GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
STARRED QUESTION NO. 241
TO BE ANSWERED ON 05.08.2026
CERTIFIED KAVACH TRAIN PROTECTION SYSTEM
*241. SHRI GODAM NAGESH:
SMT. KAMALJEET SEHRAWAT:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the commissioning milestones of the indigenous Safety
Integrity Level-4 certified Kavach train protection system including
total route coverage and the 470-kilometre implementation in a single
day in January 2026;
(b) the details of 160 kmph Vande Bharat trials on the Delhi–Howrah sector
to test system efficacy under semi-high-speed parameters;
(c) whether Kavach saturation across Delhi–Mumbai and Delhi–Howrah
routes under Mission Raftar and seven other high-speed corridors
sanctioned in Union Budget 2026-27 with a 2.93 lakh crore outlay is on
schedule and if so, the details thereof and if not, the reasons therefor;
and
(d) whether any interventions have been made to realize a zero-accident
vision by converging Kavach with AI-driven collision forecasting, live
telemetry and predictive maintenance across the railway network and
if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): A Statement is laid on the Table of the House.
*****
§STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (d) OF STARRED
QUESTION NO.241 TO BE ANSWERED ON 05.08.2026 IN LOK SABHA
(a) to (d): Safety is accorded the highest priority on Indian Railways. As a
consequence of various safety measures taken over the years, there has
been a steep decline in the number of accidents.
Number of Consequential Train Accidents has reduced as shown in the table
below:-
Year Consequential Accidents
2014-15 135
2025-26 16 (88% lesser)
2026-27 ( upto June 2026) 2
Another important index showing improvement in safety in train operations
is Consequential Accident Index, the details of which are as under:-
Consequential Accident Index:-
Year Accident Index
2014-15 0.11
2025-26 0.01 ( 91% lesser)
Page 1 of 15This index measures number of consequential accidents as a ratio of total
running kilometers of all trains.
No. of consequential accidents
Accident Index =
No. of trains X million kilometers
The various safety measures taken to enhance safety in train
operations are as under:-
1. On Indian Railways, the expenditure on Safety related activities has
increased over the years as under:-
Expenditure/Budget on Safety related activities (Rs.
Year
in Cr.)
2013-14 39,200
2022-23 87,336
2023-24 1,01,662
2024-25 1,14,022
2025-26 1,17,693
2026-27 1,20,389
2. Electrical/Electronic Interlocking Systems with centralized operation
of points and signals have been provided at 6,671 stations up to
30.06.2026 to reduce accidents due to human failure.
3. Interlocking of Level Crossing (LC) Gates has been provided at 10,395
Level Crossing Gates up to 30.06.2026 for enhancing safety at LC
Gates.
4. Complete Track Circuiting of stations to enhance safety by verification
of track occupancy by electrical means has been provided at 6,671
stations up to 30.06.2026.
Page 2 of 155. Detailed instructions on issues related with safety of Signalling, e.g.
mandatory correspondence check, alteration work protocol,
preparation of completion drawing, etc. have been issued.
6. System of disconnection and reconnection for S&T equipment as per
protocol has been re-emphasized.
7. All locomotives are equipped with Vigilance Control Devices (VCD) to
improve alertness of Loco Pilots.
8. Retro-reflective sigma boards are provided on the mast which is
located two OHE masts prior to the signals in electrified territories to
alert the crew about the signal ahead when visibility is low due to
foggy weather.
9. A GPS based Fog Safety Device (FSD) is provided to loco pilots in fog
affected areas which enables loco pilots to know the distance of the
approaching landmarks like signals, level crossing gates, etc.
10. Modern track structure consisting of 60kg, 90 Ultimate Tensile
Strength (UTS) rails, Prestressed Concrete Sleeper (PSC) Normal/Wide
base sleepers with elastic fastening, fan shaped layout turnout on PSC
sleepers, Steel Channel/H-beam Sleepers on girder bridges is used
while carrying out primary track renewals.
