**Executive Summary**
The document outlines guidelines for the appraisal and approval of Government schemes ending on March 31, 2026, for continuation into the XVIth Finance Commission cycle. Ministries and Departments must conduct outcome reviews and submit appraisal memos, adhering to specific financial thresholds and timelines. Key dates include the submission of Appraisal Memos by October 31, 2025, and appraisal/approval completion by March 31, 2026.
**Key Points / Main Content**
* **Scheme Appraisal and Approval:**
* Schemes ending on 31.03.2026, proposed for continuation, require appraisal and approval based on outcome review.
* Ministries/Departments must conduct Third Party Evaluations for Central Sector Schemes.
* Appraisal (EFC/SFC) Memos should be submitted to DoE ideally by 31.10.2025.
* Approval for continuation of schemes can be sought only if the evaluation report shows positive outcomes and assesses the need for continued operation.
* **Financial Guidelines:**
* Schemes with outlay up to Rs 500 Crore: Appraised and approved by the Administrative Ministry before 31.03.2026, giving consideration to third party evaluation reports.
* Schemes with outlay above Rs 500 Crore: Appraisal and approval through EFC.
* No CSS should have a financial outlay below Rs. 300 crore for five years.
* Financial outlay for Central Sector Schemes should not be less than Rs. 50 crore for five years.
* The total outlay of a continuing scheme should not exceed 5.5 times the average annual expenditure.
* Schemes operate as FUND LIMITED, meaning total sanctions must not exceed approved outlay.
* **Evaluation and Rationalization:**
* Evaluation of CSSs is conducted by DMEO, NITI Aayog.
* Ministries/Departments must respond to draft recommendations promptly to allow finalization of the Evaluation Report.
* Schemes should be rationalized through merger, closure, or restructuring where necessary.
* **Timelines and Procedures:**
* Ministries/Departments should circulate Appraisal (EFC/SFC) Memos to stakeholders.
* Adhere to Cabinet Secretariat timelines for finalising Cabinet/Cabinet Committee notes.
* Approval Memos must be submitted with evaluation reports ideally by October 31, 2025, to DoE.
* **Scheme Structure and Design:**
* Schemes should be formulated with consistency across components.
* Follow common norms such as Skilling and UGC norms for costing.
* Implement necessary modifications for Aadhaar seeding and direct benefit transfer through Aadhaar authentication.
* Incorporate cashless and electronic transactions.
* **Additional Guidelines for Cabinet Notes (from Cabinet Secretariat OM dated May 14, 2025):**
* Revised Timelines for finalization of Cabinet/ Cabinet Committee notes.
* Indicate financial implications in policy proposals and clarify which ministries should receive Appraisal Memo/Draft Note.
* Encourages physical meetings/VCs to speed up finalization of notes.
* Monitor delays/pendency using e-Samiksha Portal.
* **Scientific Ministries/Departments (From Cabinet Secretariat OM dated May 28, 2025):**
* For scientific ministries/departments requiring Cabinet approval, the Expenditure Finance Committee/Public Investment Board will be chaired by the Secretary (Expenditure) for:
* Continuation of ongoing schemes at the end of a Finance Commission cycle.
* New schemes and projects involving subsidies/grants/equity/incentives payable to the private sector, as well as Revised Cost Estimates of projects of such nature.
**Impact Analysis**
**Ministries/Departments**
* **Impact:** Responsible for conducting outcome reviews, Third Party Evaluations, preparing appraisal memos, adhering to financial guidelines, and rationalizing existing schemes.
* **Action Required:** Conduct outcome reviews, submit appraisal memos by the specified deadlines, and ensure compliance with the outlined financial and operational guidelines.
**NITI Aayog (DMEO)**
* **Impact:** Conducting evaluations of CSSs and providing recommendations.
* **Action Required:** Finalize and submit evaluation reports to Ministries/Departments.
**Department of Expenditure (DoE)**
* **Impact:** Receives and appraises the schemes proposed for continuation, issues guidelines.
* **Action Required:** Review appraisal memos submitted by Ministries/Departments.
**States**
* **Impact:** States need to be engaged by Ministries/Departments to ensure National goals are given due priority in their schemes and overall synergy in expenditure of Centre and States.
* **Action Required:** States need to coordinate and engage with the Ministries/Departments to ensure National goals are given due priority in their schemes.
Key Entities Referenced
XVIth Finance Commission Cycle: Period for which the guidelines for appraisal and approval of schemes are relevant.
