See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF HEAVY INDUSTRIES
RAJYA SABHA
UNSTARRED QUESTION NO. 3281
ANSWERED ON 20.03.2026
FAME-II/EV SUBSIDIES UTILISATION AND IMPACT
3281. SHRI G.C. CHANDRASHEKHAR:
Will the Minister of Heavy Industries be pleased to state:
(a) subsidies disbursed under FAME-II, data for the last three years, year-wise, State-wise;
(b) electric vehicles supported, data for the last three years, category-wise, year-wise,
State-wise; and
(c) issues flagged regarding eligibility or misuse, data for the last three years, year-wise,
State-wise?
ANSWER
THE MINISTER OF STATE FOR HEAVY INDUSTRIES
(SHRI BHUPATHIRAJU SRINIVASA VARMA)
(a): The year-wise and category-wise details of the subsidy (demand incentive) provided
to buyers in form of an upfront reduction in purchase price of the electric vehicle, under
FAME-II scheme, is as under : -
Amount in Rs. Crore
EV category FY 2022-23 FY 2023-24 FY 2024-25 Category Total
e-2W 1,088.10 2,869.63 536.22 4,493.95
e-3W 128.37 567.21 264.25 959.83
e-4W 51.02 304.17 137.41 492.6
FY Total 1,267.49 3,741.01 937.88 5,946.38
No state-wise allocation has been done under the Scheme, as the demand
incentive/subsidy is provided to EV buyers, on pan-India basis.
(b): The year-wise and category-wise, Number of electric vehicles supported (demand
incentive provided) under FAME-II during the last three years is as under:-
No. of vehicles incentivised under FAME-II Scheme
EV Category
FY 2022-23 FY 2023-24 FY 2024-25 Total
e-2W 2,27,563 8,04,175 2,58,641 12,90,379
e-3W 22,169 76,183 34,436 1,32,788
e-4W 2,200 12,380 5,984 20,564
Total 2,51,932 8,92,738 2,99,061 14,43,731
No state-wise allocation has been done under the Scheme; therefore the data is not
centrally maintained.-2-
(c): The Ministry of Heavy Industries (MHI) had received complaints against 17 original
equipment manufacturers (OEMs) under FAME-II for non-compliance with Phased
Manufacturing Programme (PMP) guidelines.
After examination of reports submitted by testing agencies, six OEMs were found to
be in violation of PMP norms. Out of these six OEMs, entire demand incentive along with
interest was recovered from three OEMs, while the remaining three OEMs which refused to
refund the wrongfully availed incentive to the Government, have been deregistered from
FAME-II scheme in FY 2023-24.
Issues are examined OEM-wise. No state-wise data for the issues reported is
maintained under FAME-II. The FAME-II scheme has concluded on 31st March, 2024.
******