Parliament Question: Complaints on NH Works

Issued by Ministry of Road Transport and Highways · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

Executive Summary: This document is a response to Lok Sabha Unstarred Question No. 3150 regarding complaints and delays related to National Highway (NH) works in Uttar Pradesh. It details the number of complaints received, their resolution status, and provides a list of delayed NH projects, including those in Jaunpur district. The response also addresses the reasons for delays and cost escalations in these projects. Key Points / Main Content: Complaints and Grievances: - The Government receives complaints through Public Grievance Portals and an Online Media attention portal. - 119 complaints regarding corruption, material quality, and project status in Uttar Pradesh were received in the last three years and the current year via Public Grievance Portal. - 118 of these complaints have been examined and resolved, with remedial actions taken as needed. - One complaint received in July 2025 is currently being addressed. - 5 complaints regarding major deficiencies in NH works in Uttar Pradesh were received in the last five financial years and the current financial year, excluding those from social media or public grievance portals, with remedial works in progress. - 1,418 complaints related to NHs and the transport sector in Uttar Pradesh were received through the online media attention portal, with 1,406 cases closed. Delayed Projects: - 54 NH projects in Uttar Pradesh, including those in Jaunpur district, have been delayed beyond their original completion dates; details are annexed. - Reasons for delays include land acquisition issues, pre-construction delays, contractor financial difficulties, force majeure events, COVID-19, statutory clearances, and material scarcity. - Cost overruns occur in some delayed Engineering, Procurement and Construction (EPC) projects; price escalation is paid if the delay is not attributable to the contractor. - Damages are imposed if the delay is attributable to the contractor. Government Actions: - The Government is awarding projects after adequate land acquisition preparation. - Initiatives to prevent delays include streamlining land acquisition via the Bhoomi Rashi portal, revamping the Parivesh Portal for faster clearances, enabling online approval of General Arrangement Drawings (GAD) for Road over Bridges (ROBs) and Road under Bridges (RUB) from the Railways, and conducting review meetings with stakeholders. Annexure Details: - The annexure lists 54 delayed NH projects in Uttar Pradesh, including those in Jaunpur district, with their original and revised target dates, project costs, and districts. Impact Analysis: Ministry of Road Transport and Highways: Impact: Responsible for addressing complaints, overseeing project completion, and implementing measures to prevent delays and cost overruns. Action Required: Continue to monitor project progress, address grievances promptly, and enforce measures to streamline project execution. Executing Agencies: Impact: Responsible for the execution and timely completion of NH projects. Action Required: Provide accurate information on project status, address deficiencies promptly, and adhere to contract conditions to avoid penalties for delays. Contractors: Impact: Subject to potential financial implications due to project delays, including price escalation or damages. Action Required: Expedite project progress, address any factors contributing to delays, and adhere to contract conditions to minimize financial risks. State Government of Uttar Pradesh: Impact: Collaborates with the Ministry of Road Transport and Highways to facilitate project execution and address issues such as land acquisition and statutory clearances. Action Required: Streamline processes related to land acquisition and clearances to support timely project completion. Citizens of Uttar Pradesh: Impact: Affected by the quality and timely completion of NH projects, impacting transportation and connectivity. Action Required: Utilize public grievance portals to report issues and provide feedback on NH works.

