Official TranscriptSubject: Record of Discussion of the 150th meeting of the PPPAC for considering the following three road project proposals: I. Construction of 4/6-Lane Greenfield Ludhiana–Rupnagar National Highway (NH205K), Package-2, including the Ludhiana Bypass, in the State of Punjab under Hybrid Annuity Mode (HAM). II. Construction of Six-Lane Access Controlled Amaravati Outer Ring Road, including the...
Subject: Record of Discussion of the 150th meeting of the PPPAC for considering the
following three road project proposals:
I. Construction of 4/6-Lane Greenfield Ludhiana–Rupnagar National Highway
(NH205K), Package-2, including the Ludhiana Bypass, in the State of Punjab under Hybrid Annuity Mode (HAM).
II. Construction of Six-Lane Access Controlled Amaravati Outer Ring Road, including the Chinakakani–Tenali Spur and Guntur–Narakodur Spur, in the State of Andhra Pradesh under Hybrid Annuity Mode (HAM).
III. Six-Laning of the Hyderabad–Vijayawada–Machilipatnam Section of NH-65 in the States of Telangana and Andhra Pradesh.
1. The 150th meeting of the PPPAC was held on 08.08.2026 at 12.00 hrs to consider the above- mentioned project proposals. List of attendees is placed in Annexure-I.
2. With the permission of Secretary (EA) Joint Secretary (IFS) welcomed all the attendees to the meeting. NHAI officials made detailed presentations on the projects at S. No. I, II and III.
Project 1: Construction of 4/6-Lane Greenfield Ludhiana–Rupnagar National Highway
(NH205K), Package-2, including the Ludhiana Bypass, in the State of Punjab under Hybrid Annuity Mode (HAM).
1. The details of the proposal are as given below:
SN Item Description
1. Name of the Project Construction of 4/6-Lane Greenfield Ludhiana–Rupnagar National Highway (NH205K), Package-2, including the Ludhiana Bypass, in the State of Punjab under Hybrid Annuity Mode (HAM).
2. Type of PPP (BOT, Hybrid Annuity Mode (HAM) BOOT, BOLT, OMT etc)
3. Location (State/ State: Punjab District/ Town) District: Ludhiana
4. Administrative Ministry of Road, Transport and Highways, Government of Ministry/ Department India
5. Name of Sponsoring Ministry of Road, Transport and Highways, Government of Authority India
6. Name of the National Highways Authority of India Implementing Agency
7. Details of Structure The Ludhiana - Rupnagar corridor was identified as Feeder Route under Bharatmala Pariyojana along with Ludhiana Bypass for decongestion of North-South corridor. The Ludhiana-Rupnagar corridor has been notified as NH-205K vide Gazette Notification S.O. 4363(E) dated 03.12.2020. Its primary objective is to strengthen connectivity from the inner 2regions of Punjab and Himachal Pradesh to the Delhi-Katra Expressway, thereby improving the efficiency of long-distance traffic movement and freight logistics across northern India.
The total length of the Corridor is 128.20 Km & being developed in 3 packages, as under:
Package Length Status
(Km) Package-1 (From 37.70 Work has been restarted by Km. 0.00 to Km. existing contractor M/s GR
37.70) Infra Project Pvt. Ltd. And current progress is around 20% Package-2 (From 47.24 Concession Agreement Km. 37.70 to Km. terminated in March, 2024
66.44 & Ludhiana due to non-handing over of Bypass for 18.50 land by the State Govt. Now Km) to be re-awarded after obtaining fresh sanction from Competent Authority. (Instant Case) Package-3 (From 43.26 Under implementation (78% Km.66.44 to Km. progress); Likely completion
90.20 incl. Kharar by 31.08.2026 spur 19.50 Km) The instant proposal pertains to Package-2 (47.24 km), The subject project (Package-2) was earlier approved under Bharatmala Pariyojana and awarded to M/s Ceigall India Limited on 31.12.2021 and Concession Agreement was signed with M/s Ceigall Ludhiana Rupnagar Greenfield Highways Pvt.
Ltd. on 08.07.2022. However, the Concession Agreement was terminated in March'2024 under Cl. 4.5 of the Concession Agreement as the Authority could not fulfil the Conditions Precedent relating to handing over of land even after 1.5 years from the date of signing of Concession Agreement leading to ‘Deemed Termination upon delay’.
The proposed project along with Delhi-Katra Expressway & preceding Ludhiana-Rupnagar Package-1 and succeeding Southern Ludhiana Bypass will complete the ring road around Ludhiana.
To ensure completion of the overall corridor, the instant package is now proposed to be taken up under NH(O). Salient
features of the project are detailed below:
S. Project Km. 37.700 to Bypass No. Features Km.66.440 Km0.000 to Km.18.500) 1 Length (km) 28.74 Km 18.5 Km 2 Pavement Flexible Flexible Type 3 Major Bridge 0 0 3(No.) 4 Minor 1/5 Nos 0/1 Nos Bridge/Minor Bridge/cum Underpass (No.) 5 Interchanges 2 No. Flyover with at- 3 Nos.
(No.) grade Rotary at Km Single 54+512, 62+622 Trumpet at Elevated with service Km 0+455, road Double Trumpet at Km 11+183, Double Dumbbell at Km 17+342 6 ROB (No.) 0 2 Nos.
7 VUP/LVUP 1/6 0/7 8 SVUP/Mini 8 Nos / 20 Nos 06 Nos. 12 Underpass Nos 9 Box Culvert 111 Nos. 77 Nos. (No.) 10 Service/Slip 1.672 Km. 0 Km.
Road 11 Connecting 2.836 Km. 5.203 Km.
