the Consultant.
3) The Consultant shall employ and provide qualified and experienced Key and Non-
key Experts and Sub-consultants as required to carry out the Services.
4) All key personnel and sub professional staff of the Authority Engineer shall use the Aadhaar
based biometric attendance! Geotagged selfie-based attendance system for marking their
daily attendance. Aadhaar based Biometric attendance! Gee-tagged selfie-based
attendance shall be marked at least once a day and anytime during the day. 1 Aadhaar
based biometric attendance! Gee-tagged selfie-based attendance system shall be installed
by the Authority Engineer its own cost at the site office in order to facilitate the attendance
marking. More systems can be installed near the project highway upto a maximum of 1
system per 50 km in order to encourage frequent visits of project highway by key
personnel and sub professional staff. A copy of monthly Aadhaar based biometric
attendance/ Geo-tagged selfie-based attendance shall be attached with Monthly Status
Report. Proper justification shall be provided for cases of absence of key personnel/ sub
professional staff which do not have prior approval from Project Director of concerned
stretch. Authority Engineer have to provide a certificate that all key personnel as envisaged
in the Contract Agreement has been actually deployed iii the project.
655) Authority Engineer will intimate concerned Project Director/Project Incharge immediately
after establishing its site office regarding installation of Aadhaar based Biometric
attendance/ Geotagged selfie-based attendance system and complete address of its site
office
6) Fake CV:- If any case of fake/incorrect/inflated CV is found, it shall be dealt with
very severely and would result in all possible penal action including blacklisting from
future projects of <Agency>. This would also apply even when the consulting firm is
not successful in getting the assignment. In case CV of a person is turned out to be
fake/incorrect/inflated during the assignment, the consultancy firms will have to
refund the salary and perks drawn including interest @12% per annumin respect of
the person apart from other consequences. In addition to above, 10% of the salary
and perks to be refunded shall be recovered from the Firm as penalty.
8.2.2 Key Personnel
1) The titles, job descriptions, minimum qualifications, and estimated periods of the
Consultant’s Key Personnel engagement in carrying out the Services are described
in Appendix B to the Contract.
2) The Key Experts shall not be entitled to be paid for overtime nor to take paid sick
leave or vacation leave except as specified in Appendix B, and the Consultant’s
remuneration shall be deemed to cover these items.
3) Working hours and holidays for Experts are outlined in Appendix B. Foreign Key
Experts carrying out Services in India shall be deemed to have commenced or
finished work in respect of the Services several days before their arrival in or after
their departure from India, as is specified in Appendix B.
4) Any leave-taking by Key Experts shall be subject to the prior approval by the
Consultant, who shall ensure that absence for leave purposes shall not delay the
progress and or impact adequate supervision of the Services. If Key Experts are not
deployed for significant periods, affecting the progress and quality of the
assignment, payments may be suspended as per clause 10.6 below.
5) Substitution of Key Experts:
a) Unless the Procuring Entity may otherwise agree in writing, no changes shall be
made in the Key Experts.
b) In case notice to commence services pursuant to Clause 2.1 of this Contract is not
ordered by Client within 120 days of signing of contract the key personnel can excuse
themselves on valid grounds, e.g., selection on some other assignment, health problem
developed after signing of contract, etc. In such a case no penalty shall be levied on
the Firm or on the person concerned. The firm shall however be asked to give a
replacement by an equal or better scoring person, whenever mobilization is ordered.
c) In case notice to commence services is given within 120 days of signing of contract
the, the Authority expects all the Key Personnel specified in the Proposal to be available
during implementation of the Agreement. The Authority will not consider any
66substitution of Key Personnel except under compelling circumstances beyond the
control of the Consultant and the concerned Key Personnel. Such substitution shall be
limited to not more than three Key Personnel subject to equally or better qualified and
experienced personnel being provided to the satisfaction of the Authority. Replacement
of the Team Leader will not normally be considered and may lead to disqualification of
the Applicant or termination of the Agreement. Replacement of one Key Personnel
shall be permitted subject to reduction of remuneration equal to 5 % (five per cent)
of the total remuneration specified for the Key Personnel who is proposed to be
replaced. In case of second replacement the reduction in remuneration shall be equal
to 10% (ten per cent) and for third and subsequent replacement, such reduction shall
be equal to 15% (fifteen per cent). The maximum age limit of replaced key personnel
shall be 65 years as on the date of submission of proposal for such replacement. The
Consultant shall make all endeavors to ensure that replacement of a Key Personnel is
approved before the concerned Key Personnel leaves the consultancy assignment, in
any case the Consultant shall submit replacement acceptable to Client not more than
3 weeks after the Key Personnel leaves the consultancy assignment, failing which Client
may terminate the Contract in pursuance to Clause 12.1 of GC. The personnel so
replaced shall be debarred from future projects for 2 years. For avoidance of doubt it
is clarified that for one position replace shall be allowed only once during currency of
contract. Repeated replacement for one key position shall not be allowed except in
case of death.
d) In case, person permanently employed with the firm is to be replaced, technical score
of both the CVs shall be compared excluding the marks given for employment with
firm. Replacement would be allowed when the Technical Score (excluding the marks
given for employment with firm) of the new key person is equal or better than the
existing key person's Technical Score excluding marks assigned for permanent
employment with the firm. However, the remuneration of such replacement shall be
reduced on proportionate basis in case the overall score of the replacement person is
less than the overall score of original person.
e) Replacement after original contract period is over: - There shall be no
limit on the replacements and no reduction in remunerations shall be made.
The replacement shall however be of equal or better score.
f) If the Employer (i) finds that any of the Personnel has committed serious
misconduct or has been charged with having committed a criminal action or (ii)
has reasonable ground to be dissatisfied with the performance of any of the
Personnel, then the consultant shall, at the Employer’s written request
specifying the grounds therefore, forthwith provide a replacement with
qualifications and experience acceptable to him. For such replacement there will
be no reduction in remuneration.
g) The remuneration to the replaced key personnel shall be paid at the original
quoted remuneration by the consultancy firm. The amount equivalent to the
reduction as mentioned in clause 5(e) above shall be deducted from the
overhead quoted by the consultancy firm.
67h) If any member of the approved team of a consultant engaged by <Agency>
leaves that consultant before completion of the job, he shall be barred for a
period of 6 months to 24 months from being engaged as a team member of any
other consultant working (or to be appointed) for any other <Agency>/ MoRTH
projects.
6) Additional Key Experts: If additional Key Experts are required to carry out the Services
during the execution of the contract, the Consultant shall submit to the Procuring
Entity for review and approval a copy of their Curricula Vitae (CVs). If the Procuring
Entity does not object in writing (stating the reasons for the objection) within twenty-
one (21) days from receiving such CVs, such additional Key Experts shall be deemed
approved by the Procuring Entity. The rate of remuneration payable to such new
additional Key Experts shall be based on the rates for other Key Experts' positions
which require similar qualifications and experience.
7) Notwithstanding anything to the contrary stated in the GCC and SCC, it shall be mandatory
to deploy the key personnel and sub-professional as per the Man- Months Input specified
in the Terms of Reference.
Inadequate deployment of key personnel and sub- professional shall lead to
deduction in the monthly payment as per following table. The key personnel and
sub-professional shall be considered to be inadequately deployed if he/she is not
present for at least 90% (Except the leaves as specified in the Special Conditions
of Contract, Appendix B: Hours of Work for Key Personnel) of the time stipulated
in the month, ds per the Man-Months input in the Terms of Reference and the
Deployment Schedule proposed by the firm
Sr. Personnel % reduction of
No. monthly
remuneration
Normal Highway Project
1 Team Leader cum Senior Highway Engineer 20%
2 Resident Engineer cum Highway Engineer 25%
3 Bridge/Structural Engineer 20%
4 Other Key Personnel 20%
5 Sub- Professional Staff 15%
Standalone Bridge Project
1 Team Leader cum Senior Bridge Engineer 20%
2 Resident cum Pavement Specialist 25%
3 Bridge/Structural Engineer 20%
4 Other Key Personnel 20%
5 Sub- Professional Staff 15%
Standalone Tunnel Project
1 Team Leader cum Senior Tunnel Expert 20%
2 Resident Engineer cum Excavation Specialist 25%
3 Tunnel Design Engineer 20%
684 Other Key Personnel 20%
5 Sub- Professional Staff 15%
Note: -
1. In the case of “Other Key Personnel (Sr. No. 4)” and “Sub – Professional Staff (Sr.
No. 5)”, “the average availability across the group shall be considered for
calculation.
2. The key personnel shall be paid for the only time he has been actually been
present at site. Further, a deduction equivalent to the percentage mentioned
above, shall be deducted from the gross bill of the consultant as deterrent for
inadequate deployment. For avoidance of doubt, in case the Team Leader cum
Senior Highway Engineer has been made available for 85 % of the stipulated time
in the month, then only 85 % of the monthly remuneration shall be paid to the
key personnel. In addition to above, a penalty equivalent to 20 % of the quoted
remuneration of Team leader shall also be deducted. In the case of “Other Key
Personnel (Sr. No. 4)” and “Sub – Professional Staff (Sr. No. 5)”, for percentage
deduction as mentioned above, total remuneration of that group shall be
considered for calculation.
3. The 50% of the above deduction shall be recovered from remuneration payable
to key personnel and remaining 50% shall be deducted from the payment due to
the firm.
4. The non-deployment of any professional staff for any reason including
replacement etc shall be considered as absence. And the deduction as mentioned
above shall be fully recovered from the payment of the firm.
5. Consultant Have to provide a certificate that all key personnel as envisaged in the
contract Agreement has been actually deployed in the project. They have to
submit the proof of Aadhar Based Biometric attendance/ Geo –tagged selfie-based
attendance/ or any other document as decided by the Authority, at the time of
submission of bills to the <agency>
8.2.3 Non-key Personnel
the Consultant must ensure the deployment of non-key Personnel as per Annexure C,
the Terms of Reference, and the approved Works plan as updated. Daily attendance
records of such non-key personnel shall be maintained by the Consultant and shared
with the Contract Manager. If the Contract Manager believes that the Consultant is not
employing sufficient Non-key personnel as is specified or otherwise for the proper
execution of the Services, he shall issue a notice to the Consultant for remedial
measures. The Consultant shall forthwith, on receiving intimation to this effect, deploy
the additional number of non-key personnel as specified by the Contract Manager
immediately, and failure on the part of the Consultant to comply with such instructions
69shall entitle the Procuring Entity to suspend payments as per GCC clause 10.6 for the
shortfall in performance or terminate the contract and/ or avail all the remedies
thereunder. Such action shall be in addition to the deduction from the Consultant’s
payment cost of shortfall personnel as per Annexure C.
8.2.4 Removal of Key and Non-key Experts or Sub-consultants on Orders The
Contract Manager
1) The Consultant shall, at the Procuring Entity’s written request, provide a
70Replacement, if the Procuring Entity finds that any of the Experts or Sub-consultant: commits
severe misconduct or has been charged with having committed a criminal act
a)
persists in any misconduct or lack of care;
b)
is found to be negligent, incompetent or incapable of discharging assigned
duties;
c)
fails to comply with any provision of the Contract;
d)
based on reasonable evidence, is determined to have engaged breached the
Code of Integrity (including Fraud and Corruption) during the execution of the
Works;
2) Subject to the requirements in the sub-clause above, and notwithstanding any
requirement from the Procuring Entity to request a replacement, the Consultant shall
take immediate action as appropriate in response to any violation in the sub-para
above. Such immediate action shall include removing (or causing to be removed)
such Key/ Non-Key Expert or sub-consultant from carrying out the Services.
3) Any replacement of the removed Experts or Sub-consultants shall possess better
qualifications and experience and be acceptable to the Procuring Entity.
4) The Consultant shall bear all costs from or incidental to any removal and/or
replacement of such Experts.
8.3. Equipment and Tools of Trade
The Consultant must ensure the deployment of Equipment and Tools of Trade necessary
to deliver services as per the Terms of Reference and approved Works plan as updated.
If the Contract Manager believes that the Consultant is not employing on the Services
sufficient Equipment/Tools of Trade as is specified or otherwise for the proper execution
of the Services within the prescribed time, the Consultant shall forthwith on receiving
intimation to this effect deploy the additional equipment/ tools of the trade as specified
by the Contract Manager immediately and failure on the part of the Consultant to
comply with such instructions shall entitle the Procuring Entity to suspend payments as
per GCC clause 10.6 for the shortfall in performance or terminate the contract and/ or
avail any or all the remedies thereunder for breach of contract.
Delivery of Services and delays
9.1. Works plan
1) Before the commencement of the Services, the Consultant shall submit for approval
of the Contract Manager a Works plan showing the Methods, schedule of delivery
of services, and deployment plans for Personnel, Equipment and Materials for the
execution of the services. The programme of delivery of Services amended as
necessary by discussions with the Contract Manager shall be treated as the agreed
Works plan for this Contract. The Services shall be carried out and monitored as per
the approved Program as updated.
2) The Contract Manager shall direct the order in which the several components of the
Services shall be provided, and the Consultant shall execute all orders the Contract
71Manager gives from time to time without delay. Still, the Consultant shall not be
relieved thereby from responsibility for the due performance of the Services in all
respects.
9.2. Commencement of Services
Effective Date of Contract: Consultant shall commence the Services and
shall proceed with due expedition and without delay from the effective date of
Contract (all dates of delivery shall be counted from such a date), which shall be
the date mentioned as the effective date in the contract, or if not so mentioned:
a) 15 days from the Procuring Entity’s notice (unless specified otherwise) to the
Consultant instructing him to begin carrying out the Services. This notice shall
confirm that the effectiveness prerequisites listed in the contract have been
met.
b) If no such order is issued,15 days from the date of the Issue of the LOA or
the signing of the Contract agreement, whichever is earlier.
2) Commencement of Services: Not later than the number of days after the
Effective Date specified in the Contract or the Notice to proceed, the Consultant
shall begin carrying out the Services after confirming the following:
a) As required by the Contract, all JV members and key experts needed at the
beginning of the assignment are effectively participating.
b) That upon provision of Bank Guarantees, advance payments, if any, are
implemented.
c) That the Procuring Entity has provided facilities (including Data, Documents
and Background Information) as per the Contract
d) that all parties involved in the assignment (users, security team, and other
relevant departments of the Procuring Entity and other third-party
stakeholders) have been informed by the Procuring Entity
e) that all permits, licences, and authorisations have been obtained.
3) Termination of Contract for Failure to Become Effective: If this Contract
has not become effective (as per sub-clause 1) above) within such period after the
date of Contract signature as specified in the Contract, either Party may, by not
less than twenty-one (21) days’ written notice to the other Party, declare this
Contract to be null and void, and in the event of such a declaration by either Party,
neither Party shall have any claim against the other Party with respect hereto.
9.3. Contract Management
9.3.1 Consultancy Management Teams
The Procuring Entity shall nominate a Contract Manager (or a Consultancy
Management Team), and the Consultant shall nominate a counterpart Team Lead to
monitor the assignment so that the output is in line with the Procuring Entity's objectives
of the Contract.
729.3.2 Review of Phases and Milestones
The Contract Manager and Consultant/ Team Lead shall hold progress meetings at
various phases and Milestones into which the assignment is divided as per Annexure A.
Unless otherwise indicated in Annexure A, the following actions would be taken during
such progress meetings.
1) Kick-off Meeting: The contract Manager and the Consultant/ Team Lead shall
meet at the start of the assignment to ensure that the Contract requirements are
clearly understood by all concerned and that the Contract Management procedures
are finalised.
2) Inception Phase Review: The inception meeting shall be held at a period
(specified in Annexure A or the Notice to Proceed) after the effective date of the
contract or, if not so specified, within 21 days of the effective date. Before this
meeting, the consultant must provide a draft Inception Report for discussion. The
Consultant shall submit a final Inception Report within the specified time in the ‘Terms
of Reference’ or as agreed in the Inception Meeting, or if not so specified, within 7
days of the Inception Meeting. Template for Inception Report may be agreed to
beforehand in the Inception Meeting. It should, at the minimum, cover comments and
suggestions on the following:
a) Terms of Reference
b) Work plan and staffing schedule
c) Facilities to be provided by the Procuring Entity
d) Working arrangements and liaison
3) Periodic Reviews: Unless otherwise decided by the Contract Manager and the
Consultant’s Team Lead, periodic review meetings (monthly if not otherwise
stipulated) shall be held to review the pace of progress as compared to the Work
Plan and remedial actions thereto.
4) Deliverables Reviews: The contract Manager and Consultant/ Team Lead may
hold other meetings to review and approve specific deliverables or phases
(including
Interim and Final Reports) as specified in Annexure A or as agreed between the
parties.
9.4. Delivery of services, Time of Delivery and Extensions Thereof
9.4.1 Delivery of Services:
The Consultant shall deliver all Services and submit deliverables as per the approved
work plan in the manner specified in the Contract.
9.4.2 Time of Delivery of Services is of Essence of the Contract:
1) The time for delivery of Services shall be deemed to be the essence of the contract.
Subject to any requirement in the contract as to the completion of any portions or
portions of the Services before completion of the whole, the Consultant shall fully
and finally complete the whole of the services comprised in the contract as per the
Delivery and Completion Schedule stipulated in Annexure A: ‘Terms of Reference’.
732) If at any time during the currency of the contract, the Consultant encounters
conditions hindering the timely performance of services; the Consultant shall
promptly inform the Procuring Entity in writing about the same and its likely duration.
3) He may request to the Procuring Entity for an extension of the delivery schedule not
less than one month before the expiry of the date fixed for completion of the services.
Procuring Entity may agree to extend the completion schedule, with or without
liquidated damages and denial clause, by issuing an amendment to the contract in
terms of the following clauses.
9.4.3 Extension for Excusable Delay Not Due to Consultant
1) If in the opinion of the Consultant, the progress of Services has at any time been
delayed due to the following reasons, then within 15 days of such happening
causing delay, he shall give notice thereof in writing to the Contract Manager, but
shall nevertheless do due diligence to bring down or make good the delays and to
proceed with the services:
Proceedings taken or threatened by or dispute with external third parties arising
otherwise than from the Consultant's own default etc. or
delay due to circumstances beyond the control of either party
delay authorized by the Contract Manager pending arbitration
or Any act or neglect of Procuring Entity, e.g.:
i) Delay or failure to issue notice to commence the services or
ii) delay or failure to issue necessary instructions for which the Consultant
had applied explicitly in writing.
iii) Delay in or failure to handover of possession of the site or the necessary
facilities/ documents/ data or instructions by the Procuring Entity to the
Consultant
iv) Delay caused by modification issued by the Contract Manager or
v) any other delay caused by the Procuring Entity due to any other cause.
2) The Consultant may also indicate the period for which the Services are likely to be
delayed and ask for a necessary extension of time. On receipt of such request from
the Consultant, the Contract Manager shall consider the same and grant such
extension of time as, in his opinion, is reasonable regarding the nature and period
of delay and the type and quantum of work affected thereby. No other
compensation shall be payable for work carried forward to the extended period.
The same rates, terms, and conditions as the original Contract shall apply during
the extended period.
9.4.4 Extension of Time for Inexcusable Delay Due to Consultant
1) If the Consultant fails to deliver the Services within the fixed/ extended period for
reasons other than those stipulated in GCC-clause 9.4.3 above, the Procuring Entity
may, if satisfied that the service delivery can still be completed within a reasonable
time, extend the period further.
742) On such extension, the Procuring Entity shall be entitled without prejudice to any
other right and remedy available on that behalf to recover from the Consultant as
agreed damages and not by way of penalty Liquidated Damages as per GCC- clause
9.5 below.
3) Provided further that if the Procuring Entity is not satisfied that the service can be
completed by the Consultant or in the event of failure on the part of the Consultant
to complete the service within the extension of time allowed further as aforesaid, the
Procuring Entity shall be entitled without prejudice to any other right or remedy
available in that behalf, treat the delay as a breach of contract and avail any or all
the remedies thereunder, whether or not actual damage is caused by such default.
4) Inordinate Delays: Delays due to the Consultant of more than one-fourth (25%) of
the total completion period shall be treated as inordinate delays. Such inordinate
delays shall be noted as poor performance and be held against the Consultant in
future procurements. A show-cause notice shall be issued to the Consultant before
declaring it a poor performance. Such delays may be considered a breach of the
contract at the option of the Procuring Entity.
9.4.5 Extension of Time for Concurrent Delay Due to Both Parties
If the Contract Manager determines that two or more events responsible for delay
overlap each other. The delays may be concurrently attributable to both Procuring Entity
and the Consultant. The proportion for extension of time as per GCC-Clause 9.4.3 or
9.4.4 above shall be determined by plotting each contributing concurrent delay on the
critical path.
9.5. Damages and Deductions Thereof
9.5.1 Right of the Procuring Entity to recover Damages.
Procuring Entity shall be entitled to, and it shall be lawful to recover Liquidated damages
and any other penalty, if levied, as detailed in this clause from all payments due, any
Performance Security, or any retention money.
9.5.2 Liquidated damages
1) For delays covered under clause 9.4.4 (Extension of Time for Inexcusable Delay Due
to Consultant) above:
a) The Procuring Entity shall, without prejudice to other rights and remedies
available to the Procuring Entity under the contract, deduct from the contract
price as liquidated damages for each week of delay or part thereof until
actual delivery or performance, but not as a penalty, a sum equivalent to the
1/2% per cent (or any other percentage if prescribed) of the related monthly
bill of the Services. Besides liquidated damages during such a delay, the
denial clause as per GCC-clause 9.5.3 shall also apply. Total damages in the
contract shall be limited as per clause 9.5.4 below.
b) Any failure or delay by any Sub-consultant, though their employment may
have been sanctioned, shall not be admitted as a ground for any extension
75of time or for exempting the Consultant from liability for any such loss or
damage as aforesaid.
9.5.3 Denial Clause:
1) For delays covered under clause 9.4.4 (Extension of Time for Inexcusable Delay Due
to Consultant) above:
a) no increases in price on account of any statutory increase in or fresh
Imposition of GST, or on account of any other taxes/ duty/ cess/ levy) leviable
in respect of the Services and incidental goods/ works stipulated in the said
Contract which takes place after the original delivery date shall be admissible
on such of the said Services, as are delivered after the said date; and
b) Notwithstanding any stipulation in the contract for an increase in price on
any other ground, including the price variation clause, no such increase after
the original delivery date shall be admissible on such Services delivered after
the said date.
c) Nevertheless, the Procuring Entity shall be entitled to the benefit of any
decrease in price on account of reduction in or remission of GST or on
account of any other tax or duty or any other ground as stipulated in the
price variation clause, which takes place after the expiry of the original
delivery date.
9.5.4 Limit on total Damages
However, deduction on account of damages for delays under this clause put together
shall be subject to a maximum of 10% (or any other percentage if prescribed) of the
entire value of the Contract of Services. Penalties/ liabilities outside this clause shall be
covered by GCC clause 12.
9.6. Force Majeure
1) On the occurrence of any unforeseen event beyond the control of either Party,
directly interfering with the delivery of Services arising during the currency of the
contract, such as war, hostilities, acts of the public enemy, civil commotion,
sabotage, fires, floods, explosions, epidemics, quarantine restrictions, strikes,
lockouts, or acts of God, the affected Party shall, within a week from the
commencement thereof, notify the same in writing to the other Party with reasonable
evidence thereof. Unless otherwise directed by the Procuring Entity in writing, the
Consultant shall continue to perform its obligations under the contract as reasonably
practicable and seek all reasonable alternative means for performance not
prevented by the Force Majeure event. If the force majeure condition(s) mentioned
above be in force for 90 days or more at any time, either party shall have the option
to terminate the contract on expiry of 90 days of commencement of such force
majeure by giving 14 days’ notice to the other party in writing. In case of such
termination, no damages shall be claimed by either party against the other except
76those which had occurred under any other clause of this Contract before such
termination.
2) Notwithstanding the remedial provisions contained in GCC-clause 9.5 and 12, none
of the Party shall seek any such remedies or damages for the other Party's delay
and/ or failure in fulfilling its obligations under the contract if it is the result of an
event of Force Majeure.
Prices and Payments
10.1. Prices
10.1.1Contract Price
1) The Contract price is outlined in the Contract. The Contract price breakdown is
provided in Appendix C, and the total payments under this Contract shall not exceed
this Contract price.
2) Any change to the Contract price specified above can be only made if the Parties
have agreed to the revised scope of Services under GCC clause 2.6 and have
amended the Terms of Reference in Appendix A in writing.
10.1.2 Firm Prices
Unless otherwise stipulated in the contract, Prices shall be fixed and firm. If the Price
Variation Clause is included, such up and down, variations shall also be payable.
10.1.3 Variations
In case the Contract provides for a Price Variation Clause or variation on any other
account, the price shall be subject to adjustment as per such clauses only during the
original Delivery Period, subject to the following:
For Extension of Time covered by clause 9.4.5 above, any increase due to such
variations during the extended delivery period beyond the original delivery
period shall not be paid by the Procuring Entity; however, it shall be entitled to
any reduction under GCC clause- 9.5.3 (Denial Clause).
Taxes and duties, if any, chargeable and payable on the Services shall be
charged on the nett price after variations.
While claiming payments where such variations are applicable, the Consultant
must submit its calculations for each invoice, even if the payment for these
variations is nil. Any price reduction due to such variations must be passed to the
Procuring Entity.
No Other Claim due to Variations: With the payment of such variations, no
additional individual claim shall be admissible on account of fluctuations in
market rates, increase in taxes/any other levies/tolls etc.
If the Price Variation clause is applicable as per the contract, the price shall be
subject to adjustment to take care of the changes in the cost of labour, material,
and fuel/ power components as per the price variation formula specified therein.
77Base Month: Unless otherwise stipulated in the contract, the ‘Base Month’ for the
‘Price Variation Clause’ shall be taken as the month before the month of the last
date of Proposal submission. Unless the contract has stipulated a different time
lag for reckoning Price Variation, the month of reckoning the variated price shall
be the month before the month in which delivery has been made. The Price
Variation shall be based on the relevant Indices in the Base Month and Month of
reckoning.
Applicability: If the Contract provides for some inputs to be supplied by Procuring
Entity free or at a fixed rate, the cost of such inputs shall be excluded from the
value of the Goods supplied in the relevant month for payment/recovery Of price
variation.
10.2. Taxes and Duties
The Consultant, Sub-consultants, and Experts shall be entirely responsible for all
taxes, duties, fees, levies etc., incurred relating to the delivery of the Services.
Further instruction, if any, shall be as provided in the Contract.
If applicable under relevant tax laws and rules, the Procuring Entity shall deduct
from all payments and deposit required taxes to respective authorities on account
of GST Reverse Charge Mechanism; Tax Deducted at Source (TDS), and Tax
Collected at Source (TCS) relating to Income Tax, labour cess, royalty etc.
Payment of GST Tax under the contract:
(a) The payment of GST and GST Cess to the Consultant shall be made only on
the latter submitting a GST compliant Bill/ invoice indicating the appropriate
HSN code and applicable GST rate duly supported with documentary evidence
as per the provision of the relevant GST Act and the Rules made there under.
The delivery of Services shall be shown as being made in the name, location/
state, and GSTIN of the beneficiary of the Services only; the location of the
procurement office of the procuring entity has no bearing on the invoicing.
(b) Provision w.r.t. E-Invoicing requirement as per GST laws: Consultant who is
required to comply with the requirements of E-invoice as per the GST Law, all
payments shall be made against proper e-invoice(s) only. Invoices issued in
violation shall not be processed for payment, as Procuring Entity shall not be
allowed to avail of Input Tax Credit (ITC) against such invoices.
(c) Returns and details required to be filled under GST laws & rules regarding
invoices (or e-invoices) should be filed promptly by the Consultant. If input tax
credit (ITC) is not available to Procuring Entity for any reason attributable to the
Consultant, then Procuring Entity shall not be liable to pay or reimburse GST
(CGST & SGST/UTGST or IGST) claimed in the invoice(s) and shall be entitled
to deduct / setoff/ recover such GST amounts (CGST & SGST/UTGST or IGST)
together with penalties and interest, if any, by adjusting against any amounts
paid or becomes payable in future to the Consultant under this contract or
under any other contract.
78(d) While claiming reimbursement of duties, taxes etc. (like GST) from the Procuring
Entity, as and if permitted under the contract, the Consultant shall also certify
that in case it gets any refund out of such taxes and duties from the concerned
authorities at a later date, it (the Consultant) shall refund to the Procuring Entity,
the Procuring Entity’s share out of such refund received by the Consultant. The
Consultant shall also refund the appropriate amount to the Procuring Entity
immediately after receiving the same from the concerned authorities.
(e) All necessary adjustment vouchers, such as Credit Notes/ Debit Notes for any
short/ excess delivery of Services or revision in prices or any other reason under
the contract, shall be submitted to the Procuring Entity in compliance with GST
provisions.
(f) GST shall be paid as per the rate at which it is liable to be assessed or has been
assessed, provided the provision of Services is legally liable to such taxes and
is payable as per the terms of the contract subject to the following conditions:
i) The Procuring Entity shall not pay a higher GST rate if leviable due to any
misclassification of the HSN number or incorrect GST rate incorporated
in the contract due to the Consultant's fault. Wherever the Consultant
invoices the Goods at GST rate or HSN number, which is different from
that incorporated in the contract, payment shall be made as per GST
rate, which is lower of the GST rates incorporated in the contract or billed.
ii) However, the Procuring Entity shall not be responsible for the Consultant's
tax payment or duty under a misapprehension of the law.
iii) The consultant is informed that he shall be required to adjust his basic
price to the extent required by a higher tax rate billed as per invoice to
match the all-inclusive price mentioned in the contract.
iv) In case of profiteering by the Consultant relating to GST tax, the
Consultant shall treat it as a violation of the Code of Integrity in the
contract and avail any or all punitive actions thereunder, in addition to
recovery and action by the GST authorities under the Act.
(g) The Consultant should issue Receipt vouchers immediately on receipt of all types
of payments along with tax invoices after adjusting advance payments, if any,
as per Contractual terms and GST Provisions.
(h) Liquidated damages or any other recoveries should be shown as deductions on
the invoice, and GST shall be applicable only on the net balance payment due.
Statutory Variation Clause: Unless otherwise stated in the contract,
statutory increase in applicable GST rate only during the original delivery period
shall be to Procuring Entity’s account. Any increase in the rates of GST beyond the
original completion date during the extended delivery period (excepting extension
under GCC-Clause 9.4.3) shall be borne by the Consultant. The benefit of any
reduction in the GST rate must be passed on to the Procuring Entity during the
original and extended delivery period. However, GST rate amendments shall be
79considered for quoted HSN code only, against documentary evidence, provided
such an increase of GST rates occurs after the last proposal submission date.
10.3. Terms and Mode of Payment
1) Unless otherwise stipulated, the usual payment term is 100% on delivery and
acceptance of Services at ‘the Site’ by the Procuring Entity and the Consultant's
production of all required documents.
2) The payments shall be made as per Procuring Entity’s payment procedures. Unless
otherwise stipulated in the contract, payments above INR 5,000 (or any other
specified threshold) to Consultants shall only be made through EFT (Electronic Funds
Transfer). The Consultant shall consent in a mandate form for receipt of payment
through NEFT (National Electronic Fund Transfer). In case of non-payment through
EFT or where the EFT facility is unavailable, payment may be released through
cheque.
3) In Domestic Contracts, payments shall only be made in Indian Rupees. In Global
Tenders, payment to foreign Consultants shall be made in the currency/ currencies
authorized in the contract. However, agency commission and local value addition
shall be paid only in Indian Rupees.
4) The Consultant shall send its claim for payment in writing as per GST-compliant
Invoice and documents, when contractually due, along with relevant documents etc.,
as stipulated in the Contract and as specified therein.
5) While claiming payment, the Consultant is also to certify in the bill that the payment
being claimed is strictly in terms of the contract and all the Consultant's obligations
for claiming that payment has been fulfilled as required.
10.4. Withholding and lien in respect of sums claimed:
1) Whenever any claim or claims for payment of a sum of money arises against the
Consultant, out of or under the contract, the Procuring Entity shall be entitled, and
it shall be lawful on his part, to withhold and also have a lien to retain such sum or
sums, in whole or in part pending finalisation or adjudication of any such claim from
-
a) any security or retention money, if any, deposited by the Consultant.
b) Any sum(s) payable till now or hereafter to the Consultant under the same
Contract or any other contract with the Procuring Entity if the security is
insufficient or if no security has been taken from the Consultant.
2) Where the Consultant is a partnership firm or a limited company, the Procuring
Entity shall be entitled, and it shall be lawful on his part, to withhold and also have
a lien to retain towards such claimed amount or amounts in whole or in part from
any sum found payable to any partner/ limited company, as the case may be,
whether in his capacity or otherwise.
3) It is an agreed term of the contract that the sum(s) of money so withheld or retained
under the lien referred above shall be kept withheld or retained till the claim arising
out of or under the contract is determined under GCC clauses 11 and/ or 12. The
80Consultant shall have no claim for interest or damages whatsoever on any account
regarding such withholding or retention under the supra lien and duly notified to the
Consultant.
4) Lien in respect of Claims in other Contracts: Any sum of money due and payable to
the Consultant (including the security deposit returnable to him) under the contract
may be withheld or retained by way of lien by the Procuring Entity or Government
against any claim of the Procuring Entity or Government in respect of payment of a
sum of money arising out of or under any other contract made by the Consultant
with the Procuring Entity or Government.
10.5. Payments to Consultant
10.5.1 General
1) All payments under this Contract shall be made to the Consultant's accounts
Specified in the contract.
2) Currency of Payment: Unless otherwise specified in the Contract, any payment
shall be made in Indian Rupees (INR).
3) The Itemized Invoices: As soon as practicable and not later than fifteen (15) days
after the end of each time interval stipulated in the Contract in this regard (if not
stipulated, then after the end of each calendar month), the Consultant shall submit
to the Procuring Entity, in duplicate, itemized invoices, accompanied by the receipts
or other appropriate supporting documents, of the amounts payable for such an
interval under GCC Clause 10.5. Separate invoices shall be submitted for expenses
incurred in foreign and local currencies. Each invoice shall show remuneration and
reimbursable expenses separately.
4) The Contract Manager shall cross-check all relevant records before passing the
Consultant's bills. Upon verification of the records by Procuring Entity, payments can
be released to the Consultant.
5) The Procuring Entity shall pay the Consultant’s invoices within sixty (60) days after the
receipt by the Procuring Entity of such itemized invoices with supporting
documents. Only a portion of an invoice not satisfactorily supported may be withheld
from the payment. Should any discrepancy exist between actual payment and costs
authorized to be incurred by the Consultant, the Procuring Entity may add or subtract
the difference from subsequent payments.
6) Except for the final payment under GCC Clause 10.5.5 below, payments do not
constitute acceptance of the Services nor relieve the Consultant of any obligations.
7) Time-Based (Inputs admeasurement): Unless instructed in writing by the Procuring
entity, payments shall not be made for any extra inputs deployed over and above
Annexure A, Annexure B, or Annexure C mentioned in the contract. Nevertheless, if
such inputs are deployed less than those stipulated, deductions shall be made based
on the rates indicated for the inputs listed in Annexures C and D in the contract.
8) The remuneration for professional staff (Key personnel and sub professional staff
quoted in Appendix C-1 shall be credited into a separate Escrow Account wherein
release of the remuneration of the Key-Personnel in their respective salary account
would be jointly regulated by the Authority and AE firm. The remaining payment(after deducting the remuneration of professional staff and any other deduction) as
quoted by the consultant shall be credited in the bank account of the consultant
firm. All payment of salary to all key personnel in their respective bank accounts
through electronic mode only. No cash transaction w.r.t salary will be made.
8) Consultants shall be paid billing rates for services rendered by the personnel of
all categories namely (i) key Personnel; (ii) sub-Professional personnel and (iii)
Support staff on man-month basis. Billing rates of remaining items of the
financial proposal, namely (i) transportation, (ii) Duty travel to site (iii) Office
Rent, (iv) office supplies communication etc. (v) reports & document printing and
(vi) survey equipment etc. shall be worked out month wise as per actual
expenditure.
9) Beginning 13th months from the last date of submission of bid, billing rates shall
be increased to cover all items of contract i.e. remuneration, vehicle hire, office
rent, consumables, furniture etc. @ 5% every 12 months. However, for evaluation
and award of the Bid proposals, the quoted initial rate (as applicable for first 12
months from last date of submission of bid) shall be multiplied by the total time
input for each position on this contract, i.e. without considering the increase in
the billing rates. All payments shall be made in Indian Rupees and shall be
subjected to applicable Indian laws withholding taxes if any. Remuneration paid
pursuant to the rates set forth in Appendix- C shall be adjusted every twelve (12)
months (and, the first time, with effect for the billing rates earned in the 13th
calendar month after the last date of submission of bid) by 5% every 12 month
for personnel. Notwithstanding any other provisions in the agreement in this
regard, this provision will prevail and override any other provision to the contrary
in this agreement
10) Payment of Authority Engineer shall be released on approval of the
monthly reports. Report shall be approved by the Authority only if it
includes all the sections prescribed in the format and submitted as per
specified timelines.
11) Payment shall be released as per rates quoted in Appendix C3- Breakup of
Local currency costs
12) For equipment based road inspection to be conducted in O&M phase,
payment shall be released as per actual use of equipment on road and rates
quoted in Appendix C3- Breakup of Local currency costs.
13) If any of the report is found to be misleading or containing incorrect
information as determined by the Authority, 10% of payment linked to that
report shall be deducted as penalty
14) It is understood(i)that the remuneration rates shall cover(A) such salaries
and allowances as the Consultants shall have agreed to pay to the Personnel
as well as factors for social charges and overhead, and (B)the cost of back
stopping by home office staff not included in the Personnel listed in
82Appendix C, and(C)the Consultants' fee;(ii)that bonuses or other means of
profit-sharing shall not be allowed as an element of overhead, and(iii)that
any rates specified for persons not yet appointed shall be provisional and
shall be subject to revision, with the written approval of the Client, once the
applicable salaries and allowances are known.
15) Remuneration for periods of less than one month shall be calculated on an hourly basis for actual
time spent in the Consultants' home office and directly attributable to the Services (one hour being
equivalent to 1/240th of a month) and on a calendar-day basis for time spent away from home office
(one day being equivalent to 1/30th of a month).
10.5.2 The rates for foreign and local Personnel are set forth in Appendix C-1.
10.5.3 Advance Payments
1) If the contract provides explicitly for Advance Payments to be made to the
Consultant, then on the request of the Consultant, the Procuring Entity shall
make the advance payment to the Consultant against submission of an
unconditional Bank Guarantee from a Commercial bank acceptable to the
Procuring Entity in amounts equal to 110% (one hundred ten per cent) of the
amount of the advance payment being requested. Such Bank Guarantee shall
be in the form outlined in Appendix E-2 or the other form the Procuring Entity
shall have approved in writing. Advance payments shall be released in not less
than two instalments commensurate with work progress.
2) The Bank Guarantee shall remain effective until the advance payment has been
repaid, but the amounts repaid by the Consultant shall progressively reduce the
guaranteed amount. Interest shall not be charged on the advance payment.
However, if the contract is terminated due to the Consultant's default, the
Advance payment shall be deemed an interest-bearing advance at the
prevailing rate (MIBID - Mumbai Interbank Proposal Rate) on the date of such
advance payment.
3) The Consultant is to use the advance payment only for the performance of
Services. The Consultant shall demonstrate that the advance payment has been
used by Utilization certificate enclosing copies of invoices or other documents
to the Contract Manager. Further instalments shall be released after getting a
satisfactory utilization certificate from the Consultant for the earlier instalment.
4) The advance payment shall be recovered in a time-based manner not linked with the
work progress by deducting proportionate amounts from payments otherwise due to the
Consultant for the Services performed. Any delayed recoveries due to the late submission
of bills by the Consultant shall attract interest at the prevailing rate (MIBID - Mumbai
Interbank Proposal Rate). No account of the advance payment or repayment shall be taken
in assessing valuations of Services performed, variations, price adjustments, or liquidated
damages.
10.5.3 Remuneration and Reimbursable Expensesa) The Procuring Entity shall pay to the Consultant (i) remuneration that shall be
determined based on time spent by each Expert in the performance of the
Services after the date of commencing of Services or such other date as the
Parties shall agree in writing; and (ii) reimbursable expenses that are actually
and reasonably incurred by the Consultant in the performance of the Services.
b) All payments shall be at the rates outlined in Appendix C and Appendix D.
c) Unless the Contract provides for the price adjustment of the remuneration rates,
said remuneration shall be fixed for the duration of the Contract.
d) The remuneration rates shall cover: (i) such salaries and allowances as the
Consultant shall have agreed to pay to the Experts as well as factors for social
charges and overheads (bonuses or other means of profit-sharing shall not be
allowed as an element of overheads), (ii) the cost of backstopping
(reinforcement/ support) by home office staff not included in the Experts’ list in
Appendix B, (iii) the Consultant’s profit, and (iv) any other items as specified in the
contract.
e) Any rates specified for Experts not yet appointed shall be provisional and be
subject to revision, with the written approval of the Procuring Entity once the
applicable remuneration rates and allowances are known.
10.5.4 "On-Account" Payments
1) the Consultant shall be entitled to be paid (unless otherwise stipulated in the
contract) by way of "On-Account" payment, only for such Services, as in the opinion
of the Contract Manager, the Consultant has executed in terms of the contract during
the period. All payments due against the Contract Manager or his representative's
certificates shall be subject to any deductions, which may be made under the
contract, always provided that the Contract Manager may by any certificate make
any correction or modification in any previous certificate, which he may have issued.
The Contract Manager may withhold any certificate if the Services or any part thereof
are not carried out as per the contractual performance standards.
2) On-Account Payments Not Prejudicial to Final Settlement: "On-Account" payments
made to the Consultant shall be without prejudice to the final settlement of the
accounts. They shall not be considered or used as evidence of any facts stated in or
inferred from such accounts, any particular quantity of service being executed, or
the manner of its execution being satisfactory.
3) The Final Payment:
10.5.5 Final Payment
1) The final payment under this Clause shall only be made after the final report/
deliverables and a final invoice, identified as such, shall have been submitted by the
Consultant and approved as satisfactory by the Procuring Entity. Completion
certificate/ Final payment shall be made only after ensuring that all facilities/
documents/ sites have been returned to the Procuring Entity as per GCC clause
5.14. The Services shall be deemed completed and finally accepted by the Procuring Entity.
2) The Consultant shall submit a final bill on the Contract Manager's acceptance
84certificate of final deliverables. The Final payment shall be made as per the following
calculations after receiving a clear "No Claim Certificate” signed by the Consultant:
a) necessary adjustment for any payments already made or retained
b) any deduction which may be made under the contract,
c) A complete account of all claims the Consultant may have on the Procuring
Entity, and the Contract Manager gave a certificate in writing that such claims
are correct,
3) The final report and final invoice shall be deemed approved by the Procuring Entity
as satisfactory ninety (90) calendar days after receipt of the final report and final
invoice by the Procuring Entity unless the Procuring Entity, within such ninety (90)
calendar day period, gives written notice to the Consultant specifying in detail
deficiencies in the Services, the final report or final invoice. The Consultant shall
promptly make any necessary corrections, and the preceding process shall be
repeated.
4) Any amount that the Procuring Entity has paid or has caused to be paid under this
Clause more than the amounts payable under the provisions of this Contract shall
be reimbursed by the Consultant to the Procuring Entity within thirty (30) days after
receipt by the Consultant of notice thereof. Any such claim by the Procuring Entity
for reimbursement must be made within twelve (12) calendar months after receipt
by the Procuring Entity of a final report and a final invoice approved by the Procuring
Entity in accordance with the above.
10.5.6 No Claim Certificate and Release of Contract Securities
The Consultant shall submit a ‘No-claim certificate’ to the Procuring Entity in such form as
shall be required by the Procuring Entity after the Services are finally accepted and
before the final payment/ performance securities are released. The Procuring Entity shall
release the contractual securities without any interest if no outstanding obligation, asset,
or payments are due from the Consultant. The Consultant shall not be entitled to make
any claim whatsoever against the Procuring Entity under or arising out of this Contract,
nor shall the Procuring Entity entertain or consider any such claim, if made by the
Consultant, after he shall have signed a "No Claim" Certificate in favour of the Procuring
Entity. The Contactor shall be debarred from disputing the correctness of the items
covered by the "No Claim" Certificate or demanding arbitration.
10.5.7 Post Payment Audit
Notwithstanding the issue of the Completion Certificate and release of final Payment,
the Procuring Entity reserves the right to carry out within 180 days (unless otherwise
stipulated in the contract) of such completion/ final payment, a post-payment audit and/
or technical examination of the Services and the final bill including all supporting
vouchers, abstracts etc. If any over-payment to the Consultant is discovered due to such
examination, the Procuring Entity shall claim such amount from the Consultant.
10.5.8 Signature on Receipts for Amounts
Every receipt for money, which may become payable, or for any security which maybecome transferable to the contractors under the contract, shall be signed by a person
authorized to do so by the Consultant (or otherwise as per GCC-Clause 4.2), to be a
suitable and sufficient discharge to the Procuring Entity in respect of the sums of money
or security purported to be acknowledged thereby. In the event of the death of any
Consultant or partner during the pendency of the contract, every receipt by anyone of
the surviving constituents shall be suitable and sufficient discharge as aforesaid.
Nothing in this Clause shall be deemed to prejudice or effect any claim that the
Procuring Entity may have against the legal representative regarding any breach of any
contract conditions by any Consultant partner/member so dying. Nothing in this clause
shall be deemed to prejudice or affect the respective rights or obligations of the
Consultant partners/ members and the legal representatives of any deceased
Consultant partners/ members.
10.6. Suspension of Payments
The Procuring Entity may, by written notice of suspension to the Consultant, suspend
part or all payments to the Consultant hereunder if the Consultant fails to deliver the
Services as per the Terms of Reference, including the non-rectification of notified defects
in the Services/ deliverables, provided that such notice of suspension (i) shall specify the
nature of the failure, and (ii) shall request the Consultant to remedy such failure within
a period not exceeding thirty (30) calendar days after receipt by the Consultant of such
notice of suspension. Such a suspension shall not entitle the Consultant to any extension
of time for delivery of Service.
10.7. Payment Against Time-Barred Claims
In accordance with the Limitation Act 1963, all claims against the Procuring Entity shall
be legally time-barred after three years calculated from when the payment falls due
unless the payment claim has been under correspondence. The Procuring Entity is
entitled to, and it shall be lawful to reject such claims.
10.8. Commissions and Fees
The Consultant shall disclose any commissions or fees that may have been paid or are
to be paid to agents, representatives, or commission agents concerning the selection
process or execution and performance of this Contract. The information disclosed must
include the name and address of the agent, representative, or commission agent, the
amount and currency, and the purpose of the commission or fee.
86Resolution Disputes
11.1. Disputes and Excepted Matters
All disputes and differences between the parties hereto, as to the construction or
operation of this Contract, or the respective rights and liabilities of the parties on any
matter in question, or any other account whatsoever, but excluding the Excepted Matters
(detailed in GCC-Clause 11.2 below); arising out of or in connection with the contract,
within thirty (30) days from aggrieved Party notifying the other Party of such matters;
whether before or after the completion/ termination of the contract, that cannot be
resolved amicably between the Contract Manager and the Consultant, shall be
hereinafter called the “Dispute”. The aggrieved party shall give a ‘Notice of Dispute’
indicating the Dispute and claims citing the relevant Contractual clause to the
designated authority requesting invoking the following dispute resolution mechanism.
Before any recourse to courts, the dispute shall be resolved through dispute resolution
mechanisms detailed subsequently in the sequence mentioned below, and the next
mechanism shall not be invoked unless the earlier mechanism has been invoked or has
failed to resolve it within the deadline mentioned therein.
Adjudication
Conciliation
Arbitration
11.2. Excepted Matters
Matters for which provision has been made in any Clause of the contract shall be
deemed as ‘excepted matters’ (matters not disputable/ arbitrable), and decisions of the
Procuring Entity, thereon, shall be final and binding on the Consultant. The ‘excepted
matters’ shall stand expressly excluded from the purview of the sub-clauses below,
including Arbitration. However, where the Procuring Entity has raised the dispute, this
sub-clause shall not apply. Unless otherwise stipulated in the contract, excepted matters
shall include but are not limited to:
1) Any controversies or claims brought by a third party for bodily injury, death, property
damage or any indirect or consequential loss arising out of or in any way related to
the performance of this Contract (“Third Party Claim”), including, but not limited to, a
Party’s right to seek contribution or indemnity from the other Party in respect of a Third-
Party Claim.
2) Issues related to the pre-award Procurement Process or conditions
3) Issues related to ambiguity in Contract terms shall not be taken up after a Contract
has been signed. All such issues should be highlighted before the signing of the
contract by the Consultant.
4) Provisions incorporated in the contract which are beyond the purview of The
Procurement Entity or are in pursuance of policies of Government, including but not
limited toa) Provisions of restrictions in terms of the Make in India policy of the
Government
b) Provisions regarding restrictions on Entities from Countries having land
borders with India in terms of the Central Government’s policies in this
regard.
c) Relaxations stipulated for Startups etc.
11.3. Adjudication
After exhausting efforts to resolve the Dispute with the Contract Manager executing the
contract on behalf of the Procuring Entity, the Consultant shall give a ‘Notice of
Adjudication’ specifying the matters which are in question or subject of the dispute or
difference indicating the relevant contractual clause, as also the amount of claim item-
wise to Head of Procurement or any other authority mentioned in the contract
(hereinafter called the “Adjudicator”) for invoking resolution of the dispute through
Adjudication. During his adjudication, the Adjudicator shall give adequate opportunity
to the Consultant to present his case. Within 60 days after receiving the representation,
the Adjudicator shall make and notify decisions in writing on all matters referred to him.
During the adjudication proceedings, the parties shall not initiate any conciliation,
arbitral, or judicial proceedings in respect of a dispute that is the subject matter of the
adjudication proceedings. If not satisfied by the decision in adjudication, or if the
adjudicator fails to notify his decision within the abovementioned time-frame, the
Consultant may proceed to invoke the process of Conciliation as follows.
