**Executive Summary**
This document summarizes the Indian government's initiatives to promote the development and deployment of energy storage technology, particularly Battery Energy Storage Systems (BESS) and Pumped Storage Projects (PSPs), to manage the intermittency of renewable energy and maintain grid stability. It outlines policy, regulatory, and demand-side measures, as well as supply-side and manufacturing-focused actions taken by the government to facilitate a transition towards renewable energy. The Central Electricity Authority (CEA) estimated requirements of 336 GWh and 411 GWh by 2029-30 and 2031-32 respectively, and guidelines for resource adequacy plans (RAP) were issued on June 28, 2023.
**Key Points / Main Content**
* **Policy and Regulatory Measures:**
* Electricity Rules amended in December 2022 to recognize Energy Storage Systems (ESS) as an integral part of the power system, enabling their participation across various functions.
* ESS included in the Harmonised Master List of Infrastructure in October 2022, allowing access to longer tenure and lower cost financing.
* Guidelines for Preparation of Resource Adequacy Plans (RAP) issued in June 2023, incorporating energy storage as a key planning resource.
* A National Framework for Promotion of Energy Storage Systems issued in September 2023, outlining a comprehensive roadmap for deployment and market integration.
* Draft safety and technical standards for BESS installations released in 2025.
* **Demand-Side Enablers and Market Development Measures:**
* Waiver of Inter-State Transmission System (ISTS) charges provided for co-located BESS projects (commissioned and PSPs awarded up to June 2028).
* CERC allowed storage-based resources to provide ancillary services in January 2022.
* Tariff-Based Competitive Bidding (TBCB) Guidelines for BESS procurement notified in March 2022.
* Consumers using diesel generators mandated to shift to cleaner backup solutions as per Electricity (Rights of Consumers) Rules, amended in December 2022.
* BESS electricity allowed to participate in High-Price Day-Ahead Market since March 2023.
* **Supply-Side and Manufacturing-Focused Measures:**
* Two Viability Gap Funding (VGF) schemes launched in March 2024 and June 2025 to support 43 GWh of Battery Energy Storage Systems.
* Production-Linked Incentive (PLI) Scheme with an outlay of ₹18,100 crore for 50 GWh of Advanced Chemistry Cell manufacturing capacity (June 2021).
* Grant for pumped storage projects infrastructure: ₹1 crore/MW for the first 200 MW (September 2023).
* CERC allowed separate grid connectivity during non-solar hours (September 2025).
* Statutory concurrence of the Central Electricity Authority dispensed with for closed-loop pumped storage projects (August 2025).
* Energy storage systems are permitted to be developed, owned, leased or operated by consumers (September 2025).
* CEA advised co-location of ESS with solar projects, recommending 10% storage capacity (February 2025).
**Impact Analysis**
**Stakeholder: Government of India**
* **Impact**: Enhanced grid stability, improved integration of renewable energy sources, promotion of energy storage technologies, and reduced reliance on traditional power sources. Facilitation of a transition to a cleaner and more sustainable energy mix.
* **Action Required**: Continue implementing and refining the policies, regulations, and schemes to further support the growth of energy storage and renewable energy.
**Stakeholder: State Utilities**
* **Impact**: Need to integrate energy storage as a key planning resource for meeting peak demand and ensuring system reliability.
* **Action Required**: Adhere to the Guidelines for Preparation of Resource Adequacy Plans (RAP), incorporating energy storage solutions to meet peak demand and ensure grid stability.
**Stakeholder: Energy Storage System (ESS) Developers and Manufacturers**
* **Impact**: Opportunities for investment and growth in the energy storage sector, supported by government policies, incentives, and market mechanisms.
* **Action Required**: Participate in the Tariff-Based Competitive Bidding (TBCB) process for procurement of BESS, take advantage of the Production-Linked Incentive (PLI) Scheme, and align with the safety and technical standards for BESS installations.
**Stakeholder: Electricity Consumers**
* **Impact**: Access to cleaner and more reliable electricity supply, as well as opportunities for developing, owning, leasing, or operating energy storage systems.