Road (3.5 m) 12 Elevated 1 Location 55+600 1 location Viaduct LHS-1x35+1x50+ from 12+302 1x30+11x25+1x30 to 13+344- RHS-1x35+1x50 17x30 and +1x25+ 1x33.65 15x30 13 Flyovers 1 No.s (1x30x5.5) at Km 8+740 14 Structure 1 No. 0 Gas Pipeline (1x45+1x21.5+1x45) 15 Wayside 2 Nos. of 2 Ha. Each amenities at Km. 47+810 (RHS & LHS) (Approach Road, Levelling & Boundary wall in scope)
8. Estimated Capital As per MoRTH circular dated 13.03.2026 Costs with breakup under major heads of S.N. Item Amount expenditure. Also (Rs. in Cr.) indicate the basis of A1 Estimated civil construction cost (excl. 1,241.93 cost estimation GST) A2 Cost of overhead utility shifting (tentative) 49.04 4A Civil cost incl. utility shifting (A1 + A2) 1,290.97 GST @18% on civil construction cost 223.55 B IC & pre-operative cost 12.91 C Financing cost 4.86 D Interest during construction 47.40 E Estimated Project Cost as on bid due 1,356.14 date (excl. GST) E1 Estimated Project Cost incl. GST 1,579.69 F Bid Project Cost (excl. GST) 1,542.56 G Contingency 15.00 H Price adjustment during construction 90.37 I Maintenance charges incl. price escalation 203.42
(nominal) J NPV of maintenance charges 83.39 K Interest on annuity (nominal) 678.07 L NPV of interest on annuity 269.13 M Supervision charges 13.56 N Agency charges 0.00 O GST @18% 457.74 N1 LA cost incl. RR & compensation for 798.29 structures N2 Other cost (environment mitigation 10.00 measures etc.) P LA and other pre-construction cost (N1 + 808.29 N2) Q TOTAL CAPITAL COST 3,809.01 R NPV OF TOTAL CAPITAL COST 3,182.38
9. Financial Viability E quity IRR: 12.00%
Project IRR: 10.31%
10. Clearances Forest Clearance: 3.3329 Ha.
Stage-1 obtained on 10.02.2022 Stage-2 obtained on 30.03.2022
Environment clearance: NA
ROB GAD approval: 2No.s of ROB’s. GADs of both approved by CBE, railway Authority on 17.05.2021
Land Acquisition: Total Land to be acquired: 337.27 Ha Land Acquisition Cost (including R&R and compensation structure) Rs. 798.3 Cr.
11. Bidding Process Single stage two- part system of bidding
12. Bidding Parameter Lowest Bid Project Cost
52. The proposed project is identified as Feeder Route under Bharatmala Pariyojana along with Ludhiana Bypass for decongestion of North-South corridor. The Ludhiana-Rupnagar corridor has been notified as NH-205K vide Gazette Notification S.O. 4363(E) dated
03.12.2020. Its primary objective is to strengthen connectivity from the inner regions of Punjab and Himachal Pradesh to the Delhi-Katra Expressway, thereby improving the efficiency of long-distance traffic movement and freight logistics across northern India.
3. The Authority would be responsible for land acquisition, statutory approvals and payment of 40% of the Bid Project Cost during construction, while the Concessionaire would undertake the design, financing and construction of the project. During the operations period, the Authority would make annuity and O&M payments. The Concessionaire would be responsible for maintaining the project assets, undertaking O&M. Bidder eligibility would be assessed based on both financial and technical capacity.
4. After and during the detailed presentation, the Chair and the PPPAC members made their observation. DoLA and DoE supported the proposal and stated that there were no further comments to offer.
5. The observations raised by the PD, NITI Aayog and the responses thereto by MoRTH /
NHAI officials are given below: i. The reasons for the increase in the cost vis-à-vis the previously appraised cost may be explained.
Response: The increase in civil cost is attributable to factors such as fly-ash, revision in the number of structures, modified guidelines for clearance around structures, along with LA cost due to arbitration. Another reason is related to the change in modalities for deriving the total capital cost, for which MoRTH had issued a new template in 2025. Costs such as interest on annuity, maintenance charges, price adjustment during construction, etc., were previously considered implicitly but were not reflected in the sanctioned amount. Such costs are now required to be included in the appraised cost.
ii. It may be clarified whether the revised cost in the instant proposal is comparable to the awarded cost of the other two packages.
Response: Considering the different time horizons in which Packages 1 and 3 have been awarded vis-à-vis the instant proposal, an accurate comparison of the costs may not possible. While the per lane km cost of instant proposal has been assessed with other projects in the region, a comparative of the unit costs across the 3 packages will be carried out.
iii. Mini underpasses have been introduced in the instant proposal. It may be confirmed whether these are standard structures which conform to the IRC specifications against which their design will be verified.
Response: These structures are standard box structures, which have been customised as per the project-specific requirements to optimise the earthwork requirements.
6. The observations raised by JS, IFS and the responses thereto by MoRTH / NHAI officials
are given below:
6i. A structure gas pipeline has been included as one of the features of the project. It may be clarified that what is the scope of work of the Concessionaire in this regard.
Response: A structure over the gas pipeline has been provided at Ch. 47+320. The Concessionaire will be required to construct only a structure over the pipeline as per conditions of the agency managing the pipeline.
7. The observations raised by the Chair and the responses thereto by MoRTH / NHAI officials
are given below: i. The road development in the region, including the instant proposal, has been taken up in multiple packages of relatively smaller sizes. The rationale for the same may be explained.
Response: Multiple packages in this region were planned during the Bharatmala Pariyojana, wherein the package sizes were usually limited to road lengths up to 30 kms and contract values of INR 1,000-1,500 Cr. The package size of the instant proposal was decided accordingly during previous appraisal.
ii. The progress for Package 1 has been quite limited at 15%, which has remained unchanged since the last PRAGATI review. Reasons for the same, other than those related to land acquisition, may be explained and whether such reasons are likely to affect the instant proposal as well.
Response: The limited progress of projects can be majorly attributable to the limited availability of earth material which has been a challenge across Punjab. While there has been no construction progress during this period in Package 1, earthwork excavation through dredging in Satluj has been proceeding based on which embankment development has progressed. In this regard, Package 3 has progressed relatively quicker due to better availability of earth material. Therefore, the timely completion of the instant proposal will be subject to availability of earth material for which possible measures are being undertaken by MoRTH / NHAI.