Key Entities Referenced

Jaunpur district: A district in Uttar Pradesh, India, specifically mentioned regarding delayed road development projects. Prayagraj: A district in Uttar Pradesh, India where bridge construction is being carried out. COVID: The COVID-19 pandemic, mentioned as a reason for delays in road projects. Uttar Pradesh: A state in northern India, where the road projects in question are located. Ministry of Road Transport and Highways: The Indian government ministry responsible for the development and maintenance of the National Highways in India. Lok Sabha: The lower house of the Parliament of India. Nitin Jairam Gadkari: The Minister of Road Transport and Highways in India. National Highway (NH): A network of highways that is managed and maintained by the Ministry of Road Transport and Highways.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS LOK SABHA UNSTARRED QUESTION NO. 3150 ANSWERED ON 07TH AUGUST, 2025 COMPLAINTS ON NH WORKS 3150. ADV PRIYA SAROJ: Will the Minister of ROAD TRANSPORT AND HIGHWAYS सड़क परिवहन औि िाजमार्ग मंत्री be pleased to state: (a) the number of complaints received via public grievance portals or from State Governments regarding corruption, use of poor-quality materials or misreporting of completion status in road projects under National Highway (NH) works in Uttar Pradesh during the last three years; (b) the number of these complaints that have been investigated and resolved and the number that remain pending; (c) the list of road development and upgradation projects in Uttar Pradesh, especially in Jaunpur district, that have been delayed beyond their original completion deadlines; and (d) the extent of cost escalation in these projects and the reasons for such delays? ANSWER THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS (SHRI NITIN JAIRAM GADKARI)(a) and (b) The Government receives complaints/ grievances via Public Grievance Portals regarding various issues. Apart from this, Government in Ministry of Road Transport & Highways has also institutionalized arrangement for receiving complaints through its Online Media attention portal. The Government takes cognizance of these grievances and takes up necessary remedial actions from time to time, which is a continuous process. 119 number of complaints/ grievances have been received through Public grievance portal (excluding complaints received from other social media platforms) regarding alleged corruption, quality of materials/ construction, tolling of damaged roads/ incomplete projects pertaining to National Highway (NH) works in the State of Uttar Pradesh during the last 3 years and current year. Of these, 118 number of complaints have been duly examined, necessary remedial actions have been taken wherever required and resolved. One complaint has been received recently in July, 2025, for which necessary action has been initiated towards its resolution. As per the information provided by the executing agencies, 5 numbers of complaints regarding major deficiencies/ damages in NH works pertaining to the state of Uttar Pradesh have been received/ found during the last five financial years and current financial year (excluding complaints received through various social media platforms/ public grievance portal, etc.). Necessary remedial works taken up for rectification of these deficiencies/ damages are at various stages of progress. Apart from above, 1,418 number of cases of complaints pertaining to various issues regarding NHs and transport sector for the State of Uttar Pradesh have been received through online media attention portal maintained by the Ministry of Road Transport & Highways. Out of these, 1,406 cases have been closed/ redressed so far.