* **Action Required**: Shift to cleaner backup solutions, including energy storage, by ceasing to use diesel generators within the timelines specified by State Commissions.
**Stakeholder: Renewable Energy Generators**
* **Impact**: Ability to improve dispatchability of renewable energy by co-locating ESS with solar power projects.
* **Action Required**: Co-locate ESS with solar projects, recommending 10% storage capacity to improve dispatchability of solar power.
Key Entities Referenced
Battery Energy Storage Systems (BESS): Energy storage technology playing a crucial role in managing variability and intermittency of renewable energy, and providing ancillary grid services.
Central Electricity Regulatory Commission (CERC): Regulatory body whose Ancillary Services Regulations, 2022, made energy storage systems eligible to provide Secondary Reserve Ancillary Services and Tertiary Reserve Ancillary Services.
Electricity Rules: Amended in December 2022 to explicitly recognize Energy Storage Systems (ESS) as an integral part of the power system.
Guidelines for Preparation of Resource Adequacy Plans (RAP): Issued in June 2023 to incorporate energy storage systems as a key planning resource for meeting peak demand and ensuring system reliability.
Ministry of Power: Union ministry responsible for policies and schemes relating to energy storage and renewable energy integration.
GOVERNMENT OF INDIA
MINISTRY OF POWER
LOK SABHA
UNSTARRED QUESTION NO.3093
ANSWERED ON 18.12.2025
BATTERY ENERGY STORAGE SYSTEM
†3093. SHRI GANESH SINGH:
Will the Minister of POWER
be pleased to state:
(a) the concrete steps that have been taken by the Government so far to develop and
deploy energy-storage technology to handle the intermittency of renewable energy and
maintain grid stability;
(b) whether the Government is contemplating adopting best practices from countries
with high renewable-energy share such as Battery Energy Storage Systems (BESS),
pumped-hydro storage and advanced grid-management systems in India’s energy-
transition strategy, if so, the details thereof; and
(c) whether any proposal exists to release a national action-plan or roadmap to increase
energy-storage capacity, reduce costs and deploy large-scale storage infrastructure in
the upcoming years, if so, the details thereof?
A N S W E R
THE MINISTER OF STATE IN THE MINISTRY OF POWER
(SHRI SHRIPAD NAIK)
(a) : To address the intermittency of renewable energy and to maintain grid stability,
the Government of India has taken a series of coordinated policy, regulatory, demand-
side and supply-side measures to promote the development and deployment of energy-
storage technologies, including Battery Energy Storage Systems (BESS) and Pumped
Storage Projects (PSPs). Details of the measures taken are placed in the Annexure.
(b) : The Government is drawing upon global best practices from countries with high
renewable-energy penetration as part of India’s energy-transition strategy.
International experience demonstrates that Pumped-hydro storage and BESS, and
advanced grid-management systems play a critical role in managing variability and
intermittency of renewable energy. In line with these practices, energy storage
systems in India are being positioned to provide ancillary grid services such as
frequency control, voltage regulation, peak shifting, congestion management and black-
start support across different time scales. Accordingly, under the Central Electricity
Regulatory Commission (Ancillary Services) Regulations, 2022, energy storage systems
have been made eligible to provide Secondary Reserve Ancillary Services and Tertiary
Reserve Ancillary Services, subject to specified conditions, thereby supporting real-
time grid stability and reliable system operation. Renewable Energy Management
Centres (REMCs) have been established for monitoring, forecasting and scheduling of
Renewable resources. Automatic Generation Control (AGC) is being used for balancing
supply and demand to manage variability of renewable energy.
……..2.- 2 -
(c) : Government has put in place a planning framework to guide large-scale
deployment of energy storage capacity in the coming years. The Central Electricity
Authority (CEA) has estimated a requirement of about 336 GWh of energy storage
capacity by 2029-30 and about 411 GWh by 2031-32 to facilitate reliable integration of
renewable energy. Further, Guidelines for Preparation of Resource Adequacy Plans
(RAP) were issued on 28.06.2023, which incorporate energy storage systems as an
important element of power sector planning. These guidelines establish a mechanism
to ensure that adequate generation, storage and demand-responsive resources are
available to reliably meet expected peak demand and maintain grid stability. Together,
the National Electricity Plan and Resource Adequacy framework provide a roadmap for
scaling up energy-storage capacity, improving system reliability and enabling India’s
energy transition.
