**Executive Summary**
The Ministry of Railways is implementing safety fencing across 16,398 km of railway tracks to prevent trespassing and enhance operational safety, particularly on routes with speeds exceeding 110 kmph. As of 18 March 2026, significant progress was reported on the ₹209.38 crore Lonavala-Pune-Daund project, which includes the construction of pedestrian subways. This information was formally presented by the Union Minister for Railways in the Lok Sabha to highlight ongoing infrastructure safety measures.
**Key Points / Main Content**
**Infrastructure and Safety Objectives**
* Indian Railways (IR) accords top priority to the safety of train operations by installing safety fencing to prevent trespassing and ensure smooth transit.
* Fencing is specifically mandated for routes where train speeds exceed 110 kmph and at other identified vulnerable locations.
* The project integrates pedestrian subways with safety fencing to facilitate the safe crossing of cattle, pedestrians, and small vehicles across railway alignments.
**Lonavala-Pune-Daund Project Status**
* A dedicated budget of ₹209.38 crore has been sanctioned for safety fencing along the entire Lonavala-Pune-Daund route.
* The project scope involves approximately 290 km of fencing and the construction of associated pedestrian subways.
* The tender for the entire section has been awarded, with 150 km of fencing completed to date.
**Zonal Distribution and Coverage**
* A cumulative total of 16,398 km of safety fencing has been installed across various railway zones.
* The North Central zone leads in coverage with 2,721 km, followed by South Central (2,326 km) and Western (2,257 km).
* Other zones with significant fencing include North Western (1,539 km), West Central (1,415 km), and Central (966 km).
**Impact Analysis**
**Pedestrians and Local Residents**
**Impact**
The safety of residents is improved by physical barriers that prevent accidental or unauthorized track entry, while pedestrian subways provide designated safe crossing points.
**Action Required**
Residents must utilize the provided pedestrian subways rather than attempting to cross tracks directly.
**Indian Railways and Zonal Authorities**
**Impact**
Operational efficiency is protected by reducing accidents involving cattle or unauthorized persons, particularly on high-speed routes.
**Action Required**
Authorities must continue to execute sanctioned works, monitor tender progress for remaining sections, and maintain the 16,398 km of existing fencing.
**Livestock Owners and Small Vehicle Operators**
**Impact**
The provision of fencing and subways reduces the risk of cattle strikes and provides a safer transit route for smaller vehicles that previously crossed tracks at-grade.
**Action Required**
Owners must ensure livestock and vehicles are diverted through the sanctioned pedestrian subways to prevent accidents and damage to railway property.
Key Entities Referenced
Indian Railways: The national railway operator implementing a large-scale safety fencing initiative across 16,398 km of tracks to prevent trespassing and ensure safe operations.
Lonavala-Pune-Daund Route: A primary project location where a ₹209.38 crore work is sanctioned for 290 km of safety fencing and pedestrian subways.
Ashwini Vaishnaw: The Union Minister for Railways who officially presented the status and progress of railway safety infrastructure works.
Lok Sabha: The lower house of India's Parliament where the detailed report on safety fencing and zonal coverage was formally tabled.
Ministry of Railways
Indian Railways Provides Safety Fencing Along
Railway Tracks Across Zones for 16,398 km to
Prevent Trespassing and Ensure Safe Train
Operations
Highest Coverage of Fencing Includes North Central (2,721
km), South Central (2,326 km) and Western (2,257 km)
Railway Zones
Safety Fencing with Pedestrian Subways Progressing on
Lonavala-Pune-Daund Route; 150 km of 290 km Completed
under ₹209.38 crore Sanctioned Work
Posted On: 18 MAR 2026 5:10PM by PIB Delhi
Safety of train operations is accorded top priority on Indian Railways (IR). As one of the important safety
measures, provision of safety fencing has been taken up on routes where the permitted speed of train
operations exceeds 110 kmph, as well as at other vulnerable locations, to prevent trespassing and ensure
safe train operation. Pedestrian subways are also being provided with safety fencing in order to facilitate
crossing of railway alignment by cattle, pedestrians and smaller vehicles.
A work has been sanctioned costing ₹209.38 Cr for providing safety fencing in entire Lonavala-Pune-
Daund route. Work includes construction of approximately 290 Km fencing with pedestrian subways.
Tender has been awarded for entire length of the section and about 150 Km of fencing has been completed
till date.
Zone-wise details of safety fencing provided along Railway tracks till date, are as under:
Zonal Railway Length of fencing provided (in Fencing Km)
Central 966
Eastern 754
East Central 730
East Coast 533Northern 736
North Central 2721
North Eastern 613
Northeast Frontier 153
North Western 1539
Southern 827
South Central 2326
South Eastern 209
South East Central 365
South Western 255
Western 2257
West Central 1415
Total 16398
This information was provided by the Union Minister for Railways, Information & Broadcasting and
Electronics & Information Technology, Shri Ashwini Vaishnaw, in a reply to questions in Lok Sabha
today.
*****
Dharmendra Tewari/ Dr. Nayan Solanki/ Ritu Raj
(Release ID: 2241894) Visitor Counter : 191