11.4. Conciliation of disputes
1) Parties may invoke Conciliation, in terms of the Arbitration and Conciliation Act
1996, by submitting a “Notice of Conciliation” to the other party with a request to
the Head of the Procuring Organisation to notify a Conciliator. Since conciliation is
voluntary, within 30 days of “Notice of Conciliation”, the Head of the Procuring
Organisation shall notify a sole Conciliator if the other party is agreeable to entering
Conciliation. If the other party is not agreeable to Conciliation, the aggrieved party
may invoke Arbitration.
2) The Conciliator shall proactively assist the parties to reach an amicable settlement
independently and impartially within the contract terms within 60 days from the
appointment date.
3) If the parties agree on a dispute settlement, they shall draw up a written settlement
agreement duly signed by the parties and conciliator. When the parties sign the
settlement agreement, it shall be final and binding on the parties. The dispute shall
be treated as resolved on the date of such agreement.
4) During the conciliation proceedings, the parties shall not initiate any arbitral or
judicial proceedings in respect of a dispute that is the subject matter of the
conciliation proceedings.
5) Termination of Conciliation: Disputes shall remain alive if the conciliation is
terminated as follows:
88a) By written declaration of the conciliator, after consultation with the parties,
to the effect that further efforts at conciliation are no longer justified on the
date of such declaration; or
b) By a written declaration of any party to the conciliator to the effect that the
conciliation proceedings are terminated on the date of such declaration; or
c) If the parties fail to reach an agreement on a settlement of the dispute within
60 days of the appointment of the Conciliator
6) On termination of Conciliation, the aggrieved party shall be free to invoke
Arbitration if the dispute is still alive.
11.5. Arbitration Agreement
11.5.1This Agreement
1) This Arbitration Agreement (hereinafter referred to as this “Agreement”) relating to
this Contract (hereinafter called the “Main Agreement” for this agreement) is made
under the provisions of The Arbitration and Conciliation Act, 1996, as amended
from time to time and the rules thereunder (hereinafter called The Arbitration Act).
This Agreement shall continue to survive termination, completion, or closure of the
Main Agreement for 120 days afterwards.
2) Subject to aforesaid provisions, relevant clauses of the contract shall apply to the
appointment of arbitrators and arbitration proceedings under this Agreement.
3) The Micro, Small and Medium Enterprises Development (MSMED) Act, 2006
provides parties to a dispute (where one of the parties is a Micro or Small Enterprise)
to be referred to the Micro and Small Enterprises Facilitation Council if the dispute
is regarding any amount due under Section 17 of the MSMED Act, 2006. If a Micro
or Small Enterprise, being a party to dispute, refers to the MSMED Act 2006, these
provisions shall prevail over this Agreement. However, if an arbitrator has already
been appointed under this agreement before the appointment of a conciliator/
arbitrator by the facilitation council, the arbitrator already appointed under this
agreement shall continue to perform the duties including on matters related to
delayed payments. Such an arbitrator shall be deemed to be the arbitrator
appointed by the facilitation council. None of the parties shall approach the
facilitation council to appoint an arbitrator once an arbitrator under this agreement
has already been appointed.
11.5.2 Notice for Arbitration
1) Authority to Appoint Arbitrator(s): For this Arbitration Agreement, ‘The Appointing
Authority’ to appoint the arbitrator shall be Head of the Procuring Organisation or
any other authority or Arbitration Institution named in the contract and includes if
there be no such authority, the officer who is for the time being discharging the
functions of that authority, whether in addition to other functions or otherwise.
2) In the event of any dispute as per GCC-clause 11.1 above, if the Adjudicator fails
to decide within 60 days (as referred in 11.3 above), or the Conciliation isterminated (as referred in sub-clause 11.4 above), then any party to the contract,
after 60 days but within 120 days of ‘Notice of Dispute” (clause 11.1 above) shall
request the other party through a “Notice for Arbitration” in writing that the dispute or
difference be referred to arbitration.
3) The “Notice for arbitration” shall specify the matters in question or the subject of the
dispute or difference, indicating the relevant contractual clause and the amount of
claim item-wise.
11.5.3 Reference to Arbitration
After appointing Arbitrator(s), the Appointing Authority shall refer the Dispute to them.
Only such dispute or difference shall be referred to arbitration regarding which the
demand has been made, with counter-claims or set off. Other matters shall be beyond
the jurisdiction of the Arbitrator(s)
11.5.4 Appointment of Arbitrator
1) Qualification of Arbitrators:
a) In the case of retired officers of The Procuring organization, they shall have
retired in the rank of Senior administrative grade (or equivalent) and shall
have retired at least 1 year prior and must not be over 70 years of age on
the date of Notice for arbitration.
b) The arbitrator(s) shall be expert with extensive experience in relation to the matter
in dispute.
c) He/ they shall not have had an opportunity to deal with the matters to which
the contract relates or who, in the course of his/ their duties as an officer of
the Procuring Organisation, expressed views on any or all of the matters
under dispute or differences. A certification to this effect (as per Format
1.1.4) shall be taken from Arbitrators. The proceedings of the Arbitral
tribunal or the award made by such Tribunal shall, however, not be invalid
merely for the reason that one or more arbitrators had, in the course of his
service, an opportunity to deal with the matters to which the contract relates
or who in the course of his/ their duties expressed views on all or any of the
matters under dispute.
d) An Arbitrator may be appointed notwithstanding the total number of
arbitration cases in which he has been appointed.
e) Not be other than the person appointed by The Appointing Authority, and if
for any reason that is not possible, the matter shall not be referred to
arbitration.
2) Replacement of Arbitrators
If one or more of the arbitrators appointed as above refuses to act as arbitrator,
withdraws from his office as arbitrator, or in the event of the arbitrator dying,
neglecting/ unable or unwilling or refusing to act for any reason, or his award being
set aside by the court for any reason, or in the opinion of The Appointing Authority
fails to act without undue delay, the Appointing Authority shall appoint new
90arbitrator/ arbitrators to act in his/ their place in the same manner in which the
earlier arbitrator/ arbitrators had been appointed. Such a re-constituted Tribunal
may, at its discretion, proceed with the reference from the stage at which it was left
by the previous arbitrator (s).
3) Appointment of Arbitrator:
a) In cases where the total value of all claims in question added together does
not exceed Rs 50,00,000/ - (Rupees Fifty Lakh only), the Arbitral Tribunal
shall consist of the sole Arbitrator. For this purpose, The Appointing Authority
shall send to the Consultant, within 60 days from receipt of a written and
valid notice for arbitration, a panel of at least four (4) names of retired
officers duly indicating their retirement dates.
b) The Consultant shall be asked to nominate at least two names out of the
panel for appointment as his nominee within 30 days from the dispatch date
of the request by The Appointing Authority. The Appointing Authority shall
appoint at least one out of them as the sole arbitrator within 30 days from
the receipt of the names of the Consultant’s nominees.
c) In cases where the total value of all claims in question added together
exceeds Rs 50,00,000/ - (Rupees Fifty Lakh only), the Arbitral Tribunal shall
consist of three (3) retired Officers of the Procuring Organisation.
arbitrators. For this purpose, The Appointing Authority shall send a panel
of at least four (4) names of such Officer(s) empanelled to work as
Arbitrators duly indicating their retirement date to the Consultant within 60
days from the day when a written and The Appointing Authority receives
valid demand for arbitration.
d) The Consultant shall be asked to nominate at least 2 names out of the panel
for appointment as his nominee within 30 days from the dispatch date of the
request by The Appointing Authority. The Appointing Authority shall appoint
at least one of them as the Consultant’s nominee. It shall also simultaneously
appoint the balance number of arbitrators from the panel or outside the
panel, duly indicating the ‘Presiding Arbitrator’ from amongst the 3
arbitrators so appointed within 30 days from the receipt of the names of the
Consultant’s nominees.
e) If the Consultant does not suggest his nominees for the arbitral tribunal
within the prescribed timeframe, The Appointing Authority shall proceed to
appoint the arbitral tribunal within 30 days of the expiry of such a time
Provided to the Consultant.
11.5.5 Failure to appoint Arbitrators.
If The Appointing Authority fails to appoint an arbitrator within 60 (sixty) days, then the
Appointment of the Arbitrator may be sought under the relevant provision of the
Arbitration and Conciliation Act 1996, as amended.11.5.6 The Arbitral Procedure
1) Effective Date of Entering Reference: The arbitral tribunal shall be deemed to
have entered the reference on the date the arbitrator(s) received notice of their
appointment. All subsequent time limits shall be counted from such date.
2) Seat and Venue of Arbitration: The seat of arbitration shall be where the Letter
of Award or the contract is issued. The venue of arbitration shall be the same as
the seat of arbitration. However, in section 20 of The Arbitration Act, the arbitrator,
at his discretion, may determine a venue other than the seat of the arbitration without
affecting the legal jurisdictional issues linked to the seat of the arbitration.
3) If the Adjudication and/ or Conciliation mechanisms had not been exhausted before
such a reference to Arbitration, the Arbitrator should ask the aggrieved party to
approach the designated authority for such mechanisms before the Arbitration
proceedings are started.
4) The claimant shall submit to the Arbitrator(s) with copies to the respondent his claims
stating the facts supporting the claims along with all the relevant documents and the
relief or remedy sought against each claim within 30 days from the date of
appointment of the Arbitral Tribunal unless otherwise extension has been granted
by Arbitral Tribunal.
5) On receipt of such claims, the respondent shall submit its defence statement and
counter-claim(s), if any, within 60 days of receipt of the copy of claims, unless
otherwise extension has been granted by Arbitral Tribunal.
6) No new claim shall be added during proceedings by either party. However, a party
may amend or supplement the original claim or defence thereof during arbitration
proceedings subject to acceptance by the Tribunal due to the delay in making it.
7) Statement of claims, counterclaims and defence shall be completed within six
months from the effective reference date.
8) Oral arguments to be held on a day-to-day basis: Oral arguments as far as possible
shall be heard by the arbitral tribunal daily, and no adjournments shall be granted
without sufficient cause. The arbitrator (s) may impose an exemplary cost on the
party seeking adjournment without sufficient cause.
9) Award within 12 (twelve) months: The arbitral tribunal is statutorily bound to deliver
an award within 12 (twelve) months from when the arbitral tribunal enters reference.
The award can be delayed by a maximum of six months under exceptional
circumstances where all parties consent to such an extension. The court's approval
shall require further extension if the award is not made out within an extended
period. When an application for an extension of time is awaiting before the court,
the arbitrator's proceedings shall continue until the disposal of the application.
10) Fast Track Procedure: The parties to arbitration may choose to opt for a fast-track
procedure either before or after the commencement of the arbitration. The award
in fast-track arbitration is to be made within six months, and the arbitral tribunal
shall be entitled to additional fees. The salient features of fast-track arbitration are:
a) The dispute is to be decided based on written pleadings only.
92b) Arbitral Tribunal shall have the power to call for clarifications and the
necessary written pleadings.
c) An oral hearing may only be held if all the parties request or the arbitral
tribunal considers it necessary.
d) The parties are free to decide the fees of the arbitrator(s) for a fast-track
procedure.
11) Powers of Arbitral Tribunal to grant Interim Relief: The parties to arbitration may
approach the arbitral tribunal to seek interim relief on the grounds available under
section 9 of the act. The tribunal has the powers of a court while making interim
awards in the proceedings before it.
12) Confidentiality: As provided in Section 42A of The Arbitration Act, all the details and
particulars of the arbitration proceedings shall be kept confidential except in certain
situations, like if the disclosure is necessary for the implementation or execution of
the arbitral award.
13) Obligation During Pendency of Arbitration: Performance of the contract shall, unless
otherwise directed by the Procuring Entity, continue during the arbitration
proceedings, and no payment due or payable by the Procuring Entity shall be
withheld on account of such proceedings, provided; however, it shall be open for
Arbitral Tribunal to consider and decide whether or not the performance of the
contract or payment therein should continue during arbitration proceedings.
11.5.7 The Arbitral Award
In the case of the Tribunal, comprising three members, any ruling on an award
shall be made by a majority of members of the Tribunal. In the absence of such
a majority, the views of the Presiding Arbitrator shall prevail.
The arbitral award shall state item-wise the sum and reasons it is based. The
analysis and reasons shall be detailed enough to infer the award.
It is further a term of this arbitration agreement that where the arbitral award is
for the payment of money, no interest shall be payable on the whole or any part
of the money for any period till the date on which the award is made in terms of
Section 31 (7) (a) of The Arbitration Act.
The arbitrator's award shall be final and binding on the parties to this Contract.
A party may apply for corrections of any computational errors, typographical
or clerical errors, or any other error of similar nature occurring in the award or
interpretation of a specific point of the award to the Tribunal within 60 days of
receipt of the award.
A party may apply to the Tribunal within 60 days of receiving the award to make
an additional award for claims presented in the arbitral proceedings but omitted
from the arbitral award.11.5.8 Savings
The Arbitral Tribunal shall decide any matter related to Arbitration not covered under
this Arbitration Agreement as per the provisions of The Arbitration Act.
11.5.9 Cost of Arbitration and fees of the Arbitrator(s)
1) The concerned parties shall bear the arbitration cost as per section 31 (A) of The
Arbitration Act. The cost shall inter-alia include fees of the Arbitrator. Further, the
fees payable to the Arbitrator shall be governed by instructions issued on the subject
by the Procuring Entity and/ or the Government from time to time, in line with the
Arbitration and Conciliation Act, irrespective of the fact whether the Arbitrator is
appointed by the Procuring Entity or the Government under this clause or by any
court of law unless directed explicitly by Hon'ble court otherwise on the matter. A
sole arbitrator shall be entitled to a 25% extra fee over such a prescribed fee.
2) The arbitrator shall be entitled to a 50 per cent extra fee if the award is made within
6 months as per provisions in section 29(A) (2) of The Arbitration Act. The Arbitrator
shall also be entitled to this extra fee in cases where the Fast Track Procedure in
section 29 (B) of The Arbitration Act is followed.
Defaults, Breaches, Termination, and closure of Contract
12.1. Termination due to Breach, Default, and Insolvency
12.1.1Defaults and Breach of Contract
In case the Consultant undergoes insolvency or receivership, neglects or defaults or
expresses inability or disinclination to honour his obligations relating to the performance of
the contract or ethical standards or any other obligation that substantively affects the
Procuring Entity’s rights and benefits under the contract, it shall be treated as a breach
of contract. Such defaults could include inter-alia:
1) Default in Performance and Obligations: if the Consultant fails to deliver any
or all of the Services or fails to perform any other contractual obligations (including
Code of Integrity or obligation to maintain eligibility and evaluation criteria based
on which contract was awarded) within the period stipulated in the contract or
within any extension thereof granted by the Procuring Entity. In the case of a Joint
Venture/ Consortium, If the performance of any JV/C member is persistently un-
satisfactory by the Procuring Entity in respect of the responsibilities assigned to him
as per the JV agreement, which is part of this Contract. The lapse/ deficiencies in
services as mentioned in ToR shall be treated as default in performance and
Obligations.
2) Insolvency: If the Consultant being an individual or if a firm, any partner thereof,
shall at any time be adjudged insolvent or shall have a receiving order or order for
the administration of his estate made against him or shall take any proceeding for
composition under any Insolvency Act for the time being in force or make any
conveyance or assignment of his effects or enter into any assignment or composition
with his creditors or suspend payment or if the firm be dissolved under the
Partnership Act, or
943) Liquidation: if the Consultant is a company being wound up voluntarily, or by order
of a Court or a Receiver, Liquidator or Manager on behalf of the Debenture-holders
is appointed, or circumstances shall have arisen which entitle the Court or
Debenture-holders to appoint a Receiver, Liquidator or Manager
12.1.2 Notice for Default:
As soon as a breach of contract is noticed, a show-cause ‘Notice of Default’ shall be
issued to the Consultant, giving two weeks' notice, reserving the right to invoke
contractual remedies. After such a show-cause notice, all payments to the Consultant
would be suspended as per GCC clause 10.6 above to safeguard needed recoveries
due to invoking contractual remedies.
12.1.3 Remedies for Breaches/ Default
In the event of an unsatisfactory resolution of ‘Notice of Default’ within two weeks of its
issue as per the sub-clause above, the Procuring Entity, if so decided, shall
1) take one; or more of the following contractual remedies.
a) Recover liquidated damages and invoke a denial clause for delays.
b) In the case of JV/C, Procuring Entity may call upon the Lead Member to assign
the work of the defaulting member to any other equally competent party
acceptable to the Procuring Entity.
c) Temporarily withhold payments due to the Consultant till recoveries due to
invocation of other contractual remedies are complete.
d) Call back any loaned property or payment advances with a levy of interest at
the prevailing rate (MIBID - Mumbai Interbank Proposal Rate).
e) Encash and/ or Forfeit performance or other contractual securities.
f) Prefer claims against the insurance, if any.
g) Terminate the Contract for default, fully or partially, including its right for Risk-
and-Cost Procurement as per the following sub-clause.
h) Initiate proceedings in a court of law for the transgression of a law, tort, and
loss not addressable by the other remedies above.
2) By written Notice of Termination for Default sent to the Consultant, terminate the
contract in whole or in part, without compensation to the Consultant.
a) Such termination shall not prejudice or affect the rights and remedies, including
under the sub-clause below, which have accrued and/ or may accrue to the
Procuring Entity after that.
b) Unless otherwise instructed by the Procuring Entity, the Consultant shall
continue to perform the contract to the extent not terminated.
c) All Defect Liability obligations, if any, shall survive despite the termination.
3) Risk and Cost Procurement: In addition to termination for default, the Procuring
Entity shall be entitled, and it shall be lawful on his part, to procure Services similar
to those terminated, with such terms and conditions and in such manner as it deems
fit at the “Risk and Cost” of the Consultant. Such Risk and Cost Procurement mustbe contracted within nine months from the breach of contract. The Consultant shall
be liable for any loss which the Procuring Entity may sustain on that account provided
the procurement, or, if there is an agreement to procure, such agreement is made.
The Consultant shall not be entitled to any gain on such procurement, and the
manner and method of such procurement shall be at the discretion of the Procuring
Entity. It shall not be necessary for the Procuring Entity to notify the Consultant of
such procurement. It shall, however, be at the discretion of the Procuring Entity to
collect or not the security deposit from the firm/ firms on whom the contract is placed
at the risk and cost of the defaulted firm.
12.1.4 Limitation of Liability
Except in cases of criminal negligence or wilful misconduct, the aggregate liability of
the Consultant to the Procuring Entity, whether under the contract, in tort or otherwise,
shall not exceed the total Contract Price, provided that this limitation shall not apply to
the cost of repairing or replacing defective equipment, or to any obligation of the
Consultant to indemnify the Procuring Entity concerning IPR infringement.
12.2. Termination for Default/ Convenience of Procuring Entity or Frustration of
Contract
12.2.1 Notice for Determination of Contract
The Procuring Entity reserves the right to terminate the contract, in whole or in
part, for its (the Procuring Entity’s) convenience or frustration of Contract as per
the sub-clause below, by serving written ‘Notice for Determination of Contract’ on
the Consultant at any time during the currency of the contract. The notice shall
specify that the termination is for the Procuring Entity's convenience or the
contract's frustration. The notice shall also indicate inter-alia, the extent to which
the Consultant’s performance under the contract is terminated, and the date
from which such termination shall become effective.
Such termination shall not prejudice or affect the rights and remedies accrued
and/ or shall accrue after that to the Parties.
Unless otherwise instructed by the Procuring Entity, the Consultant shall continue
to perform the contract to the extent not terminated.
All Defect Liability obligations, if any, shall survive despite the termination.
The Services and incidental goods/ works that can be delivered or performed
within thirty days after the Consultant’s receipt of the notice of termination shall be
accepted by the Procuring Entity as per the contract terms. For the remaining
Services and incidental goods/ works, the Procuring Entity may decide:
a) To get any portion of the balance completed and delivered at the contract
terms, conditions, and prices; and/ or
b) To cancel the remaining portion of the Services and incidental goods/ works
and compensate the Consultant by paying an agreed amount for the cost
96incurred by the Consultant, if any, towards the remaining portion of the
Services and incidental goods/ works.
12.2.2 Frustration of Contract
1) Notice of Frustration Event: Upon a supervening cause occurring after the
effective date of the contract, including a change in law, beyond the control of either
party, whether as a result of the Force Majeure clause (GCC 9.6) or within the scope
of section 56 of the Indian Contract Act, 1872, that makes it impossible to perform
the contract within a reasonable timeframe, the affected party shall give a ‘Notice
of Frustration Event’ to the other party giving justification. The parties shall use
reasonable efforts to agree to amend the contract as necessary to complete its
performance. However, if the parties cannot reach a mutual agreement within 60
days of the initial notice, the Procuring Entity shall issue a ‘Notice for Determining
the contract’ and terminate the contract due to its frustration, as in the sub-clause
above.
2) However, the following shall not be considered as such a supervening cause
a) Lack of commercial feasibility or viability or profitability or availability of
funds
b) if caused by either party's breach of obligations under this Contract or failure
to act in good faith or use commercially reasonable due diligence to prevent
such an event.
12.3. Closure of Contract
12.3.1 Unless terminated earlier under GCC clauses 12.1 and 12.2 above, this Contract
shall expire:
At the end of such a period after the Effective Date as specified in
the Contract.
Upon successful performance of all obligations by both parties,
including completion of Defect Liability obligations and final payment
termination and settlements after that, if any, as per GCC clause 12.1 or
12.2 above.
12.3.2 Cessation of Rights and Obligations
Upon termination of this Contract under Clauses GCC 12.1 or 12.2 hereof or expiration
of this Contract under GCC clause 12.3.1, all rights and obligations of the Parties
hereunder shall cease, except (i) such rights and obligations as may have accrued on
the date of termination or expiration, (ii) the obligation of confidentiality outlined in
GCC clause 5.7. (iii) the Consultant’s obligation to permit inspection, copying and
auditing of their accounts and records outlined in GCC clause 5 and to cooperate and
assist in any inspection or investigation, and (iv) any right a Party may have under the
Applicable Law.12.3.3 Cessation of Services
Upon termination of this Contract by notice under Clauses GCC 12.1 or GCC 12.2,
the Consultant shall, immediately upon dispatch or receipt of such notice, take all
necessary steps to bring the Services to a close in a prompt and orderly manner and
shall make every reasonable effort to keep expenditures for this purpose to a minimum.
Concerning documents prepared by the Consultant and equipment and materials
furnished by the Procuring Entity, the Consultant shall proceed as provided by Clauses
GCC 9.4 and GCC 5.14.
12.3.4 Payments upon Termination
Upon termination of this Contract, the Procuring Entity shall make the following
payments to the Consultant:
(a) payment for Services satisfactorily performed before the effective date of
termination; and
(b) in the case of termination under GCC clause 12.2, reimbursement of any
reasonable cost incidental to the prompt and orderly termination of this Contract,
including the cost of the return travel of the Experts.
Code of Public Procurement; Misdemeanours and
Integrity Penalties
13.1. Code of
Integrity
98Procuring authorities as well as Consultants, suppliers, contractors, and consultants -
should observe the highest standard of ethics and should not indulge in following
prohibited practices, either directly or indirectly, at any stage during the Procurement
Process or during the execution of resultant contracts:
1) “Corrupt practice” - making an offer, solicitation or acceptance of a bribe, reward or
gift or any material benefit in exchange for an unfair advantage in the
Procurement Process or to otherwise influence the Procurement Process;
2) “Fraudulent practice” - any omission or misrepresentation that may mislead or
attempt to mislead so that financial or other benefits may be obtained or an
obligation avoided. Such practices include a false declaration or false information
for participation in a Procurement Process or to secure a Contract, or in the execution
of the contract;
3) “Anti-competitive practice” - any collusion, Proposal-rigging or anti-competitive
arrangement, or any other practice coming under the purview of the Competition
Act, 2002, between two or more Consultants, with or without the knowledge of the
Procuring Entity, that may impair the transparency, fairness, and the progress of the
Procurement Process or to establish Proposal prices at artificial, non-competitive
levels;
4) “Coercive practice” - harming or threatening to harm persons or their property to
influence their participation in the Procurement Process or affect the execution of a
contract;
5) “Conflict of interest” –participation by a bidding firm or any of its affiliates who are
either involved in the Consultancy Contract to which this procurement is linked; if
they are part of more than one Proposal in the procurement; or if their personnel
have a relationship or financial or business transactions with any official of procuring
entity who are directly or indirectly related to tender or execution process of contract;
or improper use of information obtained by the (prospective) Consultant from the
Procuring Entity with an intent to gain unfair advantage in the Procurement Process
or for personal gain;
6) “Obstructive practice” - materially impede procuring entity’s investigation into
allegations of one or more of the above-mentioned prohibited practices either by
deliberately destroying, falsifying, altering; or concealing evidence material to the
investigation; or by making false statements to investigators and/ or by coercive
practices mentioned above, to prevent it from disclosing its knowledge of matters
relevant to the investigation or from pursuing the investigation, or by impeding the
Procuring Entity’s rights of an audit or access to information;
13.2. Obligations for Proactive Disclosures:
1) Procuring authorities, Consultants, suppliers, contractors, and consultants are
obliged under this Code of Integrity to suo-moto proactively declare any violation of
the Code of Integrity (pre-existing or as and as soon as these arise at any stage) in
any Procurement Process or execution of the contract. Failure to do so shall amount toa violation of this code of integrity.
2) Any Consultant must declare, whether asked or not in a Proposal-document, any
previous transgressions of such code of integrity during the last three years or of
being under any category of debarment by the Central Government or the Ministry/
Department of the Procuring Organisation from participation in Procurement
Processes. Failure to do so shall amount to a violation of this code of integrity.
13.3. Misdemeanours
The following shall be considered misdemeanours - if a Consultant, either directly or
indirectly, at any stage during the Procurement Process or during the execution of
resultant contracts:
1) Commits any of the following misdemeanours:
(a) Violates the code of Integrity mentioned in GCC-clause 13.1 or the Integrity
Pact if included in the Tender/ Contract;
(b) Any other misdemeanour, e.g., supply of sub-standard quality of material/
services/ work, non-performance or abandonment of contract, or violations of
Bid/ performance Security conditions.
2) Commits any of the following misdemeanours:
(a) Has been convicted of an offence:
i) Under the Prevention of Corruption Act, 1988; or
ii) The Indian Penal Code or any other law is in force for causing any loss
of life or property or causing a threat to public health as part of the
execution of a public procurement contract.
(b) It is determined by the Government of India to have doubtful loyalty to the
country or national security considerations.
(c) Employs a government servant who has been dismissed or removed on account
of corruption or employs a non-official convicted for an offence involving
corruption or abetment of such an offence in a position where he could corrupt
government servants or employs a government officer within one year (or any
other period prescribed by the relevant authority) of his retirement, who has
had business dealings with him in an official capacity before retirement.
13.4. Penalties for Misdemeanours
Without prejudice to and in addition to the rights of the Procuring Entity to other
remedies as per the Tender-documents or the contract, If the Procuring Entity concludes
that a (prospective) Consultant directly or through an agent has committed a
misdemeanour in competing for the tender or in executing a contract, the Procuring
Entity shall be entitled, and it shall be lawful on his part to take appropriate measures,
including the following:
13.4.1 if his Proposals are under consideration in any procurement
1) Enforcement of Bid Securing Declaration in lieu of forfeiture or encashment of Bid
Security.
1002) calling off any pre-contract negotiations and;
3) rejection and exclusion of Consultants from the Procurement Process
13.4.2if a contract has already been awarded
1) Termination of Contract for Default and availing all remedies prescribed
thereunder;
2) Encashment and/ or Forfeiture of any contractual security or bond relating to the
procurement;
3) Recovery of payments, including advance payments, if any, made by the Procuring
Entity along with interest thereon at the prevailing rate (MIBID - Mumbai Interbank
Proposal Rate);
13.4.3Remedies in addition to the above:
In addition to the above penalties, the Procuring Entity shall be entitled, and it shall
be lawful on his part, to:
1) File information against Consultant or any of its successors with the Competition
Commission of India for further processing in case of anti-competitive practices;
2) Initiate proceedings in a court of law against Consultant or any of its successors
under the Prevention of Corruption Act, 1988 or the Indian Penal Code or any other
law for transgression not addressable by other remedies listed in this sub-clause.
3) Remove the Consultant or any of its successors from the list of registered suppliers
for a period not exceeding two years. Suppliers removed from the list of registered
vendors or their related entities may be allowed to apply afresh for registration after
the expiry of the removal period.
4) Initiate suitable disciplinary or criminal proceedings against any individual or staff
found responsible.
5) Debar, a Consultant, from participation in future procurements without prejudice to
Procuring Entity’s legal rights and remedies. Debarment shall automatically extend to
all the allied firms of the debarred firm. In the case of a Joint Venture/ consortium, all
its members shall also stand similarly debarred:
A Ministry/ Department (or any of its CPSUs, attached offices, autonomous
bodies) may debar a Consultant or any of its successors from participating in any
Procurement Process undertaken by all its procuring entities for a period not
exceeding two years commencing from the date of debarment for misdemeanours
listed in GCC sub- clause 13.3 -1) above. The Ministry/Department shall maintain
such a list which shall also be displayed on their website.
Central Government (Department of Expenditure (DoE), Ministry of Finance) may
debar a Consultant or any of its successors from participating in any Procurement
Process undertaken by all its procuring entities for a period not exceeding three
years commencing from the date of debarment for misdemeanours listed in GCC
sub-clause 13.3 -above. DoE shall maintain such a list which shall be displayed on
Central Public Procurement Portal (CPPP).Section V: Special Conditions of Contract (SCC)
Document No. RFP No./ xxxx; Tender Title: Consultancy Services
(Ref ITC-clause 1.4)
{Note for Procuring Entity: Text in grey italics font within square bracket [e.g., Mention
…] are just suggestions/ directions and must be replaced by applicable text - remove
brackets and convert the font to regular and black. Delete the rows not required. Clauses
other than those mentioned below may also be mentioned if these need to be changed}
Note for Consultants: Following Special Conditions of Contract (SCC) shall apply for this
procurement. These Special Conditions shall modify/ substitute/ supplement the
corresponding (GCC) clauses as indicated below. Whenever there is any conflict
between the provision in the GCC and that in the SCC, the provision in the SCC shall
prevail.
GCC Topic To be read as
Clause No.
GCC 1, 2, 3 and 4: General, The Contract, Governing Laws and Jurisdiction,
Communications
1.1, 1.2, General No change
1.3, 1.4
2.1 Language of Contract English
3.1 Governing Laws and The courts in Delhi shall have Jurisdiction
jurisdiction
4.1, 4.3 Communications and 4.1 Notice will be deemed to be effective as follows:
notices
(a) in the case of personal delivery or registered mail,
on delivery;
(b) in the case of telexes, 24 hours following confirmed
transmission;
(c) in the case of telegrams, 24 hours following
confirmed transmission; and
(d) in the case of facsimiles, 24 hours following
confirmed transmission.
4.3 The addresses are:
Client:- Address of Employer
Attention: - …………
Telex: - …………..
Facsimile: - ………………
Consultant:- Address of consultant
Attention:-
102Cable Address: - ……………….
Telex: - …………………
Facsimile:- ……………
( Note:- Fill in the Blanks)
4.2 Persons SigningThe Authorised Representative are:
Communications
For the Client: ……………………
For the Consultants: ……………..
GCC 5 and 6: Consultant’s and Procuring Entity’s Obligations
5.7. Confidentiality and SecrecyN o change
of information
5.7.1 Property Rights No change
5.8 Performance Bond/ The performance security shall be 10% of
Security contract Price
6.1, 6.2, Facilities, Utilities to beNil
6.3 provided by Procuring
EntityGCC 7: Scope of Services and Performance Standards
7.1 Scope of Services As defined in TOR
7.1 5(c ) Lapse/ deficiencies in As per Annexure-1 of SCC
services
7.2 Eligible Services As per the Extant Guidelines of Govt of
India from time to time
GCC 8: Deployment of Resources
8.2.2 Key Personnel No Replacement of Team Leader shall be
allowed. In case of extension of bid validity,
the consultants shall submit the
replacement CV along with Extension
request.
ln addition, casual [eave for 12 days shall
be permitted in a year to each Key
Personnel/ Sub-Professional with prior
intimation to the Authority. Out of this, a
maximum of 3 CLs can be availed either
separately or together in a quarter and the
period of the CLs would be counted as Key
Personnel I Sub Professional being on duty.
GCC 9: Delivery of Services and Delays
9.1 Works plan No Change
9.2 Commencement ofThe time period shall be one month or such
Services other time period as the Parties may agree in
writing.
GCC 10: Prices and Payments
10.1.3 Variations No change
10.2 Taxes and Duties No change
10.3 Terms and Mode ofPayment shall be released as per rates
Payment quoted in Appendix C1 Breakup of Local
currency costs. However, proof of
remuneration paid to professional staffs in
previous month submitted alongwith shall
be current month's bill. The quoted
remuneration to professional staff shall be
paid by the Authority's Engineer directly
into their respective ban account . The
overhead charges shall be paid at the rate
as mentioned in Appendix C-1 "Financialproposal submission form
10.5.2 Payment to Consultants An advance payment of 10% of the contract
price in proportion to the quoted Indian currency
(INR) in the bid shall be made within 60 days
after receipt and verification of advance payment
bank guarantee. The advance payment along
with interest will be set off by the Client in equal
instalments against the statements for the first
12 months of the Service until the advance
payment has been fully set off. The advance
payment shall be in Indian Rupee.
GCC 11 Resolution of Disputes
11.2 Excepted Matters No change
11.5 Arbitration
GCC 12 Defaults, Breaches, Termination and Closure of Contract
12.3.1 Period of Contract The time period shall be ….. months ( ….
construction period of the project and
….months for Maintenance period as per
EPC Contract ). In case construction period
of EPC project is extended by more than 1
year, no escalation shall be paid to the
Authority Engineer. Any period within
which a Party shall, pursuant to this
Contract, complete any action or task,
shall be extended for a period equal to
the time during which Such Party was
unable to perform such action as a
result of Force Majeure.
Extension of Time for providing
Services of the Authority’s
Engineer may be extended
concurrently with the Extension of
Time granted, if any, to the EPC
Contractor for the project, subject
to satisfactory performance of the
Authority’s Engineer and limited to
original period of consultancy
services.
12.1.4-7) Risk and Cost Procurement No changeAnnexure-I
Type of lapses/ deficiencies in services and action to be taken against
consultant/firm and key personnel engaged during construction &
Maintenance
S. Type of deficiencies Action to be taken against consultant
No. engaged during construction &
Maintenance
Key Personnel Firm
1 (a) Failure to detect design/quality For first three, key i) For first threedeficiency in Non-key) Components* personnel may be instances, to be kept
1 (b) Failure to issue follow-up notices _to kept on “ watch list”. on watch list.
contractor/concessionaire for delays in Thereafter the ii. Thereafter, a
closure off/ NCRs, delays in furnishing concerned key monetary penalty of
detail of time & cost claims/COS/ Personnel & Team 1% of the
revised work programmes/work Leader to be consultancy fee (the
methodologies, etc. removed from the aggregate of such
1(c) Delay in submission of improper project and debarred penalties in a
MPRs, improper review of up to 6 months contract would not
methodologies, temporary works, QA exceed the
plan/manual, O& M plan/ Manual etc performance
Guarantee amount
and/or declaring the
consultant as Non-
Performer upto 6
months or till
rectification of
deficiencies and
taking adequate
measures not to
repeat such
instances in future
whichever is earlier
2 (a) Failure to detect design/quality The concerned key Declaring the
deficiency in Key Component **not personnel & Team Consultant as Non-
having substantial cost (below 1% of leader to be removed Performer up to 1
civil work (cost) and /or time implication from the project and year or till
(below 5% or project completion debarred up to 1 rectification of
periods year Deficiencies and
(b) Failure to detect deficiency in quantity taking adequate
executed vis- â-is design no( having measures not to
substantial fnancal implication (below repeat such
1% of civil work cost) Instances in future,
(c) Failure to conduct/witness tests as whichever is earlier.
prescribed in the consultancy contract
agreement
(d) Delay in processing EOT/COS
proposals, inaccurate assessment of
COS proposals, not issuing MCRs,
delays/improper review of
designs/drawings/work programme or
failure to submit
Completion/Provisional Completion
Certification as prescribed in contract
3( a) Failure to detect deficiency in quantity The concerned key In addition to
executed vis- à-vis design having personnel & team Rectification of
substantial financial implication {1% of leader to be removed deficiencies and
civil work cost or more) from the project and taking adequate
(b) Failure to detect design/quality debarred up to 2 measures not to
deficiency in Key Component having years repeat such
substantial cost (1% of civil work cost Instances in future,
or code) and/or time implication (5o/ of the consultant to be
project completion period or more) debarred up to 2
(c ) Failure to detect deficiency/not years.
reviewing design (including temporaryworks) and construction (including
methodology) of structural components
of flyover/bridges/ underpasses/
overpasses/ROB/RUB etc.
(d) Failure to propose action (like cure
period notice, levy of damages, etc.)
on contractor/concessionaire as per
contract agreement for their
default/poor progress having material
adverse effect on the project
implementation in terms of cost (1% of
civil work cost or more) and/ time (50/
of project completion period of more).
(e) Improper/wrong interpretation of
provision in contract agreement; or
wrong certification of payment/COS
value/cost & time claims; or poor
performance of services leading to cost
(1% of civil work cost) and/o‹ time (5%
of project completion period) claims
against MoRTH or its executing
agencies awarded by
DRB/CCIE/Arbitration/Court.
Note ‘” Key Components are specified as under:
i) Foundation, sub-structure and super-structure of flyovers, road over
bridges, road under bridges, vehicular under passes, vehicular over
passes, major bridges, minor bridges, etc.
ii) Tunnels
iii) Expansion joints and bear1ngs
iv) RE walls/ retaining walls
v) The crust layers of flexible pavement
vi) The crust layers of rigid pavement
vii) Embankment and slope protection
viii) Issues affecting road safety
ix) Any other work endangering/impacting/stability/ reliability/durability/
performance of pavement/structures
“The items not covered in above list shall be in the category of Non-key
Components.
# Excluding the delay solely attributable to the contractor beyond stipulated
time.Section VI: Terms of Reference
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services (Ref ITC-clause
1.4)
Note for Consultants: Regarding this Section, Consultants must fill following forms:
a) Form T-3: Comments and Suggestions on Terms of Reference, Counterpart Staff, and
Inputs to be Provided by the Procuring Entity
b) Form T-4: Description of Approach, Methodology and Work Plan in Responding to the
Terms of Reference
c) Form T-5: Work Schedule and Planning for DeliverablesTerm of Reference
Note: The term “Agreement” and clauses thereof refer to the EPC Agreement dated-----
- entered between Authority and --------(the Contractor) for the work of from
km---- to ---- of NH No.------- in the State of ------------ on Engineering, Procurement and
Construction (EPC) basis].
1. Scope
1.1 These Terms of Reference (the “TOR”) for the Authority’s Engineer are being
specified pursuant to the EPC Agreement dated........... (the “Agreement”), which
has been entered into between the Authority and (the “Contractor”) for [Two-
Laning] of
the **** section (km ** to km**) of National Highway No. ** in the State
of *** on Engineering, Procurement, Construction (EPC) basis, and a copy of
which is annexed hereto and marked as Annex-A to form part of this TOR.
1.2 The TOR shall apply to Development, construction and maintenance period of the
Project Highway.
2 Definitions and interpretation
2.1 The words and expressions beginning with or in capital letters and not defined herein
but defined in the Agreement shall have, unless repugnant to the context, the
meaning respectively assigned to them in the Agreement.
2.2 References to Articles, Clauses and Schedules in this TOR shall, except where the
context otherwise requires, be deemed to be reference to the Articles, Clauses
and Schedules of the Agreement, and references to Paragraphs shall be deemed
to be references to Paragraphs of this TOR.
2.3 The rules of interpretation stated in Clauses 1.2, 1.3 and 1.4 of the Agreement shall
apply, mutatis mutandis, to this TOR.
3 General
3.1 The Authority’s Engineer shall discharge its duties in a fair, impartial and efficient
manner, consistent with the highest standards of professional integrity and
Good Industry Practice.
3.2 The Authority’s Engineer shall perform the duties and exercise the authority in
accordance with the provisions of this Agreement, but subject to obtaining prior
written approval of the Authority before determining.
(a) any Time Extension.
(b) Any additional cost to be paid by the Authority to the Contractor;
(c) The Termination Payment; or
(d) Any other matter which is not specified in (a), (b) or (c) above and which createsan obligation or liability on either Party for a sum exceeding Rs. 5,000,000 (Rs.
Fifty lakh.)
3.3 The Authority’s Engineer shall submit regular periodic reports, once every month, to
the Authority in respect of its duties and functions under this Agreement. Such
reports shall be submitted by the Authority’s Engineer within 10 (ten) days of the
beginning of every month.
3.4 The Authority’s Engineer shall inform the Contractor of any delegation of its duties
and responsibilities to its suitably qualified and experienced personnel; provided,
however, that it shall not delegate the authority to refer any matter for the
Authority’s prior approval in accordance with the provisions of Clause 18.2 EPC
Agreement.
3.5 The Authority’s Engineer shall aid and advise the Authority on any proposal for
Change of Scope under Article 13.
3.6 In the event of any disagreement between the Parties regarding the meaning, scope
and nature of Good Industry Practice, as set forth in any provision of the Agreement,
the Authority’s Engineer shall specify such meaning, scope and nature by issuing a
reasoned written statement relying on good industry practice and authentic
literature.
3.7 Development/ Design Period
3.7.1 Authority will engage Authority Engineer at least 3 months before appointed
date of the project. During design and development period of project or
immediately after mobilization at site, the Authority Engineer shall review the
Schedule-A, Schedule-B, Schedule-C, Schedule-D and Schedule-H of the
contract agreement and DPR prepared by the Authority as per site conditions
and project Requirements and submit a comprehensive review report,
indicating suggested modification in Scope of project.
3.7.2 Authority Engineer will witness traffic census, Geotechnical Investigation and
all other investigations being carried out by the contractor and certify the
correctness of the data and maintain the details in MPR.
4. Role and responsibility of Officers of the Authority
The officer in-charge of the Authority (e.g. PD/ RO/ CGM/ Member in the case
of NHAI; RO/CE/ADG in the case of MoRTH projects executed through the
State PWDs; and PD/ED/Director in the case of NHIDCL) is responsible for
the overall supervision and monitoring of the execution of project as the
representative of the owner of the project. The Authority's Engineer is
appointed to assist the Authority for carrying out the functions as detailed
under clause 18.2 of the EPC Agreement. As such, an officer of the Authority
is vested with all such powers and responsibilities as are enjoined upon the
Authority's Engineer and is fully competent to issue any instructions for
proper monitoring and supervision of the project, either by himself or throughthe Authority's Engineer. Instructions issued by the concerned officer of the
Authority shall have the same effect as that of the Authority's Engineer in
terms of this Agreement. Wherever such concerned officer issues any
instructions or notice to the Contractor, he shall endorse a copy thereof to
the Authority's Engineer.
5 Construction Period
5.1 During the Construction Period, the Authority’s Engineer shall review and approve
the Drawings furnished by the Contractor along with supporting data, including the
geo- technical and hydrological investigations, characteristics of materials from
borrow areas and quarry sites, topographical surveys, and the recommendations of
the Safety Consultant in accordance with the provisions of Clause 10.1.6 of EPC
Agreement. The Authority’s Engineer shall complete such review and approve and
send its observations to the Authority and the Contractor within 15 (fifteen) days of
receipt of such Drawings; provided, however that in case of a Major Bridge or
Structure, the aforesaid period of 15 (fifteen) days may be extended upto 30 (thirty)
days. In particular, such comments shall specify the conformity or otherwise of such
Drawings with the Scope of the Project and Specifications and Standards.
5.2 The Authority’s Engineer shall review and approve any revised Drawings sent to
it by the Contractor and furnish its comments within 10 (ten) days of receiving
such Drawings. The review/approval of drawing should be authenticated by
Authority’s Engineer.
5.3 Verification of Material and its Sources by Authority Engineer:-
5.3.1 The Authority Engineer shall ensure that all materials used by the contractor
are procured exclusively from sources approved by the Engineer in
accordance with the contract specifications and standards.
5.3.2 The Authority Engineer shall verify and document the source of materials
proposed by the contractor during the approval process and maintain a record
of all approved material sources, including relevant test reports, certifications,
and compliance documents. The Authority Engineer shall communicate any
changes or updates regarding material source approvals to the contractor in
writing.
5.3.3 The Authority Engineer shall conduct periodic inspections to verify that the
materials delivered to the site match the approved source. Authority Engineer
shall ensure that the contractor provides evidence of procurement from the
approved source (e.g., invoices, transport receipts, or certifications).
5.3.4 In the event of non-compliance, the Authority Engineer shall immediately
notify the contractor in writing and Direct the removal of non-compliant
materials from the site at the contractor's cost. He shall ensure that corrective
actions are taken before work proceeds further.
5.3.5 In the Monthly Report the Authority Engineer shall submit Compliance status
of materials used, any issues or deviations identified, along with corrective
measures taken alongwith supporting documentation such as test reports,
certificates, and inspection records.5.3.6 The Authority Engineer shall be held accountable for any lapses in ensuring
material compliance that result in deviations from approved standards or
specifications and the suitable action under the agreement shall be taken
against the Authority Engineer.
5.4 Quality Assurance Manual and Plan forms the basis of quality of the work. It is
therefore to be ensured that the Quality Assurance Plan prepared by the
contractor be checked and submitted by Authority Engineer to Authority within 15
days time period of its submission by contractor. The Authority shall approve the
QAP within 15 days from date of submission by AE, Thus, the Authority’s Engineer
shall ensure that contents of Quality Assurance Plan is as per requirements of IRC
SP 112 and ISO : 9001. The copy of the approved Quality Assurance Plan will be
sent by Authority’s Engineer to the contractor and the Authority. The Authority’s
Engineer will after review and submit to the Authority the methodology within 10 days
of its receipt from the contractor for approval of Authority. The Authority shall
approve the methodology within 10 days of receiving from Authority Engineer. The
Authority Engineer will ensure that the methodology of the different components of
the work are prepared keeping in view the specifications & Standards and machinery
deployed by the contractor. The Authority Engineer may also offer their comments
for modifying/ improving either of the document. After receiving the corrected
document, the Authority Engineer shall review and formally submit these documents
to Authority for approval of the same
5.5 The Authority’s Engineer shall grant written approval to the Contractor, where
necessary, for interruption and diversion of the flow of traffic in the existing lane(s)
of the Project Highway for purposes of maintenance during the Construction Period
in accordance with the provisions of Clause 10.4 EPC Agreement.
5.6 The Authority Engineer shall approve the CV of Project Manager/ Dy. Project
Manager/ other key personnel deployed by the contractor at site. If Authority
Engineer, observed that qualified Key personnel have not been deployed by
contractor at site, he will submit a report in this regard to the Authority.
5.7 The Authority’s Engineer shall review the monthly progress report furnished by the
Contractor and send its comments thereon to the Authority and the contractor within
7 (seven) days of receipt of such report.
5.8 On a daily basis, the concerned key personnel of Authority Engineer shall inspect
the Construction Works. Following activities need to be undertaken during the visits.
• Review of construction including progress, quality and safety of construction
• Inspection of defects and deficiencies in construction works
• Witnessing quality inspection tests at labs established by Concessionaire
on a sample basis
Review of quality of work shall be done in reference to Quality Assurance
Plan (QAP)/Manual and ISO 9001:2008, IRC: SP: 47-1998 and IRC: SP: 57-
2000 for road bridges and roads respectively. The Authority’s Engineer also
needs to capture following documents and send to <Agency> field office via
email on a daily basis• Scanned copy of filled RFI (Request for Inspection) form including
commentary on ‘Satisfactory/Unsatisfactory’ nature of work completed by
Concessionaire
• Daily inspection report Proforma as provided in Annexure I
• Readings of quality inspection tests witnessed by the Consultant
• Minimum 6 high resolution photographs supporting the remarks made by
the Authority’s Engineer in RFI form
Team Leader will be responsible for sending daily emails to <Agency> office
5.9 On a monthly basis, the Authority Engineer shall prepare a Monthly Inspection
Report in accordance with the format prescribed in Annexure V setting forth an
overview of the status, progress, quality and safety of construction, including the
work methodology adopted, the materials used and their sources, and conformity of
Construction Works with the Scope of the Project and the Specifications and
Standards. In a separate section of the Inspection Report, the Authority Engineer
shall describe in reasonable detail the lapses, defects or deficiencies observed by it
in the construction of the Project Highway. The Authority Engineer shall send a copy
of its Inspection Report to the Authority and the Concessionaire latest by 7th of every
month. Key sections of the Monthly Progress Report are as follows.
S No. Section Sub-Sections
1.1 Construction progress in current month
1.2 Summary of strip plan
1 Executive Summary
1.3 Detailed strip plan
1.4 Current issues and recommended actions by AE
2.1 Salient Features of the Project
2.2 Project Milestones
2 Project Overview
2.3 Location Map
2.4 Key Plan
Critical issues and Action 3.1 Pending issues and action log
3
log 3.2 Obligations as per contract
4 Physical Progress 4.1 Detailed physical progress by component
5.1 LA summary
5.2 LA detail by CALA
Land Acquisition and 5.3 LA detail by village
5
Clearances 5.4 Manpower with each CALA
5.5 Clearances summary
5.6 Status of utility shifting
6 Change of Scope 6.1 Status of pending COS proposals
7 Mobilization of Resources 7.1 Resource mobilization by contractor/ concessionaire
8.1 Pen picture- Escrow
8 Financial Progress Details
8.2 Escrow details
Summary of quality control 9.1 Tests witnessed by IE/AE
9
tests 9.2 Tests conducted by IE/AE
Monitoring of maintenance 10.1 Critical issues and action log
10 obligations during 10.2 Cumulative defects and deficiencies
construction phase 10.3 Status of damages
11.1 Pen picture on safety features at construction site11.2 Accident report
11 Safety features
Annex 1: Detailed list of physical components as per
12 Annexures Schedule G
Annex 2 onwards: Additional details provided by AE
5.9.1 If at any time during the Construction Period, the Authority Engineer determines
that the Concessionaire has not made adequate arrangements for the safety of
workers and Users in the zone of construction or that any work is being carried out in
a manner that threatens the safety of the workers and the Users, it shall make a
recommendation to the Authority forthwith, identifying the whole or part of the
Construction Works that should be suspended for ensuring safety in respect thereof
5.9.2 The Authority Engineer shall prepare a Milestone Report setting forth an
overview of the status, progress, quality and safety of construction, including the
status of the milestone, the available resources and details of lack of resources, to
achieve the milestone, if any. In a separate section of the Milestone Report, the
Authority Engineer shall describe in reasonable detail the lapses, defects or
deficiencies observed by it in the achievement of the Project Highway. The
Authority Engineer shall send a copy of its Milestone Report to the Authority within
15 days of schedule Milestone Date. The Millstone report shall be approved by the
Authority before making milestone payment.