***********ANNEXURE
ANNEXURE REFERRED IN REPLY TO PART (a) OF UNSTARRED QUESTION NO.
3093 ANSWERED IN THE LOK SABHA ON 18.12.2025
*************
I. Policy and Regulatory Measures
1. The Electricity Rules were amended in December 2022 to explicitly recognise
Energy Storage Systems (ESS) as an integral part of the power system, enabling
their participation across generation, transmission and distribution functions.
2. In October 2022, ESS were included in the Harmonised Master List of
Infrastructure of the Ministry of Finance, facilitating access to long-tenure and
lower-cost financing.
3. In June 2023, the Government issued Guidelines for Preparation of Resource
Adequacy Plans by State utilities, under which energy storage has been
incorporated as a key planning resource for meeting peak demand and ensuring
system reliability.
4. A National Framework for Promotion of Energy Storage Systems was issued in
September 2023, providing a comprehensive roadmap for deployment, market
integration and regulatory facilitation of storage technologies.
5. To enhance safety and reliability of BESS installations and standardise design
and construction practices, Draft CEA (Measures Relating to Safety and Electric
Supply) (First Amendment) Regulations, 2025 and Draft Technical Standards for
Construction of BESS Regulations, 2025 have been issued.
II. Demand-Side Enablers and Market Development Measures
6. Waiver of Inter-State Transmission System (ISTS) charges has been provided for
co-located BESS projects commissioned and PSPs awarded up to June 2028, to
improve project viability (initial waiver was notified in November 2021).
7. In January 2022, CERC allowed storage-based resources to provide ancillary
services, including secondary and tertiary reserves, enabling ESS to support real-
time grid balancing alongside conventional generators.
8. Tariff-Based Competitive Bidding (TBCB) Guidelines for procurement of BESS by
distribution licensees were notified in March 2022, creating a transparent
mechanism for large-scale storage procurement.
9. Under the Electricity (Rights of Consumers) Rules, 2020, amended in December
2022, consumers using diesel generator sets have been mandated to shift to
cleaner backup solutions, including energy storage, within timelines specified by
State Commissions.
10. Electricity supplied from BESS has been allowed to participate in the High-Price
Day-Ahead Market, launched in March 2023, enabling storage to respond to peak
price signals similar to gas-based generation.
………2.- 2 -
11. The Government is implementing two Viability Gap Funding (VGF) schemes to
support development of approximately 43 GWh of Battery Energy Storage
Systems, launched in March 2024 and June 2025, to accelerate early-stage
deployment.
III. Supply-Side and Manufacturing-Focused Measures
12. The Ministry of Heavy Industries is implementing a Production-Linked Incentive
(PLI) Scheme with an outlay of ₹18,100 crore for establishing 50 GWh of
Advanced Chemistry Cell manufacturing capacity, of which 10 GWh is earmarked
for grid-scale storage (June 2021).
13. For pumped storage projects, a grant for enabling infrastructure is provided at
the rate of ₹1 crore per MW for the first 200 MW and ₹0.75 crore per MW thereafter
(September 2023).
14. CERC has allowed separate grid connectivity during non-solar hours, enabling
additional renewable capacity at existing substations and facilitating storage-
based shifting of power to evening and night hours (September 2025).
15. Statutory concurrence of the Central Electricity Authority has been dispensed
with for closed-loop, off-stream pumped storage projects to expedite project
development (August 2025).
16. Through amendment of the Electricity Rules in September 2025, energy storage
systems have been permitted to be developed, owned, leased or operated by
consumers, expanding the range of ownership and business models.
17. In February 2025, CEA issued an advisory on co-location of ESS with solar power
projects, recommending storage capacity of at least 10% of installed solar
capacity for a minimum duration of two hours, to improve dispatchability of solar
power.
*************