GOVERNMENT OF INDIA
MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE
RAJYA SABHA
UNSTARRED QUESTION NO. 2302
TO BE ANSWERED ON 12.03.2026
Clearances for industrial effluents
2302. SHRI PARIMAL NATHWANI:
Will the Minister of ENVIRONMENT, FOREST AND CLIMATE CHANGE be pleased to
state:
(a) whether environmental clearances have been granted during the last five years for
projects involving discharge of treated industrial effluents into the deep sea off the coasts
of Gujarat and Andhra Pradesh;
(b) the details of such projects, including location, industrial clusters involved, daily
discharge quantity permitted and length/depth of marine outfall pipelines;
(c) the monitoring mechanism presently in place to assess marine biodiversity impact and
compliance with Coastal Regulation Zone (CRZ) norms; and
(d) whether any violations, non-compliance notices or penalties have been recorded in
respect of such projects?
ANSWER
MINISTER OF STATE IN THE MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE
CHANGE
(SHRI KIRTI VARDHAN SINGH)
(a) & (b) The details of clearances granted during the last five years for projects involving
discharge of treated industrial effluents into the deep sea off the coasts of Gujarat and Andhra
Pradesh are given in the Annexure-I.
(c) In order to ensure monitoring of impacts on the marine environment and biodiversity,
projects involving discharge of treated effluents into the sea are required to undertake a Marine
Environmental Impact Assessment, including baseline environmental data and a marine
environmental monitoring plan covering biodiversity aspects. Further, the EAC may also
stipulate specific conditions, where required, for the regular monitoring of marine environment
and biodiversity status on the basis of baseline data. In such cases, these aspects are reported in
the six-monthly compliance report. As per the provisions of the CRZ Notification, the State
Government/Union Territory Coastal Zone Management Authorities (CZMAs) are primarily
responsible for enforcement and monitoring of the provisions of the Notification and for
facilitating its effective implementation. Further, in accordance with the Ministry’s notification
dated 30.09.2022, the State/UT CZMAs have been empowered under Sections 5, 10 and 19 of
the Environment (Protection) Act, 1986 to take necessary action for ensuring compliance with
the CRZ Notification.
1Moreover, the environmental non-compliance for combined EC and CRZ Clearances are
addressed as per provisions under Section 5, 15 and 19 of Environment (Protection) Act, 1986
and Rule 4 of Environment (Protection) Rules, 1986. Further, as per para 10 of Environment
Impact Assessment (EIA) Notification, 2006 on ‘Post Environmental Clearance Monitoring’, it
is mandatory for the project management to submit half-yearly compliance reports in respect of
the stipulated prior environmental clearance terms and conditions to the regulatory authority
concerned. The implementation of these provisions are guided by Standard Operating Procedure
(SoP) established vide Office Memorandum dated 25.11.2022 for post environmental clearance
monitoring and Compliance of projects, which prescribes the mechanism for taking action with
respect to the observed non-compliance, including procedure of seeking clarification, issuing
Show Cause Notice and concluding action. Recently, the Ministry has also notified Environment
Audit Rules, 2025 to strengthen the environmental compliance framework for projects operating
under various environmental laws. Besides, the State Pollution Control Boards are also
empowered to take remedial actions in cases of violation of Consent to Operate and Consent to
Establish conditions in accordance with Section 31A. of Air (Prevention and Control of
Pollution) Act, 1981 and Section 33A. of Water (Prevention and Control of Pollution) Act, 1974.
(d) As informed by the State Coastal Zone Management Authorities (SCZMAs) of Gujarat
and Andhra Pradesh, no such cases have been reported.
