Home India RAILWAYS Parliament Question: Bhadrachalam-Kovvur Railway Line Projec...
Date: 2026-02-04 Category: Not Applicable State: Union Government Country: India

Parliament Question: Bhadrachalam-Kovvur Railway Line Project

Issued by RAILWAYS · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

**Executive Summary** This document provides the Minister of Railways' response to questions regarding the Bhadrachalam-Kovvur Railway Line project. The response outlines the project's cost-sharing agreement with the Government of Andhra Pradesh, its current status, and other railway projects in the state. The response was prepared in answer to questions submitted to Lok Sabha, to be answered on 04.02.2026. **Key Points / Main Content** * **Project Details:** * The Bhadrachalam-Kovvur (119 Km) New Line project was sanctioned on a 50:50 cost-sharing basis with the Government of Andhra Pradesh. * The anticipated project cost is ₹3,796 crore. * The Bhadrachalam-Satupalli (56 Km) new line project was completed in May 2022. * **Budget Allocation in Andhra Pradesh:** * Budget allocation for infrastructure projects and safety works in Andhra Pradesh has increased significantly. * Average budget allocation for 2009-2014 was ₹886 crore/year (including Telangana). * Budget allocation for 2025-2026 is ₹9,417 crore (more than 10 times the average). * **Track Commissioning:** * During 2009-14, 363 Km of new track was commissioned (72.6 Km per year). * During 2014-25, 1,582 Km of new track was commissioned (143.82 Km per year). * As of 01.04.2025, 39 projects (12 New Lines and 27 Doubling) covering a total length of 4,499 km, costing ₹70,232 crore, falling fully/partly in Andhra Pradesh, have been sanctioned. * Out of these sanctioned projects, 1,178 km length has been commissioned, and an expenditure of ₹28,039 crore has been incurred up to March 2025. * **Project Status Summary:** | Category | No. of projects | Total Length (Km) | Length Commissioned (Km) | Expenditure up to March 2025 (₹ in Cr.) | | ----------------------- | --------------- | ----------------- | ------------------------ | ------------------------------------------ | | New Line | 12 | 1595 | 199 | 6,413 | | Doubling / Multitracking | 27 | 2904 | 979 | 21,626 | | **TOTAL** | **39** | **4,499** | **1,178** | **28,039** | * **Factors influencing project sanction and completion:** * **Sanction:** Anticipated traffic, connectivity, route addition, congestion, demands from government bodies, operational requirements, socio-economic factors, availability of funds. * **Completion:** Land acquisition, forest clearance, shifting utilities, statutory clearances, geological conditions, law and order, and working months. **Impact Analysis** * **Government of Andhra Pradesh** * **Impact:** The project's progress directly impacts Andhra Pradesh's railway infrastructure development and connectivity. * **Action Required:** Continue to fulfill the cost-sharing agreement for the Bhadrachalam-Kovvur Railway Line project and collaborate with the Ministry of Railways to expedite project completion. * **Citizens of Andhra Pradesh** * **Impact:** Improved railway infrastructure will enhance transportation options, potentially boosting economic activity and connectivity. * **Action Required:** No direct action required; benefit from improved transportation infrastructure as projects are completed. * **Ministry of Railways** * **Impact:** The Ministry is responsible for managing and overseeing the Bhadrachalam-Kovvur Railway Line project and other railway projects in Andhra Pradesh. * **Action Required:** Ensure timely completion of projects, monitor budget allocation and utilization, and address factors affecting project timelines.

