GOVERNMENT OF INDIA
MINISTRY OF PORTS, SHIPPING AND WATERWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 1269
ANSWERED ON 10.2.2026
COMPLETION, DELAYS AND IMPLEMENTATION GAPS OF SAGARMALA
PROJECT
1269. SHRI DIGVIJAYA SINGH:
SMT. PHULO DEVI NETAM:
Will the Minister of PORTS, SHIPPING AND WATERWAYS be pleased to state:
(a) the year-wise data since Sagarmala’s launch on projects added, projects dropped or put on
hold and projects re-scoped due to delays or infeasibility;
(b) the project-wise list of the 131 projects which are in development stage, including original
approval date, latest revised completion date and present stage of execution;
(c) the details of original project cost and the latest estimated cost for the 131 projects still at
the development stage; and
(d) how many projects have been delayed by more than three years solely due to land
acquisition issues and the cumulative cost escalation attributable to these delays?
ANSWER
MINISTER OF PORTS, SHIPPING AND WATERWAYS
(SHRI SARBANANDA SONOWAL)
(a) to (c): Since the inception of the Sagarmala scheme in March 2015, 186 projects have been
sanctioned for financial assistanceby Ministry of Ports, Shipping and Waterways. However,
sanctions of 58 projects have been withdrawn from time to time in terms of Sagarmala funding
guidelines to maintain fiscaldiscipline. No project has been re-scoped due to delay or non-
feasibility. Year wise details of projects sanctioned and sanction withdrawn for funding under
Sagarmala scheme is available at annexure-1.
At present 128 projects are funded Sagarmala scheme. Out of these, 78 projectshave
been completed and 50 projects areunder implementation. The details of these 128 projects
including sanction date, completion date, present status and project cost is available at
annexure- 2.
(d) No project under Sagarmala scheme have delayed by more than three years onaccount
of land acquisition and cost escalation.Annexure- 1
The year wise details of projects sanctioned and sanction withdrawn for funding under
Sagarmala scheme:
Financial
Year
61-5102 71-6102 81-7102 91-8102 02-9102 12-0202 22-1202 32-2202 42-3202 52-4202 62-5202
latoT
Projects
9 34 20 23 6 17 29 30 4 2 12 186
sanctioned
Sanction
0 0 0 0 0 0 0 0 0 55 3 58
withdrawnAnnexure- 2
The details of 128 projects funded under Sagarmala scheme:
Sanction Completion Project Project cost
SI. No. Project Name State/UT
Date date Status (in ₹ crore)
Providing separate
Andaman
approach way for cargo
1 and Nicobar 15/01/2021 31/12/2023 Completed 10.91
movement in Havelock
Island
jetty at Havelock
Construction of coastal Andhra
2 01/04/2014 30/09/2017 Completed 43.00
Berth at VPT Pradesh
Construction of grade
separator from H-7 area
to Port connectivity Andhra
3 27/02/2017 06/10/2020 Completed 46.34
Road by passing Pradesh
Convent Junction -
Visakhapatnam Port
2 to 4 laning of port
Andhra
4 road connectivity to NH 30/12/2015 30/09/2017 Completed 77.00
Pradesh
– 5 -Phase II
DDUGKY Phase I Andhra
5 28/07/2016 30/09/2018 Completed 0.28
Andhra Pradesh Pradesh
Centre of Excellence in
Maritime and Andhra
6 30/10/2017 30/12/2018 Completed 574.00
Shipbuilding - CEMS - Pradesh
AP - 18 out of 24 Labs
Construction of fishing
Andhra
7 harbour at Juvvaladinne 18/03/2020 30/01/2025 Completed 288.00
Pradesh
in Nellore District
Improvement of
Kakinada Anchorage Andhra
8 02/06/2021 28/02/2024 Completed 73.34
Ports infrastructure in Pradesh
East Godavari district
Recycling/Reuse of
Sewage Treated Water
from Sewarage
Infrastructure
9 Goa 13/03/2024 15/06/2025 Completed 3.18
Development
Corporation of goa Ltd
(SIDCGL) located at
KatemBaina
Road circulation plan
for ease of movement of
10 Goa 20/09/2018 11/03/2019 Completed 19.35
break bulk cargo at
Mormugao
Full rake wagon
11 Goa 26/09/2016 06/01/2019 Completed 17.65
handling line withSanction Completion Project Project cost
SI. No. Project Name State/UT
Date date Status (in ₹ crore)
paving 30m wide at
Mormugao
Removal of 2 No.s
Mooring of Spiral in the
12 Goa 25/02/2019 23/09/2019 Completed 13.87
area of Cruise Berth -
Mormugao
2nd Full rake handling
13 line RD 8A with 30m Goa 27/09/2019 21/10/2021 Completed 6.59
paving
Construction of an Up-
14 Ramp at MPT Railway Goa 11/11/2020 30/11/2024 Completed 21.99
yard Baina.
