Parliament Question: Bahraich-Jarwal Road New Railway Line

Issued by Ministry of Railways · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

**Executive Summary** The document is a response to Starred Question No. 57 in the Lok Sabha concerning the Bahraich-Jarwal Road new railway line, to be answered on 03.12.2025. It provides details on the current status of the project, including the completed Detailed Project Report (DPR), associated projects, and budget allocations. The document outlines the approval process and various factors influencing project timelines. **Key Points / Main Content** *Bahraich-Jarwal Road Connectivity:* * Bahraich and Jarwal Road are connected via Gonda Junction. * Survey for a direct Bahraich-Jarwal Road new railway line (70 km) is complete, and the Detailed Project Report (DPR) is prepared. *Sanctioned Railway Works for Improved Connectivity:* * Burhwal-Jarwal Road-Gonda Kacheri 4th Line (56 Km) * Burhwal-Jarwal Road-Gonda 3rd Line (62 Km) * Barabanki-Burhwal 3rd Line (27 Km) * Bahraich- Khalilabad New Line (240 Km) *Project Sanctioning & Approvals:* * Sanctioning requires consultation with stakeholders, including State Governments, NITI Aayog, and the Ministry of Finance. * Project sanctioning is a dynamic process with timelines dependent on appraisals and approvals. *Budget Allocation in Uttar Pradesh:* * Budget allocation for infrastructure and safety works in Uttar Pradesh has significantly increased. * 2009-14: ₹1,109 crore/year * 2025-26: ₹19,858 crore (Nearly 18 times) *Project Summary in Uttar Pradesh:* * As of 01.04.2025, 49 sanctioned projects (10 New Line, 2 Gauge Conversion, 37 Doubling) covering 3,807 Km and costing ₹62,360 crore, are falling fully/partly in the state of Uttar Pradesh. * 1,323 Km has been commissioned, with an expenditure of ₹30,611 crore up to March 2025. *Details of Projects in Uttar Pradesh:* * The document lists costs (Rs. in Cr.) for various completed projects and those taken up fully/partly in the State of Uttar Pradesh. *Sanctioned Surveys:* * In the last three years, 2022-23 to 2024-25, and the current financial year 2025-26, 119 surveys (33 New Line, 84 Doubling, and 2 Gauge Conversion) covering a total length of 6,414 Km have been sanctioned, falling fully/partly in the State of Uttar Pradesh. *Factors Affecting Project Sanction & Completion:* * Anticipated traffic, first/last mile connectivity, connection of missing links, augmentation of congested lines, demands from stakeholders, operational requirements, socio-economic considerations, and overall fund availability influence sanction. * Land acquisition, forest clearance, utility shifting, statutory clearances, geological conditions, law and order, and working months influence completion. **Impact Analysis** **Stakeholder:** Minister of Railways * **Impact:** Required to provide information on the Bahraich-Jarwal Road new railway line and related projects in response to the Lok Sabha question. * **Action Required:** Review the provided statement and prepare to answer any supplementary questions that arise. **Stakeholder:** State Governments and Government Ministries, NITI Aayog, Ministry of Finance. * **Impact:** Involved in the sanctioning of railway projects, requiring consultation and approvals. * **Action Required:** Provide timely appraisals and approvals for project sanctioning, and participate in stakeholder consultations. **Stakeholder:** Public and Government of Uttar Pradesh * **Impact:** Beneficiary of improved rail infrastructure and increased budget allocation in the state. * **Action Required:** Support land acquisition and statutory clearance to help the railway projects proceed according to their timeline.

