No.564 AMARAVATI, TUESDAY, MAY 23, 2023 G.222
NOTIFICATIONS BY GOVERNMENT
--x--GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
Energy Department - Proposal for setting up 2,2OO MW Fumped Hydro
Storage Power Projects, 3,500 MW Solar Power and 1,500 MW Wind Power
Projects by M/s. Indosol Solar Private Limited - Allotment of Captive Power
Plants of 2,2OO MW Pumped Hydro Storage Power Projects, 3,500 MW Solar
Power and 1,500 MW Wind Power Projects in Nandyal, Kurnool and YSR
Districts for energ, requirement to the proposed Integrated Solar
PV
Manulacturing Unit at Nellore District- Orders - Issued.
ENERGY (POWER.II) DEPARTMENT
G.O.Ms.No. 19 Dated:-L2.O9.2022
Read the following: -
1.G.O.Ms.No.1, Enerry (Power.ll) Dept, dt:3, l-2019.
2.G. O. Ms, No. 2, Energr(Power. II) Dept-, dated:3- 1 -20 1 9.
3.G. O.M s. No.3, Energr (Power.ll) Dept, dated:3 - 7 -2O 19.
4.G.O.Ms.No.35, Energr (Power.ll) Dept, dated: 18-1 1-2019 and
G.O.Ms.No. 1, dated: l -3-2021.
S.Proposals received on 23.08.2022 ol M/s Indosol Solar Private
Limited, Hyderabad.
6.Govt Letter No. ENEO 1 -APRE I I 3 I 2022, dated:23 -O8-2O22.
7.From the Vice Chairman & Managing Director, New and Renewable
Energr Development Corporation of Andhra Pradesh (NREDCAP),
letter No. NREDCAP/WE/PSP/lndosoll 2022 dated 25.08.2O22 and
29.08.2022.
8.From the Chairman & Managing Director, APIRANSCO, vide letter
No.CMD / CGM / Commercial & Legal / RAC / F -O5 I 2022,
dt:27.O8.2022.
9.From the Member-Convenor, APPCC, Vijayawada, letter No.CGM/
PP/ DGM / REP Projects/ D. No. I 22, dated:27 -O8-2O22.
ORDER:-
Government of Andhra Pradesh is giving prioriry for promotion of
Renewable Energr Power projects and has been rolling out multiple
initiatives, programs, policies and incentives to accelerate the development
of the renewable energr sector. The State is having good RE power potential
particularly in Rayalaseema rcgion huge extents of lands have been
',l,here
identified for promotion of RE power projects by inviting private investments.
2.
Further, the GoVernment of India has committed at the 26th session
of the Conference of the Parties (COP26) to the United Nations Framework
Convention on Climate Change (UNFCCC) held in Glasgow, United Kingdom
to reach 500 GW Non-fossil ener$T capacity by 2030 and achieve the target
of net zero emissions by 2O7O.
(P.r.o.)2
3. ln the G.O lst to 4th read above Government have issued orders
providing incentives for large scale promotion of Wind Power, Solar Power
and Wind-Solar hybrid Power Projects in the State of Andhra Pradesh.
4. In order to balance the variations in RE generation, reliable Energr
Storage solutions are required. Though various ener$/ storage technologies
are available, Pumped Hydro Storage Power Projects (PSP) offer highest
promise due to their flexible operation to balance the Variable Renewable
generation in short span of time. Andhra Pradesh is in forefront in the
country in identifying potential sites lor promotion of Pumped Storage Hydro
Power Projects. Techno-Commercial Feasibility Reports (TCFR) were
prepared with an aggregate potential of 33,240 MW. Detailed Project Reports
are under preparation lor most viable locations in phased manner.
Considering the huge capital investments required to establish PSP Projects,
the Government is intending to encourage private investments in already
identical PSP projects.
5. M/s. ISPL is setting up fully integrated Solar PV manufacturing
industry from Poly-silica to Ingot-wafer to Cell to Module which is being set
up in the State. M/ s ISPL won the Production Linked Incentive Scheme
announced by Govt. of India to promote domestic manufacturing and reduce
imports of Solar Panels which also aligns with the Aatma Nirbhar Bharat
Initiative of Govt. of India.
