## Policy Analysis Report: Corrigendum to Land Acquisition for Rampurhat Murarai 3rd Line Project
**1. Executive Summary:**
This report analyzes a corrigendum (S.O. 2160 E) issued by the Ministry of Railways, Eastern Railway, pertaining to the land acquisition process for the Rampurhat Murarai 3rd Line Phase-III project in the Birbhum District of West Bengal. The corrigendum modifies Notification No. 792 dated 10.02.2021, addressing errors in land owner information and the total area to be acquired. The key findings indicate corrections to specific plot details and a reduction in the overall acquired land area due to the deletion of a plot.
**2. Introduction:**
This report aims to provide an informative overview of the Corrigendum S.O. 2160 E, issued by the Ministry of Railways, Eastern Railway, concerning land acquisition modifications for the Rampurhat Murarai 3rd Line Phase-III project. The analysis is based solely on the provided policy text.
**3. Policy Overview:**
* **Amendment:** This document is a corrigendum to Notification No. 792 dated 10.02.2021, which itself concerned land acquisition for the Special Railway Project.
* **Core Objective(s) (Inferred):** The core objective of the *corrigendum* is to rectify inaccuracies and inconsistencies in the original land acquisition notification, ensuring accurate records and potentially reducing the scope of land acquisition. This contributes to fairness and legal compliance in the land acquisition process.
**4. Background and Rationale:**
The amendment is likely necessitated by errors discovered in the original land acquisition notification. These errors include inaccuracies in landowner names and incorrect inclusion of a plot slated for acquisition. The need to correct these errors is driven by the importance of accurate land records for fair compensation and legal defensibility of the acquisition process. The rationale behind this amendment is to ensure that only the necessary land is acquired and that landowners are correctly identified.
**5. Key Provisions / Changes:**
This section focuses specifically on the changes introduced by the amendment text:
* **Specific Part of Original Policy Changed:** The amendment modifies the details related to land ownership and area acquisition outlined in Notification No. 792 dated 10.02.2021. It specifically targets information presented in specific serial numbers (SL. No. 2 and SL. No. 5) within the notification.
* **New Rules/Provisions:**
* **SL No. 2 (Police Station Nalhati, MouzaKanior, JL No. 64):**
* **Plot No. 1059:** Deletion of the landowner name "Hasina Mamtaz, Wo Sakil AnsariNalhati".
* **Plot No. 1060:** Deletion of Plot No. 1060 entirely from the acquisition list.
* **Plot No. 1062:** Addition of the landowner name "Abdul Kudrat, So Fajal MallickKaigaria".
* **Plot No. 1056:** Addition of the landowner name "Abdul Tohid, So Fajal Sekh Kaigaria".
* **SL No. 5:** The total corrected area to be acquired is now stated as 9.85078 acres (3.98655 hectares), instead of 9.91325 acres (4.01152 hectares).
* **Difference/Effect of Changes:**
* The landowner name corrections ensure accurate records for compensation and legal purposes.
* The deletion of Plot No. 1060 reduces the overall land area required for the project, likely resulting in lower acquisition costs and less disruption for landowners.
* The total acquired area has been reduced by 0.06247 acres (0.02497 hectares), reflecting the deletion of plot 1060.
**6. Target Audience and Stakeholders:**
The primary target audience and stakeholders directly affected by this amendment include:
* Landowners in the Birbhum District, specifically those associated with Plot Nos. 1059, 1060, 1056, and 1062 in Mouza Kanior, Police Station Nalhati.
* The Eastern Railway Construction Department.
* Government agencies involved in land acquisition and compensation processes.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency:** The Eastern Railway Construction Department, under the authority of the Chief Administrative OfficerCon, is responsible for implementing these changes.
* **Timelines/Procedures:** The amendment references the original notification (No. 792 dated 10.02.2021) and the Railways Amendment Act, 2008, suggesting that the implementation will follow the established procedures outlined in these documents. The date of the corrigendum (April 27, 2021) indicates the effective date for these changes.
* **Amendment-Specific Implementation:** The Eastern Railway Construction Department must update its records to reflect the corrected landowner information and the revised total area to be acquired. They must also ensure that the acquisition process reflects the deletion of Plot No. 1060.
**8. Expected Outcomes / Impact of Changes:**
The likely intended outcomes of these specific changes are:
* **Accurate Land Records:** Ensures that land acquisition records are accurate and reflect the correct ownership and land area.
* **Reduced Acquisition Area:** Lower acquisition costs for the railway project due to the deletion of Plot No. 1060.
* **Fair Compensation:** Ensures that only the rightful owners receive compensation for the acquired land.
* **Legal Compliance:** Reduces the risk of legal challenges to the land acquisition process due to inaccurate information.
* **Improved Stakeholder Relations:** Demonstrates a commitment to transparency and accuracy in the land acquisition process, potentially improving relations with affected landowners.
**9. Conclusion:**
The Corrigendum S.O. 2160 E represents a crucial update to the land acquisition process for the Rampurhat Murarai 3rd Line Phase-III project. By correcting inaccuracies in land ownership and adjusting the total area to be acquired, the amendment promotes fairness, legal compliance, and cost efficiency in the land acquisition process. The changes directly impact landowners in the affected area and highlight the importance of accurate record-keeping in infrastructure projects.
Key Entities Referenced
Rampurhat Murarai 3rd Line PhaseIII: A Special Railway Project for which land acquisition is being carried out.
