GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 4251
TO BE ANSWERED ON 18.03.2026
ABSS IN MUMBAI-GUJARAT BELT OF WESTERN RAILWAY
†4251. SHRI PATEL UMESHBHAI BABUBHAI:
Will the Minister of RAILWAYS be pleased to state:
(a) the reasons for the abnormal increase in the initial sanctioned cost,
revised cost and actual expenditure of the stations being
redeveloped under the Amrit Bharat Station Scheme in the Mumbai-
Gujarat belt of Western Railway;
(b) whether any inquiry into this cost escalation has been conducted by
the Central Vigilance Commission (CVC), the Comptroller and Auditor
General (CAG)/any other independent agency and if so, the details
thereof;
(c) whether it is a fact that crucial contracts (such as for FOBS, CCTVs
and Signalling) in Western Railways have been awarded only to
select groups of contractors during the last five years and if so, the
details of the complaints received regarding restrictive tender
eligibility conditions and limited competition;
(d) whether any vigilance inquiry has been conducted in this regard and
if so, the details thereof; and
(e) the number of cases that have come to light in Western Railway
regarding payments made without completion of work along with
§designations of the officials involved and the disciplinary action
taken against them?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e) Modernisation / Upgradation of stations on Indian Railways is a
continuous and ongoing process and works in this regard are undertaken
as per requirement, subject to inter-se priority and availability of funds.
Development / redevelopment / upgradation / modernisation of a station
is carried out based on category of station / condition / traffic handled
etc.
Ministry of Railways has launched Amrit Bharat Station Scheme for
redevelopment of stations with a long-term approach. The scheme
involves preparation of master plans and their implementation in phases.
The redevelopment / upgradation of stations is essentially a phased and
continuous process due to brownfield project challenges and handling of
passengers and trains without undue adverse impact. The phasing of
projects accordingly may result in sanctions at different stages for
various components. The sanctions do take in account the works
previously executed at the stations, the presently sanctioned works etc.
Indian Railways has a well established mechanism to monitor
implementation of projects including their reviews, inspection, check for
quality of works and audits. Works are carried out adhering to thestandards and specifications laid down in various codes and manuals.
Inspections/audits/checks are carried out from time to time by various
agencies/officials/multi-disciplinary teams as per laid down instructions
and actions for correction including damages are taken immediately.
This is a continuous and ongoing process.
Representations / suggestions, both formal and informal for Railway
projects / works across the country are received on the basis of
demands raised by State Governments, Members of Parliament,
Ministries of Central Government, elected representatives, Railways'
own requirements, organizations / rail users etc., at various levels
including Railway Board, Zonal Railways, Division Office etc. Receipt of
such suggestions / representations is a continuous and dynamic process
and these are examined and action as found feasible and justified is
taken from time to time.
Vigilance organisations of Western Railway and Railway Board have not
received complaints regarding the issues referred in the question and no
inquiry has been conducted by these units in the said projects.
Tenders in railway are floated as per Railways laid down provisions.
Complaints if any, are investigated and disposed off as per guidelines
and laid down procedure of Central Vigilance Commission (CVC).
So far, 1338 stations have been identified for development under this
scheme, out of which 87 stations are located in Gujarat and 132 stations
are located in Maharashtra. The names of stations identified for
development under Amrit Bharat Station Scheme in Gujarat and
Maharashtra are as following:No. of
State Name of Stations
Stations
Gujarat 87 Ahmedabad, Anand, Ankleshwar, Asarva,
Bardoli, Bhachau, Bhaktinagar, Bhanvad,
Bharuch, Bhatiya, Bhavnagar, Bhestan, Bhildi,
Bilimora (NG), Bilimora Jn, Botad Jn.,
Chandlodia, Chorvad Road, Dabhoi Jn, Dahod,
Dakor, Derol, Dhrangadhra, Dwarka,
Gandhidham, Godhra Jn, Gondal, Hapa,
Himmatnagar, Jam Jodhpur, Jamnagar,
Jamwanthali, Junagadh, Kalol, Kanalus Jn.,
Karamsad, Keshod, Khambhaliya, Kim, Kosamba
Jn., Lakhtar, Limbdi, Limkheda, Mahemadabad&
Kheda road, Mahesana, Mahuva, Maninagar,
Mithapur, Miyagam Karjan, Morbi, Nadiad,
Navsari, New Bhuj, Okha, Padadhari, Palanpur,
Palitana, Patan, Porbandar, Pratapnagar, Rajkot,
Rajula Jn., Sabarmati (BG & MG), Sachin,
Samakhiyali, Sanjan, Savarkundla, Sayan,
Siddhpur, Sihor Jn., Somnath, Songadh, Surat,
Surendranagar, Than, Udhna, Udvada, Umargaon
Road, Unjha, Utran, Vadodara, Vapi, Vatva,
Veraval, Viramgam, Vishvamitri Jn., Wankaner.
