GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2843
TO BE ANSWERED ON 05.08.2026
ABSS IN BHAGALPUR LOK SABHA CONSTITUENCY, BIHAR
†2843. SHRI AJAY KUMAR MANDAL:
Will the Minister of RAILWAYS be pleased to state:
(a) the name of railway stations selected under the Amrit Bharat Station
Scheme (ABSS) in Bhagalpur Lok Sabha Constituency, Bihar along with
the status of their current progress;
(b) the work being done for development of passenger amenities, Divyang
friendly facilities, escalators, lifts, waiting rooms and parking at
Bhagalpur, Kahalgaon, Pirpainti, Naugachia and other major stations;
(c) the steps taken/being taken by the Government to connect Bhagalpur
railway station with multi-modal transport, smart station facilities and
better rail connectivity; and
(d) the likely impact of these works on tourism, trade, employment and
convenience of passengers in the Bhagalpur region?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Ministry of Railways has identified Bhagalpur, Kahalgaon,
Naugachia, Pirpainti, Sabaur and Shivanarayanpur Railway Stations of
Bhagalpur Lok Sabha Constituency for redevelopment under Amrit Bharat
Station Scheme. The progress at these stations is given below:
Kahalgaon station: The development works have been completed which
includes improvement of station building, entrance porch, improvement of
circulating area, parking, new toilet, improvement of waiting hall,
executive lounge, installation of signages, Train and Coach Indication
Boards and amenities for Divyangjan.
§
Page 1 of 16Sabaur station: The development works have been completed which
includes improvement of station building, entrance porch, improvement of
circulating area, parking, waiting hall, toilet, executive lounge, installation
of Train and Coach Indication Boards and signages.
Shivanarayanpur station: The development works have been completed
which includes improvement of station building, entrance porch,
improvement of circulating area, parking, landscaping, waiting hall, toilets,
lifts, installation of signages, Train and Coach Indication Boards, CCTV and
amenities for Divyangjan.
Pirpainti station: The development works have been completed which
includes extension and improvement of station building, entrance porch,
improvement of circulating area, parking, waiting hall, toilets, executive
lounge, artwork, ceremonial flag, installation of Train and Coach Indication
Boards, signages and amenities for Divyangjan. Additionally, the works of
12 m wide foot over bridge have been taken up.
Naugachia station: The works of new station building, improvement of
circulating area, parking, platform shelters, improvement of platform
surface and new toilet block have been taken up.
Bhagalpur station: In recent years, the works of improvement of station
building, circulating area, platform shelter, platform surface, foot over
bridge, new waiting hall, installation of Train Indication Boards and sewage
treatment plant have been completed. The works of lift and overhead water
tank have been taken up. The work of permanent holding area for crowd
management has been sanctioned.
Further, master planning for redevelopment of Bhagalpur Railway Station
under Amrit Bharat Station Scheme has been taken up. Master planning for
development of Railway stations under 'Amrit Bharat Station Scheme' is an
iterative process requiring optimization.
Page 2 of 16At Kahalgaon, Bhagalpur, Naugachia, Pirpainti, Sabaur and
Shivanarayanpur stations of Bhagalpur Lok Sabha Constituency, amenities
for Divyangjan like station entry ramp, toilet and drinking water booth are
available.
Amrit Bharat Station Scheme envisages development of stations on a
continuous basis with a long-term approach. It involves preparation of
master plans and their implementation in phases to improve the stations of
Indian Railways. The master planning, keeping in view the necessity of
each station, includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/subway to commensurate with
passenger traffic
Provision of lifts/escalators/ramps
Improvement of platform surface/ provision of platform shelter
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking development
Amenities for Divyangjans
Better passenger information systems
Provision of air concourse, executive lounges, Multimodal integration,
landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions
etc. as per necessity, phasing and feasibility and creation of city centre at
the station in the long term.
