See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF SOCIAL JUSTICE & EMPOWERMENT
DEPARTMENT OF EMPOWERMENT OF PERSONS WITH DISABILITIES
(DIVYANGJAN)
RAJYA SABHA
UNSTARRED QUESTION NO-3808
ANSWERED ON- 25/03/2026
APPROVAL RATE OF UDID
3808. SMT. SAGARIKA GHOSE
Will the Minister of SOCIAL JUSTICE AND EMPOWERMENT be pleased to state:
(a) whether Government is cognisant of the fact that applications under the Unique
Disability ID (UDID) scheme are facing an average processing delay of nearly 200 days;
(b) the reasons for such prolonged delays in processing applications and the corrective
measures undertaken or proposed to expedite approvals;
(c) whether Government has conducted awareness drives or registration camps to ensure
maximum coverage of eligible persons with disabilities under the UDID scheme; and
(d) State-wise details of the total number of UDID applications received and approved,
along with the corresponding number of Persons with Disabilities (PwDs), as per the latest
available data?
ANSWER
MINISTER OF STATE FOR SOCIAL JUSTICE AND EMPOWERMENT
(SHRI B. L. VERMA)
(a): The Unique Disability Identity (UDID) sub scheme is a flagship initiative of the
Government of India. Under the UDID sub scheme, an online centralized platform namely
UDID portal (https://swavlambancard.gov.in/) has been instituted where hospitals authorized
by the respective State/UT Governments have been onboarded for issuance of disability
certificates and Unique Disability Identity (UDID) cards to the eligible divyangjan.
As per UDID portal, the average processing time across States/UTs ranges from two days to
more than 600 days. This provision has been implemented to strengthen monitoring of the
UDID process.
(b): The Central Government acts as a policymaker and facilitator of the centralized online
UDID portal, while the issuance of UDID cards is undertaken by notified hospitals authorized
by the respective State/UT Governments based on disability assessment. Since disability
certification and card issuance require medical evaluation and infrastructure under the
purview of States/UTs, the pace, reasons for delay, and timelines depend on the availability
of medical infrastructure and specialists in the concerned States/UTs. However, the centralgovernment has undertaken following steps to make the Disability certification system
uniform, standardized and hassle free for the Hospitals as well as for the Divyangjan:
i. Disability assessment guidelines have been revised on 12.03.2024 with the provision
to include private assessment specialists where the delay and pendency is attributable
to shortage of specialists. The State/UT Governments have been requested time to
time to maximize authorized number of hospital for the issuance of UDID cards and
Disability Certificates.
ii. Eight zonal training programmes have been organized across the country covering
about 6000 assessment specialist including Chief Medical Officers, Medical
Superintendents and Specialists, to ensure uniform, fair and efficient assessment.
iii. Periodic training and orientation programmes for officials and medical authorities to
facilitate effective implementation of the UDID project and ensure timely generation
of the UDID card.
iv. Regular meetings are held by the senior officers of the department with the
States/UTs.
v. UDID enrolment centres have been established across NIs/CRCs of the Department
facilitating PwDs.
(c): The Department of Empowerment of Persons with Disabilities (DEPwD) has
undertaken various measures to enhance public awareness and enrolment under the UDID
Project, targeting persons with disabilities including in rural and remote areas. The
department has taken measures through State/UTs Governments in organising enrolment
camps, disseminating information through print, electronic, and social media platforms in
multiple languages, and conducting training and sensitisation programmes for District
Medical Authorities to facilitate smooth application and certification processes. Further, the
social media handles of DEPwD are also used for awareness generation of the UDID project.
(d): State-wise details of the total number of UDID applications received and approved,
along with the corresponding number of Persons with Disabilities (PwDs) as on 19.03.2026 is
at Annexure.
*****Annexure
Annexure referred to in reply to part (d) of the Rajya Sabha Unstarred Question No. 3808 to be
answered on 25.03.2026 regarding “Approval rate of UDID”
UDID applications approved and
Applications
State/UT corresponding number of Persons with
received
Disabilities (PwDs)
Andaman And Nicobar Islands 8090 6991
Andhra Pradesh 1026575 987831
Arunachal Pradesh 5134 4654
Assam 369770 244998
Bihar 959426 718288
Chandigarh 16822 13003
Chhattisgarh 284855 275904
Delhi 209320 110385
Goa 17188 13307
Gujarat 591875 495698
Haryana 384659 237286
Himachal Pradesh 130020 110097
Jammu And Kashmir 333499 229888
Jharkhand 283090 212893
Karnataka 1211032 934949
Kerala 539131 428442
Ladakh 4385 4271
Lakshadweep 1636 1390
Madhya Pradesh 1281661 1009305
Maharashtra 1922886 1416490
Manipur 22205 16924
Meghalaya 35453 34661
Mizoram 8014 7525
Nagaland 4539 3965
Odisha 1474262 949493
Puducherry 26259 24661
Punjab 521499 384458
Rajasthan 886754 741018
Sikkim 6295 5906
Tamil Nadu 1118084 1022956
Telangana 954237 875807
The Dadra And Nagar Haveli And Daman
6201 4724
And Diu
Tripura 46920 45452
Uttar Pradesh 2172911 1676372
Uttarakhand 115797 106725
West Bengal 398321 234379
*****