UNSTARRED QUESTION NO. 4035
TO BE ANSWERED ON 12.08.2026
CONSTRUCTION OF ROB, WIDENING OF ROAD FOR RISAMA RAILWAY
STATION
†4035. SHRI VIJAY BAGHEL:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the progress of construction works at Amrit Bharat
Station Scheme (ABSS) and the steps taken/being taken by the
Government to complete the works at a fast pace;
(b) the status of approval for construction of a Road Over Bridge (ROB) near
Risama Railway DD-19 in Durg, the widening of the road leading to front
platform of Risama Railway Station and construction of a new road to
the rear platform and proceeding reservation counter and other basic
facilities at Risama Railway stations;
(c) the status of approval for construction of double railway line from Durg
to Ravghat as many passenger trains run late by several hours; and
(d) the status of approval for regular daily operation of three-day-a-week
passenger train no. 78826 (Dallirajhara-Durg) and 78827 (Durg-
Dallirajhara) in Durg-Raoghat section, in view of the increasing number
of passengers?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d) Ministry of Railways has launched Amrit Bharat Station Scheme
for redevelopment of stations with a long-term approach.
This scheme involves preparation of master plans and their implementation
in phases to improve the stations of Indian Railways. The master planning,
keeping in view the necessity of each station, includes:
Page 1 of 13
§● Improvement of access to station and circulating areas
● Integration of station with both sides of city
● Improvement of station building
● Improvement of waiting halls, toilets, sitting arrangement, water
booths
● Provision of wider foot over bridge/subway to commensurate with
passenger traffic
● Provision of lifts/escalators/ramps
● Improvement of platform surface and provision of platform shelter
● Provision of kiosks for local products through schemes like ‘One
Station One Product’
● Parking development
● Amenities for Divyangjans
● Better passenger information systems
● Provision of air concourse, executive lounges, Multimodal integration,
landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions
etc. as per necessity, phasing and feasibility and creation of city centre at
the station in the long term.
So far, 1,340 stations have been identified for development under this
scheme, out of which 32 stations, including Bhilai, Bhilai Nagar, Bhilai
Power House, Durg and Marauda stations of Durg district, are located in
Chhattisgarh. The names of stations identified for development under Amrit
Bharat Station Scheme in Chhattisgarh are as following:
Page 2 of 13State No. of Name of Stations
Stations
Chhattisgarh 32 Akaltara, Ambikapur, Baikunthpur Road, Balod,
Baradwar, Belha, Bhanupratappur, Bhatapara,
Bhilai, Bhilai Nagar, Bhilai Power House,
Bilaspur, Champa, Dallirajhara, Dongargarh,
Durg, Hathbandh, Jagdalpur, Janjgir Naila, Korba,
Mahasamund, Mandir Hasaud, Marauda, Nipania,
Pendra Road, Raigarh, Raipur Jn, Raj Nandgaon,
Sarona, Tilda-Neora, Urkura, Uslapur
Completed Stations of Chhattisgarh:
Development works at railway stations under Amrit Bharat Station Scheme
in Chhattisgarh have been taken up at a good pace. Details of stations
completed in Chhattisgarh are as under:
State No. of Name of stations
stations
Chhattisgarh 10 Ambikapur, Balod, Bhanupratappur, Bhilai,
Champa, Dallirajhara, Dongargarh, Raj Nandgaon,
Sarona, Urkura
Out of above completed stations, Balod, Bhanupratappur and Dallirajhara
are stations of Durg - Rowghat section. The activities for development at
other stations have also been taken up at good pace and progress of some
of the stations is as given below:
Page 3 of 13Stations of Durg district in Chhattisgarh:
Bhilai Nagar station: The works of improvement of station building,
entrance porch, new station building at second entry, improvement of
circulating area, parking, approach road, landscaping, improvement
of platform surface, platform shelters, waiting hall, artwork, new
toilet block, installation of Train Indication Board, signages and CCTV
have been completed. The finishing works have been taken up.
Bhilai Power House station: The works of improvement of station
building at main entry, new station building at second entry, entrance
porch, improvement of circulating area, parking, improvement of
platform surface, 12 m wide foot over bridge, lifts, platform shelters,
entry/ exit gate, water booths and new toilet block have been
completed. The work of escalator has been taken up.
Durg station: The works of new station building at North side, service
building, Railway Protection Force barrack and Railway Protection
Force post, substation building, railway staff quarters, crew lobby
building, overhead water tank, underground water tank and
development of temporary parking have been taken up.
Marauda station: The works of improvement of circulating area,
parking, platform shelters and improvement of platform surface have
been completed. The works of extension of station building, new
toilet block, improvement of drainage and entry/exit gates have been
taken up.