Maharashtra 132 Ahmednagar, Ajni (Nagpur), Akalkot Road, Akola,
Akurdi, Amalner, Amgaon, Amravati, Andheri,
Badnera, Balharshah, Bandra Terminus,
Baramati, Belapur, Bhandara Road, Bhokar,
Bhusawal, Borivali, Byculla, Chalisgaon, ChandaNo. of
State Name of Stations
Stations
Fort, Chandrapur, Charni Road, Chhatrapati
Sambhajinagar, Chhatrapati Shivaji Maharaj
Terminus, Chinchpokli, Chinchwad, Dadar (CR),
Dadar (WR), Dahisar, Daund, Dehu Road, Devlali,
Dhamangaon, Dharangaon, Dharashiv,
Dharmabad, Dhule, Diva, Dudhani, Gangakher ,
Godhani, Gondia, Grant Road, Hadapsar,
Hatkanangale, Hazur Sahib Nanded,
Himayatnagar, Hinganghat, Hingoli Deccan,
Igatpuri, Jalgaon, Jalna, Jeur, Jogeshwari,
Kalyan Jn, Kamptee, Kandivali, Kanjur Marg,
Karad, Katol, Kedgaon, Kinwat , Kopargaon,
Kurduwadi Jn, Kurla Jn, Lasalgaon, Latur,
Lokmanya Tilak Terminus, Lonand Jn, Lonavla,
Lower Parel, Malad, Malkapur, Manmad Jn,
Manwath Road, Marine Lines, Matunga, Miraj Jn,
Mudkhed Jn, Mumbai Central, Mumbra,
Murtizapur Jn, Nagarsol, Nagpur Jn, Nandgaon,
Nandura, Nandurbar, Narkher Jn, Nashik Road,
Netaji Subhash Chandra Bose Itwari Junction,
Pachora Jn, Palghar, Pandharpur, Panvel Jn,
Parbhani Jn, Parel, Parli Vaijnath, Partur,
Phaltan, Prabhadevi, Pulgaon Jn, Pune Jn, Purna
Jn, Raver, Rotegaon, Sainagar Shirdi, Sandhurst
Road, Sangli, Satara, Savda, Selu, Sewagram,
Shahad, Shegaon, Shivaji Nagar Pune, ShriNo. of
State Name of Stations
Stations
Chhatrapati Shahu Maharaj Terminus Kolhapur,
Solapur, Talegaon, Thakurli, Thane, Titvala,
Tumsar Road, Umri, Uruli, Vadala Road,
Vidyavihar, Vikhroli, Wadsa, Wardha, Washim,
Wathar
Completed Stations:
Development works at railway stations under Amrit Bharat Station
Scheme in Gujarat and Maharashtra have been taken up at a good pace.
Details of stations completed in Gujarat and Maharashtra are as under:
No. of
State Name of stations
stations
Gujarat 21 Dakor, Derol, Godhra Jn, Hapa, Jam Jodhpur,
Jam Wanthali, Kanalus Jn, Karamsad,
Khambhaliya, Kosamba Jn, Limbdi, Mahuva,
Mithapur, Morbi, Okha, Palitana, Porbandar,
Rajula Jn, Samakhiyali, Sihor Jn., Utran
Maharashtra 17 Amgaon, Baramati, Chanda Fort, Chinchpokli,
Devlali, Dhule, Kedgaon, Lasalgaon, Lonand Jn,
Matunga, Murtizapur Jn, Nandura, Netaji
Subhash Chandra Bose Itwari Junction, Parel,
Savda, Shahad, Vadala RoadThe activities for development at other stations have also been taken up
at good pace and progress of some of the stations is as given below:
Gujarat:
Himmatnagar station: The works of new station building,
improvement of existing station building, water booth, toilet,
circulating area, parking and 12 m Foot Over Bridge have been
taken up.