Construction of 12m
wide concrete road
15 connecting berth 5 6 7 8 Goa 09/02/2021 03/06/2023 Completed 9.51
& 9 to new entry / exit
road
Balance Portion 4 Lane
road connectivity to
16 Goa 16/03/2024 30/01/2026 Completed 719.00
NH17 - for Mormugao
Port
Installation of 3 MWp
Solar Power Plant with
17 Goa 19/06/2025 21/05/2025 Completed 11.91
Virtual Net Metering on
Turnkey Basis
Coastal jetty at
18 Gujarat 27/02/2017 30/04/2025 Completed 108.00
Navlakhi for cement
Capital Dredging work
of Ro-Pax Ferry
19 services between Gogha Gujarat 21/09/2016 30/10/2018 Completed 208.85
and Dahej in Gulf of
Cambay.
Construction of RoRO/
20 Ro-Pax Facility at Gujarat 15/03/2021 30/12/2022 Completed 98.42
Hazira
Upgradation of
Dredging of Ghogha
Channel, Turning Circle
21 Gujarat 30/03/2022 30/11/2023 Completed 62.49
and Approach Channel
to achieve depth of 7
meter".
Third stage expansion
including modernisation
22 Karnataka 25/01/2017 30/12/2023 Completed 50.00
of the existing fishing
harbour of Malpe inSanction Completion Project Project cost
SI. No. Project Name State/UT
Date date Status (in ₹ crore)
Udupi District in
Karnatak
Modernisation of the
existing fishing harbour
23 Karnataka 29/12/2016 30/09/2018 Completed 19.00
at Amadalli in Uttara
Kannada
DDUGKY Phase I
24 Karnataka 05/08/2016 30/09/2018 Completed 1.53
Karnataka
Installation of Fire
25 Fighting Equipment at Karnataka 03/03/2022 30/07/2025 Completed 18.21
Karwar Port
Refurbishment and
Capacity enhancement
26 of Coastal liquid Kerala 24/04/2015 13/01/2018 Completed 19.27
terminal -COT and
NTB at CoPT
Construction of
27 Multipurpose Coastal Kerala 21/11/2017 27/10/2020 Completed 18.50
Berth at Kollam
Construction of Fishing
28 Harbour at Thalai in Kerala 29/12/2016 19/05/2018 Completed 35.00
Kannur District
Construction of Mini
Fishing
29 Kerala 25/01/2017 30/12/2018 Completed 30.00
HarbourChettuva in
Thrissur District
Reconstruction of South
Coal Berth at Cochin
30 Kerala 13/12/2019 17/08/2022 Completed 19.30
Port for handling
chemicals
Development of RORO
facilities for handling
31 Kerala 22/04/2022 30/06/2024 Completed 12.46
propylene and other
cargo at Cochin Port
Passenger Jetty at
32 Janjira Fort, Raigad Maharashtra 14/10/2022 30/01/2026 Completed 121.23
District
Construction of break
33 Maharashtra 04/03/2016 15/07/2018 Completed 72.14
water at Mandwa
Ro Ro service at
Mandwa -Phase 2 of
34 Maharashtra 26/09/2016 15/07/2018 Completed 63.00
Mandwa port
development
Construction of Ro-Ro
35 Maharashtra 14/12/2016 09/02/2024 Completed 6.73
jetties at VasaiSanction Completion Project Project cost
SI. No. Project Name State/UT
Date date Status (in ₹ crore)
Construction of
approach jetty and
sloping berth jetty and
36 Maharashtra 14/12/2016 01/12/2020 Completed 7.25
approach road to
facilitate Ro Ro jetty at
Bhayander
Construction of Ro Ro
37 Maharashtra 27/12/2016 30/10/2021 Completed 6.75
jetty atNarangi (Virar)
Construction of jetties
38 Maharashtra 22/12/2016 22/02/2024 Completed 7.40
at Ghodbunder
Construction of Ro Ro
Jetty at Malvan
39 Passenger Jetty at Maharashtra 27/12/2016 15/10/2021 Completed 10.63
Sindhudurg Port in
Maharashtra
Dredging in the
Navigational Channel
40 Maharashtra 20/11/2017 15/07/2018 Completed 16.54
for Ro-Ro Pax Services
at Mandwa
Stage II expansion of