5.10 The Authority’s Engineer shall conduct the pre-construction review of
manufacturer’s reports and standard samples of manufactured Materials, and such
other Materials as the Authority’s Engineer may require.
5.11 For determining that the Works conform to Specifications and Standards, the
Authority’s Engineer shall require the Contractor to carry out, or cause to be
carried out, tests at such time and frequency and in such manner as specified in
the Agreement and in accordance with Good Industry Practice for quality
assurance. For purposes of this, the tests specified in the IRC Special
Publication-11 (Handbook of Quality Control for Construction of Roads and
Runways) and the Specifications for Road and Bridge Works issued by
MORT&H (the “Quality Control Manuals”) or any modifications/substitution
thereof shall be deemed to be tests conforming to Good Industry Practice for
quality assurance.
5.12 The Authority’s Engineer shall witness all the quality control tests and
calibrations of plants and equipment carried out by the contractor at its site
laboratory/ main laboratory/field/plants. Those include test for all material,
mixes, products etc. Authority Engineer shall also witness all test of
proprietary products like bearing in the manufacturer’s laboratory as
mandated in respective standards. Authority Engineer will also conduct
review of quality control documents in respect of factory manufactured
materials/ proprietary products etc as per IRC:SP: 112.
5.13 The timing and location of tests referred to in Paragraph 5.10, and the
criteria for acceptance/rejection of their results shall be determined by the
Authority’s Engineer in accordance with MoRTH specifications for road &
Bridge works and respective Indian Road CongressStandards/Guidelines/Manuals together with any other Indian/ International
Standards, the methodology proposed by him at the time of bid submission
referred thereto. Authority Engineer/Independent Auditors/ officers of Authority
may also undertake minimum 1% random tests as directed by the Authority, on
random sample basis at the locations to be decided by the Authority/Independent
Auditors/ officers of Authority. These random tests shall be in addition to, and
independent of, the tests that may be carried out by the Contractor for its own
quality assurance in accordance with Good Industry Practice. These random tests
shall be tested by the Authority Engineer in contractor’s laboratory or any third party
NABL accredited laboratory as directed by the Authority. The payments of these
test shall be made by the Authority separately if the result of these tests are as per
specifications/ guidelines. If random sample/ test result is not as per the standards/
specifications, the cost of such testing shall be paid by the Contractor The cost of
establishment of own laboratory or to carry out from NABH accredited
laboratory shall be incidental to the cost of AE and will be part of overheads
to be quoted by the consultant.
5.14 The Authority Engineer shall witness collection of the all test samples including
random samples collected by AE/Independent Auditors/ Authority officers from site
and geotagged location of the collected sample shall be mentioned on the sample/
records. The details of the sample collected, and its geotag location data shall be
uploaded on datalake or any other app developed by Authority for this purpose.
5.15 In the event that results of any tests conducted under Clause 11.10 establish any
Defects or deficiencies in the Works, the Authority’s Engineer shall require the
Contractor to carry out remedial measures.
5.16 The Authority’s Engineer may instruct the Contractor to execute any work which is
urgently required for the safety of the Project Highway, whether because of an
accident, unforeseeable event or otherwise; provided that in case of any work
required on account of a Force Majeure Event, the provisions of Clause 21.6 of EPC
Agreement shall apply.
5.17 In the event that the Contractor fails to achieve any of the Project Milestones, the
Authority’s Engineer shall undertake a review of the progress of construction and identify
potential delays, if any. If the Authority’s Engineer shall determine that completion of the
Project Highway is not feasible within the time specified in the Agreement, it shall require
the Contractor to indicte within 15 (fifteen) days the steps proposed to be take to expedite
progress, and the period within which the Project Completion Date shall be achieved.
Upon receipt of a report from the Contractor, the Authority’s Engineer shall review the
same and send its comments to the Authority and the Contractor forthwith.
5.18 The Authority’s Engineer shall obtain from the Contractor a copy of all the
Contractor’s quality control records and documents before the Completion
Certificate is issued pursuant to Clause 12.2 of EPC Agreement.
5.19 Authority’s Engineer may recommend to the Authority suspension of the whole or
part of the Works if the work threatens the safety of the Users and pedestrians.
After the Contractor has carried out remedial measure, the Authority’s Engineer
shall inspect such remedial measures forthwith and make a report to the Authority
recommending whether or not the suspension hereunder may be revoked.
5.20 In the event that the Contractor carries out any remedial measures to secure thesafety of suspended works and users, and requires the Authority’s Engineer to
inspect such works, the Authority’s Engineer shall inspect the suspended works
within 3 (three) days of receiving such notice, and make a report to the Authority
forthwith, recommending whether or not such suspension may be revoked by the
Authority.
5.21 The Authority’s Engineer shall carry out, or cause to be carried out, all the Tests
specified in Schedule-K and issue a Completion Certificate or Provisional Certificate
as the case may be. For carrying out is functions under this Paragraph 4.18 and all
matters incidental thereto, the Authority’s Engineer shall act under and in
accordance with the provisions of Article 12 and Schedule-K. The Authority’s
Engineer shall use following equipment in carrying out the tests.
S No Key metrics of Asset Equipment to be used
1 Surface defects of pavement Network Survey Vehicle (NSV)
2 Roughness of pavement Laser Profilometer
3 Strength of pavement Falling Weight Reflectometer (FWD)
4 Bridges Mobile Bridge Inspection Unit (MBIU)
5 Road signs and road markings Retro-reflectometer
6 Maintenance Period
6.1 The Authority’s Engineer shall aid and advise the Contractor in the preparation of
its monthly Maintenance Programme and for this purpose carry out a joint monthly
inspection with Contractor.
6.2 The Authority’s Engineer shall undertake regular inspections, at least once every
month to evaluate compliance with the Maintenance Requirements and submit a
Maintenance Inspection Report to the Authority and the Contractor.
6.3 Visual Inspection of project highway
6.3.1 The Authority Engineer shall carry out visual inspection of entire highway stretch as
per the frequency defined in the following table
Frequency
Nature of defect or deficiency of
inspection
ROADS
(a) Carriageway and paved shoulders
(i) Breach or blockade Daily
(ii) Pot holes Daily
(iii) Cracking Weekly
(iv) Rutting Weekly
(v) Bleeding/skidding Weekly
(vi) Ravelling/Stripping of bitumen surface Weekly
(vii) Damage to pavement edges Weekly
(viii
Removal of debris Daily
)
(b) Hard/earth shoulders, side slopes, drains and culverts(i) Variation by more than 2% in the prescribed slope of camber/cross fall Weekly
(ii) Edge drop at shoulders Weekly
(iii) Variation by more than 15% in the prescribed side (embankment) slopes Weekly
(iv) Rain cuts/gullies in slope Weekly
Damage to or silting of culverts and side drains during and immediately
(v) Weekly
preceding the rainy season
(vi) Desilting of drains in urban/semi-urban areas Daily
(c) Road side furniture including road signs and pavement marking
Damage to shape or position;
(i) Daily
poor visibility or loss of retro-reflectivity
(d) Street lighting and telecom (ATMS)
(i) Any major failure of the system Daily
(ii) Faults and minor failures Daily
(iii) Streetlight with Lux Meter Weekly
(e) Trees and plantation
Obstruction in a minimum head-room of 5 m above carriageway or
(i) Daily
obstruction in visibility of road signs
(ii) Deterioration in health of trees and bushes Weekly
(iii) Replacement of trees and bushes Weekly
(iv) Removal of vegetation affecting sight line and road structures Weekly
(f ) Rest areas/Wayside amenities
(i) Cleaning of toilets Daily
(ii) Defects in electrical, water and sanitary installations Daily
(g) Toll plaza[s]
(i) Failure of toll collection equipment including ETC or lighting Daily
(ii) Damage to toll plaza Weekly
(h) Other Project Facilities and Approach roads
Damage or deterioration in Approach Roads, -[pedestrian facilities,
(i) truck lay-bys, bus-bays, bus- shelters, cattle crossings, Traffic Aid Posts, Daily
Medical Aid Posts and other works]
(j) Incident Management
Frequency
Nature of defect or deficiency of
inspection
Instances of Incident Management as reported including time of call,
(i) Daily
response time, services rendered and time of clearing of the Highway.
(ii) List of the Incident Management Services rendered. Weekly
BRIDGES
(a) Superstructure of bridges
(i) Cracks Weekly
(ii) Spalling/scaling Weekly
(b) Foundations of bridges
(i) Scouring and/or cavitation Weekly
(c) Piers, abutments, return walls and wing walls of bridges
(i) Cracks and damages including settlement and tilting Weekly
(d) Bearings (metallic) of bridges
(i) Deformation Weekly
(e) Joints in bridges(i) Loosening and malfunctioning of joints Weekly
(f) Other items relating to bridges
(i) Deforming of pads in elastomeric bearings Weekly
Gathering of dirt in bearings and joints; or clogging of spouts, weep holes
(ii) Weekly
and vent-holes
(iii) Damage or deterioration in parapets and handrails Weekly
(iv) Rain-cuts or erosion of banks of the side slopes of approaches Weekly
(v) Damage to wearing coat Weekly
Damage or deterioration in approach slabs, pitching, apron, toes, floor or
(vi) Weekly
guide bunds
(vii) Growth of vegetation affecting the structure or obstructing the waterway Weekly
6.3.2 All elements which have daily inspection frequency shall be inspected weekly as well.
Similarly, all elements which have weekly inspection frequency shall be inspected
monthly as well.
6.3.3 Daily inspection report format and weekly inspection report format has been provided
in Annexure II and III of this document respectively. Manpower which needs to
conduct visual inspection and mode of reporting is defined in the following table
Frequency of inspection Inspection to be carried out by Mode of reporting
Daily Sub-professional staff Soft copy by Email
Weekly Key personnel Soft copy by Email
Monthly Key personnel Hard copy and Soft copy
6.3.4 High resolution photographs and video of the highway stretches having defects
and/or deficiencies shall be submitted along with Weekly Inspection Report and
Monthly Status Report. Summary of key observations around defects and
deficiencies in highway stretch shall be reported in Monthly Progress Report and
detailed inspection report shall be provided as Annexure to Monthly Progress Report.
6.3.5 The Authority’s Engineer shall also be responsible for inspection and monitoring of
WaysideAmenities. ETC (Electronic Toll Collection) and ATMS (Advanced Traffic
Management System) and incident management.
6.4 Road conditions surveys
6.4.1 The carrying out of condition surveys will be one of the most important and crucial
field tasks under the project. The Authority Engineer shall carry out condition
surveys using equipment and following a frequency as defined under.
Frequency of
S No Key metrics of Asset Equipment to be used
condition
survey
At least twice a year (As per
Surface defects of
1 Network Survey Vehicle (NSV) survey months defined for the
pavement
state basis rainy season)
At least twice a year (As per
2 Roughness of pavement Laser Profilometer survey months defined for the
state basis rainy season)
Falling Weight Reflectometer
3 Strength of pavement At least once a year
(FWD)
At least twice a year (As per
Mobile Bridge Inspection Unit
4 Bridges survey months defined for the
(MBIU)
state basis rainy season)
At least twice a year (As per
5 Road signs Retro-reflectometer survey months defined for
the
state basis rainy season)
The first equipment based inspection shall be conducted at the time of completion
testing. The other inspections shall be conducted before and after the rainy seasons
as per the schedule defined in Annexure IV, except for FWD testing which shall be
conducted once a year.
Calibration of equipment, wherever needed, is required to be done in presence of
Competent Authority. Once approval of equipment, the settings and a sample data
set is provided by Competent Authority, network level data for entire project stretch
can be collected. Month of survey for each state has been defined in Annexure IV
of this document.
6.4.2 Measurement of pavement surface defects and roughness
i. The Authority Engineer shall use Network Survey Vehicles mounted with
equipment such as Laser based automatic crack detection , high resolution
digital cameras for RoW and pavement, high accuracy DGPS receiver and in
vehicle data processing software or better technology to accurately measure
following pavement surface properties
Surface defect Dimensions to be reported• Length
Cracking • Width
• Depth
• Area
Potholes
• Depth
Raveling • Indicator
• %
• Area
• Depth
Rutting
• Width
Concrete Joint/ Faulting • Length
Roughness • IRI in both wheel paths
ii. The following criteria shall be met by the process of defects detection
• Measurement of 3D road profile using such technologies as laser scanning
or other proven technologies.
• Ability to operate (collect data) at different speeds with a minimum speed
of 30km/hr and upto at least 75 km/ hr.
• Profile depth accuracy of 0.5mm
• Capability for lane tracking to control driver wander’ and ensure high
repeatability of data between surveys.
• Measure at least 3.5m width of highway lane.
• Transverse Profile including rut depth measurement of pavement surface
widths of both carriageway and shoulders. The rut depth data must be
convertible to different straightedge lengths (1.8m to 3.5m) and meet
industry standards (ASTM E1703 / E1703M).
• Pavement images with capability to automatically identify and rate distresses
• Roughness measurement with outputs of both raw longitudinal profiles and
International Roughness Index (IRI) calculation shall be reported at least
100m referenced to the preceding Location Reference Post (LRP). The
roughness must meet ASTM-E950 (equivalent to Class I road profiler). The
IRI shall be determined in both wheel paths.
• Ability to record images at user-defined intervals (e.g. every 5, 10m, etc.)
• Minimum images resolution of 1600x1200
• Outputs must include Standard JPEG image or similar industry standard
• Distance resolution of <1mm,
• Capable of achieving distance accuracy of 0.1% (i.e. within 1m over 1km
distance)
• All data outputs should be in a non-proprietary format (e.g. .CSV, .MDB,
Excel) and not require specialist software in order to view or format data
• Data should also be capable of being easily formatted into data
compatible with HDM-4
iii. The following are the set of deliverables which should be submitted after
completion of survey as part of Monthly Progress Report
• Raw data generated from the equipment which are part of Network Survey
covering the parameters mentioned in above table. It should also include
o Survey ID, Description, Date, Laneo GPS referenced data for GIS mapping
• Video logging
o Pavement imagery (AVI/JPEG)
o 360 degree imagery (JPEG)• Interpretation report covering summary of entire survey and analysis of
defects and deficiencies
6.4.3 Measurement of pavement strength
(i) The Authority Engineer shall carry out structural strength surveys for existing
pavements using Falling Weight Deflectometer technique in accordance with the
procedure given in IRC:115-2014 (Guidelines for Structural Evaluation and
Strengthening of Flexible Road Pavements Using Falling Weight Deflectometer
(FWD) Technique) and IRC: 117-2015 (Guidelines for the Structural Evaluation of
Rigid Pavement by Falling Weight Deflectometer)
(ii) The interval at which deflection measurements are to be taken up are as per
IRC:115- 2014 / IRC:117-2015. For flexible pavements, the sample size and the
interval of the data to be collected depends on the length of the uniform section
calculated and condition of the pavement section i.e. ‘good’, ‘fair’ and ‘poor’ for each
lane, established on the pavement condition data based on the criterion given in
IRC:115-2014. For rigid pavements, the deflection data may be collected at interiors,
corners, transverse joints and longitudinal joints in the outer lanes at intervals as
specified in IRC:117-2015.
(iii) The following are the set of deliverables which should be submitted after completion
of inspection test as part of Monthly Progress Report
• Data report covering following parameters
o Deflection Bowl (Transient Deflections at seven different points)
o Corrected Elastic Modulus Bituminous E1
o Corrected Elastic Modulus Granular E2
o Corrected Elastic Modulus Subgrade E3
o Subgrade CBR
• Interpretation report covering summary of entire survey results and
analysis of key parameters
6.4.4 The Authority Engineer shall carry out the condition and structural assessment
survey of the bridges in accordance with IRC-SP; 35 with the use of Mobile Bridge
Inspection unit (MBIU) or better technology.
(i) The following criteria shall be met by the process of bridge condition assessment
• Automatic folding and unfolding of platform
• 90 degree rotation of platform
• Sufficient safety features to be incorporated such as dedicated power supply,
emergency cut off system, etc
• Complete access to hidden parts of the bridge by the raters
(ii) Detailed bridge inspection report shall be submitted as per the Inspection Proforma
provided in IRC-SP 356.4.5 Measurement of retro reflection of road signs
(i) The Authority Engineer shall measure Coefficient of retro reflected luminance R
A
(night time retro reflection) of road traffic signs using a portable retro reflectometer.
(ii) The following criteria shall be met by the process of road signs retro reflection
measurement
• Measurement of retro reflective signs shall be conducted in accordance with
ASTM E1709 and ASTM E2540
• Measurement time after pressing trigger shall be less than or equal to 1 sec
• Observation angle adjustment from 0.2 degrees to 2.0 degrees
• Entrance angle adjustment from -45 degrees to +45 degrees
• Self-contained commercially available battery
• Inbuilt data storage of at least 2,000 measurements so that data transfer
requirement is minimized while the survey is being conducted
• Interface for transferring data from device to Computer
• Built in GPS to capture GPS coordinates of road sign
• Range shall be at least 0-2000 cd/lx/m2
(iii) The following are the set of deliverables which should be submitted after
completion of survey as part of Monthly Progress Report
• System generated coefficient of retro reflected luminance R (nighttime retro
A
reflection) of all road signs
• Interpretation report covering analysis of road signs falling in different range
of R
A
and actions to be taken
6.5 The Authority Engineer shall carry out following inspections of ETC lanes at toll
plazas on a month basis:
(i) Infrastructure:
• Availability of civil infrastructure at toll plazas required for installation of ETC systems
• Adequacy of hardware, software and other related items as per
IHMCL/<Agency> technical specifications and requirements
(ii) Operations:
• Adherence of various stakeholders (acquirer bank, system integrator, toll
operator, issuer bank etc) of the ETC system to the service level agreements
• Efficacy of the ETC system (RFID tagging, AVC, WIM etc) in terms of
accuracy and uptime
• Tracking and reporting toll plaza experience metrics such as average waiting
time, transaction times for different modes of payment (RFID, cash, smart
cards, QR codesetc) and congestion levels (eg. length of queue in different lanes) across 4
different times in a day
• Robustness of dispute resolution mechanisms in place for the tag holder
and toll operators by the issuer and acquirer banks
6.6 The Authority Engineer shall prepare a Monthly Status Report in O&M phase of
project in respect of its duties and functions under this Agreement and in
accordance with the format prescribed in Annexure VI. 1st deliverable of the report
which is an executive summary to the main report (Section 1) shall be submitted
to the Authority and updated on the PMIS and project specific website by 4th of
every month. Main report (Section 2 onwards) shall be submitted to the Authority
and updated on the PMIS and project specific website by 7th of every month. Key
sections of the Monthly Status Report are as follows;
S.No Sections Sub sections
1.1 Overall road condition
1.2 Key reporting metrics
1.3 Key maintenance activities undertaken
1 Executive Summary
1.4 Pending issues
1.5 Recommended actions by AE
1.6 Strip plan for maintenance
2.1 Key project details
2.2 Location map
2 Project Overview 2.3 Key plan
2.4 Summary of project features
2.5 RoW availability
3.1 Issue and action log
Critical issues and 3.2 Summary of deficiencies
3
action taken 3.3 Obligations as per contract
3.4 Inspection schedule
4.1 Summary of NCR issued
4 Monthly Inspection Report
4.2 Equipment based inspection report
5.1 Monthly ETC Report
5 Monitoring of ETC Lanes 5.2 On-ground infrastructure report
5.3 On ground ETC operations & SLA adherence
6.1 Damages for non completion of project facilities
6.2 Damages for breach of maintenance activities
6 Status of damages
6.3 Damages for non completion of major maintenance
works
Change of Scope
7 7.1 Change of Scope proposals
proposals
8 Status of pending 8.1 Status of pending disputes
disputes
9.1 Toll collection statement
9 Reports
9.2 Accident ReportS.No Sections Sub sections
9.3 Details of user complaints
9.4 Encroachment list
9.5 Lane closure report
Annex I- Detailed visual inspection report of project
highway
10 Annexures
Annex II onwards- Additional details provided by AE
6.7 The Authority’s Engineer shall specify the tests, if any, that the Contractor shall
carry out, or cause to be carried out, for the purpose of determining that the
Project Highway is in conformity with the Maintenance Requirements. It shall
monitor and review the results of such tests and remedial measures, if any, taken
by the Contractor in this behalf.
6.8 In respect of any defect or deficiency referred to in Paragraph 3 of Schedule-E, the
Authority’s Engineer shall, in conformity with Good Industry Practice, specify the
permissible limit of deviation or deterioration with reference to the Specifications
and Standards and shall also specify the time limit for repair or rectification of any
deviation or deterioration beyond the permissible limit.
6.9 The Authority’s Engineer shall examine the request of the Contractor for closure of
any lane (s) of the Project Highway for undertakings maintenance/repair thereof,
and shall grant permission with such modifications, as it may deem necessary,
within 5 (five) days of receiving a request from the Contractor. Upon expiry of the
permitted period of closure, the Authority’s Engineer shall monitor the reopening of
such lane (s), and in case of delay, determine the Damages payable by the
Contractor to the Authority under Clause 14.5 of EPC Agreement
7 Determination of costs and time
7.1 The Authority’s Engineer shall determine the costs, and/or their reasonableness,
that are required to be determined by it under the Agreement.
7.2 The Authority’s Engineer shall determine the period of Time Extension that is
required to be determined by it under the Agreement.
7.3 The Authority’s Engineer shall consult each Party in every case of determination in
accordance with the provisions of Clause 18.5 of EPC Agreement.
8 Payments
8.1 The Authority’s Engineer shall withhold payments for the affected works for which
the Contractor fails to revise and resubmit the Drawings to the Authority’s
Engineer in accordance with the provision of Clause 10.2.4 (d) of EPC Agreement.
8.2 Authority’s Engineer shall(a) within 10 (ten) days of receipt of the Stage Payment Statement from the
Contractor pursuant to Clause 19.4, determine the amount due to the
Contractor and recommend the release of 90 (ninety) percent of the
amount so determined as part payment, pending issue of the Interim
Payment Certificate; and
(b) within 15 (fifteen) days of the receipt of the Stage Payment Statement
referred to in Clause 19.4, deliver to the Authority and the Contractor an
Interim Payment Certificate certifying the amount due and payable to the
Contractor, after adjustments in accordance with the provisions of Clause
19.10 of EPC Agreement.
7.3 The Authority’s Engineer shall, within 15 (fifteen) days of receipt of the First stage
Maintenance Payment Statement from the Contractor pursuant to Clause 19.6 of
EPC Agreement, verify the Contractor’s statement and certify the amount to be
paid to the Contractor in accordance with the provisions of the Agreement.
7.4 The Authority’s Engineer shall certify final payment with 30 (thirty) days of the
receipt of the final payment statement of Maintenance in accordance with the
provisions of Clause 19.16 of EPC Agreement.
9 Other duties and functions
The Authority’s Engineer shall perform all other duties and functions as
specified in the Agreement.
10 Miscellaneous
10.1 All key personnel and sub professional staff of the Authority Engineer shall use the
fingerprint based (biometric) attendance system for marking their daily
attendance. Attendance shall be marked at least once a day and anytime during the
day. 1 Biometric Attendance System shall be installed by the Authority Engineer at
its own cost at the site office in order to facilitate the attendance marking. More
systems can be installed near the project highway upto a maximum of 1 system per
50 km in order to encourage frequent visits of project highway by key personnel
and sub professional staff. A copy of monthly attendance records shall be attached
with Monthly Status Report. Proper justification shall be provided for cases of
absence of key personnel/ sub professional staff which do not have prior approval
from Project Director of concerned stretch
10.2 A copy of all communications, comments, instructions, Drawings or Documents sent
by the Authority’s Engineer to the Contractor pursuant to this TOR, and a copy of
all the test results with comments of the Authority’s Engineer thereon, shall be
furnished by the Authority’s Engineer to the Authority forthwith.
10.3 The Authority’s Engineer shall retain at least one copy each of all Drawings and
Documents received by it, including ‘as – built’ Drawings and keep them in its safe
custody.10.4 Within 90 (ninety) days of the Project Completion Date, the Authority’s Engineer
shall obtain a complete set of as built Drawings in 2 (two) hard copies and in micro
film form or in such other medium as may be acceptable to the Authority,
reflecting the Project Highway as actually designed, engineered and constructed,
including an as-built survey illustrating the layout of the Project Highway and
setback lines, if any, of the buildings and structures forming part of project
Facilities; and shall hand them over to the Authority against receipt thereof.
10.5 The Authority’s Engineer, if called upon by the Authority or the Contractor or both,
shall mediate and assist the Parties in arriving at an amicable settlement of any
Dispute between the Parties.
10.6 The Authority’s Engineer shall inform the Authority and the Contractor of any event
of Contractor’s Default within one week of its occurrence.
11. PERFORMANCE CLAUSE
Authority’s Engineers shall be expected to fully comply with all the provisions of the
`Terms of Reference’, and shall be fully responsible for supervising the
Designs, Construction and maintenance and operation of the facility takes
place in accordance with the provisions of the EPC Agreement and other
schedules. Any failure of the Authority Engineer in notifying to Employer and
the Contractor on non-compliance of the provisions of the EPC Contract
Agreement and other schedules by the EPC Contractor, non-adherence to the
provision of ToR and non-adherence to the time schedule prescribed under
ToR shall amount to non-performance.
The Authority Engineer shall appoint its authorized representative, who shall
issue on behalf of the AE, Completion Certificate along with the Team Leader
and shall carry out any such task as may be decided by Employer. The AE
shall take prior approval of Employer before issuing Completion Certificate.
The proposal submitted shall also include the name of the authorized
representative along with the authorization letter and power of attorney.
12. CONSULTANT’S PROPOSAL
12.1 List of key personnel to be fielded by the Consultants shall be as
below:
Normal Highway Project:
i. Team Leader Cum Senior Highway Engineer
ii. Resident cum Highway Engineer
iii. Senior Quantity cum Material Expert
iv. Bridge/Structural Engineer
v. Senior Pavement Specialist
vi. Contract Specialist cum Planning Engineervii. Road Safety Expert
Standalone Bridge Project:
i. Team Leader Cum Senior Highway Engineer
ii. Resident cum Pavement Specialist
iii. Bridge/Structural Engineer
iv. Contract Specialist cum planning Engineer
v. Senior Quantity cum Material Expert
vi. Road Safety
expert Standalone Tunnel
Project:
i. Team Leader Cum Senior Tunnel Expert
ii. Resident cum Excavation Specialist
iii. Senior Geotechnical Expert
iv. Tunnel Design Engineer
v. Tunnel Safety Expert
vi. Contract Specialist cum planning Engineer
vii. Senior Geologist
12.2 Broad job-description and minimum qualification for key personnel mentioned in
Section-VIA . However, higher marks shall be accorded to the Candidate with higher
relevant qualification and experience. All the CV’s of the personals mentioned in
Para5.3 (iii) of Data Sheet shall be evaluated at the time of evaluation of technical
proposal. The age of the Key Personnel should not be more than 65 years on
the date of submission of proposal. Consultants are advised in their own interest
to frame the technical proposal in an objective manner as far as possible so that
these could be properly assessed in respect of points to be given as part of evaluation
criteria. The bio-data of the key personnel should be signed on every sheet by the
personnel concerned and the last sheet of each bio-data should also be signed by
the authorised signatory for the Consultant. The key personnel shall also certify at
the end of their bio- data proforma that they have not left any of the Employer works
without completing of their assignment and have not accepted any other offer at
the time of signing of the bio-data and as such shall be available to work with the
Authority Engineer, if the Project is awarded. In case the key personnel leaves the
assignment without approval of Employer, Employer would beat liberty to take any
appropriate action against that key personnel including debarment. The CV
submitted by selected firm/JV shall be hoisted on official website of Employer.
12.3 In addition to above, consultants are required to propose other key personnel, sub-
professional staff and other field engineers as detailed in Section-VIA and the
minimum qualification requirements for the same is enclosed in Section VIA13. PERIOD OF SERVICES
13.1 The services of an Authority’s Engineer will be in phases as per Contract
Agreement.
13.1.1 The appointment of the Authority’s Engineer shall initially be as per
details given below.
Period of service Construction Maintenance/ DLP
(in period Period
months) (in months) (in months)
Construction Period DLP Period as per Civil
+ DLP Period as per Contract Agreement
Civil Contract
Agreement
The proposed manpower deployment for this period shall be matching the
activities to be performed during the said period. The time frame for services
during the deployment of key personnel during this period shall be as shown
in Section VIA. Extension of Time for providing services of Engineer may
the Authority’s be_- extended concurrently with the Extension of EPC Time
granted, if any, to the Contractor for the project, Subject to satisfactory|
performance of the Authority’s Engineer and limited to original period of
consultancy services.
14. Project Coordinator
The Firm shall appoint a personnel from its head office to act as Project
Coordinator for the assignment with approval of the Authority. The CV of the
project coordinator shall be submitted to the Authority for approval and he
shall full fill the eligibility criteria for Team Leader as per RFP. He will be
authorized to communicate with the Authority in respect of all matters
pertaining to the project. If the performance of the project coordinator is
found unsatisfactory, the Authority may direct replacement of the project
coordinator. The cost of the Project Coordinator shall be incidental to the
Consultancy Assignment.
Annexure I- Daily Inspection Report in construction period
Results of lab
Description Name of key
tests
of inspection personnel
Componen Item Description conducted
work carried inspecting
t (Test
out the work
conducted,
Pass/Fail)
1. Road works
Embankment/ Sub
including
Grade/ GSB/ WMM/
culverts, and
DBM/ BC
minor bridges2. Major Bridge
Foundation/ Sub
works, Flyovers,
structure/ Super
ROB, RUB, VUP,
structure
PUP
3. Approach to
Foundation/ Sub
ROB/RUB/ Major
structure/ Super
Bridges/ Viaduct /
structure
RE wall
4. Other WorksAnnexure II- Daily Inspection Report in O&M period
Nature of defect/ deficiency Defect If defect Compliance of AE Remarks
found found, previous
(Yes/No) Chainage & defect
side (Yes/No/NA)
ROADS
Carriageway and paved shoulders
Breach or blockade
Pot holes
Removal of debris
Hard/earth shoulders, side slopes, drains and culverts
Desilting of drains in urban/semi-
urban areas
Road side furniture including road signs and pavement marking
Damage to shape or position; poor
visibility or loss of retro-reflectivity
Street lighting and telecom (ATMS)
Any major failure of the system
Faults and minor failures
Trees and Plantation
Obstruction in a minimum head-
room of 5 m above carriageway or
obstruction in visibility of road signs
Rest areas
Cleaning of toilets
Defects in electrical, water and
sanitary installations
Toll plaza[s]
Failure of toll collection equipment
including ETC or lighting
Other Project Facilities and Approach roads
Damage or deterioration in
Approach Roads, -[pedestrian
facilities, truck lay-bys, bus-bays,
bus- shelters, cattle crossings,
Traffic Aid Posts, Medical Aid Posts
and other works]Annexure III- Weekly Inspection Report in O&M period
Defect If defect Compliance of AE Remarks
found found, previous defect
Nature of defect or deficiency
(Yes/No) Chainage & (Yes/No/NA)
side
ROADS
(a) Carriageway and paved shoulders
(i) Breach or blockade
Roughness value exceeding 2,500
mm in a stretch of 1 km (as
(ii)
measured by a standardised
roughometer/bump integrator)
(iii) Pot holes
Cracking in more than 5% of
(iv)
road surface in a stretch of 1 km
Rutting exceeding 10 mm in more
than 2% of road surface in a
(v)
stretch of 1 km (measured with 3 m
straight edge)
(vi) Bleeding/skidding
Ravelling/Stripping of bitumen
(vii)
surface exceeding 10 sq m
Damage to pavement edges
(viii)
exceeding 10 cm
(ix) Removal of debris
Hard/earth shoulders, side slopes, drains and
(b)
culverts
Variation by more than 2% in the
(i) prescribed slope of camber/cross
fall
Edge drop at shoulders exceeding
(ii)
40 mm
Variation by more than 15% in
(iii) the prescribed side (embankment)
slopes
(iv) Rain cuts/gullies in slopeDefect If defect Compliance of AE Remarks
found found, previous defect
Nature of defect or deficiency
(Yes/No) Chainage & (Yes/No/NA)
side
Damage to or silting of culverts and
(v) side drains during and immediately
preceding the rainy season
Desilting of drains in urban/semi-
(vi)
urban areas
Road side furniture including road signs
(c)
and pavement marking
Damage to shape or position;
(i)
poor visibility or loss of retro-
reflectivity
(d) Street lighting and telecom (ATMS)
(i) Any major failure of the system
(ii) Faults and minor failures
(e) Trees and plantation
Obstruction in a minimum head-
(i) room of 5 m above carriageway or
obstruction in visibility of road signs
Deterioration in health of trees
(ii)
and bushes
(iii) Replacement of trees and bushes
Removal of vegetation affecting
(iv)
sight line and road structures
(f ) Rest areas
(i) Cleaning of toilets
Defects in electrical, water and
(ii)
sanitary installations
Toll
(g) plaza[s]
Failure of toll collection equipment
(i)
including ETC or lighting
(ii) Damage to toll plaza
(h) Other Project Facilities and Approach roadsDefect If defect Compliance of AE Remarks
found found, previous defect
Nature of defect or deficiency
(Yes/No) Chainage & (Yes/No/NA)
side
Damage or deterioration in
Approach Roads, -[pedestrian
facilities, truck lay-bys, bus-bays,
(i)
bus- shelters, cattle crossings,
Traffic Aid Posts, Medical Aid Posts
and other works]
BRIDGES
(a) Superstructure of bridges
(i) Cracks
(ii) Spalling/scaling
(b) Foundations of bridges
(i) Scouring and/or cavitation
Piers, abutments, return walls and wing
(c)
walls of bridges
Cracks and damages including
(i)
settlement and tilting
(d) Bearings (metallic) of bridges
(i) Deformation
Joints in
(e) bridges
Loosening and malfunctioning of
(i)
joints
(f) Other items relating to bridges
Deforming of pads in elastomeric
(i)
bearings
Gathering of dirt in bearings and
(ii) joints; or clogging of spouts, weep
holes and vent-holes
Damage or deterioration in
(iii)
parapets and handrails
Rain-cuts or erosion of banks of the
(iv)
side slopes of approaches
(v) Damage to wearing coatDefect If defect Compliance of AE Remarks
found found, previous defect
Nature of defect or deficiency
(Yes/No) Chainage & (Yes/No/NA)
side
Damage or deterioration in
(vi) approach slabs, pitching, apron,
toes, floor or guide bunds
Growth of vegetation affecting the
(vii) structure or obstructing the
waterwayAnnexure IV- Month of survey for equipment based road condition assessment
Equipment based road inspection shall be done by the Authority’s Engineer twice a
year as per the month of the year defined in the following table.
However, since the first survey shall be conducted at the time of completion testing,
the following modification to the schedule shall be adopted. For example, if majority
of highway length (>50%) passes through a state, where defined survey months
are May and November, if completion testing is conducted in April, then the first
equipment based survey shall be conducted in the month of April. This shall be
considered as the equipment based survey to be conducted in the month of May.
The 2nd equipment based survey shall be conducted in the month of November, the
3rd survey shall be conducted in the month of May and so on. As regards FWD, the
first test/survey shall be conducted at the time of completion in April. The 2nd
test/survey shall be conducted in April of next year and so on.
Region State Survey before Survey after rains
rains
East Bihar May Nov
East Chhattisgarh May Nov
East Jharkhand May Nov
East Orissa May Nov
East West Bengal May Nov
Central Madhya Pradesh May Nov
NE Arunachal Pradesh Mar Oct
NE Assam Mar Oct
NE Manipur Mar Oct
NE Meghalaya Mar Oct
NE Mizoram Mar Oct
NE Nagaland Mar Oct
NE Sikkim Mar Oct
NE Tripura Mar Oct
North Chandigarh May Nov
North Delhi May Nov
North Haryana May Nov
North Himachal May Nov
North Jammu And Kashmir May Nov
North Punjab May Nov
North Uttar Pradesh May NovRegion State Survey before Survey after rains
rains
North Uttaranchal May Nov
Andaman And Nicobar
South Apr Nov
Islands
South Andhra Pradesh Apr Nov
South Karnataka Apr Nov
South Kerala Apr Nov
South Pondicherry Jun Jan
South Tamil Nadu Jun Jan
West Dadar Nagar Haveli Apr Oct
West Daman And Diu Apr Oct
West Goa May Nov
West Gujarat Apr Oct
West Maharashtra May Nov
West Rajasthan Apr OctAnnexure V- Monthly Progress Report in Construction Phase
[NAME & LOGO OF IMPLEMENTING AGENCY]
[PROJECT NAME]
Authority Engineer
[NAME OF CONSULTING FIRM]
MONTHLY PROGRESS REPORT NO.
[XX] FOR THE MONTH OF:
[MONTH], [YEAR]Table of content
Contents
Page Nos.
1 Executive Summary ................................................................................. 126
1.1 Construction progress in current month 126
1.2 Current issues and recommended actions by IE / AE 126
1.3 Strip Plan (Summary) 127
1.4 Strip Plan (Details) 128
2 Project Overview ..................................................................................... 129
2.1 Salient Features of Project 129
2.2 Project Milestones 130
2.3 Location Map 131
2.4 Key Plan 132
3 Critical Issues & Action Log ...................................................................... 133
3.1 Pending Issues & Action Log 133
3.2 Obligations as per Contract 134
4 Physical Progress ..................................................................................... 134
4.1 Detailed Scope of Work & Physical Progress by Component 135
4.2 Details of verification of source of material
5 Land Acquisition and Clearance ................................................................ 136
5.1 LA Summary 136
5.2 LA Detail by CALA 136
5.3 LA Detail by Village for each CALA 136
5.4 Manpower details of CALA137
5.5 Clearances Summary 137
5.6 Status of utilities shifting 139
6 Change of Scope ..................................................................................... 139
7 Mobilization of Resources ......................................................................... 1408 Financial Progress Details (for PPP projects) .............................................. 140
8.1 Pen Picture - Escrow 1408.2 Escrow details 141
9 Summary of quality control tests .............................................................. 142
9.1 Tests witnessed by IE/ AE 142
9.2 Tests conducted by IE / AE 143
10 Monitoring of maintenanceobligations during construction phase.............. 144
10.1 Critical issues and action log 144
10.2 Summary of repair work 144
10.3 Status of damages 146
11 Safety features ..................................................................................... 146
11.1 Pen picture of safety features 146
11.2 Accident Report 147
12 Annexures ............................................................................................ 1491 Executive Summary
1.1 Construction progress in current month
Key reporting metrics Value/ %/ Amount
Scheduled Physical Progress (%)
Cumulative Physical Progress upto current month (%)
Physical Progress during current month (%)
Financial progress (%)
Cumulative Expenditure till date (Rs Cr)
Tests passed as % of total tests witnessed by IE
Tests passed as % of total tests conducted by IE
Number of pending COS proposals
Amount for pending COS (Rs Cr)
1.2 Current issues and recommended actions by IE / AE
1. Slow Progress of Structures: The progress of structures (especially,
major bridges, flyovers and ROB’s) is very slow. Overall progress is
only XX%. Out of the total YY underpasses not even single
underpass structure and its approaches is completed so far. No
bridge is open to traffic sofar.
a. Recommendation: Concessionaire should improve the progress
of structures. Request for revised workplan from Concessionaire
including specific activities on structures.
2. Status of Change of Scope Proposals: Concessionaire has submitted Xx No.
Change of Scope proposals. Yy No. of them are still pending for decision.
Concessionaire has not submitted necessary clarifications /details for the
following Changes of Scope in spite of severalreminders.
a. Recommendation: Concessionaire to submit all pending clarifications
to Authority. Authority and Concessionaire to expedite pending COS
proposals.1.3 Strip Plan
(Summary)
2. Length completed 3. Length
1. Work front Unavailable by layer (MCW) completed by
& reason for layer (Service
Unavailability Road)1.4 Strip Plan (Details)Detailed report
2 Project Overview
2.1 Salient Features of Project
Project Name
NH No. (New/ Old)
Scheme/ Phase
Mode of the Execution (BOT Toll/ BOT Annuity/ EPC/
HAM/ Item Rate/ Others)
No. of Lanes/ Configuration
Length of the Project (in Km)
Total Project Cost (in Cr)
No. of Bypasses (Name of Town, Length)
No. of Major Bridges (Number and Location)
No. of Toll Plazas (Number and Location)
No. of Fly Overs (Number and Location)
DPR Authority’s EngineerName
Lead & Consortium Members of Banks
Concessionaire Name (SPV & Parent Company)
Date of Award (LOA Date)
Appointed Date
Concession Period
Construction Period (in Days)
O&M Period (in Days)
Scheduled Date of Completion
Authority Engineer
IE / AE Agreement Date
IE / AE Mobilization Date2.2 Project Milestones
Ac
Pla
Descripti
tu
Projec on n Dela Curren
al
t (Days ned y (No. t
Milest from Physical Physical of Status
Scheduled
o ne Appoint Progress Progress Revised Date mont
Date
h s)
e d (%) (%)
Date)
Mileston [DD/MM/YYYY [DD/MM/YYYY Achieve
[Description] 25 25 5
e I ] ] d
Started
[DD/MM/YYYY [DD/MM/YYYY , not
Milesto [Description] 65 22
] ] achieve
ne II
d
Schedule
Not
d
[DD/MM/YYYY [DD/MM/YYYY
starte
Completi [Description] 100 21
] ]
d
o n2.3 Location Map2.4 Key Plan
[Above image is illustrative only. Please include chainage and name below the
axis and list of features above the axis]3 Critical Issues & Action Log
3.1 Pending Issues & Action Log
Ongoin Expected
Chainage( Action(s
g/ New Lengt Action(s) date/
S.N Issue Concerned s) )
Type Issue/ h taken till Actual Date
o Description Authorit affected suggeste
Resolve affect now for
y due to d by
d e d resolving
the issue the AE
(km) issue
1. Proposal
submitted to
Diversion of
MoEFLetter Escalate to
Ongoin sent by RO to higher level [DD/MM/YYY
1 Xx ha of Clearance MoEF [Chainage] 4 kms
g MoEF nodal officers at Y]
forest Land
Issue officer on MoEF
[DD/MM/YYY
Y]
1. Escalated
to chief
21
secretary
level through
Crcompensati
Land Resolve [CALANam DO from [DD/MM/YYY
2 on [Chainage] 2.4 km
Acquisition d e] Chairman/ Y]
disbursement
Secretary,
pending
dated
[DD/MM/YYY
Y]
Project
Slow Director to
progress by Concessionai New [Concess. call higher [DD/MM/YYY
3 [Chainage] 57 km None
concessionair re Issue Issu Name] ups of Y]
e e concessionai
re3.2 Obligations as per Contract
4 Physical Progress
Physical
Physical Progress
%
Compone Progress(Duri (Cumulati
Weighta
nt n g Current v e, Upto
g e
Month) Current
Month
)
Road Works 35.00% 5% 15.0%
Major Bridge works and ROB / 40.00% 1.20% 26.2%
RUB
Structures 21.00% 0.00% 0.8%
Other Works 4.00% 0.00% 0.0%
Physical
2 42.0%
Progress
%4.1 Detailed Scope of Work & Physical Progress by Component
Cost
Cost Planned in Value of
Weightag
Weightag Scope (As Progress %PhysicaPhysical
Component Item e in
e in Description per Scope till Date l Progress
Componen
Project of Work) Progress (7X4)
t
(%)
(%)
1 2 3 4 5 6 7 8
35.00% 1. C&G 5.00% 80 km 45 km 56% 2.8%
1. Road works
2. Embankment 5.00% 80 km 40 km 50% 2.5%
including
3. Sub Grade 5.00% 80 km 35 km 44% 2.2%
culverts, minor
4. GSB 5.00% 80 km 33 km 41% 2.1%
bridges,
5. WMM 5.00% 80 km 30 km 38% 1.9%
underpasses,
6. DBM 5.00% 80 km 28 km 35% 1.8%
overpasses,
7. BC 5.00% 80 km 27 km 34% 1.7%
approaches to
ROB/RUB/ Major
Bridges/
Structures (but
excluding service
roads)
40.00% 1. Major Bridges 10.00% 6 No 6 No 100% 10.0%
2. Major Bridge
2. Minor Bridges 5.00% 23 No 21 No 91% 4.6%
works and
3. Flyovers 5.00% 2 No 0 0% 0.0%
ROB/RUB
4. ROB 5.00% 228 No 121 No 53% 2.7%
5. VUP 5.00% 11 No 6 No 55% 2.7%
6. PUP 5.00% 15 No 6 No 40% 2.0%
7. RUB 5.00% 136 No 114 No 84% 4.2%
3. Structures 21.00% 1. Foundation 5.00% 35 km 2.2 km 6% 0.2%
(elevated 2. Sub-structure 5.00% 35 km 2.1 km 6% 0.2%
sections, 3. Super-structure 5.00% 35 km 2.1 km 6% 0.2%
reinforced earth) 4. Reinforced Earth 6.00% 35 km 2.1 km 6% 0.2%
Wall
4. Other 4.00% 1. Toll Plaza 4.00% 4 No 0 0% 0.0%
Works
GRAND TOTAL 100% 42.0
%
4.2 Details of verification of Source of material received at yard/Plant/ site
Material Quantity received at Approved quantity and Quantity received from
Project Site source of material the approved source
1. Earth
2. Aggregate3. Cement
4. Steel
5. Bitumen
6. Admixtures
7. Bearings
8. Other materials
i)
ii)
iii)5 Land Acquisition and Clearance
5.1 LA Summary
Total Total in Total to be acquired
Descriptio
Required possession at (ha)
n
(ha) start (ha)
Existing ROW 135.00 135.00 0.00
Pvt. Land To be Acquired 240.00 0.000 240.00
Public Land To be Transferred 52.00 50.35 1.65
Grand Total 427 185 242
5.2 LA Detail by CALA
Amount
Total Land
3H
3G
3DD 3ADo
Amoun Amount
Disburse
Pendin
CALA Ale cf (qt H ut ao ir )b e e d P (e i hnn agd
)
- 3 enH (D ho a (P - hie nn agd ) n )3 o e G (D ha 3 i ( D n hgP a )e nd neo a( h 3 n )A gP (e Hnd ai ne a )( h Awa dt r de dD (e RCp sro .os )i rt ee CA reLd A Rb ( sy C
.
)r o A (m Crog ou rn et
) ) (Crore Rs.)
Rs.)
CALA 1] 150 15 15 15 135 0 150 0 150 396 370 327 43
[CALA2
67 0 0 0 67 0 67 0 67 132 132 120 23
]
[CALA
23
23 23
23 0 14 9 0 23 0 0 0 0
3]
Grand
240 38 20 38 20 14 226 0 240 528 502 447 66
Total
2 2
5.3 LA Detail by Village for each
CALA CALA 15.4 Manpower details of CALA
Provided Revenu Tehsilda
Patwaris Compu
by Amins e r s/ Clerks
/ Village Accounta t er Chain
CALA <Agency / Inspect Dep. / Peons Tota
account nts operat m an
> Survey o rs/ Tehsilda Sahay l
a nt o rs
/ State o rs Kanung r s a ks
Govt o
<Agency
[CALA 1] 4 1 0 0 3 0 3 1 0 12
>
[CALA 1] State Govt 2 0 2 0 0 0 1 0 0 5
<Agency
[CALA 2]
>
[CALA 2] State Govt
Grand
Total
5.5 Clearances Summary
Environmen
t
Length
Proposal Description Status Current Stage Issues/ Comments
Impacte
d
Approval of construction in coastal Obtaine Nil Completed
zone d
Forest Land
Length
Proposal Description Status Current Stage Issues/ Comments
Impacted
Diversion of Xx ha ([Chainage]) Pending [Length in Completed Stage 1 clearance
km] pending
Diversion of Xx Ha. ([Chainage]) Obtaine Nil Ongoing
dWildlife
Length
Proposal Description Status Current Stage Issues/ Comments
Impacted
Diversion of Xx Ha. of forest Pending [Length in Ongoing Queries sent to MoEF by RO,
land km] compliance pending
TreeCutting
Length
Proposal Description Status Current Stage Issues/ Comments
Impacted
N.A. N.A. N.A. N.A. N.A.
Railway
(ROBs/RUBs)
Length
Proposal Description Status Current Stage Issues/ Comments
Impacted
[GAD Number] Proposal [Chainage] Uploaded on N.A.
Submitted, portal on
Approval pending [DD/MM/YYYY]5.6 Status of utilities shifting
Date
Date of
when Date of Date of Progre
Utility Lengt
Date of
Estimate Approval Deposit ss
Certificat Estima
request i on from t e Issue/
Catego Na Status h Depart by was by of ofPhys Agency Amoun Comme
r y m affect m ent Received Authorit super- ical
Authority for t n ts
e e d from y RO/ HQ vision Shifti
for Completi
concerne charge n g
estimate o
d dept. n
Estima
[Lengt [DD/MM/ [DD/MM/ [DD/MM/
[DD/MM
Not
Wate te [DEPART / TBD
h YYYY] YYYY] YYYY] started
r Appro MENT] YYYY]
in km]
ved
Electric
Estima
[Lengt [DD/MM/ [DD/MM/ [DD/MM/
[DD/MM
Not
te [DEPART / TBD
ity h YYYY] YYYY] YYYY] started
Appro MENT]
YYYY]
in km]
ved
Estima
[Lengt [DD/MM/ [DD/MM/ [DD/MM/ [DD/MM/
Other te [DEPART TBD
h YYYY] YYYY] YYYY] YYYY]
s Appro MENT]
in km]
ved
6 Change of Scope
Date of
COS ed/ Actual Date
first
S No. Proposal Details Current Status
Amoun of Approval
submission
t
to
AE
Construction of [Flyover Approved in principle by Authority.