Recommendations
8. After the detailed deliberations, the PPPAC unanimously, recommended the proposal “Construction of 4/6-Lane Greenfield Ludhiana–Rupnagar National Highway (NH205K), Package-2, including the Ludhiana Bypass, in the State of Punjab under Hybrid Annuity Mode (HAM)” for consideration of the Competent Authority for giving Administrative
Approval subject to following recommendations: i. The appraised Total Capital Cost of the project is INR 3,809.01 crore. The Estimated Project Cost excluding GST is INR 1,356.14 crore. ii. The project should be taken up on HAM under the NH(O) scheme.
iii. The project shall be taken up in a single package. iv. Land acquisition and necessary clearances to be obtained in a timebound manner to avoid delay in the project.
9. Revalidation of its recommendation by the PPPAC is not required for following post- recommendation changes in the project costs/bid documents:
7i. Any change in the date/time period for any time-bound actions like appointed date, financial close, construction period etc. ii. Non-substantial change in risk-allocation. iii. Any other changes/modification in the project proposal with the overall objective of making project successful.
iv. Further, MoRTH may decide whether the changes proposed post recommendations of the project proposal by the PPPAC fall within the threshold criteria as stated above. All such changes falling within the threshold criteria shall be appraised at the level of Secretary MoRTH, without any further need of revalidation by the PPPAC and shall proceed with the approval process accordingly.
8Project 2: Construction of Six lane Access Controlled Amaravati Outer Ring Road including Spur from Guntur to Narakodur- 4 lane on Hybrid Annuity Mode in the state of Andhra Pradesh
1. The details of the proposal are as given below:
SN Item Description
1. Name of the Construction of Six lane Access Controlled Amaravati Outer Ring Project Road including Spur from Guntur to Narakodur- 4 lane on Hybrid Annuity Mode in the state of Andhra Pradesh
2. Type of PPP Hybrid Annuity Mode (HAM) (BOT, BOOT, BOLT, OMT etc)
3. Location (State/ State: Andhra Pradesh District/ Town) Districts: NTR, Eluru, Krishna, Guntur & Palnadu
4. Administrative Ministry of Road, Transport and Highways, Government of India Ministry/ Department
5. Name of Ministry of Road, Transport and Highways, Government of India Sponsoring Authority
6. Name of the National Highways Authority of India Implementing Agency
7. Brief description The details of the Project Road are as under:
of the project The Salient features of the Project Highway are:
SN Project Pkg-I (Km. Pkg-2 Pkg-3 Pkg-4 Features 0+000 to (Km. (Km. (Km.
Km. 27+000 83+000 to 133+500 27+000 & to Km. Km. to Km.
Km. 83+000) 133+500) 189+000) 189+000 to Km.
189+93) Length 27.93 56 50.5 55.5 1
(km) Constructi 36 36 36 36 on Period 2 (in months) 1 no. (9 x 2 nos. 1no. 1 no.
30 = 270 (19x30 = (84x60+1x (48x60+1 m) 570 m; 50+1x30+ x20= 1x20 + 1x6 2900 m Major 8x42 + 1 0+2x30+1 Krishna 3 bridge x 20 x60 = bridge) (No.) =378 m) 5300m Cable Krishna Stayed bridge) Bridge {Span 9Arrange
ment: 19 x 60 + 1 x 190 + 1 x 350 + 1 x 190 + 17 x 60 + 1 x 50} 2 nos. (T1: Nil Nil 1 no. (T3:
2.780 km 0.510 4 Tunnels & T2: km)
1.690 km) 2 nos. 2 nos. 2nos. 2nos. (1x20+1x3 (1x20+1x (1x20+1x3 (1x20+1x
7.280+1x2 19.08+1x 7.28+1x19 37.28+ 0 = 37.28+ .08 1x20.0 =
77.280m 1x19.08+ +1x20.0 = 77.28 m and 1x20.0 96.36 m 1x30+1x 5 ROB 1x35+1x3 =115.44 and 37.28+1x
7.28+1x19 m 1x20+1x3 19.08+1x .08+1 1x30+1x 7.28+1x25 30.0 = x20.0= 37.28+ = 82.28 m) 116.36
111.36 m) 1x19.08+ m) 1x30.0=1
16.3) Number of 130 240 185 203 Structures (VUP, MNB, 6 LVUP, Box Culverts, Structure at Interchange Via Duct Nil Nil Nil Nil 7
(No) SVUP Nil Nil Nil Nil 9
(No) Nil Nil Nil Nil 10 AUP (No) Nil Nil Nil Nil 11 PUP (No) Nil Nil Nil Nil 13 FOB (No.) Major Nil Nil Nil Nil 17 junctions (No.) Minor Nil Nil Nil Nil 18 junctions (No.) Bus bays/ Nil Nil Nil Nil 19 Bus 10Shelter (No.) Truck lay Nil Nil Nil Nil 20 bye (No.) Wayside 4 21 amenities (No.) Interchang 3 6 4 4 22 es (MLFF is proposed) 23 Toll Plaza The project is scheduled to be completed in 1095 days (36 months) from the appointed date
8. Estimated Description Pkg- Pkg- Pkg- Pkg- Total Capital Costs 1 2 3 4 (in with breakup Cr) under major Civil A1 2724. 2589. 2534 2594 1044 heads of Construction 23 17 .39 .3 2.09 expenditure. Cost Also indicate the Utility shifting A2 33.39 66.96 87.5 66.3 254.2 basis of cost cost 3 5 3 estimation Total Cost A=(A1+ 2757. 2656. 2621 2660 1069 including Utility A2) 62 13 .92 .65 6.32 shifting Civil 0.18 X 3,253 3,134 3,09 3,13 12,62 Construction A1 .99 .23 3.87 9.57 1.66 Cost GST@18% IC/ Pre- B = 1% 27.58 26.56 26.2 26.6 106.9 operative of A 2 1 6 Expenses Financing Cost C = 15 15 15 15 60
0.75% of Debt Amount if A1 is less than INR 2000 Cr.,
0.5% of Debt Amount if A1> INR 2000 Cr. subject to Minimu 11m INR 15 Cr.
Interest during D (as 167.9 160.0 157. 160. 646.3 construction per 9 3 94 36 2 Financi al Model) Estimated E 2,968 2,857 2,82 2,86 11,50 Project Cost (ΣΑ:D) .18 .72 1.08 2.61 9.60
(EPC) Bid Project Cost F =As 3,386 3,299 3,25 3,30 13,24
(BPC) per .70 .23 7.77 3.74 7.44 Financi al Model Contingencies G = 1% 27.24 25.89 25.3 25.9 104.4 of A1 4 4 2 subject to minimu m of INR15 Cr.