11. Mechanisation of track laying activity through use of track machines
like PQRS, TRT, T-28 etc. to reduce human errors.
12. Maximizing supply of 130m/260m long rail panels for increasing
progress of rail renewal and avoiding welding of joints, thereby
improving safety.
13. Ultrasonic Flaw Detection (USFD) testing of rails to detect flaws and
timely removal of defective rails.
14. Laying of longer rails, minimizing the use of Alumino Thermic Welding
and adoption of better welding technology for rails i.e., Flash Butt
Welding.
Page 3 of 1515. Monitoring of track geometry by OMS (Oscillation Monitoring System)
and TRC (Track Recording Cars).
16. Patrolling of railway tracks to look out for weld/rail fractures.
17. The use of Thick Web Switches and Weldable CMS Crossing in turnout
renewal works.
18. Inspections at regular intervals are carried out to monitor and educate
staff for observance of safe practices.
19. Web based online monitoring system of track assets viz. Track
database and decision support system has been adopted to decide
rationalized maintenance requirement and optimize inputs.
20. Detailed instructions on issues related with safety of Track, e.g.
integrated block, corridor block, worksite safety, monsoon
precautions, etc. have been issued.
21. Preventive maintenance of railway assets (Coaches & Wagons) is
undertaken to ensure safe train operations.
22. Replacement of conventional ICF design coaches with LHB design
coaches is being done.
23. All unmanned level crossings (UMLCs) on Broad Gauge (BG) route have
been eliminated by January 2019.
24. Safety of Railway Bridges is ensured through regular inspection of
Bridges. The requirement of repair/rehabilitation of Bridges is taken up
based upon the conditions assessed during these inspections.
25. Indian Railways has displayed Statutory “Fire Notices” for widespread
passenger information in all coaches. Fire posters are provided in
every coach so as to educate and alert passengers regarding various
Do’s and Don’ts to prevent fire. These include messages regarding not
carrying any inflammable material, explosives, prohibition of smoking
inside the coaches, penalties etc.
26. Production Units are providing Fire detection and suppression system
in newly manufactured Power Cars and Pantry Cars, Fire and Smoke
Page 4 of 15detection system in newly manufactured coaches. Progressive fitment
of the same in existing coaches is also underway by Zonal Railways in
a phased manner.
27. Regular counselling and training of staff is undertaken.
28. Concept of Rolling Block introduced in Indian Railways (Open Lines)
General Rules vide Gazette notification dated 30.11.2023, wherein
work of integrated maintenance/ repair/replacement of assets is
planned up to 52 weeks in advance on rolling basis and executed as
per plan.
The details of the Safety related works related to better maintenance
practices, Technological improvements, better infrastructure and rolling
stock etc. undertaken by Railways are tabulated below:-
2004-05 to 2014-15 to 2014-26 Vs.
SN Item
2013-14 2025-26 2004-14
Technological Improvements
1. Use of high-quality 57,450 Km 1.63 Lakh Km More than
rails (60 Kg) (Km) 2.8 times
2. Longer Rail Panels 9,917 Km 87,219 Km Nearly 9
(260m) (Km) times
3. Electronic 837 3,691 Stations More than 4
Interlocking (Stations) Stations times
4. Fog Pass Safety As on As on 31.03.26: 352 times
Devices (Nos.) 31.03.14: 31,693 Nos.
90 Nos.
5. Thick Web Switches Nil 35,971 Nos.
(Nos.)
Better Maintenance Practices
1. Primary Rail Renewal 32,260 Km 57,583 Km 1.78 times
(Track Km)
Page 5 of 152. USFD (Ultra Sonic 79.43 Lakh 2.25 Crore More than
Flaw detection) 2.8 times
Testing of Welds
(Nos.)
