GOVERNMENT OF INDIA
MINISTRY OF POWER
LOK SABHA
UNSTARRED QUESTION NO.919
ANSWERED ON 23.07.2026
COAL ALLOCATION FOR THERMAL POWER PROJECTS
919. SHRI G KUMAR NAIK:
Will the Minister of POWER
be pleased to state:
(a) the details of all proposals received from State utilities and power
procurement agencies for coal allocation to thermal power projects tied to long-
term Power Purchase Agreements (PPAs) since 2024, project-wise;
(b) the details of coal linkages approved pursuant to such proposals along with
the name of the generating company, project capacity, State and annual coal
quantity allocated;
(c) the total quantity of coal allocated to each private sector power producer
under such approvals since 2024;
(d) whether any additional coal allocation has been approved for expansion of
capacity or exercise of options under existing tenders and if so, the details
thereof; and
(e) whether the Government maintains data on the market share of different
private power producers in thermal power capacity supported by coal linkages
and if so, the details thereof?
A N S W E R
THE MINISTER OF STATE IN THE MINISTRY OF POWER
(SHRI SHRIPAD NAIK)
(a) to (d) : The details of proposals received from State utilities and power
procurement agencies for coal allocation to thermal power projects tied to long-
term Power Purchase Agreement (PPAs) since 2024 under erstwhile Shakti
Policy, 2017 and Revised Shakti Policy, 2025 including details of quantities
allocated to each private sector Independent Power Producers (IPPs) and coal
allocation approved for expansion of capacity is given at Annexure.
(e) : As on 31.03.2026, Coal India Limited (CIL) has long-term Fuel Supply
Agreements (FSAs) of 617.7 Million Tonnes (MT) under various schemes/policies,
of which 174.6 MT is with Private Sector Power Plants (IPPs) and 443.1 MT with
Central & State Sector Power Plants. As such, the ratio of Private Sector (IPPs)
to Central & State Sector Power Plants is 28:72.
As on 31.03.2026, Singareni Collieries Company Limited (SCCL) has long-
term Fuel Supply Agreements (FSAs) of 83.08 Million Tonnes (MT) under various
schemes/policies, of which entire 83.08 MT is with Central & State Sector Power
Plants. As such, the ratio of Private Sector (IPPs) to Central & State Sector Power
Plants is 0:100.
*******ANNEXURE
ANNEXURE REFERRED IN REPLY TO PARTS (a) TO (d) OF UNSTARRED QUESTION NO. 919 ANSWERED IN THE LOK SABHA ON 23.07.2026
*************
Details of proposals received from State utilities and power procurement agencies for coal allocation to thermal power projects tied to long-term Power Purchase Agreement (PPAs) since 2024:
Capacity for Coal linkage
Thermal Power projects SLC (LT)
Sl. Proposals received from which coal allocated/ Provision under which Linkage
(State Utilities & Power Sector Approval Remarks
No State linkage earmarked granted
Procurement Agencies) date
granted (MW) (MMTPA)
Goindwal Sahib TPP& Para B(i) of Erstwhile SHAKTI
1 Punjab State 540 2.2 01.03.2024 -
(PSPCL*) Policy, 2017
Now capacity revised from
Chandrapur TPS$ Unit-10 Para B(i) of Erstwhile SHAKTI
2 Maharashtra State 140 0.56 16.08.2024 660 MW to 800 MW. State
(MAHAGENCO**) Policy, 2017
GENCO expansion unit
Gandhinagar TPS U#6 Para B(i) of Erstwhile SHAKTI
3 Gujarat State 800 3.3 16.08.2024 -
(GSECL#) Policy, 2017
Sikka TPS U#5 Para B(i) of Erstwhile SHAKTI
4 Gujarat State 800 3.3 16.08.2024 -
(GSECL#) Policy, 2017
Ukai TPS U#8 Para B(i) of Erstwhile SHAKTI
5 Gujarat State 800 3.3 16.08.2024 -
(GSECL#) Policy, 2017
Grant of linkage for 50%
Udangudi TPS St-I Para B(i) of Erstwhile SHAKTI capacity as the unit is
6 Tamil Nadu State 660 3.4 16.08.2024
(TANGEDCO@) Policy, 2017 designed for 50% domestic
and 50% imported coal.
Grant of linkage for 50%
Ennore SEZ Para B(i) of Erstwhile SHAKTI capacity as the unit is
7 Tamil Nadu State 660 3.4 16.08.2024
(TANGEDCO@) Policy, 2017 designed for 50% domestic
and 50% imported coal.
TBCB+ is under progress. TPP& Para B(iv) of Erstwhile SHAKTI
8 Kerala - 500 2.69 22.08.2024 -
yet to be identified Policy, 2017
Uttar Pradesh Mirjapur TPP& (Adani Power Para B(iv) of Erstwhile SHAKTI
9 Private(IPPs) 1,600 5.72 13.02.2024 -
Limited) Policy, 2017
Salboni TPP& 11.06.2024/ Para B(iv) of Erstwhile SHAKTI
10 West Bengal Private(IPPs) 1,600 8.21 -
(JSW Energy Limited,) 26.06.2024 Policy, 2017
Salboni TPP& 11.06.2024/ Para B(iv) of Erstwhile SHAKTI
11 West Bengal Private(IPPs) 1,600 7.87 -
(JSW Energy Limited,) 26.06.2024 Policy, 2017
Raipur TPP&
01.03.2024/ Para B(iv) of Erstwhile SHAKTI
12 Maharashtra (Adani Power Ltd.) Private(IPPs) 1,600 8.19 -
04.03.2024 Policy, 2017
11.03.2025/ Para B(iv) of Erstwhile SHAKTI Plant name not yet
13 Maharashtra Adani Power Limited Private(IPPs) 1,600 8.16
13.03.2025 Policy, 2017 finalized Anuppur Ph-II (MP) -800
MW (Hindustan Thermal
projects Ltd.)
