GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3098
ANSWERED ON 06TH AUGUST, 2026
APPROVAL FOR OUTER RING ROAD PROJECT IN KERALA
3098. ADV. ADOOR PRAKASH:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) whether the Government proposes to take fast-track measures for
granting final approval to the Vizhinjam–Navaikulam Outer Ring Road
project in Kerala considering the inordinate delay, if so, the details
thereof;
(b) the measures taken by the Government to expedite environmental
clearance for the said project;
(c) the present status of the proposal submitted to the Ministry of
Environment, Forest and Climate Change for environmental clearance;
(d) whether the Government is aware that, due to delay in
disbursement of compensation, around 6,500 families who have
handed over their land and properties have been facing difficulties
during the last four years; and
(e) whether the Government proposes to take necessary measures for
resolving the issues and expeditious execution of the project, if so, the
details thereof?ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) & (e) For development of Greenfield Highway between Vizhinjam
and Navaikkulam Outer Ring Road Project, the revised Detailed Project
Report (DPR) has been prepared. Based upon the experince in
implementing the project agumentation for National Highway 66 (NH
66), the DPR was reviewed to minimise hill cutting with provisions of
tunnels & Viaducts. The decision on investment shall be taken
considering fulfilment of criterion, traffic density and synergy with PM
Gati Shakti.
(b) & (c) Environment Appraisal Committee of Ministry of Environment,
Forest and Climate Change in the meeting held on 15th-16th July, 2026
considered and deferred the proposal for want of certain
information.
(d) The land for the project for National Highway (NH) is acquired as
per National Highway Act, 1956 and the compensation is arrived at in
accordance with applicable provisions of Right to Fair Compensation
and Transparency in Land Acquisition, Rehabilitation and
Resettlement (RFCTLARR) Act 2013, to be paid after the project is
approved by the Competent Authority.
*****