At Risama station of Durg district, located in Chhattisgarh, facilities like
platform shelter, waiting hall, drinking water arrangement, circulating area,
Page 4 of 13seating arrangement, high level platform, etc. are available. The station
approach road leading to the existing Risama station building is sufficient
to cater to present requirements of the station. The work of amenities for
Divyangjan has been completed in recent years. The works of 3 m wide
foot over bridge, platform shelter, new toilet block and new platform have
been taken up.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways including provision of passenger amenities like
approach road, booking counter, etc. is a continuous and ongoing process
and works in this regard are undertaken as per requirement, subject to
inter-se priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on category
of station/condition/traffic handled etc.
Development / Upgradation of railway stations is a complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as tree cutting, heritage, fire clearance, airport clearance
etc. These stations are in operation since long, so brownfield work
challenges are being faced, such as shifting of utilities (involving
water/sewage lines, optical fibre cables, gas pipelines, power/signal
cables, etc.), infringements, operation of trains without hindering
passenger movement, speed restrictions due to works carried out in close
proximity of the tracks and near to high voltage power lines, etc. and these
factors affect the progress of work and completion time.
Road Over Bridge / Road Under Bridge:
Sanctioning of works of Road over Bridge (ROB)/Road under Bridge (RUB) in
lieu of Level crossings (LCs) is a continuous and dynamic process of Indian
Page 5 of 13Railway. Such works are prioritised and taken up on the basis of their
impact on safety in train operations, mobility of trains & impact for road
users and feasibility etc.
No. of ROBs/ RUBs constructed on Indian Railways during the period 2004-
14 vis a vis 2014-26 (Upto May’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-26 (Upto May’26) 14,451 Nos. (192 Nos. in the State of
Chhattisgarh)
As on 01.06.2026, 4,993 Nos. ROBs/ RUBs works are sanctioned at a cost of
approx. ₹ 1,17,492 Cr on Indian Railways including 98 Nos. ROB/RUB works
at a cost of approx. ₹ 1,693 Cr in the state of Chhattisgarh which are at
various stages of planning and execution.
A work for construction of Road Under Bridge (RUB) in lieu of Level
Crossing (LC) Nos. DD-19 (Risama Level Crossing) at Km 889/7-8 has been
sanctioned and the work has been taken up.
Railways have taken several remedial measures to mitigate the problem of
water logging, as under:
Adequate drainage arrangement has been made as integral part of
planning of new RUB/underpasses.
In existing RUBs/underpasses remedial measures like water flow
diversion to nearby bridge and nallahs/drains, provision of cover shed
on approach roads, provision of hump at entry to RUB, provision of
Page 6 of 13cross drains, sealing of joints etc. have been made as per feasibility,
suitability and site requirements.
In addition, pumping arrangement has also been made for identified
RUBs, to drain out water expeditiously in case of emergency and
provision to stop road traffic in exceptional/unusual rainfall situation
for safety of road users.
Completion & commissioning of ROB/RUB works depends on various
factors like cooperation of State Governments in giving consent for
closure of LC, fixing of approach alignment, approval of General
Arrangement Drawing (GAD), land acquisition, removal of encroachment,
shifting of infringing utilities, statutory clearances from various authorities,
law and order situation in the area of project / work sites, duration of
working season in a year for the particular project / area due to climatic
conditions etc. All these factors affect the completion time of the projects
/ works.
Further, Railways have taken following measures to expedite the progress
of work:
i. Joint survey with concerned State Govt./Road Owning Authority is
done before finalizing the General Arrangement Drawing (GAD) to
ensure smooth execution.
ii. Periodic meetings of Railway & State Government officials are done
to resolve various issues related to ROB/RUB works.
iii. Standardization of superstructure and substructure drawings for
various combinations of span, skewness and width of road on the
Railway portion has been done to avoid delays during the design
approval. This has been issued in the form of a compendium, which
Page 7 of 13can be directly adopted for Road Over Bridge across Railway lines for
expeditious planning.
Reservation Counter:
Railway reservation counter facility is already available at Gundardehi
Railway Station at a distance of 07 kms from Risama Railway Station.
In addition, it is also stated that a present more than 88% reserved tickets
are issued online which is also an option to get tickets from anywhere,
anytime. Moreover, Railways has also launched RailOne App on 01.07.2025.
This App enables passengers to book reserved as well as unreserved
tickets on mobile phone. This, in effect, brings the Passenger reservation
system facility to Passenger’s palm.
Rail Connectivity:
To improve the connectivity of Rowghat with Durg, following works have
been sanctioned:
S.No. Name of Works Status
1 Dallirajahra – Rowghat New Project recently completed
Line Project (95 Km)
2 Rowghat – Jagdalpur New Line 249 Ha land out of total 818
Project (140 Km) Ha has been acquired for
the project.