6. In the reference Sth read above, M/s Indosol Solar Pvt. Ltd. (ISPL),
Hyderabad, have submitted the proposal to the Government to allocate the
Captive Power Plants to meet their Power Requirements for the Green Field
Vertically Integrated Solar Photovoltaic Manufacturing Unit for allocation of
1.50 GW Wind Power, 3.5 GW Solar Power and 2.2 GW Pumped storage
power Projects:-
Captive Plants Capacity Location
Wind Plant 1.5 GW Dhone West, Gunduthanda
ebbatam
H
Solar Plant 3.5 GW Kolimigundla (V), Kurnool
District :1200 MW,
Urinchintala,
Ananthapur
District: 600 MW,
M. Kambaladinna (V): 600 MW,
Thondur (V) : 400 MW, Kadapa
District,Kambadur, Ananthapur
District: 700 MW
Pumped Storage 2CW Paidipalcm North & East
Plant
(Contd..P.3)::3::
7 . The estimated capitai expenditure for proposed solar PV module
manufacturing unit is indicated as Rs. 20,836 Crores in the 1st phase with
a potential to create employment for more than 5,000 people in AP State.
The project is expected to create huge employment opportunities to about
1 1 ,500 people directly and 10,000 - t I ,000 people indirectly in a phased
manner (3 phases) over a period of 5 years. The manufacturing facility being
set up by M/s. ISPL is highly energr intensive and requested the
Government for allocation ol PSP, Solar and Wind Power Projects to meet the
captive power requirements thereby reducing the cost of power for their
manufacturing facilify will bring down the cost of manufacturing of solar cell
and they can compete with International Market. In the case of Captive
Power Plants an amount of Rs.25,000 crores of revenue to the Government
and 1 1,000 persons will get direct and indirect employments u.ith the
proposed project.
8. The proposal of M/s. Indosol Solar Pvt. Ltd. has been placed before
State Investment Promotion Board (SIPB) meeting held on 05.O9.2022. The
SIPB has taken the following decisions:
i. Allotment of Pumped Storage Hydro Power (PSP) Projects and Solar
Power and Wind Power Projects as follows:
a. Paidipalem East Pumped Storage Power Project in YSR Dist.-
1200 MW
b.Paidipalem North Pumped Storage Power Project in YSR Dist.-
1000 Mw
c.Solar Power in Kolimigundla mandal, Kurnool District -
3500 MW
d.Wind Power in Dhone West and Hebattam of Holagunda
mandal, Kurnool District -1500 MW
ll Extend Mega Industrial Project Status to the project to facilitate
single windou, clearances. NREDCAP will be the Nodal Agency.
However, no incentives will be provided.
lll Allotment and alienation of revenue land available if any at the
PSP project locations on outright salc basis (.r_l Rs. 5.O0 lakhs per
acre or on lease basis with lease rentals of Rs.31,000/acre with
an annual escalation of 57o for every two years, based on the
option ol the Projcct developer at Simhadripuram Mandal, YSR
District.
IV. Allotment of project areas and allocation of revenue lands
available if any in the proposed project locations for Solar and
Wind power projects on lease basis with lease rentals of
Rs.31,000/acre with an escalation of 5% for every two years
without overlapping with the capacities of other developers as per
(P,T,O)1
the provisions of AP Solar Power Policy 2018 and AP Wind Power
Policy 20 18 read with AP RE Export policy 2020. The land
allocation shall not exceed 3 acres per MW in case of Solar power
projects and 2.50 acres power projects at Kolimigundla (Mandal)
Nandyal District / M. Kambaladinne (V) and Kadarabad of
Mandal, YSR District for Solar Projects and Dhone West, Dhone
(Mandal) for Wind Projects.