41 Mirkawada Fishing Maharashtra 29/12/2016 31/03/2020 Completed 75.00
Harbour in Ratnagiri
DDUGKY Phase I
42 Maharashtra 28/07/2016 30/06/2019 Completed 5.50
Maharashtra
Centre of Excellence in
Maritime and
43 Shipbuilding -CEMS - Maharashtra 30/10/2017 28/02/2019 Completed 191.00
Maharashtra-6 out of 24
Labs
Construction of
passenger boat landing
44 Maharashtra 17/08/2020 17/04/2017 Completed 7.68
jetty at KanhojiAngre
Island
Construction of Coastal
45 Maharashtra 22/09/2017 31/03/2021 Completed 143.00
Berth at JNPT
Construction of Fishing
46 Harbor at Karanja, Maharashtra 13/08/2018 15/09/2023 Completed 149.80
Raigad district
Construction of
47 Maharashtra 23/07/2018 30/09/2021 Completed 6.50
Tourism jetty at Belapur
Construction of tourism
48 Jetty at Veldur, Distt.- Maharashtra 18/07/2018 31.06.24 Completed 7.06
Ratnagiri
Construction of Ro-Ro
49 Maharashtra 23/07/2018 31/07/2024 Completed 7.37
Jetty atSanction Completion Project Project cost
SI. No. Project Name State/UT
Date date Status (in ₹ crore)
AmbadaveShigwan in
Raigad District
‘Construction of
Approach road to
50 Maharashtra 26/03/2019 30/01/2020 Completed 15.00
Kharwadeshwari Jetty
in District Palghar
Construction of Third
51 Chemical Berth at Maharashtra 27/01/2022 27/09/2024 Completed 161.00
Pirpau, MbPT
SCADA and PLC
automation system at
52 Maharashtra 04/05/2022 31/07/2024 Completed 22.77
Marine Oil Terminal at
Mumbai Port
DDUGKY Phase I
53 Odisha 01/08/2016 31/10/2019 Completed 3.72
Odisha
Capital Dredging for
54 Puducherry 30/03/2018 31/12/2022 Completed 27.65
Puducherry Port
Development and
Operation of a full-
fledged Truck Parking
55 Terminal adjacent to Tamil Nadu 24/03/2016 06/12/2017 Completed 23.69
NH7A opposite to
Fisheries college at V.
O .Chidambaranar
Coastal berth with
dredged depth of 10.0m
56 to handle vessels up to Tamil Nadu 23/06/2015 19/12/2017 Completed 36.00
15000 DWT -length
150m at VoCPT
Coastal Cargo Berth at
57 Tamil Nadu 2015-16 21/11/2019 Completed 80.00
ChPT
Construction of
Breakwater both in
North and South side of
entrance channel-
58 Berth-1- Berth-2 and Tamil Nadu 27/02/2017 30/09/2023 Completed 135.00
Capital Dredging at
Cuddalore Port -From
entrance channel till
cargo berths
Development of paved
storage yard at Chennai
59 Tamil Nadu 16/02/2018 16/06/2023 Completed 51.46
Port for handling export
cargo
60 Construction of Bunker Tamil Nadu 23/02/2018 31/01/2023 Completed 44.00Sanction Completion Project Project cost
SI. No. Project Name State/UT
Date date Status (in ₹ crore)
berth at Chennai Port
Construction of a
fishing harbour at
61 Tamil Nadu 26/12/2016 31/08/2019 Completed 148.00
Poompuhar in
Nagapattinam District
Expansion of fishing
harbour at
62 Tamil Nadu 25/01/2017 30/09/2016 Completed 74.00
Chinnamuttomin
Kanyakumari District
DDUGKY Phase I
63 Tamil Nadu 09/08/2016 30/09/2018 Completed 2.94
Tamil Nadu
Construction of
widening the
Korampallam Surplus
course bridge and rail
64 Tamil Nadu 07/10/2020 20/02/2021 Completed 41.55
over bridge -RoB
including widening of
road from western
boundary to TTPS
Dredging the dock basin
for coastal cargo berth
65 at VOCPT -Dredging in Tamil Nadu 21/11/2017 21/04/2018 Completed 98.00
front of dedicated
coastal berth
National Technology
Centre for Ports,
66 Waterways and Coasts Tamil Nadu 30/06/2018 30/09/2022 Completed 77.03
(NTCPWC) at IIT
Madras.