Page 3 of 16So far, 1340 stations have been identified for development under Amrit
Bharat Station Scheme, out of which 98 stations including Bhagalpur,
Kahalgaon, Naugachia, Pirpainti, Sabaour and Shivanarayanpur railway
stations are located in Bihar. The names of stations identified for
development under Amrit Bharat Station Scheme in Bihar are as following:
State No. of Name of Stations
Stations
Bihar 98 Anugraha Narayan Road, Ara, Arariya Court,
Bakhtiyarpur, Banka, Banmankhi, Bapudham Motihari,
Barahiya, Barauni, Barh, Barsoi Jn, Begusarai, Bettiah,
Bhabua Road, Bhagalpur, Bhagwanpur, Bihar Sharif,
Bihiya, Bikramganj, Buxar, Chakia, Chausa, Chhapra,
Dalsingh Sarai, Darbhanga, Dauram Madhepura, Dehri
On Sone, Dholi, Dighwara, Dumraon, Durgauti, Ekma,
Fatuha, Gaya, Ghorasahan, Guraru, Hajipur Jn,
Jamalpur, Jamui, Janakpur Road, Jaynagar,
Jehanabad, Jhanjharpur, Kahalgaon, Karhagola Road,
Katihar Jn., Khagaria Jn, Kishanganj, Kudra, Labha,
Laheria Sarai, Lakhminia, Luckeesarai, Madhubani,
Maheshkhunt, Mairwa, Mansi Jn, Mashrakh, Mokama,
Motipur, Munger, Muzaffarpur, Nabinagar Road,
Narkatiaganj, Naugachia, Nawadah, Paharpur,
Patliputra, Patna, Piro, Pirpainti, Rafiganj,
Raghunathpur, Rajendra Nagar, Rajgir, Ram Dayalu
Nagar, Raxaul, Sabaur, Sagauli, Saharsa, Sahibpur
Kamal, Sakri, Salauna, Salmari, Samastipur, Sasaram,
Shahpur Patoree, Shivanarayanpur, Simri Bakhtiyarpur,
Simultala, Sitamarhi, Siwan, Sonpur Jn., Sultanganj,
Supaul, Taregna, Thakurganj, Thawe
Page 4 of 16Completed Stations:
Development works at railway stations under Amrit Bharat Station Scheme
in Bihar have been taken up at a good pace. The stations completed in
Bihar are as under:
State No. of Name of stations
stations
Bihar 8 Banmankhi, Dauram Madhepura, Kahalgaon,
Pirpainti, Sabaur, Shivanarayanpur, Simultala, Thawe
The activities for development at other stations in Bihar have also been
taken up at good pace and progress of some of the stations is as given
below:
Gaya station: The work of new second entry arrival building has been
completed. The works of new second entry departure building, main
entry new arrival & departure building, new platform no. 8, new
platform shelters, air concourse and improvement of circulating area
have been taken up.
Muzaffarpur station: The work of combined terminal building, 3 m
wide skywalk (north side), booking counter and office buildings have
been completed. The work of main station building (phase-I), elevated
road, arrival terminal building, departure terminal building, multi-level
car parking, 6m wide skywalk (south side), 18 m wide foot over bridge
and sewage treatment plant have been taken up.
Kishanganj station: The works of platform surfacing at platform no.
1&2, drinking water taps at platform no. 1&2, improvement of
circulating area, parking at second entry, approach road and
Page 5 of 16boundary wall have been completed. The works of platform shelter
and 12 m Foot Over Bridge have been taken up.
Bapudham Motihari station: The works of new East side station
building, West side station building, arrival building, parcel office,
coolie room, GRP office, telecom building, substation building, new air
concourse and light Road Over Bridge have been taken up.
Sitamarhi station: The works of temporary booking office, parcel
building and coolie rest room have been completed. The works of new
second entry station building, main entry station building, overhead
water tank and underground water tank have been taken up.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on category
of station/condition/traffic handled etc.
Escalators and lifts at railway stations are provided as per extant policy
depending upon techno-economic feasibility and inter-se priority of the
stations. So far, 04 escalators and 10 lifts have been provided at various
railway stations in Bhagalpur Lok Sabha Constituency of Bihar.
Trains Serving Bhagalpur:
Indian Railways (IR) constantly endeavours to improve connectivity
for the travelling passengers and accordingly to facilitate the passengers
of Bhagalpur, IR have introduced 63411/63412 Sahibganj-Bhagalpur MEMU
w.e.f. 01.01.2026.
Page 6 of 16Accordingly, at present, Bhagalpur station is served by 108 train
services including 22309/22310 Howrah-Jamalpur Vande Bharat Express.