Allocation of 3.0 TMC of water on one-time non-consumptive
basis and O.45 TMC water towards annual evaporation losses
from the existing Paidipalem Reservoir as per the Industrial
Water Supply Policy / Guidelines and subject to guidelines
issued by the Water Resources Department.
vl. Green Energr Development Charge shall be levied for the
component of Pumped Storage Power Project @ - Rs 1 lakh/ MW
of installed capacity/year for first 25 years from the date of
commissioning of the project and of Rs 2 Lakhs/ MW instalied
@)
capacity/year thereafter.
v11. Govt. of Andhra Pradesh will support and facilitate the project for
availing grants of special category projects under central Govt.
schemes.
vlll Govt. of Andhra Pradesh will facilitate the project for availing
benefits provided as per National Energr Storage Policy without
any financial commitment from Govt. of Andhra Pradesh.
tx Payment of Rs. 50,0O0 per MW to rhe Nodal Agency (NREDCAP)
for
PSP capacities towards registration charges within two
months from the date ol allocation of the projects by the
Government.
x Payment of Statutory fee and charges to NREDCAp for Wind and
Solar Power capacities within two months from the date of
allocation of the projects by the Government.
xl Reimbursement of actual expenditure incurred by the NREDCAp
by the developer, towards preparation of Feasibility Reports,
Detailed Project Report, carrying out various field investigations
and expenditur e towards obtaining various clearances of the said
PSP projects as and when demand notice is raised by NREDCAP.
xll. The project completion timelines in case of pSp projects is 6
Years and in case of Wind and Solar Power project is 2 years from
the date of handing over of revenue lands available if any at the
proposed project locations.
(Contd.P.5)c
9.
Government after detailed examination of the proposal of M/s. Indosol
Solar Pvt. Ltd., in consultation with various stakeholders i.e, Revenue Dept.,
EFS&T Dept./ WRD Department. APIRANSCO in the light of the decisions
taken in the State Investment Promotion Board, havc decided to extend the
incentives as per the decisions of State Investment promotion Board as per
the incentives given to the Adani Green Energr Limited/Greenko Energies
Private Limited in the case of Pumped Storage projects and policies of Solar,
Wind and Hybrid Policies of 2018 issued by the Govt in the G.Os lst to 4th
read above.
10.
Accordingly, the Government here by issue the lollowing orders:-
l. 2200 MW of Pumped Storage Hydro Power (PSP) Projects, 3SO0 MW
of Solar Power and 1500 MW of Wind Power Projects are allotted to
M/s. Indosol Solar Pvt. Ltd. at the fotlowing locations:
Sl.No. Project Project Location Capacity
Com nent
1 Pumped Storagc Paidipalem East, 1200 MW
Hydro Project Simhadripuram
Mandal, YSR Dist.
2 Pumped Storage Paidipalem North, 1000 Mw
Hydro Project Simhadripuram
Mandal YSR Dist.
3 Solar Power Kolimigundla mandal, 3.500 MW
Kurnool Dist.,
M
Kambaladinne
&
Kaderabad villages of
Mylavaram
Mandal,
YSR Dist.
4 Wind Power Dhone West and 1500 MW
Hebattam, Holagunda
mandal,
Nandyal/
Kurnool Districts.
Total 7,2OO MW
II Mega Industrial Project Status has been accorded to the project to
facilitate single window clearances. NREDCAP will be the Nodal
Agency. However, no incentives will be provided.
ll1. Allotment on lease basis/ alienation of revenue land available if
any at the PSP project locations either on outright sale basis Rs.
@
5.O0 lakhs per acre or on lease basis with lease rentals of
Rs.31,OOO/acre with an escalation of 57o for every two years, based
on the option of the Project developer at Simhadripuram Mandal,
YSR District.
(P.r.o.)6
Allotment of project areas and allocation of revenue lands available
lV.
if any in the proposed project locations for Solar and Wind power
projects on lease basis with lease rentals of Rs.31,000/acre with an
es..lrtio., of 57o for every two years without overlapping with the
capacities of other developers as per the provisions of AP Solar
Power Policy 2018 and AP Wind Power Policy 2018 read with AP RE
Export Policy 2O20. The land allocation sha11 not exceed @ 3 acres
p.i Uw in case of Solar Power projects in Kolimingundla Mandal,
kurnool District and M.Kambaladinne and Kaderabad villages of
Mylavaram Mandal, YSR District for Solar Projects and @2.50 acres
per MW at Dhone West, Dhone Mandal and Hebbattam village,
Holagunda Mandal , Kurnool District in case ol Wind Projects.