3. Weld failures (Nos.) In 2013-14: In 2025-26: 93 %
3,699 Nos. 272 Nos. reduction
4. Rail fractures (Nos.) In 2013-14: In 2025-26: 92%
2,548 Nos. 208 Nos. reduction
Better Infrastructure and Rolling Stock
1. New Track KM added 14,985 Km 36,429 Km Almost 2.5
(Track Km) times
2. Flyovers 4,148 Nos. 14,362 Nos. More than 3
(RoBs)/Underpasses times
(RUBs) (Nos.)
3. Unmanned Level As on As on 31.03.26: Removed
crossings 31.03.14: Nil
(Nos.) on BG 8,948 (All eliminated by
31.01.19)
4. Manufacture of LHB 2,337 Nos. 49,366 More than
Coaches (Nos.) 21 times
Implementation of Kavach:-
1. Kavach is an indigenously developed Automatic Train Protection (ATP)
system. Kavach is a highly technology intensive system, which requires
safety certification of highest order (SIL-4).
2. Kavach aids the Loco Pilot in running of trains within specified speed
limits by automatic application of brakes in case Loco Pilot fails to do so
and also helps the trains to run safely during inclement weather.
Page 6 of 153. The first field trials on the passenger trains were started in February
2016. Based on the experience gained and Independent Safety
Assessment of the system by Independent Safety Assessor (ISA), three
firms were approved in 2018-19, for supply of Kavach Ver 3.2.
4. Kavach was adopted as National ATP system in July, 2020.
5. Implementation of Kavach System involves following Key Activities:
a. Installation of Station Kavach at each and every station, block
section.
b. Installation of RFID Tags throughout the track length.
c. Installation of telecom Towers throughout the section.
d. Laying of Optical Fibre Cable along the track.
e. Provision of Loco Kavach on each and every Locomotive running on
Indian Railways.
6. Based on deployment of Kavach version 3.2 on 1,465 RKm on South
Central Railway and experience gained, further improvements were
made. Finally, Kavach specification version 4.0 was approved by RDSO
on 16.07.2024.
7. Kavach version 4.0 covers all the major features required for the diverse
railway network. This is a significant milestone in safety for Indian
Railways. Within a short period, IR has developed, tested and started
deploying Automatic Train Protection System.
8. Major improvement in Version 4.0 includes increased Location Accuracy,
Improved Information of Signal Aspects in bigger yards, Station to
Station Kavach interface on OFC and Direct Interface to existing
Electronic Interlocking System. With these improvements, Kavach
Ver.4.0. is planned for large scale deployment over Indian Railways.
Page 7 of 159. After extensive and elaborate trials, Kavach Version 4.0 has been
successfully commissioned on 2,633 Route Kilometres as on 31.07.26,
covering the high density Delhi- Mumbai and Delhi-Howrah routes as
below:
SN Section Progress (Route Km)
(1) Delhi-Mumbai route: 1,423 Rkm
i Tilak Bridge – Junction cabin – Palwal 1,327
– Mathura –Kota-Nagda-Ratlam–
Vadodara-Virar section
ii Vadodara – Ahmedabad section 96
(2) Delhi – Howrah route: 1,210 Rkm
i. Chipyana – Tundla – Kanpur – 563
Subedarganj section
ii. Kanpur – Lucknow section 71
iii. Mirzapur - DDU (Excluding) section 64
iii. DDU(FOC)-Bhabua Road section 50
iv. Sasaram - Pheser section 43
v. Gaya -Sarmatarn- Nimiaghat section 159
vi. Chota Ambana - Bardhaman – Howrah 260
section
The above includes, three sections namely Vadodara - Virar, Gaya -
Sarmatarn & Jn Cabin – Palwal, totalling about 470 Rkm, Kavach in
which commissioned on 30.01.26.
10. In addition, track side Kavach implementation work has been taken up
on 21,794 RKM covering all GQ,GD,HDN and identified sections of
Indian Railways.
Page 8 of 1511. The total Progress of key items of Kavach on Indian Railway sections
are as under:-
SN Item Progress
i Laying of Optical Fibre Cable 11,547 Km
ii Installation of Telecom 1,721 Nos.