(c) and (d) 54 number of NHs projects taken up in the State of Uttar Pradesh (including NHs projects in Jaunpur District) have been delayed beyond the original stipulated completion date. Details of these projects are annexed. Various factors such as issues related to land acquisition, delays in pre-construction activities, financial difficulties faced by contractors, force-majeure events, COVID, statutory clearances and scarcity of construction materials etc. have resulted in delays and cost overrun in certain projects. All delayed projects do not face cost escalation. In Engineering, Procurement and Construction (EPC) projects, cost overrun is incurred in some delayed projects. If delay is not attributable to the Contractor, price escalation is paid as per defined format in contract condition. This may or may not result in additional cost as the final value of price escalation depends upon final settlement of bills after expiry of the project contract/ concession period. If delay is attributable to the Contractor, damages are imposed and there is no additional cost due to delay. The Government has taken number of steps to prevent such delay like awarding projects after adequate preparation in terms of land acquisition. Also, various initiatives including streamlining and expediting the land acquisition process through Bhoomi Rashi portal, revamping the Parivesh Portal to facilitate faster forest and environmental clearances, enabling online approval of General Arrangement Drawings (GAD) for Road over Bridges (ROBs) and Road under Bridges (RUB) from the Railways, and conducting review meetings at various levels with all stakeholders, including State Governments. The Government is taking all necessary steps for timely completion of these projects.ANNEXURE ANNEXURE REFERRED TO IN REPLY TO PART (c) AND (d) OF LOK SABHA UNSTARRED QUESTION NO. 3150 FOR ANSWER FOR 07.08.2025 ASKED BY ADV PRIYA SAROJ REGARDING COMPLAINTS ON NH WORKS. Details of NHs projects taken up in the State of Uttar Pradesh (including NHs projects in Jaunpur District) those have been delayed beyond the original stipulated completion date (Amount in Rupees Crore) Sl. Original Revised Total Target date Target Date District Project Name Projec No of of t Cost Completion Completion Jaunpur, Widening & Upgradation to four lane configuration from 1 Km.34.900 (Bhadohi) to 396 14.05.2024 30.11.2025 Bhadohi km.73.134 (Jaunpur) of NH- 135A on EPC mode Bareilly, Shahjaha npur, Balance work of Bareilly- Hardoi, Sitapur section NH-24 (New 2 697.42 16.03.2021 Completed Lakhimpu NH-30) from Km. 262.000 to r Km. 419.590 Khiri, Sit apur Improvement and Up- gradation of Existing Road to 2/4-lane with Paved Shoulder Shahjaha 3 from Km.40.000 to 88.750, 338.57 02.02.2025 09.09.2025 npur start of Khutar Bypass to start Bypass of Shahjahanpur of NH-731Sl. Original Revised Total Target date Target Date District Project Name Projec No of of t Cost Completion Completion Construction of Balance 3 No Shahjaha Major/ Minor Bridges at Km. npur, 327+545, Km.411+105 & Km. Hardoi, 415+865, 01 Nos. VUP at Km. 4 63.75 22.02.2025 Completed Lakhimpu 416+685 and 2-Lane Cross- r Khiri Flyover at Km. 413+830 on Sitapur existing 4-Laning of Bareilly- Sitapur of NH-24 Kanpur Nagar, 6L of Chakeri - Allahabad 5 Fatehpur, from 483.687 to km. 628.753 2159 09.07.2021 Completed Kausha of Old NH-02 mbi 6 Lucknow Lucknow Ring Road Pkg-1 1062 06.02.2023 Completed 7 Lucknow Lucknow Ring Road Pkg-2 981 05.12.2021 Completed Barabank 8 Lucknow Ring Road Pkg-3A 292.07 14.01.2021 Completed i Kanpur Lucknow Expressway 9 Lucknow 1413 30.07.2025 30.10.2025 Pkg-1 Kanpur Lucknow Expressway 10 Unnao 1513 08.05.2025 30.09.2025 Pkg-2 11 Lucknow Lucknow Hardoi Pkg-4 280.72 23.10.2024 30.09.2025 Western side spur of Rampur- Rudrapur Section connecting NH-24 to NH-87 bypassing 12 Rampur 240.4 01.11.2024 31.03.2026 Rampur town” (Design Km 00+000 to Km Design Km 13+700(Length= 13.70 km) 2-Lane Existing Rampur Bypass of Rampur to be developed to 4-Lane in the 13 Rampur 188.91 15.04.2024 30.09.2025 State of Uttar Pradesh (Km 0+000 to Km 10+190) (Length= 10.19 km)Sl. Original Revised