Centrally Sponsored Schemes: Schemes co-financed by the central and state governments. The circular provides guidelines for the evaluation and appraisal of these schemes.
NITI Aayog: A think tank of the Government of India, involved in evaluation and funding patterns of schemes.
Department of Expenditure (DoE): The department under the Ministry of Finance responsible for the appraisal and approval of schemes.
Cabinet Secretariat: Government body responsible for facilitating decision making in government through streamlining inter-ministerial consultations.
No. 01(01)/PFC-II/2025
Government of India
Ministry of Finance
Department of Expenditure
[PFC-II Division]
North Block, New Delhi
Dated: 06 June, 2025
OFFICE MEMORANDUM
Subject: Guidelines for Appraisal and Approval of Schemes ending on
31st March 2026 and to be continued during the XVIth Finance
Commission Cycle - reg.
Reference is invited to Department of Expenditure’s OM No. 24(35)/PF-
11/2012 dated O5t August, 2016 vide which Ministries and Departments
were informed that in order to improve the quality of Government
expenditure, every scheme should have a sun-set date and continuation of a
scheme shall be based on an outcome review. Further, for aligning the
schemes with the financial resources cycle of Central and State governments,
these were made co-terminous with the Finance Commission cycles (FC).
2. The XVth FC cycle will end on 31-03-2026. Therefore, schemes ending
on 31.03.2026 and which are proposed for continuation over the next FC
cycle are to be subjected to an appraisal and approval process based on an
‘outcome review’. Development Monitoring and Evaluation Office (DMEO),
NITI Aayog is conducting an evaluation exercise covering the Centrally
Sponsored Schemes. For Central Sector Schemes, the Ministries/
Departments concerned have to carry out Third Party Evaluation for which
this Department has already issued an OM No. 66(59)/PFC-II/2018 dated
05.05.2025 containing Terms of Reference (ToRs) for conducting Third Party
Evaluation. After getting the schemes evaluated, Appraisal (EFC/SFC) Memos
must be submitted for appraisal/comments by DoE, by the Ministries/
Departments concerned ideally by 31.10.2025.
3. The following paragraphs provide the general guidelines for preparing
and forwarding proposals for appraisal and approval of schemes proposed for
continuation beyond 31-03-2026 including schemes. of _ scientific
Ministries /Departments (Ref: Cabinet Secretariat OM No. 1/50/1/2025-Cab.
dated 28 May, 2025(Copy enclosed)). These guidelines are equally applicable
to both CSSs and CSs.
°FINANCIAL
(i) Schemes with estimated outlay upto Rs 500 Crore for the period from
2026-27 to 2030-31 may be appraised and approved by the
Administrative Ministry as provided in the DoE’s OM No. 24(35)/PF-
11/2012 dated 05.08.2016. -It may be ensured that such
appraisal/approval is completed before 31.03.2026 giving requisite
cognizance to third party evaluation report on the Schemes
appraised /approved. A list of all such Schemes (both CSS and CS) shall
be provided to DoE in the prescribed format (Annexure I).
(ii) As regards Schemes with estimated outlay above Rs 500 Crore, for the
period from 2026-27 to 2030-31, the appraisal and approval will be done
through EFC as per this DoE’s OM No. 24(35)/PF-II/2012 dated
05.08.2016.
(iii) Keeping in view the minimum critical mass required for a central
government scheme to have meaningful impact across States/UTs, it
must be ensured that no CSS should have financial outlay below Rs. 300
crore for five years.
(iv) With regard to CSs, it may be ensured that the financial outlay should
not be less than Rs. 50 crore for five years.
(v) Normally, a Central Sector Scheme with an outlay of less than Rs 100
Crore should have achieved its purpose during a given FC cycle.
However, in exceptional cases, if such a scheme is to be continued in the
next FC cycle, based on an evaluation report which justifies continuation
of the said scheme, the scheme shall be subjected to appraisal/approval
process as provided in Para 8 of DoE’s OM No.24(35)/PF-II/2012 dated
05.08.2016.
(vi) The total projected outlay of a continuing scheme of a
Ministry/Department for five years over the XVItt FC cycle should not
ordinarily be more than 5.5 times of average of the annual expenditure
under the scheme for FYs 2021-22 to FY 2023-24 (AE) and FY 2024-25
(RE).
(vii) Ministry/Department will have the flexibility to seek more funds for a
scheme with commensurate reduction in another scheme based on
specific justification.
(vii) All schemes will operate as FUND LIMITED schemes, which means that
the total sanctions over the FC cycle must not exceed the approved
outlay.