Towers
iii Station Data Centre 1,009 station
iv Installation of Track side 7,726 RKm
equipment
v Provision of Kavach in Loco 6,290 Nos.
12. In addition, work for installation of Kavach in 7,190 Locomotives and
1,200 EMU/MEMU has been taken up.
13. Further, Kavach Trials at 160 Kmph have been held successfully in
Chipyana Buzurg - Tundla section in the Delhi-Howrah route with
Vande Bharat Trainset.
14. The funds utilized on Kavach works so far up to Jun'26 is Rs. 3,875
Crores. The allocation of funds during the year 2026-27 is Rs. 2,066
Crores. Kavach work is going at good pace in the entire country.
Requisite funds are made available as per the progress of works.
Increasing of Speed potential on Indian Railways:
Speeding up of trains is a constant endeavor and a continuous process
which is dependent upon upgradation of tracks, signaling system, OHE,
high powered locos, modern coaches etc.
Upgradation and improvement of railway tracks on Indian Railways to
increase the speed potential have been carried out in a big way during last
12 years. The measures for track upgradation include use of 60 kg rails,
Page 9 of 15wider base concrete sleepers, thick web switches, weldable CMS
crossings, longer rail panels, H Beam sleepers, modern track renewal and
maintenance machines etc.
As a result of above measures, there has been significant increase in
speed potential of the tracks. The details of speed potential of railway
tracks during 2014 vis-a-vis 2026 are as under:
2014 2026
Sectional Speed
(kmph)
Track Km % Track Km %
130 & above 5,036 6.3 24,173 22.5
110 - 130 26,409 33.3 62,482 58.1
< 110 47,897 60.4 20,897 19.4
Total 79,342 100 1,07,552 100
It may be seen that about 81% of the railway tracks on Indian Railways
have been upgraded to 110 Kmph and above.
Further, two major routes i.e New Delhi – Mumbai & New Delhi – Howrah of
the Golden Quadrilateral have been taken up for enhancing the speed
potential up to 160 Kmph under Mission Raftaar.
Budget Utilization 2026-27:
Out of total Budget grant of Rs.2,93,030 Cr. in 2026-27, till July’26,
expenditure of Rs. 1,14,973 Cr. has been incurred i.e. about 39%.
High Speed Corridors:
Presently, the Mumbai-Amdavad High Speed Rail (MAHSR) Project (508 km)
is under execution. The Project is passing through the States of Gujarat,
Maharashtra and Union Territory of Dadra & Nagar Haveli with 12 stations
Page 10 of 15planned at Mumbai, Thane, Virar, Boisar, Vapi, Billimora, Surat, Bharuch,
Vadodara, Anand, Amdavad and Sabarmati.
Entire land (1389.5 Ha.) for MAHSR project has been acquired. All Statutory
Clearances have been obtained. All 1651 utilities have been shifted. The
delay in land acquisition in the State of Maharashtra has impacted the
project till 2021. The land acquisition picked up in 2022 in Maharashtra.
The progress of various major items so far is as under:
Item Progress
Piers 452 kms.
Girder 356 kms.
Track Bed 209 kms.
OHE Masts 190 kms.
The progress of stations is given below:-
S.N. Station Status
1 Sabarmati Foundation & structural works completed.
Finishing work have been taken up.
2 Amdavad Structural works completed. Finishing works
and track works have been taken up.
3 Anand/Nadiad
4 Vadodara Foundation & structural works completed.
Finishing work have been taken up.
5 Bharuch
Structural works completed and finishing works
6 Surat
have been taken up. At Surat, Bilimora and
7 Bilimora
Bharuch Track works have also been taken up.
8 Vapi
Page 11 of 159 Boisar Foundation works have been taken up and in
advanced stage. Structural works have been
10 Virar
taken up.
11 Thane
12 BKC (Mumbai) This is an underground station. Foundation
works almost completed and Base Slab has
been taken up.