******
2Annexure -I
S.N. Name of the Location Name of Daily Available data on
project involving industrial discharge length/ depth of
the discharge of clusters quantity marine outfall
treated involved permitted pipelines
industrial
effluents into the
deep sea off the
coasts of
Gujarat
Gujarat
1. M/s. Sarigam Clean GIDC GIDC Sarigam 25 MLD Onshore length-
Initiative (CETP- Sarigam, 11.5 KM
Sarigam) for existing Ta:Umbergaon Off shore length -
CETP expansion from , Dist Valsad. 5.6 KM
12.5 MLD to 25 MLD Total Length-
17.11 KM
Depth- 7.8 meter
2. Dholera Special Dholera Dholera SIR 12 MLD Length - 13.5 KM from
Investment CETP to Discharge
Regional Point
Development
Authority
(DSIRDA)-60
MLD CETP
3. 50 MLD Sea Water Dholera Dholera SIR 79.332 MLD Length - 6.532 KM
Desalination Plant (Off shore - 4.65867
in Dholera SIR KM+ On
shore- 1.84701
KM)
4. Pipeline for 'Deep Porbandar Treated 80 MLD Length- 5.64 km (Off
sea disposal of effluent shore- 5 km + 0.64 km
treated collected On shore)
effluent (80 MLD) from
from Village Chikasa existing CETPs
near Navi Bandar, at Jetpur,
District Porbandar Bhatgam and
from proposed
CETP at
Manpur, Derdi
5. RSPL Chemical Village : Individual 1.2 MLD 1737.9 meter
Complex Kuranga, industry
Taluka :
Dwarka,
Dist : Dev
Bhumi
Dwarka
36. M/s GHCL Locati Individual 1.45 MLD 1. Outfall pipeline-
Limited. on: industry 1: 2770.17 meter
Villag length & 9.4
e: meter depth.
Bada, 2. Outfall pipeline-
Ta. 2: 3281.88 meter
Mand length & 10.7
vi, meter depth.
Dist:
Kutch
.
7. Nirma Ltd. (Soda Vill.: Kalatalav Individual 12 MLD 900 meter
Ash Division), Tal: Bhavnagar, industry
Bhavnagar DIST:
Bhavnagar,
8. Agrocel Industries Village, Avania Individual 0.255 MLD 7105 Meter
Pvt. Ltd., 364002 DIST: industry Length,
Bhavnagar Bhavnagar, 100 dia. pipeline
Ghogha
9. Vapi Green Environ Land GIDC Vapi 70 MLD Onshore length:
Limited ( ETP) Fall 15.43 KM
Point Offshore length:
identifi 14.25 KM
ed at Total Length:
Tata 29.68 KM
Wadi – Depth: 17.87
Coordi Meter
nates is
(20°21’6.
09” N,
72°48’33
.89"
E)
10. Gujarat Fluoro Dahej, Gujarat Individual 3.239 MLD Onshore pipeline
chemicals Ltd. industry length: 9 km &
Dahej Offshore pipeline
length is 3 km
11. PCPIR, SEZ-II, Dahej, Dahej, Gujarat GIDC- Dahej 90 MLD Total length
Gujarat (change in 4335.27 m
outfall location) Onshore pipeline
900 MLD 0.87 km and
offshore
pipeline 3.46 km
12. Expansion of Dahej, Individual 63.062 MLD Onshore length-381
petrochemical GUJARAT industry meter & Offshore
Complex of length–
Reliance industries 3261 m
Limited at Dahej
13. M/s. Grasim Veraval, Tal: Individual 27 MLD Length of Pipeline:
Industries Limited, Veraval, Dist: industry 1590 meters
Unit-Indian Rayon Gir Somnath, (Onshore: 430
meters,
Offshore: 1160
4meters)
Depth at Outfall point:
18 meters
14. GHCL Limited At:Sutrapada NA 16000 Length of Pipeline
, Tal: M3/Hour from Landfall
Sutrapada, point: 440 meters
Dist: Gir Depth: Depth at
Somnath, Outfall point: 10
meters
Andhra Pradesh
1. M/s. Shreas Industries 18°07’15” N Pharmaceutical 2770 KLD On shore: 10.3km
Ltd., & Off shore:3.95km
Pydibheemavaram, 83° 37’ 29” Depth: 14m
Srikakulam E
2. M/s. Auroactive 18009’10”N Pharmaceutical 589 KLD On shore:
Pharma Pvt. Ltd., & 14.102km Off
Pydibheemavaram, 83037’17”E shore: 1.064 km
Srikakulam. Depth: 9m
3. M/s. Divis 17056’14” N Pharmaceutical 1881 KLD Onshore (1.350
Laboratories Ltd., & 83028’52” km) Offshore (1.50
Unit-II, E km)
Chippada,Visakhapatn Depth: 15m
am
4. M/s. Divis 17.2095 N & Pharmaceutical 500 KLD On shore:140 m
Laboratories Ltd., Unit 82.4726 E Off shore:1140 m
-III, Ontimamidi Depth: 11.3m
Village, Thondangi
Mandal, Kakinada.
5. M/s. Lyfius Pharma 17° 6' Pharmaceutical 7768 KLD On shore:5.5 km
Pvt. Ltd.,AV Nagaram, 47.232'' N & Off shore:2km
Kakinada. 82° 14' Depth: 12.3
36.8664'' E
***********