### **Summary of the Integrated Processing Development Scheme (IPDS)**
**Overview and Objective**
The Ministry of Textiles has been implementing the Integrated Processing Development Scheme (IPDS) since the 12th Five-Year Plan (FYP). The primary objective of the scheme is to enhance the global competitiveness of the Indian textile industry by adopting environmentally friendly processing standards and technologies. The scheme focuses on addressing pollution in the textile sector by supporting the establishment of new Common Effluent Treatment Plants (CETPs) and the upgradation of existing CETPs in processing clusters and parks.
**Implementation Status**
Active implementation of the scheme concluded in 2021. Currently, the scheme continues solely to fulfill committed liabilities for ongoing projects. Approved parks under the scheme are utilizing advanced technologies, including Zero Liquid Discharge (ZLD) and Multi-Effect Evaporators (MEE), to facilitate the recovery of treated water.
**Project Financials and Progress**
As of March 2026, the total cost for approved projects stands at ₹705.2 crore, with the Government of India (GoI) having released ₹213.02 crore in grants.
| S. No. | Project Name | Location (District, State) | Project Cost (₹ Crore) | GoI Grant Released (₹ Crore) | Status |
| :--- | :--- | :--- | :--- | :--- | :--- |
| 1 | Balotra Water Pollution Control Treatment & RO Pvt Ltd | Barmer, Rajasthan | 131.89 | 62.45 | Nearing Completion |
| 2 | Jasol Water Pollution Control Treatment & RO Pvt Ltd | Barmer, Rajasthan | 38.50 | 14.43 | Nearing Completion |
| 3 | Sanganer Enviro Project Development | Jaipur, Rajasthan | 159.00 | 37.50 | Under Implementation |
| 4 | NextgenTextile Park | Pali, Rajasthan | 129.42 | 6.30 | Under Implementation |
| 5 | Pali Common Effluent Treatment Plant | Pali, Rajasthan | 100.00 | 37.50 | Under Implementation |
| 6 | Gujarat Eco Textile Park | Palsana, Gujarat | 146.39 | 54.84 | Nearing Completion |
| **-** | **TOTAL** | **-** | **705.20** | **213.02** | **-** |
**Administrative Information**
This information was provided by the Minister for Textiles, Shri Giriraj Singh, in a written reply to Lok Sabha (USQ 3915) on March 17, 2026.
Key Entities Referenced
Integrated Processing Development Scheme (IPDS): A government scheme launched to support Common Effluent Treatment Plants (CETPs) and textile processing parks to enhance competitiveness and address environmental pollution.
Ministry of Textiles: The primary ministry responsible for implementing and overseeing the IPDS and its associated infrastructure projects.
12th Five Year Plan (12th FYP): The policy period during which the IPDS was initiated to facilitate environmentally friendly processing standards in the textile sector.
Rajasthan and Gujarat: The primary states where major IPDS projects, including the Balotra, Jasol, Sanganer, and Gujarat Eco Textile Park, are being implemented.
Shri Giriraj Singh: The Minister for Textiles who provided the official update on the status and funding of projects under the scheme.
Ministry of Textiles
INTEGRATED PROCESSING DEVELOPMENT
SCHEME (IPDS)
Posted On: 17 MAR 2026 1:59PM by PIB Delhi
In order to facilitate the Indian Textile Industry to become globally competitive using environmentally
friendly processing standards and technology, and to address the issues of pollution in the textile
processing sector, the Ministry has been implementing Integrated Processing Development Scheme since
12th FYP to support new Common Effluent Treatment Plants (CETP)/ upgradation of CETPs in existing
processing clusters as well as new processing parks. The scheme was under implementation till 2021; after
that the scheme has been continued to meet committed liabilities only.
The details of the projects approved under the scheme and their present status is as below:
(In crore)
S. Name of the Project State District Project GoI Status
No. Cost Grant
Released
1 Balotra Water Pollution Rajasthan Barmer 131.89 62.45 Nearing
Control Treatment & Completion
Reverse Osmosis Private Ltd
2 Jasol Water Pollution Rajasthan Barmer 38.5 14.43 Nearing
Control Treatment & Completion
Reverse Osmosis Private
Limited
3 Sanganer Enviro Project Rajasthan Jaipur 159 37.5 Under
Development Implementation
4 NextgenTextile Park Rajasthan Pali 129.42 6.3 Under
Implementation
5 Pali Common Effluent Rajasthan Pali 100 37.5 Under
Treatment Plant Implementation
6 Gujarat Eco Textile Park Gujarat Palsana 146.39 54.84 Nearing
CompletionTOTAL 705.2 213.02
The parks approved under the Scheme are implementing Zero Liquid Discharge (ZLD) technology.
Another technology being implementing is Multi Effect Evaporator (MEE) which further helps in
recovery of treated water.
This information was provided by THE MINISTER FOR TEXTILES SHRI GIRIRAJ SINGH in a written
reply to a question in Lok Sabha today.
****
MAM/VN
(Lok Sabha USQ 3915)
(Release ID: 2241105) Visitor Counter : 172