[+/ -
1 Name] at [DD/MM/YYYY] Detailed quantities in proper order [DD/MM/YYYY]
Amount]
[Chainage] yet to be submitted
Clarifications to be submitted by
Nallah diversion through [+/ -
2 box culvert at[Chainage] [DD/MM/YYYY] Concessionaire , expected Amount] [DD/MM/YYYY]
date[DD/MM/YYYY]1 Mobilization of Resources: - All contractor equipment should be mandatorily fitted with
GPS and the tracking of the same shall be maintained by the AE and submitted as part of the
MPR. Vehicles without evidence of GPS history shall not be accepted as part of machinery
deployment of the Contractor by the AE. The details of Mobilization of resource shall be
submitted in the following format
2
Details Expecte
Deploy Reason(s)
of
Age of Planned d Delay
S Equipment Ma Mod ownershi Actual e d for Remark
Equipm / due to
No Name k e e l p/Hiring Quantit During Under/Ove s
e nt Require Under-
. y the r
d Mobilizat
Mont h Mobilizatio
Quantit i on
n
y
Excavator/
5
Poclain
Paver 2
Transit Meter 0
Plate
0
Compactors
[ADD
OTHERS]
2. Financial Progress Details (for PPP projects)
2.1 Pen Picture - Escrow
Cumulative
Cumulative Inflow to Outflow from
inflow to Escrow
TPC (Cr) outflow from Escrow during Escrow during
till previous
Escrow till the month (Cr) the month(Cr)
month (Cr)
previous
month(Cr)
1,206 1,033 900 30 35
Are the Escrow withdrawals in accordance with the order of withdrawal as
specified in the Concession Agreement?
Tick as applicableIf not, details to be provided below:
2.2 Escrow details
Escrow Plan Escrow Escrow
Cumulativ Escrow Plan Escrow Plan Escrow Actual
till date- Actual till Actual till
TPC (Cr) e exp. till till date- till date- till date-
Equity date- date-
date (Cr) Debt VGF (BOT) Equity (BOT)
(BOT) (Cr) Debt VGF
(BOT)(Cr) (Cr) (Cr)
(BOT) (BOT)
(Cr) (Cr)
1,206 1,033 900 306 - 769 264 -3. Summary of quality control tests
3.1 Tests witnessed by IE/ AE
Total test up
Frequenc Total test in This Cumulative No.
to Previous
y of Month of tests
Descriptio Uni Month Remar
tests
n t k s
No. Conducte Pas Fai Conducte Pas Fai Conducte Pas Fai
Qty.
s d s l d s l d s l
Sub grade
150
Procter test 1 m3 0 0 0 0 0 0 0 0 0
0
Atterberg 150
1 m3 0 0 0 0 0 0 0 0 0
Limits 0
Free Swell 150
1 m3 0 0 0 0 0 0 0 0 0
Index 0
Grain Size 150
1 m3 0 0 0 0 0 0 0 0 0
Analysis 0
300
C.B.R 1 m3 0 0 0 0 0 0 0 0 0
0
Granular Sub Base
Gradation 1 200 m3 151 151 0 5 5 0 156 156 0
Atterberg
1 200 m3 151 136 15 5 5 0 151 136 15
Limits
150
Procter test 1 m3 0 0 0 0 0 0 0 0 0
0
Wet Mix
Macadam
Filter
materia
l
Concrete
Cement
Water
Prim
e
Coat
Tack coat
Dense
BituminouTotal test up
Frequenc Total test in This Cumulative No.
to Previous
y of Month of tests
Descriptio Uni Month Remar
tests
n t k s
No. Conducte Pas Fai Conducte Pas Fai Conducte Pas Fai
Qty.
s d s l d s l d s l
s
Macadam
Bituminou
s Concrete
Bitumen
test
DLC
Steel
3.2 Tests conducted by IE / AE
<Quality inspection test results to be reported in a table similar to the table
provided in previous section>4. Monitoring of maintenance obligations during construction phase
4.1 Critical issues and action log
oNS
noitpircseD
eussI
weN/gniognO
eussI
denrecnoC ytirohtuA )s(eganiahC eud
detceffa
eussi
eht
ot
htgneL
detceffa
)mk(
nekat
)s(noitcA
won
llit
)s(noitcA yb
detseggus
CS
etaD
detcepxE
gnivloser
rof
eussi
1 Drying up Ongoing Concessionair e 325+200 2.6 Irregular Replacemen t NA
of plants to watering of plants
on median 327+800 and daily
watering
2 Large New Concessionair e 387+300 0.1 None Filling of <DD/M
potholes LHS potholes M>
4.2 Summary of repair work
Work Work
done upto done
SNo Description Unit Total Balance Remarks
previous during
month reporting
month
1 Carriageway and paved shoulders
(a) Pot Holes Sqm 42 - - 42
(b) Roughness value mm
exceeding 2,500mm
(c ) Cracking in more than 5% Sqm 7179 - - 7179
of road surface
(d) Rutting exceeding 10mm Sqm 5 - - 5
in more than 2% of road
surface
(e) Bleeding/Skiding Sqm
(f) Ravelling Sqm
(g) Damage to pavement m
edges exceeding 10cm
2 Hard/Earth ShouldersWork Work
done upto done
SNo Description Unit Total Balance Remarks
previous during
month reporting
month
(a) Rain cuts/ gullies in slope Cum 650 25 - 625
(b) Edge drop at shoulders m
exceeding 40 mm
3 Drains and culverts
(a) Cleaning of Culvert Nos 1 - - 1
(b) Damage to or silting of
culverts
(c) Silting of drains in
urban/ semi urban areas
4 Road furniture
(a) Sign Boards Nos 456 - - 456
(b) Kilometer Stones
(c ) Metal Beam Crash Barrier
(d) Bus Shelters Nos 72 4 - 68
(e) Junction signs Nos 26 8 - 18
(f) Median Grills Rmt 894 - - 894
(g) Studs Nos 5328 - - 5328
(h) Delinators Nos 8236 - - 8236
(i) Road Marking Sqm 1899 - - 1899
(j) Kerb Painting Sqm 4575 - - 4575
(k) Guard Posts Nos 3657 - - 3657
5 Street lighting and telecom (ATMS)
(a) Street lights Nos
(b) Telecom Nos
6 Trees and plantation
(a) Removal of vegetation Ha 77.42 - 3.57 73.85
affecting sight line and
road structures
(b) Replacement of trees and Nos 15072 - - 15072
bushesWork Work
done upto done
SNo Description Unit Total Balance Remarks
previous during
month reporting
month
7 Buildings and bridges
(a) Rest areas
(b) Toll plazas
(c ) Bridges
4.3 Status of damages
SNo Period Amount of damages (Rs)
1 Upto June 2016
2 Jul 2016
3 Aug 2016
4 Sep 2016
Total
5. Safety features
5.1 Pen picture of safety features
Details to be provided after assessment of the site requirement vis-à-vis
provisions in the Concession Agreement:
Suggested Remedial
Financial implications of
Location of Black Measures within Additional
additional Remedial
Spots provisions of Remedial
Measures for
Concession Measures (if any)
Authority(Cr.)
Agreement5.2 Accident Report
oN
S
etaD on eganiahC
tnedicca
fo
emiT
)F/M(
xeS
A B C D E F G H I J K
No of
affecte
d
persons noitacol
tnediccA
tnedicca
fo
erutaN
fo
noitacifissalC
sesuaC
fo snoitidnoc
daoL
noitidnoc
daoR
fo
epyt
noitcesretnI
noitidnoc
rehtaeW
mitciv
fo
egA
mitciv
fo
epyT
elcihev
fo
epyT
lataF rojaM roniM
yb
dedivorp
pleH
382/050 05:25
1 1/1/17 M 2 2 3 4 1 1 - 1 3 1 3 - 1 1 Ambu
RHS pmMapping of report fields to responses
A 1. Urban 2. Rural
1. Overturned 2. Head On Collision 3. Hit from Back 4. Hit to Fix Object 5. Right turn Collision
B
6. Left turn Collision 7. Veered Out off The Road 8. Hit Pedestrian 9. Unknown/Hit & Ran Away
C 1. Fatal 2. Major injury 3. Minor injury
1. Drunken 2. Over Speeding 3. Vehicle out of Control 4. Driven on wrong side 5. Mechanical
D
Problem 6. Drowsiness/Not Applicable 7. Fault of Driver
E 1. Normally Loaded 2. Overloaded/Handing 3. Empty 4. Unknown
F 1. Straight road 2. Slight Curve 3. Sharp Curve 4. Hump 5. Dip
1. T-Junction 2. Y-Junction 3. Four arm Junction 4. Staggered Junction 5. Junction with more
G
than 6. Round about
1. Fine/Clear 2.Mist/Fog 3. Cloudy 4. Light Rain 5. Heavy Rain 6. Strong Wind 7. Dust Storm 8.
H
Cold 9. Hot
I 1. 0-18 Years 2. 18-25 Years 3. 25-40 Years 4.40-60 Years 5. 60-80 Years
J 1. Driver 2. Passenger 3. Pedestrian 4. Cyclist 5. Others
1. Two Wheeler 2. Auto Rickshaw 3. Car/Jeep 4. Bus 5. Light Truck 6. Heavy Truck 7. Tractor
K
8. Bicycle 9. Cycle Rickshaw 10. Hand Drawn Cart 11. Animal Drawn Cart6. Annexures
Annex 1. Detailed List of Physical Components as per Schedule G
Physical
Component
Item
A- Widening and strengthening of existing road
(1) Earthwork up to top of the sub-grade
(2) Granular work (sub- base, base, shoulders)
(a) GSB
(b) WMM
(3) Shoulders
(4) Bituminous work
(a) DBM
(b) BC
(5) Rigid Pavement
Concrete work
(6) Widening and repair of culverts
(7) Widening and repair of minor bridges
B- New realignment/bypass
(1) Earthwork up to top of the sub-grade
(2) Granular work (sub- base, base, shoulders)
Road works
(a) GSB
including culverts,
(b) WMM
minor bridges,
(3) Shoulders
underpasses,
(4) Bituminous work
overpasses,
(a) DBM
approaches to
(b) BC
ROB/RUB/ Major
(5) Rigid Pavement
Bridges/
Concrete work
Structures (but
C-New culverts, minor bridges, underpasses, overpasses on existing
excluding service road,
roads) realignments, bypasses:
(1) Culverts
(2) Minor bridges
(a) Foundation
(b) Sub-structure
(c) Super-structure (including crash barriers etc. complete)
(3) Cattle/Pedestrian underpasses
(a) Foundation
(b) Sub-structure
(c) Super-structure (including crash barriers etc. complete)
(4) Pedestrian overpasses
(a) Foundation
(b) Sub-structure
(c) Super-structure (including crash barriers etc. complete)
(5) Grade separated structures
(a) UnderpassesPhysical
Component
Item
(i) Foundation
(ii) Sub-structure
(iii) Super-structure (including crash barriers etc.complete)
(b) Overpass
(i) Foundation
(ii) Sub-structure
(iii) Super-structure (including crash barriers etc. complete)
(c) Flyover
(i) Foundation
(ii) Sub-structure
(iii) Super-structure (including crash barriers etc. complete)
(d) Foot over Bridge
A- Widening and repairs of Major Bridges
(1) Foundation
(a) Open Foundation
(b) Pile Foundation/Well Foundation
(2) Sub-structure
(3) Super-structure (including crash barriers etc. complete)
B- Widening and repair of
(a) ROB
(1) Foundation
(2) Sub-structure
(3) Super-structure (including crash barriers etc. complete)
(b) RUB
(1) Foundation
(2) Sub-structure
(3) Super-structure (including crash barriers etc. complete)
MajorBridge works
C- New Major Bridges
and ROB/RUB
(1) Foundation
(a) Open Foundation
(b) Pile Foundation/Well Foundation
(2) Sub-structure
(3) Super-structure (including crash barriers etc. complete)
D- New rail-road bridges
(a) ROB
(1) Foundation
(2) Sub-structure
(3) Super-structure (including crash barriers etc. complete)
(b) RUB
(1) Foundation
(2) Sub-structure
(3) Super-structure (including crash barriers etc. complete)
Structures (1) Foundation
(elevated sections, (2) Sub-structure
reinforced (3) Super-structure (including crash barriers etc. complete)
earth)Physical
Component
Item
(4) Reinforced Earth Wall (includes Approaches of ROB, Underpasses,
Overpasses, Flyover etc.
(i) Service roads/ Slip Roads
(ii) Toll Plaza
(iii) Road side drains
(iv) Road signs, markings, km stones, safety devices, ….
(a)Road signs, markings, km stones, ….
(b) Concrete Crash Barrier/ W-Beam Crash Barrier in Road work
(v) Project facilities
(a) Bus bays
(b) Truck lay-byes
(c) Rest areas
Other Works (vi) Repairs to bridges/structures
(vii) Road side plantation
(viii) Protection works
(a) Boulder Pitching on slopes
(b) Toe/Retaining wall
(ix) Tunnel
(a) Excavation
(b) Construction of support systemincluding rock bolting, lining etc.
(c) On complete completion of tunnel
(x) Miscellaneous
* The above list is illustrative and may require modification as per the
actual scope of the workAnnex 2. Onwards
IE / AE should include comments, status update, data points and reports
in following annexures which have not been included elsewhere in the
main report. Such reports may include but not limited to:
• Review status of drawings/ design reports
• Review status of other documents
• Minutes of review meeting
• Detailed Inspection report of project highway
• Correspondence details
• Weather report
• Organizational chart of Concessionaire / Contractor and IE / AE
• List of lab equipment
• Details of user complaints
• Project photographsANNEXURE-VI - FORMAT FOR MONTHLY PROGRESS REPORT DURING O&M PHASE
[NAME & LOGO OF IMPLEMENTING AGENCY]
[PROJECT NAME (O&M)]
Authority Engineer
[NAME OF CONSULTING FIRM]
MONTHLY STATUS REPORT NO. [XX]
FOR THE MONTH OF: [MONTH], [YEAR]Table of content
Contents Page
Nos.
1 Executive Summary ................................................................................. 156
1.1 Overall road condition 156
1.2 Key reporting metrics 156
1.3 Key maintenance activities undertaken 156
1.4 Pending issues 157
1.5 Recommended actions by Authority Engineer 157
1.6 Strip Plan for maintenance 158
2 Project Overview ..................................................................................... 159
2.1 Key project details 159
2.2 Location Map 160
2.3 Key plan 161
2.4 RoW availability 161
2.5 Summary of project features 162
3 Critical Issues and Action taken ................................................................ 163
3.1 Issue and action log 163
3.2 Summary of items (Cumulative Observations/ Deficiencies) 163
3.3 Obligations as per contract 165
3.4 Major maintenance and Inspection schedule 166
4 Inspection Report .................................................................................... 167
4.1 Summary of NCR issued 167
4.2 Equipment based inspection report 167
5 Monitoring of ETC lanes ........................................................................... 169
5.1 Monthly ETC Report 169
5.2 On-ground infrastructure report 169
5.3 On-ground ETC operations and SLA adherence 170
6 Status of Damages for breach of maintenance activities ............................. 1706.1 Damages for non completion of project facilities 170
6.2 Damages for breach of maintenance activities 171
6.3 Damages for non completion of major maintenance/ periodic overlay
171
7 Change of Scope proposals ...................................................................... 172
8 Status of pending disputes ....................................................................... 172
9 Reports ................................................................................................... 173
9.1 Monthly Toll Collection Report (Applicable only if project highway is tolled)
173
9.2 Accident Report 174
9.3 Details of complaints 176
9.4 Encroachment list 177
9.5 Lane Closure Report 177
10 Annexures ............................................................................................ 1781 Executive Summary
1.1 Overall road condition
Road LHS RHS
condition
Satisfactory road condition 40 km 20 km
Poor road condition 50 km 70 km
Total length of project 90 km 90 km
1.2 Key reporting metrics
Key metrics Value/Amoun
t
No of pending NCRs 35
Damages amount recommended on Concessionaire (Rs Cr) Rs 5.9 Cr
No of pending Change of Scope proposals 2
No of pending disputes 2
Monthly toll collection (Rs Cr) (If applicable) Rs 3.8 Cr
No of accidents 12
No of encroachments 47
1.3 Key maintenance activities undertaken
Asset Maintenance activities
undertaken
• Concessionaire has commenced the work for renewal and repair of pavement
Pavement
on the project highway w.e.f 14th September 2016
Shoulder
Drainage • Cleaning of drainage in built up areas n progress
Median
• Concessionaire has taken up repairs and maintenance of MBCB and electric
Road furniture
poles, etc on issuance of NCPs from Authority Engineer
Bridges
• As per provisions of CA and policy decided by MoRTH/<Agency>, 2 ETC lanes
at each toll plaza have been operationalised w.e.f. 25th September 2016. The
Buildings connectivity of ETC lanes with Central Clearing House (CCH) has been achieved
and presently ETC lanes are operationalized in Hybrid Mode due to less
number of tags purchased by highway users
• Planting of new trees from Chainage 200+300 to 226+650
Horticulture
• Trimming of plants which were causing obstruction to highway users1.4 Pending issues
• Overlay on the entire stretch of project length of 252 km and service roads has not
been taken up by Concessionaire yet since the date of completion of overlay is due
in next 25 days
• Over all progress is very slow regarding repair of potholes and rutting on Main
Carriageway which is causing inconvenience to highway users and is also a concern
from road safety point of view.
• Street lighting in
– Anantapur bypass completed on main carriageway and is energized but
for service roads street lighting is pending on both sides
– Kurnool bypass erection of poles only completed in main carriageway not
yet energized till to date, but for service roads not started
1.5 Recommended actions by Authority Engineer
• In spite of the repeated requests, there is no material change in status of works
pertaining to repairs/ rectifications of defects on the project highway. AE has
recommended the damages of Rs 5.9 Cr on the Concessionaire on account of delay
in repairs of defects in road and bridge works in terms of the provision of Clause
15.8.1 of the Concession Agreement. Concessionaire shall be liable for imposition
of further damages on similar lines till the date of completion
• Concessionaire is requested to take at most care for completing the overlay before
31.03.2017 since the existing road condition is getting deteriorated day by day
causing much inconvenience to the traffic1.6 Strip Plan for maintenance
Satisfactory road condition
(Maintenance not required)
Poor road condition
(Maintenance
required)Main report
2 Project Overview
2.1 Key project details
Project Name
NH no (New/Old)
Mode of the Project
No. of Lanes
Length of the Project
Total Project Cost
Concessionaire/ Contractor
Date of Award (LOA date)
Appointed Date
Commercial Operation Date (COD)
Concession Period
O&M Period
Authority Engineer
AE Agreement Date
AE Mobilization Date
AE Scheduled Completion Date
AE EOT (Extension Of Time)2.2 Location Map
2.3 Key plan
2.4 RoW availability
Width of RoW available on both sides of the highway
WoR
fo
htdiW
-SHL
elbaliava
>20 m
20 m
18 m
16 m 16 16 16 16 16 16 16
14 m
12 m
10 m
8 m 8.2 8.2 8.2 8.2 8.2
6 m
4 m 4.7 4.7 4.7 4.7 4.7
2 m 1.8 1.8
Chainage
WoR
fo
htdiW
-SHR
elbaliava
2 m
4 m
6 m 6.2 6.2 6.2 6.2 6.2 6.2
8 m
10 m 10 10
12 m
14 m
16 m
18 m 17.5 17.5 17.5 17.5 17.5 17.5 17.5 17.5
20 m
>20 m 25 25 252.5 Summary of project features
SNo Particular Value
s
1 No of flyovers 2
2 Service Road 45
3 ROBs 5
261.975, 299.606, 350.547,
4 ROB location (chainage)
396.135 & 420.302
5 RUBs 0
6 RUB location (chainage) NA
7 No of Bypass 7
8 Length of Bypass 43
9 No of Major Bridges 7
10 No of Minor Bridges 67
11 No of Culvert 640
12 No of VUP 16
13 No of PUP/ Cattle Underpass 12
14 No of Major Intersection/ Junction 22
15 No of Toll Plaza 3
16 Location of Toll Plaza (chainage)
17 No of Truck Laybye 30
18 No of Bus Bays 122
19 No of Wayside Amenities 0
20 Location of Wayside Amenities (chainage) NA3 Critical Issues and Action taken
3.1 Issue and action log
oNS
noitpircseD
eussI
weN/gniognO
eussI
denrecnoC ytirohtuA )s(eganiahC eud
detceffa
eussi
eht
ot
htgneL
detceffa
)mk(
nekat
)s(noitcA
won
llit
)s(noitcA yb
detseggus
CS
etaD
detcepxE
gnivloser
rof
eussi
Drying up Replacemen t
of plants Concession 325+200 to Irregular of plants
1 Ongoing 2.6 NA
on aire 327+800 watering and daily
median watering
Large Concession 387+300 Filling of <DD/M
2 New 0.1 None
potholes aire LHS potholes M>
3.2 Summary of items (Cumulative Observations/ Deficiencies)
Work Work
done upto done
SNo Description Unit Total Balance Remarks
previous during
month reporting
month
1 Carriageway and paved shoulders
(a) Pot Holes Sqm 42 - - 42
(b) Roughness value mm
exceeding 2,500mm
(c ) Cracking in more than 5% Sqm 7179 - - 7179
of road surface
(d) Rutting exceeding 10mm Sqm 5 - - 5
in more than 2% of road
surface
(e) Bleeding/Skiding Sqm
(f) Ravelling Sqm
(g) Damage to pavement m
edges exceeding 10cm
2 Hard/Earth Shoulders
(a) Rain cuts/ gullies in slope Cum 650 25 - 625Work Work
done upto done
SNo Description Unit Total Balance Remarks
previous during
month reporting
month
(b) Edge drop at shoulders m
exceeding 40 mm
3 Drains and culverts
(a) Cleaning of Culvert Nos 1 - - 1
(b) Damage to or silting of
culverts
(c) Silting of drains in
urban/ semi urban areas
4 Road furniture
(a) Sign Boards Nos 456 - - 456
(b) Kilometer Stones
(c ) Metal Beam Crash Barrier
(d) Bus Shelters Nos 72 4 - 68
(e) Junction signs Nos 26 8 - 18
(f) Median Grills Rmt 894 - - 894
(g) Studs Nos 5328 - - 5328
(h) Delinators Nos 8236 - - 8236
(i) Road Marking Sqm 1899 - - 1899
(j) Kerb Painting Sqm 4575 - - 4575
(k) Guard Posts Nos 3657 - - 3657
5 Street lighting and telecom (ATMS)
(a) Street lights Nos
(b) Telecom Nos
6 Trees and plantation
(a) Removal of vegetation Ha 77.42 - 3.57 73.85
affecting sight line and
road structures
(b) Replacement of trees and Nos 15072 - - 15072
bushes
7 Buildings and bridges
(a) Rest areas
(b) Toll plazas
(c ) Bridges3.3 Obligations as per contract
Please write a summary of contractual obligations of Concessionaire and non-
compliances of critical obligations highlighting reasons for delay and stating pending
actions
• Critical obligations of Concessionaire as per contract
• Non compliances of critical contractual obligations3.4 Major maintenance and Inspection schedule
Item Responsibility Last completed Due date
on
Major maintenance Concessionaire [DD/MM/YY] [DD/MM/YY]
Periodic overlay Concessionaire [DD/MM/YY] [DD/MM/YY]
Pavement
inspection Authority Engineer [DD/MM/YY] [DD/MM/YY]
using NSV
Roughness using
Authority Engineer [DD/MM/YY] [DD/MM/YY]
Laser Profilometer
Pavement
Authority Engineer [DD/MM/YY] [DD/MM/YY]
strength using
FWD
Bridge inspection
Authority Engineer [DD/MM/YY] [DD/MM/YY]
using MBIU
Road sign
inspection Authority Engineer [DD/MM/YY] [DD/MM/YY]
using
Reflectometer
Other4 Inspection Report
4.1 Summary of NCR issued
Total NCR
NCR issued in NCR closed in
issued till Balance NCR
SNo Highway reporting reporting
previous (A+B-C)
asset month (B) month (C)
month
(A)
1 Pavement 48 12 25 35
2 Shoulder 7 0 3 4
3 Drainage
4 Median
5 Road furniture
6 Bridges
7 Buildings
8 Horticulture
9 [Other assets]
Total
4.2 Equipment based inspection report
Pavement Surface Defects Roughness Pavement Strength
gnitratS eganiahC gnidnE eganiahC rebmun
enaL
)mc( skcarC )mc( selohtoP )mc( gnilevaR )mc( gnideelB htped gnittuR )mm( htped erutxeT )mm( dikS ecnatsiseR )mm( IRI lanoitanretnI( ssenhguoR )xednI citsalE suludoM suonimutiB cit s1aElE suludoM citsalE suludoM edarGbuS
0.000 0.500 L1 2X10 20X35 2.5X1.2 4X12 25 1.4 4.23 7110 34 14
0.500 1.000 L1 3X5 10X15 1.5X0.8 3X10 24 1.8 2.68 7430 36 15
1.000 1.500 L1
Report of equipment based inspection needs be provided as an Annexure to
monthly report as per the defined frequency. Following documents/media to be
submitted for equipment based inspection.
• Video footage of all cameras installed on Network Survey Vehicle- ROW cameras
and pavement camera
• Network Survey Vehicle report capturing dimensions of following key metrics
of pavement– Cracks
– Potholes
– Raveling
– Bleeding
– Rutting
– Texture depth
– Skid resistance
– Roughness (IRI)
• Falling Weight Deflectometer (FWD) report capturing following key metrics
of pavement strength
– Deflection Bowl (Transient Deflections at seven different points)
– Corrected Elastic Modulus Bituminous E1
– Corrected Elastic Modulus Granular E2
– Corrected Elastic Modulus Subgrade E3
– Subgrade CBR
– Bituminous layer coefficient A1
– Base layer coefficient A2
– Granular base layer coefficient A3
– Modified structural number
• Mobile Bridge Inspection Report (MBIU) capturing following key metrics of bridges
– Condition Approach
– Condition Signs
– Condition Debris
– Condition Joint
– Condition Deck
– Condition Rails
– Condition Protect
– Condition Stream
– Condition Superstructure
– Condition Piers
– Condition Abutment
• Retro reflectometer report capturing following key metrics of road furniture
– Coefficient of retroreflected luminance R A (night time retroreflection) of
road traffic signs5 Monitoring of ETC lanes
5.1 Monthly ETC Report
For
TYPE OF VEHICLE Corresponding For Previous Month For Current Month
month of previous
year
No of Fee No of Fee Fee No of Fee
vehicles Collected vehicles Collected per vehicles Collected
vehicle
A Car Total 3845 384500 4659 465,900.00 100 4289 428,900.00
B LCV Total 1521 243360 1312 209,920.00 160 1399 223,840.00
C Bus Total 2404 793386 2284 765,207.00 201 2349 786,915.00
D Truck Total 1603 528924 1523 510,138.00 134 1566 524,610.00
E 3 Axle Total 18990 6836400 16310 5,953,150.00 365 15127 5,521,355.00
F MAV Total 16119 8381880 21111 11,188,830.00 530 18790 9,958,700.00
Over
G Total 1 630 27 17,280.00 640 36 23,040.00
Size
Total for the
49844 18,050,61 52963 19,898,834 49016 18,265,66
Month
8 1
5.2 On-ground infrastructure report
Total number of plaza lanes =
Total number of dedicated ETC
lanes = Total number of hybrid
lanes =
Equipment as
Units Equipment
Tota Units per
SNo Description damaged owner/ Remark
l working specifications
/ provider s
unit (Y/N)
missing
s
1 Hardware
(a) Over-head transceiver 4 3 1 ABC Co. Y
(b) Hand-held reader
(c ) Lane controller
(d) AVC
(e) Camera
(f) Weigh-in-motion
(g) Static weigh bridge(h) Any other items
2 SoftwaresEquipment as
Units Equipment
Tota Units per
SNo Description damaged owner/ Remark
l working specification
/ provider s
unit s (Y/N)
missing
s
(a) Software – Lane/ Plaza
level
(b) TMS
(c) Any other items
5.3 On-ground ETC operations and SLA adherence
Average Average
Average
queue queue Average Average Average Average
transctio
Lane length length Transactio transaction transactio transactio
n time
during during n time time n time n time
(others)
peak time non peak (cash) (RFID) (cards) (wallet)
time
UPI – 20
Lane 1 10 vehicles 5 vehicles 15 seconds 10 seconds 20 seconds 25 seconds
seconds
Lane 2
Lane 3
• Average system uptime = 80%
• Transactions uploaded (as per SLA) = 80%
• Blacklists uploaded (as per SLA) = 50%
• Blacklists downloaded (as per SLA) = 85%
6 Status of Damages for breach of maintenance activities
6.1 Damages for non completion of project facilities
SNo Period Amount of damages
(Rs)
1 Upto June 2016 15,00,35,000
2 Jul 2016 2,00,88,000
3 Aug 2016 2,00,88,000
4 Sep 2016 1,94,40,000
Total 20,96,51,000
Supporting Calculations for damages for Sep 2016
• No of days in Sep = 30
• Performance security is Rs 64,80,00,000
• As per CA Clause 12.3.2 damages payable is 0.1% of performance
security per day = Rs 6,48,000
• Total damages payable = 30 X 6,48,000 = Rs 1,94,40,0006.2 Damages for breach of maintenance activities
SNo Period Amount of damages (Rs)
1 Upto June 2016 1,00,35,000
2 Jul 2016 6.63,196
3 Aug 2016 6,63,196
4 Sep 2016 52,22,444
Total 1,65,83,836
Supporting Calculations for damages for reporting month
oN
S
fo
erutaN tcefed tinU latoT
ytitnauQ
etaR
riaper
o tsoC
detamitse
sa
sa
segamaD
AC rep
ta
segamaD edis
rehgih fo etaD
noitcepsni
sa
syad
fo
oN
AC rep
segamaD
morf
syad
fo
oN
segamad segamaD tnuoma
6.3 Damages for non completion of major maintenance/ periodic overlay
SNo Period Amount of damages (Rs)
1 June 2016 6,48,000
2 Jul 2016 2,00,88,000
3 Aug 2016 2,00,88,000
4 Sep 2016 1,94,40,000
Total 6,02,64,000
Supporting Calculations for damages for Sep 2016
• No of days in Sep = 30
• Performance security is Rs 64,80,00,000
• As per CA Clause 12.3.2 damages payable is 0.1% of performance security per
day = Rs 6,48,000
• Total damages payable = 30 X 6,48,000 = Rs 1,94,40,0007 Change of Scope proposals
Date of Expected
SN
Proposal Details first Current status COS Amount / Actual
o
submission date of
to AE approval
Approved in principle by
Construction of [Flyover [DD/MM/YYYY Authority. Detailed [DD/MM/YYY
1 [+/- Amount]
Name] at [Chainage] ] quantitSCs in proper order Y]
yet to be submitted
Clarifications to be
Nallah diversion through
[DD/MM/YYYY submitted by [DD/MM/YYY
2 box culvert at [+/- Amount]
] Concessionaire, expected Y]
[Chainage]
date [DD/MM/YYYY]
8 Status of pending disputes
Date of first Dispute
SN Curren
Dispute Details submission Suggested resolution by AE Amount (if
o t
to AE applicable)
stage
Increased tollable
No merit in increasing tollable
length to be
1 [DD/MM/YYYY] length hence no action required NA SAROD
applicable in toll fee
by <Agency>
calculations
Filling stations B/w
<Agency>to consider the
energized without Concession
2 [DD/MM/YYYY] Concessionaire's request for [+/-
obtaining NOC from aire and
intervention and assistance Amount]
ministry <Agency>9 Reports
9.1 Monthly Toll Collection Report (Applicable only if project highway is tolled)
For
TYPE OF VEHICLE Corresponding For Previous Month For Current Month
month of previous
year
Fee
No of Fee No of Fee No of Fee
per
vehicles Collected vehicles Collected vehicles Collected
vehicl
e
Single 3845 384500 4659 465,900.00 100 4289 428,900.00
A Car Return 1506 218370 1972 295,800.00 150 1758 263,700.00
Local 769 38450 979 48,950.00 50 1029 51,450.00
Single 1521 243360 1312 209,920.00 160 1399 223,840.00
B LCV Return 134 31490 162 38,880.00 240 132 31,680.00
Local 1683 134640 1838 147,040.00 80 1461 116,880.00
Single 2404 793386 2284 765,207.00 201 2349 786,915.00
C Bus Return 359 177903 173 87,567.00 303 203 102,717.00
Local 277 45738 205 34,782.00 102 318 54,060.00
Single 1603 528924 1523 510,138.00 134 1566 524,610.00
D Truck Return 240 118602 116 58,378.00 202 136 68,478.00
Local 185 30492 136 23,188.00 68 212 36,040.00
Single 18990 6836400 16310 5,953,150.00 365 15127 5,521,355.00
E 3 Axle Return 131 70740 34 18,700.00 550 37 20,350.00
Local 69 12420 84 15,540.00 185 131 24,235.00
Single 16119 8381880 21111 11,188,830.00 530 18790 9,958,700.00
F MAV Return 2 1550 20 15,800.00 790 35 27,650.00
Local 6 1560 18 4,770.00 265 8 2,120.00
Single 1 630 27 17,280.00 640 36 23,040.00
G
Over
Return 0 0 - 965 -
Size
Local 0 0 - 320 -
Total for the
49844 18,050,61 52963 19,898,834 49016 18,265,66
Month
8 19.2 Accident Report
oN
S
etaD
on
eganiahC
tnedicca
fo
emiT
)F/M(
xeS
A B C D E F G H I J K
No of
affecte
d
persons
noitacol
tnediccA
tnedicca
fo
erutaN
tnedicca
fo
noitacifissalC
sesuaC
elcihev
fo
snoitidnoc
daoL
noitidnoc
daoR
lortnoc
fo
epyt
noitcesretnI
noitidnoc
rehtaeW
mitciv
fo
egA
mitciv
fo
epyT
elcihev
fo
epyT
lataF ojaM
r
oniM
r
yb
dedivorp
pleH
382/050 05:25
1 1/1/17 M 2 2 3 4 1 1 - 1 3 1 3 - 1 1 Ambu
RHS pmMapping of report fields to responses
A 1. Urban 2. Rural
B 1. Overturned 2. Head On Collision 3. Hit from Back 4. Hit to Fix Object 5. Right turn Collision
6. Left turn Collision 7. Veered Out off The Road 8. Hit Pedestrian 9. Unknown/Hit & Ran Away
C 1. Fatal 2. Major injury 3. Minor injury
D 1. Drunken 2. Over Speeding 3. Vehicle out of Control 4. Driven on wrong side 5. Mechanical
Problem 6. Drowsiness/Not Applicable 7. Fault of Driver
E 1. Normally Loaded 2. Overloaded/Handing 3. Empty 4. Unknown
F 1. Straight road 2. Slight Curve 3. Sharp Curve 4. Hump 5. Dip
G 1. T-Junction 2. Y-Junction 3. Four arm Junction 4. Staggered Junction 5. Junction with more
than 6. Round about Junction
H 1. Fine/Clear 2.Mist/Fog 3. Cloudy 4. Light Rain 5. Heavy Rain 6. Strong Wind 7. Dust Storm 8.
Cold 9. Hot
I 1. 0-18 Years 2. 18-25 Years 3. 25-40 Years 4.40-60 Years 5. 60-80 Years
J 1. Driver 2. Passenger 3. Pedestrian 4. Cyclist 5. Others
K 1. Two Wheeler 2. Auto Rickshaw 3. Car/Jeep 4. Bus 5. Light Truck 6. Heavy Truck 7. Tractor
8. Bicycle 9. Cycle Rickshaw 10. Hand Drawn Cart 11. Animal Drawn Cart9.3 Details of complaints
Contact
Toll Complaint Name of the Details of Compliance by the
SNo Date details
plaz No person complaint concessionaire
of
a
person
Mr. Shailendra Mr. Shailendra
Gurjar, LIG- Complaints
44,RSS regarding Pot holes Pot holes are
1 81 8/9/2016
mohalla, on the Highway repaired
Shivaji Nagar, may cause
Bhopal (M.P.) accidents.
Dr. Diwakar
Animals are
Dr. Anil complaints that
continuously driven
Diwakar, HIG presence of
out from the Road
Swarganga Animals and also
2 82 10/9/2016 by the Highway
Complex Bus Pot holes on road
Patrolling team and
Stand Seoni are obstructing the
Pot holes are
(M.P.) driving which may
repaired.
cause accidents.
The Exemption
under Indian Toll
(Army and Air
Maj. Sidharth while force) Act 1901, to
travelling in army personnel
Maj. Sidharth, personal car wants travelling in private
3 83 11/9/2016 238 Fd wksp Exemption from vehicle may be
C/o- 56 APO Toll Fee on given if on Govt.
production of I.D. duty with requisite
Card pass as specified
in the Indian Toll
(Army and Air
Force Rules, 1942)9.4 Encroachment list
oNS
)mk(
eganiahC
hctertS
)SHR/SHL(
ediS
tcirtsiD
/
lisheT egalliV
epyt
tnemhcaorcnE
)tnenamreP
/yraropmeT(
,llats
aeT(
yrogetaC
)cte
,elpmeT /weN(
tnemhsilbatsE
)gnitsixe
)m(
egde
daor
morf
ecnatsiD
dna
htdiw
tnemhcaorcnE
htgnel
rehcaorcnE
fo
emaN
212+50 Temporar Tea Vijay Kumar
1 LHS Kurnool Kurnool New 7 5mX3.5m
0 y stall Reddy
213+20 Dinnedevara Permanen Godow 10.5m X
2 RHS Kurnool Existing 5 Buddana
0 Padu t n 4m
9.5 Lane Closure Report
S.No Date Chainage (Km) Side Time of Closure Reasons for Lane Remarks
Closure & Approval
From To Details
9/9/201 215+30 215+35
1 RHS 1pm-4pm Patch work
6 0 010 Annexures
Annexure 1: Detailed visual inspection report of project highway
Assets to be covered- Pavement, Shoulder, Drainage, Median, Bridges,
Road furniture, Buildings, Horticulture, Service Road
Description
SNo NCP/ Date of Chainage Side AE Remarks
of defect
SNo issue
1 311 15.08.2016 Potholes 311+200 LHS To be repaired
To be filled
2 312 15.08.2016 Cracking 311+500 RHS
immediately
3
4
Annexure 2 onwards:
AE should include comments, status update, data points and reports in
following annexures which have not been included elsewhere in the main
report. Such reports may include but not limited to:
• Minutes of review meeting
• Correspondence details
• Weather report
• Organizational chart of Concessionaire and AE
• Project photographsAnnexure VII-OUTPUT FORMAT FROM NETWORK SURVEY VEHICLE AND
FWD TESTING
[NAME & LOGO OF IMPLEMENTING AGENCY]
[PROJECT NAME]
Authority Engineer
[NAME OF CONSULTING FIRM]
OUTPUT FROM NETWORK SURVEY VEHICLE AND FWD TESTINGTable of contents
Contents Page Nos.
SECTION ROAD INVENTORY DATA
1
161
1.1. Location Reference Post (LRP) Master 161
1.2. Carriageway Type 162
1.3. Road Type 162
1.4. Pavement Type 163
1.5. Pavement Width 164
1.6. Shoulder Type 165
1.7. Shoulder Width 166
1.8. Topography 166
1.9. Cross Section 167
1.10. Drain Type 168
1.11. Median Opening 169
1.12. Right Of Way 170
1.13. Pavement composition 171
1.14. Carriageway Furniture 173
1.15. Wayside Amenities 174
1.16. Land Use 175
SECTION ROAD CONDITION DATA 176
2
2.1. Visual condition 176
2.2. Roughness 179
2.3. Rutting 180
2.4. Texture Depth 181
2.5. Skid Resistance 182
2.6. Falling Weight Deflectometer (FWD) 183
2.7. Falling Weight Deflectometer (FWD) Rigid 187Annexure VII: OUTPUT FORMAT FROM NETWORK SURVEY VEHICLE AND
FWD TESTING (SECTION 1: TESTING AT TIME OF COMPLETION, SECTION 2:
FWD ATTRIBUTES - ANNUALLY, BALANCE PARAMETERS –BIANNUALLY
AFTER CONSTRUCTION PHASE)
In addition to the reports being submitted on equipment based inspection as
specified in Section 4.2 of the Monthly Progress Report in the O&M phase, the
Authority Engineer (AE) shall submit electronically in excel (.xls) format certain key
parameters to the Project Director in the following format.
Worksheets under Section 1 (‘Road inventory data’) shall be updated from surveys
conducted only once at the time of completion testing. Worksheets under Section 2
(‘Road condition data’) shall be updated from surveys carried out annually for FWD
attributes and biannually for the remaining attributes.
The fields to be updated in each of the worksheets are described below. Each
description is followed by an example of data for a sample project.
SECTION 1 - ROAD INVENTORY DATA
Road inventory data consists of parameters which provide basic information about
roads such as pavement type, number of lanes, topography, etc. These parameters
are largely static in nature, and therefore a survey to update this dataset shall be
conducted only once at the time of completion testing. The road inventory data shall
be used to update specific worksheets listed below.
1.1 Location Reference Post (LRP) Master
The following table lists the fields which need to be populated for the ‘LRP Master’
attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
LRP Name Name of location reference post (LRP) Km stone 17
Chainage Chainage of the survey point (in km) 17
Direction Direction of survey Increasing
• Increasing (chainage)
• Decreasing (chainage)
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Old NH Number Old National Highway number NH0065
Section Code HYD-VIJ (Hyderabad-
Code indicating starting and ending locations of section
Vijayawada)A sample output is shown below for reference
NH Survey Old NH Section
LRP Name Chainag Direction Latitud Longitude Altitude
Numbe Date Numbe Code
e e
r r
NH0xxx Road Start 1.230 Increasing 9.98897 78.02671 63.07767 23-12-15 NH0yyy ABC-DEF
NH0xxx Km Stone 8 8.000 Increasing 9.98444 78.02934 68.60126 23-12-15 NH0yyy ABC-DEF
NH0xxx Km Stone 8 8.030 Increasing 9.98341 78.03004 68.15520 23-12-15 NH0yyy ABC-DEF
NH0xxx Km Stone 9.008 Increasing 9.98107 78.03078 65.17153 23-12-15 NH0yyy ABC-DEF
NH0xxx Km Stone 12.012 Increasing 9.96328 78.04160 56.03436 23-12-15 NH0yyy ABC-DEF
NH0xxx Km Stone 17 17.085 Increasing 9.95385 78.05255 56.24748 23-12-15 NH0yyy ABC-DEF
1.2 Carriageway Type
The following table lists the fields which need to be populated for the
‘Carriageway Type’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
HYD-VIJ
Section Code Code indicating starting and ending locations of section (Hyderabad-
Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Type of carriageway, classified into one of the below Divided
categories:
Carriageway Type
• Divided
• Undivided
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference
Start End Carriagewa Date of
NHNumbe Section Latitude Longitude
Chainage Chainage y Survey
r
Type
NH00xx ABC-DEF 0.000 0.794 Undivided 06-05-17 9.98897 78.02671
NH00xx ABC-DEF 0.794 1.000 Undivided 06-05-17 9.98444 78.02934
NH00xx ABC-DEF 1.000 2.810 Undivided 06-05-17 9.98341 78.03004
NH00xx ABC-DEF 2.810 4.335 Undivided 06-05-17 9.98107 78.03078
NH00xx ABC-DEF 4.335 6.666 Undivided 06-05-17 9.96328 78.04160
NH00xx ABC-DEF 6.666 12.906 Undivided 06-05-17 9.95385 78.052551.3 Road Type
The following table lists the fields which need to be populated for the ‘Road
Type’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code
section Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Classification of road on basis of number of lanes Four Lane
• Single Lane
• Two Lane
Road Type
• Intermediate Lane
• Four Lane
• Six Lane
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
Start End Date of
NHNumbe Section RoadType Latitud Longitude
Chainage Chainage Survey
r e
NH00xx ABC-DEF 0.000 0.794 Two Lane 06-05-17 9.98897 78.02671
NH00xx ABC-DEF 0.794 1.000 Two Lane 06-05-17 9.98444 78.02934
NH00xx ABC-DEF 1.000 2.810 Two Lane 06-05-17 9.98341 78.03004
NH00xx ABC-DEF 2.810 4.335 Two Lane 06-05-17 9.98107 78.03078
NH00xx ABC-DEF 4.335 6.666 Two Lane 06-05-17 9.96328 78.04160
NH00xx ABC-DEF 6.666 12.906 Two Lane 06-05-17 9.95385 78.05255
1.4 Pavement Type
The following table lists the fields which need to be populated for the
‘Pavement Type’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code
section Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
Direction • Increasing (chainage)
• Decreasing (chainage)
Pavement Type Classification of pavement based on type of surface: AsphaltField Description Example
• Asphalt
• Cement concrete
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
Start End Pavement Date
NHNumbe Section Directio Latitud Longitude
Chainage Chainage Type of
r n e
Survey
ABC-
NH00xx 0.000 0.804 Both Asphalt 06-05-17 9.98897 78.02671
DEF
ABC-
NH00xx 0.804 1.000 Both Asphalt 06-05-17 9.98444 78.02934
DEF
ABC-
NH00xx 1.000 1.172 Both Asphalt 06-05-17 9.98341 78.03004
DEF
ABC-
NH00xx 1.172 2.821 Both Asphalt 06-05-17 9.98107 78.03078
DEF
ABC-
NH00xx 2.821 4.350 Both Asphalt 06-05-17 9.96328 78.04160
DEF
ABC-
NH00xx 4.350 6.710 Both Asphalt 06-05-17 9.95385 78.05255
DEF
ABC-
NH00xx 6.710 12.925 Both Asphalt 06-05-17 9.93102 78.05648
DEF
1.5 Pavement Width
The following table lists the fields which need to be populated for the
‘Pavement Width’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code
section Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
Direction • Increasing (chainage)
• Decreasing (chainage)
Width of the pavement in metres, classified into one of >7m and <10.5m
the below categories
• >= 3.75m and < 5.5m
Pavement Width • >5.5m and < 7m
• >= 7m and < 10.5m
• >=10.5m and <=12.5m
• > 12.5m
Width of the pavement in metres, rounded to two 7.0
Pavement Width Value
places after decimalField Description Example
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
Pavemen
Section Start End Pavement Survey
NH Directio t Latitud Longitud
Code Chainage Chainage Width Date
Number n Widt e e
h
Value
NH00xx ABC-DEF 0.000 0.794 Both 7 – 10.5 m 7.00 06-05-17 9.98897 78.02671
NH00xx ABC-DEF 0.794 1.000 Both 7 – 10.5 m 7.00 06-05-17 9.98444 78.02934
NH00xx ABC-DEF 1.000 2.810 Both 7 – 10.5 m 7.00 06-05-17 9.98341 78.03004
NH00xx ABC-DEF 2.810 4.335 Both 7 – 10.5 m 7.00 06-05-17 9.98107 78.03078
NH00xx ABC-DEF 4.335 6.666 Both 7 – 10.5 m 7.00 06-05-17 9.96328 78.04160
NH00xx ABC-DEF 6.666 12.906 Both 7 – 10.5 m 7.00 06-05-17 9.95385 78.05255
1.6 Shoulder Type
The following table lists the fields which need to be populated for the
‘Shoulder Type’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code section Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
• Increasing (chainage)
Direction • Decreasing (chainage)
Type of shoulder, classified into one of the below Gravel
categories:
• None
• Paved
• Gravel
Shoulder Type • Earth
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
Section End
NH Start Directio ShoulderType Survey Latitud Longitude
Code Chainage
Number Chainage n Date e
NH00xx ABC-DEF 0.000 0.763 Increasing No Shoulder 09-01-16 9.98897 78.02671
NH00xx ABC-DEF 0.763 0.834 Increasing Gravel 09-01-16 9.98444 78.02934NH00xx ABC-DEF 0.834 1.254 Increasing Gravel 09-01-16 9.98341 78.03004
NH00xx ABC-DEF 1.254 2.945 Increasing Gravel 05-01-16 9.98107 78.03078
NH00xx ABC-DEF 2.945 4.327 Increasing Gravel 05-01-16 9.96328 78.04160
NH00xx ABC-DEF 4.327 4.405 Increasing Gravel 05-01-16 9.95385 78.05255
NH00xx ABC-DEF 4.405 6.844 Increasing Gravel 05-01-16 9.93102 78.05648
NH00xx ABC-DEF 6.844 9.359 Increasing Gravel 05-01-16 9.91229 78.04961
NH00xx ABC-DEF 9.359 12.966 Increasing Gravel 05-01-16 9.89041 78.03458
1.7 Shoulder Width
The following table lists the fields for the ‘Shoulder Width’ attribute, which
need to be populated. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code section Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
• Increasing (chainage)
Direction • Decreasing (chainage)
Width of the shoulder in metres, classified into one of < 1m
the below categories
• No shoulder
• < 1m
• >= 1m and <= 2m
Shoulder Width • > 2m
Width of the shoulder in metres, rounded to one place 0.5
Shoulder Width Value after decimal
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
Shoulder
Section Start End Shoulder Survey
NH Direction Width Latitude Longitude
Code Chainage Chainage Width Date
Number Value
No
NH0xxx ABC-DEF 0.000 0.785 Increasing 0.0 03-01-16 9.98897 78.02671
Shoulder
No
NH0xxx ABC-DEF 0.785 2.612 Increasing 0.0 03-01-16 9.98444 78.02934
Shoulder
NH0xxx ABC-DEF 2.612 3.170 Increasing 1-2m 2.0 03-01-16 9.98341 78.03004
NH0xxx ABC-DEF 3.170 5.194 Increasing 1-2m 2.0 03-01-16 9.98107 78.03078
NH0xxx ABC-DEF 5.194 6.793 Increasing 1-2m 2.0 03-01-16 9.96328 78.04160
NH0xxx ABC-DEF 6.793 11.404 Increasing 1-2m 2.0 03-01-16 9.95385 78.052551.8 Topography
The following table lists the fields which need to be populated for the
‘Topography’ attribute. The descriptions of the fields are given below.