Key Entities Referenced

Ministry of Railways: The ministry responsible for railways in India, the subject of the question. Bahraich-Jarwal Road New Railway Line: The specific railway line project which is the subject of the parliamentary question. Uttar Pradesh: The state where the projects discussed are located, which significantly impacts their applicability and scope. Detailed Project Report (DPR): The key document inquired about, essential for understanding project status. NITI Aayog: Government body involved in project approvals.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF RAILWAYS LOK SABHA STARRED QUESTION NO. 57 TO BE ANSWERED ON 03.12.2025 BAHRAICH-JARWAL ROAD NEW RAILWAY LINE †*57. DR. ANAND KUMAR: Will the Minister of RAILWAYS be pleased to state: (a) whether Detailed Project Report (DPR) of the Bahraich-Jarwal Road new railway line has been prepared given the fact that survey work for the said railway line has been completed; (b) if so, the details thereof and if not, the timeline for the completion of DPR of the said project; (c) whether the Government proposes to start the construction work of the said railway line soon, if so, the timeline fixed for the said work; (d) whether the Government has allocated budget for the construction work of the said new railway line in the current financial year; and (e) if so, the details thereof and if not, the timeline fixed for the allocation of budget for the construction work of the said railway line? ANSWER MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY (SHRI ASHWINI VAISHNAW) (a) to (e): A Statement is laid on the Table of the House. *****STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (e) OF LOK SABHA STARRED QUESTION NO. 57 TO BE ANSWERED ON 03.12.2025 (a) to (e): Bahraich and Jarwal Road are already connected via Gonda Junction on the existing railway network. To improve the connectivity, following works have been sanctioned: Length S. No. Project (in Km) 1 Burhwal-Jarwal Road-Gonda Kacheri 4th Line 56 2 Burhwal- Jarwal Road-Gonda 3rd Line 62 3 Barabanki-Burhwal 3rd Line 27 4 Bahraich- Khalilabad New Line 240 Further, to provide direct connectivity, a survey for construction of Bahraich-Jarwal Road new railway line (70 Km) was sanctioned. The survey has been completed and Detailed Project Report (DPR) has been prepared. After preparation of Detailed Project Report (DPR), sanctioning of project requires consultation with various stake-holders including State Governments and necessary approvals viz. appraisal of NITI Aayog, Ministry of Finance etc. As sanctioning of projects is a continuous and dynamic process, exact timelines depend upon appraisals and approvals by various stakeholders. Uttar Pradesh Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure projects and safety works, falling fully/partly in the State of Uttar Pradesh is as under: Period Outlay 2009-14 ₹1,109 crore/year 2025-26 ₹19,858 crore (Nearly 18 times) The details of commissioning/laying of new track falling fully/partly in the State of Uttar Pradesh during 2009-14 and 2014-25 is as under: Contd…2-2- New Track Period Average Commissioning of new tracks Commissioned 2009-14 996 Km 199 Km/year 2014-25 5272 Km 479 Km per year (More than 2 times) As on 01.04.2025, 49 projects (10 New Line, 02 Gauge Conversion and 37 Doubling) of 3,807 Km length, costing ₹62,360 crore falling fully/partly in the State of Uttar Pradesh are sanctioned, out of which 1,323 Km length has been commissioned and an expenditure of ₹30,611 crore has been incurred upto March’ 2025. The summary is as under:- Category No of Total Length Exp sanctioned Length Commissioned upto Projects (Km) Upto Mar'25 Mar'25 (Km) (Rs. in Cr.) New Line 10 1227 340 10517 Gauge Conversion 02 67 0 281 Doubling/Multitracking 37 2513 983 19813 Total 