In exercise of the powers conferred under section 181 1 read with Sections 14, sub Section h of Section 61, Section

Date: 29th February 2024
Category: Extra Ordinary
New Delhi

Read or download the official PDF of this gazette notification issued by the Joint Electricity Regulatory Commission for UT of Jammu & Kashmir and UT of Ladakh on 29th February 2024. Classified under Extra Ordinary.

Official Gazette Notification Text

Official Transcript

रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99 xxxGIDHxxx सी.जी.-जे.के.-अ.-29022024-252484 xxxGIDExxx CG-JK-E-29022024-252484 असाधारण EXTRAORDINARY भाग III—खण् ड 4 PART III—Section 4 प्राजधकार स ेप्रकाजित PUBLISHED BY AUTHORITY स.ं 122] िई ददल्ली, बधु िार, फरिरी 28, 2024/फाल्ग िु 9, 1945 No. 122] NEW DELHI, WEDNESDAY, FEBRUARY 28, 2024/PHALGUNA 9, 1945 सयं ुक्त जिद्यतु जिजियामक...

PolicyIndex Takeaway
Get AI summary →
  • ✓ A Distribution Franchisee Agreement (DFA) framework is established between MGOs and Distribution Licensees.
  • ✓ The regulations are applicable to the entire Union Territory of Jammu & Kashmir and the Union Territory of Ladakh.
  • ✓ The regulations apply to both new and existing micro-grid projects with a capacity between 10 kW and 1000 kW.
  • ✓ Existing micro-grid projects must comply with these regulations, including technical standards and safety measures, within six months of the notification date (February 12, 2024).
  • ✓ The regulations outline various operational models for Micro-Grid Operators (MGOs) to supply electricity in areas not currently served by the grid.