Field Descriptio Example
n
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code section Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Topography of the road, classified into one of the Flat
below categories
• Flat
• Rolling
Topography • Hilly
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
Section Start End Survey
NH Topography Latitud Longitude
Code Chainage Chainage Date
Number e
NH0xxx ABC-DEF 0.000 0.808 Flat 05-01-16 9.98897 78.02671
NH0xxx ABC-DEF 0.808 1.254 Flat 05-01-16 9.98444 78.02934
NH0xxx ABC-DEF 1.254 2.828 Flat 05-01-16 9.98341 78.03004
NH0xxx ABC-DEF 2.828 4.363 Flat 05-01-16 9.98107 78.03078
NH0xxx ABC-DEF 4.363 6.724 Flat 05-01-16 9.96328 78.04160
NH0xxx ABC-DEF 6.724 12.933 Flat 05-01-16 9.95385 78.05255
1.9 Cross Section
The following table lists the fields which need to be populated for the ‘Cross
Section’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code section Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
• Increasing (chainage)
Direction • Decreasing (chainage)
Cross section type, classified into one of the below Fill
Cross Section categoriesField Description Example
• Cut
• Fill
• Cut and Fill
• Level
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
Section Start End
NH Direction Cross Section Survey Latitud Longitude
Code Chainage Chainage
Number Date e
NH0xxx ABC-DEF 0.000 0.822 Increasing Level 03-01-16 9.98897 78.02671
NH0xxx ABC-DEF 0.822 2.642 Increasing Level 03-01-16 9.98444 78.02934
NH0xxx ABC-DEF 2.642 3.199 Increasing Level 03-01-16 9.98341 78.03004
NH0xxx ABC-DEF 3.199 5.360 Increasing Level 03-01-16 9.98107 78.03078
NH0xxx ABC-DEF 5.360 5.715 Increasing Fill 03-01-16 9.96328 78.04160
NH0xxx ABC-DEF 5.715 6.941 Increasing Level 03-01-16 9.95385 78.05255
NH0xxx ABC-DEF 6.941 11.163 Increasing Level 03-01-16 9.93102 78.05648
1.10 Drain Type
The following table lists the fields which need to be populated for the ‘Drain
Type’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code section Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
• Increasing (chainage)
Direction • Decreasing (chainage)
Type of drain, classified into one of the below Open lined drain
categories
• Open unlined drain
• Open lined drain
• Covered line drain
Drain Type • No drain
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671A sample output is shown below for reference:
NH Section Start End Direction Drain Type Survey Latitud Longitud
Number Code Chainage Chainage Date e e
Open Unlined
NH0xxx ABC-DEF 0.000 0.069 Increasing 09-01-16 9.98897 78.02671
Drain
NH0xxx ABC-DEF 0.069 0.782 Increasing Open Lined Drain 09-01-16 9.98444 78.02934
Open Unlined
NH0xxx ABC-DEF 0.288 0.000 Decreasing 09-01-16 9.98341 78.03004
Drain
Open Unlined
NH0xxx ABC-DEF 0.782 0.846 Increasing 09-01-16 9.98107 78.03078
Drain
Open Unlined
NH0xxx ABC-DEF 0.846 1.254 Increasing 09-01-16 9.96328 78.04160
Drain
Open Unlined
NH0xxx ABC-DEF 1.254 2.265 Increasing 05-01-16 9.95385 78.05255
Drain
Open Unlined
NH0xxx ABC-DEF 1.929 0.288 Decreasing 09-01-16 9.93102 78.05648
Drain
NH0xxx ABC-DEF 1.952 1.929 Decreasing No Drain 09-01-16 9.91229 78.04961
Open Unlined
NH0xxx ABC-DEF 2.265 3.005 Increasing 05-01-16 9.89041 78.03458
Drain
Open Unlined
NH0xxx ABC-DEF 2.680 1.952 Decreasing 09-01-16 9.88489 78.02995
Drain
Open Unlined
NH0xxx ABC-DEF 3.005 4.424 Increasing 05-01-16 9.87474 78.02828
Drain
Open Unlined
NH0xxx ABC-DEF 3.109 2.680 Decreasing 09-01-16 9.87363 78.02744
Drain
Covered Line
NH0xxx ABC-DEF 3.320 3.109 Decreasing 09-01-16 9.84857 78.01535
Drain
Open Unlined
NH0xxx ABC-DEF 3.917 3.320 Decreasing 09-01-16 9.83764 78.00392
Drain
Open Unlined
NH0xxx ABC-DEF 4.424 4.601 Increasing 05-01-16 9.83711 77.98576
Drain
Open Unlined
NH0xxx ABC-DEF 4.601 5.693 Increasing 05-01-16 9.83386 77.97729
Drain
1.11 Median Opening
The following table lists the fields which need to be populated for the ‘Median
Opening’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code section Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
• Increasing (chainage)
Direction • Decreasing (chainage)
Type of median, classified into one of the below Raised
categories
• Raised;
• Depressed;
• Barrier;
• None.
Median TypeField Description Example
Width of the median in metres, rounded to one place 0.5
Median Width after decimal
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
Section Start End Median Median Survey
NH Direction Latitud Longitud
Code Chainage Chainage Type Width Date
Number e e
NH00xx ABC-DEF 0.000 0.794 Both Raised 0.5 05-01-16 9.98897 78.02671
NH00xx ABC-DEF 0.794 1.000 Both Raised 0.5 05-01-16 9.98444 78.02934
NH00xx ABC-DEF 1.000 2.810 Both No Median 0.0 05-01-16 9.98341 78.03004
NH00xx ABC-DEF 2.810 4.335 Both Raised 1.5 05-01-16 9.98107 78.03078
NH00xx ABC-DEF 4.335 6.666 Both No Median 0.0 05-01-16 9.96328 78.04160
NH00xx ABC-DEF 6.666 12.906 Both No Median 0.0 05-01-16 9.95385 78.05255
1.12 Right Of Way
The following table lists the fields which need to be populated for the ‘Right of
Way’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code section Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
• Increasing (chainage)
Direction • Decreasing (chainage)
Row Width Width of Right of Way (in metres) 24
Remarks
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
Section Start End ROW Survey
NH Direction Remark Latitud Longitude
Code Chainage Chainage Width Date
Number s e
NH0xxx ABC-DEF 0.000 1.000 Increasing 28 05-05-15 9.98897 78.02671
NH0xxx ABC-DEF 1.000 2.000 Increasing 24 05-05-15 9.98444 78.02934
NH0xxx ABC-DEF 2.000 3.000 Increasing 30 05-05-15 9.98341 78.03004
NH0xxx ABC-DEF 3.000 4.000 Increasing 26 05-05-15 9.98107 78.03078
NH0xxx ABC-DEF 4.000 11.000 Increasing 24 05-05-15 9.96328 78.041601.13 Pavement composition
The following table lists the fields which need to be populated for the ‘Pavement
composition’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code
section Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
Direction • Increasing (chainage)
• Decreasing (chainage)
Type of pavement Asphalt
Pavement Type • Asphalt
• Cement concrete
Bituminous Surface Type of bituminous surface course BC
Course Type
Bituminous Surface Thickness of BSC layer in mm 40
Course Thickness MM
BSC Construction Year Year of construction of BSC layer in flexible pavements 2015
Bituminous Base Type of bituminous base course DBM
Course Type
Bituminous Base Thickness of BBC layer in mm 100
Course Thick—ness
BBC Construction Year Year of construction of BBC layer in flexible pavements 2015
Granular Base Type Type of granular base WMM
Granular Base Thick- Thickness of GB layer in mm 250
ness
GB Construction Year Year of construction of GB layer in flexible pavements 2015
Pavement Quality Type of pavement quality concrete PQC
Concrete Type
Pavement Quality Thickness of PQC layer in mm 300
Concrete Thickness
PQC Construction Year Year of construction of PQC layer in rigid pavements 2015
Dry Lean Concrete Thickness of DLC layer in mm 100
Thickness MM
Dry Lean Concrete Type of dry lean concrete DLC
Type
DLC Construction Year Year of construction of DLC layer in rigid pavements 2015
Granular Sub Base Type of granular sub base GSB
Type
Granular Sub Base Thickness of GSB layer in mm 200
Thickness
GSB Construction Year Year of construction of GSB layer 2014
Design CBR Design CBR of the subgrade, expressed in % 5%
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897Field Description Example
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
Bitumino
Bitumino Bitumino BSC Bitumin BBC Granula
Sec- Star End us Base Granu
NH Direc Pavem u s u s Constru o us Constru r Base
tion t Chai Course l ar
No. - e nt Surface Surface c-tion Base c-tion Thickne
Code Chai nag Thicknes Base
tion Type Course Course Year Course Year ss
nag e s Type
Type Thickness Type
e
NH00x ABC- Both
0.0 5.0 Asphalt BC 40.0 2015 DBM 100 2015 WMM 250
x DEF side
NH00x ABC- Both
5.0 11.0 Asphalt BC 40.0 2015 DBM 80 2015 WMM 250
x DEF side
NH00x ABC- Both
11.0 20.0 Asphalt SDBC 25.0 2015 BM 115 2015 WMM 250
x DEF side
NH00x ABC- Both
20.0 22.0 Asphalt BC 40.0 2015 DBM 100 2015 WMM 250
x DEF side
NH00x ABC- Both
22.0 30.0 Asphalt SDBC 25.0 2015 BM 115 2015 WMM 250
x DEF side
NH00x ABC- Both
30.0 31.0 Asphalt BC 40.0 2015 DBM 100 2015 WMM 250
x DEF side
(table continued…)
Pavem
Dry
GB
Pavem e nt
PQC Lean Dry DLC Granul
Granul
GSB
e nt Quality a r Desi
Const Const Concre Lean Const ar Constr Surve Lati Longi
Quality Concre SubBas g n
r r t e Concrer SubBa u ction y t t ude
Concre t e e CBR
uctio uctio Thickn t e uctio s e Year Date ude
t e Type Thickn Thickn
n Year n ess Type n Type
e e ss
Year Year
ss
05-05-
2015 NA NA NA NA NA NA GSB 300 2015 5% 9.99 78.03
15
05-05-
2015 NA NA NA NA NA NA GSB 300 2015 5% 9.98 78.03
15
05-05-
2015 NA NA NA NA NA NA GSB 300 2015 5% 9.98 78.03
15
05-05-
2015 NA NA NA NA NA NA GSB 300 2015 5% 9.98 78.03
15
05-05-
2015 NA NA NA NA NA NA GSB 300 2015 5% 9.96 78.04
15
05-05-
2015 NA NA NA NA NA NA GSB 300 2015 5% 9.95 78.05
15
1.14 Carriageway Furniture
The following table lists the fields which need to be populated for the ‘Carriageway
Furniture’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code
section Vijayawada)
Chainage Chainage of the point (in km) 0.500
Direction of survey Increasing
Direction • Increasing (chainage)
• Decreasing (chainage)Field Description Example
Wayside amenities classified into one of the below Road sign
categories:
• Crash barriers
Wayside Amenity Type
• Signs
• Street Lights
• Km stone
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
NHNumbe SectionCode Chainage Direction EventType SurveyDat Latitud Longitude
r e e
Street Light
NH00xx ABC-DEF 0.012 Increasing 03-01-16 9.98897 78.02671
Start
Street Light
NH00xx ABC-DEF 0.287 Increasing 03-01-16 9.98444 78.02934
End
NH00xx ABC-DEF 2.491 Decreasing Road Sign 03-01-16 9.98341 78.03004
NH00xx ABC-DEF 2.708 Decreasing Road Sign 03-01-16 9.98107 78.03078
NH00xx ABC-DEF 3.496 Increasing Road Sign 03-01-16 9.96328 78.04160
NH00xx ABC-DEF 5.160 Increasing Road Sign 03-01-16 9.95385 78.05255
NH00xx ABC-DEF 5.356 Decreasing Road Sign 03-01-16 9.93102 78.05648
NH00xx ABC-DEF 8.402 Decreasing Road Sign 03-01-16 9.91229 78.04961
NH00xx ABC-DEF 10.966 Decreasing Road Sign 03-01-16 9.89041 78.03458
1.15 Wayside Amenities
The following table lists the fields which need to be populated for the ‘Wayside
Amenities’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code
section Vijayawada)
Chainage Chainage of the point (in km) 0.500
Direction of survey Increasing
Direction • Increasing (chainage)
• Decreasing (chainage)
Wayside amenities classified into one of the below Restaurant/Motel
categories:
• Bus shelter;
• Culverts;
Wayside Amenity • Restaurant/Motel;
• Toilet/Public convenience;
• Rest Rooms for short stay;
• Toll Plaza;
• First aid/Medical centre;Field Description Example
• Telephone booth;
• Petrol pump/minor repair shop (optional);
• Police Station;
• Temple /Mosque;
• Bridges.
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Data Source
Remarks
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
NH Section Survey Data
Chainage Direction Wayside Remark Latitude Longitude
Number Code Date Source
Amenity s
ABC-
NH00xx 0.650 Increasing Restaurant/Motel 05-01-16 9.98897 78.02671
DEF
ABC-
NH00xx 1.998 Increasing Restaurant/Motel 05-01-16 9.98444 78.02934
DEF
ABC-
NH00xx 5.524 Increasing Petrol Pump 05-01-16 9.98341 78.03004
DEF
ABC-
NH00xx 11.413 Increasing Restaurant/Motel 05-01-16 9.98107 78.03078
DEF
1.16 Land Use
The following table lists the fields which need to be populated for the ‘Land
Use’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code
section Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
Direction • Increasing (chainage)
• Decreasing (chainage)
Land use classified into one of the below categories: Commercial
• Residential;
• Commercial;
Land Use • Industrial;
• Agricultural;
• Water bodies;
• Mixed.
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897Field Description Example
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
NHNumbe SectionCode StartChainag EndChainage Direction LandUse SurveyDat Latitude Longitud
r e e e
NH00xx ABC-DEF 0.000 0.797 Increasing Mixed 03-01-16 9.98897 78.02671
NH00xx ABC-DEF 0.511 0 Decreasing Mixed 03-01-16 9.98444 78.02934
NH00xx ABC-DEF 0.797 2.699 Increasing Mixed 03-01-16 9.98341 78.03004
NH00xx ABC-DEF 0.835 0.511 Decreasing Mixed 03-01-16 9.98107 78.03078
NH00xx ABC-DEF 0.987 0.835 Decreasing Mixed 03-01-16 9.96328 78.04160
NH00xx ABC-DEF 1.641 0.987 Decreasing Agriculture 03-01-16 9.95385 78.05255
Barren
NH00xx ABC-DEF 2.081 1.641 Decreasing 03-01-16 9.93102 78.05648
Land
NH00xx ABC-DEF 2.378 2.081 Decreasing Agriculture 03-01-16 9.91229 78.04961
NH00xx ABC-DEF 2.458 2.378 Decreasing Agriculture 03-01-16 9.89041 78.03458
NH00xx ABC-DEF 2.699 3.234 Increasing Agriculture 03-01-16 9.88489 78.02995
SECTION 2 - ROAD CONDITION DATA
Road condition data consists of parameters which directly affect maintenance
requirements of the road. These parameters are dynamic in nature, and therefore a
survey to update this dataset shall be conducted annually for FWD testing and every
six months as per Annexure IV for network survey vehicle testing. The first survey
shall be conducted at the time of completion testing and the remaining surveys shall
be conducted as per the defined frequency.
As an example, if majority of highway length (>50%) passes through a state, where
defined survey months are May and November, if completion testing is conducted
in April, then the first network survey shall be conducted in the month of April. This
shall be considered as the network survey to be conducted in the month of May.
The 2nd survey shall be conducted in the month of November, the 3rd survey shall be
conducted in the month of May and so on. As regards FWD, the first test/survey
shall be conducted at the time of completion in April. The 2nd test/survey shall be
conducted in April of next year and so on.
The road condition data shall be used to update specific worksheets, which are listed below.
2.1 Visual condition
The following table lists the fields which need to be populated for the ‘Visual
Condition’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065Field Description Example
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code
section Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
Direction • Increasing (chainage)
• Decreasing (chainage)
Number of the lane: L1, L2, R1, R2, etc., L1 being 1st L1
Lane Number lane on the left from centreline of carriageway, L2 being
2nd lane on the left from centerline and so on
Percent of pavement area affected by ravelling, which 2
is converted to the following rating scale:
• 1 - Very Poor (> 30%)
Ravelling • 2 - Poor (11-30%)
• 3 - Fair (6-10%)
• 4 - Good (1-5%)
• 5 - Very Good (0%)
No. of potholes, which is converted to the following 1
rating scale:
• 1 - Very Poor (> 5)
Pot Holes • 2 - Poor (3-5)
• 3 - Fair (2)
• 4 - Good (1)
• 5 - Very Good (0)
Pavement area containing edge breaks, which is 3
converted to the following rating scale:
• 1 - Very Poor (> 5m2)
Edge Break • 2 - Poor (1-5m2)
• 3 - Fair (0.5-1m2)
• 4 - Good (0-0.5m2)
• 5 - Very Good (0m2)
Percent of pavement area affected by cracking, which 3
is converted to the following rating scale:
• 1 - Very Poor (> 30%)
Cracking • 2 - Poor (21-30%)
• 3 - Fair (11-20%)
• 4 - Good (5-10%)
• 5 - Very Good (<5%)
Percent of pavement area affected by disintegration, 2
which is converted to the following rating scale:
• 1 - Very Poor (> 50%)
Disintegration • 2 - Poor (20-50%)
• 3 - Fair (10-20%)
• 4 - Good (1-10%)
• 5 - Very Good (<1%)Field Description Example
Percent of pavement area affected by depression, 5
which is converted to the following rating scale:
• 1 - Very Poor (> 5%)
Depression • 2 - Poor (3-5%)
• 3 - Fair (1-2%)
• 4 - Good (0-1%)
• 5 - Very Good (0)
Percent of pavement area affected by bleeding, which 3
is converted to the following rating scale:
• 1 - Very Poor (> 50%)
Bleeding • 2 - Poor (20-50%)
• 3 - Fair (10-20%)
• 4 - Good (1-10%)
• 5 - Very Good (<1%)
Percent of pavement area affected by patching, which 4
is converted to the following rating scale:
• 1 - Very Poor (> 30%)
Patching • 2 - Poor (16-30%)
• 3 - Fair (6-15%)
• 4 - Good (2-5%)
• 5 - Very Good (<2%)
Condition of the drain, which is converted to 2
the following rating scale:
Drain Condition • 1 - Poor
• 2 - Fair
• 3 - Good
Condition of the shoulder, which is converted to the Fair
following rating scale:
Shoulder Condition • 1 - Poor
• 2 - Fair
• 3 - Good
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
Start End Lane
NHNumbe Section Directio Ravelling PotHoles EdgeBreak Cracking
Chainage Chainage Numbe
r n r
NH00xx ABC-DEF 0.000 0.500 Increasing L1 4 4 4 4
NH00xx ABC-DEF 0.500 1.000 Increasing L1 4 4 4 5
NH00xx ABC-DEF 1.000 1.500 Increasing L1 5 5 4 5
NH00xx ABC-DEF 1.500 2.000 Increasing L1 5 5 5 5
NH00xx ABC-DEF 2.000 2.500 Increasing L1 5 5 5 5
NH00xx ABC-DEF 2.500 3.000 Increasing L1 5 5 4 5
NH00xx ABC-DEF 3.000 3.500 Increasing L1 5 5 4 5
NH00xx ABC-DEF 3.500 4.000 Increasing L1 5 4 3 5Start End Lane
NHNumbe Section Direction Ravelling PotHoles EdgeBreak Cracking
Chainage Chainage Numbe
r r
NH00xx ABC-DEF 4.000 4.500 Increasing L1 4 4 4 5
NH00xx ABC-DEF 4.500 5.000 Increasing L1 5 5 4 5
NH00xx ABC-DEF 5.000 5.500 Increasing L1 5 5 4 5
NH00xx ABC-DEF 5.500 6.000 Increasing L1 5 5 4 5
NH00xx ABC-DEF 6.000 6.500 Increasing L1 5 5 4 5
NH00xx ABC-DEF 6.500 7.000 Increasing L1 5 5 4 5
NH00xx ABC-DEF 7.000 7.500 Increasing L1 5 5 5 5
NH00xx ABC-DEF 7.500 8.000 Increasing L1 5 5 4 5
NH00xx ABC-DEF 8.000 8.500 Increasing L1 5 5 4 5
NH00xx ABC-DEF 8.500 9.000 Increasing L1 5 5 4 5
NH00xx ABC-DEF 9.000 9.500 Increasing L1 5 5 4 5
NH00xx ABC-DEF 9.500 10.000 Increasing L1 5 5 3 5
(table continued…)
Drain Date of
Disintegratio Depression Bleeding Patching ShoulderConditio Latitude Longitude
Condition Survey
n n
4 4 4 4 2 2 06-05-17 9.98897 78.02671
4 4 4 4 2 2 06-05-17 9.98444 78.02934
5 5 5 4 2 2 06-05-17 9.98341 78.03004
5 5 5 5 2 2 06-05-17 9.98107 78.03078
5 5 5 5 2 2 06-05-17 9.96328 78.04160
5 5 5 5 2 2 06-05-17 9.95385 78.05255
5 5 5 5 2 3 06-05-17 9.93102 78.05648
4 4 4 4 2 3 06-05-17 9.91229 78.04961
4 4 4 4 2 2 06-05-17 9.89041 78.03458
5 5 5 5 2 2 06-05-17 9.88489 78.02995
5 5 5 5 2 2 06-05-17 9.87474 78.02828
5 5 5 5 2 2 06-05-17 9.87363 78.02744
5 5 5 5 2 2 06-05-17 9.84857 78.01535
5 5 5 5 2 2 06-05-17 9.83764 78.00392
5 5 5 5 2 2 06-05-17 9.83711 77.98576
5 5 5 5 1 2 06-05-17 9.83386 77.97729
5 5 5 5 2 2 06-05-17 9.81804 77.97875
5 5 5 5 2 2 06-05-17 9.77426 77.98129
5 4 4 4 2 2 06-05-17 9.73071 77.97999
5 5 5 3 2 2 06-05-17 9.68686 77.97017
2.2 Roughness
The following table lists the fields which need to be populated for the
‘Roughness’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
Code indicating starting and ending locations of HYD-VIJ (Hyderabad-
Section Code
section Vijayawada)Field Description Example
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
Direction • Increasing (chainage)
• Decreasing (chainage)
LwpIri International roughness index (IRI) of left wheel 2.33
path measured from laser profilometer
RwpIri International roughness index (IRI) of right wheel path 1.97
measured from laser profilometer
LaneIri Average of the International roughness index (IRI) 2.15
of left and right wheel paths
Speed Speed of vehicle in km/h 42
Survey Date
Date of survey in the format <DD-MM-YYYY> 06-05-17
Latitude
Latitude of survey point 9.98897
Longitude
Longitude of survey point 78.02671
A sample output is shown below for reference:
NH Section Start End Lane Survey
Directio LwpIrRwpIr LaneIr Speed LatitudLongitude
Numbe Code ChainageChainage Numbe Date
r
n
r
i i i e
ABC- 06-05-
NH00xx 0.0 0.1 Increasing L1 3.31 5.16 4.24 20 9.98897 78.02671
DEF 17
ABC- 06-05-
NH00xx 0.1 0.2 Increasing L1 2.81 3.54 3.18 37 9.98444 78.02934
DEF 17
ABC- 06-05-
NH00xx 0.2 0.3 Increasing L1 2.31 1.92 2.12 42 9.98341 78.03004
DEF 17
ABC- 06-05-
NH00xx 0.3 0.4 Increasing L1 2.17 2.37 2.27 46 9.98107 78.03078
DEF 17
ABC- 06-05-
NH00xx 0.4 0.5 Increasing L1 2.11 1.72 1.92 42 9.96328 78.04160
DEF 17
ABC- 06-05-
NH00xx 0.5 0.6 Increasing L1 2.33 1.97 2.15 49 9.95385 78.05255
DEF 17
ABC- 06-05-
NH00xx 0.6 0.7 Increasing L1 2.37 2.00 2.19 42 9.93102 78.05648
DEF 17
ABC- 06-05-
NH00xx 0.7 0.8 Increasing L1 2.15 2.17 2.16 33 9.91229 78.04961
DEF 17
ABC- 06-05-
NH00xx 0.8 0.9 Increasing L1 2.45 2.05 2.25 32 9.89041 78.03458
DEF 17
ABC- 06-05-
NH00xx 0.9 1.0 Increasing L1 2.18 2.51 2.35 48 9.88489 78.02995
DEF 17
2.3 Rutting
The following table lists the fields which need to be populated for the ‘Rutting’
attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
HYD-VIJ (Hyderabad-
Section Code Code indicating starting and ending locations of section
Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500Field Description Example
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
Direction • Increasing (chainage)
• Decreasing (chainage)
Number of the lane: L1, L2, R1, R2, etc., L1 being 1st L1
Lane Number lane on the left from centreline of carriageway, L2 being
2nd lane on the left from centerline and so on
Rutting Left Rut depth in mm, measured from left wheel path 20
Rutting Right Rut depth in mm, measured from left wheel path 18
Rutting Avg Average rut depth measured from left and right wheel 19
paths
Speed Speed of vehicle in km/h 42
Survey Date Date of survey in the format <DD-MM-YYYY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
NH Section Start End Lane Ruttin Ruttin Ruttin Survey
Directio Speed Latitud Longitud
Numbe Code ChainageChainage Numbe g g g Date
r n r Left Right Avg e e
ABC- 06-05-
NH00xx 0.0 0.5 Increasing L1 15 14 15 20 9.98897 78.02671
DEF 17
ABC- 06-05-
NH00xx 0.5 1.0 Increasing L1 20 18 19 37 9.98444 78.02934
DEF 17
ABC- 06-05-
NH00xx 1.0 1.5 Increasing L1 10 8 9 42 9.98341 78.03004
DEF 17
ABC- 06-05-
NH00xx 1.5 2.0 Increasing L1 5 6 6 46 9.98107 78.03078
DEF 17
ABC- 06-05-
NH00xx 2.0 2.5 Increasing L1 10 10 10 42 9.96328 78.04160
DEF 17
ABC- 06-05-
NH00xx 2.5 3.0 Increasing L1 7 5 6 49 9.95385 78.05255
DEF 17
ABC- 06-05-
NH00xx 3.0 3.5 Increasing L1 20 18 19 42 9.93102 78.05648
DEF 17
ABC- 06-05-
NH00xx 3.5 4.5 Increasing L1 5 5 5 33 9.91229 78.04961
DEF 17
ABC- 06-05-
NH00xx 4.5 5.0 Increasing L1 5 5 5 32 9.89041 78.03458
DEF 17
2.4 Texture Depth
The following table lists the fields which need to be populated for the
‘Texture Depth’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
HYD-VIJ (Hyderabad-
Section Code Code indicating starting and ending locations of section
Vijayawada)
Start Chainage Chainage of the start point (in km) 0.500Field Description Example
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
Direction • Increasing (chainage)
• Decreasing (chainage)
Number of the lane: L1, L2, R1, R2, etc., L1 being 1st L1
Lane Number lane on the left from centreline of carriageway, L2 being
2nd lane on the left from centerline and so on
Texture Left Texture depth of pavement in mm, measured from left 0.40
wheel path
Texture Right Texture depth of pavement in mm, measured from left 0.30
wheel path
Texture Average Average texture depth measured from left and right 0.35
wheel paths
Speed Speed of vehicle in km/h 42
Survey Date Date of survey in the format <DD-MM-YYYY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
NH Section Start End Lane TexturTextur Texture Survey
Direction Speed Latitud Longitud
Numbe Code Chainag Chainage Numbe e e Average Date
r e r Left Right e e
ABC- 06-05-
NH00xx 0.0 0.5 Increasing L1 0.40 0.30 0.35 20 9.98897 78.02671
DEF 17
ABC- 06-05-
NH00xx 0.5 1.0 Increasing L1 0.60 0.50 0.55 37 9.98444 78.02934
DEF 17
ABC- 06-05-
NH00xx 1.0 1.5 Increasing L1 0.80 0.90 0.85 42 9.98341 78.03004
DEF 17
ABC- 06-05-
NH00xx 1.5 2.0 Increasing L1 0.40 0.40 0.4 46 9.98107 78.03078
DEF 17
ABC- 06-05-
NH00xx 2.0 2.5 Increasing L1 0.30 0.30 0.3 42 9.96328 78.04160
DEF 17
ABC- 06-05-
NH00xx 2.5 3.0 Increasing L1 0.70 0.60 0.65 49 9.95385 78.05255
DEF 17
ABC- 06-05-
NH00xx 3.0 3.5 Increasing L1 0.40 0.50 0.45 42 9.93102 78.05648
DEF 17
ABC- 06-05-
NH00xx 3.5 4.5 Increasing L1 0.90 0.80 0.85 33 9.91229 78.04961
DEF 17
ABC- 06-05-
NH00xx 4.5 5.0 Increasing L1 0.40 0.30 0.35 32 9.89041 78.03458
DEF 17
2.5 Skid Resistance
The following table lists the fields which need to be populated for the ‘Skid
Resistance’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
HYD-VIJ (Hyderabad-
Section Code Code indicating starting and ending locations of section
Vijayawada)Field Description Example
Start Chainage Chainage of the start point (in km) 0.500
End Chainage Chainage of the end point (in km) 1.500
Direction of survey Increasing
Direction • Increasing (chainage)
• Decreasing (chainage)
Number of the lane: L1, L2, R1, R2, etc., L1 being 1st L1
Lane Number lane on the left from centreline of carriageway, L2 being
2nd lane on the left from centerline and so on
Skid Left Skid resistance of pavement measured as skid 25
number, measured from left wheel path
Skid Right Skid resistance of pavement measured as skid number, 24
measured from left wheel path
Skid Average Average skid resistance measured from left and right 24.5
wheel paths
Speed Speed of vehicle in km/h 42
Survey Date Date of survey in the format <DD-MM-YYYY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
NH Section Start End Lane Skid Skid Skid Surve
Directio Speed Latitud Longitud
Numbe Code Chainage Chainag Number Left Right Averag y
r e n e Date e e
ABC- 06-05-
NH00xx 0.0 0.5 Increasing L1 25.0 24.0 24.5 20 9.98897 78.02671
DEF 17
ABC- 06-05-
NH00xx 0.5 1.0 Increasing L1 23.0 23.0 23.0 37 9.98444 78.02934
DEF 17
ABC- 06-05-
NH00xx 1.0 1.5 Increasing L1 23.0 24.0 23.5 42 9.98341 78.03004
DEF 17
ABC- 06-05-
NH00xx 1.5 2.0 Increasing L1 22.0 22.0 22.0 46 9.98107 78.03078
DEF 17
ABC- 06-05-
NH00xx 2.0 2.5 Increasing L1 20.0 21.0 20.5 42 9.96328 78.04160
DEF 17
ABC- 06-05-
NH00xx 2.5 3.0 Increasing L1 24.0 24.0 24.0 49 9.95385 78.05255
DEF 17
ABC- 06-05-
NH00xx 3.0 3.5 Increasing L1 28.0 28.0 28.0 42 9.93102 78.05648
DEF 17
ABC- 06-05-
NH00xx 3.5 4.5 Increasing L1 21.0 21.0 21.0 33 9.91229 78.04961
DEF 17
ABC- 06-05-
NH00xx 4.5 5.0 Increasing L1 25.0 24.0 24.5 32 9.89041 78.03458
DEF 17
2.6 Falling Weight Deflectometer (FWD)
The following table lists the fields which need to be populated for the ‘FWD’
attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065Field Description Example
HYD-VIJ (Hyderabad-
Section Code Code indicating starting and ending locations of section
Vijayawada)
Chainage Chainage of survey point (in km) 0.500
Direction of survey Increasing
Direction • Increasing (chainage)
• Decreasing (chainage)
Number of the lane: L1, L2, R1, R2, etc., L1 being 1st lane on the L1
Lane Number left from centreline of carriageway, L2 being 2nd lane on the left
from centerline and so on
Air Temperature Air temperature recorded in °C 33
Surface Temperature Temperature of the pavement surface, recorded in °C 39.3
Peak Load Peak impulse load, measured in kN 45.7
Deflection0 Surface deflection at the test load center, measured in micron 246
Surface deflection at location 1 from the test load center,
Deflection1
measured in micron 110
Distance1 Distance of location 1 from the test load center 300
Surface deflection at location 2 from the test load center,
Deflection2
measured in micron 153
Distance2 Distance of location 2 from the test load center 600
Surface deflection at location 3 from the test load center,
Deflection3
measured in micron 110
Distance3 Distance of location 3 from the test load center 900
Surface deflection at location 4 from the test load center,
Deflection4
measured in micron 76
Distance4 Distance of location 4 from the test load center 1200
Surface deflection at location 5 from the test load center,
Deflection5
measured in micron 59
Distance5 Distance of location 5 from the test load center 1500
Surface deflection at location 6 from the test load center,
Deflection6
measured in micron 44
Distance6 Distance of location 6 from the test load center 1800
Surface deflection at location 7 from the test load center,
Deflection7
measured in micron 35
Distance7 Distance of location 7 from the test load center 2100
Surface deflection at location 8 from the test load center,
Deflection8
measured in micron 28
Distance8 Distance of location 8 from the test load center 2400
Elastic Modulus
BituminousE1
Elastic modulus of bituminous layer, back calculated in MPa 3359
Elastic Modulus
GranularE2
Elastic modulus of granular layer, backcalculated in MPa 396
Elastic Modulus
Elastic modulus of subgrade, back calculated in MPa 90
SubGradeE3Field Description Example
Corrected Elastic
Corrected elastic modulus of bituminous layer in MPa 3424
Modulus BituminousE1
Corrected Elastic
Modulus GranularE2 Corrected elastic modulus of granular layer in MPa 300
CorrectedElasticModul
Corrected elastic modulus of subgrade in MPa 69
usSubGradeE3
Bituminous Layer Thickness of bituminous layer in mm 105
Base Layer Thickness of base layer in mm 230
GSB Layer Thickness of GSB layer in mm 200
Subgrade CBR CBR of subgrade 0.08
BituminousLayerCoeffic
Layer coefficient of the bituminous layer
ientA1 0.36
BaseLayerCoefficientA 2
Layer coefficient of the base layer
0.17
GranularBaseLayerCoe
Layer coefficient of the GSB layer
fficientA3 0.17
Structural Number Structural number of the pavement 3.86
Modified Structural
Modified structural number including contribution from subgrade
Number 4.85
Survey Date Date of survey in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:
Pe
NH Lane Air Surface
Sectio Chainag Directi a k Deflectio Deflectio Locatio Deflectio
Numb Numb Temperatu Temperatu
n Code e o n Loa n 0 n 1 n 1 n 2
e r e r r e r e
d
ABC-
NH00xx 0.500 RHS R2 32.6 43.7 45.7 333 188 300 243
DEF
ABC-
NH00xx 1.000 LHS L1 29.9 32.6 45.4 317 163 300 217
DEF
ABC-
NH00xx 1.499 RHS R1 33.0 39.3 45.7 246 110 300 153
DEF
ABC-
NH00xx 2.000 LHS L2 28.7 32.4 46.0 293 130 300 187
DEF
ABC-
NH00xx 2.500 RHS R2 33.7 45.8 45.3 429 232 300 316
DEF
ABC-
NH00xx 3.000 LHS L1 29.0 33.0 45.7 343 204 300 252
DEF
ABC-
NH00xx 3.500 RHS R1 33.5 45.4 44.5 373 194 300 268
DEF
ABC-
NH00xx 4.010 LHS L2 28.9 33.5 45.0 348 201 300 254
DEF
ABC-
NH00xx 4.500 RHS R2 33.3 40.3 46.0 393 241 300 301
DEF
(table continued…)Locatio Deflectio Locatio Deflectio Locatio Deflectio Locatio Deflectio Locatio Deflectio Locatio Deflectio
n 2 n 3 n 3 n 4 n 4 n 5 n 5 n 6 n 6 n 7 n 7 n 8
600 180 900 128 1200 102 1500 75 1800 58 2100 42
600 158 900 104 1200 70 1500 48 1800 38 2100 28
600 110 900 76 1200 59 1500 44 1800 35 2100 28
600 126 900 81 1200 62 1500 44 1800 32 2100 23
600 227 900 152 1200 116 1500 86 1800 71 2100 58
600 196 900 144 1200 117 1500 85 1800 65 2100 48
600 187 900 118 1200 83 1500 47 1800 31 2100 22
600 198 900 135 1200 105 1500 64 1800 42 2100 26
600 231 900 162 1200 123 1500 82 1800 62 2100 46
(table continued…)
Sub
Loca ElasticMod ElasticMod ElasticMod CorrectedElasti CorrectedElast CorrectedElast Bitum Bas GS gra
tionulusBitumi ulusGranul ulusSubGra c i i i eLa BLa de
8 nousE1 arE2 deE3 ModulusBitumi cModulusGran cModulusSubGr nousL yer yer CB
n ousE1 ularE2 adeE3 ayer R
2400 6213 185 100 6447 135 78 105 230 200 0.08
2400 5356 195 100 5295 143 78 105 230 200 0.08
2400 3359 396 90 3424 300 69 105 230 200 0.08
2400 4830 226 100 4770 169 78 105 230 200 0.08
2400 4570 137 97 4781 93 75 105 230 200 0.08
2400 8454 135 100 8374 91 78 105 230 200 0.08
2400 4394 165 100 4590 117 78 105 230 200 0.08
2400 7817 139 96 7762 95 74 105 230 200 0.08
2400 7666 123 95 7847 81 73 105 230 200 0.08
(table continued…)
Granular Base Modifie
Bituminous Layer Base Layer Structura Survey
Layer d Latitude Longitud
Coefficient A1 CoefficientA2 l Date
Coefficient A3 Structura e
Number
l
Number
0.45 0.13 0.13 3.68 4.82 01-07-16 9.98897 78.02671
0.42 0.13 0.13 3.56 4.70 23-06-16 9.98444 78.02934
0.36 0.17 0.17 3.86 4.85 01-07-16 9.98341 78.03004
0.41 0.14 0.14 3.65 4.79 23-06-16 9.98107 78.03078
0.41 0.11 0.11 3.24 4.34 01-07-16 9.96328 78.04160
0.49 0.11 0.11 3.58 4.72 23-06-16 9.95385 78.05255
0.40 0.12 0.12 3.34 4.48 01-07-16 9.93102 78.05648
0.48 0.12 0.12 3.67 4.75 23-06-16 9.91229 78.04961
0.48 0.11 0.11 3.53 4.59 01-07-16 9.89041 78.03458
2.7 Falling Weight Deflectometer (FWD) RigidThe following table lists the fields which need to be populated for the ‘FWD
Rigid’ attribute. The descriptions of the fields are given below.
Field Description Example
NH Number New National Highway number NH0065
HYD-VIJ (Hyderabad-
Code indicating starting and ending locations of section
Section Code Vijayawada)
Chainage Chainage of the point (in km) 0.500
Direction of survey Increasing
• Increasing (chainage)
Direction • Decreasing (chainage)
Lane Number Number of the lane: L1, L2, R1, R2, etc. L2
Air Temperature Air temperature recorded in °C 30.1
Surface Temperature Temperature of the pavement surface, recorded in °C 39.4
Peak Load Peak impulse load, measured in kN 103.7
Deflection1 Surface deflection at the test load center, measured in micron 140
Surface deflection at 300 mm from the test load center, measured
Deflection2 in micron 121
Surface deflection at 600 mm from the test load center, measured
Deflection3 in micron 108
Surface deflection at 900 mm from the test load center, measured
Deflection4 in micron 101
Concrete Slab
Thicknessh Thickness of concrete slab, measured in mm 300
Area of deflection basin, calculated from measured deflections, in
Area of Deflection
Basin cm2 761
Radius of Relative
Stiffness Radius of relative stiffness, calculated in mm 823
NormalizedDeflectiond Normalized deflection at location 1, in mm 3.1
1
NormalizedDeflectiond 2 Normalized deflection at location 2, in mm 2.9
NormalizedDeflectiond
Normalized deflection at location 3, in mm 2.4
3
NormalizedDeflectiond
Normalized deflection at location 4, in mm 1.9
4
Modulus of Subgrade
Modulus of subgrade reaction, measured in MPa/m 131
Reaction k
Elastic Modulus of
Elastic modulus of concrete, calculated in MPa 26118
Concrete Ec
Cube Strength of Cube strength of concrete, calculated inMPa 27
Concrete fck
Flexural strength of
Flexural strength of concrete, calculated in MPa 3.7
concrete fmr
Date Of Testing Date of testing in the format <DD-MM-YY> 06-05-17
Latitude Latitude of survey point 9.98897
Longitude Longitude of survey point 78.02671
A sample output is shown below for reference:Pea Concrete
Sectio Chain Lan Air Surface
Directi k Deflecti Deflecti Deflecti Deflecti Slab
NH n - e Temperatu Temperatu
o n Loa o n 1 o n 2 o n 3 o n 4 Thickness
No Code -age No. r e r e
d h
NH00x ABC- 104.
0.0 LHS L2 29.0 34.9 167 143 130 119 300
x DEF 1
NH00x ABC- 104.
0.5 RHS R2 30.5 38.1 141 130 122 115 300
x DEF 4
NH00x ABC- 105.
1.0 LHS L1 30.0 35.6 147 111 100 91 300
x DEF 2
NH00x ABC- 102.
1.5 RHS R1 28.9 38.3 140 126 116 107 300
x DEF 4
NH00x ABC- 103.
2.0 LHS L2 30.1 39.4 140 121 108 101 300
x DEF 7
NH00x ABC- 104.
2.5 RHS R2 29.0 37.5 150 134 126 117 300
x DEF 6
NH00x ABC- 102.
3.0 LHS L1 30.6 38.9 124 109 104 92 300
x DEF 7
NH00x ABC- 105.
3.5 RHS R1 29.3 39.1 149 136 128 119 300
x DEF 9
NH00x ABC- 104.
4.5 RHS R2 30.3 41.0 138 127 121 114 300
x DEF 9
(table continued…)
Modul Flexur
Radius Elastic Cube
Area of Normali Normali Normali Normali u s of a l Date
of Modul Streng
Deflect z ed z ed z ed z ed Subgra streng Of Latit Longit
Relativ u s of t h of
i on Deflecti Deflecti Deflecti Deflecti de t h of Testin u de u de
e S Concre Concre
Basin o n d1 o n d2 o n d3 on d4 Reacti concre g
tiffnes te Ec te fck
o n k te fmr
s
25-06- 9.9889 78.0267
759 816 3 3 2 2 112 21590 19 3
16 7 1
28-06- 9.9844 78.0293
821 1214 3 3 3 2 62 58161 135 8
16 4 4
25-06- 9.9834 78.0300
684 580 3 3 2 1 246 12051 6 2
16 1 4
28-06- 9.9810 78.0307
796 1014 3 3 3 2 87 39783 63 6
16 7 8
25-06- 9.9632 78.0416
761 823 3 3 2 2 131 26118 27 4
16 8 0
28-06- 9.9538 78.0525
800 1040 3 3 3 2 79 39908 64 6
16 5 5
25-06- 9.9310 78.0564
789 971 3 3 3 2 107 41290 68 6
16 2 8
28-06- 9.9122 78.0496
814 1150 3 3 3 2 66 50086 100 7
16 9 1
28-06- 9.8904 78.0345
826 1257 3 3 3 2 59 64082 164 9
16 1 8RFP Document - RFP No./ xxxx
Section VI-A: List of Key Experts and Required Qualifications:
RFP Document No. RFP No./ xxxx; Tender Title:
Consultancy Services (Ref ITC-clause 1.4)
Note for Consultants: Regarding this Section, Consultants must fill following forms:
a) Form T-6: Team Composition, Assignment, and Key Experts’ Inputs
b) Annex to Form T-6: Key Expert Curriculum Vitae (CV)
The total estimated inputs of the Key Experts and their breakup is given below:Enclosure-A
MAN MONTHS INPUT FOR KEY PROFESSIONAL STAFF
AUTHORITY ENGINEER
Normal Highway Project
(For projects with length 0-60 km)
S. No. Key Personnel Man-month Man-month in
in Defect
Constructio Liability Period
A: Key Personnel n Period of of 60 months
18 months
Team Leader Cum Senior Highway Engineer 18 15
Resident cum Highway Engineer 18 60
Bridge/Structural Engineer 18 10
Senior Pavement Specialist 18 0
Senior Quality cum Material Expert 18 0
Contract specialist cum planning Engineer 5 3
Road Safety Expert 6 10
Sub Total 101 98
Total for Construction and Maintenance 199
B: Sub Professional Staff
Survey Engineer 18 10
Assistant Highway Engineer (2 Nos) 2 x 18 1 X 60
CAD Expert 4 4
Environmental Engineer 4 0
Assistant Bridge Engineer 18 0
Assistant Quality cum Material Engineer (2 nos) 2 x 18 0
Electrical Engineer 4 3
HTMS/Toll Expert 2 0
Quantity Surveyor 18 8
Horticulture cum Landscaping Expert 6 18
Lab technician 2x18 0
Document/ Data entry Operator 18 0
Sub Total 200 103
Total for Construction and Maintenance 303
Sub Total 182 0
Total for Construction and Maintenance 72
Grand Total 574Note:
1. The other inputs like support staff shall be provided by the Consultant of an acceptable type
commensurate with the roles and responsibilities of each position
2. In case of project having different construction period, Man Month Input shall be adjusted
proportionately
3. The Financial Expert or Legal expert or any other expert as per project requirement may be
required for the project for specific needs. Their deployment shall be arranged by the Consultant
on specific requisition from the Authority and the payment shall be made as per the actual
deployment. The Financial Expert or Legal expert or Contract Specialist shall be paid at the
rates quoted for Senior Pavement Specialist.
MAN - MONTHS INPUT FOR KEY PROFESSIONAL STAFF
AUTHORITY ENGINEER
Normal Highway Project
(For projects with length more than 60 km)
S. No. Key Personnel Man-month in Man-month in
Construction Defect Liability
period of 24 Period of 60
A: Key Personnel
months months
Team Leader Cum Senior Highway Engineer 24 15
Resident cum Highway Engineer (2 nos) 2x24 1x60
Bridge/Structural Engineer 24 15
Senior Pavement Specialist 24 0
Senior Quality cum Material Expert 24 0
Contract Specialist cum planning Engineer 6 3
Road Safety Expert 8 15
Sub Total 158 108
Total for Construction and Maintenance 266
B: Sub Professional Staff
Survey Engineer (3 nos) 3x24 1x10
Assistant Highway Engineer (3 nos) 3x24 1x60
CAD Expert 8 4
Environmental Engineer 6 0
Assistant Bridge Engineer (2 nos) 2 x 24 0
Assistant Quality cum Material Engineer (3 nos) 3 x 24 0
Electrical Engineer 4 3
HTMS/Toll Expert 3 0
Quantity Surveyor 24 8
Horticulture cum Landscaping Expert 8 28
Lab technician 4x24 0
Document/ Data Entry Operator 24 0
Sub Total 437 113
Total for Construction and Maintenance 550Total for Construction and Maintenance 406
Grand Total 783
912
Note:
1. The other inputs like support staff shall be provided by the Consultant of an acceptable type
commensurate with the roles and responsibilities of each position
2. In case of project having different construction period, Man Month Input shall be adjusted
proportionately
3. The Financial Expert or Legal expert or Contract Specialist may be required for the project
for specific needs. Their deployment shall be arranged by the Consultant on specific requisition
from the Authority and the payment shall be made as per the actual deployment. The Financial
Expert or Legal expert or Contract Specialist shall be paid at the rates quoted for Senior
Pavement Specialist.MAN - MONTHS INPUT FOR KEY PROFESSIONAL STAFF
AUTHORITY ENGINEER
Standalone Bridge Project
Man-month in
S. No. Key Personnel Man-month in
Defect Liability
Construction period of
A: Key Personnel Period of 60
36 months
months
1. Team Leader Cum Senior Bridge 36 15
Engineer
2. Resident cum Pavement Specialist 36 60
3. Bridge/Structural Engineer 36 15
4. Senior Contract Specialist cum 10 0
Planning Engineer
5. Senior Quality cum Material Expert 36 0
6. Road Safety Expert 12 10
Sub Total 166 100
26
Total for Construction and 6
Maintenance
B: Sub Professional Staff
(To be decided by the Authority as per
requirement of the Project at the time of
preparation of RFP)
(a)
(b)
(c)
d) Lab technician 36 3
Sub Total
a)
b)
c)
Sub Total
Total for Construction and
Maintenance
Grand Total
Note: The number of key personnel may be modified as per the requirement
with the approval of Competent Authority.MAN - MONTHS INPUT FOR KEY PROFESSIONAL STAFF
AUTHORITY ENGINEER
Standalone Tunnel Project
Man-month
Man-month
S. No. Key Personnel in Defect
in
Liability
A: Key Personnel Constructio
Period of 60
n period of
months
60 months
1. Team Leader Cum Senior Tunnel Expert 60 15
2. Resident cum Excavation Specialist 60 60
3. Senior Geotechnical Expert 60 0
4. Tunnel Design Engineer 60 0
5. Tunnel Safety Expert 60 5
6. Contract Specialist cum planning Engineer 10 0
7. Senior Geologist 20 0
Sub Total 33 80
0
Total for Construction and Maintenance 41
0
B: Sub Professional Staff
(To be decided by the Authority as per requirement of the Project
at the time of preparation of RFP)
Lab technician
Sub Total
(To be decided by the Authority as per requirement of the Project at
the time of preparation of RFP)
Total for Construction and Maintenance
Grand
Total
Note: The number of key personnel may be modified as per the requirement with
the approval of Competent Authority.Enclosure-B
QUALIFICATION OF KEY PERSONNEL
TEAM LEADER CUM SENIOR HIGHWAY ENGINEER
This is the senior most position and the expert engaged as the team leader shall be
responsible for reviewing the entire Project preparation and implementation activities of
the Concessionaire. He shall check all the Designs being prepared by the Concessionaire,
ensure execution of works on site as per specification and standards, and continuously
interact with the <Agency> and the Concessionaire. He shall undertake Project site visits
and shall guide, supervise, coordinate and monitor the work of other experts in his team
as well as those of the Concessionaire. The candidate is required to be a Senior Highway
Engineer, who should have a proven record of supervising, organising and managing of
construction of highway projects and also of Project preparation of large magnitudes
projects, as defined below, financed by international lending agencies and others.
Knowledge of Project management shall be an added advantage.
He should have the following qualification / experience.