49 3807 1323 30611 Details of some of the recently completed projects falling fully/partly in the State of Uttar Pradesh are as under: S. Cost Project No. (Rs. in Cr.) Domingarh-Gorakhpur-Kusumhi - 3rd Line and 1 508 Gorakhpur-Nakaha Jungle Doubling (21 Km) Bahraich-Nanpara-Nepal Ganj Gauge Conversion 2 342 (56 Km) 3 Ballia-Ghazipur city Doubling (65 Km) 650 4 Ghazipur city-Tarighat New Line (17 Km) 1766 5 Gonda-Gorakhpur Loop Gauge Conversion (260 Km) 863 6 Gonda-Bahraich Gauge Conversion (60 Km) 318 7 Barabanki-Akbarpur Doubling (161 Km) 1700 Kaptanganj-Thawe-Chhapra Gauge Conversion (234 8 819 Km) 9 Pilibhit-Shahjahanpur Gauge Conversion (83 Km) 589 10 Indara-Dohrighat Gauge Conversion (34 Km) 213 11 Lucknow-Pilibhit Gauge Conversion (263 Km) 1634 12 Bhadoi-Janghai Doubling (31 Km) 168 13 Lahota-Bhadoi Doubling (39 Km) 184 Contd…3-3- 14 Meerut-Muzaffarnagar Doubling (55 Km) 430 15 Phaphamau-Prayagraj Doubling (14 Km) 212 16 Muzaffarnagar–Tapri Doubling (52 Km) 525 17 Utretia-Raibareilly Doubling (66 Km) 662 18 Raibareilly-Amethi Doubling (60 Km) 668 19 Alamnagar-Utretia Doubling (20 Km) 358 20 Bhimsen—Jhansi Doubling (206 Km) 2620 21 Etawah-Mainpuri New Line (58 Km) 313 22 Malhaur-Daliganj Doubling (13 Km) 183 23 Ruma Chakeri- Chandari 3rd Line (13 Km) 177 Bareilly-Pilibhit-Tanakpur Gauge Conversion (102 24 313 Km) 25 Rosa-Sitapur Cantt-Burhwal Doubling (181 Km) 2094 26 Jaunpur- Akbarpur (Tanda) Doubling (77 Km) 676 27 Ramna- Renukut-Singrauli Doubling (160 Km) 2436 28 Janghai- Phaphamau Doubling (47 Km) 414 29 Varanasi-Madhosingh-Prayagraj Doubling (120 Km) 2018 30 Karaila Road- Shaktinagar Doubling (32 Km) 763 31 Deoband (Muzzafarnagar)-Roorkee (27 Km) 1289 32 Agra-Etawah New Line(110 Km) 427 Some of the projects falling fully/partly in the State of Uttar Pradesh which have been taken up are as under: SN. Project Cost (Rs. in Cr.) 1 Barabanki-Burhwal 3rd Line (27 Km) 426 2 Burhwal- Gonda Kacheri 4th line (56 Km) 796 3 Burhwal-Gonda 3rd Line (62 Km) 1118 4 Bahraich- Khalilabad New Line (240 Km) 4940 5 Katra-Ayodhya Dham Doubling (10 Km) 466 6 Pt. Deen Dayal Upadhyaya- Prayagraj 3rd Line (150 2649 Km) 7 Billi-Chunar Doubling (102 Km) 1424 8 Chhapra-Ballia Doubling (65 km) 1046 9 Unchhar-Amethi New Line (66 Km) 1229 10 Etah-Kasganj New Line ( 29 Km) 389 11 Phephna-Indara, Mau-Shahganj Doubling (150 Km) 1778 12 Gorakhpur- Valmikinagar Doubling (96 Km) 1121 13 Varanasi-Pt. Deen Dayal Upadhyaya 3rd and 4th Line 2464 (15 Km) Contd…4-4- 14 Jhansi-Khairar-Manikpur & Khairar-Bhimsen Doubling 4330 (431 Km) 15 Sahjanwa-Dohrighat New Line (81 Km) 1320 In last three years 2022-23, 2023-24, 2024-25 and current financial year 2025-26, 119 surveys (33 New Line, 84 Doubling and 02 Gauge Conversion) covering a total length of 6,414 Km have been sanctioned falling fully/partly in the State of Uttar Pradesh. Sanction of any railway project depends upon many parameters/factors which include the following:  Anticipated traffic projections and remunerativeness of the proposed route  First and last mile connectivity provided by the project  Connection of missing links and providing additional route  Augmentation of congested/saturated lines  Demands raised by State Governments/Central Ministries/Public representatives,  Railway’s own operational requirements  Socio-economic considerations  Overall availability of funds Completion of Railway project/s depends on various factors which include the following:  Land acquisition  Forest clearance  Shifting of infringing utilities  Statutory clearances from various authorities  Geological and topographical conditions of area  Law and order situation in the area of project site  Number of working months in a year for particular project site etc. All these factors affect the completion time and cost of the project/s. *****