Price Escalation H =% 248.1 239.0 235. 239. 962.6 during of A 9 5 97 46 7 construction defined period below 15 years 15% of 445.2 428.6 423. 429. 1726.
Maintenance E 3 6 16 39 44 period (flexible pavement) NPV of J 141.3 136.1 134. 136. 548.1 Maintenance 7 1 36 34 7 charges including escalation Interest on K = 1,484 1,428 1,41 1,43 5754.
Annuity 50% of .09 .86 0.54 1.31 8 E NPV of Interest L 464.1 446.8 441. 447. 1799. on Annuity 3 6 13 62 73 Supervision M = 1% 29.68 28.58 28.2 28.6 115.1 charges of E 1 3 GST N = 18 1,011 981.0 968. 982. 3943.
% of (F .80 5 58 52 96 + G+ 12H+I+K+ M) LA and other O 774.7 1,553 1,44 1,53 5314. pre-construction 7 .42 7.22 9.55 96 charges Total Capital P = 7,407 7,984 7,79 7,98 3127 Cost F+G+H .70 .74 6.81 0.54 6.73 +I+K+( M+N+O ) NPV of Total Q = 5,845 6,480 6,31 6,47 25112 Capital Cost {(F+G+ .59 .76 2.11 3.99 .45 H+J+L+ M) *1.18} +O
9. Financial Pkg-I Pkg-II Pkg-III Pkg-IV Viability PIRR 10.47% 10.47% 10.47% 10.47% EIRR 12% 12% 12% 12%
10. Clearances SN Approvals/Clearances Status 1 Land Acquisition Status 3A Completed 2 Environmental clearance Yet to be Initiated 3 Status of ROB clearance In progress 4 Cutting of Live Trees Yet to be Initiated 5 Utility Shifting Estimates In-progress 6 Forest Clearance Yet to be Initiated
11. Bidding Process S ingle stage two- part system of bidding
12. Bidding Lowest Bid Project Cost Parameter
2. Member NHAI explained that the proposed project, the Outer Ring Road (ORR) is a greenfield infrastructure project being developed to improve regional connectivity around the capital city of Amaravati and the major urban centres of Vijayawada, Guntur and Tenali.
The project includes 189.93 km of the ORR main corridor and a 5.20 km four-lane Narakodur spur road, with connectivity to six National Highways, seventeen interchanges, twenty major bridges, ninety-five minor bridges, one hundred and five underpasses, and will pass through five districts, namely NTR, Eluru, Krishna, Guntur and Palnadu.
3. The Authority would be responsible for land acquisition, statutory approvals and payment of 40% of the Bid Project Cost during construction, while the Concessionaire would undertake the design, financing and construction of the project. During the operations period, the Authority would make annuity and O&M payments. The Concessionaire would be responsible for maintaining the project assets, undertaking O&M. Bidder eligibility would be assessed based on both financial and technical capacity.
4. After and during the detailed presentation, the Chair and the PPPAC members made their observation. DoLA and DoE supported the proposal and stated that there were no further comments to offer.
5. The observations raised by the PD, NITI Aayog and the responses thereto are given below:
13i. Considering that it is a circular road with an approximate radius of 60 km and the area within is not densely populated, the basis for the proposed alignment may be elucidated.
Response: The proposed alignment has been provided by the State Government based on the anticipated future growth and development of Amaravati. The alignment has been finalised with reference to the Amaravati Regional Development Plan, which considers the planned development and future growth of the region.
ii. For a six-lane highway, approximately 70 m of the proposed 140 m RoW would be utilised, leaving around 35 m of land on either side. There is a risk that this vacant land may be encroached upon over time, particularly when widening or upgrading the corridor after 20–30 years. The mechanisms proposed to protect and preserve this land for future use may kindly be detailed.
Response: NHAI officials explained that a similar approach was adopted for the Hyderabad Outer Ring Road, where land was acquired for a 150 m RoW. The corridor was developed as an eight-lane facility comprising the main carriageway and two-lane service roads on either side. The space between the main carriageway and the service roads was retained for future transportation requirements. For instance, a metro system is currently being developed within this reserved space.
Similarly, the additional land within the proposed 140 m RoW for the Amaravati ORR would be preserved for future transportation and other infrastructure requirements. To prevent encroachment and protect the land, NHAI would provide appropriate fencing and boundary walls along the corridor. The cost of such fencing and boundary protection measures has already been factored into the overall project cost.
iii. Whether the vacant land available within the additional 35 m on either side of the proposed 140 m RoW could be utilised for solar power generation or other productive purposes was discussed. It was suggested that, if the land is required to be preserved for future development, its interim utilisation should be explored in a manner consistent with its intended long-term purpose.
Response: NHAI officials informed that provision for solar energy generation has already been made at certain interchanges. The possibility of extending and scaling up solar energy generation to utilise the available land would be examined further.
Whether the two tunnels proposed on the northern side of the project could be avoided by exploring an alternative alignment was raised for consideration.
Response: NHAI officials explained that the northern side of the proposed alignment is close to the Telangana State boundary. The terrain in this area is hilly, and the proposed tunnels are required to negotiate the difficult terrain and maintain the overall alignment.
Accordingly, avoiding the tunnels may not be feasible
6. The observations raised by JS, IFS and the responses thereto are given below: i. The contribution of the State Government towards the project, and the corresponding cost saving for the project were sought.
14Response: The State Government’s contribution/support towards the project comprises a GST waiver of approximately INR 2,000 crore, waiver of seigniorage charges amounting to approximately INR 590 crore, and contribution towards Land Acquisition (LA) costs of approximately INR 1,000 crore, subject to the provision of 140 m Right of Way (RoW).
Accordingly, the total contribution/support from the State Government is estimated at approximately INR 3,562.35 crore.