(ix) For schemes which contemplate saturation and demand driven
approach,(eg. Scholarships/ PMAY etc), the outlay shall be determined
based on the approximate number of beneficiaries to be covered in a FC
2cycle and sanctions shall be restricted to the approved outlay with a
flexibility to carry forward any committed expenditure within the
approved outlay to the next FC cycle. The details of such spill over
expenditure should be part of the EFC Memo. However, if there is a
need for upward revision of the outlay during the approved duration of
the Scheme, due to increase in the number of beneficiaries beyond the
projected figure (as the scheme aims for saturation), the Administrative
Ministry/Department should seek specific approval for the increased
outlay from the competent authority with due concurrence from
Department of Expenditure.
(x) Funding pattern proposed in a Centrally Sponsored Scheme
should be as per NITI Aayog’s OM No.O-11013/02/2015-CSS&CMC
dated 17.08.2016 and 26.10.2019.
EVALUATION
(xi) Evaluation of CSSs is being done by DMEO, NITI Aayog. On receipt of
the draft Evaluation Report from NITI Aayog, Ministries and
Departments are requested to respond to the draft recommendations
quickly allowing NITI Aayog to finalise the final Evaluation Report and its
submission. Ministries and Departments are requested to formulate the
scheme taking into consideration the recommendations of the Report
and submit the Appraisal Memo to DoE.
(xii) The approval for continuation of the schemes may be sought only if the
evaluation report for the scheme shows positive outcomes and brings out
an assessment to the effect that though the scheme has been effective in
achieving its previously laid down objectives /targets, there still is a
need to continue the scheme in view of its mandate, performance and/or
scaling up of targets.
(xiii) Depending upon the findings and recommendations of the evaluation
process and its recommendations, a scheme may be continued in its
present form or with necessary modifications.
(xiv) Recommendations of XVI‘ FC, wherever relevant, will also be considered
while appraising a scheme for continuation including its financial outlay.
(xv) For continuing schemes, especially CSSs, Ministries and Departments
are advised to engage with States to ensure that National goals are given
due priority in their schemes and ensuring overall synergy in
expenditure of Centre and States.
wes
WorkTIMELINES
(xvi) Ministries/Departments should circulate the Appraisal (EFC/SFC)
Memos to all the stakeholders including Ministries/Departments/NITI
Aayog and incorporate their comments in the final Appraisal Memo for
appraisal.
(xvii)Cabinet Secretariat vide its OM no. F. No. 1/50/2/2024- Cab.
Dated14.05.2025 (copy enclosed) has mandated timelines for finalising
Cabinet/Cabinet Committee notes. Timelines mentioned in the Annex
thereto must be followed for the appraisal process as well.
(xviii) Ministries/ Departments should ensure submission of Appraisal Memo
along with evaluation reports at the earliest and ideally by 31st October,
2025 to DoE (see para 2 above).
(xix) Based on the data available with DoE it is noted that several schemes of
a Ministry/Department may require fresh appraisal and approval for
continuation beyond 31.03.2026. Therefore, composite appraisal of all
the schemes of a particular Ministry/Department, as far as possible,
shall be carried out as per the schedule to be circulated in due course of
time / intimated separately.
SCHEME STRUCTURE/ DESIGN
(xx) Schemes may be formulated with consistency across components. For
example, if a scheme is a Central Sector Scheme, then all the
components must be funded in the same pattern (unless justification for
otherwise is provided). Specific recommendation in this regard may be
obtained from the EFC/SFC after consulting DoE.
(xxi) The Ministries/Departments should follow common norms such as
Skilling norms, UGC norms etc for costing purposes.
(xxii) For continued improvement in public services delivery, the
Government is placing great emphasis on Aadhaar seeding and transfer
of direct benefit through Aadhaar authentication. The proposals for
continuation of schemes should effect necessary modification in the
implementation mechanism accordingly. Disbursement of the funds
should be done through Aadhaar Enabled Payment System (AEPS) to
ensure Aadhaar authentication, and not merely Aadhaar seeding in
such cases.
(xxiii) Similarly, cashless and electronic transactions of financial resources
should be incorporated suitably in the scheme design to promote the
objective of digital and less-cash economy.
LE
S(xxiv) Schemes may be designed in a manner which allows for inter-
component flexibility for transfer of resources across components for
better targeting and effectiveness. While inter-component flexibility is
encouraged, Ministries and Departments must have a ceiling beyond
which this must not be allowed lest more than required resources are
spent on easy to implement components. Specific approval in this
regard must be detailed in the Appraisal Memo with appropriate
justification.
