Lok Sabha Unstarred Question No. 895, answered on July 24, 2025, addresses the progress of the proposed four-lane road construction from Basirhat to Jangipur, covering the districts of Nadia, Murshidabad, and North 24 Parganas. The question was posed by MD Abu Taher Khan, inquiring about the project's progress, expected completion date, and the potential for a special meeting involving the Union Government, State Government, and local administration to expedite the project.
In response, the Minister of Road Transport and Highways, Shri Nitin Jairam Gadkari, stated that National Highway NH 312, which runs through the specified districts, was entrusted to the National Highways Authority of India (NHAI) in 2023. As of July 2025, the Detailed Project Report (DPR) for the four-laning of the 318 km stretch has not been prepared. The government intends to consult with all stakeholders, including the State Government and local administration, when the DPR is undertaken.
Key Entities Referenced
Ministry of Road Transport and Highways: The Indian government ministry responsible for the development and maintenance of road transport infrastructure.
Basirhat: Starting point of the four lane road project, located in West Bengal, India.
Jangipur: Ending point of the four lane road project, located in West Bengal, India.
Nadia district: One of the districts through which the road project passes, located in West Bengal, India.
Murshidabad district: One of the districts through which the road project passes, located in West Bengal, India.
North 24 Parganas district: One of the districts through which the road project passes, located in West Bengal, India.
National Highways Authority of India (NHAI): The Indian government agency responsible for the development, maintenance and management of National Highways in India.
National Highway NH 312: The specific National Highway which is being upgraded to a four-lane road between Basirhat and Jangipur.
GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 895
ANSWERED ON 24TH JULY, 2025
COMPLETION OF FOUR LANE ROAD FROM BASIRHAT TO JANGIPUR
895. MD ABU TAHER KHAN:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार् ग मंत्री
be pleased to state:
(a) the progress of the construction work of 318 Km long four lane road
from Basirhat to Jangipur covering all three districts Nadia, Murshidabad and
North-24 Parganas;
(b) the time by which the project is likely to be completed; and
(c) whether the Union Government is going to arrange a special meeting
with State Government and Local Administration of these districts to take
urgent measures for expediting this project as it is much needed for the
people, farmers and businessmen of these backward areas and if so, the
details thereof?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (c) National Highway (NH) - 312, passing through the districts of
Nadia, Murshidabad and North 24 Parganas from Basirhat to Jangipur has
been entrusted to National Highways Authority of India (NHAI) in year 2023.
The Detailed Project Report (DPR) for 4-laning has not been
prepared. Government will undertake consultation with all stakeholders
including the State Government and local administration whenever the DPR
for the stretch is taken up.
*****