7. The observations raised by DS, PIU and the responses thereto are given below: i. The details of cost optimisation and rationalisation measures undertaken in the project, and their impact on the overall project cost may be described
Response: NHAI officials stated that several project components have been rationalised to optimise the project cost, including reduction of the median width from 12 m to 5 m, reduction of tunnel width from 8 m to 6 m, removal of the Tenali Spur from the project scope, reduction in the extent of proposed service roads, and revision of the embankment slope from 2:1 to 1.5:1. These optimisation measures have resulted in savings of approximately INR 3,178 crore, thereby reducing the total project cost from approximately INR 13,620 crore to INR 10,442 crore.
8. The observations raised by the Secretary MoRTH and the responses thereto are given
below: ii. The Hon’ble CM had indicated that fly ash available at the site would be provided by the State Government. Has the corresponding cost been factored into the State’s contribution? Has the financial impact of this provision been assessed?
Response: NHAI officials stated that the cost implication of the fly ash to be made available by the State Government is being assessed. NHAI will undertake the assessment and submit the details of the associated cost and its impact on the State’s contribution.
9. The observations raised by the Chair and the responses thereto are given below: i. The rationale for structuring the project into four packages was sought, considering that the total length of the ORR is approximately 189 km and NHAI has previously implemented project packages of 75–90 km in length.
Response: The project has been divided into four packages primarily considering the large structures, including 2 major bridges, and three tunnels involved in the project. The construction of the major bridge structures is expected to take approximately 4 years.
Accordingly, the project has been structured into multiple packages to facilitate effective construction and timely implementation. Given the scale and complexity of the structures involved, it would not be feasible to consolidate the project into only two packages.
ii. The project envisages a Peacock Feather-themed iconic bridge design. Is such an iconic design necessary for the project? What would be the difference in cost and functionality compared with a conventional bridge, and what other design alternatives have been considered? 15Response: The proposed Peacock Feather-themed iconic bridge would cost approximately INR 220 crore more than a conventional bridge. The additional cost is attributable to the architectural and aesthetic features associated with the iconic design.
iii. Clarification was sought on whether the second bridge is also comparable in cost to the proposed Peacock Feather-themed iconic bridge, including the respective lengths and estimated costs of both bridges, considering the significant expenditure of public funds involved.
Response: NHAI officials explained that the second bridge is a conventional bridge with a length of approximately 5.4 km and an estimated cost of around INR 700 crore. The proposed Peacock Feather-themed iconic bridge is approximately 3 km long and has an estimated cost of around INR 900 crore. The higher cost of the iconic bridge is primarily due to its specialised architectural and structural design.
iv. The rationale for implementing the project under the Hybrid Annuity Model (HAM), instead of the Build-Operate-Transfer (BOT) model, despite the project's financial viability, was sought.
Response: NHAI officials cited that the project is proposed under HAM for the following key
reasons: Uncertainty in traffic growth: Amaravati is a new city that is still under development, and the future traffic growth is expected to be significant but is difficult to predict at this stage. Implementing the project under BOT at present may result in the Government foregoing the potential future value of the asset. It is therefore considered more appropriate to develop the project under HAM and consider monetisation through Toll- Operate-Transfer (TOT) after 5-7 years, once sufficient visibility on traffic growth is available. As an example, the Western Peripheral Expressway (KMP Expressway) in Haryana was inaugurated in 2018. An offer for TOT monetisation in 2020-21 valued the asset at approximately INR 2,000 crore. Considering the expected increase in traffic, the valuation subsequently increased to approximately INR 5,000 crore in 2024 and is currently estimated at around INR 9,000 crore. This illustrates the potential for significant appreciation in asset value once traffic matures.
Long construction period and financing costs: The project involves several major structures, resulting in a relatively long construction period. Under the BOT model, a construction period extending to 4 years or more would lead to substantial Interest During Construction (IDC), which could significantly increase the overall project cost (almost half the project cost). BOT projects are generally more suitable where the construction period can be limited to approximately 2-3 years. Given the complexity of the proposed project, BOT may therefore not be financially viable.
Package structure and traffic risk: Under the BOT model, the number of packages would need to be reduced, potentially to two packages. This could create a traffic availability risk if one package is completed while the other remains under construction.
Similar concerns have been observed in projects such as the Nashik–Akalkot Highway, where staggered completion of packages can affect traffic availability and consequently the financial viability of the project.
v. If the project is implemented under HAM, a significant portion of the project cost will be borne by the Government. Therefore, greater prudence is required in determining the structures and design elements to be included in the project. In this context, the inclusion of an expensive iconic or specialised bridge may need to be reconsidered.
16Under BOT, the private concessionaire brings in the required capital and recovers the investment through toll revenues. However, under HAM, there is a need to exercise greater cost discipline and optimise the project cost.
Response: NHAI agreed with the observation and acknowledged the need for greater cost prudence under the HAM structure. NHAI further indicated that the asset could be considered for monetisation through TOT after approximately 5-7 years of operation, once sufficient traffic data is available, and the traffic growth potential of the corridor has been assessed.
vi. What is the typical Right of Way (RoW) considered for a six-lane highway? The proposed RoW of 140 m appears to be on the higher side and may have significant implications for the Union Budget, particularly considering the State Government's limited capacity to fund the associated costs. Can the proposed RoW be reconsidered?
Response: The typical RoW for a six-lane highway is generally in the range of 75-80 m.
However, the proposed 140 m RoW has been discussed at the highest level within the State Government, considering the long-term and futuristic development requirements of Amaravati.
The Hyderabad Outer Ring Road (ORR), which was developed with an RoW of approximately 150 m, was cited as an example. Despite the wider RoW, the capacity has been found to be inadequate over a period of around 20 years due to the city's growth and increasing traffic. Accordingly, considering Amaravati as a futuristic city with significant anticipated growth, the higher RoW has been proposed to cater to long-term development requirements.
vii. The details of the tunnels and bridges proposed under the project was sought, including their package-wise distribution and the corresponding estimated costs.
Response: The project area is located close to the sea and has several irrigation channels and watercourses, resulting in a significant number of bridge structures. The project comprises approximately 20 major bridges, 88 minor bridges, and 77 underpasses. The details of these structures, including their package-wise allocation and corresponding costs, were presented during the meeting.
viii. The Chair requested that a detailed presentation be prepared covering the overall project cost, the key factors contributing to the additional cost, and the rationale for implementing the project under the Hybrid Annuity Model (HAM). The presentation should also clearly highlight the financial implications for the Union Government, the contribution and support being provided by the State Government, and the various cost optimisation measures undertaken. The presentation may incorporate all the key issues and points discussed during the meeting.