Para B(iv) of Erstwhile SHAKTI
14 Madhya Pradesh Newzone TPP (MP) - 1600 Private(IPPs) 4,100 20.16 27.11.2024 -
Policy, 2017
MW (Torrent Power Ltd.)
Anuppur (MP)- 800 MW
(Adani Power Ltd.)
Pirpainti TPP& Para B(iv) of Erstwhile SHAKTI
15 Bihar Private(IPPs) 2,400 10.43 11.02.2025 -
(Adani Power Ltd.) Policy, 2017
OPG Power Generation
Ltd.(150 MW)
Baradhara TPP (DB power) 11.06.2024/ Para B(iv) of Erstwhile SHAKTI
16 Karnataka Private(IPPs) 2,000 10.26 -
(125 MW) 26.06.2024 Policy, 2017
Kamalanga TPP (GMR
Energy) (100 MW)
Baradhara TPP (DB power) 11.06.2024/ Para B(iv) of Erstwhile SHAKTI
17 Assam Private(IPPs) 500 2.55 Utilized only for 125 MW
-125 MW 26.06.2024 Policy, 2017
TBCB+ is under progress. 01.03.2024/ Para B(iv) of Erstwhile SHAKTI
18 Rajasthan - 3,299 16.89 -
TPP yet to be identified 04.03.2024 Policy, 2017
TBCB+ is under progress. 11.06.2024/ Para B(iv) of Erstwhile SHAKTI
19 West Bengal - 800 3.1 -
TPP& yet to be identified 26.06.2024 Policy, 2017
TBCB+ is under progress. 11.06.2024/ Para B(iv) of Erstwhile SHAKTI
20 Uttar Pradesh - 4,000 20.88 -
TPP& yet to be identified 26.06.2024 Policy, 2017
TBCB+ is under progress. 11.03.2025/ Para B(iv) of Erstwhile SHAKTI
21 Uttarakhand - 1,320 6.72 -
TPP& yet to be identified 13.03.2025 Policy, 2017
TBCB+ is under progress. Para 2 (II) (A) (ii) (b) of Window I
22 Gujarat - 4,000 20.38 29.07.2025 -
TPP& yet to be identified of Revised SHAKTI Policy, 2025
TBCB+ is under progress for
developing the stranded
TBCB+ is under progress. Para 2 (II) (A) (ii) (b) of Window I
23 Tamil Nadu - 660 3.4 29.07.2025 brownfield Ennore TPS$
TPP& yet to be identified of Revised SHAKTI Policy, 2025
Expansion (1X660 MW)
project through PPP route.
TBCB+ is under progress. Para 2 (II) (A) (ii) (b) of Window I
24 West Bengal - 1,600 7.32 04.12.2025 -
TPP& yet to be identified of Revised SHAKTI Policy, 2025
Chapar Ultra-Supercritical Para 2 (II) (A) (ii) (b) of Window I
25 Assam Thermal Power Project (Adani Private(IPPs) 3,200 15.83 29.07.2025 of Revised SHAKTI Policy, 2025 -
Power Limited)
Para 2 (II) (A) (ii) (b) of Window I
Anuppur TPP& (800 MW)
26 Madhya Pradesh Private(IPPs) 1,000 4.83 29.07.2025 of Revised SHAKTI Policy, 2025 -
(Adani Power Ltd.)
Rajiv Gandhi TPP& at Hisar Para 2 (II) (A) (ii) (a) of Window I State GENCO expansion
27 Haryana State 800 3.14 04.12.2025
(HPGCL<) of Revised SHAKTI Policy, 2025 unitCoal linkage granted only
Marwa TPP& (2x500 MW) Para 2 (II) (A) (ii) (a) of Window I for the balance capacity as
28 Chhattisgarh State 1,000 0.4 16.03.2026
(CSPGCL) of Revised SHAKTI Policy, 2025 the plant is linked to coal
block
Satpura TPS$ Unit 13 (1 x 660 Para 2 (II) (A) (ii) (a) of Window I State GENCO expansion
29 Madhya Pradesh State 660 2.9 17.06.2026
MW) (MPPGCL) of Revised SHAKTI Policy, 2025 unit
Proposed power plant of
Para 2 (II) (A) (ii) (c) of Window I
30 Gujarat Torrent Power Limited (800 Private(IPPs) 724 3.2 17.06.2026 IPP Expansion unit
of Revised SHAKTI Policy, 2025
MW)
Proposal for 2800 MW coal
Para 2 (II) (A) (ii) (b) of Window I
31 Madhya Pradesh - linkage under
of Revised SHAKTI Policy, 2025
consideration
Proposal for 1600 MW coal
Para 2 (II) (A) (ii) (b) of Window I
32 Andhra Pradesh - linkage is under
of Revised SHAKTI Policy, 2025
consideration
Proposal for 800 MW coal
Panipat TPS&
33 Haryana State - linkage is under
(HPGCL)
consideration
Legend:
* - Punjab State Power Corporation Limited (PSPCL).
** - Maharashtra State Power Generation Company Limited (MSPGCL)
# - Gujarat State Electricity Corporation Limited (GSECL)
@ - Tamil Nadu Generation and Distribution Corporation Limited. (TANGEDCO)
< - Haryana Power Generation Corporation Limited (HPGCL)
& - Thermal Power Plant (TPP)
$ - Thermal Power Station (TPS)
+ - Tariff Based Competitive Bidding (TBCB)
***************