Ministries and Departments are requested to use the 25% flexi-fund
allowance as stated in para 6.2 of NITI Aayog’s OM no. O-
11013/02/2015/-CSS & CMC dated 17 August 2016 for CSSs.
RATIONALISATION
(xxvi) Schemes denote public funded programmes which may or may not
have components/sub-components. Based on the recommendations of
the third-party evaluation, experience gained in implementing the
scheme/component etc, following may be attempted:
a. recalibrating the design, the architecture of the scheme going
forward.
b. restructuring of the scheme whereby redundancies, ineffective
and sub optimal interventions are removed.
c. closure of schemes which have either outlived their utility or
have fulfilled their objectives.
(xxvii) To eliminate overlap of activities /objectives for the same target
beneficiaries, the proposal should reflect clear convergence architecture
with other similar or related schemes of Central Government. This is
desirable for optimum deployment of resources.
(xxviii) Ministries/ Departments should examine various ongoing schemes
being administered by them / other Ministries to explore the
possibilities of merger / dropping of schemes with overlapping
objectives.
(xxix) It has been a constant endeavour of the Government to rationalize
schemes through merger, closure, restructuring which have become
redundant or ineffective with passage of time. Before formulating
proposal for continuation of schemes, necessary rationalization of
existing schemes should be ensured by Ministries/ Departments.
L wi we :
4
WW
owPMU AND ADMINISTRATIVE EXPENSES
(xxx) Unnecessary creation of Establishment, Administrative Expenses and
thin spread of resources on these should be avoided. As far as possible,
a single monitoring body such as a PMU should be established at the
Central Ministerial level/state level.
POST CREATION
(xxxi) Implementation of CSSs should not result in creation of permanent
posts. Similarly, CSs should also not ordinarily result in creation of permanent
posts.
4. The appraisal of the schemes of various Ministries/Departments shall be
carried out as per the schedule which will be informed separately.
Expenditures under any scheme for which the approval date ends on
31.03.2026 will not be allowed unless the appraisal and approval processes
are completed by 31.03.2026.
5. This issues with the approval of Secretary (Expenditure).
Encl: As above ‘ we oo
WA
(Hema Jaiswal)
Dy. Director General (PFC-II)
To,
All the Secretaries to the Government of India
All the Financial Advisers to the Government of Indi
Copy to:
Be Prime Minister’s Office
Cabinet Secretariat
Internal Circulation
Website of DoE
eSAnnexure-I
List of CSS/CS Schemes with an outlay upto Rs 500 Crore which have
been appraised/approved by the Administrative Ministry /Department
Name of the Ministry/Department:
S.No. Name of Nature Period | Financial | Date of | Date of
the Scheme | (CS/CSS) Outlay | Appraisal | Approval
(Rs. in Cr)
: we eo
x
WAN
°F. No. 1/50/2/2024 - Cab.
Cabinet Secretariat
Rashtrapati Bhawan
ek
New Delhi, the 14° May, 2025
OFFICE MEMORANDUM
Subject: Timelines for finalizing Cabinet / Cabinet Committee notes and measures
for expediting finalization of notes.
The undersigned is directed to say that an analysis of time-cycle of notes at various
stages was undertaken by this Secretariat which revealed delays at every stage of
preparation/ finalization of notes. A Committee of Secretaries (CoS) deliberated upon this
issue in its meetings held on 16.11.2024 and 06.05.2025. Based on its recommendations,
and to expedite finalization of Cabinet/ Cabinet Committee notes resulting in faster
decision-making of important policies, programmes and schemes of the Government,
timelines for various stages in finalization of notes have been reviewed and reassessed.
Remedial actions for checking delays have also been considered.
2: Accordingly, in supersession of extant instructions on the subject, relevant
guidelines contained in the Handbook on writing Cabinet Notes and the Time Frame for
Appraisal and Approval of Schemes and Projects contained in Department of Expenditure
O.M. No. 24(35)/PF-II/2012 dated 05.08.2016 relating to timelines for various stages of
appraisal and approval processes, the revised timelines contained in the Annex to this
Memo., are for information and compliance of Ministries (which term also includes
Departments for the purpose of this Memo).