Recommendations:
After detailed deliberations, the PPPAC recommended that the proposal for “Construction of Six- Lane Access Controlled Amaravati Outer Ring Road, including a four-lane spur from Guntur to Narakodur, on Hybrid Annuity Mode (HAM) in the State of Andhra Pradesh” may be further 17examined, particularly with respect to the overall project cost and the associated financial implications.
Following such examination and resolution of the issues discussed during the meeting, the proposal may thereafter be reconsidered by PPPAC.
Project 3: Six-Laning of the Hyderabad–Vijayawada–Machilipatnam Section of NH-65 in the States of Telangana and Andhra Pradesh.
1. The details of the proposal are as given below:
S Item Description N
1. Name of the Six-laning of Hyderabad – Vijayawada - Machilipatnam Section of NH-65 Project [from design Ch. 39.850 to Ch. 266.150 (Hyderabad – Vijayawada
Section) & from design Ch. 4.000 to Ch. 63.695 (Vijayawada - Machilipatnam Section), total length 285.995 Km] in the States of Telangana & Andhra Pradesh The instant project is part of Pune – Machilipatnam Corridor (NH-65).
Length Total Capital Pkg Project/NH no.
(Km) Cost (Rs in Cr.) Hyderabad – Vijayawada Ch. 39.85 to 1 181.300 7,321.97 Ch. 221.15 Hyderabad – Vijayawada Ch. 221.15 2 45.000 2,965.11 to Ch. 266.15 Vijayawada – Machilipatnam Ch. 4.00 3 59.696 1,786.91 to Ch. 63.695 Total (Hyderabad – Vijayawada –
285.995 12073.99 Machilipatnam)
2. Type of PPP Hyderabad – Vijayawada Section (Pkg-1 & Pkg-2): BOT (Toll) (BOT, BOOT, Vijayawada - Machilipatnam Section (Pkg-3): Hybrid Annuity Mode BOLT, OMT etc)
3. Location State: Telangana & Andhra Pradesh (State/ District: Yadadri Bhuvanagiri, Nalgonda & Suryapet Districts of the District/ Town) Telangana State and NTR & Krishna District of the Andhra Pradesh State
4. Administrativ Ministry of Road, Transport and Highways, Government of India e Ministry/ Department
5. Name of Ministry of Road, Transport and Highways, Government of India Sponsoring Authority
6. Name of the National Highways Authority of India Implementing Agency
187. Brief of the S. Details Hyderabad Hyderabad Vijayawada – Project No. – – Machilipatnam Vijayawada Vijayawada Ch. 4.00 to Ch.
Ch. 39.85 to Ch. 221.15 63.695 (59.695 Ch. 221.15 to Ch. Km) Pkg-3 (181.30 Km) 266.150 Pkg-1 (45.00 Km) Pkg-2 1 Length 181.300 45.000 59.695 2 Carriageway 6-Lane with 6-Lane with 6-Lane with Width Paved Paved Paved Shoulders Shoulders Shoulders/ 4- lane with Service Roads 3 Major Bridges 3 Nos. 5 Nos. 3 Nos.
4 Minor Bridges 40 Nos. 7 Nos. 4 Nos.
5 Culverts 328 Nos. 109 Nos. 89 Nos.
6 Flyover/Viaduct 1 No. 1 Nos. 1 Nos.
7 Overpass Nil. Nil. Nil.
8 VUP 16 Nos. 6 Nos. 7 Nos.
9 LVUP 30 Nos. 7 Nos. 4 Nos.
10 SVUP 3 Nos. 3 Nos. Nil.
11 CUP/PUP 13 Nos. 2 Nos. Nil.
12 ROB/RUB Nil. Nil. Nil.
13 Major/ Minor 33 Nos./104 15 Nos./21 26 Nos./28 Junctions Nos. Nos. Nos.
14 Interchanges Nil Nil Nil 15 Length of 336.46 Km 69.20 Km 114.005 Km Service/ Slip Road 16 Length of Nil. Nil. Nil.
Ramps & Loops 17 Toll Plaza Close Tolling Close Tolling Close Tolling is is proposed. is proposed. proposed.
MLFF Toll MLFF Toll MLFF Toll collection collection collection system is system is system is proposed on proposed on proposed on 19entry-exits at entry-exits at entry-exits at 6 23 locations 6 locations locations (BHS)
(BHS) and (BHS) and at and at start & at start & start & end end point of the end point of point of the package the package package 18 Avg. Traffic 45725 35811 31181 considered
(PCU) 19 Design Traffic 200 MSA/ 90 MSA 150 MSA
(MSA) 90 MSA
8. Estimated Hyderabad-Vijayawada Section of NH-65 Capital Costs Hyderabad Hyderabad – with breakup – S. Vijayawada under major Details Vijayawada No Ch. 221.15 to heads of Ch. 39.85 to Ch. 266.15 expenditure. Ch. 221.15 Also indicate Civil Construction Cost the basis of including Utility Shifting Cost cost i 5,035.05 1,512.68 without Escalation (Base year estimation 2025-26) Total Civil Construction Cost 1 including Utility Shifting Cost 5,035.05 1,512.68 up to Appointed Date Escalation during Construction 2 @ 4% (As per Financial 295.39 88.74 Model) IC/Pre-Operative Expenses @ 3 50.35 15.13 1% (As per Financial Model) Financing charges 0.75% of 4 35.66 10.71 debt (As per Financial Model) Interest During Construction 5 401.11 120.51
(IDC) @ 10.97% p.a.