The list of train services serving Bhagalpur station is as under:-
SN Train No. & Name
1 12253 SMVT Bengaluru - Bhagalpur Express
2 12254 Bhagalpur - SMVT Bengaluru Express
3 12335 Bhagalpur - Lokmanya Tilak (T) Express
4 12336 Lokmanya Tilak (T) - Bhagalpur Express
5 12349 Godda - New Delhi Express
6 12350 New Delhi - Godda Express
7 12367 Bhagalpur - Anand Vihar (T) Express
8 12368 Anand Vihar (T) - Bhagalpur Express
9 13015 Howrah - Jamalpur Express
10 13016 Jamalpur - Howrah Express
11 13023 Howrah - Gaya Express
12 13024 Gaya - Howrah Express
13 13031 Howrah - Jaynagar Express
14 13032 Jaynagar - Howrah Express
15 13071 Howrah - Jamalpur Express
16 13072 Jamalpur - Howrah Express
17 13229 Godda - Rajendra Nagar (T) Express
18 13230 Rajendra Nagar (T) - Godda Express
19 13235 Sahibganj - Danapur Express
20 13236 Danapur - Sahibganj Express
21 13241 Banka - Rajendra Nagar (T) Express
22 13242 Rajendra Nagar (T) - Banka Express
23 13333 Dumka - Patna Express
24 13334 Patna - Dumka Express
25 13401 Bhagalpur - Danapur Express
Page 7 of 1626 13402 Danapur - Bhagalpur Express
27 13403 Ranchi - Bhagalpur Express
28 13404 Bhagalpur - Ranchi Express
29 13409 Malda Town - Kiul Express
30 13410 Kiul - Malda Town Express
31 13415 Malda Town - Patna Express
32 13416 Patna - Malda Town Express
33 13419 Bhagalpur - Muzaffarpur Express
34 13420 Muzaffarpur - Bhagalpur Express
35 13423 Bhagalpur - Ajmer Express
36 13424 Ajmer - Bhagalpur Express
37 13429 Malda Town - Anand Vihar (T) Express
38 13430 Anand Vihar (T) - Malda Town Express
13435 Malda Town - Gomti Nagar Amrit Bharat
39
Express
13436 Gomti Nagar - Malda Town Amrit Bharat
40
Express
41 14003 Malda Town - New Delhi Express
42 14004 New Delhi - Malda Town Express
43 15089 Godda - Gomti Nagar Express
44 15090 Gomti Nagar - Godda Express
45 15097 Bhagalpur - Jammu Tawi Express
46 15098 Jammu Tawi - Bhagalpur Express
47 15553 Bhagalpur - Jaynagar Express
48 15554 Jaynagar - Bhagalpur Express
49 15619 Gaya - Kamakhya Express
50 15620 Kamakhya - Gaya Express
51 15625 Deoghar - Agartala Express
52 15626 Agartala - Deoghar Express
Page 8 of 1653 15647 Lokmanya Tilak (T) - Guwahati Express
54 15648 Guwahati - Lokmanya Tilak (T) Express
55 15657 Delhi - Kamakhya Express
56 15658 Kamakhya - Delhi Express
57 15733 Balurghat - Bathinda Express
58 15734 Bathinda - Balurghat Express
59 15743 Balurghat - Bathinda Express
60 15744 Bathinda - Balurghat Express
61 15925 Deoghar - Dibrugarh Express
62 15926 Dibrugarh - Deoghar Express
63 18185 Tatanagar - Godda Express
64 18186 Godda - Tatanagar Express
65 18603 Ranchi - Godda Express
66 18604 Godda - Ranchi Express
67 20501 Agartala - Anand Vihar (T) Rajdhani Express
68 20502 Anand Vihar (T) - Agartala Rajdhani Express
69 20507 Sairang - Anand Vihar (T) Rajdhani Express
70 20508 Anand Vihar (T) - Sairang Rajdhani Express
71 22309 Howrah - Jamalpur Vande Bharat Express