S. Ministries are also requested to take note of the following for facilitating timely
finalization of notes:
(i) Sponsoring Ministry shall refer the Appraisal Memo/ Draft Note to only those
Ministries whose business is impacted as stipulated under Rule 4 of the Government of
India (Transaction of Business) Rules, 1961. Careful scrutiny and judicious selection of
Ministries for consultations will help in reducing unnecessary delays.
(ii) The mode of transmission of Cabinet/ CCEA note by the sponsoring Ministry will be
through dispatch of hard copy of the note to stakeholder Ministries. The sponsoring
Ministry will ensure that the hard copy of the note is delivered on the same day as the
date mentioned in its forwarding memo.*
(iii) | While circulating the Appraisal Memo/ Draft Note, the sponsoring Ministry shall also .
flag to each Ministry the Specific points or paragraphs or issues on which comments are
solicited. It is also advisable that these are, as far as possible, clearly delineated and
mentioned in the forwarding memo by the sponsoring Ministry. This will give clarity to
consulted Ministries as to what is expected of them, and will enable them to expedite their
comments.
(iv) Financial implicatibns in policy proposals shall be (at least roughly) indicated/
flagged by the sponsorihg Ministry to enable D/o Expenditure to give its comments
expeditiously on the Draft Note.
(v) In case the proposal is complex, it is advisable that a preliminary inter-ministerial
meeting through physical mode/ VC may be convened by the sponsoring Ministry
immediately after circulation of draft note, to familiarize the consulted Ministries with the
proposal(s) contained thdrein and to give clarity.
(vi). Intra-ministerial meetings/ VCs may also be convened by consulted Ministries,
where necessary, with Attached/ Subordinate offices/ IFD/ Wings, etc. for expediting
comments.
(vil) The Sponsoring Ministry is expected to pursue vigorously with consulted Ministries
whose comments are cdnsidered critical for an informed decision making in respect of
that proposal.
(viii) Regular review and monitoring of pendency should be undertaken in Senior
Officers’ Meetings in respect of Cabinet/ Cabinet Committee Notes being piloted by the
Ministry as well as those pending with it. The Secretary of sponsoring Ministry may
consider reminding Setretaries of consulted Ministries in case comments are not
forthcoming. If required, eetings may also be convened through physical mode/ vc.
4, A new module, namely, ‘Inter-Ministerial Consultations’ is now available on e-
Samiksha portal which will enable Ministries concerned, and the Cabinet Secretariat, to
monitor and review delays/ pendency occurring at various stages of finalization of
Cabinet!) CCEA notes. Generation of various reports and other features/ functionalities
based on the suggestions/ recommendations made in the aforementioned CoS meetings
have been incorporated in the module. Ministries concerned are required to upload baredetails of Cabinet/ CCEA notes on the portal. It is clarified that the content of the proposal
is not required to be uploaded on the portal. In cases where the subject of Cabinet/ CCEA
itself is sensitive, the same may be suitably modified or redacted by sponsoring Ministry
while uploading relevant information on the portal.
oy Finalization of Cabinet/ CCEA notes is a collaborative exercise. It is, therefore,
imperative that efforts are made by both the sponsoring as well as consulted Ministries to
ensure that the revised timelines for finalization of notes are strictly adhered to.
6. These instructions may be disseminated to all concerned for strict compliance.
en
(Satendra Singh)
Additional Secretary
Tele: 2301 2697
All Secretaries to the Government of IndiaAnnex to Cabinet Secretariat O.M. No. 4/50/2/2024-Cab. dated 14.05.2025
Revised timelines for finalization of Cabinet! Cabinet Committee notes
@
Revised
| SI. Activity
Timeline
No. rame in cases where proposals involve Appraisal of Schemes & Projects
Time f Consulted Ministries to furnish comments on Detailed Paper/ 21 days
he Detailed Project Report and draft EFC/PIB memo. circulated by
sponsoring Ministty
Preparation of final EFC/ PIB memo. by sponsoring Ministry 14 days
based on comments received, and circulating the same for
Appraisal and Approval
Fixing the date of EFC/ PIB meeting by Department of 7 days
3.
Expenditure after receiving the final EFC/ PIB memo.