O&M during Construction on 6 0 0 existing highway Estimated Project Cost 7 (without GST) 5,817.56 1,747.77 (1+2+3+4+5+6) 8 Estimated project cost per km 32.09 38.84 20GST @18% on Civil Construction Cost (Sno. 1, 2 & 959.48 288.26 9 6) 10 GST @18% on Sno. 3 & 4 15.48 4.65 Total Project Cost (with 6,792.52 2,040.68 11 GST) (7+9+10) 12 Pre-Construction Cost
(i) Land Acquisition Cost 529.45 924.43
(ii) Environmental Cost 0 0 Total Cost of Pre-Construction
529.45 924.43
(iii) Activities Total Capital Cost [11+12 7,321.97 2,965.11 13 (iii)] Vijayawada-Machilipatnam Section of NH-65 A1 Civil Construction Cost 751.36 A2 Utility Shifting Cost 15.03 A Total Civil Cost i/c Utility Shifting (A1+A2) 766.39 Civil Construction Cost + 18% GST (A1+B) 886.60 IC/Pre-operative Expense (B= 1% of A) (As B 7.66 per Ministry's Circular dated 06.11.2025) Financing Cost (C=0.75% of debt) (as per C 4 Financial Model) (subject to minimum Rs 4 Cr) Interest during Construction (as per D 28.72 Financial Model) E Estimated Project Cost (EPC) (Sum: A to D) 806.77 Bid Project Cost (BPC) (as per Financial F 883.89 Model) Contingencies (1.5% of A1 subject to G 11.27 minimum of Rs. 10 Cr.) Price Escalation during construction period H 53.65 (for 2 years) (7% of A) Maintenance Charges including price I 121.02 escalation (15% of E) NPV of Maintenance charges including price J 43.90 escalation 21K Interest on Annuity (50% of E) 403.39 L NPV of Interest on Annuity 144.22 M Supervision Charges (1% of E) 8.07 Agency Charges (1.5% of A, subject to N minimum Rs 8 Cr. and maximum of 12 Cr.) (No 0.00 agency charge for NHAI) O GST [18% of (F+G+H+I+K+M+N)] 266.63 P LA and other pre-construction charges 39.00 Q Total Capital Cost (F+G+H+I+K+M+N+O+P) 1786.91 R NPV of Total Capital Cost 1390.09
8.
9. Financial S. Particulars Hyderabad Hyderabad Vijayawada – Viability No – – Machilipatnam Vijayawada Vijayawada Ch. 4.00 to Ch.
Ch. 39.85 Ch. 221.15 63.695 (59.695 to Ch. to Ch. Km) (Pkg-3)
221.15 270.88 (Pkg-1) (Pkg-2)
1. Equity IRR 14% 14% 12%
2. Project IRR 12.15% 12.18% 10.20%
3. Civil Construction 5,035.0 1,513.0 766.39 Cost incl Utility (Rs. in Cr.)
4. Estimated Project 5817.57 1747.77 806.77 Cost (Rs. in Cr.)
5. Estimated Bid NA NA 883.89 Project Cost for
12.00% Equity IRR (Rs. in Cr.) 10 Clearances 1. Status of Land Acquisition is as under: . S. Description Present Status Present Status No (Hyderabad – (Vijayawada – Vijayawada Machilipatnam
Section) Section) 1 Total Land Required 1387.628 351.185
(Ha) 2 Land Available (Ha) 1174.295 344.685 3 Addl. Land Required 213.333 6.50
(Ha) A Forest Land (Ha) 0.0 0.0 22B Private Land (Ha) 213.333 6.50 4 3A Status (Ha) Under Under Verification Verification with with CALA Office CALA Office 5 3D Status (Ha) - - 6 3G Status (Ha) - -
2. Status of various clearances is as below:
Sl Approvals/ Concerned Status No Clearances Agencies 1 Forest Diversion Not Applicable 2 Wildlife Clearance Not Applicable 3 Environment Not Applicable Clearance 4 Tree Felling Forest Tree enumeration is Permissions Department under progress 5 Electrical Utilities TGSPDCL, Approval under APSPDCL, progress. Shifting is TGTRANSCO, under the scope of APTRANSCO, Concessionaire Power Grid 6 Water Supply Mission Approval under Utilities Bhagiratha, progress. Shifting is RWS, Municipal under the scope of Water Supply Concessionaire 7 ROB GAD Not Applicable 8 Canal Crossing State Irrigation Approval under GAD Dept. progress
11. Bidding Single stage two- part system of bidding Process 12 Bidding Lowest Bid Project Cost . Parameter 2 The proposed project is identified as Feeder Route under Bharatmala Pariyojana along with Ludhiana Bypass for decongestion of North-South corridor. The Ludhiana-Rupnagar corridor has been notified as NH-205K vide Gazette Notification S.O. 4363(E) dated 03.12.2020. Its primary objective is to strengthen connectivity from the inner regions of Punjab and Himachal Pradesh to the Delhi-Katra Expressway, thereby improving the efficiency of long-distance traffic movement and freight logistics across northern India.
3 The Authority would be responsible for land acquisition, statutory approvals and payment of 40% of the Bid Project Cost during construction, while the Concessionaire would undertake the design, financing and construction of the project. During the operations period, the Authority would make annuity and O&M payments. The Concessionaire would be responsible for maintaining the project assets, undertaking O&M. Bidder eligibility would be assessed based on both financial and technical capacity.
4 After and during the detailed presentation, the Chair and the PPPAC members made their observation. DoLA and DoE supported the proposal and stated that there were no further comments to offer.
235 The observations raised by the PD, NITI Aayog and the responses thereto are given below: i. It is being assumed that some part of the present traffic will get diverted to the service roads being proposed. However, considering the limited speed of travel in the service roads and the possibility of the same being encroached upon, there may be a risk of local traffic continuing to use the main carriageway leading to congestion.
Response: Generally, it has been seen that around 10-20% traffic gets diverted to service roads from the main carriageway in similar other projects. This may be attributed to the service roads being toll-free as well as the good quality of road construction. Therefore, a substantial diversion of local traffic to the service roads has been assumed in the instant proposal as well.
ii. Package 2 of the instant proposal, proposed to be implemented under BOT (Toll), would function as a radial road to the Amaravati ORR, which is proposed to be implemented under HAM. From the perspective of future TOT monetisation, whether Package 2 should be considered for clubbing with the Amaravati ORR was discussed, given that traffic may be distributed between the radial road and the ORR once both corridors are operational.
