In exercise of powers conferred under Section 178 of the Electricity Act,

Issued by Central Electricity Regulatory Commission · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

Executive Summary: The Central Electricity Regulatory Commission (CERC) amends its regulations regarding the procedure, terms, and conditions for granting trading licenses. The amendments, effective from the date of notification in the Official Gazette, modify the trading margin for banking transactions and the letter of credit requirements for short-term contracts exceeding one month. These changes are made under the powers conferred by Section 178 of the Electricity Act, 2003. Key Points / Main Content: * **Trading Margin Amendment:** * The trading margin for banking transactions shall not be less than zero (0.0) paise/kWh from either party involved. * **Letter of Credit Amendment:** * For short-term contracts exceeding one month, the letter of credit in favor of the seller must be equivalent to 1.05 times the monthly contract value. * The validity period of the letter of credit should match the validity of the contract. Impact Analysis: * **Electricity Traders:** * Impact: Affected by the revised trading margin for banking transactions and the new letter of credit requirements for short-term contracts. * Action Required: Ensure trading margins comply with the new minimum limit. For contracts longer than one month, provide a letter of credit equivalent to 1.05 times the monthly contract value, valid for the contract duration. * **Central Electricity Regulatory Commission (CERC):** * Impact: Responsible for implementing and enforcing the amended regulations. * Action Required: Update guidelines and monitoring processes to reflect the changes in trading margin and letter of credit requirements. * **Parties involved in Banking Transactions:** * Impact: Directly affected by the revised trading margin for banking transactions * Action Required: To ensure that the trading margin from either of the parties to the banking transaction is not less than zero 0.0 paise/kWh * **Seller:** * Impact: Will need to ensure that the letter of credit validity is equivalent to the validity of the contract. * Action Required: To provide a letter of credit equivalent to 1.05 times the monthly contract value, valid for the contract duration where the duration of the short term contract is more than one month