Fishing harbor at
Mookaiyur in
67 Tamil Nadu 19/07/2018 30/08/2019 Completed 113.90
Ramanathapuram
district
Construction of fish
landing centre at
68 Kunthukal in Tamil Nadu 27/02/2019 14/09/2020 Completed 74.00
Ramanathapuram
District of Tamil Nadu.
Modern elevated steel
bridge for safe
69 trasportof tourists from Tamil Nadu 17/12/2020 31/01/2025 Completed 37.00
Vivekananda Rock to
Thiruvalluvur statue
Development of Buffer
70 Tamil Nadu 13/03/2024 10/02/2025 Completed 49.06
Parking yard forSanction Completion Project Project cost
SI. No. Project Name State/UT
Date date Status (in ₹ crore)
Trailers / Trucks at the
backup areas of Berth
No. 24B(BD-II) in
Chennai Port Authority
RoB cum Flyover at
West
71 Ranichak level crossing 24/11/2015 28/12/2020 Completed 127.80
Bengal
at KoPT
Improvement of road
connectivity to facilitate West
72 27/09/2016 18/04/2023 Completed 13.52
trade and port users at Bengal
KoPT
Upgradation of the track
10-12-14-16-18-19-20- West
73 27/09/2016 30/06/2018 Completed 47.00
21- 22 and 23 at EJC Bengal
yard of KoPT
Upgrade of existing rail
West
74 network at Kolkata 05/10/2016 10/01/2018 Completed 9.00
Bengal
Dock System
2nd Railway Line from
Durgachak take off West
75 01/02/2016 03/08/2021 Completed 117.00
point to ‘A’ cabin at Bengal
Durgachak at HDC
Improvement of road
connectivity to facilitate West
76 24/09/2018 18/03/2023 Completed 87.91
trade and port users at Bengal
KoPT, Phase-2
Design, Engineering &
Construction for
Rehabilitation of No.7,
NSD Old Berth West
77 12/07/2022 01/09/2024 Completed 80.74
including Development Bengal
of Backyard at N.S.
