See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 503
TO BE ANSWERED ON 03.12.2025
AMRIT BHARAT STATION SCHEME FOR MAHARASHTRA
503. SMT. SUPRIYA SULE:
SHRI MOHITE PATIL DHAIRYASHEEL RAJSINH:
DR. AMOL RAMSING KOLHE:
PROF. VARSHA EKNATH GAIKWAD:
SHRI SANJAY DINA PATIL:
SHRI BHASKAR MURLIDHAR BHAGARE:
Will the Minister of RAILWAYS be pleased to state:
(a) the objectives and scope of the Amrit Bharat Station Scheme and the
manner in which it differs from other station redevelopment initiatives
undertaken by Railways;
(b) the total number of railway stations identified in Maharashtra under
the Amrit Bharat Station Scheme and the Station Redevelopment
Programme separately, along with the names of these stations;
(c) current status of redevelopment work at these stations in the said
state including details of project cost, contractors/agencies involved and
expected timelines for completion;
(d) passenger amenities and infrastructure improvements being provided
under these schemes such as roof plazas, waiting lounges, lifts,
escalators, and digital displays;(e) total amount of funds allocated, released, utilised for these projects
in the said state during the last three years, year and station-wise; and
(f) whether there have been any delay, land acquisition issues,
coordination challenges in implementing these schemes in the said
state, if so, the measures taken/being taken to address them?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f) Ministry of Railways has launched Amrit Bharat Station
Scheme for redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their
implementation in phases to improve the stations. The master
planning includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement,
water booths
Provision of wider foot over bridge/air concourse
commensurate with passenger traffic
Provision of lift/escalators/ramp
Improvement /Provision of platform surface and cover over
platforms Provision of kiosks for local products through schemes like
‘One Station One Product’
Parking areas, Multimodal integration
Amenities for Divyangjans
Better passenger information systems
Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at
each station.
The scheme also envisages sustainable and environment friendly
solutions, provision of ballastless tracks etc. as per necessity,
phasing and feasibility and creation of city centre at the station in
the long term.
So far, 1337 stations, including 132 stations located in the state of
Maharashtra have been identified for development under Amrit Bharat
Station Scheme. The name of stations identified for development under
Amrit Bharat Station Scheme in the state of Maharashtraare as
following:
State No. of Name of Stations
Stations
Maharashtra 132 Ahmednagar, Ajni (Nagpur), Akalkot Road,
Akola, Akurdi, Amalner, Amgaon, Amravati,
Andheri, Badnera, Balharshah, Bandra
Terminus, Baramati, Belapur, Bhandara Road,
Bhokar, Bhusawal, Borivali, Byculla,State No. of Name of Stations
Stations
Chalisgaon, Chanda Fort, Chandrapur, Charni
Road, Chhatrapati Sambhajinagar,
Chhatrapati Shivaji Maharaj Terminus,
Chinchpokli, Chinchwad, Dadar (CR), Dadar
(WR), Dahisar, Daund, Dehu Road, Devlali,
Dhamangaon, Dharangaon, Dharashiv,
Dharmabad, Dhule, Diva, Dudhani, Gangakher,
Godhani, Gondia, Grant Road, Hadapsar,
Hatkanangale, Hazur Sahib Nanded,
Himayatnagar , Hinganghat, Hingoli Deccan,
Igatpuri, Jalgaon, Jalna, Jeur, Jogeshwari,
Kalyan Junction, Kamptee, Kandivali, Kanjur
Marg, Karad, Katol, Kedgaon, Kinwat,
Kopargaon, Kurduwadi Junction, Kurla
Junction, Lasalgaon, Latur, Lokmanya Tilak
Terminus, Lonand Junction, Lonavla, Lower
Parel, Malad, Malkapur, Manmad Junction,
Manwath Road , Marine Lines, Matunga, Miraj
Junction, Mudkhed Junction, Mumbai Central,
Mumbra, MurtizapurJunction, Nagarsol,
Nagpur Junction, Nandgaon, Nandura,
Nandurbar, NarkherJunction, Nashik Road,
Netaji Subhash Chandra Bose Itwari Junction,
Pachora Junction, Palghar, Pandharpur,State No. of Name of Stations
Stations
Panvel Junction, Parbhani Junction, Parel,
Parli Vaijnath, Partur, Phaltan, Prabhadevi,
PulgaonJunction, Pune Junction, Purna
Junction, Raver, Rotegaon , Sainagar Shirdi,
Sandhurst Road, Sangli, Satara, Savda, Selu ,
Sewagram, Shahad, Shegaon, Shivaji Nagar
Pune, Shri Chhatrapati Shahu Maharaj
Terminus Kolhapur, Solapur, Talegaon,
Thakurli, Thane, Titvala, Tumsar Road, Umri,
Uruli, Vadala Road, Vidyavihar, Vikhroli,
Wadsa, Wardha, Washim, Wathar
Development works at railway stations under Amrit Bharat Station
Scheme in the state of Maharashtra have been taken up at a good pace.