The progress on the River Bridges is as under:-
S.N. River Name Status
1 Sabarmati River Sub-Structure work completed,
(480m) Superstructure work has been taken up.
2 Meshwa River Bridge construction completed. Track
(120m) works completed and OHE works have been
3 Vatrak River (280m) taken up at Mohar River. Track works in
4 Mohar (Shedhi) progress at Vatrak River.
River (160m)
5 Mahi River (720m) Foundation completed. Pier works and
Girder launching have been taken up.
6 Vishwamitri River Bridge construction completed.
(80m)
7 Dhadhar River
(120m)
8 Narmada River 21 out of 25 wells completed; 6 out of 24
(1366m) spans launched
9 Kim River (120m) Bridge construction completed.
10 Tapi River (720m) 09 out of 13 Pier Cap completed.
Page 12 of 1511 Mindhola River
(240m)
12 Purna River (360m)
13 Ambika River
(200m)
14 Venganiya River
(200m)
15 Kaveri River (120m)
Bridge construction completed. Track and
16 Kharera River
Electrical works have been taken up.
(120m)
17 Auranga River
(320m)
18 Par River (320m)
19 Kolak River (160m)
20 Daman Ganga River
(360m)
21 Darotha River (80m)
22 Jagani River (360m) Substructure works have been completed.
23 Vaitarna River 17 Pile Cap and 15 Pier (out of 58)
(2320m) completed.
24 Ulhas River Branch Temporary Access Bridge (TAB) completed
(120m) to start the foundation work.
25 Desai Khadi River Geo-technical Investigation (GTI) has been
Bridge (400m) completed and Design work has been taken
up.
The work of the under-sea tunnel (approximately 21 km) has commenced,
out of which 4.8 km of tunnel between Ghansoli and Shilphata in
Maharashtra has been completed.
Page 13 of 15On the Surat - Vapi section (97 km) entire civil works including river bridge
construction, have been completed and 86% of the track bed has been laid.
To strengthen national transport infrastructure, provide a fillip to regional
connectivity, economic growth, tourism, investment and employment
generation, and encourage modal shift from road and air transport to rail,
the Government has announced the development of the following seven
new High-Speed Rail (HSR) corridors in the Union Budget 2026-27: -
(i) Mumbai–Pune
(ii) Pune–Hyderabad
(iii) Hyderabad–Bengaluru
(iv) Hyderabad–Chennai
(v) Chennai–Bengaluru
(vi) Delhi–Varanasi
(vii) Varanasi–Siliguri
Post Budget announcement, the cost updation, alignment finalization etc.
have been taken up in DPR. Based on the experience gained from MAHSR
project, National High Speed Rail Corporation Limited (NHSRCL) has taken
up activities for a standardised set of designs and technical specifications
for the Infrastructure of future corridors, such as viaducts, bridges, tunnels
and stations, train control systems including train protection systems etc.
Being highly capital intensive, the decision to sanction any HSR Corridor/
Project depends on many factors such as outcome of DPR, techno-
economic feasibility studies and availability of resources such as financing
options etc.
Page 14 of 15Technological improvements in Indian Railways (IR):
Technological improvements in Indian Railways (IR) are a continuous
process. Some of the major technologies deployed/Piloted over Indian
Railways are as under:
1. Machine Vision Inspection System (MVIS): MVIS is an Artificial
Intelligence (AI)/ Machine Learning (ML) based system which generates
alert on detecting any hanging, loose or missing components of moving
trains.
2. Wheel Impact Load Detector (WILD): WILD is a way-side inspection
system that measures the impact of wheel on track to identify the
defective wheel in Rolling Stock.
3. Integrated Track Monitoring Systems (ITMS): ITMS are deployed for
comprehensive inspection and monitoring of Railway tracks. The ITMS
utilizes machine learning and image processing to monitor and detect
defects in railway track components such as rails, sleepers, and
fastenings. The data from ITMS is analysed for urgent and planned
maintenance of track. Presently four (04) ITMS are deployed for track
recording and monitoring of IR track.
*****