Aliocation ol 3.0 TMC of water on one-time non-consumptive basis
and 0.45 TMC water towards annual evaporation losses from the
existing Paidipalem Reservoir as per the Industrial Water Supply
Policy / Guidelines and subject to guidelines issued by the Water
Resources Department.
vl. Green Energr Development Charge sha11 be levied for the
component of Pumped Storage Power Project only @ - Rs1 lakh/
MW of installed capacity/year for first 25 years from the date of
commissioning of the project and Rs 2 Laklns I MW installed
capacity/year thereafl er.
Govt. of Andhra Pradesh will support and facilitate the project for
v11
availing grants of special category projects under Central Govt'
schemes.
Govt. of Andhra Pradesh will facilitate the project for availing
v111.
benefits provided as per National Energ}r Storage Policy without
any financial commitment from Govt. of Andhra Pradesh.
Registration Charges of Rs. 50,0O0 per MW sha1l be paid to the
1X
NREDCAP for PSP capacities within two months from the date of
this order.
x. Statutory fee and charges to NREDCAP shall be paid for Wind and
Solar Power capacities within two months from the date of this
order.
Actual expenditure incurred by the NREDCAP towards preparation
x1
of Feasibility Reports, Detailed Project Report, carrying out various
field investigations and expenditure towards obtaining various
clearances of the said PSP projects shall be reimbursed / paid by
M/s. Indosol Solar Pvt. Ltd. as and when demand notice is raised
by NREDCAP.
(Contd..P.7)7
xll. The aliocated projects shall be executed and commissioned within
a period of 6 (Six) years from the date of handing over of revenue
Iands available if any at the proposed project locations, failing
which the entirc land shall be resumed back to the Government.
x l. The Porest Department shall extend necessary support and
facilitate to carry out surveys and investigations in forest areas and
diversion of forest lands.
1 1. The Revenue Department/ EFS & T/ Industries & Commerce/ Water
Resources Department/ AffRANSCO shall take necessary action
accordingly with respect to their issues mentioned at para 10 above.
12.
The Vice Chairman & Managing Director, New and Renewable Energr
Development Corporation of Andhra Pradesh Ltd.,, Tadepalli shall take
further necessary action accordingly.
(BY ORDBR AND IN THI1] NAME OF THE GOVERNOR OF ANDHRA
PRADESH)
K. VIJAYANAND
SPECIAL CHIEF SECRETARY TO GOVERNMENT
To
M/s Indosol Solar Pvt. Ltd., 6-3-879l8, 3rd Floor, G Pulla Reddy Sweets
Buildings, Begumpet, Hyderabad-SOO 0 16.
The Vice Chairman & Managing Director, NREDCAP, Tadepalli.
The Chairman & Managing Director, APIRANSCO, Vidyuth Soudha,
Vijayawada.
The Chiel Commissioner of Land Administration & Special Chief Secretary to
Government, APIIC Towers, Mangalagiri.
The Special Chief Secretary to Governmenr, Revcnuc Department.
The Special Chief Secretary to Government, Finance Department.
The Special Chief Secretary to Govt., Industries & Commerce Department.
The Special Chief Secretary to Government, EFS&T Department.
The Principal Secretary to Government, Water Resources Department.
The Principal Chief Conservator of Forests, GoAP, Guntur.
The Collector & District Magistrate, Kurnool District.
The Collector & District Magistrate, Nandyal District.
The Collector & District Magistrate, YSR District.
Copv to:
The Commissioner of Industries, Vijayawada.
The Managing Director, APGENCO, Vidyuth Soudha, Vijayawada.
The Chairman & Managing Director, APSPDCL, Tirupati.
The Chairman & Managing Director, APCPDCL, Vijaya'*'ada.
The Chairman & Managing Director, APEPDCL, Visakhapatnam.
(P.r.o.)B
The P.S to Special Chief Secretary to Chief Minister'
The P.S. to Secretary to Chief Ministcr.
The P.S. to Minister for Energr, FES & T and Mines & Geolory'
The P.S., to Special Chief Secretary to Government, Energr Dept
Sf/ Scs.
/ / FORWARDED: :BY ORDER/ /
K
tlo.,-.
SECTION OFFICER