1. Essential Qualifications.
a) Graduate in Civil Engineering from recognized university.
b) Total Professional Experience of at least 12 years in handling Highway Projects.
c) At least 5 years experience as Team Leader/Project Manager or similar capacity
in Highway Development Project.
d) He should have handled as Team Leader/Project Manager or similar capacity of
at least two projects in Construction Supervision / IC (of length 40% of project
length or more of similar configuration (2/4/6 laning**)
e) He should have handled as Team Leader or similar capacity of at least two
Projects of project Preparation of major highway Project (of length 40% of project
length or more of similar configuration (2/4/6 laning**).
f) Experience as Team Leader/Project Manager or similar capacity in Operation and
Maintenance of Major Highway Projects (of length 40% of project length or more
of similar configuration (2/4/6 laning**).
2. Preferential Qualifications.
a) Post Graduate Degree in Construction Management/Transportation/Highway
Engineering//Structural Engineering/ any specialised stream of Civil
Engineering.
b) Highway Development Projects (of length 40% of project length or more of
similar configuration (2/4/6 laning**) taken up under EPC.
c) Degree/Diploma/Certificate in Project Management/Training programme
in Highways Engineering from IAHE
d) Note: (1) Similar Capacity includes the following positions
i. On behalf of Consultant: Team Leader / Resident Engineer (Construction
Supervision/IE/AE).ii. On behalf of Contractor : Project Manager (Construction/ Construction
Supervision)
iii. In Government Organizations : Superintending Engineer (or equivalent)
and above
(2) Only those projects will be considered for evaluation at Sl. No. 1(d), 1(e) &
1(f) above, where the input of the personnel is 12 months, 9 months and 12 months
respectively.
RESIDENT CUM HIGHWAY ENGINEER
The Resident cum Highway Engineer shall be responsible for supervising the works of
highway to be constructed by the Concessionaire for this project. He shall also inspect
the pavement rehabilitation and repair works to be undertaken by the Concessionaire.
He should have the following qualification / experience.
1. Essential Qualifications.
a) Graduate in Civil Engineering from a recognized University.
b) Professional Experience of at least 12 years in Highway Projects.
c) At least 5 years experience in similar capacity in Highway Development Project.
d) Should have handled at least 2 major projects(of length 40% of project length
or more of similar configuration (2/4/6 laning**) and above).
2. Preferential Qualifications.
a) Post Graduate Degree in Transportation/Highway Engineering/Structural
Engineering/Geotechnical Engineering/any specialised stream of Civil
Engineering.
b) Attended Minimum 5 days training programme in field related to Design and
supervision of Highways related topic from IAHE
c) Experience of Highway Project (of length 40% of project length or more of similar
configuration (2/4/6 laning**) and above) of Construction / Construction
Supervision / IC of Highway projectsBRIDGE & STRUCTURAL ENGINEER
The Bridge& Structural Engineer shall be responsible for checking the designs of bridges,
ROBs, interchanges and any other structure to be constructed in the Project highway
and supervising the works of bridges, interchanges and any other structure to be
constructed by the Concessionaire for this project. He shall also inspect the bridge
rehabilitation and repair works to be undertaken by the Concessionaire. He should have
thorough understanding and experience with international `best practices’ of modern
bridge construction technology.
He should have the following qualification / experience.
1. Essential Qualifications.
a) Graduate in Civil Engineering from a recognized University.
b) Professional Experience of at least 10 years in handling Highway/Bridge projects.
c) At least 5 years experience in Construction / Construction Supervision of bridge
/Interchange / any other structures.
d) Experience in similar capacity in supervision of at least 2 Major Highway Bridges.
e) Experience in supervision of Rehabilitation and repair of 2 nos Major Bridges.
2. Preferential Qualifications.
a) Post Graduate Degree in Structural Engineering.
b) He should have thorough understanding and experience of modern bridge
construction technology. viz., Precast Segmental, Balanced Cantilever Construction,
Extradosed Bridge, Full Span Launching, Incremental Launching.
c) Attended 3 days residential training programme on Collapse/failure of
bridges/structures.
SENIOR PAVEMENT SPECIALIST
The expert shall be continuously interacting with the Concessionaire, for the review of
highway designs and drawings using sophisticated computer software and also construction
and O&M works and to ensure life cycle cost effectiveness and viable design of pavement
including appropriate rehabilitation / strengthening of the existing two lane pavement which
is significantly distressed. He shall also be responsible for ensuring complete adherence to
maintenance standards during Construction and Operation period. Thus, the position
requires a pavement specialist with thorough knowledge and understanding of international
‘best practices’ in the field of Design, Construction and maintenance of flexible/rigid type
of pavements including latest Codal stipulations and specifications.
He should have the following qualification / experience.
1. Essential Qualifications.
a) Graduate in Civil Engineering from a recognized University.
b) Professional Experience of at least 10 years in Pavement Design / Pavement
Construction / Pavement Maintenance of Highways / Roads / Airfield Runways
c) Experience of at least 5 years in similar capacity in Construction / Construction
Supervision of 2/4/6 laning** of major highway projects.
d) Experience as Pavement / Geotechnical Engineer in Construction/Construction
Supervision of at least 2 major highway projects (of length 40% of project length or
more of similar configuration (2/4/6 laning**) and above).
2. Preferential Qualifications.
a) Post Graduate Degree in Highway Engineering / Pavement
Engineering
/Transportation Engineering
b) Experience as a Pavement Specialist/Pavement Engineer in Highway project(of
length 40% of project length or more of similar configuration (2/4/6 laning**) and
above).
c) Attended residential training programme related to pavement/highway design
design from IAHESENIOR QUALITY/MATERIAL EXPERT
The Quality/Material Expert shall review the test results of bore holes, quarry and borrow
area material to find out their strength characteristics and suitability for using them in
construction. He shall inspect the Concessionaire’s field laboratories to ensure that they are
adequately equipped and capable of performing all the specified testing requirements of
the contract. He shall look into the quality assurance aspect of the construction works and
supervise the setting-up of the various Concessionaire’s rock crushers and bituminous
mixing plants to ensure that the specified requirements for such equipment are fully met.
Experience in latest Quality Management techniques in highway projects shall have added
advantage.
He should have the following qualification / experience.
1. Essential Qualifications.
a) Graduate in Civil Engineering from a recognized University.
b) Professional Experience of at least 10 years in handling Highway projects.
c) Experience of at least 5 years as Senior Quality/ Material Expert or in similar capacity
in Construction / Construction Supervision /major highway projects
d) Experience as Senior Quality/ Material Expert or in similar capacity in handling of at
least 2 similar highway projects.(of length 40% of project length or more of similar
configuration (2/4/6 laning**) and above)
2. Preferential Qualifications.
a) Post Graduate Degree in Geotechnical Engineering / Foundation Engineering / Soil
Mechanics.
b) Trained in 16 days material testing process course imparted by Indian Academy of
Highway Engineers or CRRIROAD SAFETY EXPERT
Shall be responsible for the overall Road Safety Aspect of the Project. He shall ensure that
safety provisions as per relevant codes are strictly followed at site during Construction of
Road and also during the Maintenance Period
1. Essential Qualifications.
a) Graduate in Civil Engineering from a recognized University.
b) Professional Experience of at least 10 years in handling Highway projects.
c) Minimum 5 years experience in Road Safety works of Major Highway Projects (4 / 6
laning projects)
d) Experience in similar capacity in Road Safety Audit of at least 2 nos. 2/4/6 lane**
highway / expressway project including 1 nos. at design stage
e) Experience in similar capacity in the field of Road Safety Management Plan.
2. Preferential Qualifications
a) Post Graduate Degree in Traffic Transportation/Safety Engineering.
b) Experience in similar capacity in identification and improvement of black spots on
Major Highway Project.
c) Experience in similar capacity in Preparation of Road Safety Management Plan for
inter urban Highways.
d) 15 days Certificate course on Road Safety Audit from IAHE/CRRITEAM LEADER CUM SENIOR BRIDGE ENGINEER
This is the senior most position and the expert engaged as the team leader shall be
responsible for reviewing the entire Project preparation and implementation activities of the
contractor.
He shall check all the Designs/Drawings/Plan & Profile being prepared by the
Concessionaire for pavement as well as structures with assistance of other experts in
the team.
He shall ensure execution of works on site as per specification and standards with all
adequate safety measures for workmen, machinery and road users, and continuously
interact with the NHAI and the Concessionaire.
He shall continuously keep a track of the physical & Financial progress of the work,
available work front, pending permissions, identify anticipated bottlenecks in timely
completion of the project in time, and update the program schedule on MS Project or
Prima Vera or any other project scheduling software on regular intervals.
He shall be responsible for uploading all requisite details, as may be required from
time to time, on Datalake portal of Ministry/NHAI/NHIDCL.
He shall examine and submit his recommendations, with the assistance of his team
at site as well as authorized representative of AE/IE, on all the EOT, Change of Scope
& Force Majeure proposals & any Disputes that arise during execution/O&M phase
submitted by the Contractor/Concessionaire.
He shall be responsible to ensure that there is no loss to Authority on account of
misrepresentation of facts/reports/invoices/poor construction quality etc.
He shall undertake Project site visits and shall guide, supervise, coordinate and monitor the
work of other experts in his team as well as those of the Contractor/Concessionaire.
He shall track the mobilisation of resources done by the Contractor/Concessionaire
on monthly basis and report the same to Authority as well
Contractor/Concessionaire.
Any delay in approvals/recommendations from the Authority Engineer shall be
attributable to the Team Leader/AE/IE, as the case may be.
The candidate is required to be a team leader/Senior Highway Engineer, who should have
a proven record of supervising, organising and managing of construction of highway
projects and also of Project preparation of large magnitudes projects, as defined below,
financed by international lending agencies and others. Knowledge of Project management
shall be an added advantage.
He should have the following qualification / experience.
1. Essential Qualifications.
a) Graduate in Civil Engineering from recognized university.
b) Total Professional Experience of at least 12 years in handling Bridge Projects.
c) At least 5 years experience as Team Leader/Project Manager or similar capacity
in Highway Development Project.
d) He should have handled as Team Leader/Project Manager or similar capacity of
at least two projects in Construction Supervision / IC (of length 40% of project
length or more of similar configuration (2/4/6 laning**)
e) He should have handled as Team Leader or similar capacity of at least Two
projects in Construction Supervision / AE/ IE/ Project preparation involving at
least one Major Bridge (minimum 300 m length without approaches) in the Project
(of length 40% of project length or more of similar configuration (2/4/6 laning**)
f) Experience as Team Leader/Project Manager or similar capacity in Operation and
Maintenance of Major Bridge (minimum 300 m length without approaches) in theProject (of length 40% of project length or more of similar configuration (2/4/6
laning**).
2. Preferential Qualifications.
a) Post Graduate Degree in Structural Engineering or equivalent.
b) Highway Development Projects (of length 40% of project length or more of
similar configuration (2/4/6 laning**).
c) Degree/Diploma/Certificate in Project
Management
d) Residential training programme on Collapse/failure of bridges/structures.
e) Note: (1) Similar Capacity includes the following
positions
i. On behalf of Consultant: Team Leader / Resident Engineer (Construction
Supervision/IE/AE).
ii. On behalf of Contractor : Project Manager (Construction/ Construction
Supervision)
In Government Organizations : Superintending Engineer (or equivalent) and
above
iii. (2) Only those projects will be considered for evaluation at Sl. No. 1(d), 1(e) &
1(f) above, where the input of the personnel is 12 months, 9 months and 12
months respectively.TEAM LEADER CUM SENIOR TUNNEL ENGINEER
Duties: The Team Leader will reside at project site throughout the period of construction
supervision services. He will be overall in-charge of the project supervision of the
construction package. He shall act as representative of the consulting firm appointed by
the Authority. His duties will involve overall superintendence over the Resident Engineers
and other experts of the construction package. He will guide, monitor, supervise and
control all the activities related to supervision for the construction package. He will
interact with the Project Director/ General Manager and the other officials of the
Authority. He should have the following qualification / experience.
(1) Essential Qualifications.
a) Graduate in Civil/Mining Engineering or equivalent from a recognized university.
b) Total professional experience of at least20 years
c) Professional Experience of at least 15 years in handling major tunnelling projects
d) He should be involved in at least 10 years in construction/construction supervision
of major Road/ Rail/ Metro tunnel projects
e) At least 5 years’ experience as Team Leader/Resident Engineer/Project Manager
or similar capacity in supervision of transportation tunnel projects of length equal
to or more than 4 km
f) He should have handled as Team Leader or similar capacity of at least two
projects in Construction Supervision of transportation tunnels equal to more than
4 Km length
g) Not more than 65 years of age.
(2) Preferential Qualifications.
a) Post Graduate or chartered engineer in Mining Engineering/ Geotechnical
Engineering/ Structural Engineering/ Rock Mechanics or equivalent.
b) Project preparation/ design experience of transportation Tunnel
projects
c) at least one training course preferably in relevant field in past two
years from IAHE
d) Note: (1) Similar Capacity includes the following positions
i) On behalf of Consultant: Team Leader / Resident Engineer/Professional
Engineer/Charted Engineer (Construction Supervision/IE/AE).
ii) On behalf of Contractor : Project Manager/ Professional Engineer/Charted
Engineer (Construction/ Construction Supervision)
iii) In Government Organizations : Superintending Engineer (or equivalent) and above
(2) Only those projects will be considered for evaluation at Sr. no 1(d), 1(e) and 1(f)
where the input of the personnel is at least of one year.
(3) Unless otherwise mentioned specifically, tunnel projects of length > 1.5km shall
be considered as major tunnel projects.RESIDENT ENGINEER CUM TUNNEL EXCAVATION EXPERT
Duties: He shall oversee construction supervision of the project stretch and shall
coordinate with all other experts of the project and shall report to the Team Leader. He
shall be directly responsible for regulating the construction process. He shall be assisted
by Tunnel Engineers, Tunnel Lining Experts and Tunnel ventilation Expert and other
support engineers/personnel. He shall deal directly with the tunnel engineers/experts and
other support staff attached with the Team Leader to ensure that the construction process
is well controlled as per established specification controls to avoid later quality control
stage problems. Expert shall be responsible for checking and verifying the excavation
plan and methodology submitted by the Contractor. He shall monitor the tunnel
excavation activities including blasting. He shall also monitor the tunnel lining activities
including installation of water proofing layers. He will be required to be fielded throughout
the Currency of the project. The candidate is expected to be thoroughly familiar with
various standard/specifications, contract procedures, Primavera or other project
management software, design and quality control etc. In addition he will be responsible
for tunnel works during Operation & Maintenance period of the project.
He should have the following qualification / experience.
(1) Essential Qualifications.
a) Graduate in Civil/Mining Engineering from a recognized University.
b) Total Professional Experience of at least 15 years
c) He should have at least 10 years’ experience in similar capacity for major
tunnel projects
d) At least 7 years’ experience in construction supervision of major
transportation tunnel construction projects
e) Should have handled construction/construction supervision of at least 2
transportation Tunnel projects of length equal or more than 4 km
f) Experience in tunnel design/ DPR preparation/ feasibility study/ design review
of transportation Tunnel projects of length equal or more than 4 km
g) Not more than 65 years of age.
(2) Preferential Qualifications.
a) Post Graduate or chartered engineer in
civil/mining
b) at least one training course preferably in relevant field in past two
years from IAHE
c) Note:
(1) Unless otherwise mentioned specifically, tunnel projects of length > 1.5km shall
be considered as major tunnel projects.TUNNEL DESIGN ENGINEER
Duties: The Tunnel Design Engineer shall be responsible for checking the designs of
tunnel/design review and other incidental works to be constructed in the Project using
sophisticated computer software. He shall be responsible for Detailed Design Calculation
and drawing for tunnels. He shall be responsible for comprehensive assessment of
structural condition of all the tunnel assets. His expertise shall include computer aided
design methods for Tunnel Engineering with particular reference to Tunnel design.
He should have the following qualification / experience.
2) Essential Qualifications.
a) Graduate in Civil Engineering from a recognized University.
b) Professional Experience of at least 20 years
c) Experience of at least 12 years in major tunnel projects
d) Experience in tunnel design (Road/ Rail/ Metro) of at least 12 years
e) Experience in similar capacity in construction/construction supervision of 2
transportation tunnel projects of length at least equal to 4 Km each
f) Experience in similar capacity in design of at least 3 transportation tunnel
projects of length at least equal to 4 Km each
g) Not more than 65 years of age.
3) Preferential Qualifications.
a) Post Graduate in Engineering in structural engineering
b) Innovative transport tunnel design (road/ Rail/ Metro) such as immersed
tunnel and sub-sea bored tunnel
c) at least one training course preferably in relevant field in past two
years from IAHE
Note:
(1) Unless otherwise mentioned specifically, tunnel projects of length > 1.5km shall
be considered as major tunnel projects.SENIOR GEO-TECHNICAL EXPERT
Duties: He will be responsible for supervising all the tests to be done in different stages
of construction, besides ensuring that specified tests are done as per codal stipulations
and as per the specifications laid down in the contract for all the different stages of
construction. The Senior Geotechnical Engineer shall be responsible for checking and
verifying the Specifications for Geotechnical investigations and the geotechnical details
submitted by the Contractor. He shall assist the Team Leader & Tunnel Design Engineer
in design of tunnel. He shall monitor the tunnel excavation activities including blasting
He should have the following qualification / experience.
(1) Essential Qualifications.
a) Graduate in Civil Engineering/masters in engineering geology or equivalent
from a recognized University.
(2) Professional Experience of at least 20 years
(3) Experience of at least 10 years in Construction / Construction Supervision of
transportation tunnel projects in developed countries
(4) Experience as Geotechnical Engineer in Construction/Construction Supervision of at
least 4 transportation Tunnel projects of length equal to or more than 4 Km
(5) Specific experience in construction of tunnel projects involving vertical shaft
sinking of at least 200 meter of vertical depth
(6) Experience in similar capacity in project preparation of at least 2 transportation
tunnel projects each of minimum 4 Km in length
(7) Not more than 65 years of age.
(8) Preferential Qualifications.
a) Post Graduate in Rock Mechanics/ Foundation Engineering/ Tunnel
Engineering
b) at least one training course preferably in relevant field in past two
years from IAHE
c) Note:
(1) Unless otherwise mentioned specifically, tunnel projects of length >
1.5km shall be considered as major tunnel projects.TUNNEL SAFETY EXPERT
Duties: The Tunnel Safety Expert shall be responsible for checking and verifying the
Safety Plan prepared by the Contractor. He will also ensure effective implementation of
the Safety Plan, undertake safety audits during Construction, Operation and Maintenance
of the Tunnel.
(1) Essential Qualifications.
a) Post Graduate in Civil/Mining Engineering from recognized university.
b) Total Professional Experience of at least 20 years
c) Experience of at least 7 years in transportation tunnel safety management in
developed countries
d) At least 10 years’ experience in transportation tunnel safety works
e) Experience in similar capacity of tunnel safety audits during construction stage
of at least 2 transportation tunnel projects each of which should be minimum 4
km in length
f) Not more than 65 years of age.
(2) Preferential Qualifications.
a) Any professional Certification from a recognized/statutory body in
safety/health/shot firer/ Explosives.
b) at least one training course preferably in relevant field in past two
years from IAHE
c)
Note:
(1) Unless otherwise mentioned specifically, tunnel projects of length > 1.5km shall
be considered as major tunnel projects.SENIOR GEOLOGIST
Duties: The Senior Geologist shall be responsible for checking and verifying the geological
details submitted by the Contractor. He shall assist Team Leader & Tunnel Design
Engineer in design of Tunnel. He shall monitor the tunnel excavation activities including
blasting. The candidate should have exposure of working in Himalayan region and good
understanding of rock and soil mechanics. He should have experience of tunnel works with
appropriate design software. The candidate should be a Post Graduate in Geology
preferably with exposure in Himalayan region. He should have a minimum 20 years of
professional experience of geological works, out of which 5years should be in similar
capacity for tunnelling design/ construction projects in the Himalayan region.
(1) Essential Qualifications.
a) Masters in Geology/Applied Geology from recognized university.
b) Total Professional Experience of at least 20years
c) At least 7years experience in similar capacity in construction/construction
supervision of transportation tunnel projects
d) Experience of 5 years of construction/construction supervision of major
transportation tunnel projects in the Himalayan region using NATM technology
e) He should have handled at least 2 highway tunnel projects of
construction/construction supervision in similar capacity of 4 Km length each
f) Not more than 65 years of age
(2) Preferential Qualifications.
a) He should have handled at least 2 major transportation tunnel projects in
similar capacity in project preparation/DPR.
b) Training/ certificate course in relevant field from an institute of Repute.
Note:
(1) Unless otherwise mentioned specifically, tunnel projects of length > 1.5km shall
be considered as major tunnel projects.
CONTRACT cum Planning Engineer
Duties: He will be deployed in working season in stages for cumulative duration of period
mentioned in Enclosure-A for obtaining his expert opinion on emerging contractual
issues and review the project planning. His key responsibilities will be to guide and assist
Team Leader/Employer in all aspects of contract management and project planning in
proper implementation of contract provisions including controlling the project cost of the
construction package. He will also be required to offer his advice on contractual
complications arising during the implementation as per the request of the employer. He
will be required to prepare manuals/schedules for the consultants team/employer based
on the provisions of the contract document. He will be responsible for giving appropriate
suggestions in handling claims of the contractors and any dispute arising thereof.(1) Essential Qualifications.
a) Graduate in Civil Engineering from a recognized University.
b) Professional Experience of 15 years in Contract Management/ planning Engineer.
c) Experience of at least 4 years as Contract Specialist /planning Engineeron any
National/State Highway project/Bridge Project.
d) Contract Manager and planning Engineer of a large Highway/Bridge contract say
over Rs.150 crore including experience of handling Variation orders, claims of
the contractor and there appropriate disposal for at least 2 projects.
e) Handled at least one Arbitration cases in respect of any Highway/Bridge projects.
f) Not more than 65 years of age.
(2) Preferential Qualifications.
(a) Degree in Law/PG in management/certificate course in management/ certificate
course in construction management/certificate course in contract management.
(b) Training/ certificate course in relevant field from an institute of Repute.
(c) Certificate in MS Road/ MS Project/ PrimaveraRESIDENT CUM PAVEMENT SPECIALIST
The expert shall be continuously interacting with the Concessionaire, for the review of
highway designs and drawings using sophisticated computer software and also
construction and O&M works and to ensure life cycle cost effectiveness and viable design
of pavement including appropriate rehabilitation / strengthening of the existing
pavement. He shall also be responsible for ensuring complete adherence to maintenance
standards during Construction and Operation period. Thus, the position requires a
pavement specialist with thorough knowledge and understanding of international ‘best
practices’ in the field of Design, Construction and maintenance of flexible/rigid type of
pavements including latest Codal stipulations and specifications.
He should have the following qualification / experience.
3. Essential Qualifications.
a) Graduate in Civil Engineering from a recognized University.
b) Professional Experience of at least 12 years
c) Experience of at least 5 years in similar capacity in Construction / Construction
Supervision of 2/4/6 laning** of major highway projects.
d) Experience in similr capacity in handling at least 2 major highway projects (of
length 40% of project length or more of similar configuration (2/4/6 laning**)
and above).
4. Preferential Qualifications.
a) Post Graduate Degree in Highway Engineering/ Geotechnical Engineering/
Transportation Engineering/ Structural Engineering
b) Experience in similar capacity in Highway project construction/ construction
supervision on EPC mode (of length 40% of project length or more of similar
configuration (2/4/6 laning**) and above).
c) at least one training course preferably in relevant field in past two
years from IAHESUB PROFESSIONAL
SURVEY ENGINEER
The candidate should be Graduate in Civil Engineering at least 5 years experience
or diploma in civil Engineering with 10 years experience in the field of surveying in
highway projects and they should have also dealt with at least 2 project of similar
nature. This position requires thorough understanding of modern computer based
method of surveying with total station digital level etc.
ASSISTANT HIGHWAY ENGINEER
The Candidate should be Graduate in Civil Engineering with minimum 5 year
experience or diploma in Civil Engineering with 10 years experience in highway
Projects. He should have dealt with atleast 2 project of similar nature.
CAD EXPERT
He should be Graduate in Civil Engineering/Computer Science having experience 3
year experience in computer related design method for highway engineering.
ENVIRONMENTAL ENGINEER
The Candidate should be Graduate in Civil Engineering/Environmental Engineering
or other relevant qualification. He should have at least 6 years experience out of
which 2 years in highway projects. He should have good knowledge of MOEF
guidelines/requirements for mitigation measures.
ASSISTANT BRIDGE ENGINEER
The Candidate should be Graduate in Civil Engineering with minimum 5 year
experience or diploma in civil Engineering with 10 years experience in highway
Projects. He should have handled at least 2 major bridge project.
ASSISTANT QUALITY CUM MATERIAL ENGINEER
The Candidate should be Graduate in Civil Engineering with minimum 5 year
experience or diploma in civil Engineering with 10 years experience in highway
Projects. He should have handled at least 2 project.
ELECTRICAL ENGINEER
The Candidate should be Graduate in Electrical Engineering from recognised
institute. He should have at least 5 years experience.
HTMS/TOLLING SYSTEM EXPERT
The candidate should be a Systems Engineer having experience of at least 5 Years.He should be well versed either in preparation of standards or in implementation of
projects of electronic toll collection and ATMS/ITS/HTMS. He should have
bachelor’s degree in Electronics/Computer Science/IT. He should have knowledge
of international latest practices in the field of electronic toll collection (ETC) and
ATMS/ITS/HTMS. He should have work experience of either design or
implementation on at least 1 ATMS/ITS/HTMS project and at least 1 ETC project in
similar capacity.
QUANTITY SURVEYOR
He should be Graduate or equivalent in Civil Engineering having Min. 5 years of
professional experience or diploma in civil Engineering with 10 years experience in
preparation of highway project estimates. He should have Min. 3 years experience
in Preparation of Bill of Quantities/estimates for major highway projects costing
Rs.300 Crore or above.
HORTICULTURE CUM LANDSCAPING SPECIALIST
He should be a Graduate in Agriculture with specialization in
Horticulture/Arboriculture having minimum 5 year of field experience in
Horticulture/Arboriculture and landscaping. He should have minimum 5 years field
experience.
Lab Technician: - Graduate in Civil Engineering with one year experience or Diploma in
Civil Engineering or B.Sc. with 3 year experience.Section VII: Evaluation/ Scoring Criteria
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services (Ref ITC-clause 1.4)
Consultants must fill up the following Forms regarding this Section:
a) Form T-2: Consultant’s Organisation and Experience
b) Form T-2A Technical Capacity
c) Form T-3: Comments and Suggestions on Terms of Reference, Counterpart Staff, and Inputs
to be Provided by the Procuring Entity
d) Form T-4: Description of Approach, Methodology and Work Plan in Responding to the
Terms of Reference
e) Form T-5: Work Schedule and Planning for Deliverables
f) Form T-6: Team Composition, Assignment, and Key Experts’ Inputs
g) Annex to Form T-6: Key Experts’ Curriculum Vitae (CV)
The eligibity and evaluation criteria shall be as follows as given in this section below:-
• The points assigned to Technical Evaluation criteria are:
S.
Descriptio Marks
No.
n
1 Relevant experience for the assignment 25
2 Rating of the Firm 40
2 Experience in use of technology for road inspection 10
4 Qualifications and competence of the key staff for the assignment 25
Total 100
1. Sub criteria for Relevant Experience of the firm for the assignment
Average Annual Turnover (last 3 years) from consultancy business of civil Engineering
5
Projects (Min 3% of the EPC of Project for which AE has been invited)
No of Highway Professionals with the Firm
5
Experience as Independent Engineer/Authority Engineer/Construction Supervision in Number of
7
Highway Projects of length equal to project length for which AE bids are invited of similar category
for which RFP invited of 2/ 4/6**-laning or more in last 7 years*
Experience in DPR preparation for Number of Highway Projects (of length equal to project length 3
of similar category for which RFP invited of 2/4/6**-laning or more) in last 7 years *
In hand DPRs for Authority (Ministry /NHAI/NHIDCL-As applicable) Projects (presently 10
under progress)
Experience in Construction Supervision as AE/IE/PMC of Major structures having length of more 3
than 500 meter in last 7 years.
Experience preparation of DPR of Major structures having length of more than 500 meter in 2
last 7 years.
Additional requirement in case of specialized projects*** **
** Consultants should give details of the experience of the firm considering the
completed and the on-going highway assignments, separately for PPP and
non-PPP Projects along with experience certificates from clients. This list of
the completed works should also include those assignments which are
substantially (90% of Contract value) completed. No Qualification/Experience
etc. shall be considered without proof of experience.
Experience of Authority’s Engineer for having offered consultancy services
to a private organization shall not be considered as relevant experience for
current assignment.
** Similar projects means 2/4/6 lane as applicable for the project for which RFP is
invited. For 2-lane projects experience of 4/6 lane also to be considered with
a multiplication factor of 1.5. Experience of 4/6 lane shall be considered
interchangeably for 4/6 laning projects. For 4/6 laning projects, experience of
2 lane will be considered with a multiplication factor of 0.4, but only for those
2 lane projects whose cost of consultancy services was more than Rs.3.0
crores.
*** In case the project includes any specialized nature of work such as tunnels,
specialized structures etc. in substantial quantum, this requirement/Marks
may be included by suitably adjusting marks of other attributes.
In case of JV the turnover and experience details of Lead and JV Employer’s
certificate should be submitted substantiating the experience claimed by the
firm.
2. Sub- Criteria for assessment of rating of the Firm
S. Rating of the Marks
No lead Partner
1. A- Grade firm 40
2. B- Grade Firm 30
3. C- Grade Firm 20
4. D- Grade firm 10
5. Unrated firm 5
For evaluation purpose Rating of the firm published by NHAI shall be
considered.
3. Sub criteria for Ownership of technology/ Equipment for road inspection
Sr. Maximu
Description Sub-
No. m
Points
PointsOwnership of Network Survey vehicle technology for
1 2.0
pavement inspection
Ownership of Mobile Quality Control Unit having Soil
2. 3.0
Testing, Asphat Testing, Concrete testing, Aggregate
Testing and pavement testing equipment onboard along
with sufficient IT and communication systems
Ownership of NABL Acerbated Lab by the firm
3. 1.5
Ownership of Mobile Bridge Inspection Unit or better
4. 1.5
technology for bridge inspection
Ownership of Falling Weight Reflectometer (FWD) or
5. 1.0
better
technology for pavement strength measurement
6. Ownership of Retro reflectometer technology 1.0
Total 10
Note: A. The Authority’s Engineer owning the equipment’s shall be required to
submit proof of ownership.
B. The experience of the JV firms in use of technology shall also be counted in the evaluation. The
experience of firm or JV firm in NSV or equivalent technology, FWD or equivalent technology, MBIU or
equivalent technology and Retro reflectometer or equivalent technology shall be supported by
experience certificate. The experience of a firm/ JV firm for a private concessionaire/ contractor (client) shall
be considered certificate by the Govt Department. Any false certification shall attract penel provisions as per
contract
4. Qualification and competence of following professional/sub-professional staff
for the assignment shall be evaluated. The weightage for various key staff are as under:-
Normal Highway Project:
S. No Staff Marks.
Position
1 Team Leader Cum Senior Highway Engineer 7
2 Resident cum Highway Engineer 4
3 Bridge/Structural Engineer 3
4 Pavement Specialist 3
5 Quality cum Material Expert 3
6 Contract Specialist cum Planning Engineer 2
7 Road safety Expert 3
Total 25
Standalone Bridge Project:
S. No Staff Marks.
Position
1 Team Leader Cum Senior Bridge Engineer 7
2 Resident cum Pavement Specialist 4
3 Bridge/Structural Engineer 4
4 Contract Specialist 2
5 Road Safety Expert 36 Planning Engineer 2
7 Quality cum Material Expert 3
Total 25
Standalone Tunnel Project:
S. No Staff Marks.
Position
1 Team Leader Cum Senior Tunnel Expert 7
2 Resident Engineer cum Excavation Specialist 4
3 Geotechnical Expert 4
4 Tunnel Design Engineer 3
5 Tunnel Safety Expert 3
6 Geologist 2
7 Contract Specialist cum Planning Engineer 2
Total 25
Sub criteria for qualification of Key Personnel (i.e. Professional staff)
General qualifications 25
Adequacy for the project 70
Employment with firm 5
Total 100
The technical proposal should score at least 75 points to be considered responsive for
financial evaluation.
v) Detailed evaluation criteria which is to be used for evaluation of technical bids is
as indicated below as Appendix-EC.
vi) The Authority’s Engineer should carryout self-evaluation based on the evaluation
criteria at Appendix-EC. While submitting the self-evaluation along with bid,
Authority’s Engineer shall make references to the documents which has been relied
upon in his self-evaluation.
vii) Detailed/complete technical evaluation of a bidder shall be made available to that
bidder only giving opportunity to the bidder to respond within 7 days in case they
have any objection on their evaluation.
viii) The single currency for price conversion is INR. For evaluation of bid proposals, the
foreign currency conversation rate of 1US Dollar = Rs. And 1 Euro = Rs. – shall be
used.
ix) The weightage given to technical proposal is 60%.The weightage to the
Performance Security Quoted by bidder shall be 20% and The weightage given to
financial quote is 20%.
Remarks: Based on experience and the Consulting Industry’s Capacity,
Project specific requirement etc., <Agency> may modify the above
criteria for Selection of AE.Appendix-EC
1. Evaluation Criteria for Assessment of Experience of the Firm.
Reference/Details Marks self-
Max.
S. No. Descriptio of projects Claimed assessed
Marks
n for self- by the
assessment bidder
1 Average Annual Turnover (last 3 years) from 5
consultancy business of civil Engineering Projects
< 3% of TPC – 0 marks
3% of TPC – 3.0 marks
Add for additional turnover 0.50 (Zero point five)
marks for every 1% of TPC above 3% of TPC subject to
maximum 2.0 marks.
2. Nos of Highways Professional with Firm 5
2.1 <10 0
2.2 10-20 3
2.3 >20 but ≤30 4
2.5 >30 5
*The pr ofessionals who possess degree in Civil Engineering/Transport Planning /Transport
Economics/Traffic Management / Geology/ Environment Science or Engineering and 8
years experience in highway/bridge /tunnel with employment in the firm for more than
one year. The current Employment Certificate shall be uploaded by Key Personnel on
INFRACON.
3. Experience as Independent 7
Engineer/Authority Engineer/Construction
Supervision in Number of Highway Projects
of length equal to project length for which
AE bids are invited of similar category for
which RFP invited of 2/ 4/6**-laning or
more in last 7 years*
1 project – 3 marks Add 0.5(one) mark
extra for completed assignment of Authority
Engineer/Independent Engineer and add
0.25 (Zero point five) marks extra for
completed assignment of supervision
consultancy subject to maximum 4 (Four)
4. Experience in DPR preparation for Number of Highway 3
Projects (of length 40% of project length of similar
category for which RFP invited of 2/4/6**-laning or
more) in last 7 years *
2 project – 2 marks Add 0.5 (Zero point five) marks
extra for each additional project subject to maximum 1
mark.5 Experience in Construction Supervision as AE/IE/PMC 3
of Major structures having length of more than 500
meter in last 7 years.
2 project – 1.0 marks Add 0.5 (Zero point five) marks
extra for each additional project subject to maximum
2.0 marks
6 Experience in Preparation of DPR of Major structures 2
having length of more than 500 meter in last 7 years.
2 project – 1.0 marks Add 0. 5 (Zero point twofive)
marks extra for each additional project subject to
maximum
1.0 marks
7 Additional requirement in case of specialized ***
projects***
Note 1: In case of JV the turnover and experience details of Lead and JV partners
to be added.
Note 2: Employer’s certificate/ certificate from Statutory Auditor should be
submitted substantiating the experience/turnover claimed by the firm.
Note 3: ** For 4/6 laning projects, experience of 2 lane will be considered with
a multiplication factor of 0.4, but only for those 2 lane projects whose cost of
consultancy services was more than Rs.3.0 crores.
*** In case the project includes any specialized nature of work such as tunnels,
specialized structures etc. in substantial quantum, this requirement/Marks
may be included by suitably adjusting marks of other attributes.
1A. Evaluation Criteria for assessment of rating of the Lead Firm
S. Rating of the Marks
No lead Partner
1. A- Grade firm 40
2. B- Grade Firm 30
3. C- Grade Firm 20
4. D- Grade firm 10
5. Unrated firm 5
For evaluation purpose Rating of the firm published by NHAI shall be
considered.
2. Evaluation Criteria for assessment of experience in use of
technology for road inspection
Sr. Maximu Referenc Marks
Description
No. m e/Details self-
Points
of assessedprojects by the
Claimed bidder
for self-
assessme
nt
Ownership of Network Survey vehicle
1 2.0
technology for pavement inspection
Ownership of Mobile Quality Control Unit
2. 3.0
having Soil Testing, Asphat Testing, Concrete
testing, Aggregate Testing and pavement
testing equipment onboard along with
sufficient IT and communication systems
Ownership of NABL Acerbated Lab by the firm
3. 1.5
Ownership of Mobile Bridge Inspection Unit or
4. 1.5
better technology for bridge inspection
Ownership of Falling Weight Reflectometer
5. 1.0
(FWD) or better
technology for pavement strength
measurement
6. Ownership of Retro reflectometer technology 1.0
Total 10
Notes:
(i) The Consultants owning the equipment shall be required to submit proof of ownership.
3 Evaluation Criteria for assessment of score of Key Staff for adequacy of the
Assignment.
3.1 Team Leader cum Senior Highway Engineer
Reference/Details Marks self-
Max.
S. No. Description of projects Claimed assessed by
Points
for self- the bidder
assessment
1 General Qualification 25
i) Graduate in Civil Engineering 17
ii) Post-Graduation in Management/ 03
Construction/ Transportation/Highway
Engineering/Structural Engineering or
equivalent specialized stream of civil
engineering
iii) Minimum 15 days training course from 03
IAHE/CRRI / Govt institute in any filed
related to Highway developmentiv) Essential Software 2
Experience- (MS Roads/
Projects, Prima Vera or other
relevant software )
2 Adequacy for the Project 70
a) Professional Experience in Highway
Projects:
i) Total Professional Experience in handling 15
Highway projects
< 12 years -0
15 years -8 marks
Add 1 mark extra for each additional year of
experience subject to maximum 7 (seven) marks.
ii) Experience as Team Leader or similar capacity in 15
Highway Development Projects (similar
configuration (2/4/6 laning**) and above)
< 5 years -0
5 years -11 marks
Add 1 marks extra for each additional year of
experience subject to maximum 4 (four) marks.
iii) Experience as Team Leader or similar capacity in 5
Highway Development projects (of length equal to
project length or more of similar configuration
(2/4/6 laning**) and above) on EPC
1 project -3 marks add 1 mark extra for additional
projects subject to maximum2 (two) mark
b) Experience as Team Leader or similar capacity of 10
project Preparation including design of major
highway Project (of length equal to project length
or more of similar configuration (2/4/6 laning**)
and above).
< 2 projects -0Reference/Details Marks self-
Max.
S. No. Descriptio of projects Claimed assessed by
Points
n for self- the bidder
assessment
2 Projects -8 marks
Add 1 marks for each additional project subject to
maximum 2 marks.
c) Experience in position of Team Leader/Project 20
Manager or similar capacity in Construction
Supervision/IC involving length equal to project
length or more of similar configuration (2/4/6**
laning) and above
< 2 projects – 0
2 Projects – 16 marks
Add 2 marks extra for each additional project
subject to maximum 4 (four) marks
d) Experience as Team Leader or similar capacity in 5
Operation and Maintenance of Major Highway (of
length equal to project length or more of similar
configuration (2/4/6 laning**) and above).
1 project – 4 marks
Add 1 mark extra for each additional project
subject to maximum 1 (one) mark
3 Employment with the Firm 5
< 1 year -0
1 year – 3 marks
Add 0.5 marks for each subsequent year subject
to maximum 2 marks
Total : 100
Note:
(1) Similar Capacity includes the following positions
i) On behalf of Consultant: Team Leader/Resident Engineer (Construction
Supervision/IE/AE/DPR).
ii) On behalf of Contractor: Project Manager (Construction/Construction Supervision)
iii) In Government Organizations: Superintending Engineer (or equivalent) and above
(2) Only those projects will be considered for evaluation at S. No. 2(b) where the input of
the personnel is not < 9 months.
(3) Only those projects will be considered for evaluation at S. No. 2I, (d) where the input
of the personnel is not < 12 months.(4) In case of experience on behalf of Authority’s Engineer or Contractor, the experience shall
be duly endorsed by the respective Government agency. In case of non-availability of
endorsement from Govt. Agency, the experience uploaded on INFRACON Portal will be taken
into consideration. However, the key personnel/ bidder will be solely responsible for any fake
information/ CV, which may result in debarment.
3.2 Resident cum Highway Engineer
Reference/Details Marks self-
Max.
S. No. Descriptio of projects Claimed assessed by
Points
n for self- the bidder
assessment
1 General Qualification 25
i) Graduate in Civil Engineering 17
ii) Post Graduation in 03
Transportation/Highway
Engineering/Structural
Engineering/Geotechnical Engineering
iii) Minimum 15 days training certificates 03
from IAHE/ any Govt Institute in
Highways
iv) Essential Software 2
Experience- (MS Roads/
Projects, Prima Vera or other
relevant software )
2 Adequacy for the Project 70
Professional Experience
i) Total Professional Experience in handling Highway 15
projects
< 12 years -0
12 years -12 marks
Add 1 mark extra for each additional year of experience
subject to maximum 3 (three) marks.
ii) Experience as Resident Engineer/Highway 20
Engineer/Project Director/Project
Manager/Superintending Engineer or
equivalent/Executive Engineer or equivalent on
construction works/Authority Engineer/Independent
Engineer Projects (similar configuration (2/4/6
laning*) and above).
< 5 years -0; 5 years -15 marks
Add 1 marks extra for each additional year of
experience subject to maximum 5 (five) marks.iii) Experience in similar capacity in handling major 2/4/6- 25
laning** projects (of length equal to project length or
more of similar configuration (2/4/6 laning**) and
above)
< 2 nos. -0
1 nos. -19 marks
Add three marks extra for each additional project
subject to maximum 6 (Six) marks.
iv) Experience in similar capacity of Highway Project of 5
Construction/Construction Supervision/IC on EPC
Mode(of length equal to project length or more of
similar configuration (2/4/6 laning**) and above)
1 Project- 4 marks
Add 1 (one) mark extra for each additional project
subject to maximum 1 (one) mark
v) Experience as RE or similar capacity in Operation and 5
Maintenance of Major Highway (of length equal to
project length or more of similar configuration (2/4/6
laning**) and above).
1 project – 4 marks
Add 1 mark extra for each additional project subject to
maximum 1 (one) mark
3 Employment with the Firm 5
< 1 year -0
1 year – 3 marks
Add 0.5 marks for each subsequent year subject to
maximum 2 marks
Total : 100
Note:
(1) Similar Capacity includes the following positions
i) On behalf of Consultant: Resident / Highway Engineer
ii) On behalf of Contractor: Resident Engineer/ Highway Engineer / Project
Manager (Construction/Construction Supervision)
iii) In Government Organizations: Executive Engineer (or equivalent) and above
(2) Only those projects (in numbers) will be considered for evaluation above, where the input
of the personnel is not < 12 months
(3) In case of experience on behalf of Authority’s Engineer or Contractor, the experience shall
be duly endorsed by the respective Government agency. In case of non-availability of
endorsement from Govt. Agency, the experience uploaded on INFRACON Portal will be taken
into consideration. However, the key personnel/ bidder will be solely responsible for any fake
information/ CV, which may result in debarment.3.3 Bridge/Structural Engineer
Reference/Details Marks self-
Max.
S. No. Descriptio of projects assessed by
Points
n Claimed for self- the bidder
assessment
1 General Qualification 25
i) Graduate in Civil Engineering 18
ii) Post-Graduation in Structural Engineering 04
iii) training in residential training 03
programme on Collapse/failure of
bridges/structures from IAHE/Govt
Institute
2 Adequacy for the Project 70
i) Total Professional Experience in handling 15
Highway/Bridge projects
< 10 years -0
10 years -11 marks
Add one mark extra for each additional 2 year
subject to maximum 4(four) marks
ii) Experience in similar capacity in 20
Design/Construction/Construction Supervision of
Bridges/ROB/Flyover/Interchanges/any other such
structures (similar configuration (2/4/6 laning**)
and above)
< 5 years -0; 5 years -15 marks
Add 1 (one) mark extra for each additional
completed year of experience subject to maximum
5 (five) marks
iii) Experience in similar capacity in supervision of Major 20
Highway Bridges/ROB/Flyover/ Interchanges/ any
other structures
< 2 Bridges -0
02 Bridge -15 marks
Add 2.5 mark extra for each additional bridge
subject to maximum 5 marksiv) Experience in similar capacity in supervision of 10
Rehabilitation and repair of Major
Bridges/ROB/Flyover/ Interchanges/ any other
structures
< 2 nos. – 0
2 nos. -8 marks
> 3 nos.- 10
v) Experience in similar capacity of modern bridge 5
construction technology viz., Precast Segmental,
Balanced Cantilever Construction, Extra dosed
Bridge, Full Span Launching, Incremental
Launching.
Experience in 1 project – 4 marks
More than one project – 5 marks
3 Employment with the Firm 5
< 1 year -0
1 year -3 marks
Add 0.5 marks for each subsequent year subject to
maximum 2 marks
Total : 100
Note:
(1) Similar Capacity includes the following positions
i) On behalf of Consultant/Contractor: Bridge Engineer/Project Manager (Bridges)
ii) On behalf of Government: Executive Engineer
(2) Only those projects (in numbers) will be considered for evaluation above, where the input
of the personnel is not < 12 months
(3) In case of experience on behalf of Authority’s Engineer or Contractor, the experience shall
be duly endorsed by the respective Government agency. In case of non-availability of
endorsement from Govt. Agency, the experience uploaded on INFRACON Portal will be taken
into consideration. However, the key personnel/ bidder will be solely responsible for any fake
information/ CV, which may result in debarment.
3.4 Senior Pavement Specialist
Reference/Details of Marks self-
Max.
S. No. Description projects Claimed for assessed by
Points
self-assessment the bidder
1 General Qualification 25
I) Graduate in Civil Engineering 18II Post-Graduation in Transportation/Highway 04
) Engineering/Pavement engineering or
equivalent
iii Training certificate from IAHE / Govt Institute in 03
) design/ maintained of pavement
2 Adequacy for the Project 70
Professional Experience
i) Total Professional Experience of Pavement 20
Design/Construction and Maintenance of
Highways/Roads/Air Field Runway
< 10 years -0
10 years -15 marks
Add one mark extra for each additional year of
experience subject to maximum 5 (five) marks.
ii) Experience in Similar capacity in 20
Construction/Construction Supervision of 2/4/6-
laning** of major Highway Projects (similar
configuration (2/4/6 laning**) and above)
< 5 years -0; 5 years -15 marks
Add one mark extra for each additional year of
experience subject to maximum 5 (five) marks.
iii) Experience in similar capacity as Pavement/Geo- 25
technical Engineer in construction/ construction
supervision of Major Highway projects (of length
equal to project length or more of similar
configuration (2/4/6 laning**) and above)
< 2 nos. -0
2 nos. -20 marks
Add 2.5 marks extra for each additional project
subject to maximum 5 marks.
iv) Experience in similar capacity on EPC Projects (of 5
length equal to project length or more of similar
configuration (2/4/6 laning**) and above)
1 Project- 4 marks
Add 1 (one) mark extra for each additional project
subject to maximum 1 (one) mark3 Employment with the Firm 5
< 1 year -0
1 year – 3 marks
Add 0.5 marks for each subsequent year subject to
maximum 2 marks
Total : 100
Note:
(1) Similar Capacity includes the following positions
i) On behalf of Consultant/Contractor: Pavement Specialist/ Pavement Engineer/
Pavement Expert / Highway Engineer
ii) On behalf of Government: Executive Engineer
(2) Only those projects (in numbers) will be considered for evaluation above, where the
input of the personnel is not < 6 months
(3) In case of experience on behalf of Authority’s Engineer or Contractor, the experience
shall be duly endorsed by the respective Government agency. In case of non-availability of
endorsementfrom Govt. Agency, the experience uploaded on INFRACON Portal will be taken into
consideration. However, the key personnel/ bidder will be solely responsible for any fake
information/ CV, which may result in debarment.
3.5 Senior Quality/Material Expert
Reference/Details Marks self-
Max.
S. No. Descriptio of projects Claimed assessed by
Points
n for self- the bidder
assessment
1 General Qualification 25
I) Graduate in Civil Engineering 18
II) Post Graduation in Geotechnical
Engineering/ Foundation Engineering/ Soil 04
Mechanics/ Rock Mechanics
16 days material testing process 03
course imparted by Indian Academy
of Highway Engineers orCRRI
2 Adequacy for the Project 70
Professional Experience
i) Total Professional Experience in handling 15
Highway/Bridge projects
< 10 years -0
10 years -11
Add one mark extra for each additional year of
experience subject to maximum 4 (four) marks.
ii) Experience in similar capacity in 25
Construction/Construction Supervision of major
Highway Projects ((similar configuration (2/4/6
laning**) and above))
< 5 years -0; 5 years -19
Add 2.0 (two) marks extra for each additional year of
experience subject to maximum 6 (Six) marks.
iii) Experience in similar capacity in handling Similar 30
Highway projects (of length equal to project length or
more of similar configuration (2/4/6 laning**) and
above)
< 2 nos. -0
2 nos. - 25
Add 2.5 marks extra for each additional project
subject to maximum 5 (five) marks.3 Employment with the Firm 5
< 1 year – 0
1 year – 3
Add 0.5 marks for each subsequent year subject to
maximum 2 marks
Total : 100
Note:
(1) Similar Capacity includes the following positions
i) On behalf of Consultant/Contractor: Quality Expert/ Material Engineer/Material
Expert/ Quality Engineer/ Geo-Technical Expert.
ii) On behalf of Government: Executive Engineer
(2) Only those projects (in numbers) will be considered for evaluation above, where the input
of the personnel is not < 12 months
(3) In case of experience on behalf of Authority’s Engineer or Contractor, the experience shall
be duly endorsed by the respective Government agency. In case of non-availability of
endorsement from Govt. Agency, the experience uploaded on Infracon Portal will be taken
into consideration. However, the key personnel/ bidder will be solely responsible for any fake
information/ CV, which may result in debarment.