72 22310 Jamalpur - Howrah Vande Bharat Express
73 22311 Godda - Lokmanya Tilak (T) Express
74 22312 Lokmanya Tilak (T) - Godda Express
22405 Bhagalpur - Anand Vihar (T) Garib Rath
75
Express
22406 Anand Vihar (T) - Bhagalpur Garib Rath
76
Express
77 22947 Surat - Bhagalpur Express
78 22948 Bhagalpur - Surat Express
79 53029 Azimganj - Bhagalpur Passenger
Page 9 of 1680 53030 Bhagalpur - Azimganj Passenger
81 53403 Rampur Hat - Gaya Passenger
82 53408 Jamalpur - Rampur Hat Passenger
83 53415 Sahibganj - Jamalpur Passenger
84 53416 Jamalpur - Sahibganj Passenger
85 53441 Deoghar - Jamalpur Passenger
86 53442 Jamalpur - Deoghar Passenger
87 63411 Sahibganj - Bhagalpur MEMU
88 63412 Bhagalpur - Sahibganj MEMU
89 63431 Sahibganj - Jamalpur MEMU
90 63432 Jamalpur - Sahibganj MEMU
91 73401 Godda - Bhagalpur DMU
92 73402 Bhagalpur - Godda DEMU
93 73419 Sahibganj - Bhagalpur DEMU
94 73420 Bhagalpur - Sahibganj DEMU
95 73429 Bhagalpur - Jamalpur DEMU
96 73430 Jamalpur - Bhagalpur DEMU
97 73435 Bhagalpur - Jamalpur DEMU
98 73436 Jamalpur - Bhagalpur DEMU
99 73441 Hansdiha - Bhagalpur DEMU
100 73442 Bhagalpur - Hansdiha DEMU
101 73443 Hansdiha - Bhagalpur DEMU
102 73444 Bhagalpur - Hansdiha DEMU
103 73445 Hansdiha - Bhagalpur DEMU
104 73446 Bhagalpur - Hansdiha DEMU
105 73447 Banka - Bhagalpur DEMU
106 73448 Bhagalpur - Banka DEMU
107 73449 Banka - Bhagalpur DEMU
108 73450 Bhagalpur - Banka DEMU
Page 10 of 16Besides, introduction of train services, which is an on-going process,
depends on various factors which include-
● Capacity of that section.
● Availability of path.
● Availability of required rolling stock.
● Availability of matching infrastructure for rolling stock.
● Maintenance requirement of railway tracks and other assets.
● Occupancy and the traffic requirement of the section.
Improving connectivity of Bhagalpur:
To improve connectivity at Bhagalpur railway station, following
works/surveys have been taken up:
S NO. Project Status
1 Pirpainti-Bhagalpur Project has been
doubling (51 Km) commissioned.
2 Bhagalpur-Dumka- Project has been sanctioned
Rampurhat doubling (177 recently at a cost of ₹3,169 Cr.
Km)
3 Bhagalpur Byepass line Project has been sanctioned
(13.38 Km) recently at a cost of ₹303 Cr.
4 Bhagalpur-Jamalpur 3rd Project has been sanctioned
Line (53Km) recently at a cost of ₹1156 Cr.
5 Bhagalpur-Barharwa 3rd & DPR has been Prepared.
4th line (128 Km)
6 Bhagalpur-Jamalpur 4th FLS has been sanctioned for
Line (53Km) preparation for DPR.
Page 11 of 16After firming up of Detailed Project Report (DPR), sanctioning of project
requires consultation with various stake-holders including State
Governments and necessary approvals viz. appraisal of NITI Aayog,
Ministry of Finance etc. As sanctioning of projects is a continuous and
dynamic process, exact timelines depend upon appraisals and approvals by
various stakeholders.