Till now, works of 15 stations (Amgaon, Chanda Fort, Chinchpokli,
Devlali, Dhule, Kedgaon, Lasalgaon, Lonand Junction, Matunga,
Murtizapur Junction, Netaji Subhash Chandra Bose Itwari Junction,
Parel, Savda, Shahad and Vadala Road) in the state of Maharashtra have
been completed under this scheme.The works at other stations have
also been taken up at good pace and progress of some of the above
stations is as given below:
Wathar station: The works of new portico, improvement of station
building, water booth, new main entry gate, parking area, circulating
area, improvement of entrance lobby, compound wall of parking area,platform shelter at platform no. 1, platform surfacing, improvement of
waiting room, signages and station illumination have been
completed. The finishing works have been taken up.
Nandgaon station: The works of entrance and exit gate, platform
surfacing, platform shelter, improvement of station building, booking
office, Foot Over Bridge, boundary wall, circulating area, parking
area, signage and lighting have been completed. The finishing works
have been taken up.
Nandura station: The works of platform surfacing, platform shelter,
booking office, entrance gate, improvement of waiting hall, toilet,
station building, circulating area, parking area, signages, coach
indication board, station illumination and boundary wall have been
completed. The finishing works have been taken up.
Hadapsar station: The works of new station building, waiting hall, 12
m Foot Over Bridge, underground tank, platform shelter, improvement
of platform surfacing, circulating area, station illumination, signages,
lifts, escalators and landscaping have been completed. The finishing
works have been taken up.
Baramati station: The works of platform shelter, septic tank, toilet,
compound wall, water booth, improvement of booking office, platform
surfacing, waiting room, portico, circulating area, signages and
station illumination have been completed. The finishing works have
been taken up.Development / redevelopment / upgradation / modernisation of stations
on Indian Railways is a continuous and ongoing process and works in
this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. The priority for development /
redevelopment / upgradation / modernisation of stations is accorded to
higher category of station over lower category of station while
sanctioning and executing the works.
Further, development / upgradation / modernization of stations including
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation and expenditure under
Plan Head-53 are maintained Zonal Railway-wise and not work-wise or
station-wise or state-wise. The state of Maharashtra is covered under
the jurisdiction of four railway zones, namely, Central Railway, South
Central Railway, South East Central Railway and Western Railway. For
the last three years and the current year, ₹ 11,190 crore has been
allocated while an expenditure of ₹ 9,198 crore has been incurred during
the last three years and current year (up to October, 2025).
Suggestions/ Representations, both formal and informal for Railway
projects/ works across the country are received on the basis of demands
raised by State Governments, Members of Parliament, Ministries of
Central Government, elected representatives, Railways' own
requirements, organizations/ rail users etc., at various levels including
Railway Board, Zonal Railways, Division Office etc. Receipt of such
proposals / requests/ suggestions/ representations is a continuous and
dynamic process and these are examined and action as found feasibleand justified is taken from time to time and centralized compendium for
the same is not maintained.
Development / Upgradation of railway stations is complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as fire clearance, heritage, tree cutting, airport
clearance etc. The progress also gets affected due to brownfield related
challenges such as shifting of utilities (involving water/sewage lines,
optical fibre cables, gas pipe lines, power/signal cables, etc.),
infringements, operation of trains without hindering passenger
movement, speed restrictions due to works carried out in close
proximity of tracks and high voltage power lines, etc. and these factors
affect the completion time. Therefore, no time frame can be indicated at
this stage.
*****