Key Entities Referenced

Central Electricity Regulatory Commission (CERC): A statutory body responsible for regulating the electricity sector in India. It is the primary regulatory body mentioned in the document. Electricity Act, 2003: The primary legislation governing the electricity sector in India, providing the legal framework for the CERC's regulatory powers. Central Electricity Regulatory Commission Procedure, Terms and Conditions for grant of trading licence and other related matters Regulations, 2020: The original regulations that this notification seeks to amend. These regulations pertain to the procedure, terms, and conditions for granting trading licenses in the electricity sector. New Delhi: The location where the notification was issued. Central Electricity Regulatory Commission Procedure, Terms and Conditions for grant of trading licence and other related matters First Amendment Regulations, 2020: The short name for these regulations. Sanoj Kumar Jha: Secretary of the Central Electricity Regulatory Commission. Mayapuri, New Delhi: Location of the Government of India Press. Banking transaction: Transaction with trading margin shall not be less than zero 0.0 paisekWh from either of the parties
Official Source Record View Original Source →
See Full Document Text
रिज(cid:7021)(cid:7069)ी स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99 सी.जी.-डी.एल.-अ.-02112020-222897 xxxGIDHxxx CG-DL-E-02112020-222897 xxxGIDExxx असाधारण EXTRAORDINARY भाग III—ख(cid:7003)ड 4 PART III—Section 4 (cid:7079)ािधकार स े(cid:7079)कािशत PUBLISHED BY AUTHORITY स.ं 461] नई (cid:7408)द(cid:7016)ली, सोमवार, नव(cid:7013) बर 2, 2020/का(cid:7414)तक(cid:6981) 11, 1942 No. 461] NEW DELHI, MONDAY, NOVEMBER 2, 2020/KARTIKA 11, 1942 ubZ fnYyh] 25 ekpZ] 2020 –dsUæh; fo|qr fofu;ked vk;ksx] fo|qr vf/kfu;e] 2003 ¼2003 dk 36½ ds v/khu iznŸk 'kfä;k sa vkSj bl fufeŸk lkeF;Zdkjh lHkh vU; 'kfä;k sa dk iz;ksx djr s gq,] vkSj iwoZ izdk'ku ds i'Pkkr~ dsUæh; fo|qr fofu;ked vk;ksx ¼O;kikj vuqKfIr iznku djus ds fy, izfØ;k] fuc/a ku vkSj 'krs± o vU; lac) ekeys½ fofu;e] 2020 ¼ftl s blds i'Pkkr~ bls ewy fofu;e dgk x;k gS½ dk s la'kksf/kr dju s ds fy, ,rn~ }kjk fuEufyf[kr fofu;e cukrk gS] vFkkZr~ :- d- bu fofu;eka s dk laf{kIr uke dsUæh; fo|qr fofu;ked vk;ksx ¼O;kikj vuqKfIr iznku dju s ds fy, izfØ;k] fuc/a ku vkSj 'krs± o vU; lac) ekeys½ ¼izFke la'kks/ku½ fofu;e] 2020 gSA [k- ;s fofu;e 'kkldh; jkti= esa vf/klwpuk dh rkjh[k ls izo`Ÿk gksaxsA 5333 GI/2020 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC. 4] ewy fofu;ekas ds fofu;e 8 ds [kaM ¼1½ ds mi&[kMa ¼³½ esa ,d u;k ijra qd fuEukuqlkj tksM+k tk,xk%& "ijraq ;g fd O;kikj ekÆtu fdlh Hkh ikVhZ ls cSad laO;ogkj ds fy, 'kwU; ¼0-0½ iSls@fdyksokV ?kaVk ls de ugha gksxkA" 9 3-1 fofu;e 9 ds [kaM ¼10½ ds mi&[kMa ¼[k½ ds ckn ,d u;k ijarqd fuEukuqlkj tkMs +k tk,xk%& "ijraq ;g fd tgka vYidkfyd lafonk dh vof/k ,d ekg ls vf/kd gS] ogka foØsrk ds i{k esa lk[k&i= lafonk dh oS/krk ds lerqY; oS/krk vof/k ds lkFk ekfld lafonk ewY; dk ,d n'keyo 'kwU; ikap ¼1-05½ xquk ds lerqY; gksxk" lukst dqekj >k] lfpo [foKkiu-III@4@vlk-@314@2020-21] dsUæh; fo|qr fofu;ked vk;ksx ¼O;kikj vuqKfIr iznku dju s ds fy, izfØ;k] fuca/ku vkSj 'krs± o vU; lac) ekeys½ fofu;e] 2020 fnukda 31 tuojh] 2020 ds Hkkjr ds jkti= ¼vlk/kkj.k½ ds Hkkx III] [kaM 4] la- 43 esa izdkf'kr gqvk FkkA CENTRAL ELECTRICITY REGULATORY COMMISSION AMENDMENT New Delhi, the 25th March, 2020 No. L-1/253/2019/CERC .—In exercise of powers conferred under Section 178 of the Electricity Act, 2003 (36 of 2003) and all other powers enabling it in this behalf, and after previous publication, the Central Electricity Regulatory Commission hereby makes the following regulations, to amend the Central Electricity Regulatory Commission (Procedure, Terms and Conditions for grant of trading licence and other related matters) Regulations, 2020 (hereinafter referred to as the “Principal Regulations”) namely:- 1. Short Title and Commencement a. These regulations may be called the Central Electricity Regulatory Commission (Procedure, Terms and Conditions for grant of trading licence and other related matters) (First Amendment) Regulations, 2020. b. These regulations shall come into force with effect from the date of notification in Official Gazette. 2. Amendment to Regulation 8 of the Principal Regulations: 2.1 A new proviso shall be added to sub-clause (e) of clause (1) of Regulation 8 of the Principal Regulations, as under:-[भाग III—ख(cid:7003) ड 4] भारत का राजप(cid:7074) : असाधारण 3 “Provided that the trading margin shall not be less than zero (0.0) paise/kWh from either of the parties to the banking transaction.” 3. Amendment to Regulation 9 of the Principal Regulations: 3.1 A new proviso shall be added after sub-clause (b) of clause (10) of Regulation 9, as under:- “Provided that where the duration of the short term contract is more than one month, the letter of credit in favour of the seller shall be equivalent to one point zero five (1.05) times of the monthly contract value with validity period equal to validity of the contract” SANOJ KUMAR JHA, Secy. [ADVT-III/4/Exty./314/2020-21] Note: The Central Electricity Regulatory Commission (Procedure, Terms and Conditions for grant of trading licence and other related matters) Regulations, 2020 were published in Part III, Section 4, No. 43 of the Gazette of India (Extraordinary) dated January 31, 2020. Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064 and Published by the Controller of Publications, Delhi-110054