Issue of minutes of EFC/ PIB after the appraisal meeting has 7 days
4.
been done if
Time frame for finalization of Notes
(i) Consolidation of draft Cabinet/ Cabinet Committee note
5. (DCN) and its circulation by sponsoring Ministry to D/o 7 days
Expenditure for dbtaining approval (in cases of agreement with
recommendations of Appraisal Body)
(ii) D/o Expenditure to communicate its comments to sponsoring 7 days
Ministry
Consulted Ministties to furnish comments on DCN circulated by
sponsoring Department on:
(i)
Legislative and policy proposals 21 days
Propogals (Projects/ Schemes) which have been
(ii)
appraised (in cases of disagreement with the 7 days
recommendations of Appraisal Body)
(iii) __ Proposals other than those listed at 6 (i) & 6 (ii) above 14 days
Sponsoring Ministry to finalize single note for Cabinet/ Cabinet Immediately after
Committee and circulate 06 copies of note to Cabinet completion of
Secretariat and 01 copy to Prime Minister's Office inter-ministerial
consultation
Furnishing of ¢omments, if any, by Cabinet Secretariat to 7 days
sponsoring Minigtry
Revision of note based on comments of Cabinet Secretariat and 10 days from the
forwarding requisite number of copies to Cabinet Secretariat receipt of
comments
In so fa ir n a ss tr uc co tn is ou nl st a cti oo nn t iw ni ut eh t toh e bE em p ino w fe orr ce ed aT ne dc h tn ho el ro e gy is G nr oo u cp h ( aE nT gG e) ii ns c to hn ec e pr rn ee sd cr, i bth ee d
e tix mt ea ln it ne. Accordingly, proposals in the prescribed proforma i.e. ‘Self-Appraisal Form for
S Seu cb rm ei ts as rii ao tn Oo .f M .N o Nt o.e s 1/t 5o 0 /E 2m /p 20o 2w 2e -r Cae bd . dT ae tc eh dn o 0l 2o .g 0y 5 .2G 0r 2o 3u ,p ’ w oa us l dp r be es c cr li eb ae rd e dv bi yde E TCa Gb i in ne at
time bound manner not later than within a month of receipt. Such proposals as are within
the mandate of ETG will be placed before the ETG prior to their submission to the EFC/
Cabinet/ Cabinet Committee. Further, draft Cabinet/ Cabinet Committee notes, along with
inter-ministerial comments, shall also be shared with the ETG.
RRRREEsai F. No. 1/50/1/2025 — Cab.
GOVERNMENT OF INDIA (s1R@ ater)
CABINET SECRETARIAT (sifftise aftr)
RASHTRAPATI BHAWAN (areata wa)
New Delhi, the 28 May, 2025
OFFICE MEMORANDUM
Subject: EFC / PIB appraisal of schemes/ projects needing cabinet approval —
reg.
The Department of Expenditure has prescribed procedures for appraisal of
schemes and projects through the mechanism of the Standing Finance Committee/
Expenditure Finance Committee/ Department Investment Board/ Public Investment
Board. The procedure for appraisal of schemes and projects in scientific Ministries /
Departments has been re-examined in accordance with recent Cabinet decisions and
evolving circumstances.
2. It has been decided that, notwithstanding anything contained in the instructions
of the Department of Expenditure, for Schemes and Projects requiring Cabinet
approval, the Expenditure Finance Committee/Public Investment Board shall be
chaired by the Secretary (Expenditure) in the following types of cases: -
(i) Continuation of ongoing Schemes of scientific Ministries/Departments at the
end of a Finance Commission cycle.
(ii) New schemes and projects of scientific Ministries/Departments involving
subsidies/grants/equity/incentives payable to the private sector, as well as
Revised Cost Estimates of projects of such nature.
3. The procedure in paragraph 2 shall also apply to all schemes/projects cleared
by the Digital Communications Commission which require Cabinet approval (whether
or not they fall under sub-paras (i) and (ii) of paragraph 2 above).
4. This instruction does not apply to the Department of Space and the Department
of Atomic Energy which have special appraisal/approval procedures.
5. For the purpose of this instruction, ‘Cabinet approval’ includes approval of
Committees of the Cabinet, when the context so requires.
(Satendra Singh)
Additional Secretary
Tele: 2301 2697
To
\Sécretary, M/o Electronics and Information Technology
Secretary, Dio Telecommunications
c\ Secretary, M/o Environment, Forest and Climate Change
a4”
? Page 1of2.
Secretary, D/o Agricultural Research and Education
Secretary, Dio Bio-Technology
Secretary, M/o Earth Stiences
Secretary, Dio Science and Technology
Secretary, D/o Scientiflc and Industrial Research
Secretary, D/o Health Research
oa
Copy to:
Secretary, D/o Expendlture
(Satendra Singh)
Additional Secretary
Copy also to:
Principal Secretary to the Prime Minister
(Satendra Singh)
Additional Secretary
Page 2 of 2