Dock of KDS - SMP,
Kolkata’
Anti-erosion work on
the left bank of river
Hooghly/ Bhagirathi West
78 23/03/2023 28/02/2025 Completed 14.99
Block & P.S. Kalyani, Bengal
Nadia district, Kolkata
(WB)
DDUGKY Phase II Andaman Under
79 Andaman & Nicobar and Nicobar 24/08/2021 31/03/2026 Implementat 7.09
Islands Island ion
Development of Sea Andaman Under
80 14/01/2021 30/04/2026 24.98
Port Terminal at and Nicobar ImplementatSanction Completion Project Project cost
SI. No. Project Name State/UT
Date date Status (in ₹ crore)
Havelock SwarajDweep Island ion
Modernisation of Under
Andhra
81 Visakhapatnam Fishing 30/03/2022 30/11/2026 Implementat 178.51
Pradesh
Harbour ion
Under
DDUGKY Phase II Andhra
82 12/03/2019 31/03/2026 Implementat 5.98
Andhra Pradesh Pradesh
ion
Augmentation of
Under
Firefighting facilities at
83 Goa 05/06/2025 31/03/2026 Implementat 17.76
Berth no. 8 of MgPA on
ion
Turnkey basis
International &
Domestic Cruise Under
84 Terminal and Ferry Goa 15/07/2020 31/03/2026 Implementat 87.44
Terminal at Mormugao ion
Port, Goa
Construction of Ro-Ro/ Under
85 Ro-Pax facility at Gujarat 03/11/2021 31/12/2026 Implementat 90.49
Muldwarka ion
Under
DDUGKY Phase II
86 Gujarat 04/07/2019 31/03/2026 Implementat 10.85
Gujarat
ion
National Maritime Under
87 Heritage Complex, Gujarat 25/02/2019 31/03/2026 Implementat 573.12
Lothal ion
Construction of fishing Under
88 harbor at Mangrol Gujarat 16/10/2017 31/03/2026 Implementat 158.00
(Phase-III), Junagarh ion
Occupational Safety and Under
89 Health Training in Gujarat 20/09/2016 31/03/2026 Implementat 30.00
Alang ion
Under
DDUGKY Phase II
90 Karnataka 29/02/2024 31/03/2026 Implementat 2.18
Karnataka
ion
Under
Development of Fishing
91 Karnataka 28/02/2018 31/12/2026 Implementat 196.51
Harbour at Kulai
ion
Development of
existing fish landing Under
92 center at Karnataka 13/08/2018 31/03/2026 Implementat 138.60
HejamadiKodiin Udupi ion
district of Karnataka
Construction of coastal Under
93 Karnataka 14/09/2017 31/03/2026 65.00
cargo berth at Old ImplementatSanction Completion Project Project cost
SI. No. Project Name State/UT
Date date Status (in ₹ crore)
Mangaluru Port ion
Under
DDUGKY Phase II
94 Kerala 12/03/2019 31/03/2026 Implementat 25.46
Kerala
ion
Modernization and up- Under
95 gradation of Cochin Kerala 11/03/2022 30/09/2026 Implementat 169.17
Fishing Harbour ion
Under
DDUGKY Phase II
96 Maharashtra 21/10/2019 31/03/2026 Implementat 15.11
Maharashtra
ion
Modernization of
Under
existing Fishing Harbor
97 Maharashtra 02/04/2016 30/05/2026 Implementat 92.52
at Sassoon Dock,
ion
Mumbai
Development of Fishing Under
98 Harbour at Mallet Maharashtra 20/01/2022 31/03/2026 Implementat 96.60
Bunder, Mazgaon ion
Under
Development of Ro-Ro
99 Maharashtra 03/08/2020 30/06/2026 Implementat 21.66
Service at Rewas
ion
Construction of Ro-Pax Under
100 jetty and Terminal at Maharashtra 06/08/2021 30/04/2026 Implementat 82.92
Mora, Distt. Raigad ion
Construction of fishing
Under
harbour at Anandwadi
101 Maharashtra 28/03/2018 30/05/2026 Implementat 88.44
(Deogad) in Sindhudurg
ion
District
Construction of
Approach Jetty and
Under
sloping berth jetty and
102 Maharashtra 14/12/2016 31/03/2026 Implementat 6.59
Approach Road to
ion
facilitate Ro-Ro Jetty at
Manori, Maharashtra
Construction of jetty at Under
103 Arnala fort- Tal Vasai- Maharashtra 25/09/2020 31/03/2026 Implementat 9.94
Dist. Thane ion
Up-
gradation/modernization Under
104 of International Cruise Maharashtra 27/01/2017 31/03/2026 Implementat 363.30
Terminal at Indira ion
Dock, Mumbai
Under
Tourism Jetty at Kashid
105 Maharashtra 30/03/2018 31/03/2026 Implementat 99.82
in Raigad District
ionSanction Completion Project Project cost
SI. No. Project Name State/UT
Date date Status (in ₹ crore)
Under
DDUGKY Phase II
106 Odisha 11/02/2025 31/03/2026 Implementat 22.83
Odisha
ion
Ro-pax Jetty and allied
infrastructure
Under
connecting Kaninali in
107 Odisha 05/04/2021 10/03/2026 Implementat 136.98
Bhadrak District
ion
&Talchua in
Kendrapada District".