Birbhum District: The district in the State of West Bengal where the Rampurhat Murarai 3rd Line PhaseIII project is located.
West Bengal: The state in India where the land acquisition for the railway project is taking place.
Railways Amendment Act, 2008: The act under which land acquisition is being carried out.
Eastern Railway: The railway zone responsible for the construction project, with headquarters in Kolkata.
Kolkata: City in West Bengal, location of Eastern Railway headquarters and place of publication of the corrigendum.
Nalhati: Police Station in Birbhum District, West Bengal where land acquisition is taking place.
MouzaKanior: Area of land being acquired under Police Station Nalhati, Birbhum District, West Bengal
V.K. SRIVASTAVA: Chief Administrative OfficerCon, Eastern Railway, Kolkata
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
सी.जी.-डी.एल.-अ.-03062021-227364
xxxGIDHxxx
CG-DL-E-03062021-227364
xxxGIDExxx
असाधारण
EXTRAORDINARY
भाग II—खण् ड 3—उप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 2003] िई दिल्ली, बृहस्ट्प जतर्ार, ििू 3, 2021/ज्य ष्े ठ 13, 1943
No. 2003] NEW DELHI, THURSDAY, JUNE 3, 2021/JYAISTHA 13, 1943
रेल मत्रं ालय
(पर्ू व रेलर्)े
(जिमाणव जर्भाग)
िजु िपत्र
कोलकाता, 27 अप्रलै , 2021
का.आ. 2160(अ).— अजधसूचिा संख्या 792 दििाकं 10.02.2021 के संिोधि में जर्िेष रेलर् े पररयोििा के
जलए भूजम अजधग्रहण की, यािी "रामपरु हाट - मुरारी तीसरी लाइि (चरण- III)" बीरभूम जिले म,ें पजिम बगं ाल राज्य म ें
उप-धारा (I) के 20E तहत रेलर्े (संिोधि) अजधजियम, 2008 भारत के रािपत्र, असाधारण, भाग II खंड 3 उप-खंड (ii)
संख्या 724 दििाकं 22.02.2021 म ें प्रकाजित हुआ ।
A. SL िंबर 2 म,ें पुजलस स्ट्टेिि - िलहटी, मौिा-काजियोर, िेएल िंबर- 64 को जिम्नजलजखत सही करि े के जलए:-
1) प्लॉट िंबर 1059 म,ें भूजम के माजलक का िाम - 20. हसीिा ममताि, पजत-साकील आिसारी-िलहटी को हटाया
िाएगा ( पष्ठृ स ं5) I
2) प्लॉट िंबर 1060 को हटा दिया िाए क्योंदक प्लॉट का अजधग्रहण िहीं दकया िाएगा ( पष्ठृ स ं5) I
2993 GI/2021 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
3) प्लॉट िंबर 1062 म,ें भूजम के माजलक का िाम - अब्िलु कुिरत, जपता- फिल मजल्लक - कागाररया िोडा िाएगा
( पष्ठृ स ं5) I
4) प्लॉट िंबर 1056 म,ें भूजम के माजलक का िाम - अब्िलु तोजहि, जपता- फिल सखे - कैगररया िोडा िाएगा
( पष्ठृ स ं8) I
B. SL िंबर 5 के अंत म,ें कुल सही क्षत्रे 9.85078 एकड/3.98655 हक्े टेयर का अजधग्रहण दकया िाएगा, 9.91325
एकड/ 4.01152 हक्े टेयर ( पृष्ठ स ं11) के बिाय। यह प्लॉट िबं र 1060 को हटािे के कारण ह।ै
[फा. स.ं – म.ु प्र. अ./जि./ भ.ू /306]
र्ी. के. श्रीर्ास्ट्तर्, मुख्य प्रिासजिक अजधकारी/ जिमावण,
पूर्व रेलर्े/ कोलकाता
MINISTRY OF RAILWAsYS
(EASTERN RAILWAY)
(Construction Department)
CORRIGENDUM
Kolkata, the 27th April, 2021
S.O. 2160 (E).— In modification of Notification No. 792 dated 10.02.2021 of Land Acquisition
for Special Railway Project, namely “Rampurhat - Murarai 3rd Line (Phase-III)” in Birbhum District,
in State of West Bengal under sub-section (I) of section 20E of the Railways (Amendment) Act, 2008
published in Gazette of India, Extraordinary, part II section 3 sub-section (ii) vide No. 724 dated
22.02.2021.
A. In SL. No. 2, Police Station- Nalhati, Mouza-Kanior, JL No.- 64 following to be corrected:-
1) In Plot No. 1059, Name of the land owner – 20. Hasina Mamtaz, W/o Sakil Ansari-Nalhati to be
deleted (Page No. 14).
2) Plot No. 1060 to be deleted as the Plot will not be acquired (Page No. 14).
3) In Plot No. 1062, Name of the land owner – Abdul Kudrat, S/o Fajal Mallick-Kaigaria to be added
(Page No. 15).
4) In Plot No. 1056, Name of the land owner – Abdul Tohid, S/o Fajal Sekh – Kaigaria to be added
(Page No. 17).
B. At the end of SL. No. 5, Total corrected area to be acquired 9.85078 acres/3.98655 hectares instead
of 9.91325 acres/4.01152 hectares (Page No. 19). This is due to deletion of Plot No. 1060.
[F. No. CAO/Con/L/306]
V.K. SRIVASTAVA, Chief Administrative Officer/Con,
Eastern Railway/Kolkata.
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.