Land acquisition has been
completed in Jagdalpur –
Palli – Kurkanar (12 Km)
Page 8 of 13S.No. Name of Works Status
Section and works on
important major bridges,
RoBs, earthwork, minor
bridges etc. have been
taken up in the section.
Land acquisition work has
been taken up in Rowghat –
Kurkanar (128 Km) Section.
CHHATTISGARH
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Chhattisgarh is as under:
Period Outlay
2009-2014 ₹311 Cr./year
2026-2027 ₹7,470 Cr. (approx. 24 times)
Track Construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Chhattisgarh is as under:
Page 9 of 13New Track Average Commissioning of new
Period
Commissioned tracks
2009-14 32 Km 6.4 Km per year
2014-26 1,311 Km 109.29 Km per year (17 times)
Projects Sanctioned:
As on 01.04.2026, 36 projects (8 New Lines and 28 Doubling), of total
length of 2,398 Km, costing ₹48,202 crore falling fully/partly in the State of
Chhattisgarh are sanctioned. The summary is as under:-
Category No. of Total Length Total Exp upto
projects Length Commissioned till March 2026
(in km) March, 2026 (in Km) (₹ in cr.)
NL 8 887 262 7,535
DL 28 1,512 889 11,298
TOTAL 36 2,398 1,151 18,833
Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in the
state of Chhattisgarh are as under:
S.No. Name of Project Cost (₹ in
cr.)
1 Kharsia-Korichhapar New Line (43 Km) 851
2 Bilaspur-Urkura 3rd line (110 Km) 365
3 Salka Road-Khongsara doubling (26 Km) 181
4 Durg-Rajnandgaon Doubling (31 Km) 250
Page 10 of 13S.No. Name of Project Cost (₹ in
cr.)
5 Khodri-Anuppur Doubling with flyover at Bilaspur (72 792
Km)
6 Champa-Jharsuguda 3rd Line (152 Km) 1,227
7 Pendra Road-Annupur 3rd Line (50 Km) 394
8 Raipur-Titlagarh Doubling (203 Km) 1,171
9 Dallirajahra-Rowghat (95 Km) 1,628
Ongoing Projects:
Some of the major projects falling fully/partly in the State of Chhattisgarh
which have been taken up are as under:
S.N Name of Project Cost
(₹ in cr.)
1 Kharsia-Dharamjaygarh New Line (122 Km) 3,407
2 Gevra Road-Pendra Road New Line (135 Km) 3,724
3 Dharamjaigarh-Korba New Line (63 Km) 1,686
4 Chirimiri-Nagpur Halt New Line (17 Km) 670
5 Sardega-Bhalumunda New Line (37 Km) 1,282
6 Kharsia-Parmalkasa New Double line (278 Km) 7,854
7 Rowghat-Jagdalpur New Line (140 Km) 3,513
8 Kirandul-Jadgalpur Doubling (150 km) 1,780
9 Jagdalpur-Koraput Doubling (107 Km) 1,547
10 Jharsuguda-Bilaspur 4th line (206 Km) 2,596
11 Gevra Rd-Pendra Rd Doubling (135 Km) 3,475
12 Rajnandgaon-Nagpur 3rd line (228 Km) 3,545
13 Boridand-Ambikapur Doubling (80 Km) 1,577
Page 11 of 13S.N Name of Project Cost
(₹ in cr.)
14 Durg-Rajnandgaon 4th line (31 Km) 464
15 Gondia-Dongargarh 4th line (84 Km) 2,223
16 Baikunth-Urkura 4th line (26 Km) 426
17 Champa-Korba 3rd Line (42 Km) 755
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
Presently, Durg-Dallirajhara sector is served by 10 train services which
include 6 daily train services and 02 train services operating on 6-days a
week. These are listed below:
S.No. Train No. & Name
1 78815 Raipur -Antagarh DMU (Daily)
2 78816 Antagarh-Raipur DMU (Daily)
3 78817 Durg-Dalli Rajhara DMU (Daily)
4 78818 Antagarh-Durg DMU (Daily)
5 78824 Durg-Dalli Rajhara DMU (Daily)
Page 12 of 13S.No. Train No. & Name
6 78825 Dalli Rajhara-Durg DMU (Daily)
7 68764 Raipur -Tadoki MEMU (6 days)
8 68765 Tadoki-Raipur MEMU (6 days)
9 78826 Dalli Rajhara-Durg DMU
10 78827 Durg-Dalli Rajhara DMU
Besides, increase in frequency of train service on any route/section is an
on-going process, which depends on various factors including:
Capacity of that section
Availability of path
Availability of required rolling stock
Availability of matching infrastructure for rolling stock
Maintenance requirement of railway tracks and other assets
Occupancy and the traffic requirement of the section.
*****
Page 13 of 13