GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2899
TO BE ANSWERED ON 05.08.2026
CHENNAI-BENGALURU/HYDERABAD-BENGALURU HIGH SPEED RAIL
CORRIDORS
2899. SHRI P C MOHAN:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the current status of the 306 km Chennai-Bengaluru and
about 607 km Hyderabad-Bengaluru high speed rail corridors including
the progress on the final alignment survey including the Detailed
Project Report for each, which are likely to be completed by March
2027;
(b) the details of the length, number of stations and key alignment points
falling within Karnataka for each corridor;
(c) the expected timeline for commencement of construction of both
corridors; and
(d) the details of the projected travel time and overall benefits expected for
passengers after operationalisation of these corridor?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Presently, the Mumbai-Amdavad High Speed Rail (MAHSR) Project
(508 km) is under execution. The Project is passing through the States of
Gujarat, Maharashtra and Union Territory of Dadra & Nagar Haveli with 12
stations planned at Mumbai, Thane, Virar, Boisar, Vapi, Billimora, Surat,
Bharuch, Vadodara, Anand, Amdavad and Sabarmati.
Entire land (1389.5 Ha.) for MAHSR project has been acquired. All Statutory
Clearances have been obtained. All 1651 utilities have been shifted. The
Page 1 of 4
§delay in land acquisition in the State of Maharashtra has impacted the
project till 2021. The land acquisition picked up in 2022 in Maharashtra.
The progress of various major items so far is as under:
Item Progress
Piers 452 kms.
Girder 356 kms.
Track Bed 209 kms.
OHE Masts 190 kms.
The progress of stations is given below:-
S. No. Station Status
1 Sabarmati Foundation & structural works completed.
Finishing work have been taken up.
2 Amdavad Structural works completed. Finishing works
and track works have been taken up.
3 Anand/Nadiad
4 Vadodara Foundation & structural works completed.
Finishing work have been taken up.
5 Bharuch
6 Surat Structural works completed and finishing works
have been taken up. At Surat, Bilimora and
7 Bilimora
Bharuch Track works have also been taken up.
8 Vapi
9 Boisar Foundation works have been taken up and in
advanced stage. Structural works have been
10 Virar
taken up.
11 Thane
12 BKC (Mumbai) This is an underground station. Foundation
works almost completed and Base Slab has
been taken up.
Page 2 of 4The progress on the River Bridges is as under:-
S. No. River Name Status
1 Sabarmati River (480m) Sub-Structure work completed,
Superstructure work has been taken up.
2 Meshwa River (120m) Bridge construction completed. Track
3 Vatrak River (280m) works completed and OHE works have
4 Mohar (Shedhi) River been taken up at Mohar River. Track
(160m) works in progress at Vatrak River.
5 Mahi River (720m) Foundation completed. Pier works and
Girder launching have been taken up.
6 Vishwamitri River (80m) Bridge construction completed.
7 Dhadhar River (120m)
8 Narmada River (1366m) 21 out of 25 wells completed; 6 out of 24
spans launched
9 Kim River (120m) Bridge construction completed.
10 Tapi River (720m) 09 out of 13 Pier Cap completed.
11 Mindhola River (240m)
12 Purna River (360m)
13 Ambika River (200m)
14 Venganiya River (200m)
15 Kaveri River (120m)
16 Kharera River (120m) Bridge construction completed. Track
17 Auranga River (320m) and Electrical works have been taken up.
18 Par River (320m)
19 Kolak River (160m)
20 Daman Ganga River
(360m)
21 Darotha River (80m)
22 Jagani River (360m) Substructure works have been
completed.
23 Vaitarna River (2320m) 17 Pile Cap and 15 Pier (out of 58)
completed.
24 Ulhas River Branch Temporary Access Bridge (TAB)
(120m) completed to start the foundation work.
25 Desai Khadi River Geo-technical Investigation (GTI) has
Bridge (400m) been completed and Design work has
been taken up.
Page 3 of 4The work of the under-sea tunnel (approximately 21 km) has commenced,
out of which 4.8 km of tunnel between Ghansoli and Shilphata in
Maharashtra has been completed.
On the Surat–Vapi section (97 km) entire civil works including river bridge
construction, have been completed and 86% of the track bed has been laid.
To strengthen national transport infrastructure, provide a fillip to regional
connectivity, economic growth, tourism, investment and employment
generation, and encourage modal shift from road and air transport to rail,
the Government has announced the development of the following seven
new High-Speed Rail (HSR) corridors in the Union Budget 2026-27:-
(i) Mumbai–Pune
(ii) Pune–Hyderabad
(iii) Hyderabad–Bengaluru
(iv) Hyderabad–Chennai
(v) Chennai–Bengaluru
(vi) Delhi–Varanasi
(vii) Varanasi–Siliguri
Post Budget announcement, the cost updation, alignment finalization &
land survey etc. have been taken up in Detailed Project Report (DPR). The
details of the stations/cities covered, investment, route length, benefits
such as travel time etc. can be firmed up only after DPR is finalised.
However, being highly capital intensive, the decision to sanction any HSR
Corridor/Project depends on many factors such as outcome of DPR, techno
economic feasibility studies and availability of resources such as financing
options etc.
*****
Page 4 of 4