Total Target date Target Date District Project Name Projec No of of t Cost Completion Completion 4L Prayagraj Greenfield By- pass from design Km 50+860 (near Nibi Kala Uperhar) to 14 Prayagraj design Km 64+763 on NH-19 349.48 26.03.2025 11.10.2025 (near Khodaypur Kasgaon) including Interchange loop at NH-19 Pkg-3 Construction of 4 Lane NH-29 Bypass connecting NH-29 (near Sandaha Village Km. 11.170 of NH-29) (Revasa Village Km. 818.800 of NH-2) as part of Bypass to Varanasi 15 Varanasi 949 14.02.2022 15.01.2026 (Phase II, Package 2) from Design Chainage Km. 30.600 to Km. 57.320 26.720 Km. (Total Length 27.270 Km. including interchange loop at NH-2) Improvement and Rehabilitation of Existing Ayodhya Bypass from Design 16 Ayodhya 218 07.03.2025 27.08.2025 Km 121+600 to Km 144+020 (Design Length 22.420 km) of NH-28 (New NH-27) 4-laning of Varanasi Gorakhpur section of NH-29 from km 88.000 (design Gorakhpu Chainage 84.160) to km 17 840 07.10.2019 30.11.2025 r 148.000 (design Chainage 149.540) [Package-III from village Birnon to Village Amilla]Sl. Original Revised Total Target date Target Date District Project Name Projec No of of t Cost Completion Completion 4-laning of Varanasi Gorakhpur section of NH-29 from km 148.000 (design Gorakhpu 18 Chainage 149.540) to km 1030 07.10.2019 30.10.2025 r 208.300 (design Chainage 215.160) [Package-IV from Village Amilla to Gorakhpur] Four Laning of Sonauli - Gorakhpur section of NH-29E Gorakhpu from Design Ch. 0+000 to 19 1458 05.03.2025 12.02.2026 r Design Ch. 79+540 (from Existing Ch. 0+000 to Existing Ch. 80+295) 2/4 Laning with PS of Raebareli to Jagdishpur 20 Raebareli 720.81 06.01.2024 30.09.2025 section (Km 0.000 to Km 47.800) of NH-330A Construction of Four Lane Highway from Gazipur - Ballia - UP/Bihar State Border Azamgar 21 (Greenfield) section of NH- 1706.5 02.07.2025 29.12.2025 h 31: Package-I [from Hridaipur (km 0.000) to Shahapur (km 42.500)] Construction of Four Lane Highway from Gazipur - Ballia Azamgar - UP/Bihar State Border 22 617.89 14.06.2025 11.12.2025 h (Greenfield) section of NH- 31: Package-IV [Buxar Spur of length 17.270 km]Sl. Original Revised Total Target date Target Date District Project Name Projec No of of t Cost Completion Completion Balance work of Construction of Ring Road for 23 Raebareli Raebareli City on eastern 320 04.04.2022 31.10.2025 side of NH-24B (Phase-1) on EPC mode. Construction of two lane Lakhimpu ROBs at km.103.907 & 24 100 20.06.2022 30.09.2025 r kheri km.120.985 of NH-730 on EPC mode Construction of ROB at LC Sonebha 25 no.50/B/E at km.298.000 on 29 18.04.2023 31.12.2025 dra NH-75E on EPC mode Widening of existing four lane to six lane road from km 26 Meerut 3.000 to km 7.469 of NH-235 45 01.01.2024 Completed (New NH-334) under EPC mode Rehabilitation & Upgradation of NH-731A from Km.0.00 to Pratapga 27 Km.35.00 to 2-lane with 265 30.08.2023 30.09.2025 rh paved shoulder under EPC mode Construction of 6-lane bridge on Ganga on NH-96 and its 28 Prayagraj 1948 15.02.2024 30.06.2026 approaches in Phaphamau Allahabad on EPC mode Construction of Two lane with paved shoulder from Chandaul Km. 0+000 to Km.10+603 29 128 19.03.2024 31.10.2025 i (UP-Bihar Border to Chandauli) of NH-219 on EPC mode Basti, Improvement and upgradation to two lane with 30 Santkabir Paved Shoulder configuration 307 02.05.2024 30.11.2025 Nagar from existing km 55.00 to km 90.00 (Design length 34.76)Sl. Original Revised Total Target date Target Date District Project Name Projec No of of t Cost Completion Completion of NH-227A (near Chhapia Village to near Sikriganj) on EPC Mode. Construction of one flyover at Km 2+735 and one Major 31 Pilibhit 127 08.06.2024 31.10.2025 bridge at Km 31+260 on NH- 730 on EPC basis Etawah, Widening & Strenghtening of section from Bharthana 32 chowk to Kodarkoot (km.0.00 262 18.09.2024 30.09.2025 Auraiya to km.40.00) of NH-91-A on EPC mode Construction of Gilaula bypass with 2L+PS