Dahod station: The works of improvement of station building,
porch, platform surfacing of platform no. 1, improvement of booking
counter, waiting hall, waiting room, pay and use toilet, circulating
area, entry/exit gate and signages have been completed. The work
of 12 m Foot Over Bridge has been taken up.
Limkheda station: The works of new station building, raising of
platform no. 1 & 2, improvement of platform surface, toilet at
platform no. 1 & 2/3, improvement of circulating area and entry/exit
gate have been completed. The works of signages and 6 m Foot
Over Bridge have been taken up.
Asarva station: The works of new station building, porch, new
waiting room, booking counter and toilet block have been
completed. The works of new platform shelter, platform surfacing,
circulating area, parking, Divyangjan facilities and finishing work of
concourse area have been taken up.Maharashtra:
Palghar station: The works of new platform shelter at platform no.
2/3, platform surfacing, new coping blocks and tactile tile work at
platform no. 4 have been completed. The works of utility shifting
and 12 m Foot Over Bridge have been taken up.
Diva station: The works of improvement of station building,
circulating area and parking on East side, new entry gate, platform
raising and flooring of platform no. 5/6 and 7/8, platform shelter at
platform no. 7/8, new toilet block, sewage treatment plant on West
side, improvement of Foot Over Bridge at Kalyan end and Mumbai
end have been completed. The work of new 6 m Foot Over Bridge
has been taken up.
Mumbra station: The works for improvement of platform surface,
seating arrangement, new toilet block, improvement of booking
office, circulating area, sewage treatment plant and flooring of
Foot Over Bridge have been completed. The work of escalator has
been taken up.
Titwala station: The works for station building, entrance gate,
platform surfacing, improvement of ticket booking office, toilet
block, sewage treatment plant, improvement of two wheeler
parking and approach road on East and West side have been
completed. The work of new 6 m Foot Over Bridge has been taken
up.Master plans include the following:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/air concourse commensurate
with passenger traffic
Provision of lift/escalators/ramp
Improvement /Provision of platform surface and cover over
platforms
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking areas, Multimodal integration
Amenities for Divyangjans
Better passenger information systems
Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at each
station.
Amrit Bharat Station Scheme also envisages sustainable and
environment friendly solutions, provision of ballastless tracks etc. as per
necessity, phasing and feasibility and creation of city centre at the
station in the long term.
Development / Upgradation of railway stations is complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as fire clearance, heritage, tree cutting, airportclearance etc. The progress also gets affected due to brownfield related
challenges such as shifting of utilities (involving water/sewage lines,
optical fibre cables, gas pipe lines, power/signal cables, etc.),
infringements, operation of trains without hindering passenger
movement, speed restrictions due to works carried out in close
proximity of tracks and high voltage power lines, etc. and these factors
affect the completion time.
Development / Upgradation / Modernization of stations including Amrit
Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation and expenditure under
Plan Head-53 are maintained Zonal Railway-wise and not work-wise or
station-wise or state-wise.
Gujarat is covered under the jurisdiction of two railway zones, namely,
North Western Railway and Western Railway. For these zones, an
allocation of ₹ 2,081 crore has been made for the financial year 2025-26,
out of which an expenditure of ₹ 2,089 crore (up to February, 2026) has
been incurred so far.
Maharashtra is covered under the jurisdiction of four railway zones,
namely, Central Railway, South Central Railway, South East Central
Railway and Western Railway. For these zones, an allocation of ₹ 3,834
crore has been made for the financial year 2025-26, out of which an
expenditure (up to February, 2026) of ₹ 3,886 crore has been incurred so
far.
*****