3.6 Road Safety Expert
S. Descriptio Max. Reference/ Marks
No. n Points Details of self-
projects assesse
Claimed for d by the
self-
bidder
assessment
1 General Qualification 25
I) Graduate in Civil Engineering 18
II) Post-Graduation in Traffic/ Transportation/ 04
Safety Engineering or equivalent
15 days Certificate course on Road Safety 03
Audit from IAHE/CRRI
2 Adequacy for the Project 70
Professional Experience
i) Total Professional Experience in handling Highway/Bridge 15
projects
< 10 years -0
10 years -11 marks
Add one mark extra for each additional year of experience
subject to maximum 4 (four) marks.ii) Experience in similar capacity in Road Safety works on 15
Major Highway Project (similar configuration (2/4/6 laning**)
and above).
< 5 years -0
5 years -11 marks
Add one mark extra for each additional year of experience
subject to maximum 4 (four) marks.
iii) Experience in similar capacity in Road Safety Audits of 2/4/6- 20
laning** Highway projects at different stages including at
least one at design stage
< 2 nos. -0
2 nos. -15 marks
Add 2.5 marks extra for each additional project subject to
maximum 5 marks.
iv) Experience in similar capacity in identification and 10
improvement of black spots on Major Highway Project
(similar configuration (2/4/6 laning**) and above)
< 2 nos. -0
2 nos. -8 marks
Add 2 marks extra for each additional improvement of black
spots subject to maximum 2 marks.
v) Experience in similar capacity of preparing Road Safety 5
Management Plans for Inter Urban Highway
1 project -4 marks
2 or more -5 marks
vi) Experience in similar capacity in field of Road Safety 5
Management Plan
1 project -4 marks
2 or more -5 marks
3 Employment with the Firm 5
<1 year- 0
1 year – 3 marks
Add 0.5 marks for each subsequent year subject to
maximum 2 marks
Total : 100
Note:
(1) Similar Capacity includes the following positions
i) On behalf of Consultant/Contractor: Road Safety Expert
ii) In Government Organizations: Executive Engineer (or equivalent) and above
(2) Only those projects (in numbers) will be considered for evaluation above, where the
input of the personnel is not < 6 months3.7 Team Leader cum Senior Bridge Engineer:
Reference/Detail Marks self-
Max.
S. No. Description s of projects assessed by
Points
Claimed for self- the bidder
assessment
1 General Qualification 25
i) Graduate in Civil Engineering 17
ii) Post Graduation in /Structural 03
Engineering or equivalent specialised
stream of civil engineering
iii) training programme on 03
Collapse/failure of
bridges/structures or bridge
design from IAHE/ Govt Institute
iv) Essential Software Experience- 02
(MS Roads/ Projects, Prima
Vera or other relevant software
)
2 Adequacy for the Project 70
a) Professional Experience in
Bridge Projects:
i) Total Professional Experience in handling 15
Bridge projects
< 15 years -0
15 years -12 marks
Add 1 mark extra for each additional year of
experience subject to maximum 3 (three)
marks.
ii) Experience as Team Leader or similar capacity 10
in Highway Development projects of (similar
configuration (2/4/6 laning**) and above)
< 5 years -0
5 years -8 marks
Add 1 marks extra for each additional year of
experience subject to maximum 2 (two)
marks.iii) Experience as Team Leader or similar capacity 5
in Highway Development projects (of length
equal to project length or more of similar
configuration (2/4/6 laning**) and above)
1 project -4 marks add 1 mark extra for
additional projects subject to maximum1 (one)
mark
b) Experience as Team Leader or similar 30
capacity of at least Two projects in
Construction Supervision / AE/ IE/ Project
preparation involving at least one Major
Bridge (minimum 300 m length without
approaches) in the Project (project length or
more of similar configuration (2/4/6 laning**)
< 2 projects -0
2 Projects -20 marks
Add 5 marks for each additional project subject
to maximum 10 marks.
c) Experience as Team Leader/Project Manager 10
or similar capacity in Operation and
Maintenance of Major Bridge (minimum 300
m length without approaches) in the Project
(of length project length or more of similar
configuration (2/4/6 laning**)
1 project – 8 marks
Add 1 mark extra for each additional project
subject to maximum 2 (two) mark
3 Employment with the Firm 5
< 1 year -0
1 year – 3 marks
Add 0.5 marks for each subsequent year
subject to maximum 2 marks
Total : 100
3.8 Resident cum Pavement Specialist
Reference/Details of Marks
Max.
S. No. Description projects Claimed for self-
Points
self-assessment assessed
by the
bidder
1 General Qualification 25
i) Graduate in Civil Engineering 17ii) Post Graduation in 03
Transportation/Highway
Engineering/Structural
Engineering/Geotechnical Engineering
iii) Training programme from IAHE in 03
Highway/Pavement
iv) Essential Software Experience- 02
(MS Roads/ Projects, Prima
Vera or other relevant software
)
2 Adequacy for the Project 70
Professional Experience
i) Total Professional Experience in handling Highway 20
projects
< 12 years -0
12 years -16 marks
Add 2 mark extra for each additional year of
experience subject to maximum 4 (four) marks.
ii) Experience as Resident Engineer/Project 20
Director/Project Manager/Superintending Engineer
or equivalent/Executive Engineer or equivalent on
construction works/Authority
Engineer/Independent Engineer Projects (similar
configuration (2/4/6 laning*) and above).
< 5 years -0; 5 years -15 marks
Add 1 marks extra for each additional year of
experience subject to maximum 5 (five) marks.
iii) Experience in similar capacity in handling major 25
2/4/6-laning** projects (of length 40% of project
length or more of
similar configuration (2/4/6 laning**) and above)
< 2 nos. -0
2 nos. -19 marks
Add three marks extra for each additional project
subject to maximum 6 (Six) marks.iv) Experience in similar capacity of Highway Project 5
of Construction/Construction Supervision on EPC
Mode (of length 40% of project length or more of
similar configuration (2/4/6 laning**) and above)
1 Project- 4 marks
Add 1 (one) mark extra for each additional project
subject to maximum 1 (one) mark
3 Employment with the Firm 5
< 1 year -0
1 year – 3 marksReference/Details Marks self-
Max.
S. No. Descriptio of projects Claimed assessed by
Points
n for self- the bidder
assessment
Add 0.5 marks for each subsequent year
subject to maximum 2 marks
Total : 100
3.9 Senior Contract Specialist cum Planning Engineer
S. No. Descriptio Max. Reference Marks
n Points / Details of self-
projects assessed
Claimed by the
for self- bidder
assessment
1 General Qualification 25
I) Graduate in Civil Engineering 17
II) Post Graduate Degree in Law/PG in 03
management/certificate course in management/
certificate
course in construction management/certificate course
in contract management
iii) IAHE training programme on contract 03
Management/ project planning
iv) Essential Software Experience- (MS 02
Roads/ Projects, Prima Vera or other
relevant software )
2 Adequacy for the Project 70
Professional Experience
i) Total Professional Experience of Contract Management/ 20
planning Enginner.
< 15 years -0
15 years -15 marks
Add one mark extra for each additional year of experience
subject to maximum 5 (five) marks.
ii) Experience as Contract Specialist/ Planning Engineer on 20
any National/State Highway project.
< 4 years -0
4 years -15 marks
Add one mark extra for each additional year of experience
subject to maximum 5 (five) marks.iii) Contract Management of a large Highway contract say 15
over Rs.150 crore including experience of handling
variation orders, claims of the contractor and there
appropriate disposal
< 2 nos. -0
2 nos. -10
Add 2.5 marks extra for each additional project subject to
maximum 5 (five) marks.
iii) Planning Engineer of a large Highway Project say over 10
Rs.150 crore including experience of handling variation
orders, claims of the contractor and there appropriate
disposal
< 2 nos. -0
2 nos. -50
Add 2.5 marks extra for each additional project subject
to maximum 5 (five) marks.
v) Experience of Handling Arbitration cases in respect of any 5
Highway project.
1 project -4 marks
2 or more projects-5 marks
3 Employment with the Firm 5
<1 year- 0
1 year – 3 marks
Add 0.5 marks for each subsequent year subject to
maximum 2 marks
Total : 100
3.10 Team Leader cum Senior Tunnel Expert:
S. No. Descriptio Max. Reference Marks
n Points / Details of self-
projects assessed
Claimed by the
for self- bidder
assessment
1 General Qualification 25
I) Graduate in Civil/Mining Engineering or equivalent 18
II) Post-Graduate or chartered engineer in Mining 04
Engineering/ Geotechnical Engineering /Structural
Engineering/Rock Mechanics or equivalent
Attended Minimum 5 days training on tunnel from 03
IAHE/ITA/ any othe institute of repute
2 Adequacy for the Project 70
Total Professional Experiencea i) < 20 years -0 7
20years -5 marks
Add one mark extra for each additional year of experience
subject to maximum 2 (Two) marks.
a ii) Total professional experience in handling major tunnelling 8
projects
<15 years – 0 marks
15 years – 6 marks
Add 1 mark extra for each additional year of experience
subject to maximum 2 (two) marks.
a iii) Experience in major tunnel construction/construction 10
supervision projects (Road/Rail/Metro)
<10 years – 0 marks
10 years – 7 marks
Add 1.5 marks extra for each additional year of
experience subject to maximum 3 marks.
b Experience in Similar Capacity
b i) Experience as Team Leader or similar capacity in 10
construction
supervision of major tunnel projects (Road/Rail/Metro)
of length equal to or more than 4 Km
S. No. Descriptio Max. Reference Marks
n Points / Details of self-
projects assessed
Claimed by the
for self- bidder
assessment
<5 years – 0 marks
5 years – 7 marks
Add 1.5 marks extra for each additional year of experience
subject to maximum 3 marks
b ii) Experience as Team Leader or similar capacity of project 10
Preparation/Design of tunnel projects(Road/Rail/Metro) of
length 4 Km or more
1 Project – 8 marks
Add 1 mark extra for each additional projects subject to
maximum 2 marks.
b iii) Experience as Team Leader or similar capacity in 20
construction supervision of tunnels (Road/Rail/Metro) of
length 4 km or more
<2 project -0 marks
2 Projects – 15 marks
Add 1.25 mark extra for each additional projects subject to
maximum 5(five) marks.C) Experience in project preparation/ design of major tunnel 5
projects apart from those under 2 (b) (ii)
(Road/Rail/Metro)
1 project -4
marks
2 or more -5 marks
3 Employment with the Firm 5
<1 year- 0
1 year – 3 marks
Add 0.5 marks for each subsequent year subject to
maximum 2 marks
Total : 100
Note: As per RFP, Definition of Team Leader includes Project Manager/Resident Engineer/ or any
equivalent position.
** tunnel projects, unless specifically mentioned, to be considered for evaluation has to be
major tunnels of length equal to or more than 1.5 Km3.11R esident cum Tunnel Excavation Expert:
S. No. Descriptio Max. Reference Marks
n Points / Details of self-
projects assessed
Claimed by the
for self- bidder
assessment
1 General Qualification 25
I) Graduate in Civil/Mining Engineering or equivalent 18
II) Post-Graduate or chartered engineer in civil/Mining 04
Engineering or equivalent
Attended Minimum 5 days training on tunnel from 03
IAHE/ITA/ any othe institute of repute
2 Adequacy for the Project 70
Total Experience
a i) <15 years – 0 15
15 years – 12 marks
Add 1 mark extra for each additional year of experience
subject to maximum 3 (three) marks.
A ii) Total professional experience in handling major tunnelling 10
projects
< 10 years – 0
10 years – 7 marks
Add 1.5 marks extra for each additional year of
experience subject to maximum 3 (three) marks.
b Experience in Similar Capacity
b i) Experience as Tunnel Excavation Expert or similar capacity 10
in construction supervision of major tunnelling projects
(Road/Rail/Metro)
< 7 years – 0
7 years – 7 marks
Add 1.5 marks extra for each additional year of experience
subject to maximum 3 (three) marks.
b ii) Experience as Tunnel Excavation Expert or similar capacity in 20
construction supervision of tunnel projects
(Road/Rail/Metro) of minimum length of 4 km (Minimum
one year supervision in a project)
< 2 projects – 0
2 projects – 15 marks
Add 2.5 marks extra for each additional projects subject to
5 (five) marks.
b iii) Experience in tunnel design/ DPR/ preparation / feasibility 10
study/design review involving major tunnel projects
(Road/Rail/Metro) of minimum length of 4 km (minimum 1
year experience in a project)
1 project – 7 marksS. No. Descriptio Max. Reference Marks
n Points / Details of self-
projects assessed
Claimed by the
for self- bidder
assessment
Add 1 mark extra for each additional projects subject to
maximum 3 (three) marks
C) Experience in construction of major tunnel projects 5
(Road/Rail/Metro) apart from those under 2 (b) (ii)
1 project – 3 marks
Add 1 mark extra for each additional projects subject to
maximum 2 (two) marks.
3 Employment with the Firm 5
<1 year- 0
1 year – 3 marks
Add 0.5 marks for each subsequent year subject to
maximum 2 marks
Total : 10
0
Note:- Max Age = 65 Years
** tunnel projects, unless specifically mentioned, has to be major tunnels of length equal to or
more than 1.5 Km to be considered for evaluation
3.12T UNNEL DESIGN ENGINEER:
S. No. Descriptio Max. Reference Marks
n Points / Details of self-
projects assessed
Claimed by the
for self- bidder
assessment
1 General Qualification 25
I) Graduate in Civil Engineering or equivalent 18
II) Post-Graduate in Engineering (Structural) 04
Attended Minimum 5 days training on tunnel from 03
IAHE/ITA/ any othe institute of repute
2 Adequacy for the Project 70
Total Professional Experience
a i) <20 years – 0 15
20 years – 11 marks
Add 1 mark extra for each additional year of experience
subject to maximum 4 (four) marks.A ii) Total Professional Experience in handling major Tunnel 10
projects
<12 years – 0
12 years- 7 marks
Add 1 mark extra for each additional year of experience
subject to maximum 3 (three) marks.S. No. Descriptio Max. Reference Marks
n Points / Details of self-
projects assessed
Claimed by the
for self- bidder
assessment
b Experience in Similar Capacity
b i) Experience in tunnel design (Road/Rail/Metro) works in 10
similar capacity
<12 years – 0
12 years – 7 marks
Add 1 mark extra for each additional year of experience
subject to maximum 3 (three) marks.
b ii) Experience in similar capacity in Project Preparation/DPR 15
involving design of tunnels (Road/Rail/Metro)of more than
4 km length (Min. 1 year experience in a project)
< 3 projects – 0
3 projects – 11 marks
Add 1 mark extra for each additional projects subject to
maximum 4 (four) marks.
b iii) Experience in similar capacity in construction/construction 10
supervision projects involving design/design review of
tunnels of more than 4 Km length (Min. 1 year experience
in project)
<2 projects – 0
2 projects – 7 marks
Add 1.5 mark extra for each additional projects subject to
maximum 3(three) marks.
c i) Experience in innovation tunnel design (Road/Rail/Metro) 5
like immersed tunnel and sub-sea bored tunnel 1 projects
– 4 marks
2 or more projects -5 marks
c ii) Experience in design tunnel projects(Road/Rail/Metro) 5
apart from those under 2 (b) (ii)
1 project – 4 marks
2 or more projects – 5 marks
3 Employment with the Firm 5
<1 year- 0
1 year – 3 marks
Add 0.5 marks for each subsequent year subject to
maximum 2 marks
Total : 100
Note: Max Age =65Years** tunnel projects, unless specifically mentioned, has to be major tunnels of length equal to or
more than 1.5 Km to be considered for evaluation
3.13T UNNEL SAFETY EXPERT
S. No. Descriptio Max. Reference Marks
n Points / Details of self-
projects assessed
Claimed by the
for bidder
self-
assessment
1 General Qualification 25
I) Graduate in Civil/Mining Engineering or equivalent 18
II) Any professional Certification from a 04
recognized/statutory body on safety/health/shot firer
Attended Minimum 5 days training on tunnel safety 03
from IAHE/ITA/ any other institute of repute
2 Adequacy for the Project 70
Total Professional Experience
a i) <20 years – 0 15
20 years – 11 marks
Add 1 mark extra for each additional year of experience
subject to maximum 4 (four) marks.
A ii) Experience Tunnel (Road/Rail/Metro) Safety Works 15
<10 years – 0
10 years – 11 marks
Add 1 mark extra for each additional year of experience
subject to maximum 4 (four) marks.
a iii) International exposure in tunnel safety works in developed 10
countries
<7 years – 0
7 years – 7 marks
Add 1 mark extra for each additional projects subject to
maximum 3 (three) marks.
b Experience in Similar Capacity
b i) Experience in similar capacity of Tunnel Safety Audits 20
during construction stage of tunnel
projects(Road/Rail/Metro) of minimum length of 4 Km
< 2 projects – 0
2 projects – 15 marks
Add 1.25 mark extra for each additional projects subject to
maximum 5 (five) marks.
b ii) Experience in similar capacity of Tunnel Safety Audits in 10
design stage on tunnel projects (Road/Rail/Metro)
1 project – 8 marks
2 or more – 10 marksS. No. Descriptio Max. Reference Marks
n Points / Details of self-
projects assessed
Claimed by the
for self- bidder
assessment
C) Experience in construction of major tunnel projects 5
(Road/Rail/Metro) using
1 project – 3 marks
Add 1 mark extra for each additional projects subject to
maximum 2 (two) marks.
3 Employment with the Firm 5
<1 year- 0
1 year – 3 marks
Add 0.5 marks for each subsequent year subject to
maximum 2 marks
Total : 100
Note: Max Age = 65 Years
** tunnel projects, unless specifically mentioned, has to be major tunnels of length equal to or more than
1.5 Km to be considered for evaluation3.14S enior Geotechnical Expert:
S. Descriptio Max. Reference Marks
No. n Points / Details of self-
projects assessed
Claimed by the
for self- bidder
assessment
1 General Qualification 25
I) Graduate in Civil Engineering / Masters in 18
Engineering Geology or equivalent from a
recognized university
II) Post Graduate in Rock Mechanics /Foundation 04
Engineering/ Tunnel Engineering
iii) Attended Minimum 5 days training on tunnel 03
safety from IAHE/ITA/ any other institute of
repute in Geotechnical
2 Adequacy for the Project 70
Total Professional Experience
a i) <20 years – 0 15
20 years – 11 marks
Add 1 mark extra for each additional year of
experience subject to maximum 4 (four) marks.
A ii) Experience in Construction/ Construction Supervision 10
of major tunnel projects(Road/Rail/Metro
< 10 years – 0
10 years – 7 marks
Add 1 mark extra for each additional year of
experience subject to maximum 3 (three) marks.
b Experience in Similar Capacity
b i) Experience as Geotechnical engineer or similar 25
capacity in construction/ construction supervision of
at least 4 tunnel projects(Road/Rail/Metro) of length
equal to or more than 4 km
< 4 projects – 0
4 projects -17 marks
Add 2 mark extra for each additional project subject
to maximum 8 (eight) marks
b ii) Experience as Geotechnical engineer or similar 5
capacity in Construction/ Construction Supervision of
major tunnel projects involving vertical shaft sinking
of at least 200m vertical depth
1 project – 4 marks
2 or more projects – 5 marksS. Descriptio Max. Reference Marks
No. n Points / Details of self-
projects assessed
Claimed by the
for self- bidder
assessment
B iii) Experience as Geotechnical engineer or similar 15
capacity in design/project preparation of tunnel
projects(Road/Rail/Metro) of at least 4 km length
< 2 projects – 0
2 projects – 11 marks
Add 2 marks extra for each additional projects subject
to maximum 4 (four) marks.
3 Employment with the Firm 5
<1 year- 0
1 year – 3 marks
Add 0.5 marks for each subsequent year subject to
maximum 2 marks
Total : 100
Note:- Max Age =65 Years
** tunnel projects, unless specifically mentioned, has to be major tunnels of length equal to or
more than 1.5 Km to be considered for evaluation.
3.15 Senior GEOLOGIST:
S. Descriptio Max. Reference Marks
No. n Points / Details of self-
projects assessed
Claimed by the
for self- bidder
assessment
1 General Qualification 25
I) Masters in Geology /Applied Geology 22
from recognized university.
iii) Attended Minimum 5 days training on tunnel 03
safety from IAHE/ITA/ any other institute of
repute in Geotechnical
2 Adequacy for the Project 70
Total Professional Experience
a i) <<20 years – 0 20
20 years – 15 marks
Add 1 mark extra for each additional year of experience
subject to maximum 5 (five) marks.
A ii) Experience in major Tunnel construction/construction 15
supervision Projects (Road/Rail/Metro) using NATM
technology
< 5 years – 0
5 years – 12 marksAdd 1.5 marks extra for each additional year subject to
maximum 3 (three) marks.
b Experience in Similar Capacity
b i) Experience in major Tunnel(Road/Rail/Metro) Construction 15
works in similar capacity
< 7 years – 0
7 years – 12 marks
Add 1 mark extra for each additional year of experience
subject to maximum 3 (three) marks.
b ii) Experience in similar capacity in project preparation/DPR 10
involving of major tunnel projects (Road/Rail/Metro). (Min
1 year experience in a project)
<2 projects – 0
2 projects -7 marks
Add 1.5 marks extra for each additional projects subject to
maximum 3 (three) marks.
b iii) Experience in similar capacity in highway tunnel 10
construction/construction supervision with minimum length of
4 Km
< 2 projects – 0
2 project – 7 marks
Add 1.5 marks extra for each additional projects subject to
maximum 3 (three) marks.
3 Employment with the Firm 5
<1 year- 0
1 year – 3 marks
Add 0.5 marks for each subsequent year subject to
maximum 2 marks
Total : 100
Note: Max Age = 65 Years
** tunnel projects, unless specifically mentioned, has to be major tunnels of length equal to or
more than 1.5 Km to be considered for evaluation
Note: applicable to all key personnel:
If a key personnel has worked in next lower category to the similar capacity, the marks
allotted to key personnel in the category ‘experience in similar capacity’ shall be reduced To
two thirds of marks in this category. This shall be applicable for evaluation of all key
personnel.
2. ** Similar projects means 2/4/6 lane as applicable for the project for which RFP is
invited. For 2-lane projects experience of 4/6 lane also to be considered with a
multiplication factor of
1.5. Experience of 4/6 lane shall be considered interchangeably for 4/6 laning projects. For
4/6 laning projects, experience of 2 lane will be considered with a multiplication factor of
0.4.4.0 Requirements with respect to Technical Capacity Provision for
maximum number of consultancy services to be awarded to one consultant:
(i) The maximum number of consultancy services to be awarded to one consultant will
be governed by the following provisions:
• Residual AE/IE Bid Capacity viz., “R” shall be more than the tentative length of the Project
For Normal Highway Projects
• R= CL x TF - RP
Wherein:
Completed Length (CL) = Length of AE/IE completed NHs/Expressways in last 5 FY.
Turnover Factor (TF)= Multiplication factor based on Turnover
Average Annual Turnover of Last 5 Financial years Turn Over Factor “TF”
Upto 50 cr 1.00
50 to 250 cr 1.25
>250 crores 1.50
Running Projects (RP)= Length of AE/IE Projects in Hand wherein provisional Completion Certificate/ completion
certificate not issued, Includes projects for which firm has emerged as H-1 bidder but LOA have not been issued.
R to be calculated for each JV member & weighted average as per Share in JV be considered.
The applicants shall submit the requisite details for determination of technical capacity in the prescribed
format Technical Capacity (Form T-11) enclosed.BIDDING FORMSTechnical ProposalForm T-1: Proposal Form (Covering Letter)
(Ref ITC-clause 9.2)
(To be submitted as part of Technical Proposal, along with supporting documents, if
any)
(on Consultant’s Letter-head)
(Strike out alternative phrases not relevant to you)
Consultant’s Name
[Address and Contact Details]
Consultant’s Reference No. Date……….
To
The President of India, through
Head of Procurement
Procuring Organisation
[Complete address of the Procuring Entity]
Ref: Your RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services
Sir/ Madam
1. We, the undersigned, offer to provide consulting services in accordance with your
above-referenced Request for Proposals (RFP) and our Proposal. We are hereby
submitting our Proposal, which includes this Technical Proposal and a separately
uploaded Financial Proposal. Commercial information about our organisation is
enclosed in Form T-1A.
We are submitting our Proposal without any Sub-consultants or JV.
Or
We are submitting our Proposal with the following firms as Sub-consultants:
{Insert a list with each Sub-consultant's full name and address.}
Or
We are submitting our proposal as a joint venture with {Insert a list with each
member's full name and legal address and indicate the lead member}. We have
attached a copy of the following document signed by every participating
member, which details the (likely) legal structure and the confirmation of joint
and severable liability of the members of the said joint venture.
our letter of intent to form a joint venture
the JV agreement2) Our Eligibility and Qualifications to participate
a) We confirm that we continue to comply with all the eligibility (including the
absence of conflict of interest and debarment) and qualification criteria
stipulated in this RFP. We shall be dutybound to proactively inform you of
any change in our compliance with these criteria as soon as it occurs.
b) We confirm that we don’t have any Conflict of Interest as stipulated in this
RFP. We shall be duty bound to proactively inform you of any change in our
compliance with Conflict-of-Interest stipulations as soon as it occurs.
3) Our Proposal to deliver Services:
We offer to deliver the subject Services of requisite Performance Standards and within
Delivery Schedules in conformity with the RFP Document. The relevant details are
submitted in ‘Form T-4: Description of Approach, Methodology and Work Plan in
responding to Terms of Reference’; Form T-5: Work Schedule and Planning of
Deliverables and Form T-6: Team Composition, Assignment and Key Experts’ Inputs’.
4) Prices:
We hereby offer to perform the Services at our lowest prices and rates mentioned in
the separately uploaded Financial Proposal. It is hereby confirmed that the prices
quoted therein by us are:
(a) Based on the terms of delivery and delivery schedule confirmed by us; and
(b) Cost break-up of the quoted cost, showing inter-alia costs (including taxes and
duties thereon) of all the included incidental Goods/ Works considered necessary
to make the proposal self-contained and complete, has been indicated therein,
and
(c) based on the terms and mode of payment as stipulated in the RFP Document. We
have understood that if we quote any deviation from the terms and mode of
payment, our Proposal is liable to be rejected as nonresponsive, and
(d) have been arrived at independently, without restricting competition, any
consultation, communication, or agreement with any other Consultant or
competitor relating to:
i) those prices; or
ii) the intention to submit an offer; or
iii) the methods or factors used to calculate the prices offered.
(e) Have neither been nor shall be knowingly disclosed by us, directly or indirectly,
to any other Consultant or competitor before the Proposal opening unless
otherwise required by law.
5) We declare regarding commissions or fees paid or are to be paid to agents,
representatives, or commission agents concerning the selection process or execution
and performance of this Contract, that: No such commissions or gratuities or fees have been paid are to be paid by us
to any third party
Or
We have paid/ are due to pay the following commissions/ gratuities/ fees:
-------------
(indicate the name and address of the agent, representative, or commission agent,
the amount and currency, and the purpose of the commission or fee.)
6) No change in the Key Experts
Except as stated in the RFP Document, we undertake to negotiate a Contract based
on the proposed Key Experts. We accept that substituting Key Experts for reasons
other than those stated in ITC-Clause 12.3 may lead to the termination of contract
negotiations.
7) Affirmation of terms and conditions of the RFP Document:
We have understood the complete terms and conditions of the RFP Document. We
accept and comply with these terms and conditions without reservations, although
we are not signing and submitting some of the RFP document's sections. Deviations,
if any, are submitted by us in Form T-7: ‘Terms and Conditions - Compliance’. We
also explicitly confirm acceptance of the Arbitration Agreement as given in the RFP
Document.
8) Bid Security: We have submitted the Bid Security as
a) Earnest Money Deposit (EMD) for the amount of Rs.
(Rupees……………………………….) valid upto in favour of
…………………… in the form of Insurance Surety Bonds/ Account Payee
Demand Draft/ Fixed Deposit Receipt/ Banker’s cheque/ Payment online/ Bank
Guarantee in Form T-9A, with reference number dated , issued
by . as per the RFP Documents. or
b) Bid Securing Declaration (BSD, in lieu of Bid Security, if permitted in TIS) in
stipulated format vide Form T-9B.
9) Abiding by the Proposal's Validity
We agree to keep our Proposal valid for acceptance for a period upto -------, as
required in the RFP Document, or for a subsequently extended period, if any, agreed
to by us, and are aware of penalties in this regard stipulated in the RFP Document in
case we fail to do so.
10) Non-tempering of Downloaded RFP Documents and Uploaded Scanned Copies We
confirm that we have not changed/ edited the contents of the downloaded RFP
Document. We realise that any change noticed at any stage, including after the
contract award, shall be liable to punitive action in this regard stipulated in the RFP
Document. We also confirm that scanned copies of documents/ affidavits/
undertakings uploaded during the shortlisting process and this RFP are valid, true,and correct to the best of our knowledge and belief. We shall be responsible if any
dispute arises regarding the validity and truthfulness of such documents/ affidavits/
undertakings. We undertake to submit for scrutiny, on-demand by the Procuring
Entity, originals and self-certified copies of all such certificates, documents, affidavits/
undertakings.
11) A Binding Contract:
We further confirm that if our proposal is accepted, all such terms and conditions
shall continue to be acceptable and applicable to the resultant contract, even though
some of these documents may not be included in the contract Documents submitted
by us. We do hereby undertake that until a formal contract is signed or issued, this
Proposal and your written Letter of Award shall constitute a binding contract between
us.
12) Performance Guarantee and Signing the contract
We further confirm that if our proposal is accepted, we shall provide you with
performance security of the required amount stipulated in the RFP Document for the
due performance of the contract. We are fully aware that in the event of our failure
to deposit the required security amount and/ or execute the agreement, the Procuring
Entity has the right to avail of any or all punitive actions stipulated in the RFP
Document.
13) Penalties for misinterpretation or misrepresentation:
We hereby confirm that the particulars given above are factually correct and nothing
is concealed and undertake to advise any future changes to the above details. We
understand that any misinterpretation or misrepresentation would violate the Code
of Integrity and attract penalties, as this RFP Document mentions.
14) Consultant’s Authorized Signatory:
a) Full Name:
b) Designation:
c) Signing as:
A sole proprietorship firm. The person signing the Proposal is the sole proprietor/
constituted attorney of the sole proprietor,
A partnership firm. The person signing the Proposal is duly authorised being a
partner to do so under the partnership agreement or the general power of attorney,
A company. The person signing the Proposal is the constituted attorney by a
resolution passed by the Board of Directors or in pursuance of the Authority conferred
by the Memorandum of Association.
A Society. The person signing the Proposal is the constituted attorney.
We confirm that we are duly authorized to submit this Proposal and make
commitments on behalf of the Consultant. We acknowledge that our digital/digitized
signature is valid and legally binding. Supporting documents are submitted herewith.Documents to be submitted: Registration Certificate/ Memorandum of
Association/ Partnership Agreement/ Power of Attorney/ Board Resolution
15) Rights of the Procuring Entity to Reject Proposal(s):
We further understand that you are not bound to accept the lowest or any Proposal
you may receive against your above-referred RFP Document.
……………………..
(Signature with date)
………………………..
(Name and designation)
Duly authorized to sign Proposal for and on behalf of
[name, address, and seal of Consultant]Form T-1A: Consultant’s Commercial Information
Note: Consultant shall fill in the following information and enclose certified copies of the
documentary proof/ evidence to substantiate the corresponding statement wherever
necessary and applicable.
(Please tick appropriate boxes or strike out sentences/ phrases not applicable to you)
Consultant particulars:
a) Name of the Consultant:……………….
b) Corporate Identity No. (CIN): ……………………………………..
c) Registration, if any, with The Procuring Entity: …………………………………..
d) Place of Registration/ Principal place of business”
……………………………….
e) Complete Postal Address: …………………………………………..
f) Pin code/ ZIP code: ………………………………………………….
g) Telephone nos. (with country/ area codes): ………………………
h) Mobile Nos.: (with country/ area codes): ……………………..
i) Contact persons/ Designation: …………………………………….
j) Email IDs: …………………………………………………………….
Submit a self-certified copy of the registration certificate – in case of a partnership firm
– Deed of Partnership; in case of a Company – Notarized and certified copy of its
Registration; and in case of Society – its Byelaws and registration certificate of the firm.
All these documents should be Notarized.
Taxation:
PAN number: ……………………………………………….
Type of GST Registration as per the Act (Normal Taxpayer, Composition, Casual
Taxable Person, SEZ, etc.): ………………………….
GSTIN number: ................................................ in Consultant and Service Site
States
Registered/ Certified Offices from where the Services would be supported and
Place of Service Site for GST Purpose: ……………….
Contact Names, Nos. & email IDs for GST matters (Please mention primary and
secondary contacts): …………………………………
Comments on Tax liability and the breakup of CGST, SGST, IGST and Cess
in this assignment:
Documents to be submitted: Self-attested Copies of PAN card and GSTIN Registration.
Trade Registrations and Licences
We have the following registrations/ licences required for the performance of this
Service (tick as applicable). Authenticated copies of these are enclosed herewith:
EPF
ESI
Labour Licence Any other required -------------------------------- --.
Consultant’s Authorized Representative Information
Name:
Address:
Telephone/ Mobile numbers:
Email Address:
(Signature with date)
………………………..
(Name and designation)
Duly authorized to sign Proposal for and on behalf of
[name, address and seal of Consultant]
DA: As aboveForm 1.2: Eligibility Declarations
(On Consultant’s Letter-head)
(Along with supporting documents, if any)
REOI document No. REOI/ xxxx; Tender Title: Consultancy Services
Consultant’s Name_________________________ [Address and Contact Details]
Consultant's Reference No.___________________________ Date……….
[Note: The list below is indicative only. You may attach more documents as required to confirm your
eligibility criteria.]
Eligibility Declarations
(Please tick appropriate boxes or cross out any declaration not applicable to the consultant)
We hereby confirm that we comply with all the stipulations of REOI Clause 4.1 of the REOI document and
declare as under and shall provide evidence of our continued eligibility to the Procuring Entity as and when
it may be requested:
1) Legal Entity of Consultant: We are:
a) : ____________________________ relevant documents enclosed)
b) We are a Consultancy Services provider with valid registration regarding GSTIN, PAN, EPF, ESI, Labour,
or equivalent registration certificate as applicable to the subject Services.
2) Eligibility: We solemnly declare that we (including our affiliates or subsidiaries, or constituents):
(a) are not insolvent, in receivership, bankrupt or being wound up, not have our affairs administered by a
court or a judicial officer, not have our business activities suspended and are not the subject of legal
proceedings for any of these reasons;
(b) (including our affiliates or subsidiaries, or constituents for any part of the assignment):
i) Do not stand declared ineligible/ blacklisted/ banned/ debarred by the Procuring Organisation or its
Ministry/ Department from participation in its procurement processes; and/ or
ii) Are not convicted (within three years preceding the last date of EOI submission) or stand declared
ineligible/ suspended/ blacklisted/ banned/ debarred by appropriate agencies of the Government of India
from participation in procurement processes of all its entities for offences mentioned in REOI document in
this regard.
iii) We have neither changed our name nor created a new "Allied Entity", consequent to the above
disqualifications.
(c) Do not have any association (as consultant/ partner/ Director/ employee in any capacity) with such
retired public official or near relations of such officials of Procuring Entity, as counter-indicated, in the
REOI document.
(d) We have no conflict of interest, which substantially affects fair competition. The quoted prices are
competitive without adopting unfair/ unethical/ anti competitive means. No attempt has been made or
shall be made by us to induce any other consultant to submit or not to submit an EOI to restrict
competition.
(e) We certify that we fulfil other additional eligibility conditions if prescribed in the REOI document.
3) We certify that we are not an entity from a country identified to restrict Consultants from India from
participation in their Government Procurements as per EOI clause 4.2.1
4) Restrictions on procurement from consultants from a country or countries or a class of
countries under Rule 144 (xi) of the General Financial Rules 2017:
"We have read the clause regarding restrictions on procurement from a consultant of a country whichshares a land border with India and on sub-contracting to contractors from such countries, and solemnly
certify that we fulfil all requirements in this regard and are eligible to be considered. We certify that:
a) we are not from such a country or, if from such a country, we are registered with the Competent
Authority (copy enclosed). and;
b) we shall not subcontract any assignment to a contractor from such countries unless such a contractor is
registered with the Competent Authority.
5) Startup Status: We confirm that we are (Certificate of Recognition issued by the Department for
Promotion of Industry and Internal Trade (DPIIT) enclosed herewith)/ are not a Startup entity as per the
Department of Promotion of Industrial and Internal Trade – DPIIT.
6) Penalties for false or misleading declarations: We hereby confirm that the particulars given above are
factually correct and nothing is concealed and undertake to advise any future changes to the above
details. We understand that any wrong or misleading self-declaration would violate the Code of Integrity
and attract penalties.
…………………….. ………………………..
(Signature with date) (Name and designation)
Duly authorised to sign EOI for and on behalf of
……………………………………….
……………………………………….Name, address, and seal of the Consultant] DA: As in Sr 1 to 5 above, as
applicableForm T-2: Consultant’s Organisation and Experience
(Ref ITC-clause 9.2)
(To be submitted as part of Technical Proposal) (on Consultant’s
Letter-head)
(Along with supporting documents, if any) Consultant’s Name
[Address and Contact Details]
Consultant’s Reference No. Date……….
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services
Form-2: Please fill out this form to briefly describe the Consultant’s organization and outline
the recent consultant experience most relevant to the assignment. In the case of a joint
venture, information on similar assignments shall be provided for each partner. For each
assignment, the outline should indicate the names of the Consultant’s Key Experts and Sub-
consultants who participated, the duration of the assignment, the contract amount (total
and, if it was done in the form of a joint venture or a Sub- consultant, the amount paid to
the Consultant), and the Consultant’s role/involvement.
A - Consultant’s Organization :- The proposal should contain the following
information in enclosed format attached
• Year of Establishment of Firm
• Average annual turnover (last three years)
Note: The Firm shall submit Certificate of Incorporation and audited balance sheet for
the last three years [FY 2014-2015, FY 2015-2016 and FY 2016-2017]*. For claiming
experience of Highway projects, completion certificate from employer should be enclosed.
The proposal should also contain the details of the key personnel viz. their name,
qualification, expertise area, experience and years of association with the firm.
*To be modified appropriately.
The following information related to the firm should be provided in the proposal.
i. Name of the package applied for:-
ii. Year of establishment of firm*
Consultant Year of Country Type of Organization
Establishmen Individua Partnership Corporation Other
t l
Individual / Lead
Partner (of JV)/
Minor Partner of
JV/Associate
NOTE:- Year of Establishment of Lead Partner of JV shall be considered.
*Copy of Certificate of incorporation shall be submitted.
iii. Office/ Business Address/Telephone nos. /Cable Address.
iv. Narrative description of firm (Not more than 2 sheets)
v. Name of two (2) principals who may be contacted with title and
telephone number/fax number/e-mail.vi. Financial Statement of the last three years. **
Sl. No. Particula <2014- < 2015- <2016-
r 15> 16> 17>
i. Annual turnover from Consulting business of
civil Engineering Projects
ii. Total Assets
iii. Current Assets
Balance Sheet/ Auditor Certificate of last 3years <2014-15, 2015-16 and 2016-17> shall
be submitted as evidence of Annual Turnover. Annual financial statement turnover duly
certified by the Statutory Auditor with UDIN certifying turnover from consulting buissness
of civil Engineering Projects may also be Provided.
** a) The amount shall be stated in INR. (Consider 1US Dollar = Rs. And 1 Euro
= Rs.) (This will be the exchange rates as per Reserve Bank of India rounded off
to nearest Rupee applicable at the time of RFP invitation).
b) The currency conversion rate for the respective years shall be mentioned for
other International currencies.
B - Consultant’s Experience
1. List only previous similar assignments completed in the last [ 7 ] years.
i) List only those assignments for which the Consultant was legally contracted
by the client directly or was one of the joint venture members. Assignments
completed by the Consultant’s individual experts working privately or through
other consulting firms cannot be claimed as the relevant experience of the
Consultant or that of the Consultant’s partners or Sub-consultants - but can
be claimed in their CVs. The Consultant should be prepared to substantiate
the claimed experience by presenting copies of relevant documents and
references, as requested by the Procuring Entity. Experience as Authority
Engineer/Independent Consultant/Construction supervision of Highway projects, separately
for PPP and non-PPP Projects during the last 7 years. ***
S Projects Type of Description Client (with Total Fee Fee received %age of Approx. Period
No Name / Year Services of Highway complete for the by Applicant (in total fee Cost of
Sole rendered Project/ address, Consultancy case of received Highway
Consultant/ Length contact Assignment JV/Association) by the Project
Prime (kms) person, (INR) firm
Consultant of Telephone
JV / minor Nos. and
Authority’s Fax Nos.)
Engineer of
JV/ /as
associate
consultant
1 2 3 4 5 6 7 8 9 10
A. Completed / Substantially completed projects:S Projects Type of Description Client (with Total Fee Fee received %age of Approx. Period
No Name / Year Services of Highway complete for the by Applicant (in total fee Cost of
Sole rendered Project/ address, Consultancy case of received Highway
Consultant/ Length contact Assignment JV/Association) by the Project
Prime (kms) person, (INR) firm
Consultant of Telephone
JV / minor Nos. and
Authority’s Fax Nos.)
Engineer of
JV/ /as
associate
consultant
1.
2.
3.
B. Projects in progress:
1.
2.
3.
ii) Experience in DPR/ Feasibility Study cum Preliminary Design Report preparation of 2/4/6
laning / Bridge Highway Projects separately for the PPP and non-PPP projects during the last
7 years. ***
S No Projects Name / Type Length Client Total Fee Fee received by %age of Period
Year of (with for the Applicant total fee
Sole of Project Complete Consultancy (in case of received
Consultant/ Services (kms) address, Assignment JV/Association) by the firm
Prime Rendered contact (INR) ca
Consultant of JV / person, se of JV)
minor Authority’s telephone
Engineer of JV/ /as Nos. and
associate Fax Nos.)
consultant
1 2 3 4 5 6 7 8 9
***a) 2/4/6 lane/Bridge work as applicable for the project for which RFP is invited. For 2-
lane projects experience of 4/6 lane also to be considered with a multiplication factor
of 1.5. Experience of 4/6 lane shall be considered interchangeably for 4/6 laning
projects. For 4/6 lane projects, experience of 2 lane will be considered with a
multiplication factor of 0.4, but only for those 2-lane projects whose cost of
consultancy services was more than Rs.3.0 crores. For standalone bridge projects,
experience in bridge work (either standalone project or as a part of road project) only
be considered.
b) Only those projects, to be included in the table which are Highways Projects and
for which clients certificates from the concerned Government agencies are enclosed
with the proposal.
c) The details of bridges having length more than 200m (500m in case the project
consist of bridges of length more than 500m) in the listed projects is to be
specifically mentioned.
d) The weightage given for experience of a firm would depend on the role of the firm inthe respective assignments. The firm’s experience would get full credit if it was
the sole firm in the respective assignment. If the applicant firm has completed
projects as JV with some other firms, weightage shall be given as per the JV
share***. However if the applicant firm has executed the project as associate with
some other firms, 25% weightage shall be given to the applicant firm for the
projects completed under such association
e) For weightage of experience in any past Consultancy assignment, experience
certificate from the client shall be submitted. In absence of clear demarcation of JV
share in client certificate, the weightage will be treated as 60 % for lead partner
and 40% for minor partner. Annual turnover duly certified by Chartered Accountant
shall be accepted. In case of non-availability of such documents no weightage of
turnover/experience will be considered.
iii) Assignments on hand including those for which the Letter of Acceptance from the clients received
as on 7 days prior to due date for submission of proposals: The details shall be given in the following
format.
S. Name of Client Role of the Date of Date of Present Team Members provided
No Assignment firm letter of Agreemen status of by the firm
Sole, Lead/ Acceptance t if signed Assignment
Other in JV or
sub-
Name DOB Position
consultant
(1) (2 (3) (4) (5 (6 (7 (8) (9) (10)
) ) ) )
Key Personnel Number of key personnel employed
Sole Applicant JV (1)
(Lead Member
in case of JV)
Team Leader cum Senior Highway Engineer
Resident cum Highway Engineer
Bridge/Structural Engineer
Senior Pavement Specialist
Senior Quality cum Material Expert
Road Safety Expert
2. FACILITY FOR FIELD INVESTIGATION AND TESTING
1. State whether applicant has in-house (created in house at site)/ outsourced/ not
available facility for
• Surface defects detection and roughness measurement using Network Survey
Vehicle
• Pavement strength measurement using FWD
• Bridge inspection using Mobile Bridge Inspection Unit• Road signs inspection using Retro Reflectometer
2. In-case answer to 1 is available (created in house at site) a list of field investigation
and testing equipment is to be attached
3. In case answer to 1 is outsourced/not available – arrangements made or
proposed to be made for each of the above field investigations is to be attached
4. For experience in NSV, FWD, MBIU and reflectometer, references need to be
provided in the following format:
REFERENCES
Relevant Services Carried Which Best Illustrate Qualifications
The following information should be provided in the format below for each reference
assignment for which your firm, either individually as a corporate entity or as one of
the major companies within a consortium, was legally contracted by the client:
Assignment Name: Country:
Location within Country: Professional Staff Provided by your firm:
Name of Client : No. of Staff :
Address : No. of Staff Months :
Technology Used:
Start Date Completion Date Approx. Value of Services in INR/current USD):
(Month / Year) (Month / Year)
Name of JV/Association Firm(s)if any: No. of Months of Professional Staff provided by
Associated Firm(s)
Status of your Company in the Assignment i.e., Sole/Lead Member/Other Member/Associate
Narrative Description of Project :
Description of Actual Services Provided by your Company:
Signature of Authorised Representative
(Certificate from Employer regarding experience should be furnished)Form T-2A
Format for Technical Capacity of Applicants
(TO BE FILLED BY THE SOLE CONSULTANT & IN CASE OF JV, SEPARATELY BY JV MEMBERS
BIDDING FOR THE ASSIGNMENT)
Details of all in-hand AE/ IE/ SC projects or AE/ IE/
(i)
SC awarded by MoRTH or its executing agencies for NH works
and centrally sponsored road works:
Sl. Project Civil works Start Scheduled Whether In case of JV,
No. Description Provisionally Date Completion awarded in share of
completed or Current Financial Contract Fee
Original assignment Year (%)
period+ one year
lapsed
(Yes/ No) (Yes/ No)
1 2 3 4 5 6 7
Format for undertaking by the firm for in-hand AE/ IE/ SC Projects:
The undersigned on behalf of --------------------------------- (name of consulting firm) certify that the firm do not
have any other in-hand/ awarded AE/ IE/ SC project other than those listed above. Date (dd/mm/yyyy)
[Signature of authorized representative of the Firm]
Note 1:
The figures in Col 7 be rounded off to the nearest integer i.e. in case remaining bid-capacity
comes to 0.5 or more then it will be considered as 1, in case less than 0.5 then it will be
considered as 0 (Zero).
Note 2:
Clarification for technical capacity utilised in case of JV with other firm than proposed in current
assignment.
In case Firm-1 proposes for new JV with other partner, then capacity utilisation will be calculated
on the basis of JV share in existing assignments e.g.
JV in one project with 30% share:-One projectX0.3=0.3 JV in one project with70% share:-One projectX0.7=0.7 JV in one project with 50% share:-One
projectX0.5=0.5 JV in two projects with 80% share:-Two projectX0.8=1.6 The
weighted utilization of the Capacity of Firm-1=3.1
Note 3:
The Consultant shall re-submit the bid capacity details as per above format at the time of opening of Financial Bid.
Form T-3: Comments and Suggestions on the Terms of Reference,
Counterpart Staff, and Facilities to be provided by the Procuring Entity
(Ref ITC-clause 9.2)
(To be submitted as part of Technical Proposal) (Along with supporting documents, if any)
(on Consultant’s Letter-head)
RFP Document No. RFP No./ xxxx;
Tender Title: Consultancy Services
Consultant’s Name
[Address and Contact Details]
Consultant’s Reference No. Date……….
Form T-3: Comments and Suggestions on the areas that have not been provided or any changes
*to the existing provisions of the Terms of Reference, Counterpart Staff, and Facilities to be
provided by the Procuring Entity that could improve the quality/effectiveness of the assignment.
Specifically mention where your proposal deviates from Section VI: Terms of Reference. A - ON
THE TERMS OF REFERENCE
Note: Suggest and justify any modifications or improvements to the Scope of Work you are
proposing to improve performance in carrying out the assignment (such as deleting some activity
you consider unnecessary, adding another, or proposing a different phasing of the activities).
Such suggestions should be concise, to the point, and incorporated into your proposal.
Consultants must maintain the same numbering and structure as in Section VI: ‘Terms of Reference’
and Section VI-A: List of Key Experts and Required Qualifications.
B - ON COUNTERPART STAFF AND FACILITIES & OTHER AREAS
{Comments on counterpart staff and facilities to be provided by the Procuring Entity. For
example, administrative support, office space, etc., if any}Form T-4: Description of Approach, Methodology a nd
Work Plan in Responding to the Terms of Reference
(Ref ITC-clause 9.2)
(To be submitted as part of Technical Proposal) (on Consultant’s Letter-head)
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services
Consultant’s Name_________________________
[Address and Contact Details]
Consultant’s Reference No.___________________________ nce Date……….
Form T-4: a description of the approach, methodology for quality control and work
plan for performing the assignment, including a detailed description of the proposed
methodology and staffing for training if the Terms of Reference specify training as a
specific component of the assignment.
{Suggested structure of your Response:
a) Technical Approach and Methodology
b) Work Plan
c) Organization and Staffing}
A) Technical Approach and Methodology
{Please explain your understanding of the objectives of the assignment as outlined in
the ‘Terms of Reference’ (TORs), the technical approach, and the methodology you
would adopt for implementing the tasks to deliver the expected output(s), and the degree
of detail of such output. Please do not repeat/copy the TORs here.}
B) Work Plan.
{Please outline the plan for implementing the main activities/tasks of the assignment,
their content and duration, phasing and interrelations, milestones (including interim
approvals by the Procuring Entity), and tentative delivery dates of the reports. The
proposed work plan should be consistent with the technical approach and methodology,
showing your understanding of the TOR and ability to translate them into a feasible
working plan. A list of the final documents (including reports) to be delivered as final
output(s) should be included here. The work plan should be consistent with Form T-5:
‘Work Schedule and Planning of Deliverables’.}
C) Organization and Staffing.