Shrawast configuration starts near km 33 62 05.11.2024 30.09.2025 i 281.930 of NH-730 and ends near km 284.900 of NH-730 on EPC mode Construction of ROB at 34 Banda 51 24.03.2025 08.08.2026 Km.202.992 on NH-76 Balance work of Construction of bypass for providing inter connectivity Pratapga along National Highway (NH) 35 82 13.05.2025 15.09.2025 rh around the Pratapgarh City (Pratapgarh bypass) on item rate tender from km.2.9 to Km.13.88 (Pkg.II) Siddharth Construction of Shohratgarh 36 189 23.05.2025 28.02.2026 nagar Bypass on NH-730Sl. Original Revised Total Target date Target Date District Project Name Projec No of of t Cost Completion Completion Improvement and upgradation to two lane with paved shoulder configuration Gorakhpu 37 from existing km 90.00 to 403 10.06.2025 31.10.2025 r 130.00 (Design length 39.15) of NH-227A (near Sikriganj to Barhalganj) Construction of ROB at 38 Mahoba Km.146.488 of NH-76 79 19.06.2025 31.12.2025 including approaches Construction of Pratapgarh Pratapga 39 Bypass (Extension) 225 30.06.2025 25.02.2026 rh connecting NH-31 to NH-330 Rehabilitation and upgradation to 2L+PS of Near 40 Etawah Karri village-Etawah section 211 17.02.2024 31.08.2025 (Km30.000 to Km 57.346) (Pakage-II) of NH-92 Shahjaha Rehabilitation and npur, upgradation to 2L+PS of Miranpur Katra to radhaita section of NH-730C 41 173 27.07.2024 31.10.2025 (Km.114.000 to Km 137.250) Pilibhit (pakage-III) under GNHCP with the loan assistance of world Bank on EPC mode. Rehabilitation and upgradation to 2L+PS of Mainpuri, 42 Bewar, near Karri village 237 15.03.2024 31.10.2025 Etawah section (Km0.00 to Km30.00) (Pakage-I) of NH-92Sl. Original Revised Total Target date Target Date District Project Name Projec No of of t Cost Completion Completion Rehabilitation and Farrukha upgradation to 2L+PS of 43 bad, Mai Bewar- Allahaganj- section of 325 23.11.2024 31.10.2025 npuri NH-730C (Km.0.000 to Km 52.770) (pakage-I) Construction of Greenfield Connectivity to Jewar Gautamb International Airport from 44 udh 1660.5 20.06.2025 18.03.2026 DND-Faridabad-Ballabhgarh Nagar Bypass KMP Link - Spur to Delhi Mumbai Expressway Construction of 4 lane connector from Delhi Meerut Ghaziaba Expressway (Km. 50+000 of 45 d and Pkg-IV) to Km. 8+520 of NH- 1147.3 29.03.2024 31.12.2025 Meerut 235 in the state of Uttar Pradesh on EPC Mode (Length 14+600 Kms) Development of six-lane access controlled in Uttar Ghaziaba Pradesh portion of Delhi- 46 d and Saharanpur Highway from 2002.8 07.11.2023 31.08.2025 Baghpat Delhi/UP Border to EPE Junction (Ch. 14.750 to Ch. 31.600) Spur of Meerut-Garh- Mukteshwar section(NH- 47 Meerut 709A) connecting NH-119 224.96 16.02.2025 31.10.2025 and NH-58 bypassing Meerut Town on EPC Mode. Bijnor - Kotawali section of 48 Bijnor NH-709AD (package-iv)from 188.59 03.05.2023 25.08.2025 Km. 153.660 to Km. 175.280Sl. Original Revised Total Target date Target Date District Project Name Projec No of of t Cost Completion Completion 6L access control Greenfield highway of Vill-Khyawari to Saharanp 49 Vill-Latifpur at Saharanpur 1428.2 31.08.2024 30.09.2025 ur Bypass from Km. 82.000 to Km. 119.790 (Pkg-4) 6L access control Greenfield Baghpat, highway of Vill-Lohadda to 50 Muzaffar Vill-Karaunda Mahajan from 1335.5 31.08.2024 30.09.2025 nagar Km. 27.000 to Km. 56.500 (Pkg-2) 6L access control Greenfield highway of Vill-Karaunda 51 Shamli Mahajan to Vill-Khyawari 1160 31.08.2024 30.09.2025 from Km. 56.500 to Km. 82.000 (Pkg-3) 4L Spur of Panipat - Shamli connecting NH-709AD (Panipat – Shamli – 52 Shamli 326.79 13.10.2024 30.09.2025 Muzaffarnagar) and NH-709A (Karnal – Meerut) bypassing Shamli district (UP) 6L access controlled Greenfield highway of Junction of EPE (Vill.- 53 Baghpat 1602 31.08.2024 30.09.2025 Mavikalan) to Vill.-Lohadda from Km. 0.000 to Km. 27.000 (Pkg-1) Shamli, 4 laning of Shamli Byapss- 54 Saharanp Saharanpur section of NH- 739.09 26.11.2022 30.09.2025 ur 709B Pkg-2 *****