GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 2510
ANSWERED ON 13.03.2026
ADDITIONAL BUDGETARY SUPPORT FOR RAILWAY INFRASTRUCTURE PROJECTS IN
ODISHA
2510 SHRI NIRANJAN BISHI:
Will the Minister of RAILWAYS be pleased to state:
(a) whether Government proposes to allocate additional budgetary support for railway infrastructure
projects in Odisha in the financial year 2026–27; and
(b) if so, the details thereof and if not, the reasons therefor?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) and (b):
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure
projects and safety works, falling fully/partly in the State of Odisha is as under:
Period Outlay
2009-14 ₹ 838 Cr./year
2025-26 ₹ 10,599 Cr. (Nearly 13 times)
Track Construction:
The details of commissioning/laying of new track falling fully/partly in the State of Odisha during
2009-14 and 2014-25 is as under:
Period New Track Commissioned Average Commissioning of new tracks per year
2009-14 267 Km 53 Km
2014-25 2,150 Km 195 Km
(More than 3.5 times)
Project Sanctioned:
As on 01.04.2025, 49 projects (19 New Lines and 30 Doubling), of a total length of 4,010 Km, costing
₹ 67,496 crore, falling fully/partly in Odisha, are sanctioned, out of which 1,429 km length has been
commissioned and an expenditure of ₹28,043 crore has been incurred upto March’ 2025. The summary
is as under:-
.…2/-
§-2-
Length
No of Total Length Total Exp upto
Commissioned till
Category sanctioned NL/GC/DL Mar'25
Mar'25
Projects (in Km) (₹ in Cr)
(in Km)
New Lines 19 1,544 256 6,270
Doubling/Multi-
30 2,466 1,173 21,773
tracking
Total 49 4,010 1,429 28,043
Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in Odisha are as under:
S. No. Name of Project Cost
(In Crores of ₹)
Daitari-Banspani New Line and Jakhapura-Haridaspur 3rd Line
1 1,317
(179 Km)
2 MCL siding from Jharsuguda - Sardega New Line (53 Km) 1,598
3 Haridaspur-Paradeep New Line (82 Km) 2,397
4 Angul-Sukinda New Line (104 Km) 2,834
5 Champa-Jharsuguda 3rd Line (152 Km) 1,227
6 Sambalpur-Titlagarh Doubling (182 Km) 2,262
7 Rourkela-Jharsuguda 3rd Line (101 Km) 1,313
8 Banspani-Daitari-Tomka-Jakhapura Doubling (164 Km) 1,827
9 Sambalpur-Talcher Doubling (174 Km) 1,539
10 Raipur - Titlagarh Doubling (203 Km) 1,171
11 Jharsuguda-Sardega Doubling (50 Km) 3,200
Ongoing Projects:
Further, some of the main projects falling fully/partly in Odisha which have been taken up are as under:
S.No. Name of Project Total Cost
(In Crores of ₹)
1 Junagarh-Nabarangpur New Line (116 Km) 2,865
2 Nabarangpur-Jeypore New Line (41 Km) 748
3 Jeypore-Malkangiri New Line (130 Km) 2,344
4 Malkangiri – Pandurangapuram New Line (174 Km) 3,592
5 Buramara-Chakulia New Line (60 Km) 1,459
6 Gunupur-Therubali New Line (74 Km) 1,166
7 Puri - Konark New Line (32 Km) 492
8 Badampahar-Kendujhargarh New Line (82 Km) 1,876
9 Bangriposi-Gorumahisani New Line (86 Km) 2,269
10 Bargarh Road-Nawapara Road New Line (138 Km) 2,622
11 Vizianagram-Titlagarh 3rd Line (265 Km) 6,996
….3/-
§-3-
S.No. Name of Project Total Cost
(In Crores of ₹)
12 Jarapada- Budhapank 3rd & 4th Line with flyover at Talcher (101 810
Km)
13 Budhapank- Salegaon via Rajatgarh 3rd & 4th Line (170 Km) 2,023
14 Nergundi - Vizianagaram 3rd Line (385 Km) 4,963
15 Kottavalasa-Koraput Doubling (189 Km) 2,500
16 Koraput-Singapur Road Doubling (165 Km) 2,362
17 Jagdalpur-Koraput Doubling (107 Km) 1,547
18 Jharsuguda-Bilaspur 4th line (206 Km) 2,596
19 Bondamunda-Ranchi Doubling (159 Km) 3,029
20 Narayangarh-Bhadrak 3rd line (153 Km) 2,136
21 Bhadrak-Nergundi 3rd Line (92 Km) 1,284
Completion of Railway project/s depends on various factors which include the following:
Land acquisition
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****
§