Key Entities Referenced

Bhadrachalam-Kovvur Railway Line Project: The central subject of the parliamentary question, concerning its survey, completion, funding, revised cost estimates, and reasons for delay. Ministry of Railways: The government ministry responsible for the Bhadrachalam-Kovvur Railway Line Project. Andhra Pradesh: The state where the Bhadrachalam-Kovvur Railway Line Project is located, influencing its cost sharing and budgetary allocations.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF RAILWAYS LOK SABHA UNSTARRED QUESTION NO. 735 TO BE ANSWERED ON 04.02.2026 BHADRACHALAM-KOVVUR RAILWAY LINE PROJECT 735. SHRI PUTTA MAHESH KUMAR: Will the Minister of RAILWAYS be pleased to state: (a) whether the Government has undertaken any study/survey regarding the Bhadrachalam-Kovvur Railway line during the last five years and if so, the details thereof; (b) the details of the steps undertaken to expedite completion of the railway line during the last five years; (c) the details of the total funding allocated/released/utilised for completion of the railway line; (d) whether the Government has initiated/taken steps for revised estimates for cost of the total project and if so, the details thereof; and (e) the details of the reasons of delay in completion of the project and the steps undertaken by the Government for expedited completion of the same? ANSWER MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY (SHRI ASHWINI VAISHNAW) (a) to (e): Bhadrachalam-Kovvur (119 Km) New Line project was sanctioned on 50:50 cost sharing basis with Government of Andhra Pradesh at an anticipated cost of ₹3,796 crore. Out of which, Bhadrachalam-Satupalli (56 Km) new line project has already been completed in May 2022. Contd…2-2- ANDHRA PRADESH: Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure projects and safety works, falling fully/partly in the State of Andhra Pradesh is as under: Period Outlay 2009-2014 ₹886 cr./year (including Telangana) 2025-2026 ₹9,417 cr. (more than 10 times) The details of commissioning/laying of new track falling fully/partly in the State of Andhra Pradesh during 2009-14 and 2014-25 is as under: New Track Average Commissioning of new Period Commissioned tracks 2009-14 363 Km 72.6 Km per year 2014-25 1,582 Km 143.82 Km per year (Nearly 2 times) As on 01.04.2025, 39 projects (12 New Lines and 27 Doubling), covering total length of 4,499 km length, costing ₹70,232 crore, falling fully/partly in Andhra Pradesh, have been sanctioned, out of which 1,178 km length has been commissioned and an expenditure of ₹28,039 crore has been incurred upto March 2025. The status of the work is summarized as: No. of Total Length Exp upto Category projects Length Commissioned March 2025 (Km) (Km) (₹ in cr.) New Line 12 1595 199 6,413 Doubling 27 2904 979 21,626 /Multitracking TOTAL 39 4,499 1,178 28,039 Zonal Railway wise details of Railway projects are made available in public domain on Indian Railway’s website. Details of some of the recently completed projects falling fully/partly in the State of Andhra Pradesh are as under: Contd…3-3- S.No. Name of Project Cost (₹. in cr.) 1 Vijaywada – Gudivada – Bhimavaram - Narsapur, 4,688 Gudivada-Machlipatnam & Bhimavaram-Nidadavolu doubling (221 Km) 2 Guntur-Tenali doubling (24 Km) 205 3 Nandyal-Yerraguntla new line (126 Km) 1,050 Jaggayyapeta-Mellacheruvu-Janpahad new line 4 737 (48 Km) 5 Obulavaripalle-Krishnapattnam new line (113 Km) 2,300 6 Vizianagaram-Kottavalsa 3rd Line (35 Km) 285 7 Raichur-Guntakal doubling (81 Km) 388 8 Guntakal-Kalluru doubling (41 Km) 410 9 Yelahanka-Penukonda doubling (123 Km) 1,104 10 Gooty-Dharmavaram doubling (90 Km) 1,800 Some of the projects falling fully/partly in the State of Andhra Pradesh which have been taken up are as under: S.N Name of Project Cost (Cr) 1 Kotipalli-Narsapur new line (57 Km) 2,120 2 Nadikude-Srikalahasti new line (309 Km) 3,122 3 Rayadurg-Kalyandurg-Tumkur new line (207 Km) 2,496 4 Marikuppam-Kuppam new line (24 Km) 297 5 Malugur – Palasamudram new line (18 Km) 342 6 Malkangiri- Bhadrachalam - Pandurangapuram new 3,592 line (174 Km) 7 Errupalem-Amravati-Namburu new line (57 Km) 2,047 8 Kottavalasa-Koraput Doubling (189 Km) 2,500 9 Vijaywada- Gudur 3rd line (287 Km) 6,509 10 Guntakal- Guntur Doubling (401 Km) 4,306 11 Pennukonda-Dharmavarm Doubling (42 Km) 308 12 Gooty-Pendekallu Doubling (29 Km) 352 13 Duvvada - Simhachalam North 3rd & 4th line (21 Km) 356 14 Kottavalasa - Vizianagram 4th line (35 Km) 493 15 Gudur-Renigunta 3rd Line (83 Km) 877 16 Nergundi - Barang & Khurda Road - Vizianagaram 3rd 4,963 line (385 Km) Contd…4-4- In last three Years i.e. 2022-23, 2023-24, 2024-25 and current financial year 2025-26, 65 surveys (15 New Line, 50 Doubling) covering a total length of 6,985 Km have been taken up falling fully/partly in the State of Andhra Pradesh. Sanction of any railway project depend upon many parameters/factors which include the following:  Anticipated traffic projections and remunerativeness of the proposed route  First and last mile connectivity provided by the project  Connection of missing links and providing additional route  Augmentation of congested/saturated lines  Demands raised by State Governments/Central Ministries/Public representatives,  Railway’s operational requirements  Socio-economic considerations  Overall availability of funds Completion of Railway project/s depends on various factors which include the following:  Land acquisition  Forest clearance  Shifting of infringing utilities  Statutory clearances from various authorities  Geological and topographical conditions of area  Law and order situation in the area of project site  Number of working months in a year for particular project site etc. All these factors affect the completion time and cost of the project/s. *****

Continue your research