Date: 2015-01-27Category: Extra OrdinaryState: Union GovernmentCountry: India
In exercise of the powers conferred by sub-section (1) of Section 3 of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962 (50 of 1962), the Central Govt. hereby declares its intention to acquire the right of user therein.
Executive Summary:
This notification, issued by the Central Government of India, declares the intention to acquire the right of user in land for laying the Mangalore Hassan Mysore Solur LPG Pipeline by Hindustan Petroleum Corporation Limited. The land is located in Hassan Taluk, Hassan District, Karnataka State, as described in the attached schedule. Interested parties have 21 days from the date the notification is made available to the public to object in writing.
Key Points / Main Content:
* **Pipeline Project:** The Central Government intends to acquire the right of user for land to lay the Mangalore Hassan Mysore Solur LPG pipeline.
* **Implementing Agency:** Hindustan Petroleum Corporation Limited (HPCL) will lay the pipeline.
* **Geographic Location:** The land is situated in Hassan Taluk, Hassan District, Karnataka State, as detailed in the schedule.
* **Legal Basis:** This action is taken under Section 3(1) of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962.
* **Objection Mechanism:** Any person with interest in the land can object in writing.
* **Objection Deadline:** Objections must be submitted within 21 days from the date the notification copies are available to the general public.
* **Objection Submission:** Written objections should be sent to The Competent Authority SLAO, MangaloreHassanMysoreSolur LPG Pipeline Project, Hindustan Petroleum Corporation Limited, Government of India Enterprises, No. 2711, Kesare 3rd Stage, R.S.Naidunagar, Mysore570007.
Impact Analysis:
Landowners in Hassan Taluk, Hassan District, Karnataka State:
* Impact: Landowners are affected by the proposed acquisition of right of user on their land for the pipeline project.
* Action Required: Landowners who have objections to the acquisition must submit them in writing to the Competent Authority within 21 days of the notification's public availability.
Hindustan Petroleum Corporation Limited (HPCL):
* Impact: HPCL is responsible for laying the Mangalore Hassan Mysore Solur LPG pipeline.
* Action Required: HPCL is required to undertake the pipeline project according to the provisions outlined and address any objections raised during the objection period.
Competent Authority SLAO, MangaloreHassanMysoreSolur LPG Pipeline Project:
* Impact: This authority is responsible for receiving and processing objections to the land acquisition.
* Action Required: The authority must review and address any objections received within the stipulated timeframe.
Key Entities Referenced
Hindustan Petroleum Corporation Limited: A Government of India Enterprise laying the Mangalore Hassan Mysore Solur Pipeline.
Mangalore Hassan Mysore Solur Pipeline: A pipeline project for the transportation of LPG.
Hassan Taluk: A taluk in Hassan District, Karnataka where the pipeline is proposed to be laid.
Hassan District: A district in Karnataka where the pipeline is proposed to be laid.
Karnataka State: The state in India where the pipeline project is located.
Petroleum and Minerals Pipelines Acquisition of Right of User in Land Act, 1962: The act under which the Central Government declares its intention to acquire the right of user in the land for laying the pipeline.
New Delhi: Place of publication of notification
Pawan Kumar: Under Secretary, Ministry of Petroleum and Natural Gas