Modernization and Under
108 upgradation of Paradip Odisha 03/01/2022 19/07/2026 Implementat 99.75
Fishing Harbour ion
Construction of fishing
harbor at Chandipur Under
109 (Balaramagadi) in Odisha 06/08/2018 31/03/2026 Implementat 49.94
Balasore district, ion
Odisha.
Ro-pax Jetty and allied
infrastructure
Under
connecting Balugaon in
110 Odisha 21/09/2020 31/03/2026 Implementat 37.02
Khurda District
ion
&KrishnaprasadGada in
Puri District
Under
DDUGKY Phase II
111 Puducherry 14/02/2022 31/03/2026 Implementat 2.22
Puducherry
ion
Upgradation of
Nagapattinam Port
Infrastructure for the
Under
passenger ferry service
112 Tamil Nadu 21/08/2024 10/05/2026 Implementat 10.47
from Nagapattinam
ion
(India) to
Kankesanthurai (Sri
Lanka)
Creation of Berthing
Under
facilities for the tourist
113 Tamil Nadu 07/03/2023 20/03/2026 Implementat 7.58
vessels at Agni
ion
Theertham, Tamil Nadu
Creation of additional
berthing facilities for Under
114 the tourist vessels at Tamil Nadu 08/02/2023 20/03/2026 Implementat 3.66
VilloondiTheertham, ion
Tamil Nadu
DDUGKY Phase II Under
115 Tamil Nadu 27/03/2019 31/03/2026 10.67
Tamil Nadu ImplementatSanction Completion Project Project cost
SI. No. Project Name State/UT
Date date Status (in ₹ crore)
ion
Modernization and up- Under
116 gradation of Chennai Tamil Nadu 22/02/2022 30/06/2026 Implementat 97.95
Fishing Harbour ion
Development of Under
117 Passenger jetty at Tamil Nadu 23/03/2018 27/02/2026 Implementat 20.00
Kanyakumari ion
Setting up of Centre for
Inland and Coastal
Under
Maritime Technology West
118 07/03/2019 30/03/2026 Implementat 69.20
(CICMT) at Indian Bengal
ion
Institute of Technology,
Kharagpur
Development of River
Cruise terminal and
Under
river tourism facility West
119 11/08/2025 30/02/2027 Implementat 75.82
along with riverfront Bengal
ion
beautification works at
KDS, SMP, Kolkata’
Augmentation of
Under
Firefighting facilities at
120 Maharashtra 30/09/2025 31/01/2026 Implementat 52.69
Pir Pau Terminal of
ion
Mumbai Port
Construction of Under
121 Approach road to Maharashtra 17/10/2025 30/01/2026 Implementat 29.41
Narangi Jetty ion
Construction of four
EXIM Godowns and Under
122 concrete roads around Tamil Nadu 25/11/2025 31/05/2026 Implementat 54.34
EXIM Godowns at ion
Chennai Port
Development of paved
storage yard at Under
123 marshalling yard and JD Tamil Nadu 25/11/2025 31/05/2026 Implementat 45.90
(east) back up area for ion
handling EXIM cargoes
Under
Smart Lighting on
124 Kerala 25/11/2025 30/04/2026 Implementat 2.01
Willingdon Island
ion
2.3 MWp roof mounted
Under
grid connected solar West
125 24/11/2025 31/03/2026 Implementat 30.70
power plant at Bengal
ion
Khidderpre Dock-IISanction Completion Project Project cost
SI. No. Project Name State/UT
Date date Status (in ₹ crore)
Extension and
Improvement of
Loading Platform of full
rake No.8 and
Under
modification to railway
126 Goa 02/12/2025 31/07/2026 Implementat 12.58
infrastructure for
ion
Handling two rakes
simultaneously at Line
No. 08 and 8A at
Mormugao Port
Revamping/upgradation
Under
of 6 roads in port West
127 11/12/2025 31/03/2026 Implementat 19.35
operational areas of Bengal
ion
KDS under SMPA
Creation of additional
birthing and Land side Under
128 facilities at Chellanam Kerala 19/12/2025 31/03/2027 Implementat 7.65
Fishing Harbor in ion
Kerala
Total 8,936
*****