{Please describe the structure and composition of your team, including the list of the Key
Experts, Non-Key Experts, and relevant technical and administrative support staff. The
Organization and staffing should be consistent with Form T-6: ‘Team Composition,
Assignment, and Key Experts’ Inputs.}
……………………..
(Signature with date)
………………………..
(Name and designation)
Duly authorized to sign Proposal for and on behalf of……………………………………….
[name, address, and seal of Consultant ]
DA: Relevant documents like technical data, literature, drawings, and other documentsForm T-5: Work Schedule and Planning for Deliverables3
(Ref ITC-clause 9.2)
(To be submitted as part of Technical Proposal) (on Consultant’s Letter-head)
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy
Services Consultant’s Name
[Address and Contact Details]
Consultant’s Reference No. Date……….
{Please outline the Plan for implementing the main activities/ tasks of the assignment, their
content and duration, phasing and interrelations, milestones (including interim approvals by the
Procuring Entity), and tentative delivery dates of the deliverables. The proposed work plan should
be consistent with the technical approach and methodology, showing your understanding of the
ToR, any challenges likely to be encountered during the programmatic implementation, the
mitigations proposed and the ability to translate them into a feasible working plan. A list of the final
documents (including reports) to be delivered as final output(s) should be included here. The work
plan should be consistent with the Work Schedule Form.}
A. Activity Schedule
Month wise Program(information of Bar Chart)
[1st,2nd, etc. are months from the start of
assignment]
S Item of Activity 1 2 3 4 5 6 7 8 9 1 1 1
r (Works) s n r t t t t t t 0 1 2
t d d h h h h h h
. t t t
h h h
N
o
.
1 .........................
.......................
2 .........................
.......................
3 .........................
.......................
4 .........................
.......................
- .........................
.......................
- .........................
.......................B. Completion and Submission of Reports
S Reports : Program
r me Date)
.
N
o
1 Monthly reports
(Design and Construction)
2 Quarterly Reports
3 Various others reports as provided in the Concession Agreement such as
Completion ReportForm T-6: Team Composition, Assignment, and Key Experts’ Inputs
(Ref ITC-clause 9.2)
(To be submitted as part of Technical Proposal) (on Consultant’s Letter-head)
RFP Document No. RFP No./ xxxx;
Tender Title: Consultancy Services
Consultant’s Name
[Address and Contact Details]
Consultant’s Reference No. Date……….
Note to Consultants: RFP indicates key Personnel (Managers/ Supervisors/ Executives/
Specialists/ Technicians) and the number of non- key staff required to perform the
services to the required performance standards and quality. The consultant shall
quote the cost of these personnel in the Financial Proposal. TIME SCHEDULE FOR
PROFESSIONAL PERSONNEL
2. Technical/Managerial Staff
Sl. No. Name Position Task
1
2
3
4
…
…
i. Support Staff
Sl. No. Name Position Task1
2
3
4
…
…Annex to Form T-6: Key Expert Curriculum Vitae (CV)
(For all Key Experts separately) (Ref ITC-clause
9.2)
(To be submitted as part of Technical Proposal) (Along with
supporting documents, if any)
(on Consultant’s Letter-head)
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services Consultant’s Name
[Address and Contact Details]
Consultant’s Reference No.
Date………
. Proposed Position : ………………………………………………
Photograp
h Name of
Firm:.....................................................................................
...
Name of Staff :........................................................................................
Profession :..............................................................................................
Date of Birth :
YearswithFirm/Entity: ...........................................Nationality:..............................
Membership of
Professional Societies :.........................................................................
Detailed Task Assigned : Please attach printout of CV along with all the relevant
details uploaded on infracon portal.
Certification by the Candidate
I, the undersigned,(Name and Address) undertake that this CV correctly describes
myself, my qualifications and my experience and Employer would be at liberty to
debar me if any information given in the CV, in particular the Summary of
Qualification & Experience vis-à-vis the requirements as per TOR is found incorrect.
I further undertake that I have neither been debarred by <Agency> or any other
central/stage government organization nor left any assignment
with
th
e consultants engaged by Employer / contracting firm (firm to be supervised now)for any continuing work of Employer without completing my assignment. I will be
available for the entire duration of the current project (named… ).If I leave this
assignment in the middle of the
work, Employer would be at liberty to debar me from taking
any assignment in any of the Employer works for an appropriate period of time
to be decid ed by the Employer. I have no objection if my services are extended
by the Employer for this work in future.
I further undertake that my CV is being proposed for this project by (the applicant firm)
and I have not given consent to any other consultant(s) to propose my CV for any
position for this project.
I further undertake that if due to my inability to work on this project due to
unavoidable circumstances, due to which consultant’s firm is forced to seek
replacement. In such unavoidable circumstances, I shall not undertake any
employment in Employer projects during the period of assignment of this project and
Employer shall consider my CV invalid till such time.
I undertake that I have no objection in uploading/hosting of my credentials by
Employer in public domain.
For Key Personnel having intermittent inputs, add the following:
I further certify that I am associated with the following assignments as on date (as
on 7 days prior to due date for submission of proposal) including those for which
LOA has been received by the firm and the inputs in these assignments shall not
effect the work of the current assignment.
Name of Assignment Client Date of Likely start Likely end Total input of the
LOA (Month / Year) (Month / Year) person (man-
months)
Adequacy for the Assignment:
Detailed Tasks Assigned on Consultant’s Reference to Prior Work/Assignments that
Team of Experts: Best Illustrates Capability to Handle the
Assigned Tasks
{List all deliverables/tasks as in FORM T-
5 in which the Expert shall be involved)Expert’s contact information: (e-mail …………………., phone ............... )
Date (Signature of Key Personnel)
(Day/Month/Year)
The Authority’s Engineer should carryout self-evaluation based on the evaluation
criteria at Appendix-EC and furnish the same here. While submitting the self-
evaluation along with bid, Authority’s Engineer shall make references to the
documents which have been relied upon in his self-evaluation.
Certification by the firm
The undersigned on behalf of ----------( name of consulting firm) certify that Shri (name
of proposed personnel) to the best of our knowledge has neither been debarred by
<Agency> or any other Central/State Government organization nor left his
assignment with any other consulting firm engaged by the Employer /Contracting
firm(firm to be supervised now) for the ongoing projects. We understand that if the
information about leaving the past assignment is known to the Employer, Employer
would be at liberty to remove the personnel from the present assignment and debar
him for an appropriate period to be decided by the Employer.
…………………………………………………………..Date ..... (Day/Month/Year)
[Signature of authorized representative of the Firm]
a) Deleted.
b) Deleted.
c) Deleted.
d) Deleted.
e) Deleted.
f) DeletedForm T-7: Terms and Conditions - Compliance
(Ref ITC-clause 9.2)
(To be submitted as part of Technical Proposal)
(on Consultant’s Letter-head)
Consultant’s Name
[Address and Contact Details]
Consultant’s Reference No. Date……….
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services
Note to Consultants: Fill up this Form regarding Terms and Conditions in the RFP
Document, maintaining the same numbering and structure. Add additional details not
covered elsewhere in your Proposal in this regard.
Sl. No. Ref of RFP Document Subject Confirmation/ Justification/
Section, Clause Deviation/ Reason
Exception/
Section Clause/
reservation
sub-clause
We shall comply with, abide by, and accept without variation, deviation, or reservation
all terms and conditions of the RFP Document, except those mentioned above. If
mentioned elsewhere in our Proposal, contrary terms and conditions shall not be
recognised and shall be null and void.
……………………..
(Signature with date)
………………………..
(Name and designation)
Duly authorized to sign Proposal for and on behalf of
……………………………………….
……………………………………….
[name, address, and seal of Consultant ]
DA: If any, at the option of the Consultant.Form T-8: Checklist for Consultants
(Ref ITC-clause 9.2)
(To be submitted as part of Technical Proposal)
(on Consultant’s Letter-head)
Consultant’s Name
[Address and Contact Details]
Consultant’s Reference No.
Date……….
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services
Note to Consultants: This checklist is merely to help the Consultants prepare their
Proposals; it does not override or modify the tender requirement. Consultants must do
their own due diligence also.
Sr Documents submitted, duly filled, signed Yes/ No/
NA
1. Form T-1.- Proposal Form (to serve as covering letter and
declarations applicable for both the Techno-commercial and
Financial Proposal)
2. Form T-1A: Consultant’s Commercial Information, Power of
attorney, Registration Certificates, etc.
3. Form T-2: Consultant’s Organisation and Experience
4. Form T-3: Comments and Suggestions on Terms of Reference…
5. Form T-4: Description of Approach, Methodology and Work
Plan…
6. Form T-5: Work Schedule and Planning of Deliverables
7. Form T-6: Team Composition, Assignment and Key Experts’
Inputs. Annex containing all CVs
8. Form T-7: Terms and Conditions - Compliance
9. Form T-8: This Checklist – was ticked appropriately
10. Form T-9A: Bank Guarantee Format for Earnest Money Deposit
or Form T-9B: Bid Securing Declaration – as applicable
11. Form T-10: Duly signed Integrity Pact, If stipulated in AITC.
12. Financial Proposal was separately uploaded
13. Any other requirements, if stipulated in TIS/ AITC; or if considered
relevant by the ConsultantForm T-9A: Bank Guarantee Format for Earnest Money
Deposit
(The Bank Guarantee shall be on a Stamp Paper of appropriate value in accordance
with Stamp Act and shall be purchased in the name of the guarantee issuing Bank or
the Party on whose behalf the BG is being issued.)
(Ref ITC-clause 13.1.2 and GCC-clause 5.8)
Ref Bank Guarantee No……………
Date……………………………...
To
The President of India, through
Head of Procurement
Procuring Organisation
[Complete address of the Procuring Entity]
Whereas M/s……………………………………………………with its Registered/ Head
Office at…………………………. (name and address of the Consultant, hereinafter
called “the Consultant”, which expression shall, unless repugnant to the context or
meaning thereof, include its successors, administrators, executors and assigns) has
undertaken to submit a proposal, in pursuance of Tender no ……….. date…………….
(hereinafter called “the Tender”).
And Whereas you (unless repugnant to the context or meaning thereof, including your
successors, administrators, executors, and assigns) have stipulated in the said Tender
that the Consultant shall furnish you with a bank guarantee by a Commercial bank for
the sum specified therein as Earnest Money Deposit for compliance with its obligations
as per the Tender;
And Whereas we …………………… with our Head Office at………………………….
(name and address of the Bank, hereinafter referred to as the ‘Bank’, which expression
shall, unless repugnant to the context or meaning thereof, include its successors,
administrators, executors and assigns) have agreed to give the Consultant such a bank
guarantee.
Now, Therefore, we hereby affirm that we are guarantors and responsible to you, on
behalf of the Consultant, up to a total of
…………………………………………………….(amount of the guarantee in words
and figures), and we undertake to pay you, upon your first written demand declaring
the Consultant to be in default under the Tender and without cavil or argument, any sum
or sums within the limits of (amount of guarantee) as aforesaid, without your needing
to prove or to show grounds or reasons for your demand or the sum specified therein,
notwithstanding any difference between you and the Consultant or any dispute pending
before any Court, Tribunal, Arbitrator or any other authority.
Form T-9A: Bank Guarantee Format for Earnest Money Deposit [125]We hereby waive the necessity of your demanding the said debt from the Consultant
before presenting us with the demand.
The Bank undertakes not to revoke this guarantee during its currency without your
previous consent and further agrees that the guarantee herein contained shall continue
to be enforceable till you discharge this guarantee. This guarantee will not be discharged
due to a change in the constitution of the Bank or the Consultant’s.
We further agree that no change or addition to or other modification of the terms of the
Tender made by you shall in any way release us from any liability under this guarantee,
and we hereby waive notice of any such change, addition, or modification.
This guarantee shall be valid until the ………….day of …….20……
Our………………………………….branch at………………*(Name & Address of
the
………….…………..*(branch) is liable to pay the guaranteed amount depending on the
filing of a claim and any part thereof under this Bank Guarantee only and only if you
serve upon us at our .................... * branch a written claim or demand and received by
us at our …………………..* branch on or before Dt… .......... otherwise, the bank shall
be discharged of all liabilities under this guarantee after that.
(Signature of the authorized officer of the Bank)
………………………………………….
………………………………………….
Name and designation of the officer
…………………………………………
Seal, name & address of the Bank and address of the
Branch
*Preferably at the authority's headquarters competent to sanction the expenditure for
procurement of goods/services or at the concerned district headquarters or the state
headquarters.Form T-9B: Bid Securing Declaration
Consultants exempted from submission of Bid Security are also required to submit this.
(on Consultant’s Letter-head)
Consultant’s Name
[Address and Contact Details]
Consultant’s Reference No. Date……….
To
The President of India, through
Head of Procurement
Procuring Organisation
[Complete address of the Procuring Entity]
Ref: RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services
Sir/ Madam
We, the undersigned, solemnly declare that:
We understand that according to this RFP document's conditions, the Proposal must be
supported by a Bid Securing Declaration in lieu of Bid Security.
We unconditionally accept the conditions of this Bid Securing Declaration. We
understand we (all members individually and jointly in case of JV/C) shall stand
automatically suspended from being eligible for bidding in any tender in Procuring
Organisation for 2 years from the date of opening of this Proposal if we breach our
obligation(s) under the tender conditions if we:
Withdraw/ amend/ impair/ derogate, in any respect, from our Proposal, within
the Proposal validity; or
Being notified within the Proposal validity of the acceptance of our Proposal by
the Procuring Entity:
(a) Refused or failed to produce the original documents for scrutiny or the
required Performance Security within the stipulated time under the RFP
document's conditions.
(b) Fail or refuse to sign the contract.
We know that this Proposal-Securing Declaration shall expire
1) If the contract is not decided - forty-five days after the expiration of the Proposal
validity, any extension to it.
2) If the contract is not awarded to us - not later than thirty days after the conclusion of
the resultant contract, or
Form T-9B: Bid Securing Declaration [127]3) If the contract is awarded to us - after receipt of performance security from them
(Signature with date)
………………………..
(Name and designation)
Duly authorized to sign Proposal for and on behalf of……………………….
[name, address, and seal of Consultant ]
Dated on …………. day of ................ [insert date of signing]
Place… ........................................... [ insert place of signing]
DA:…………………………………………………Form T-10: Integrity Pact
(If stipulated in TIS, ref Claus 9.2.1 of ITC)
(To be signed on Plain Paper)
(To be submitted as part of Technical Proposal)
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services
This Agreement (hereinafter called the Integrity Pact) is made on day of the month
of 202 at , India.
BETWEEN
Procuring Organisation, ----------------------------------- through Head of the Procuring
Organisation, for and on behalf of President of India (hereinafter called the “The
Principal”, which expression shall mean and include unless the context otherwise
requires, his successors in office and assigns) of the First Part
AND
M/ s. (hereinafter called the “The Consultant”,
which expression shall mean and include unless the context otherwise requires, his
successors and permitted assigns) of the Second Part.
PREAMBLE
‘The Principal’ intends to award, under laid down organizational procedures, contract/ s for
, ‘The Principal’ values full compliance with all relevant laws
of the land, rules, regulations, economical use of resources and fairness/ transparency
in its relations with its Consultant(s) and/ or Consultant(s).
In order to achieve these goals, the Principal shall appoint Independent External
Monitors (IEMs) who shall monitor the Procurement Process and the execution of the
contract for compliance with the abovementioned principles.
Section 1 - Commitments of the ‘The Principal’
(1) ‘The Principal’ commits itself to take all measures necessary to prevent corruption
and to observe the following principles: -
a. No employee of the Principal, personally or through family members, shall, in
connection with the tender for, or the execution of a contract, demand, take a promise
for or accept, for self or third person, any material or immaterial benefit which the
person is not legally entitled to.
b. The Principal shall, during the Procurement Process, treat all Consultant(s) with
equity and reason. The Principal shall, in particular, before and during the Procurement
Process, provide to all Consultant(s) the same information and shall not provide to any
Consultant(s) confidential/ additional information through which the Consultant(s) could
obtain an advantage in relation to the Procurement Process or the contract execution.
c. The Principal shall exclude from the process all known prejudiced persons.
(2) If the Principal obtains information on the conduct of any of its employees, which
is a criminal offence under the IPC/ PC Act, or if there be a substantive suspicion in thisregard, the Principal shall inform the Chief Vigilance Officer and in addition, can initiate
disciplinary actions.
Section 2 - Commitments of the ‘Consultant’
(1) The ‘Consultant’ commit themselves to take all measures necessary to prevent
corruption. The ‘Consultant’ commit themselves to observe the following principles
during participation in the Procurement Process and during the contract execution.
a. The ‘Consultant’ shall not, directly or through any other person or firm, offer,
promise, or give to any of the Principal’s employees involved in the Procurement Process or
the execution of the contract or to any third person any material or other benefit which he
is not legally entitled to, in order to obtain in exchange any advantage of any kind
whatsoever during the Procurement Process or during the execution of the contract.
b. The ‘Consultant’ shall not enter any undisclosed agreement or understanding
with other Consultants, whether formal or informal. This applies in particular to prices,
specifications, certifications, subsidiary contracts, submission or non-submission of
Proposals or any other actions to restrict competitiveness or to introduce cartelisation in
the Procurement Process.
c. The ‘Consultant’ shall not commit any offence under the relevant IPC/ PC Act;
further, the ‘Consultant’ shall not use improperly, for purposes of competition or
personal gain, or pass on to others, any information or document provided by the
Principal as part of the business relationship, regarding plans, technical proposals, and
business details, including information contained or transmitted electronically.
d. The ‘Consultant’ of foreign origin shall disclose the name and address of the
Agents/ representatives in India, if any. Similarly, the Consultant/ Contractors of Indian
Nationality shall furnish the name and address of the foreign principals, if any. Further
details, as mentioned in the “Guidelines on Indian Agents of Foreign Suppliers”, shall
be disclosed by the Consultant. Further, as mentioned in the Guidelines, all the
payments made to the Indian agent/ representative must be in Indian Rupees only. A
copy of the “Guidelines on Indian Agents of Foreign Suppliers” is placed in the Appendix to
this agreement.
e. The ‘Consultant’ shall, when presenting their Proposal, disclose any and all
payments made, are committed to, or intends to make to agents, brokers, or any other
intermediaries in connection with the contract award.
f. Consultant who has signed the Integrity Pact shall not approach the Courts while
representing the matter to IEMs and shall wait for their decision in the matter.
(2) The ‘Consultant’ shall not instigate third persons to commit offences outlined
above or be an accessory to such offences.
Section 3 - Disqualification from Procurement Process and exclusion from future
contracts
If the ‘Consultant’, before award or during execution, has committed a transgression
through a violation of Section 2, above or in any other form such as to put their reliability
or credibility in question, the Principal is entitled to disqualify the ‘Consultant’ from theProcurement Process or take action as per the procedure mentioned in the “Guidelines on
Banning of business dealings”.
Section 4 - Compensation for Damages
(1) If the Principal has disqualified the ‘Consultant’ from the Procurement Process
prior to the award according to Section 3, the Principal is entitled to demand and recover
from the ‘Consultant’ the damages equivalent to Earnest Money Deposit/ Bid Security.
(2) If the Principal has terminated the contract according to Section 3, or if the
Principal is entitled to terminate the contract according to Section 3, the Principal shall
be entitled to demand and recover from the Consultant liquidated damages of the
contract value or the amount equivalent to Performance Bank Guarantee.
Section 5 - Previous transgression
(1) Consultant declares that no previous transgressions occurred in the last three
years with any other Company in any country conforming to the anti-corruption
approach or with any Public Sector Enterprise in India that could justify his exclusion
from the Procurement Process.
(2) If the Consultant makes an incorrect statement on this subject, he can be
disqualified from the Procurement Process, or action can be taken as per the procedure
mentioned in “Guidelines on Banning of business dealings”.
Section 6 - Equal treatment of all Consultants/ Contractors/ Subcontractors
(1) In the case of Sub-contracting, the Principal Consultant shall take responsibility
for the adoption of the Integrity Pact by the Sub-contractor.
(2) The Principal shall enter into agreements with identical conditions as this one with
all Consultants and Contractors.
(3) The Principal shall disqualify from the Procurement Process all Consultants who
do not sign this Pact or violate its provisions.
Section 7 - Criminal charges against violating Consultant(s)/ Consultant(s)/
Subcontractor(s)
If the Principal obtains knowledge of the conduct of a Consultant, Consultant or
Subcontractor, or of an employee or a representative or an associate of a Consultant,
Consultant or Subcontractor, which constitutes corruption, or if the Principal has
substantive suspicion in this regard, the Principal shall inform the same to the Chief
Vigilance Officer.
Section 8 - Independent External Monitor
(1) The Principal appoints a competent and credible Independent External Monitor
for this Pact after approval by Central Vigilance Commission. The task of the Monitor is
to review independently and objectively whether and to what extent the parties comply
with the obligations under this agreement.
(2) The Monitor is not subject to instructions by the representatives of the parties and
performs his functions neutrally and independently. The Monitor would have access to
all Contract documents whenever required. It shall be obligatory for him/ her to treatthe information and documents of the Consultants/ Contractors as confidential. He/ she
reports to the Head of the Procuring Organisation.
(3) The Consultant(s)/ Consultant(s) accepts that the Monitor has the right to access,
without restriction, all Project documentation of the Principal, including that provided by
the Consultant. The Consultant shall also grant the Monitor, upon his request and
demonstration of a valid interest, unrestricted and unconditional access to their project
documentation. The same is applicable to Sub-contractors.
(4) The Monitor is under contractual obligation to treat the information and
documents of the Consultant(s)/ Sub-contractor(s) with confidentiality. The Monitor has
also signed declarations on ‘Non-Disclosure of Confidential Information’ and of Absence
of Conflict of Interest. In case of any conflict of interest arising at a later date, the IEM
shall inform the Head of the Procuring Organisation and recuse himself/ herself from that
case.
(5) The Principal shall provide to the Monitor sufficient information about all
meetings among the parties related to the Project, provided such meetings could have
an impact on the contractual relations between the Principal and the Consultant. The
parties offer the Monitor the option to participate in such meetings.
(6) As soon as the Monitor notices, or believes to have noticed, a violation of this
agreement, he shall so inform the Management of the Principal and request the
Management to discontinue or take corrective action, or to take other relevant action.
The monitor can, in this regard, submit non-binding recommendations. Beyond this, the
Monitor has no right to demand from the parties that they act in a specific manner,
refrain from action, or tolerate action.
(7) The Monitor shall submit a written report to the Head of the Procuring
Organisation within 8 to 10 weeks from the date of reference or intimation to him by
the Principal and, should the occasion arise, submit proposals for correcting problematic
situations.
(8) If the Monitor has reported to the Head of the Procuring Organisation a
substantiated suspicion of an offence under the relevant IPC/ PC Act, and the Head of
the Procuring Organisation has not, within the reasonable time, taken visible action to
proceed against such offence or reported it to the Chief Vigilance Officer, the Monitor
may also transmit this information directly to the Central Vigilance Commissioner.
(9) The word ‘Monitor’ would include both singular and plural.
Section 9 - Pact Duration
This Pact begins when both parties have legally signed it. It expires for the Consultant
12 months after the last payment under the contract and for all other Consultants 6
months after the contract has been awarded. Any violation of the same would entail
disqualification of the Consultants and exclusion from future business dealings.
If any claim is made/ lodged during this time, the same shall be binding and continue
to be valid despite the lapse of this pact as specified above unless it is discharged/
determined by the Head of the Procuring Organisation.Section 10 - Other provisions
(1) This agreement is subject to Indian Law. The place of performance and
jurisdiction is the Registered Office of the Principal, i.e., New Delhi.
(2) Changes and supplements, as well as termination notices, need to be made in
writing. Side agreements have not been made.
(3) If the Consultant is a partnership or a consortium, this agreement must be signed
by all partners or consortium members.
(4) Should one or several provisions of this agreement turn out to be invalid, the
remainder of this agreement remains valid. In this case, the parties shall strive to come
to an agreement with their original intentions.
(5) Issues like Warranty/ Guarantee etc., shall be outside the purview of IEMs.
(6) In the event of any contradiction between the Integrity Pact and its Appendix, the
Clause in the Integrity Pact shall prevail.
For and on behalf of the Principal
(Name of the Officer and Designation)
(Office Seal)
For and on behalf of ‘Consultant.’
(Name of the Officer and Designation)
(Office Seal)
For and on behalf of the Principal
Place
Date
Witness 1:
(Name & Address)
Witness 2:
(Name & Address)
≤══≥Appendix to Integrity Pact
Guidelines for Indian Agents of Foreign Suppliers
1.0 There shall be compulsory registration of agents for all Global (Open) Tender and Limited Tender.
An agent who is not registered with ‘The Principal’ shall apply for registration in the registration form with the
appropriate unit.
1.1 Registered agents shall file an authenticated Photostat copy duly attested by a Notary Public/ Original
certificate of the Principal confirming the agency agreement. It should cover - the precise relationship,
services to be rendered, and mutual interests in business - generally and/ or specifically for the tender.
Any commission/ remuneration/ salary/ retainership, which the agent or associate receives in India or
abroad from the Principal, whether should be brought on record in the Agreement and be made explicit.
1.2 Wherever the Indian representatives have communicated on behalf of their principals and the foreign
parties have stated that they are not paying any commission to the Indian agents, and the Indian
representative is working on the basis of salary, or a retainer, a written declaration to this effect should
be submitted by the party (i.e., Principal) before finalizing the order.
2.0 Disclosure of particulars of agents/ representatives in India, if any.
2.1 Consultants of Foreign nationality shall furnish the following details in their offers:
2.1.1 The ‘Consultant’ of foreign origin shall disclose the name and address of the agents/ representatives in
India, if any and the extent of authorization and authority given to commit the Principals. In case the
agent/ representative be a foreign Company, it shall be confirmed whether it is an existing Company and
details of the same shall be furnished.
2.1.2 The amount of commission/ remuneration included in the quoted price(s) for such agents/
representatives in India.
2.1.3 Confirmation of Consultant that the commission/ remuneration, if any, payable to his agents/
representatives in India, may be paid by ‘The Principal’ in Indian Rupees only.
2.2 Consultants of Indian Nationality shall furnish the following details in their offers:
2.2.1 The ‘Consultant’ of Indian Nationality shall furnish the name and address of the foreign principals, if
any, indicating their nationality as well as their status, i.e., whether manufacturer or agents of
manufacturer holding the Letter of Authority of the Principal authorizing the agent specifically to make an
offer in India in response to tender either directly or through the agents/ representatives.
2.2.2 The amount of commission/ remuneration included in the price (s) quoted by Consultant for himself.
2.2.3 Confirmation of the foreign principals of Consultant that the commission/ remuneration, if any,
reserved for Consultant in the quoted price(s), may be paid by ‘The Principal’ in India in equivalent Indian
Rupees on satisfactory completion of the Project or supplies of Services.
2.3 In either case, in the event of contract materializing, the terms of payment shall provide for payment
of the commission/ remuneration, if any, payable to the agents/ representatives in India in Indian Rupees on
expiry of 90 days after the discharge of the obligations under the contract.
2.4 Failure to furnish correct and detailed information as called for in clauses above shall render the
concerned Proposal liable to rejection or, in the event of a contract materializing, the same liable to
termination by ‘The Principal’. Besides this, there would be a penalty of banning business dealings with
‘The Principal’ or damage or payment of a named sum.FORMATSFormat 1: Contract Form
(Ref ITC-clause 13)
The President of India, through
Head of Procurement
Procuring Organisation
[Complete address of the Procuring Entity]
Contract No…………. dated…………….
To
Consultant [Write Name]
[Complete address of the Consultant]
Subject: ---------------------------------------------------------------------------------------------
Ref: 1. This office’s Letter of Award No……………..….. dated ……..
2. This office RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services, dated…………. and subsequent Amendment
No.…………., dated .......... (If any). (Hereinafter referred to as ‘the RFP Document’)
3. Your Tender No……… dated…….. and subsequent communication(s)/ Revised Offer No………… dated …….. (If any), exchanged
between you and this office in connection with this tender. (Hereinafter referred to as ‘Your Offer’)
Dear Sir/ Madam,
Your Proposal referred above, read with subsequent letters mentioned above, for the Services stipulated in the Schedules annexed
herewith, have been accepted. Terms and conditions in this Contract and the documents listed in the clause below shall apply.
Note: The words, expressions, definitions, and abbreviations used in this Contract shall have the same meanings as those assigned in
the General Condition of Contract enclosed.
2)
The following documents attached hereto shall be deemed to form an integral part of this Contract:
a) The General Conditions of the Contract;
b) The Special Conditions of the Contract;Procurement of Consultancy Services
c) Appendices:
i) Appendix A: Terms of Reference
ii) Appendix B: Key Experts
iii) Appendix C: Remuneration Cost Estimates
iv) Appendix D: Reimbursable Cost Estimates
v) Appendix E-1: Bank Guarantee Format for Performance Security
vi) Appendix E-2: Bank Guarantee Format for Advance Payments
In the event of any inconsistency between the documents, the following order of precedence shall prevail: this Contract Form; the Special
Conditions of Contract; the General Conditions of Contract; Appendix A; Appendix B; Appendix C and Appendix D; Appendix E-1; and
Appendix E-2. Any reference to this Contract shall include, where the context permits, a reference to its Appendices.
3)
Key Information
a) Summary of Costs
Name of Work: Procurement of Consultancy Services
Tender No: Tend No./ xxxx
Name of the Bidder/ Bidding
Firm/ Company:
Remuneration CGST SGST %age IGST %age Cess %age Reimbursables Total Cost
as per %age And And Amount And Amount And as per Appendix Contract with
Appendix C Amount Amount D Taxes
1 2 3 4 5 6 7 8
%age of GST
Cost in Figs
Cost in Words
b) Timelinesi) Effective Date of The Contract as per Work Plan in Appendix A
ii) Completion Date of the Services as per Work Plan in Appendix A
4)
The mutual rights and obligations of the Procuring Entity and the Consultant shall be as outlined in the Contract, in particular:
a) the Consultant shall carry out the Services in accordance with the provisions of the Contract; and
b) the Procuring Entity shall make payments to the Consultant in accordance with the provisions of the Contract.
(Signature, name and address of [Procuring Entity]’s authorized, official) For
and on behalf of the President of India
Received and accepted this Contract ……………………………………………………..
(Signature, name, and address of the Consultant’s executive duly authorized to sign on behalf of the Consultant. For a joint venture,
either all members shall sign or only the lead member, in which case a power of attorney to sign on behalf of all members shall be
attached.)
For and on behalf of ………………………
(Name and address of the Consultant)
…………………….
(Seal of the Consultant) Place: Date:Appendix A: Description of Services
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services
Contract No ; Date
Consultant’s Name
[This Appendix shall include the final Terms of Reference (TORs), Approach,
Methodology and Work Schedule and Planning of Deliverables, worked out by the
Procuring Entity and the Consultant during the negotiations; dates for completion of
various tasks; location of performance for different tasks; detailed reporting
requirements; Procuring Entity’s input, including counterpart personnel assigned by the
Procuring Entity to work on the Consultant’s team; specific tasks that require prior approval
by the Procuring Entity.]
Terms Reference
Insert the text based on Section VI (Terms of Reference) of the RFP and modify it based
on Forms T-1 through Form T-7 in the Consultant’s Proposal. Highlight the changes to
Section VI of the RFP]Approach, Methodology and Quality Control plan
Insert the text based on Form T-4 in the Consultant’s Proposal as negotiated between the
Procuring Entity and the Consultant.Work Schedule and Planning for Deliverables
Insert the text based on Form T-5 in the Consultant’s Proposal as negotiated between the
Procuring Entity and the Consultant.Appendix B: Key Experts
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services
Contract No ; Date
Consultant’s Name
[Insert a table based on Form T-6 of the Consultant’s Technical Proposal and finalized at
the Contract’s negotiations. Attach the CVs (updated and signed by the respective Key
Experts) demonstrating the qualifications of Key Experts.]
The Consultants Key personnel and all other Professional / Sub Professional / Support
Staff/Sub-Consultancy personnel shall work 6 days (Mondays through Saturday) every
week and observe the Gazetted Holidays of Government of India as Holidays. The
Consultant shall work as per the work program of the EPC Contractor. In this context in
case the work plan of the Consultant needs suitable modifications, the same shall be carried
out and submitted to the client for consideration. The Consultants hours of work normally
shall match with that of Contractor’s activities on the site. No extra remuneration shall be
claimed or paid for extra hours of work required in the interest of Project completion.
ln addition, casual Leave for 12 days shall be permitted in a year to each Key Personnel/
Sub-Professional with prior intimation to the Authority. Out of this, a maximum of 3 CLs
can be awaited either separately or together in a quarter and the period of the CLs would
be counted as Key Personnel /Sub Professional being on duty.
In respect of foreign personnel, one day per trip as travel time from and to the country of the
Government shall be allowed.APPENDIX C-: FINANCIALPROPOSALSUBMISSIONFORM FROM: (Name of Firm)
Subject:
We, the undersigned, offer to provide the consulting services for the above in accordance with
your Request for Proposal dated [Date], and our proposal. Our attached financial proposal is for
the sum of [Amount in words and figures]. This amount is exclusive of the local taxes which we
have estimated at (Amount in Words and Figures). The percentage of overhead charges on the
remuneration as mentioned in Serial no. I of Appendix C-1 (Summary of cost) w.r.t. the
professional staff shall be [Amount in words and figures]
Our financial proposal shall be binding upon us upto the expiration of the validity period of the
proposal, i.e., [Date].
We undertake that, in competing for (and, if the award is made to us, in executing) the above
contract, we will strictly observe the laws against fraud and corruption in force in India namely
“Prevention of Corruption Act 1988”.
Commission and gratuities, if any, paid or to be paid by us to agents relating to this proposal
and contract execution, if we are awarded the contract, are listed below:
Name and Address of Agents ............................... ............................... Amount and Currency
........................... ........................... Purpose of Commission or Gratuity ……..…………………
……………………….
We understand you are not bound to accept any proposal you receive.
We remain,
Yours sincerely,
Managing Director/Head of the firm/ Authorised Representative of the firm* Name of the firm
Address *Lead Member in case of JVAPPENDIX C-1
Remuneration Cost Estimates
(To be filled by the Authority before inviting Bid and amount to
be filled by bidder)
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services Contract No
; Date Consultant’s
Name
No. Description Amount (Rs.)
I Remuneration for Local Professional Staff
II Supporting Staff
III Transportation
IV Duty Travel to Site
V Office Rent
VI Office Supplies, Utilities and Communication
VII Office Furniture and Equipment
VIII Reports and Document Printing
IX Road Survey Equipment
X Contingencies
Xi %Overhead of the firm on remuneration of local Professional
Staff. (The % overhead cannot be quote@ less than 10%. If
remuneration quote @ less than 10%, the financial proposal
will be non-responsive and will not be considered for further
evaluation.
Sub Total
Goods and Services Tax Payable in India
Total Costs (Including Tax)
Note: Payments will be made as per stipulations of the Conditions of Contract.
We, the undersigned, offer to provide the consulting services for the above in accordance
with your Request for Proposal dated [Date], and our proposal. Our attached financial
proposal is for the sum of
RFP Document - RFP No./ xxxxAnnex to Appendix C-1: BREAKDOWN OF LOCAL CURRENCY COSTS
(To be filled by the Authority before inviting Bid)
II. REMUNERATION FOR LOCAL PROFESSIONAL STAFF
Normal Highway Project
For Project with Construction Period of 18 months
No. Position Name Construction Period 18 months +
DLP 60 months
Rate No. of man- Amount
months*
Professional Staff
Team Leader cum Senior Highway
1.
Engineer
2. Resident cum Highway Engineer
3. Bridge/Structural Engineer
4. Senior Pavement Specialist
5. Senior Quality cum Material Expert
6. Contract Specilist cum planning Engineer
7. Road Safety Expert
Sub – Total
Sub-professional
1. Survey Engineer
2. Highway Design Engineer
3. Assistant Highway Engineer
4. CAD Expert
5. Environmental Engineer
6. Bridge Design Engineer
7 Assistant Bridge Engineer
8. Assistant Quality cum Material Engineer
9. Electrical Engineer
10. HTMS/Toll Expert
11. Quantity Surveyor
12. Horticulture cum Landscaping Expert
13 Lab Technician
Sub Total
TotalFor Project with Construction Period of 24 months
No. Position Name Construction Period 24 months +
DLP 60 months
Rate No. of man- Amount
months*
Professional Staff
Team Leader cum Senior Highway
1.
Engineer
2. Resident cum Highway Engineer
3. Bridge/Structural Engineer
4. Senior Pavement Specialist
5. Senior Quality cum Material Expert
6. Contract specialist cum Planning Engineer
7. Road Safety Expert
Sub – Total
Sub-professional
1. Survey Engineer
2 Highway Design Engineer
3 Assistant Highway Engineer
4 CAD Expert
5 Environmental Engineer
6 Bridge Design Engineer
7 Assistant Bridge Engineer
8 Assistant Quality cum Material Engineer
9 Electrical Engineer
10 HTMS/Toll Expert
11 Quantity Surveyor
12. Horticulture cum Landscaping Expert
13 Lab Technician
Sub Total
Total
*The man-month against each key personnel/sub – professional shall be same
as specified in Enclosure A of TOR.For Standalone Bridge Project:
No. Position Name Construction Period 36 months +
DLP 60 months
Rate No. of man- Amount
months*
Professional Staff
Team Leader cum Senior Bridge
1.
Engineer
2. Resident cum Pavement Specialist
3. Bridge/Structural Engineer
4. Senior Contract Specialist
5. Senior Quality cum Material Expert
6. Contract Specilist cum Planning Engineer
7. Road Safety Expert
Sub – Total
Sub-professional
(To be decided by the Authority as per
requirement of the Project at the time of
preparation of RFP)
Sub Total
Total
For Standalone Tunnel Project:
No. Position Name Construction Period 60 months +
DLP 60 months
Rate No. of man- Amount
months*
Professional Staff
Team Leader cum Senior Tunnel
1.
Expert
2. Resident Engineer cum Excavation Specialist
3. Senior Geotechnical Expert
4. Tunnel Design Engineer
5. Tunnel Safety Expert
6. Senior Geologist
7. Contract Specialist cum planning Engineer
Sub – TotalNo. Position Name Construction Period 60 months +
DLP 60 months
Rate No. of man- Amount
months*
Sub-professional
(To be decided by the Authority as per
requirement of the Project at the time of
preparation of RFP)
Sub Total
Total
II. Support Staff
No. Position Name Staff Months Billing Amount( )
Rate(
)
1. Office Manager TBN
2. Accountant cum Cashier TBN
3. Steno cum Computer TBN
Operator
4. Office Boy ( 1 no) TBN
Total :
Note: Billing rates as indicated above shall be increased in accordance of clause
10.5.1 (10) of General Conditions of Contract for the personnel of all categories
namely (i) key Personnel; (ii) sub- Professional personnel and (iii) Support staff. The
increase as above shall be payable only on the remuneration part of Key Personnel,
Sub-Professional Personnel and support staff. However, for evaluation of Bid
proposals, the quoted initial rate shall be multiplied by the total time input for each
position on this contract, i.e. without considering the increase in the billing rates
III. Transportation (Fixed rate on rental basis)
The vehicles provided by the Consultants shall include the cost for rental, drivers,
operation, maintenance, repairs, insurance, etc. for all complete approx.
3000km/month run
Sr. No Description of Qty. Total Rate/ Amount
Vehicles (No. of vehicle- Vehicle
month)
-
During Construction During
Month
Period Development and
O&M Period
1 1 Innova or
equivalent
4000 km/
month2 2 Balero or
equivalent
4000
km/month
3. 1Pick up Van
4000
km/month
Total
Duty Travel to Site (Fixed Costs) (For all Lengths of projects) : Professional and Sub-
Professional Staff
Trips Number of Trips Rate* Amount
* Rate quoted includes Hotel charges, travel cost etc. complete.
IV. Office Rent (Fixed Costs)– Minimum 200 sqm area of office shall be
rented. The rent cost includes electricity and water charges, maintenance, Cleaning,
repairs, etc. complete.
Nos. of Months Rate/month Amount
48
The rent cost includes electricity and water charges, maintenance, cleaning, repairs,
etc. complete.
V. Office Supplies, Utilities and Communication (Fixed Costs)
No Ite Months Monthly Amount in
m Rate Rs.
1. Office Supplies
2. Drafting Supplies
3. Computer Running Costs
4. Domestic and International
Communication
VI. Office Furniture and Equipment (Rental)
The cost shall include rental charges towards all such furniture and equipment as
required for proper functioning of office. Office furniture shall include executive
tables, chairs, visitor chairs, steel almirahs, computer furniture, conference table etc.
Office equipment shall include as a minimum of telephone (2 external & 10 internal
lines), photocopier (15ppm, 12000 copies per month with A3 & A4 input) fax
machine, PCs(5 No., Intel Core 2 Duo E8300, 19’’ colour TFT, Cache-6MB, RAM-2GB, HDD-250 GB, DVD Writer, Key board, optical scroll mouse, MS- Windows Vista
Business, pre-loaded anti-virus etc.), laser printers (2 no., 14 ppm, 266 MHZ, 5000
pages per month, 600x600 dpi or better etc., Engineering Plan printer (1 no.),
binding machine (1 no.), plotter A0 size, overhead projector, AC (4 no., 1.5 Ton),
Water Coolers (as required)etc.
Nos. of Months Rate/month Amount
48
Reports and Document Printing
No. Description No. of No. of Total Rate per Amount
Report Copies per Nos. of Copy ( )
s Report copies
1 Monthly reports 84 3 252
(Design and Construction)
2 Half yearly Reports 8 3 24
3 Various others reports as provided in
the Concession Agreement such as
Completion Report
Total
VII. Road Survey Equipment
The cost shall include carrying out survey using equipment, manpower, software
and report processing.
Ite Kms Rate No of times Amount
m per km survey to be (INR)
(INR) conducted
Surface defects detection and roughness measurement 8
using Network Survey Vehicle
Pavement strength measurement using FWD 4
Bridge inspection using Mobile Bridge Inspection Unit 8
Road signs inspection using Retro Reflectometer 8
Total
VIII. Overhead
The consultant shall quote a fixed percentage of overhead, which may include overhead
charges over the salary of key personnel, sub professional staff, expenditure to carry out
the random test and establishment of a its own laboratory at site or to carry out test from
NABL accridated laboratory, cost of the coordinator/ other support staff and profits.APPENDIX C-2
Amount of performance Security Quoted by Bidder
(To be quoted by Bidder)
RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services Contract No
; Date
Consultant’s Name
Amount of Performance security to be Rs …………..
submitted by bidderAppendix D-1: Bank Guarantee Format for
Performance Security
(The Bank Guarantee shall be on a Stamp Paper of appropriate value in accordance
with Stamp Act and shall be purchased in the name of the guarantee issuing Bank or
the Party on whose behalf the BG is being issued.)
(Ref ITC-clause 13.1.2 and GCC-clause 5.8)
Ref Bank Guarantee No……………
Date……………………………...
To
The President of India, through
Head of Procurement
Procuring Organisation
[Complete address of the Procuring Entity]
Whereas M/s……………………………………………………with its Registered/ Head
Office at…………………………. (name and address of the Consultant, hereinafter
called “the Consultant”, which expression shall, unless repugnant to the context or
meaning thereof, include its successors, administrators, executors and assigns) has
undertaken, in pursuance of contract no ……….. date……………. to delivery
……………… (description of Services) (hereinafter called “the contract”).
And Whereas you (unless repugnant to the context or meaning thereof, including your
successors, administrators, executors and assigns) have stipulated in the said contract
that the Consultant shall furnish you with a bank guarantee by a Commercial bank for
the sum specified therein as security for compliance with its obligations as per the
contract;
And Whereas we …………………… with our Head Office at………………………….
(name and address of the Bank, hereinafter referred to as the ‘Bank’, which expression
shall, unless repugnant to the context or meaning thereof, include its successors,
administrators, executors and assigns) have agreed to give the Consultant such a bank
guarantee.
Now, Therefore, we hereby affirm that we are guarantors and responsible to you, on
behalf of the Consultant, up to a total of
…………………………………………………….(amount of the guarantee in words
and figures), and we undertake to pay you, upon your first written demand declaring
the Consultant to be in default under the contract and without cavil or argument, any
sum or sums within the limits of (amount of guarantee) as aforesaid, without your
needing to prove or to show grounds or reasons for your demand or the sum specified
therein, notwithstanding any difference between you and the Consultant or any dispute
pending before any Court, Tribunal, Arbitrator or any other authority.We hereby waive the necessity of your demanding the said debt from the Consultant
before presenting us with the demand.
The Bank undertakes not to revoke this guarantee during its currency without your
previous consent and further agrees that the guarantee herein contained shall continue
to be enforceable till you discharge this guarantee. This guarantee will not be discharged
due to a change in the constitution of the Bank or the Consultant’s.
We further agree that no change or addition to or other modification of the terms of the
contract to be performed thereunder or of any of the contract documents which may be
made between you and the Consultant shall in any way release us from any liability
under this guarantee, and we hereby waive notice of any such change, addition, or
modification.
This guarantee shall be valid until the ………….day of …….20……
Our………………………………….branch at………………*(Name & Address of
the
………….…………..*(branch) is liable to pay the guaranteed amount depending on the
filing of a claim and any part thereof under this Bank Guarantee only and only if you
serve upon us at our .................... * branch a written claim or demand and received by
us at our …………………..* branch on or before Dt… .......... otherwise, the bank shall
be discharged of all liabilities under this guarantee after that.
(Signature of the authorized officer of the Bank)
……………………………………
…….
……………………………………
…….
Name and designation of the officer
…………………………………………
Branch
Seal, name & address of the Bank and address of the
*Preferably at the authority's headquarters competent to sanction the expenditure for
procurement of goods/services or at the concerned district headquarters or the state
headquarters.Appendix D-2: Bank Guarantee Format for Advance Payment
(The Bank Guarantee shall be on a Stamp Paper of appropriate value in accordance
with Stamp Act and shall be purchased in the name of the guarantee issuing Bank or
the Party on whose behalf the BG is being issued.)
(Ref GCC-clause 10.5.2)
Ref Bank Guarantee No……………
Date……………………………...
To
The President of India, through
Head of Procurement
Procuring Organisation
[Complete address of the Procuring Entity]
Whereas M/s……………………………………………………with its Registered/ Head
Office at…………………………. (name and address of the Consultant, hereinafter
called “the Consultant”, which expression shall, unless repugnant to the context or
meaning thereof, include its successors, administrators, executors and assigns) has
undertaken, in pursuance of contract no ……….. date……………. to delivery
……………… (description of Services) (hereinafter called “the contract”).
And Whereas you (unless repugnant to the context or meaning thereof, including your
successors, administrators, executors, and assigns) have agreed in pursuance of the said
terms and conditions of the contract to make an advance payment of Rs.........................
(Rupees...............................................only) to the Contractor on the Contractor
furnishing a Bank Guarantee in the manner herein contained.;
And Whereas we …………………… with our Head Office at………………………….
(name and address of the Bank, hereinafter referred to as the ‘Bank’, which expression
shall, unless repugnant to the context or meaning thereof, include its successors,
administrators, executors and assigns) do hereby affirm that we are guarantors and
responsible to you, on behalf of the Consultant, up to a total of
…………………………………………………….(amount of the guarantee in words
and figures), and we undertake to pay you, upon your first written demand declaring
the Consultant to be in default under the contract and without cavil or argument, any
sum or sums within the limits of (amount of guarantee) as aforesaid, without your
needing to prove or to show grounds or reasons for your demand or the sum specified
therein, notwithstanding any difference between you and the Consultant or any dispute
pending before any Court, Tribunal, Arbitrator or any other authority.
We hereby waive the necessity of your demanding the said debt from the Consultant
before presenting us with the demand.The Bank undertakes not to revoke this guarantee during its currency without your
previous consent and further agrees that the guarantee herein contained shall continue
to be enforceable till you discharge this guarantee. This guarantee will not be discharged
due to a change in the constitution of the Bank or the Consultant’s.
We further agree that no change or addition to or other modification of the terms of the
contract to be performed thereunder or of any of the contract documents which may be
made between you and the Consultant shall in any way release us from any liability
under this guarantee, and we hereby waive notice of any such change, addition, or
modification.
This guarantee shall be valid until the ………….day of …….20……
Our………………………………….branch at………………*(Name & Address of
the
………….…………..*(branch) is liable to pay the guaranteed amount depending on the
filing of a claim and any part thereof under this Bank Guarantee only and only if you
serve upon us at our .................... * branch a written claim or demand and received by
us at our …………………..* branch on or before Dt… .......... otherwise, the bank shall
be discharged of all liabilities under this guarantee after that.
(Signature of the authorized officer of the Bank)
………………………………………….
………………………………………….
Name and designation of the officer
…………………………………………
Seal, name & address of the Bank and address of the
Branch
*Preferably at the authority's headquarters competent to sanction the expenditure for
procurement of goods/services or at the concerned district headquarters or the state
headquarters.Format 2: Authorization To attend Pre-Proposal
(Refer to ITC-clause 7)
(on Company Official Letter Head)
Consultant’s Name
[Address and Contact Details]
Consultant’s Reference No. Date……….
To
Head of Procurement
Procuring Organisation
[Complete address of the Procuring Entity]
Ref: RFP Document No. RFP No./ xxxx; Tender Title: Consultancy Services
Subject: Authorization to attend Pre-Proposal Conference on (date).
Following persons are hereby authorized to attend the Pre-Proposal Conference for the tender
mentioned above on behalf of (Consultant)
in the order of preference given below.
Sr. Name Government Photo ID Type/
Number
I.
II.
Alternate
Representative
Note:
1. Maximum of two representatives (carrying valid Government photo IDs) shall be permitted
to attend the Pre-Proposal opening. An alternate representative shall be permitted when
regular representatives cannot attend.
2. Permission to enter the hall where the pre-Proposal conference is conducted may be refused
if authorization as prescribed above is not submitted.
Signatures of Consultant
or
The officer authorized to sign the Proposal.
Documents on behalf of the Consultant
[name & address of Consultant and seal of company]
Format 3: Authorization to Attend Pre-Proposal Conference