Bihar:
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects falling fully/partly in the Bihar is as
under:-
Period Outlay
2009- ₹1,132 Cr./year
14
2026- ₹10,379 Cr. (More than 9 times)
27
Track construction:
The details of commissioning/ laying of new track falling fully/partly in the
State of Bihar is as under:-
Period New Track Average Commissioning of new
Commissioned tracks
2009- 318 Km 63.6 Km/year
14
2014- 2,034 Km 169.5 Km/year (More than 2.5
26 times)
Page 12 of 16Projects sanctioned:
As on 01.04.2026, 59 projects (32 New Lines, 01 Gauge Conversions and 26
Doubling), covering a total length of 5,067 km, costing ₹96,651 crore, falling
fully/partly in Bihar are sanctioned. The summary is as under:-
Category No of Total Length Total Exp
sanction Lengt Commis upto Mar'26
ed h sioned (₹ in Cr)
Projects (in till
Km) Mar'26
(in Km)
New 32 2,616 533 14,806
Lines
Gauge 1 69 52 544
Conversio
n
Doubling/ 26 2,382 465 14,509
Multi-
tracking
Total 59 5,067 1,050 29,860
Recently completed projects:
Details of some of the recently completed projects falling fully/partly in
Bihar are as under:-
Cost (₹
SN. Project
in Cr)
1 Patna bridge (28 Km) 3,310
2 Munger rail cum road Bridge (15 Km) 3,040
3 Kosi Bridge (22 Km) 863
4 Daniawan-Biharsharif new line (38 Km) 354
5 Chandan-Banka new line (40 Km) 496
6 Rampurhat-Mandarhill new line (130 Km) 908
Page 13 of 167 Maharajganj-Masrakh new line (35 Km) 412
8 Rajgir-Tilaiya & Natesar-lslampur new line (67 Km) 726
9 Jaynagar-Narkatiaganj gauge conversion (260 Km) 967
10 Kaptanganj-Chhapra gauge conversion (234 Km) 819
11 Sakri-Nirmali, Saharasa-Forbesganj gauge conversion 2,113
(206 Km)
12 Mansi-Saharsa, Saharsa-Purnia, Banmakhi- Bihariganj 752
gauge conversion (169 Km)
13 Sahibganj-Pirpainti doubling (23 Km) 129
14 Maheshkunt-Thanabihpur doubling (32 Km) 115
15 Hajipur-Ramdayalu Nagar doubling (48 Km) 367
16 Pirpainti-Bhagalpur doubling (51 Km) 493
17 Kiul-Gaya doubling (124 Km) 2,462
18 Hajipur-Bachwara doubling (72 Km) 930
19 Araria-Galgalia (Thakurganj) new line (110 Km) 2,132
20 Samastipur-Darbhanga Doubling (38 Km) 874
Ongoing projects:
Some of the projects falling fully/partly in the State of Bihar which have
been taken up are as under:
SN. Project Cost
(Rs. in
Cr.)
1 Sakri-Hasanpur new line (76 Km) 802
2 Fatuha-lslampur new line (167 Km) 3,158
3 Koderma-Tilaiya new line (65 Km) 2,287
4 Hajipur-Sagauli new line (151 Km) 2,820
5 Araria-Supaul new line (96 Km) 2,170
6 Kursela-Bihariganj new line (58 Km) 194
7 Pirpainti-Jassidih new line (97 Km) 2,700
8 Chhitauni-Tumkuhi Road new line (59 Km) 1,881
9 Jalalgarh-Kishanganj new line (51 Km) 407
Page 14 of 1610 Sitamarhi-Nirmali new line (189 Km) 2,833
11 Bihta-Aurangabad new line (120 Km) 3,606
12 Gaya-Chatra and Gaya-Natesar new line (135 Km) 4,543
13 Sultanganj-Katuria new line (77 Km) 291
14 Jaynagar-Bijalpura Gauge conversion (69 Km) 900
15 Dhanbad-Sonnagar 3rd line (291 Km) 7,906
16 Sagauli-Valmikinagar Doubling (110 Km) 1,456
17 Muzaffarpur-Sugauli Doubling (101 Km) 1,745
18 Barauni-Bachwara 3rd & 4th line (32 Km) 486
19 Narkatiaganj-Darbhanga, Sitamarhi-Muzaffarpur 4,080
doubling (256 Km)
20 Chhapra-Ballia Patch Doubling (65 Km) 1,046
21 Katihar-Kumedpur and Katihar-Mukuria Doubling 943
(65 Km)
22 Son Nagar-Andal Multitracking (749 Km) 12,334
23 Punarakh- Bhaktiyarpur New 4th line & balance 422
3rd line (28 Km)
24 Aluabari Road-Thakurganj Doubling (20 Km) 327
25 Bhagalpur-Jamalpur 3rd line (53 Km) 1,156
26 Bhagalpur-Dumka-Rampurhat doubling (177 Km) 3,169
27 Bakhtiyarpur-Rajgir-Tilaiya doubling (104 Km) 2,192
28 Bakthiyarpur-Fatuha 3rd and 4th line (24 Km) 931
29 Punarakh-Kiul 3rd and 4th line (50 Km) 2,668
30 Kiul-Jhajha 3rd Line (54 Km) 962
31 Mansi-Saharsa doubling (44 Km) 499
Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
Sanction of any railway project depend upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the proposed
route
Page 15 of 16 First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives,
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Improvement of railway infrastructure has a multiplier effect on the
economy with increased job creation and improved economic growth.
*****
Page 16 of 16