Response: It was clarified that Package 2, having a length of approximately 45 km, has a relatively lower project cost and lower traffic projections, resulting in comparatively lower project risk. Further, appropriate traffic mitigation measures have been incorporated to address potential traffic diversion concerns. It was explained that long-distance traffic bound towards Machilipatnam is expected to utilise the Amaravati ORR, while traffic bound towards Vijayawada or Guntur is expected to primarily utilise the Package 2 radial road. The bidders for Package 2 would also be informed about the proposed Amaravati ORR so that the upcoming ORR and its potential impact on traffic may be suitably factored into their bids.
iii. In a BOT (Toll) project, there is a provision for trigger traffic. Once the Amaravati ORR is operationalised, there is a possibility of traffic in Package 2 being lower vis-a-vis the present traffic. The target traffic based on the projections may therefore be rationalised to minimise the possibility of dispute / litigation at a later stage.
Response: The target traffic for Package 2 will be suitably defined by incorporating the possibility of traffic diversion due to the Amaravati ORR. The bidder will be provided adequate visibility of the traffic in this regard.
iv. The alignment passes through regions which have seen severe floods in the recent years. It may be clarified whether suitable disaster-resilience measures have been incorporated in the structural design.
Response: The design has been finalised after consideration of such factors.
6 The observations raised by JS, IFS and the responses thereto are given below: i. In Part 2 of the instant proposal, the existing traffic appears to be significant. It appears that the present proposal for capacity expansion may not be sufficient to 24cater to the expected traffic beyond COD and that further augmentation of capacity may be warranted later.
Response: The traffic between Hyderabad and Vijayawada is a combination of local traffic and through traffic, which reduces the speed of travel thereby causing congestion. In order to segregate the local traffic which also includes sizeable proportion of two wheelers, dedicated service roads have been proposed along with multiple entry and exit points. As a result of the local traffic being segregated from the through traffic, the overall average speed of travel on the main carriageway is expected to increase which will optimise the traffic handling capacity of the corridor. Further widening of the main carriageway would require additional RoW which will not be possible due to habitation along the alignment.
7 The observations raised by the Chair and the responses thereto by MoRTH / NHAI officials
are given below: i. Considering the limited project length of Package 2, it may be clarified whether the possibility of undertaking Packages 1 and 2 as a single package has been assessed.
Response: While the overall project length is 285 km, it has been broken down into different packages from a viability and land acquisition perspective. Considering the traffic as well as the limited land acquisition requirement in the Hyderabad to Vijayawada stretch, Package 1 has been found to be viable on BOT (Toll) mode. For Package 2, the existing stretch is already under BOT (Toll) till 2031 and the buyback of the same has been initiated. Further this package has some land acquisition requirement, owing to connecting bypasses, for which additional duration of time is expected. As a result, this has been proposed as a separate package. Considering the limited traffic envisaged in the Vijayawada- Machilipatnam stretch, it has been proposed as a separate package under HAM model.
Recommendations 8 After the detailed deliberations, the PPPAC unanimously, recommended the proposal “Six- Laning of the Hyderabad–Vijayawada–Machilipatnam Section of NH-65 in the States of Telangana and Andhra Pradesh.” for consideration of the Competent Authority for giving
Administrative Approval subject to following recommendations:
The appraised project cost details are as below: Amount (in INR Crore) SN Details Package-1 Package-2 Package-3
1. Estimated Project Cost (without 5,817.56 1,747.77 806.77 GST)
2. Total Capital Cost 7,321.97 2,965.11 1,786.91 i. The project should be implementation under the BOT (Toll) mode for Packages 1 and 2 and under the HAM for Package 3 ii. The concession period of the projects SN Details Package-1 Package-2 Package-3
1. Concession Period 20 Years including 2.5 17 Years including 2 years of construction years of construction period period 25iii. Land acquisition and necessary clearances to be obtained in a timebound manner to avoid delay in the project 9 Revalidation of its recommendation by the PPPAC is not required for following post- recommendation changes in the project costs/bid documents:
i. Any change in the date/time period for any time-bound actions like appointed date, financial close, construction period etc. ii. Non-substantial change in risk-allocation. iii. Any other changes/modification in the project proposal with the overall objective of making project successful.
iv. Further, MoRTH may decide whether the changes proposed post recommendations of the project proposal by the PPPAC fall within the threshold criteria as stated above. All such changes falling within the threshold criteria shall be appraised at the level of Secretary MoRTH, without any further need of revalidation by the PPPAC and shall proceed with the approval process accordingly.
10 The meeting ended with a vote of thanks to the Chair. *** 26Annexure-I List of the attendees of the 150th meeting of the PPPAC for considering the proposal a. Department of Economic Affairs, Ministry of Finance
1. Ms. Anuradha Thakur, Secretary (EA)
2. Ms. Laya Madduri JS (IFS)
3. Shri. Jai Patil, Deputy Secretary (PIU)
4. Ms. Shraddha D Narwade, Assistant Director (PIU)
5. Shri. Deepak Meena, ASO (PIU) b. Department of Expenditure
1. Shri. Bharat Indora, Under Secretary c. NITI Aayog
1. Shri. Partha Sarathi Reddy, Programme Director, NITI Aayog d. Department of Legal Affairs
1. Shri. Hemant Kumar, Deputy Legal Adviser e. Ministry of Road Transport and Highways
1. Shri. V. Umashankar, Secretary MoRTH (Online)
2. Shri. Manoj Kumar, Chief Engineer (BP&SP) (Online) f. National Highway Authority of India
1. Shri. Vipnesh Sharma, Member (P)
2. Shri. Rupesh Kr. Srivastava, GM (T)-PB&HR - NHAI
3. Shri. Devesh Goyal, DGM (T) -PB&HR - NHAI
4. Shri. Aryaman, Manager (T) -PB&HR - NHAI
5. Shri. Vipin Mangla, GM -NHAI
6. Shri. Prashant S Sagar, Deputy Manager- NHAI
7. Shri. Ramlakhan, Manager-NHAI
8. Shri. Anil Kumar- Almonds Securities- FC, NHAI
9. Ms. Ila Dobhal- FC, NHAI
10. Shri. Aditya Sharma, DPR Consultant, M/s SA infra
11. Shri. Bhavik Bhardwaj, Financial Consultant, M/s Resurgent 27